HomeMy WebLinkAboutCHANGE ORDER NO. 1 TO CONTRACT BETWEEN AUGUSTA, GEORGIA AND SOMMERS CONSTRUCTION LLC ESTIMATE
Date Estimate#
Sommers Construction LLC
PO Box 950 4-20-2018 6795
Evans, Ga. 30809
706-955-8244
Name/Address
Augusta Regional Airport
1501 Aviation Way
Augusta,Ga.30906
Description Total
Request for Change Order#3 6,707.00
All labor,material,and supervision to install charging station per drawings.The change will require a slab to complete as
no remnants are large enough to cut the top.
Counter $3,611.00
Electrical $ 1,272.00
Labor for Blocking/Sheetrock $750.00
Material $ 100.00
Sub Total -$5,733.00
0/P $974.00
Total $6,707.00
Total $6,707.00