This Amendment is made and entered into this 1st day of January,2018,between AUGUSTA,
GEORGIA,by and through the Augusta-Richmond County Commission,a political subdivision of the
State of Georgia(hereinafter"Augusta"),and ESG OPERATIONS,INC.,a Georgia corporation,
(hereinafter`BSG").This is Amendment No. 7 to the Agreement dated the 16th day of December 2009,
between Augusta and ESG.
NOW THEREFORE,Augusta and ESG agree to amend the Agreement as follows:
REPLACE Article 4.1 with the following new Article:
4.1 Augusta shall pay to ESG a base fee equal to the Augusta budget shown in Appendix F. This
includes the actual cost of the Scope of Services performed by ESG plus a Management and
Administrative Fee.The base fee shall not include services which are not specifically defined by
Section 2 of this Agreement. The base fee for this Amendment shall be Five Million Ninety-Five
Thousand Twenty Dollars($5,095,020)and the Management and Administrative Fee shall be Six
Hundred Eleven Thousand Four Hundred Two Dollars($611,402). The base fee and the
Management and Administrative Fee shall be payable in advance in equal monthly installments
and for the seventh term of this Agreement the monthly amount shall be Four Hundred Seventy-
Five Thousand Five Hundred Thirty-Five Dollars and Sixteen Cents($475,535.16). Said base fee
shall be for the period beginning on January 1St,2018 and ending on December 3151,2018.
Thereafter,the Base Fee will be negotiated as described in Article 4.2. The Management and
Administrative Fee shall increase proportionally with the base fee adjustments described in
Articles 4.2 and 4.4.
REPLACE Article 7.1 with the following new Article:
7.1 The Agreement is extended for an additional five year term which shall commence January 1,
2020 and end on December 31,2024. Thereafter,this Agreement may be renewed by Augusta for
successive five(5)year terms subject to the mutual agreement of the parties to the terms and
conditions of such renewal.
REPLACE Appendix F with the following new Appendix F.
DELETE Appendix I in its entirety.
ADD Appendix L and M.
All other terms and conditions remain in effect in accordance with the Agreement referenced in this
Amendment.
Both parties indicate their approval of this Amendment by signature below.
Authorized signatures:
ESG OPERATIONS INC/ AUGUSTA,GEORGIA
By: i /1 By:
Jo - . S k 'E,Princi,al S ,l& Hardi• Davis,Jr.
it/i0BMayor
y: :�
Daniel E.Grosel ,PE,Principal 4,e
/�/III0.i� 2$ Zc'I ATTEST••�,o'7(i fp. .,, lii
Date: « e,:
se ., LiaV f,o 0:
is Date s
I �i C�%.. ,i' 3 a .1
op J,
O
K V0.
Appendix F
2018 Project Budget and Staffing Plan
Project Budget
PERSONNEL SERVICES $ 1,800,020.00
ADMINISTRATIVE EXPENSES $ 100,000.00
UTILITIES $ 190,000.00
CHEMICALS $ 620,000.00
MATERIALS & SUPPLIES $ 120,000.00
VEHICLES & EQUIPMENT $ 115,000.00
OUTSIDE SERVICES $ 320,000.00
BIOSOLIDS MANAGEMENT $ 1,160,000.00
MAINTENANCE & REPAIR $ 420,000.00
TOTAL OPERATING BUDGET $4,845,020.00
MANAGEMENT & ADMINISTRATIVE FEE
(12%) 581,402.00
CONTRACTOR'S SUBTOTAL $ 5,426,422.00
DIRECTOR'S ALLOWANCE $ 250,000.00
MANAGEMENT & ADMINISTRATIVE FEE
(12%) 30,000.00
DIRECTOR'S ALLOWANCE SUBTOTAL 280,000.00
TOTAL 2018 BUDGET $ 5,706,422.00
Appendix F (Continued)
2018 Project Budget and Staffing Plan
Project Staffing Plan
Budgeted Position Budgeted Number
Project Director 1
Assistant Project Manager 1
Operations Manager 1
Lab/SSES Manager 1
Maintenance Manager 1
Land Application Manager 1
Operators 10
Lab Analysts 2
IPP Technicians 2
Mechanics 5
Maintenance Support 3
Administrative 1
Education Specialist 2
• •
Appendix L —
JB Messerly Digester 1 Rehabilitation
The JB Messerly WPCP's Digester 1 is in need of repair. ESG proposes to install a new lid,mix pump and
jet mix nozzles, sludge heater and recirculation pump consistent with proposal dated January 2, 2018. The
estimated costs are as follows:
Summary of Cost Estimate
Item Description Cost
1 Digester Mixing $ 142,000
2 Digester Lid $ 894,000
3 Digester Piping and Misc. $ 90,150
4 Sludge Heater and Recirculation $ 313,500
5 Digester Walls $ 317,000
Subtotal $ 1,756,650
6 Tax $ 99,596
7 Design $ 131,749
8 Contingency $ 263,498
Sub-Total $ 2,251,493
10 Mark Up $ 190,776
Total $ 2,442,269
ESG's cost estimate is Two Million Four Hundred Forty-Two Thousand Two Hundred Sixty-Nine dollars
(2,442,269)inclusive of a nine percent markup. ESG will invoice Augusta monthly based on the actual cost
incurred for this work.
U
Appendix M —
JB Messerly Dewatering Rehabilitation
The JB Messerly WPCP's dewatering equipment has reached the end of its useful service life. ESG is
proposing to remove the existing equipment,install three new 2M belt filter presses and control system,one
sludge feed pump and associated piping, construct a building around the equipment, replace the sludge
conveyor system and enhance the polymer feed system consistent with proposal dated January 2,2018.The
estimated costs are as follows:
Summary of Costs Estimate
Item Description Cost
1 Belt Filter Press Installation $ 1,420,550
2 Building $ 375,000
3 Sludge Conveyance $ 177,500
4 Polymer Feed $ 31,000
Subtotal $ 2,004,050
6 Tax $ 133,000
7 Design $ 135,000
8 Contingency $ 274,382
Sub-Total $ 2,546,432
10 Mark Up $ 213,243
Total $ 2,759,675
ESG's cost estimate is Two Million Seven Hundred Fifty-Nine Thousand Six Hundred Seventy-Five dollars
(2,759,675)inclusive of a nine percent markup. ESG will invoice Augusta monthly based on the actual cost
incurred for this work.