HomeMy WebLinkAboutCONTRACT MODIFICATION NUMBER 2 BETWEEN AUGUSTA, GEORGIA AND GRIFFIN CONTRACTING, INC. FOR ARFF PAVEMENT REHABILITATION CONTRACT MODIFICATION NUMBER 2 OWNER: Augusta Regional Airport CONTRACTOR: Griffin Contracting,Inc 1501 Aviation Way 122 Pipemakers Circle,Suite 207 Augusta,GA 30906 Savannah,GA 31418 PROJECT: ARFF Pavement Rehabilitation CONTRACT DATE: May 26,2016 PROJECT NUMBER: AIP No. 3-13-0011-038-2015 DESCRIPTION OF CHANGE: The purpose of Change Order 2 is to compensate the Contractor for additional excavation required to accommodate the pavement section and to zero out any quantities of materials that were not needed for completion of this project. NEW ITEMS 1.Additional Excavation. There was an additional amount of excavation within the project limits compared to the unclassified excavation quantity in the original contrail. Item P-152.1: 443 CY at$27.00 COST ADDITION/(DELETION): $11,961.00 DAYS ADDITION I(DELETION): 0 JUSTIFICATION: The original bid documents did not provide for enough excavation to construct the designed pavement section. The revised quantity is based on as-constructed quantities. 2.Reduction of quantities. The following items are to be reduced in quantity. Item P-101.1: 200 SY at$12.00 Item X-106.1: 115 CY at$17.85 Item P-152.2: 105 SY at$6,00 Item P-156.2: 5 EA at$310.00 Item P-209.1: 131 CY at$69.00 Item X-405.1: 50.09 TON at$99.75 Item P-620.1: 310 SF al$2.00 Item P-620.2: 590 SF at$3.00 Item D-701.1: 40 LF at$51.00 Item D-701.2: 3 LF at$54.00 COST ADDITION/(DELETION): ($25,260.23) DAYS ADDITION I(DELETION): 0 JUSTIFICATION: During the final project closeout there were several items that did not balance. This change order zeros out these items to account for quantities not installed for this project due to slight changes in project limits during the course of construction. This is the final change order for the construction of this project. COST ANALYSIS: The unit prices from the original contract are being held for the revised quantities. CONTRACT MODIFICATION NUMBER 2 OWNER: Augusta Regional Airport CONTRACTOR: Griffin Contracting,Inc 1501 Aviation Way 122 Pipemakers Circle,Suite 207 Augusta,GA 30906 Savannah,GA 31418 PROJECT: ARFF Pavement Rehabilitation CONTRACT DATE: May 26.2016 PROJECT NUMBER: AIP No 3-13-0011-038-2015 NO WORK COVERED BY THIS CHANGE ORDER MAY PROCEED UNTIL CONTRACTOR IS IN RECEIPT OF A COPY OF FULLY EXECUTED ORDER BY THE CONTRACTOR, THE OWNER AND THE ENGINEER IF CONTRACTOR IS IN AGREEMENT WITH THIS CHANGE,CONTRACTOR SHOULD EXECUTE ALL COPIES AND RETURN ALL COPIES TO THE CONSTRUCTION PROJECT MANAGER WITHIN SEVEN(7)CALENDAR DAYS. THIS CHANGE WILL INCREASE OR DECREASE THE CONTRACT AMOUNT AND TIME TO COMPLETE BY THE AMOUNT SHOWN BELOW. ALL OTHER TERMS OF THE CONTRACT, INCLUDING THE GENERAL, SUPPLEMENTARY AND OTHER CONDITIONS OF THE CONTRACT SHALL APPLY TO THIS CHANGE ORDER UNLESS EXPRESSLY MODIFIED BY THIS CHANGE, DESCRIPTION OF CHANGE: Changes generally consist of minor modifications to quantities for ultimate work performed during the course of the project Additional quantities of excavation were also needed to accommodate the pavement section. ORIGINAL TOTAL CONTRACT PRICE �_ $544,43210': APPROVED COST ADDITIONS(DELETIONS)TO DATE $8,455.20 AMOUNT OF THIS CHANGE ORDER. (S 13,299,23) REVISED TOTAL CONTRACT PRICE $639,581.97 PERCENTAGE FOR THIS CHANGE ORDER OF ORIGINAL CONTRACT PRICE -2.44% TOTAL CHANGE ORDER PERCENTAGE OF ORIGINAL CONTRACT PRICE 0.89% ORIGINAL TOTAL CONTRACT CALENDAR DAYS 5D' CALENDAR DAY ADDITIONS(DELETIONS)PREVIOUS CHANGE ORDERS 8 CALENDAR DAY ADDITIONS(DELETIONS)THIS CHANGE ORDER 0 REVISEDTOTAL CONTRACT CALENDAR DAYS S8 CONTRACTOR ACKNOWLEDGES.BY ITS EXECUTION AND ACCEPTANCE OF THIS CHANGE ORDER, THAT THE ADJUSTMENTS IN CONTRACT PRICE AND TIME SHOWN HEREON CONSTITUTES FULL AND COMPLETE COMPENSATION AND SATISFACTION FOR ALL COSTS AND MODIFICATIONS OF PERFORMANCE TIME INCURRED BY THE CONTRACTOR AS A RESULT OF THIS CHANGE ORDER. NO OTHER CLAIM FOR INCREASED COST OF PERFORMANCE OR MODIFICATIONS OF TIME WILL BE GRANTED BY THE OWNER FOR THIS WORK COVERED BY THIS CHANGE.THE CONTRACTOR HEREBY WAIVES AND RELEASE ANY FURTHER CLAIMS FOR COST OR TIME AGAINST THE OWNER ARISING FROM OR RELATING TO THE MATTERS OF WORK SET FORTH OR CONTEMPLATED BY THIS CHANGE ORDER CONTRACTOR'S ACCEPTANCE.Griffin Contracting .401 -- 7.4 8//7 (_„„ ig • ure Date 77Co� ✓ ti. s 47-1-72)0477I,e- Printed Name Title A/E R OMMENDEQ„EOR APPROVAL:Mead I Hunt,Inc. ��--- 1110)I" Signature Date Christopher J.Blrkmeyer,P.E. Project Manager Printed Name Title OWNER REC• -■":: AUGUSTA-RICHMOND COUNTY, GEORGIA /70L-44.: ::::> /lel, By: Hardie Davis, Jr. Date qii....ximmilk it ATTEST: i�L1 ',� , ,�!i '�%� ,0 r / L s4.4,,,-.4.,'-' r !rc * : 0 f D. e OCA 2E` EORGIto, (BALANCE OF PAGE LEFT INTENTIONALLY BLANK)