Augusta-Richmond County,Georgia CPB#328-041110-210328103
CAPITAL PROJECT BUDGET
15th Street Pedestrian Improvements
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project is set up and authorized to CPB#328-041110-210328103 and Supplemental
Agreement 1 to award the preliminary engineering concept phase of the Design Consultant Services
Agreement to Wolverton 8s Associates,Inc.,in the amount of$1,347,424.97 for the
15th Street Pedestrian Inprovements Project.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
SPLOST Phase VI $ 373,510
SPLOST Phase VI $ 382,610
TIA Discretionary $ 109,078
TIA Funds $ 1,347,425
$ 2,212,623
Section 3: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.\ y
Adopted this t day of Jva 1 20` 1
Approved
Hon. l a s,Jr.,Mayor
Original-Commission CouIfy
e
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
I of 2 6/20/2017
Augusta-Richmond County,Georgia CPB#328-041110-210328103
CAPITAL PROJECT BUDGET
15th Street Pedestrian Improvements
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB ADDITION CPB
SPLOST PHASE VI $ (373,510.00) $ - $ (373,510.00)
328-041110-5212115
210328103
SPLOST PHASE VI $ (382,610.00) $ (382,610.00)
328-041110-5212115
210328103
TIA DISCRETIONARY $ (109,078.00) $ (109,078.00)
TIA Funds $ (1,347,425.00) $ (1,347,425.00)
371-041110-T15040146
TOTAL SOURCES: $ (865,198.00) $ (1,347,425.00) $ (2,212,623.00)
USE OF FUNDS
ENGINEERING
328-041110-5212115 $ 756,120.00 $ - $ 756,120.00
TIA DISCRETIONARY $ 109,078.00 $ 109,078.00
TIA FUNDS $ 1,347,425.00 $ 1,347,425.00
TOTAL USES: $ 865,198.00 $ 1,347,425.00 $ 2,212,623.00