CAPITAL PROJECT BUDGET
5th Street Bridge over the Savannah River(Bridge Repair and Restoration)
(Bid 16-247)
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby amended:
Section 1: The project is authorized to CPB#371-041110-T15041217. This request is to award the
Preliminary Engineering Phase of Design Consultant Services Agreement to Civil Services, Inc.
in the amount of$200,916.27 for the 5th Street Bridge over the Savannah River(Bridge Repair and
Restoration).
Funding is available in the TIA project budget:
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
TIA Design $ 750,000
$ 750,000
Section 3: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this roject.
/�tl 1if�
Adopted this day of l 1 1 20\
Approved
Hon. -.le Hardie Davis,Mayor
/490
342
1.14.2015
Augusta-Richmond County, Georgia CPB#371-041110-T15041217
CAPITAL PROJECT BUDGET
5th Street Bridge over the Savannah River(Bridge Repair and Restoration)
(Bid 16-247)
CPB AMOUNT CPB New
SOURCE OF FUNDS CPB Addition CPB
TIA Project ($750,000) ($750,000)
371-041110/5414210-T15041217
TOTAL SOURCES: ($750,000) ($750,000)
USE OF FUNDS
ENGINEERING
371-041110-5414210/T15041217 $750,000 ($200,916) $549,084
TOTAL USES: $750,000 ($200,916) $549,084
1.14.2015