HomeMy WebLinkAboutCHANGE ORDER ONE HIGHLAND AVE RESURFACING FROM WRIGHTSBORO RD TO WINDSOR RD BLAIR CONSTRUCTION INC CPB HIGHLAND AVE RESURFACING WRIGHTSBORO RD TO WHEELER CHANGE NUMBER ONE •
Change Order Number: One Date: 07/10/2014
Project Title Highland Avenue Resurfacing from Wrightsboro Road to Wheeler Road
Original Contract Date: 12/17/2013 Project Number: 371 - 041110- T13041119
Owner: Augusta- Richmond • County P.O. Number . P242177
Contractor: Blair Construction, Inc.
The following change order is hereby made to the proposal for the above project: See Attached
TOTAL AMOUNT OF THIS CHANGE ORDER S137,31,0,QQ
The Contract time will be Increased /Decreased by 0 calendar days as a result of this change.
Original Contract Amount $517,079.90
Previous Change Order
(Increased / Decreased) S 0.00
This Change Order
(Increased / Decreased) $ 137,300.00
TOTAL CONTRACT WITH CHANGE ORDER(S) $654,379.90
* * * * * * * * * * * **
Funding Source /Account Number: 371- 041110- 54,14110/T13041119
/
�
Requested By: � � _ / L � //
AO
2/o i -
Contractor
err'
Submitted By: Ala I■ /� Date: (9/7/1_
Engin :ling ing • nstr ctio - ager
il C
Accepted By: j 111 Date:
E gineering Depa m 'n gad
Approved By: C c'%l/2(
Date: 1 (- (
Mayor
,
Augusta - Richmond County, Georgia CPB# 371 - 041110- T1304119
CAPITAL PROJECT BUDGET
Highland Avenue Resurfacing from Wrightsboro Rd. to Wheeler Rd.
Change Number One
BE IT ORDAINED by the Commission - Council of Augusta- Richmond County, Georgia that the following
Capital Project Budget is hereby authorized:
Section 1: This project is authorized to CPB# 371- 04110/T13041119. This Change Number One is
for Blair Construction, Inc. additoonal funds in the amount of $94,902 to be used
for the improvement of the Cross Walk additional work.
Funds are available in the construction budget account numbers: TIA Budgeted account
TIA Discretionary account in the amount of $94,902.
Section 2: The following revenues are anticipated to be available to the Consolidated Government to
complete the project.
TIA Budgeted $268,841
TIA Discretionary $248,238
TIA Discretionary $94,902
$611,981
Section3: Copies of this Capital Project Budget shall be made available to the Comptroller for direction in
carrying out this project.
Adopted this day of
Approved
Honorable Deke Copenhaver, Mayor
7//y
Original- Commission Council Office
Copy- Engineering Department
Copy- Finance Department
Copy- Procurement Department
1 of 11.16 2010
I • f
Augusta - Richmond County, Georgia CPB# 371 - 041110- T1304119
CAPITAL PROJECT BUDGET
Highland Avenue Resurfacing from Wrightsboro Rd. to Wheeler Rd.
Change Number One
CPB AMOUNT
SOURCE OF FUNDS CPB
TIA Funds
3�XXX300C ($268,841) ($268,841)
Discretionary Funds
HOC{ ($248,238) ($94,902) ($343,140)
TOTAL SOURCES: ($517,079) ($611,981)
USE OF FUNDS
ROADS
moo= $517,079 $94,902 $611,981
TOTAL USES: $517,079 $94,902 $611,981
2 of 2 11.16.2010