HomeMy WebLinkAboutCONTRACT MODIFICATION #1 -FIRE HOUSE RENOVATIONS PROJECT IN THE AMOUNT $10,565.28 (AUGUSTA REGIONAL AIRPORTTotal Contract Amount
Original Contract Amount
$193,730.06
Changes to Contract Amount from This Contract Modification (CM#1)
+ $10,565.28
Revised Contract Total
$204,295.34
Total Contract Time
Original Contract Time
180 calendar days
Changes to Contract Time from This Contract Modification
4 calendar days
184 calendar days
Revised Contract Time Total
Item #
Description
Unit
Quantity
Unit Price
Total Price
1
Permitting Fees (Foundation/Demolition and Building
Permits)
LS
1
$1,127.05
$1,127.05
2A
Complete CMU Wall Above Removed Ceiling and
Block in Exposed Steel Column
LS
1
$2,716.33
$2,716.33
2B
Rebuild Common Column/Door Jamb Between New
and Existing Bay
LS
1
$5,252.56
$5,252.56
3
Provide Power and Vent for Proposed Cascade
System.
LS
1
$1,469.34
$1,469.34
Total:
310,565.28
Contract Modification #1
Airport: Augusta Regional Airport Date Initiated: January 30, 2013
Owner. City of Augusta Project: Fire House Renovations
Contractor: Contract Management, Inc.
The architectural drawings required the two existing rooms in the Fire Station vehicle bay
Project Number 0733 -20
The contractor is requested to perform the following work described upon receipt of an
approved copy of this document or as directed by the engineer.
This document shall become an amendment to the contract and all provisions of the contract
will apply.
Description and Justification for Change
Brief description and justification of the proposed contract changes and locations:
1. Permitting Fees (Foundation/Demolition and Building Permits). The Contractor was
required to pay for the permits before the Building Inspection Department would release the
permit. Per the contract, it states "...the County will not charge the Contractor for such
permits and inspections obtained from the County". The permits required include
demolition/footing permit ($315.33) and the final permit for the building ($811.72). This
modification is an increase to the contract amount by $1,127.05. Refer to attached
proposal dated 6 November 2012.
2A. Complete CMU Wall Above Removed Ceiling and Block in Exposed Steel Column.
area to be removed. Upon demolition of the walls and ceiling, it was determined the block
on the south wall did not extend to the roof line as all the other wall sections did. The
record drawings of the original construction of the Fire Station did not provide any details of
Page 1 of 2
Augusta Regional Airport
this particular wall section. Therefore, the condition was unforeseen. This modification is
an increase to the contract amount by $2,716.33. Refer to attached proposal dated 6
December 2012.
2B. Rebuild Common Column/Door Jamb Between New and Existing Bay. The
architectural drawings indicated to remove only the existing jamb side of Door #4 and install
new masonry to provide bearing for the new beam over the new Door #4. It was the
architect's intent to leave three sides of the existing column in place and install a new forth
side which would become the new jamb of Door #4. The current conditions have only less
than two sides of the existing column remaining and some very poor existing masonry
construction. The record drawings of the original construction of the Fire Station did not
provide any details of this particular column. Therefore, the condition was unforeseen, and
it is recommended to rebuild the column correctly to ensure proper support for the existing
Door #3 beam. This modification is an increase to the contract amount by $5,252.56.
Refer to attached proposal dated 6 December 2012. Change Order Request 2A and 2B
include 4 additional days to the contract time.
3. Provide Power and Vent for Proposed Cascade System. After the award of the contract
for the Fire Station Renovations, a Cascading System to refill breathing tanks used by fire
personnel was acquired and recommended to be installed in the new building addition. In
order to operate this system, 230-V power and an air vent will be required. This
modification is an increase to the contract amount by $1,469.34. Refer to attached
proposal dated 11 December 2012.
Recommended
by:
Change
Administrated
by:
Accepted by:
Approved by:
Approved by:
Fire Station Renovations Contract Modification # 1
Virgo Gambill Architects, P.C. Date
Camp • = & aris Eng
ntract Management, Inc.
Augusta Regional Airport
City of Augusta
Submit 4 original copies to the City of Augusta.
Page 2 of 2
1/30/13
Date
l -31- l3
Date
x_31 - 13
Date
Date
)7'0 3
AUGUSTA RICHMOND COUNTY
ffal Deke S. Copenhaver, Mayor
0
0
a m 0
v' e�l
1 b
1 $ C 4 id�ii .4•
IJEP. iazyv‘
Lena-Bonner, Clerk
NANC moleAuski
ATTEST:
Approved as to Form:
Andrew Mackenzie, sq.
Total Contract Amount
Original Contract Amount
$193,730.06
Changes to Contract Amount from This Contract Modification (CM#1)
+ $10,565.28
Revised Contract Total
$204,295.34
Total Contract Time
Original Contract Time
180 calendar days
Changes to Contract Time from This Contract Modification
4 calendar days
Revised Contract Time Total
184 calendar days
Item #
Description
Unit
Quantity
Unit Price
Total Price
1
Permitting Fees (Foundation/Demolition and Building
Permits)
LS
1
$1,127.05
$1,127.05
2A
Complete CMU Wall Above Removed Ceiling and
Block in Exposed Steel Column
LS
1
$2,716.33
$2,716.33
2B
Rebuild Common Column/Door Jamb Between New
and Existing Bay
LS
1
$5,252.56
$5,252.56
3
Provide Power and Vent for Proposed Cascade
System
LS
1
$1,469.34
$1,469.34
Total:
$10,565.28
Airport: Augusta Regional Airport
Owner. City of Augusta
Contractor: Contract Management, Inc.
Contract Modification #1
Date Initiated: January 30, 2013
Project: Fire House Renovations
Project Number 0733 -20
The contractor is requested to perform the following work described upon receipt of an
approved copy of this document or as directed by the engineer.
This document shall become an amendment to the contract and all provisions of the contract
will apply.
Description and Justification for Change
Brief description and justification of the proposed contract changes and locations:
1. Permitting Fees (Foundation/Demolition and Building Permits). The Contractor was
required to pay for the permits before the Building Inspection Department would release the
permit. Per the contract, it states "...the County will not charge the Contractor for such
permits and inspections obtained from the County". The permits required include
demolition/footing permit ($315.33) and the final permit for the building ($811.72). This
modification is an increase to the contract amount by $1,127.05. Refer to attached
proposal dated 6 November 2012.
2A. Complete CMU Wall Above Removed Ceiling and Block in Exposed Steel Column.
The architectural drawings required the two existing rooms in the Fire Station vehicle bay
area to be removed. Upon demolition of the walls and ceiling, it was determined the block
on the south wall did not extend to the roof line as all the other wall sections did. The
record drawings of the original construction of the Fire Station did not provide any details of
Page 1 of 2
Augusta Regional Airport
this particular wall section. Therefore, the condition was unforeseen. This modification is
an increase to the contract amount by $2,716.33. Refer to attached proposal dated 6
December 2012.
2B. Rebuild Common Column/Door Jamb Between New and Existing Bay. The
architectural drawings indicated to remove only the existing jamb side of Door #4 and install
new masonry to provide bearing for the new beam over the new Door #4. It was the
architect's intent to leave three sides of the existing column in place and install a new forth
side which would become the new jamb of Door #4. The current conditions have only less
than two sides of the existing column remaining and some very poor existing masonry
construction. The record drawings of the original construction of the Fire Station did not
provide any details of this particular column. Therefore, the condition was unforeseen, and
it is recommended to rebuild the column correctly to ensure proper support for the existing
Door #3 beam. This modification is an increase to the contract amount by $5,252.56.
Refer to attached proposal dated 6 December 2012. Change Order Request 2A and 2B
include 4 additional days to the contract time.
3. Provide Power and Vent for Proposed Cascade System. After the award of the contract
for the Fire Station Renovations, a Cascading System to refill breathing tanks used by fire
personnel was acquired and recommended to be installed in the new building addition. In
order to operate this system, 230-V power and an air vent will be required. This
modification is an increase to the contract amount by $1,469.34. Refer to attached
proposal dated 11 December 2012.
Recommended Virgo Gambill Architects, P.C.
by:
Change
Administrated
by:
Accepted by:
Approved by:
Approved by:
Camp . _ & - aris Engi
ntract Management, Inc.
Fire Station Renovations Contract Modification # 1
Augusta Regional Airport
Submit 4 original copies to the City of Augusta.
Page 2 of 2
Date
1/30/13
Date
/ -31 —/3
Date
1_ 31- 13
Date
AUGUSTA RICHMOND COUNTY
cj .
Deke S. Copenhaver, Mayor
27
Approved as to Form:
Andrew Mackenzie, sq.