HomeMy WebLinkAboutDEDUCTIVE CHANGE ORDER #1 WITH APAC FOR AUGUSTA REGIONAL AIRPORTItem
No.
Description
Unit
Unit
Price
Original
Quantity
Revised
Quantity
Original
Cost
Revised Cost
15A
Unclassified Excavation
CY
$20.41
0
1,400
$0.00
$28,574.00
20
Temporary Silt Fence
LF
$4.00
18,084
19,834
$72,336.00
$79,336.00
22
Rock Check Dams
EA
$1,400.00
2
3
$2,800.00
$4,200.00
26B
Bituminous Repair Under PCC Slabs
TON
$110.00
3,000
2,687
$330,000.00
$295,570.00
38
30" Class IV RCP
LF
$200.00
33
0
$6,600.00
$0.00
39A
42" Class IV RCP
LF
$259.72
0
33
$0.00
$8,570.76
46A
Adjustment of Drainage Structure for 42" RCP
EA
$575.00
0
1
$0.00
$575.00
49A
#2 XHHW Wire for MALSR Lights
LF
$4.52
0
1,795
$0.00
$8,113.40
52A
Electrical Duct under PCC 2W -2"
LF
$15.58
0
210
$0.00
$3,271.80
54A
4" PVC Protection for FAA Cable
LS
$3,591.11
0
1
$0.00
$3,591.11
56A
New Manhole and Connections to Replace Pull Box
EA
$9,200.00
0
1
$0.00
$9,200.00
64
L -868 Light Base Can for RWCL or TDZ
EA
$850.00
377
301
$320,450.00
$255,850.00
64A
Labor and Materials for Omitted TDZ Cans
EA
$123.09
0
76
$0.00
$9,354.84
65A
Relocate PAPIs Twice - Temporary
EA
$1,700.00
0
2
$0.00
$3,400.00
67A
Relocate TW Edge Light Twice
EA
$600.00
0
15
$0.00
$9,000.00
70
Permanent Seeding and Mulching
MSF
$30.00
940
959
$28,200.00
$28,770.00
72
Sodding
SY
$4.00
22,813
26,063
$91,252.00
$104,252.00
Total Contract Amount
Original contract total:
$14,256,033.97
Previous change order(s) total:
$0.00
This change order total:
- $9.09
Revised contract total:
$14,256,024.88
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL AVIATION ADMINISTRATION
AIRPORT IMPROVEMENT PROGRAM
CHANGE ORDER NUMER: 1 or SUPPLEMENATAL AGREEMENT
NUMBER: N/A
AIRPORT: Augusta Regional Airport DATE: 20 November 2011
OWNER: Augusta Regional Airport AIP PROJECT #: 3 -13- 0011 -033
CONTRACTOR: APAC - Tennessee, Ballenger Paving Division
You are requested to perform the following described work upon receipt of an approved copy of
this document or as directed by the engineer:
Total Cost: $851,638.00 $851,628.91
*NOTE: Quantity adjustments for existing contract pay items will be made at contract unit
prices. All other costs are considered incidental to this contract modification and will not be
measured.
Page 1 of 5
Total Contract Time
Original contract time:
163 days
Changes to contract time from previous change
order(s):
0 days
Changes to contract time from this change
order:
0 days
Revised contract time total:
163 days
This document shall become an amendment to the contract and all provisions of the contract will
apply.
JUSTIFICATION FOR CHANGE
1. Brief description of the proposed contract change(s) and location(s).
• Item 15A: Unclassified excavation. This work is to re -grade the ditch at the outfall of
the 48" RCP (station 39 +36, east of RW 17 -35).
• Item 20: Temporary silt fence: This item will be placed around the additional grading
work at the 48" pipe outfall (station 39 +36, east of RW 17 -35).
• Item 22: Rock check dams: This item will be placed at the additional grading work at
the 48" pipe outfall (station 39 +36).
• Item 26B: Bituminous repair under PCC slabs: This item was in the contract to repair
damaged portions of the milled asphalt prior to PCC paving.
• Item 38: 30" class IV RCP pipe: This item was planned to connect structure SD5 to the
existing structure north of TW E at station ± 75 +00.
• Item 39A: 42" class IV RCP: This item was used to connect structure SD5 to the
existing structure north of TW E at station ± 75 +00.
• Item 46A: Adjustment of drainage structure for 42" RCP: This is structure SD5 located
at station 74 +77.
• Item 49A: #2 XHHW wire for MALSR lights: This cable is located at the MALSR
system at both thresholds (stations 20 +00 and 100 +01).
• Item 52A: Electrical duct under PCC 2W -2 ": This item is located at TW B and TW D.
• Item 54A: 4" PVC protection for FAA cable: This protection is located at either side of
TWs B and D.
• Item 56A: New manhole and connections to replace pull box: This pull -box is located
at station 64 +63 on the west side of the runway.
Page 2 of 5
• Item 64: L -868 light base can for RWCL or TDZ: The contract is reduced by 76 TDZ
cans, located from 20 +00 to 40 +00 and from 82 +00 to 100 +01.
• Item 64A: Labor and materials for omitted TDZ cans: This item encompasses 76
locations, from 20 +00 to 40 +00 and from 82 +00 to 100 +01.
• Item 65A: Relocate PAPIs twice — temporary: This item is off RW 8 -26, located at
baseline B station 22 +00 and 58 +10.
• Item 67A: Relocate TW edge light twice: This item is located at the radii on TWs C, F,
and G.
• Item 70: Permanent seeding and mulching: This increase in this item is located along
the proposed ditch line, station 39 +36, east of RW 17 -35.
• Item 72: Sodding: The increase in this item is located along the proposed ditch line,
station 39 +36, east of RW 17 -35.
2. Reason(s) for the change(s).
• Item 15A: Unclassified excavation: This work is necessary to properly drain water
from the new 48" RCP. The pipe profile did not change from that of the original;
however, the ditch line slowly elevated over the years and needs re- graded.
• Item 20: Temporary silt fence: This item is required to provide erosion and sediment
protection while excavating for the ditch line.
• Item 22: Rock check dams: This item is required to provide erosion and sediment
protection while excavating for the ditch line.
• Item 26B: Bituminous repair under PCC slabs: This item is being reduced because the
total amount was not necessary for the project.
• Item 38: 30" class IV RCP pipe: This item had to be changed to 42" RCP because the
existing pipe connecting to structure SD5 was 42 ". This was a change from the as- builts
used to design the system.
• Item 38B: 42" class IV RCP pipe: This pipe replaces the deleted 30" RCP.
• Item 46A: Adjustment of drainage structure for 42" RCP: The contractor had to
modify SD5 to accommodate the existing 42" RCP.
• Item 49A: #2 XHHW wire for MALSR lights: This cable was necessary to re- connect
the FAA MALSR system that the contractor demolished and replaced in order to elevate
the runway thresholds.
Page 3 of 5
• Item 52A: Electrical duct under PCC 2W -2 ": The contractor extended the existing duct
bank under one taxiway and replaced the duct under another. The replaced duct was
unusable because of a bend in the center and because of its condition.
• Item 54A: 4" PVC protection for FAA cable: The taxiway shoulders at B and D were
extended 15' in width; as a result, the existing FAA cable beneath the new pavement had
to be protected with conduit.
• Item 56A: New manhole and connections to replace pull box: The existing pull -box at
station 64 +63 was not airport- rated; as a result, the contractor replaced it with an airport-
rated manhole of the same design as used elsewhere on the project. The extra cost was to
demolish the existing pull -box and to make connections to existing circuits.
• Item 64: L -868 light base can for RWCL or TDZ: The contract is reduced by 76 TDZ
cans due to the proximity of the cans to construction joints.
• Item 64A: Labor and materials for omitted TDZ cans: In lieu of TDZ cans, the
contractor ran conduit and counterpoise to the location of future cans in the proposed
locations. This work required circular saw cuts and installation of extra PVC pipe at each
location.
• Item 65A: Relocate PAPIs twice — temporary: This item was included to temporarily
remove and replace the RW 8 -26 PAPIs.
• Item 67A: Relocate TW edge light twice: The increased width of RW 8 -26 for
temporary operations changed the geometry of the TW turnoffs on TWs C, F, and G.
This necessitated the temporary movement of some of the MITLs.
• Item 70: Permanent seeding and mulching: This item is for erosion control and re-
establishment of grass growth along the new proposed ditch at the 48" pipe outfall.
• Item 72: Sodding: This item is for erosion control and re- establishment of grass
growth along the new proposed ditch at the 48" pipe outfall.
3. The sponsor's share of this cost is available from:
The net change of this contract modification is negative.
4. If this is a supplemental agreement involving more than $2,000, is the cost estimate based on
the latest wage rate decision? Yes ❑ No ❑ Not applicable
5. Has consent of surety been obtained? Yes ❑ Not necessary •
6. Will this change affect the insurance coverage? Yes ❑ No •
Page 4 of 5
7. If yes, will the policies be extended? Yes ❑ No ❑ Not applicable •
8. Has this change order been discussed with FAA officials? Yes • No ❑
When: 11/21/2011 With whom: Mr. Nick Goodly, Atlanta ADO
A1P PROJECT NO. 3 -13- 0011 -033 CONTRACT MODIFICATION NO. 1
kt )aa)aol 1
Date
Recommended by:
Accepted by:
Approved by:
Approved by:
13
Campbell & Paris Engineers — Engineer
APAC - Tennes - e, B : lenger Paving Division - Contractor
414 A
Aug a ' - 'gional Airport
L
Federal Aviation Administration
NOTE: Change Orders and Supplemental Agreements require FAA approval prior to
construction, otherwise no Federal participation can be granted.
Submit 4 copies to the FAA
Page 5 of 5
Date
5 )9-
Date
Date
Via P
AUGUSTA RICHMOND COUNTY
ATTEST:
(12--e-/›.?/
Deke S. Copenhaver, Mayor
Approved.as. -ta,E , :a. ,
ada; /704
Andrew Mackenzie, Esq.
1