HomeMy WebLinkAboutSUPPLEMENTAL AGREEMENT NUMBER 3 CRANSTON ENGINEERING GROUP $348,741.70 ROCK CREEK/WARREN LAKE RESTORATION (CPB ROCK CREEK/WARREN LAKE RESTORATION AUGUSTA-RICHMOND COUNTY
AUGUSTA, GA ENGINEERING DEPARTMENT
SUPPLEMENTAL AGREEMENT
Augusta Richmond County Project Number(s): 322-04-207822001
Supplemental Agreement Number: 3
Purchase Order Number: 165515
WHEREAS, We, Cranston Engineering Group, Consuitant, entered into a contract with Augusta-
Richmond County on May 5, 2009, for engineering design services associated with the Rock
Creek/Warren Lake Restoration Project., File Reference No. 09-014 (A), and
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not covered
by the scope of the original contract, we desire to submit the following Supplemental Agreement
to-wit:
Additional Engineering services for Sediment Sampling & Testing
And p/ans for lake Aumond, Cake Hiers Pond &Upper lake O/mstead
It is agreed that as a result of the above described modification the contract amount is increased
by $148,520.70 from $200,221.00 to a new total of �348.741.70.
Any modifications to submittal dates shall be as identified in the attached proposal. This
agreement in no way modifies or changes the original contract of which it becomes a part, except
as specifically stated herein.
NOW, THEREFORE, We, Cranston Engineering Group, Consuitant, hereby agree to said
Supplemental Agreement consisting of the above mentioned items and prices, and agree that this
Supplemental Agreement is hereby made a part of the original contract to be performed under the
specifications thereof, and that the original contract is in full force and effect, except insofar as it
might be modified by this Supplemental Agreement.
This .2� day of�P����i-��� , 2012
RECOMMEND FOR APPROVAL:
CITY OF AUGUSTA-RICHMOND COUNTY
AUGUSTA, GEORGIA
� • ,
Deke Copenhaver, Mayor a-`' �'�`' � ��
....... .,.._�.. . _,.�.:,.d.
._.._,.. _ �„
Ap�roved: Date ��„�� �° ; Approved: Date 3���'�`Z --
�� �� � ��,�,�� =� � [ATTACHED CORPORATE SEALZ
,� �
, ,. ,.
;� . � �°���� ���� �
.. �� � � � ,
� , , ,'
ATTEST: ; £� - • A
� - � �;..
E � ,
� . � E::
�
� � ,�S'��� �� o �� ; ,
Titde: ` r y ����'f/ Title: —
� � ���.
(5�02 — For changes` �ate�'�han $20 ;.� Apri12010
.t "r
¢� � . �
. � �
Augusta County, Georgia CPB#322
CAPITAL PROJECT BUDGET
ROCK CREEK/WARREN LAKE RESTORATION
CHANGE NUMBER ONE
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County, Georgia that the following
Capital Project Budget is hereby authorized:
Section 1: This project is authorized to CPB#322-041110-207822001 for Rock Creek/Warren Lake
Restoration project Change Number One and Supplemental Agreement Number Three in the
amount of $148,520.70 for Cranston Engineering to provide Sediment Sampling & Testing
and Plans for Lake Aumond & lake Hiers Pond and Upper Lake Olmstead Dredging.
F�znding is available in the project contingency account to be transferred to the project
Engineering account.
Section 2: The following revenues are anticipated to be available to the Consolidated Government to
complete the project.
Special 1% Sales Tax, Phase II $1,200,000
Section 3: The following amounts are appropriated for the project:
By Basin By District
Varies $1,200,000 2nd $1,200,000
Section 4: Copies of this Capital Project Budget shall be made available to the Comptroller for direction in
carrying out this project.
Adopted this � b day of i���%�L c�a� ���-
Approved
� �� �
�'�lr � 1 ��,�
Honorable Deke Copenhaver, Mayor
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
1 of 2 April 6, 2010
�
. f' -
Augusta-Richmond County, Georgia CPB#322-041110-207822001
CAPITAL PROJECT BUDGET
ROCK CREEK/WARREN LAKE RESTORATION
CHANGE NUMBER ONE
CPB AMOUNT CPB NEW CPB
SOURCE OF FUNDB CPB CHANGE AMOUNT
SPECIAL 1% SALES TAX, PHASE II
322-04-1110-292822444 ($1,200,000) ($1,200,000)
TOTAL 30URCES: ($1, 200,000� ��i,2oo,000�
U8E OF FUNDB
ENGINEERING
322-04-1110-5212115-207822001 $300,000 $148,521 $448,521
STORM DRAINAGE
322-04-1110-5414710-207822001 $900,000 ($148,521) $751,479
TOTni. U8E8: $1,200,000 $O $1,200,000
2 0( p Apri16, 2010