Loading...
HomeMy WebLinkAboutCHANGE ORDER ONE SITEC LLC GOSHEN LAKE SOUTH DRIVE DRAINAGE MANAGEMENT (CPB GOSHEN LAKE SOUTH DRIVE DRAINAGE IMP) Change Order Number: One Date: 11/21/2011 Project Title Goshen Lake South Drive Draina�e Mana�ement Original Contract Date: 7 19 2011 Project Number: 324-041110-202824041 Owner: Au�usta-Richmond Countv P.O. Number: P198644 Contractor: SITEC, LLC The following change order is hereby made to the proposal for the above project: See Attached TOTAL AMOUNT OF THIS CHANGE ORDER 5143,723.00 The Contract time will be Increased /Decreased by 0 calendar days as a result of this change. Original Contract Amount $�„714.50 Previous Change Order (Increased / Decreased) 5 0.00 This Change Order (increased / Decreased) 5113,723.00 TOTAL CONTRACT WITH CHANGE ORDER(S) $183.437.50 ************* Funding Source/Account Number: � Requested By: ' `'•' �s' Date: � �� Contr � or � _ ! Z' �' �-� � Submitted By: Date: _ � � Engineer' C s ctio nager c Accepted By: - Date: � � En ' eering Department Head Approved By: � � �R Date: �. � a / � -�, Ma or .. � . Augusta-Richmond County, Georgia CPB#324-041110-201824041 CAPITAL PROJECT BUDGET GOSHEN LAKE SOUTH DRNE DRAINAGE IMPROVEMENTS CPB AMOUNT CPB NEW SOURCE OF FUNDS CPB CHANGE CPB SPLOST, PHASE IV 324-04-1110-201824041 ($39,715) ($39,715) SPLOST, PHASE IV F�xnd Account 324-041110-6011110 ($143,723) ($143,723) TOTAL SOURCES: ($39,715) ($143,723) ($183,438) USE OF FUNDS STORM DRAINAGE 324-041110-5414710-201824041 $39,715 $143,723 $183,438 TOTAL USES: $39,715 $143,723 $183,438 2 of 2 11.212011 � 1 . `. � Augusta-Richmond County, Georgia CPB#324-041110-201824041 CAPITAL PROJECT BUDGET GOSHEN LAKE SOUTH DRIVE DRAINAGE IMPROVEMENTS BE IT ORDAINED by the Commission-Council of Augusta-Richmond County, Georgia that the following Capital Project Budget is hereby adopted: Section 1: This project be set up is authorized to CPB#324-041110-201824041. �,inding is needed for Change Order One for the Goshen Lake South Drive project correct the safety and drainage issues associated with the failing C.M.P. within The Goshen Subdvision for Sitec, LLC in the amount of $143,723.00. Funding is available in SPLOST Phase IV F�.ind balance account to be transferred to the Goshen Lake South Drive project account. Section 2: The following revenues are anticipated to be available to the Consolidated Government to complete the project. Special 1% Sales Tax, Phase IV $ 39,715 Special 1% Sales T�, Phase IV F�.ind Balance $ 143,723 $ 183,438 Section 3: The following amounts are appropriated for the project: By Basin By District McBean 8 Section 4: Copies of this Capital Project Budget shall be made available to the Comptroller for direction in carrying out this project. Adopted this �� day of �_e�c.� �G � Zl' Approved C ..� `" �.� Honorable Deke Copenhaver, Mayor Original-Commission Council Office Copy-Engineering Department Copy-Finance Department Copy-Procurement Department 1 of 2 11.21.2011