HomeMy WebLinkAboutCHANGE ORDER ONE SITEC, INC GOSHEN LAKE SOUTH DRIVE DRAINAGE MANAGEMENT (CPB GOSHEN LAKE SOUTH DRAINAGE IMP Change Order Number: One Date: 11/21/2011
Praject Title Goshen i.ake South Drive Draina�e Mana�ement
Original Contract Date: 7 19 2011 Project Number: 324-041110-201824041
Owner: Au�usta-Richmond Countv P.O. Number: P198&44
Contractor: SITEC. LLC
The following change order is hereby made to the proposal for the above project: See Attached
TOTAL AMOUNT OF THIS CHANGE ORDER $143,723.00
The Contract time will be Increased Decreased by 0 calendar days as a result of this change.
Originai Contract Amount �39,714.�0
Previous Change Order
(Increased / Decreased) 5 0.00
This Change Order
(Increased / Decreased) 5 113,723.00
TOTAL CONTRACT WITH CHANGE ORDER(S) $183.437.50
*************
Funding Source/Account Number:
�--,.- rT` ` �
Requested By: � Date: � 5
Contr�or
� Z b� Z� �
Submitted By: Date: � �
Engineer' C s ctio nager
c
Accepted By: - Date: � �
En ' eering Department Head
<`-�
Approved By: `1, �- Date: �. ��� r Z,
Ma ar
, e .
<, ,
Augusta-Richmond County, Georgia CPB#324-041110-201824041
CAPITAL PROJECT BUDGET
GOSHEN LAKE SOUTH DRIVE DRAINAGE IMPROVEMENTS
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project be set up is authorized to CPB#324-041110-201824041. F�inding
is needed for Change Order One for the Goshen Lake South Drive project
correct the safety and drainage issues associated with the failing C.M.P. within
The Goshen Subdvision for Sitec, LLC in the amount of $143,723.00. Funding
is available in SPLOST Phase IV Fund balance account to be transferred to the
Goshen Lake South Drive project account.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales T�, Phase IV $ 39,715
Special 1% Sales Tax, Phase IV �znd Balance $ 143,723
$ 183,438
Section 3: The following amounts are appropriated for the project:
By Basin By District
McBean g
Section 4: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this �� day of ��c� o�G �/ Z�"
Approved
\���
Honorable Deke Copenhaver, Mayor
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
1 of2 11.21.2011
` ! '
Augusta-Richmond County, Georgia CPB#324-041110-201824041
CAPITAL PROJECT BUDGET
GOSHEN LAKE SOUTH DRNE DRAINAGE IMPROVEMENTS
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB CHANGE CPB
SPLOST, PHASE IV
324-04-1110-201824041 ($39,715) ($39, 715)
SPLOST, PHASE IV Flznd Account
324-041110-6011110 (� 143,723) ($143,723)
TOTAL SOURCES: ($39,715) ($143,723) ($183,438)
USE OF FUNDS
STORM DRAINAGE
324-041110-5414710-201824041 $39,715 $143,723 �183,438
TOTAL USES: $39,715 $143,723 $183,438
2 of 2 11.21.2011