HomeMy WebLinkAboutCONTRACT MODIFICATION NO2 AUGUSTA REGIONAL AIRPORT CONCESSION AREA IMPROVEMENTS CP&E 0733 October 6, 2011
Concession Area Improvements
CONTRACT MODIFICATION NO. 2
AUGUSTA REGIONAL AIRPORT
Concession Area Improvements
DESCRIPTION
Scope of Work - This Change Order is a result of field changes required to ensure the
Concession Area Improvements are fully operational. The following changes to the project are
being requested:
1. New cooler refrigeration equipment $3,300.00
2. Provide one 110 volt 20 amp GFI receptacle at hood $650.00
3. Furnish labor and materials to replace the 11/2" water valve on the
cold water main serving the concession area. $500.00
4. Add fire suppression system including valve and using existing cylinders. $2,960.00
5. Control wiring for cooler $373.00
6. Control wiring for hood fans $1,867.00
7. Add gas piping and gas regulator for the new supply fan for the kitchen
exhaust hood. $1,244.00
8. Reconfigure the ansul system heads based on actual equipment layout. $230.00
9. Disconnect and reconnect the temporary power for the temporary
concession stand. $403.00
10. Fire Marshall required that a Type K fire extinguisher be located in the
kitchen. $230.00
11.Added a receptacle for the heat tape required on the condensate drain
lines in the cooler and freezer. $547.00
12. Change wall framing detail over the cooer and freezer. ($300.00)
13.Add switching for lights in the dining area and bar area. $833.00
14.Adding stainless steel skirt at top of hood $2,296.00
15.Add eight (8 each) receptacles in the room across from the concession
area. $3,299.00
� �� � Office of the Administrator
����:��::,
/' �� �� '�� k ������'�� .
i� � �<` `�3
G�" : .��.H. �.`�.%�::�;.;`.,� A Frederick L Rtusell, Adminisd�ator � Room 801 - Muntcipai Building
-.:ax�. °'�z��=.
530 Greene Street- AUGUSTA, GA: 30901
Tameka Allen, Deputy Administrator (706) 821-2400 - FAX.(706) 821-2819
VVilliarn P. Shanahan, Deputy Administratnr www.august�ga.gov
December 20, 2011
Mr. Gary Le Tellier .
Director — Augusta Regional Airport
1501 Aviation Way
Augusta, GA 30906
Dear Gary:
lYie Augusta-Richmond County Commission, at their �egular meeting held on Tuesday, December 20, 2011 took
action on the following items.
9. Ap�roved the request bf ihe Augusta Aviation Commission for approval of Change Modificati�n #4 to the
Choate Construction Company Contract. (Approved by Public Services Committee December 12, 2011)
12. Approved Reeves Construction Ghange Modifiration #2 in ttie amount of$33,66U.00 at Augusta Regional
Airpflrt. {Approved by Pubiic Services Commiftee December 12, 2011)
13. Appro'v.ed Reeves Construction Contract: Modification !#3 in the amount of $159,512.40 at Augusta
Regional Airport. (Approved by Public Services Committee December 12, 2011)
,. �.
,�.... . , . . �
ia.
. �._; .
� ����` ;: '� ,. .,..� � �,a � � . . � � ,���:���,
�, . . .. �" P�,F � ,
, �
,:� t, P � ' '-"�3 -�+F bi., ' _ �.
� .
,.{� - � . . «...
.
y ' ..;
N � �
t
_. .� .. �� � .
- p -.'.. � •. . s � - nv^�P�.x . .,., r ,.,,.
If you have any questions, please cbrltact me.
Your iruly, �
amek� Allen
Deputy Administrator
12-20-11: #!9, #12, �i13, #1�4
cc: Ms. Donna Williams
Ms. Geri Sams
CP&E 0733 October 6, 2011
Concession Area Improvements
16. Rewire the lighting in the gift shop to operate on two local switches. $1,278.00
TOTAL ADDS $19,710.00
ORIGINAL CONTRACT AMOUNT $287,016.00
CONTRACT MODIFICATION #1 $5,720.00
CONTRACT MODIFICATION #2 $19,710.00
REVISED CONTRACT AMOUNT $312,446.00
CP&E 0733 October 6, 2011
Concession Area tm�raven�snts
SlGNATURE PAGE
RECOMMENUE :
� October 6
Ja Mayfield, PE
V' e President
CAMPBELI, ANO PARIS ENGqdEERS DAT�E
ACCEPTED:
lo � ?,�r1
Max Kn ht
SD CLIFTON C NSTRUCTI�N COMPANY DA7E
APPROVED:
SPONSOR: AUGUSTA, GEORGiA
_.���,�,.�,��- /
C���� , ' `� ,`��'���,'� C. (. � -� �/ 2 � — '
� David S. Copenhaver, Mayqr �'�
�� �� CITY O� AUGUSTA � � � ° � �� ��� DATE
f{ I �` � ' `� � � �
�/ V� � � � � fl '� � .
t i� o R' � _._.._ _
fx a » �
` � , ��� o �
Atles�: Lena B n r, Cier �ot�c5�nn3i��o�• :•�`&;�
CITY F UGUSTf��pi„����c3 �oo.osw°°o•�,��',�r'� DATE
�
� �� t +�; ��,�,`�°���T �������
.��'�t2: °�,.`c.'��D / /'� �'] � �
�V� d /
Ja Fo reste ha�rman
AU U A AVIATION COMMISSION OATE
1 �
�� d
j � 1-
� `w" � �' l � �.� ' I �'--
Gary L eliier, AAE, Executive Direcior
AUGU TA REGIONAL AIRPOR7 AT S�SH FIELD DATE
� � � _ 1 -�0-�1
st: Julie Orwen, Administraiive Manager
AUGUS7A REGIONAL AIRPORT AT BUSH FIELD DATE
ITEM #1
�L� 1 �l�l
car�s�RUCrfa�, iNC.
Gomrr:erciai
Augusta 31, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposal
Dear Jack,
Following is our cost to provide new refrigeration equipment for the existing
cooler box that will be reduced in size to fit the available space.
Southern Mechanical's Proposed cost for the new outdoor and indoor units for the
cooler (see attached proposal) $2,975.00
S.D. Clifton's Mark Up $ 325.00
TOTAL ADD $3,300.00
Please let us know as soon as possible if you want us to proceed with this change.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-maiL•
sdclifton@knology.net
08/26/2010 13:18 7068230606 SOUTHERN MECHANICAL PAGE 01/01
� T T���j � Posi O�ce Box 298'7, Au�usta, Gcorgia 309i4 �h� py�de�
�•� •L' (706) 823-0004 Fax (70b) 823-o0U6
MECHANICAL I�VC. Nunnber: ONG
�
Date: _ D � � � " 1 � 1 ob Number: o?O/D -- � /S
To; Job Name and I.ocation
` �:1�. G� i F7711.1 ��/�tSi �U�GisT"ff s�/kr�O�T C�w'�Sfo�.�
14'�Y�,�,� [C� t r (� /S'o I �v��-rto�! ,(�,�
l9v�usr� �� _
Wc hcrcby agiree to the changc(s} or addi.donal work spcci�ed below:
•�o�r j o�Ro v�� E,t/� �� �/P�N�� � n GooL�r�
"�2���1
r,�,,o��a��r�oQ�.� �ENA�to����s2a6
�c/�A�/1�4 i �2-1Yt�OF,c. � T (�[, � 20� rijA s � �3 � l�
NOTE• 7hia Chang+e Ordsr btcomet pp+a of mid fec cor{Jornw�roe wlth 1J+e wsting co�etract SlRned Chim�gz Otder masl be reaefved prior tv work protesdtng.
We Agrcc hcrcby to make tUe change(s) specifred above at ti�is price - $ Zq75� �
Date o#' A�e�.. t '�0 `�� Previous Contract Amount - $
Authoriaed REV�SEA CONTRAC'�' TOT�.L: $
signacure:
Payment will bc made as follows: PER CONTRAGT
AC C@�J t@ C� — The above prices and speaflWtlons oP ti�ls Change Order are satisfactory and are fiereby accepYed. All work to be
pertormed under the same terms and conditions as specifled in tfie origlna! contract uniess otberwise stlpulat2d.
Authorizcd Signaturc:� Date of Acceptance:
������ ITEM #2
CONSTRItCTiON, 14�C.
Commercial
September 14, 2010
Can�pbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29A�64
Attn: Jack Ma�eld
Via email; jmayfield a�campbell-paris.com
Re: Augusta Airport Concessions
Cha�ige Order Proposal
Dear Jack,
The electrical drawings do not show a couvenience outlet on the watl under the
kitchen llood or power for any of the three �quipment items under the hood. We don't
know if any electrical wiil be required, but want to give you the cost to provide one (1
each) 110volt 20 a�ilp Ground Fault Interupter device under the kitchen hood for control
wiring if needed. This device will be on a shunt trip breaker at the panel, since it is under
the hQOd.
Mundy & Salley Electrical's cost 604,
S.D. Clifton's Mark Up $ .77 �/� �D� ��
TOTAL ADD 00 �1'
Please let us luiow as soon as possible if you want us xo proceed with this change.
Sincerely,
Max Knight
Project ]Vlanager
P.O. Box 949 — Evans, GA 3Q809 — 706-731-0978 — F�: 706-733-4{))30- E niai�l:
sc�cla#'ton�kno#ogy.net
M
MUNDY & SALLEY, INC.
&
ELECTRICAL CONTRACTORS
S INDUSTRIAL, COMMERCIAL
P.O.BOX 211534 4096 BUSINESS PARK CT.
MARTINEZ, GA. EVANS, GA. 30809
PHONE(706)860-4647 FAX(706)855-2097
ADDITIONAL WORK AUTHORIZATION
CONTRACTOR: CLIFTON CONSTRUCTION DATE: 9-].3-10
ATTENTION: MAX KNIGHT C.O.# 1003
JOB NRME: AUGUSTA AIRPORT - CONSESSIONS RENOVATIONS -
WE HEREBY AGREE TO THESE SPECIFIED CHANGES A,ND CHARGES LISTED:
*x�*********,t**�*,t***,t**�r*�r******,t*�r**,t**��****�r*�r*****�*******x�**
* FURNISH ADDITIONAL LABOR/MATERIALS TO PROVTDE (1) 110V 20A *
* GFI REQUIRED DEVICE UNDER KITCHEN HOOD FOR CONTROL WIRING. *
* THIS DEVICE WILL REQUIRED TO BE ON SFiUNT-TRIP BREAKER AT *
* PRNEL W/CONTROL CIRCUIT. *
* *
* PLEASE ADVISE TO PROCEED. *
* *
* ,�
* MATERIALS »$281.72 *
* LABOR »$243.69 *
* 15$»$ 78.82 *
* TOTAL » $604.23 *
* *
■����a�������r��������r��rrra����r������������������� u�����r������r�����������a�
ADDITIONAL CHARGE FOR ABOVE WORK:$604.23
PAYMENT TO BE MADE AS FOLLOWS: AADED TO CONTRACT
OWNER ; AGREES TO THE ADDITIONAL WORK AND CHARGES AS SPECIFIED AB�VE:
AUTHORI2ED SIGNITURE:
CONTRACTOR ; AGREES TO FURNISH ALL LABOR AND MATERIALS TO COMPLETE PtORK
AS SPECIFIED ABOVE AT PRICE SPECIFIED ......................
AUTHOI2IZED SIGNITURE:
ITEM #3
�LIFT�N
�QN��'�iUCT��N, INC.
�,,,
Go.menercial
September 20, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposal
Dear Jack,
Following are change order proposals for the above referenced project:
1. Furnish labor and materials to replace the 11/2" water valve on the cold water
main serving the concession area. Since this area could not be isolated, water for
the entire airport had to be tumed off, which meant that the work had to be done
after midnight.
Coleman Construction's cost (see attached) $454.50
S.D. Clifton's Mark Up 45.50
TOTAL ADD $500.00
Please let us know as soon as possible if you want us to proceed with this change.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
Ct�l_EArI:�N Cc�N�TP�t?CTI��N, INt..
Plumbing•Piping•Fabricabon P.O. Boa1470
Harlem, GA 30814
Phone (706) SSb-3400
Fax (706) 556-6ll6
Request for Change Order
S.D. Clifton Conslruction, inc. Date: 09/16/10
3424 Wheeler Road RCO #2
Augusta, GA 30907
Attn; Ma�c Knight
Project: Concession Renovation for Augusta Regional Airport
Re: Replace Existing Gate Valve
Ma�c,
Per your request, please find following our request for change order to replace
existing 1'/2" gate valve on potable cold water main serving the new Concession Area
As no other valves can be located to isoiate this area, valve replacement will entail water
shut down for the entire facility and must be performed duriug 3 shift.
] ea. - 1%z" bronze sweat gate valve $ 88.00
Shop supplies and consumables - $ 12.00
Sales tax & mark-up - $ 17.00
Total materials - $ 117.00
Labor to drain system, install new valve, test, refill system -
3 hours @$ 112.50 ea. (premium time) $ 337.50
Total Requested Change - $ 454.50
Please let us know as soon as possible if these changes aze acceptable. If you have
any questions or comments, or if you need any additional information, please do not
hesitate to contact us.
Thank you,
�
1
Chris Rollins - Project Manger
ITEM #4
�LIFT�N
�c�r��a��cT�caN, �NC.
Gomrnercial
October 5, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposal
Dear Jack,
In our phone conversation last week you asked me to obtain a proposal for
furnishing a valve that would shut off the gas to the equipment under the hood in the
event of a fire. I asked Southern Mechanical to provide a price for this valve. Southern
Mechanical is installing the existing hood. The fire extinguishing system (ansul system)
in the existing hood has been removed, we did find the two cylinders which are dated
2002.
Southern Mechanical has provided a proposal for the valve and a new fire protection
system for the hood, since the old one has been removed.
1. Fumish and install a new fire protection system in the kitchen hood including the
gas shut off valve.
Southern Mechanical's cost (see attached) $2,650.00
S.D. Clifton's Mark Up 310.00
TOTAL ADD $2,960.00
Please let us know as soon as possible if you want us to proceed with this change.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
i
�
� � T������ Post Ot�ice Box 2987, Augusta, Georgia 3�914 Change D�de� �
U (706)823-0004 Fax (706) 823-OOOb
�VIE�HAN�C1�►L, iN�:. Number: '7�wt�
Date: �� ' � ' �� Job Numbet: �°/O � �/s `
Io: Job Name and •Lacation: �
;
s, D GGl�ro �iNsT, �v�a vsrA ;G(a�l� ���r�Po��'
���.� f�n//C k' T �oN C�ssio�c./ k`��tia r/A rro� ;
i
i
We hereby agree to the change(s) ol additional woik specified beiow:
f
I
�vG'P�-� � /�l�7�l.L : �
;
,�, �
'�C'��osv��r �,2�� ��pPT�SS�DK� �Y57�:7Y1 �oT� j
.�X��r��/� G�'��?��.5'T h�o0�. Tf�iS ��vGGUD�c ill�cv
CyG/ND�2 5� C� S 5f1�/� � U� LU� ,� F�!/tlC� � C •
C�sT � � 100 . °—° i
i
i
� 1���>Ci" �"� ,'�"-vs� �x�sr�n1� �'G�Np��S � � t�l'o, o_o
NO7E: This Change Orde� becomes par! of and in confosmmtCe with the txisling contract S'rgned Chmige Prde� must 6e received prio� to work psocesding
i
We Agee hereby to make the change(s) specified above at tlus price - $ I
Date of Agr�eemen �d' �"�� Previous ConUact Amount - $
Authorized REVISED CONTRACT TOTAL: $
Signature:
�
Paymeat will be made as foltows: PER CONTRACT
�
AC C 2p t. e C� — The above prices and specifications of this Change Order are satisfactory and are hereby accepted.. Ali work to be
performed under the same terms and conditions as specifled in the origina! contract untess otherwise stipuiated.
. �
Authorized Signature: Date of Acceptance:
;
i
ITEM #5 and 6
CLIFTON
CONSTRUCTtON, INC.
Corn�nercial
November 8, 2010
Campbell-Paris, Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Ma�eld
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposals
Dear Jack,
Last week, we discovered that the following electrical items were not shown on
the contract documents, but do need to be addressed in order to complete the project.
1) The drawings do not indicate the control wiring for the walk in cooler equipment
Mundy & Salley's cost (see attached quote) $339.12
S.D. Clifton's Mark Up 33.88
TOTAL ADD $373.00
2) The exhaust fan and supply fan for the existing hood have to be interlocked and
controlled by a remote cabinet that came with the fans, since the make up air fan has a
gas heater included. The existing hood has only two simple toggle switches, so the
conduit and wiring for the remote cabinet is in addition to the contract documents.
Mundy & Salley Electrical's cost to provide and install conduit and wiring from
the make up air fan and the exhaust fan to the new remote control cabinet. (see attached
proposal) $1,698.00
S.D. Clifton's Mark Up 169.00
TOTAL ADD $1,867.00
Please let us know as soon as possible if you want us to proceed with these
changes.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
M
MUNDY & SALLEY, INC.
&
ELECTRICAL CONTRACTORS
S INDUSTRIAL, COMMERCIAL
P.O.BOX 211534 4096 BUSINESS PARK CT.
MARTINEZ, GA. EVANS, GA. 30809
PHONE(706)860-4647 FAX(706)855-2097
ADDITIONAL WORK AUTHORIZATION
CONTRACTOR: CLIFTON CONSTRUCTION DATE: 11-03-10
ATTENTION: MAX KNIGHT C.O.# 1009
JOB NAME: AUGUSTA AIRPORT - CONCESSION RENOVATIONS
WE HEREBY AGREE TO THESE SPECIFIED CHANGES AND CHARGES LISTED:
********,t*****************,t****t,t***************,t**,t*************
* FURNISH ADDITIONAL LABOR/MATERIALS TO PROVIDE CONTROL WIRE *
* AND TERMINATIONS FOR WALK-IN COOLERS SYSTEM. *
* *
* *
* *
* PLEASE ADVISE TO PROCBSD. *
* *
* *
* MATERIALS »$ 66.88 *
* LABOR»$228.00 *
* 15 0 »$ 44 . 24 *
* TOTAL» $ 3 3 9 .12 *
* *
i�����������������������r����r�����r�r�r�rt������������������r��������������r�■
ADDITIONAL CHARGE FOR ABOVE WORK:$339.12
PAYMENT TO BE MADE AS FOLLOWS: ADDED TO CONTRACT
OWNER ; AGREES TO THE ADDITIONAL WORK AND CHARGES AS SPECIFIED ABOVE:
AUTHORIZED SIGNITURE:
CONTRACTOR;AGREES TO FURNISH ALL LABOR AND MATERIALS TO COMPLETE WORK
AS SPECIFIED ABOVE AT PRICE SPECIFIED ......................
AUTHORIZED SIGNITURE:
M
MUNDY & SALLEY, INC.
&
ELECTRICAL CONTRACTORS
S INDUSTRIAL, COMMERCIAL
P.O.BOX 211534 4096 BUSINESS PARK CT.
MARTINEZ, GA. EVANS, GA. 30809
PHONE(706)860-4647 FAX(706)855-2097
ADDITIONAL WORK AUTHORIZATION
CONTRACTOR: CLIFTON CONSTRUCTION DATE: 11-01-10
ATTENTION: MAX KNIGHT C.O.# 1008
JOB NAME: AUGUSTA AIRPORT - CONCESSION RENOVATIONS
WE HEREBY AGREE TO THESE SPECIFIED CHANGES AND CHARGES LISTED:
*******,t,t****t,t*******,t*****,t,t********,t******,t*********,t******�t*
* FURNISH ADDITIONAL LABOR/MATERIALS TO PROVIDE %" CONDUIT WITH *
* REQUIRED #14 CONDUCTORS AND 2-PAIR SHIELDED CABLES TO THE *
* SUPPLY/EXHAUST HOODS FROM REMOTE CONTROL CABINET @ HOOD, THIS *
* INCLUDES ALL FINAL CONNECTIONS TO HOOD SYSTEM. *
* *
* PLEASE ADVISE TO PROC$ED. *
� *
* *
* MATERIALS »$ 717.28 *
* LABOR»$ 760.00 *
* 15%»$ 221.60 *
* TOTAL»$1,698.88 *
* *
i��r������r���r�r������rr��������r��������������������������������������������•
ADDITIONAL CHARGE FOR ABOVE WORK:$1,698.88
PAYMENT TO BE MADE AS FOLLOWS: ADDED TO CONTRACT
OWNER ; AGREES TO THE ADDITIONAL WORK AND CHARGES AS SPECIFIED ABOVE:
AUTHORIZED SIGNITURE:
CONTR.ACTOR;AGREES TO FURNISH ALL LABOR AND MATERIALS TO COMPLETE WORK
AS SPECIFIED ABOVE AT PRICE SPECIFIED ......................
AUTHORIZED SIGNITURE:
ITEM #7
CLIFTQN
coNS��ucT�aN, wc.
Commercial
November 29, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.cam
Re: Augusta Airport Concessions
Change Order Proposal
Dear Jack,
It just came to my attention that the supply fan for the hood has a gas heater in it,
which will require a gas line be run to the supply fan. The drawings do not show a gas
line to the supply fan. I asked Coleman Construction to provide me a price to add the gas
line and connection to the supply fan. Following is the cost:
Coleman's cost (see attached quote) $1,131.00
S.D. Clifton's Mark Up 113.00
TOTAL ADD $1,244.00
Please let us know as soon as possible if you want us to proceed with this change.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-73 1-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
CLIFTtJT�T ITEM #8
CONBTRUCTIO-N, tNC.
t�
Commercial
March 29, 2011
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Orders
Dear Jack,
Following is an updated summary of the approved changes to date.
Reconfigure the ansul system heads based on actual equipment layout.
Metro Fire & Safety's cost $200.00
Clifton's Mark Up $30.00
TOTAL ADD $230.00
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
C t c�N�TP.LTt.TI�N, INC.
Plumbing•Piping•Fsbrication P.O, Box1470
Hsrlem, GA 3081�
Phone (706) SSb-3q00
Fax (7D6) 556�6ll6
Request for Change Order
S.D. Clifton Construction, Inc. Date: 11/29/10
3424 Wheeler Road RCO #3
Augusta, GA 30907 .
Attn: Max Knight
Project: Concession Renovation for Augusta Regional Airport
Re: Install Gas Supply for Make Up Air Unit
Max,
Per your request, please find following our request for change order to install a 1"
natural gas supply line with step-down gas pressure regulator for the new rooftop Make
Up Air Unit (MAi�.
Our price assumes installation will be performed during normal business hours.
1 ea. - 1"gas pressure regulator $ 169.OQ
1 lot - 1" steel pipe, fittings, supports, etc. $ 281.00
Estimated incoming freight. $ 25.00
Shop supplies and consumables - $ 47.00
Sales tax & mark-up - $ 89.00
Total materials - $ 61 I.00
Labor to install piping & regulator -
8 hours @$ 65.00 ea. (regulaz time) $ 520.00
Total Requested Change - $ 1,13 l.00
Please let us know as soon as possible if these changes are acceptable. If you have
any questions or comments, or if you need any additiona] information, please do not
hesitate to contact us.
Thank you,
� �--
Chris Rollins - Project Manger
ITEM #9
CLIFTON
CONSTRI�CTiO�, INC.
Cammercia!
December 23, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposals
Dear Jack,
o are the change order proposals we talked about yesterdav
1. Add switching ining room lighting and li m the bar. These
lights will have to be rewire .
Mundy & Sall �' see attache ' $757.77
. i on's Mark Up .23
TOTAL ADD $833.00
2. Additional labor and materials to disconnect and reconnect the temporary power
for the temporary concession stand.
Mundy & Salley's cost (see attached) $366.85
S.D. Clifton's Mark Up 36.15
TOTAL ADD $403.00
Please let us know as soon as possible if you want us to proceed with these
changes.
On another note: we discovered that there is a gas leak in the gas line in the
supply fan for the hood. Once we repair, there should not be any gas odor
present.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
M
MUNDY & SALLEY, INC.
&
ELECTRICAL CONTRACTORS
S INDUSTRIAL, COMMERCIAL
P.O.BOX 211534 4096 BUSINESS PARK CT.
MARTINEZ, GA. EVANS, GA. 30809
PHONE(706)860-4647 FAX(706)855-2097
ADDITIONAL WORK AUTHORIZATION
CONTRACTOR: CLIFTON CONSTRUCTION DATE: 12-22-10
ATTENTION: MAX KNIGHT C.O.# 1012
JOB NAME: AUGUSTA AIRPORT — CONCESSION STAND RENOVATIONS
WE HEREBY AGREE TO THESE SPECIFIED CFiANGES AND CHARGES LISTED:
***,t*******,t**,t*********�t****,t*******,t**************************
* ADDITIONAL LABOR/MATERIALS TO DISCONNECT AND RECONNECT *
* TEMPORARY POWER AND TEMPORARY CONCESSION STAND. *
* *
* *
* PLEASE ADVISE TO PBOCESD *
* *
* *
* *
* MATERIALS »$ 15.00 *
* LABOR»$304.00 *
* 15%»$ 47.85 *
* TOTAL »$366.85 *
* *
i�������ra�������������������r��r��rr������������r��r�rr����r��r��r�����r��r����
ADDITIONAL CHARGE FOR ABOVE WORK:$366.85
PAYMENT TO BE MADE AS FOLLOWS: ADDED TO CONTRACT
OWNER • AGREES TO THE ADDITIONAL WORK AND CHARGES AS SPECIFIED ABOVE:
AUTHORIZED SIGNITURE:
CONTRACTOR;AGREES TO FURNISH ALL LABOR AND MATERIALS TO COMPLETE WORK
AS SPECIFIED ABOVE AT PRICE SPECIFIED ......................
AUTHORIZED SIGNZTURE:
ITEM #10
cL1�TON
CO.NSTRU�TiC�N, I�1C.
Commerciai
March 29, 2011
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Orders
Dear Jack,
Following is an updated summary of the approved changes to date.
Fire Marshall required that a Type K fire extinguisher be located in the kitchen.
Cost of Fire Ext from Metro Fire & Safety $200.00
Clifton's Mark Up $30.00
TOTAL ADD $230.00
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
��,IFTON ITEM #11
CONSTRUCTIQN, INC.
Commerciai
March 29, 2011
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Orders
Dear Jack,
Following is an updated summary of the approved changes to date.
Added a receptacle for the heat tape required on the condensate drain lines in the cooler
and freezer.
Mundy & Salley's cost $315.89
Clifton's escort cost $160.00
Clifton's Mark Up $71.11
TOTAL ADD $547.00
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
ITEM #12
��� 1 ��
CFJ�NSTRUET�ON, INC.
,�`
Cor�mercial
September 10, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposal
Dear Jack,
Following is our proposal to change the wall framing detail above the cooler and
freezer. We have used this detail numerous times over coolers and freezers in
convenience stores and restaurants. I have attached a sketch of the proposed detail.
Credit to change this detail will be DEDUCT $300.00
Please let us know as soon as possible if you want us to proceed with this change.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail: '
sdclifton@knology.net
ITEM #13
�LIFTtJN
CONSTRI�CTIf�N, INC.
�.
Comrnerciai
December 23, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposals
Dear Jack,
Following are the change order proposals we talked about yesterday.
1. Add switching for the dining room lighting and lighting behind the bar. These
lights will have to be rewired.
Mundy & Salley's cost (see attached) $757.77
S.D. Clifton's Mark Up $ 75.23
TOTAL ADD $833.00
2. = al labor and materials to disconnect and reconnect the te � y�ower
for the tempora � ssion stand.
Mundy & Salley's cos $366.85
S.D. Clifton's p 36.15
TOTAL ADD � 00
Please let us know as soon as possible if you want us to proceed with these
changes.
On another note: we discovered that there is a gas leak in the gas line in the
supply fan for the hood. Once we repair, there should not be any gas odor
present.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
M
MUNDY & SALLEY, INC.
&
ELECTRICAL CONTRACTORS
S INDUSTRIAL, COMMERCIAL
P.O.BOX 211534 4096 BUSINESS PARK CT.
MARTINE�, GA. EVANS, GA. 30809
PHONE(706)860-4647 FAX(706)855-2097
ADDITIONAL WORK AUTHORIZATION
CONTRACTOR: CLIFTON CONSTRUCTION DATE: 12-22-10
ATTENTION: MAX KNIGHT C.O.# 1011
JOB NAME: AUGUSTA AIRPORT - CONCESSION STAND RENOVATIONS
WE HEREBY AGREE TO THESE SPECIFIED CHANGES AND CHARGES LISTED:
***************************************t************************t
* ADDITIONAL LABOR/MATERIALS TO ADD SWITCHING FOR DINNING ROOM *
* LIGHTING AND LIGHTING BEHIND BAR AREA, LIGHTING WILL HAVE TO *
* BE REWIRED. *
* *
* PLEASE ADVISE TO PROCEED *
* *
* *
* *
* MATERIALS »$ 88.93 *
* LABOR»$570.00 *
* 15%»$ 98.84 *
* TOTAL»$757.77 *
* *
i�����������������������r����r������������������������Rr����r����������������r�
ADDITIONAL CHARGE FOR ABOVE WORK:$757.77
PAYMENT TO BE MADE AS FOLLOWS: ADDED TO CONTRACT
OWNER:AGREES TO THE ADDITIONAL WORK AND CHARGES AS SPECIFIED ABOVE:
AUTHORIZED SIGNITURE:
CONTRACTOR ; AGREES TO FURNISH ALL LABOR AND MATERIALS TO COMPLETE WORK
AS SPECIFIED ABOVE AT PRICE SPECIFIED ......................
AUTHORI2ED SIGNITURE:
ITEM #14
CLIFTC�N
�ON���i�CT1QN, INC.
Corn�ercial
November 1, 2010
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Order Proposals
Dear Jack,
Following are two change order requests for the above referenced project:
1) The existing kitchen hood does not have the stainless steel shroud that will conceal the
space between the top of the hood and the ceiling. We have obtained a quote from a local
sheet metal company to fabricate and install this shroud.
Advance Industrial Group's cost (waiting on written quote) $2,087.50
S.D. Clifton's Mark Up $ 208.50
TOTAL ADD $2,296.00
Please let us know as soon as possible if you want us to proceed with these
changes.
Sincerely,
, Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knology.net
�� j ��
"�►.,.,+r�r..�
industrial M�.intenance & Machine, Inc_
N ov�►n ber 1, ?.O 10
Clifton Construction, Tnc. Quote #lUlG86
4324 Whecicr Rd.
M.artinez, Ga. 30907
ATT'N: Aob Wallace
RE; Quotation f'or Stai.nless Steel Ho�d Skirt
Dear $ob:
T am pleased to provide you with the following quotation foz� your considera.tion
rc�arding the stainless stccl hood skirt for the Augusta R.egional Arrport that we looked at
last week. The price for this project will be �2087.50 and will consist of the fvilowing:
•Provide labor and ma.terial to fa.brica.te the sttsiaa.less steel hodd skirt.
•Provid� labor ancl material lo insta111hc fabricatcd hood skirt at the A«gusl�
kegio�ial Airport.
•Hood skitt to be cx,nstructed af 22 Gauge T�e 304 Stainlcss Steel with #3
polishcd finish and measure 16" high x 48" dccp x 14'-0" long and.
•Hood skirt to be supported with a center support mounted to ihe wa.11.
Thank you f4r this opportu.nity to work widi you on tliis project, Ple�se review the abovc
quotation and IeC me know if you should have any questions or i�eed any ad.ditional
information.
Sin�erely,
Richard Grove
4183 Mike Padgett Nwy., Augusta, GA 30906
Phone:706.793.9710 Fax:706,793.9711
www.indmachine.com
' Z = ll_r,".�a��;� nrC�tEEL9G� IE!��sr�-�=�i '=-'�'r' '�'��di�l __'C�t-lC�-ll-
ITEM #15
CLIFTQN
cor�s��ucT�aN, ir�c.
Cammercial
February 9, 2011
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport
Electrical Proposals
Dear Jack,
Following is the cost to provide labor and materials to install eight (8 each)
duplex receptacles in the room across from the concession area. Four of the receptacles
will be surface mounted using wire mold at the knee wall. The remaining four (4)
receptacles will be mounted in the walls with the wiring being fished from above. These
eight receptacles will be on two circuits, which will be extended to this area from the
basement. Minor drywall patching is included. Also includes security escorting as
required.
Mundy & Salley's cost $2,169.00
Drywall and Paint repair & touch up $ 350.00
Security escort $ 350.00
S.D. Clifton's Mark Up 430.00
TOTAL ADD $3,299.00
Let me know if you have any questions or conems.
Sincerely,
Max Knight
Project Manager
P.O. Box 949 — Evans, GA 30809 — 706-731-0978 — Fax: 706-733-4030- E-mail:
sdclifton@knoiogy.net
�L�F'i ��� ITEM #16
Ct7NSTRUCTtON, INC.
-;
Camm��cial �
March 29, 2011
Campbell-Paris Engineers
303 Wingo Way
Mt. Pleasant, SC 29464
Attn: Jack Mayfield
Via email: jmayfield@campbell-paris.com
Re: Augusta Airport Concessions
Change Orders
Dear Jack,
Following is an updated summary of the approved changes to date.
Rewire the lighting in the gift shop to operate on two local switches. This was
done by Mundy & Salley on time and material, with Clifton Construction
providing escorting.
Mundy & Salley's cost $791.91
Clifton's escort costs $320.00
Clifton's Mark Up $166.09
TOTAL ADD $1,278.00
Sincerely,
Max Knight
Project Manager