Change Order Number: #1 Date: September 6. 2011
Project Title: Ft Gordon CM an.Risk
Original Contract Date: February 14, 2011 Project Number:
Owner: __ Augusta Utilities P.O. Numbe
Contractor: Tetra Tech Inc.
The following change order is hereby made to the proposal for the above project: Addition of Raw Water
Irrigation System per attached scope and pricing. Other components of this Change Order include a
design-build element for order control at Chafee Ave Lift Station & Hypochlorite System at Ground
Water Plant #1 per attached scope and pricing.
TOTAL AMOUNT OF THIS CHANGE ORDER $ 7,208,935.00
The Contract time will be Increased/Decreased by -0- calendar days as a result of
this change. The date of completion including this change order is Julv 31, 2012
Original Contract Amount $ 22,993,573.00
Previous Change Order
(Increased / Decreased) $ _p_
This Change Order
(Increased / Decreased) $ 7,208,935.00
TOTAL CONTRACT WITH CHANGE ORDER(S) $ 30,204,508.00
��*�***�**��*
Funding Source/Account Number 507043490-5425410 / 88887777-5425410.Ft Gordon
511043410-5212115 / 80310812-5212115 Chafee Ave Lift Station
51 4 410- 2 2115 / 80310813-5212115 Ground Water Plant # 1
Requested By: Date: 6
Pr ' ct I�Q er
Submitted By: Q�, �„� Date: 28 �
Department Head
Finance Endorsement: � - � � �.� ,o ate: 9-� //
omp ol r
Recommended By: Date: �f«28�--�1
minis ator
Approved By: � Date: � � � `� /l �
, a
Accepted By: Date: ,� 1 �
ontra tor `��--