ENGINEERING DEPARTMENT
SUPPLEMENTAL AGREEMENT
Augusta Richmond County Project Number(s): 324-041110-201824110
Supplemental Agreement Number: 4
Purchase Order Number: 85641
WHEREAS, We, URS Corporation, entered into a contract with Augusta-Richmond County on "March 18,
2003", for engineering design services associated with the "Downtown Traffic Signal & Street Light Upgrade A
Project", Project No. 324-041110-201824110, File Reference No. 11-014 (A), and
WHEREAS, certain revisions to the design requested by Augusta-Richmond County are not covered by the
scope of the original contract, we desire to submit the following Supplemental Agreement to-wit:
Additional Engineering services are needed to supplement the URS contract to cover
utility coordination, engineering and design of Group B of the Downtown Traffic Signal
Upgrade project.
It is agreed that as a result of the above described modification the contract amount is increased by
$279.233.10 from $782,402.58 to a new total of $1.061,635.68.
Any modifications to submittal dates shall be as identified in the attached proposal.
This agreement in no way modifies or changes the original contract of which it becomes a part, except as
specifically stated herein.
NOW, THEREFORE, We, URS Corporation, hereby agree to said Supplemental Agreement consisting of the
above mentioned items and prices, and agree that this Supplemental Agreement is hereby made a part of the
original contract to be performed under the specifications thereof, and that the original contract is in full force
and effect, except insofar as it might be modified by this Supplemental Agreement.
This _� day of �, �L'' , 2011.
(�'
RECOMMEND FOR APPROVAL:
CITY OF AUGUSTA-RICHMOND COUNTY
AUGUSTA, ORGIA
� -�� �
Honorable Deke Copenhaver, Mayor URS Corporation
Approved Date: �' � � Approy.�d Date: �•Z
�ACHE C RPORA ,
� _ ,:
ATT . ,, �
�'`.��'
Carol F. Brandenburg-Smith
Title: Assistant Secretary �
URS Corporation
(SA03 - For changes more than $20,000)
Augusta-Richmond County, Georgia CPB# 324-041110-201824110
CAPITAL PROJECT BUDGET
DOWNTOWN TRAFFIC SIGNAL 8a STREET LIGHT UPGRADE (A)
CHANGE NUMBER FOUR
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: The project is authorized to CPB# 324-041110-201824110 Change Number Four. This proposal
address the Polara audible pedestrian crossing devices along Broad Street as part of the
signal upgrades between 12th Street and 5th Street. Funding will come from Downtown
Traffic Signal & Street Light Upgrade (A) SPLOST Ph. IV Contingency
Account Project F�,inds in the amount of $58,582.00.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1% Sales T�, Phase IV $ 300,000
Special 1% Sales T�, Phase IV $ 2,023,000
$ 2,323,000
Section 3: The following amounts are appropriated for the project:
By Basin By District
Varies $ 2,323,000 2nd $ 2,323,000
Section 4: Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this � day of �
� Approve �
� ,.,.� _..
Honorab eke Copenhaver , Mayor
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
1 of 2 4.18.2011
V �
♦
Augusta-Richmond County, Georgia CPB# 324-041110-201824110
CAPITAL PROJECT BUDGET
DOWNTOWN TRAFFIC SIGNAL � STREET LIGHT UPGRADE (A)
CHANGE NUMBER FOUR
CPB AMOUNT CPB NEW
30URCE OF FUNDS CPB CHANGE CPB
SPECIAL 1% SALES TAX, PHASE IV
324-04-1110-6011110-201824110 $2,323,000 $0 $2,323,000
TOTAL 80URCES: $2,323,000 $0 $2,323,000
USE OF FUNDS
ENGINEERING
324-04-1110-5212115-201824110 $963,003 $963,003
ADVERTISMENT
324-041110-5233119-201824110 �2,000 $2,000
TRAFFIC SIGNALS
324-041110-5414610-201824110 $58,582 $58,582
CONTINGENCY
324-041110-6011110-201824110 $1,357,997 ($58,582) $1,299,415
TOTAL USElS: $2,323,000 $O $2,323,000
2 Of 2 4.18.2011