HomeMy WebLinkAboutCHANGE ORDER ONE BLAIR CONSTRUCTION BELAIR HILLS SUBDIVISION IMPROVEMENTS Change Order Form
Change Order Number: ONE Date: 01/04/2011
Project Title: Belair Hills Subdivision Improvements
Original Contract Date: 9/21/08 Project Number: 324 -04- 203824335
Owner: ARC P.O. Number: P155705
Contractor: Blair Construction
TOTAL AMOUNT OF THIS CHANGE ORDER $ 244,407.11
As a result of this Change Order, the anticipated contract completion date is thirty (30)
days from Commission approval date.
Original Contract Amount $ 6,549,090.64
Previous Change Order(s) Total $
This Change Order $ 244,407.11
TOTAL CONTRACT WITH CHANGE ORDER(S) $ 6,793,497.75
* * * * * * * * * * * **
Funding Source /Account Number: 324 - 041110- 6011110- 207824999 - 6011110
Requested By: L . ,,. ,i �, "� `�/ Date: I I v I f i
/Const Ition, ager
Submitted By: i/ " % , J ,1 Date: 2/0/
Departme t " ead
Approved By: C.12 4 ciit Date: ti / I t
Mayor
Accepted By: ab X / tip% Date: /-13_ 20//
Contractor
cc: Anthony (Tony) Williams, Construction Manager
Geri Sams, Director Procurement
Eric Loggins, Accountant
Valerie Jenkins, Engineering
Tim Schroder, Finance
File