HomeMy WebLinkAboutCHANGE ORDER ONE TO J HARRIS TRUCKING STORM DRAINAGE IMP AT VILLAGE WEST Change Order Form
Change Order Number: ONE Date: 10/26/2010
Project Title: Storm Drainage Improvements at Village West
Original Contract Date: 4/1/2010 Project Number: 324 - 041110 - 210824702
Owner: ARC P.O. Number: P180285
Contractor: J. Harris Trucking
TOTAL AMOUNT OF THIS CHANGE ORDER $ 25.229.79
As a result of this Change Order, the anticipated contract completion date is thirty (30)
days from Commission approval date.
Original Contract Amount $ 297,101.48
Previous Change Order(s) Total $
This Change Order $ 25.229.72
TOTAL CONTRACT WITH CHANGE ORDER(S) $ 322,331.27
* * * * * * * * * * * * *
Funding Source /Account Number: 324 - 041110- 0000000
Requested B : j ._�� " ;� / �
q Y Date: /2K 7/0 foistructAirrf - ,
Submitted By , ,i /! J ; "L s _._Date: lZ 2
Department Head
Finance Endorsement: ,c9Uy14/7 6 (A ),,tat p,„4 Date: / //
Finance Director
Approved By: Date: t / i /r J
ay or
Accepted By: Date:
ontractor 1
cc: Anthony (Tony) Williams, Construction Manager
Geri Sams, Director Procurement
Valerie Jenkins, Dept Accountant
Tip Schroder, Finance
g C L ® L 5 EGG o