HomeMy WebLinkAboutR W ALLEN EXHIBIT G-1 TEE CENTER Exhibit G -1
Authorization for Construction
Pursuant to this agreement, the Owner and the Construction Manager hereby execute
this Exhibit G -1 and further agree as follows:
1. The Construction Manager's Guaranteed Maximum Price ( "GMP ") proposal for the
entire Project has been established. The Construction Manager's GMP for the TEE
Center Project, dated December 7, 2010, attached hereto and incorporated herein,
is accepted by the Owner.
2. The General Conditions Guaranteed Maximum Cost for the $1,082,670.00
Project, including this Bid Package, is
3. Preconstruction Services $26,400.00
4. The Subcontracts Cost is:
Bid Package #1 $250,930.00
Bid Package #2 $1,796,647.00
Bid Package #3 $710,842.00
Bid Package #4 $3,199,543.00
5. The Lump Sum Fixed Management Fee for the Project, $780,000.00
including this Bid Package, is
6. The Guaranteed Maximum Price per attachment A (Value
Engineering) for the Project is: $27,900,000.00
7. The Date of Substantial Completion shall be 24 months after
Notice -to- Proceed
Items 2, 3, and 5 above were previously agreed to and included in the agreement.
Owner: Construction Manager:
Augusta, Georgia R.W. Allen, LLC
By:
0 , - - -e> v (Signature) (Seal) (Signature) (Seal)
Ip#iv = 5 • Gvv 5d— .... T --.... sic_
(Name) (Name)
Wilk oA— `Fi23 i o:
(Titl -) i , (Title)
/ kil /
(Attest) b y s ' ' (Street Address - No PO Box)
(City Cle 1 ••••00,400 19 °^ 1 (City, State, Zip)
�,
� 4 mq�` Eot�C� 1 • • t.4-. 2. 1\
D /7/f7 Signature g'®`� Date of Signature
9 9
1 of 1
1
1015 Broad Street Augusta, Georgia 30901
Office 706,733.2800 I Fax 706.733.3879 www.rwallen.com
wow
4 " P A
Decernber 7, 2009
Ivir. Jacques Ware
RWAllen
Project Manager, Heery IDED
Augusta Richmond County
Capital Improvements Program Management
501 Greene Street
Augusta, GA 30901
RE: Guaranteed Maximum Price Contract
Augusta Tee Center
Mr. Ware,
It is our understanding that Augusta-Richmond County would like to execute a Guaranteed
Maximum Price (GMP) contract with R.W. Allen, LLC. Based on our 75% pricing exercise we
produced a GMP number of $29,471,109.00. After a thorough estimate reconciliation meeting
with Heery, we were able to reduce the GMP nunaber. However, we still exceeded the
established GMP of $27,900,000.00. Therefore, R. W. Allen has developed the attached list of
scope clarification savings and value engineering (ongoing) items in an effort to achieve the
desired GMP.
R. W. Allen, LLC will execute the GMP contract in the amount of $27,900,000.00 based on the
project cost reconciliation and the acceptance of the attached value engineering items which are
required to achieve the desired GMP.
If you have any questions or concerns regarding the attached items, please do not hesitate to
contact us.
Sincerely,
R.W.. Allen, LLC
Scott A. Clark
President and CEO
_p
Construction Services
.,
'
Attachment A
2 2010
C._ 1 1171
5 Augusta Trade Exhibit & Event Center
P
k.
Potential Savings
. � .
'
^ ^
75% GMP Estimate dated 11/17/10 $29/71,109
Potential Savings
Design Contingency Reducton ($479885)
Subtotal $28,991
Scope Clarifications
Refine wood decking & gu-lam beam scope ($20,000)
Metal Wall Panel Scope ($20,000)
Door Hardware Scope ($15,080)
Etiminate utility screen wall ($10,000)
Elimiaate roof screen wall at Iow roof area ($G,OOO)
Refine painting scope ($20'000)
Refine flooring scope ($90,000)
Refine eevator scope ($84,000)
Refine fire protection scope ($05,000)
Value Engineering
Eliminato treatment for wood decking ($4,000)
Eflminate FSC requirements for wood decking ($8,000)
Eliminate treatment for glu-4am beams ($18,000)
Eliminate fSC requirements for gIuiam beams ($21,000)
Provide schedue 10 fire sprinkler pipe in Iieu of schedule 40 TBD
Eliminate AVVI certified cabinet/millwork mariufacturer ($190,000)
Reduce parapet @ courtyard along the kitchen roof ($40,000)
Eliminate (J) toilets (#x~ tile, acr. &fianmin0) ($7,500)
Eliminate utility screen wall ($12,500)
Eliminate roofscreen wall at Iow roof area ($5,000)
Install TPDin lieu nf metal roof panels ($40,000)
Modify duct insulation & stainless wrap ($80,000)
Reduce metal panel scope TBD
Eliminate duct cteaning ($75,800)
Provide metal coping in tieu of caststone @ stucco parapets ($20,000)
Install ACT in tieu of stucco drive thru ceillag ($I5,000)
Provide stucco in Iieu of brick @ the west elevation ($3,500)
Provide 5000# standard size car wlth 46 bi-parting doors for freight elev. ($130,000)
Provide holed hydrautic elevators in Iieu traction elevators ($65,000)