HomeMy WebLinkAboutKissingbower Road
Augusta Richmond GA
DOCUMENTNAME: \0SS'()S~ ~
DOCUMENT TYPE:'?'( ~~\
YEAR: 00
BOX NUMBER: \ \
BLENUMBER:\~~~
NUMBER OF PAGES: ~
,
OLD ENGINE COMPANY NO, I
452 ELLIS STREET
POST OFFICE BOX 2546
AUGUSTA, GEORGIA 30903,2546
~'1'5"""'"
, .
Cranston, Robertson & Whitehurst, ~
ENGDNEERS PLANNERS SURVEYORS
J, CRAIG CRANSTON, P.E" R,L.S,
THOMAS H. ROBERTSON, P.E., R.L.S.
ELDRIDGE A. WHITEHURST, JR., P,E,
JAMES B. CRANFORD, JR., P,E,
DENNIS J, WELCH, P,E,
TELEPHONE (706) 722.1588
TELECOPIER (706) 723.8379
E.MAIL CRWPCQCRWPC.COM
JOHN T. ATfAWAY, R.L.B,
WAYNE SWANN, R.L.S,
MICHAEL S. BERGLUND
STEVEN M. BRYANT
DWIGHT E, FUNDERBURK, II
BOBBY M. USRY
KEITH A. LAWRENCE
KELVIN G. OGLESBY
September 22, 2000
Ms. Robin McMillon
Augusta Utilities Department
2760 Peach Orchard Road
Augusta. Georgia 30906
I-lAND DELIVERY
Re:
Kissingbower Road Area
Sanitary Sewer Extension, Phases I V and V
Our File No. 96-088.0 I
Dear Robin:
In accordance with your request. we are pleased to offer the following proposal for revising
our current construction plans, providing construction phase services. and for providing as-built
record drawings for the sanitary sewer project located on and near Kissingbower Road. George Road.
Haynie Drive, and Milton Road.
I. REVISIONS TO CURRENT CONSTRUCTION PLANS
According to the review of the current plans by CH2M Hill and our subsequent meeting on
Thursday. September 14. 2000. we have listed below the revisions that were requested.
A, We propose to:
I, Update existing plan to reflect the current government otticials in office,
2, Revise the name on each sheet from Augusta-Richmond County Utilities to Augusta
Uti I i ties Department.
3. Provide X.y.z val LIes for each manhole, including I'inished 1 id elevation with a qual ifying
note as to the expected tolerance. Coordinates based on assumed system with control
monuments shown on plans.
4, Add stationing for each match line shown.
5. Move sewer taps out of manholes.
6, Acid note specifying type of sewer piping.
7, Change detail of "Trenching, Backfilling and Repaving" to match current AugLlsta-
Richmond County Public Works Department requirements./ D
b.~'>i"
L/:
..
.
;;
~
1\1s, Robin McMillon
September 22. 2000
Page 2
B, We "viii revise the contract documents per CH2M Hill's technical review memo to:
I, Reflect current government officials.
2. Meet current Augusta Utilities Department standards.
], Add supplementary condition adding program manager.
4, Provide contract duration in proposal and agreement sections.
5. Revise asphalt overlay dimension,
6. Move additional items at unit prices to contract items with an estimated quantity and
add riprap to list.
7, Revise technical specifications for excavating, trenching and bacldilling for pipe lines
to match the current Augusta-Richmond County Public Works Department standard.
i{, Correct technical specification labeling of the Measurement and Payment Section hom
-06 to -07.
<), Revise technical specitication for ductile iron pipe 10 specify epoxy lining in accordance
with the standard specifications of the Augusta Utilities Department.
Fee Proposal
Our tee for this work will be a lump sum of$I,640.00,
Time of Completion
We are prepared to begin work at your direction and expect to complete the job within two
weeks of receiving your notice to proceed.
II. CONSTRlJCTION PHASE SERVICES
We propose (0 furnish the following construction phases services as required: assisting you
with securing bids li'om qualitied contractors, advising you concerning the award of a contract,
issuing a notice to proceed, making periodic observations of the construction work as it progresses
to observe the progress and general quality, furnishing wri tten observation reports of the
observations made during each visit, issuing instructions to the contractor, reviewing the contractor's
monthly applications for partial payment, determining the amounts owing to the contractor,
i nterpreti ng the con tract documents and technical speci fications. consulti ng as necessary wi th
Augusta Utilities Department and CH2M Hill program manager, making a linal inspection to
determine whether or not the work has been completed substantially in accordance with the plans
and specilications. and reviewing the contractor's application for tinal payment.
Any observation services provided will be for the purpose of monitoring compliance with the
plans. specifications. and contract documents, and will not in any manner be a guarantee of the
methods, appliances. or schedules employed by the contr8ctor, nor for the safety of the job,
i.
~
.
~
.
Ms, Robin McMillon
September 22, 2000
Page 3
Fee Proposal
Our fee for this work will be on a time and material basis not to exceed $5,760.00, according
to our rates in effect at the time services are provided. A current rate table is attached. This fee is
based on the construction contract duration of 180 days. For any increase in the length of the
contract, we would expect to provide additional services on a time and material basis,
III. RECORD DRA W.lNGS
We propose to furnish final as-built drawings showing northern and easting values (Georgia
State Plane Coordinates) for each sanitary manhole and to provide elevations for manhole lids and
inverts, Sewer service locations will be shown using the dimensions from the field prints provided
by the contractor. This information will be shown on the construction plans and will be provided
to Augusta Utilities Department on mylar and electronically in CAD f(wmat.
Fee Proposal
Our fee for this work will be a lump slim of $5,1 60.00.
Time of Completion
We are prepared to begin work at your direction after construction actIVities have been
completed and expect to complete this phase of the project within four weeks of receiving your
notice to proceed,
We appreciate the opportunity of making this proposal and trllst that you find it satisfactory,
Should you have any question concerning the scope of the services offered, or the fees, please do not
hesitate to give us a call.
Sincerely,
CRANSTON, ROBERTSON & WHITEHURST, p,c.
w~~
Wayne Swann
Project Manager
WS/vlk
\\:-'lalilll!:-';'_l'\l\J\,FlIl'..,II!{UI'( IS..\I.\'}(,():-;X ~lllltJ Il,\'j..illlI.\\-pll
.i>.
,
". .t
"
Cranston, Robertson & Whitehurst, PC.
ENGUNEERS PLANNERS SURVEYORS
OLD ENGINE COMPANY NO, I
452 ELLIS STREET
POST OFFICE BOX 215U
AUGUSTA, GEORGIA 30903.2546
J. CRAIG CRANSTON, P.E., R.I..S,
THOMAS H. ROBERTSON, P.E., R.L.S,
ELDRIDGE A. WIDTEHURST, JR., P,E.
JAMES B. CRANFORD, JR" P.E.
DENNIS J. WELCH, P,E,
TELEPHONE (706) 722.1588
TELECOPIER (706) 722.6379
E.MAIL CRWPC@CRWPC,COM
June 15, 2000
JOHNT. ATrAWAY, R.L.S.
WAYNE SWANN, R.L.S.
MlCIlAEL S. BERGLUND
STEVEN M. BRYANT
DWIGHT E, FUNDERBURK, U
BOBBY M. USRY
KEITH A. LAWRENCE
KBLVIN G. OGLESBY
SCHEDULE OF RATES & CHARGES
TIME & MATERIAL BASIS
Personnel Charges
Senior Principal Engineer
Principal Engineer
Senior Professional Engineer
Professional Engineer
Project Engineer III
Project Engineer II
Project Engineer I
Engineering Technician II
Engineering Technician I
Land Surveyor II
Land Surveyor I
Field Project Supervisor
Survey Party
CADD Operator III
CADO Operator II
CADO Operator I
Inspector II
Inspector I
Stenographer
$ 150.00/Hr.
135.00/Hr.
105.00/Hr.
85.00/Hr.
75.00/Hr.
70.00/Hr.
60.00/Hr.
60.00IHr.
50.00/Hr.
80.00/Hr.
55.00/Hr.
50.00/Hr.
105.00/Hr.
65.00/Hr.
60.00/Hr.
45.00IHr.
60.001Hr.
50.00/Hr.
40.001Hr.
Reimbursable Charges:
Travel Expenses:
Mileage
Lodging, etc.
$0.37/mile
Cost plus 15%
Blueprinting:
Paper Prints
Paper Sepias
Mylar Sepias
$O.50/Sq.Ft.
$1.50/Sq.Ft.
$2.50/Sq.Ft.
Other Reimbursable Items:
Cost plus 15%