December 26, 2000
Mr. Max Hicks, P.E.
Augusta Utilities Department
360 Bay Street, Suite 180
Augusta, Georgia 30901
Attn: 2000 CIP Program Manager
RE: Fairington Subdivision Sanitary Sewer Extension
Project No. 50200 .
Dear Mr. Hicks:
Southern Partners, Inc. is pleased to submit this proposal to provide professional services
for the design of approximately 34,000 linear feet of sanitary sewer, 700 services and necessary
appurtenances to serve properties in the Fairington Subdivision and surrounding areas. More
particularly:
- Connector line from the Horsepen Sewer Line to the F airington Subdivision,
- Fairington Drive from Tobacco Road to Teakwood Drive,
- Highpointe Drive from Bowen Drive to Bowen Drive,
- Teakwood Drive from Fairington Drive to Spirit Creek Road,
- Sadie Court from Lynncrest Drive to the dead end,
- Carrington Drive from Clayborn Drive to the dead end,
- Lynncrest Drive from Teakwood Drive to the dead end,
- Beacon Hill Drive from Teakwood Drive to Carrington Drive,
- Hickory Cove Road from Teakwood Drive to Carrington Drive,
- Elmwood Court from Teakwood Drive to the qead end,
- Clayborn Drive from Teakwood Drive to Spirit Creek Road,
- Carrington Court from Teakwood Drive to the dead end,
- Lincolnton Parkway from Kevin Road to Spirit Creek Road,
- Broxton Court from Lincolnton Parkway to the dead end,
- Country Lane from Lincolnton Parkway to Spirit Creek Road,
- Spirit Creek Road from Kevin Road to Lincolnton Parkway,
- Mikey Drive from Teakwood Drive to Clayborn Drive,
- Mikey Court from Teakwood Drive to the dead end,
- Creek Court from Spirit Creek Road to the dead end,
- Spirit Court from Spirit Creek Road to the dead end, and
- Connection of the Pinnacle Place lift station to the trunk line,
~J.R.fr Our fee for these services is One Hun,dred Eighty One Thousand Three Hundred Fifty Dollars
~rJ)~~.)~ and No Cents ($181,350.00).
1233 Augusta West Parkway
Augusta. GeorgIa 30909
Phone (706) 855-6000
Fax (706) 869-9847
-
. ,
~
Mr, Max Hicks
"
( December 26, 2000
Page 2
We propose to furnish the following services:
1. Conduct field surveys of the proposed sanitary sewer route to determine property
boundaries, line and grade, utilities and other physical encroachments.
2. Prepare conceptual plans (30% submittal) for determining routing, sizing and
design considerations unique to this project.
2. Prepare preliminary plans (60% submittal) for the installations of these lines.
Preliminary plans will be reviewed with Augusta Utilities Department and the
Program Manager before work is started on the final plans.
3. Prepare final construction plans (90% submittal) and bid documents, including a
construction cost estimate.
4. Discuss bid results with the program manager to determine any items that may
cause the selection of a contractor other than the low bidder.
5. Prepare easement plats as needed for lines that cross private property.
6. Monitor the general progress (surveillance) of the project and review all job
submittals.
Augusta Utilities Department will provide all available maps and plans for sanitary sewer
and water lines in and adjacent to the project area, all GIS information (digital and paper) and all
other pertinent information available in the public records.
This project can be ready for concept review within 90 days of receipt of your purchase
order and authorization to proceed. An estimated schedule is attached, Payment for services will
be based on percentages completed. Invoices will be submitted in accordance with a mutually
agreed upon schedule to allow time for review by the Program Manager.
We appreciate this opportunity to be of service to Augusta Utilities. If you have any
questions, please call me.
~rely, C...:.. _. _
- ~;5:) ~L?Y~
David W. Simoneau, P.E.
Senior Engineer
Attachment
(
. .. ~
;.. Jl
> ,
, '.
.. .
a
,-
(
..
FAIRINGTON SUBDIVISION SANITARY SEWER
ESTIMATED DESIGN SCHEDULE
AUTHORIZATION TO PROCEED: JANUARY 29,2001
SURVEYS COMPLETE, INCLDUING DRAFTING: MARCH 19, 2001
CONCEPT PLANS (30%) COMPLETE: APRIL 23, 2001
PRELIMINARY PLANS (60%) COMPLETE: JUNE 4, 2001
FINAL PLANS (90%) COMPLETE: JULY 9, 2001
READY FOR BIDS: AUGUST 6,2001