CAPITAL PROJECT BUDGET
EISENHOWER EMERGENCY DRIVEWAY
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: The project is authorized to CPB#jNA. This project proposes to construct a
driveway which will provide emergency vehicle access for emergencies at both
Lynndale School and the ball parks. On occasions Eisenhower Drive is blocked
by trains, providing no access to the school and the ball parks in case of an
Emergency. Funding is available in SPLOST PH 2 Recapture.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1 % Sales Tax, Phase 2
GOaT STATE AID CONTRACT
$
$
$
30,000
9,000
39,000
Section 3: The following amounts are appropriated for the project:
By Basin
Phinizy Swamp
39,000
By District
1st $ 39,000
$
Section 4:
Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
day of -9lh1~ JOdi
Approved
U2~ t/ -
Honorable ~openhaver, Mayor
Adopted this f}?-
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
1 of 2
CPB#/NA
1-22-2008
. ~
AugUsta-Richmond County, Georgia
CAPITAL PROJECT BUDGET
EISENHOWER EMERGENCY DRIVEWAY
CPB AMOUNT CPB
CPB CHANGE
SOURCE OF FUNDS
SALES TAX, PHASE IV
326-04-1110-6011110-288811333
($30,000)
($9,000)
GOaT STATE AID CONTRACT
($39,000)
$0
TOTAL SOURCES:
USE OF FUNDS
CONSTRUCTION
326-04-1110-5414110-000000000
$39,000
$39,000
$0
2of2
NEW
CPB
($30,000)
($9,000)
($39,000)
$39,000
$39,000
CPB#/NA