Augusta-Richmond County, Georgia
CPB#323-041110-296823215
CAPITAL PROJECT BUDGET
ALEXANDER DRIVE IMPROVEMENTS
(WASHINGTON ROAD TO RIVERWATCH PARKWAY)
CHANGE NUMBER SEVEN
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is hereby adopted:
Section 1: This project be set up is authorized to CPB#323-04111O-296823215. Additional
funding is needed to complete the acquisition of right-of way, demolition, utility
relocation, environmental and changes in roadway design documentation.
Funds in the amount of $1,000,000 are available in SPLOST Fund Balance and
SPLOST Phase II Recapture.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1 % Sales Tax, Phase II Recapture
Special 1 % Sales Tax, Phase III Recapture
Augusta Utilities
Special 1 % Sales Tax, Phase III Recapture
Special 1 % Sales, Tax Fund Balance
Special 1 % Sales Tax, Phase III Recapture
Augusta Utilities
$ 500,000
$ 2,522,795
$ 24,768
$ 86,680
$ 2,500,000
$ 117,680
$ 105,850
$ 5,857,773
Section 3: The following amounts are appropriated for the project:
Rock Creek
By Basin
$5,857,773
By District
$ 5,857,773
Section 4:
Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
-rJ;:.
Adopted this? day of -l4 .~ d f d tJ 6' r
APprovi
UJ~
Original-Commission Council Office
Copy- Engineering Department
Copy- Finance Department
Copy-Procurement Department
1of2
10/6/08
.,.#
Augusta:Richmond County, Georgia
CPB#323-041110-296823215
CAPITAL PROJECT BUDGET
ALEXANDER DRIVE IMPROVEMENTS
(WASHINGTON ROAD TO RIVERWATCH PARKWAY)
CHANGE NUMBER SEVEN
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB CHANGE CPB
SPLOST, PHASE II
322-04-1110-6011110-292822333 $0 ($500,000) ($500,000)
SPLOST, PHASE III
323-04-1110-000000-000000000 ($2,522,795) $0 ($2,522,795)
AUGUSTA UTILITIES
507043420-5212115/89800510-5212115 ($24,768) $0 ($24,768)
SPLOST PHASE III
323-04-1110-6011111-296823333 ($86,680) $0 ($86,680)
SPLOST, FUND BALANCE
322-000-000000/39-52110 ($2,000,000) ($500,000) ($2,500,000)
SPLOST PHASE III
323-04-1110-6011110-296823333 ($117,680) $0 ($117,680)
AUGUSTA UTILITIES ($105,850) $0 ($105,850)
507043410-5212115-80800030
TOTAL SOURCES: ($4,857,773) ($1,000,000) ($5,857,773)
USE OF FUNDS
ENGINEERING
323-04-1110-5212115-296823215 $664,237 $0 $664,237
ADVERTISING
323-04-1110-5233119-296823215 $0 $0 $0
RAILROAD PERMIT
323-04-1110-5414610-296823215 $0 $0 $0
RIGHT OF WAY
323-04-1110-5411120-296823215 $4,193,536 $1,000,000 $5,193,536
UTILITIES
323-04-1110-5414510-296823215 $0 $0 $0
507043410-5212115-80800030
AUGUSTA UTILITES
507043420-5212115/89800510-296823215 $0 $0 $0
CONSTRUCTION
323-04-1110-5414110-296823215 $0 $0 $0
SIGNALS
323-04-1110-5414610-296823215 $0 $0 $0
CONTINGENCY
323-04-1110-6011110-296823215 $0 $0 $0
TOTAL USES: $4,857,773 $1,000,000 $5,857,773