Augusta-Richmond County, Georgia
CPB#324-041110-201824117
CAPITAL PROJECT BUDGET
EAST BOUNDARY STREET AND DRAINAGE IMPROVEMENTS
(Laney Walker Blvd. to Broad Street)
CHANGE NUMBER FIVE
BE IT ORDAINED by the Commission-Council of Augusta-Richmond County,
Georgia that the following Capital Project Budget is here by adopted:
Section 1: The project is authorized to CPB#324-041110-201824117. This project is to address
drainage related issues in the general area from Laney Walker Boulevard to
Broad Street. This project will also include roadway improvements to include
resurfacing, adding curb, gutter, and sidewalk where feasible. The funding for
this project was set up for Advertising, Engineering, Right of Way, Utilities,
Construction and Contingency. Additional funding in the amount of $156,000
is required to fully fund this project. Funds are available in SPLOST PH IV
Recapture.
Section 2: The following revenues are anticipated to be available to the Consolidated
Government to complete the project.
Special 1 % Sales Tax, Phase IV
Special 1 % Sales Tax, Phase II
GDOT STATE AID CONTRACT
CDBG FUNDS
Special 1 % Sales Tax, Phase II
Special 1 % Sales Tax, Phase IV Recapture
$ 1,167,000
$ 853,000
$ 450,000
$ 300,000
$ 1,000,000
$ 156,000
$ 3,926,000
Section 3: The following amounts are appropriated for the project:
By Basin
Phinizy Swamp
$ 3,926,000
By District
1st $ 3,926,000
Section 4:
Copies of this Capital Project Budget shall be made available to the
Comptroller for direction in carrying out this project.
Adopted this /9 day Of.;i..d. ~tJ tJ 1
Approved .
U
Hono~~nhaver. Mayor
Original-Commission Council Office
Copy-Engineering Department
Copy-Finance Department
Copy-Procurement Department
1of2
1-22-2008
Augusta-Richmond County, Georgia
CPB#324-041110-201824117
CAPITAL PROJECT BUDGET
EAST BOUNDARY STREET AND DRAINAGE IMPROVEMENTS
(Laney Walker Blvd. to Broad Street)
CHANGE NUMBER FIVE
CPB AMOUNT CPB NEW
SOURCE OF FUNDS CPB CHANGE CPB
SALES TAX, PHASE IV
324041120-0000000-000000000 ($1,167,000) ($1,167,000)
SALES TAX, PHASE II
322-04-1110-6011110-292822444 ($853,000) ($853,000)
GDOT STATE AID CONTRACT ($450,000) ($450,000)
CDBG FUNDS ($300,000) ($300,000)
SALES TAX, PHASE II CONTINGENCY
324041110-6011110-292822444 ($1,000,000) ($1,000,000)
SALES TAX, PHASE IV RECAPTURE
324041110-6011110-207824999 ($156,000) ($156,000)
TOTAL SOURCES: ($3,770,000) ($156,000) ($3,926,000)
USE OF FUNDS
ADVERTISING
324041110-5212119-201824117 $2,000 $2,000
ENGINEERING
324041110-5212115-201824117 $148,000 $148,000
UTILITIES
324041110-5414510-201824117 $60,000 $60,000
RIGHT OF WAY
324041110-5411120-201824117 $50,000 $50,000
CONSTRUCTION
324041110-5414110-201824117 $3,510,000 $156,000 $3,666,000
CONTINGENCY
324041110-6011110-201824117
TOTAL USES: $3,770,000 $156,000 $3,926,000
2of2 1-22-2008
Office Of1he Administrator
Tameka Allen, Intrrim Deputy Administrator
Robert lrverett, InkTim Deputy Adminilltr'..tor
Room 801 - Municipal8uilding
:;;10 Greene Street-AUGUSTA, QA. 30'01
(706) 821-2400 - FAX (706) 821-28"
www.augusmga.gov
February 19. 2008
Mr. Abie Ladson
Engineering Director
505 Greene Street
Augusta. GA 30901
Dear Abie:
The Augusta-Richmond County Commission. at their regular meeting held on Tuesday. February
19,2008. took action on the followIng items.
35. L Approved Change Number Five (CPB#l32~~jj1l=2$l.1.D241171in the .mount qf$156.000 funds
frc:iffi""SP(OSrPhase ~Recapture. Also. transfer $156,000 to Project Construction for the East
Boundary Street and Drainage Improvements Project and approve Change Order Number One
with Mabus Brothers Construction in the amount of $506.000 as requested by the Engineering
Department. (Approved by Engineering Services Committee February 13. 2008)
44. Approved resolution creating street lighting districts. (Approved Engineering Services Committee
January 30, 2008)
If you have any questions, please contact me.