Loading...
HomeMy WebLinkAboutAMENDMENT NO 1 WORK AUTHORIZATION NO 17 -. ...:, CITY OF AUGUSTA. by and through AUGUSTA REGIONAL AIRPORT AVIATION COMMISSION Amendment No.1 to Work Authorization No. 17 LPA Project No. AR209035 It is agreed to amendment Work Authorization No. 17 as follows: Description of Assignment: The contracted time covered by Work Authorization No. 17 will expire on October 22,2007; see attached Exhibit A "Explanation of Schedule Revision." Consultant will continue to provide Architectural and Engineering Construction Administration services for Augusta Regional Airport as set forth in Work Authorization No. 17, with the approval of this Amendment No.1, beginning October 23,2007. Basis of Comoensation/Period of Services: I. Compensation: F or Architectural, and Engineering Services, as outlined in Description of Assignment above, the CONSULTANT shall be paid Fourteen Thousand Dollars and No Cents ($14,000.00) per month. 2. Period of Services: Consultant will provide services stated above until such time as the project reaches Substantial Completion or the Owner is no longer in need of said services. Page 1 of2 100307 ~:~,~ Title: Mavor Agreed as to scope of services, time schedule, and budget: City of Augusta by and through WITNESZ9 p;, !~tCl.--, WITNESS: WITNESS: WITNESS: Page 2 of2 100307 By: ~ ~~:.,.,.;~-,-..- I ..'.:...:t\ \-'~' '~, ...~. Augusta, 'Georg~~" '". By: Title: Vice President ,- EXHIBIT A EXPLANATION OF SCHEDULE REVISION LP A's agreement with the Augusta Regional Airport Commission to provide Construction Administration (CA) services for the Terminal Improvement Program was based on an assumption that the Contractor would be Substantially Complete with the entire project (4 phases) by October 22, 2007. This is based on a NTP date of on or about April 13, 2005 and a contract time of905 days, plus 18 days for Master's week breaks, or a total of923 days. Further, we understand, and for reasons beyond LP A's control, the Contractor has been granted an additional 92 days based on Change Orders to date. This brings the new current date established for Substantial Completion to January 22,2008. Finally, it is also our understanding, based on the most recent submitted schedule, that the Contractor is actually planning to achieve Substantial Completion of Phase 4 on or about April 14, 2008.or six (6) months later than the original date established for Substantial Completion.