HomeMy WebLinkAboutGARNTO & GEARIG BROTHERS CONSTRUCTION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
rr--
Ii
I
I
i
I
I
II
II
I
I
I
,
I
I
II
"
I
,
i
i
I
,
.
1.
<I
II
.1
I
,
i
j
I
I
CONTRACT DOCIThiENTS
FOR
DL~MOND LAKES
TENNIS COMPLEX
Prepared for
AUGUSTA, RICHMOND COITNTY COMMISSION
L Cranston Engineering Group, P.C.
~~p ENGINEERS - PLAl\i'NERS - SURVEYORS
,\( I /"
452 ELLIS STREET. AUGUSTA, GEORGL" 30901
POST OFFICE BOX 2546, AUGUSTA, GEORGIA 30903
TELEPHONE 706-722-1588
FACSIMILE 706-722.g37~
mail@cranstonengineering.com
May 20, 2008
2006-0066
I
1I
ii
I
I
I
I
II
,I
h
II
"
II
r
II
I
I
"
"
Ii
l
JUL-16-2008 16:04
ARC PURCHASING
P.03
I
r
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
~(,lftJ!<"m.('l/(. ~)CI.o)ttnl/'1I1
I A
'~, &':-1'1 W!rfI7I-J. ~i;f"r'If."
TO:
FROM:
All Bidders
Phyllis Mills, Quality Assurance Analyst
Geri Sams ~ f~
Procurement Director
DATE:
July 16, 2008
SUBJ:
BID ITEM;
OPENING:
Clarification of Specifications
08~14a Diamond Lakes Tennis Complex for Augusta Recreation & Parks
Wednesday, July 23rd at 3;00 P.M.
ADDENDUM NO.1
I. The following items have been revised or added to the contract documents and
specifications:
Invitation to Bids - Delete in its e[1tirety the original sentence "No BID may be withdrawn
for a period of 90 days after time has been called on the date of opening," and
replace with the revised sentence:
"No BID may be withdrawn for a period of 60 days after time has been called on
the date of opening."
AfJreement - In the first sentence of the third paragraph under ARTICLE /I - TIME OF
COMPLETION - LIQUIDATED DAMAGES delete and replace the liquidated
damages daily sum of "Three Hundred Dollars ($300.00)" with "One Hundred
Dollars ($100.00)."
General Conditions - Delete the Index to Articles of the General Conditions and General
Conditions in its entirety and replace with the revised Index to General
Conditions and General Conditions enclosed on Pages 2-17 of 17.
II. The following questions from the Pre-Bid Conference and subsequent submitted
questions have been addressed:
1. Is the bottom of the fence on the tennis courts requiring a tension rail or
w~? .
Continuous top and bottom rails shall be provided as part of the fencing.
2. Will the Contractor be required to water and maintain the landscaping for
any period of time outside of the contract?
It will be the Owner's responsibility for maintaining and watering the trees once
the Contractor reaches Substantial Completion.
Room 60S. S30 Green Street, Augusta Georgia 30911
(706) 821-2422 - Fax (706) 821-2811
WWW.8U2ustael\.ROV
Register at www.demandstar.com/suoolier for automatic bid notification
JUL-16-2008 16:04
ARC PURCHASING
P.04
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION
GC-01
GC-02
GC~03
GC~04
GC-05
GC~06
GC-07
GC-oa
GC~09
GC-10
GC-11
GC-12
GC-13
GC-14
GC-15
GC-16
GC-17
GC~18
GCM19
GC-20
GC-21
GC-22
GC-23
GC-24
GC-25
GC-26
GC-27
GC-28
GC-29
GC-30
GC-31
GC-32
GC-33
GC-34
GC-35
GC-36
GC-37
GC-38
SECTION GC-O
INDEX TO GENERAL CONDITIONS
Definition of Terms
Execution, Correlation and Intent of Documents
Authority of the Engineer
Contractor's Obligation
Insurance Requirements
Contractor's Breakdown of Lump Sum Payment
Subcontracting
Applicable Requirements
Permits and Licenses
Plans and Specifications
Surveys
Materials and Appliances
Schedule of Work
Field Office Facilities
Lands for Work
Contractorls Personnel
Protection of the Public and of Work and Property
Existing Structures and Utilities
Changed Conditions
Inspection of Work
Correction of Work Before Final Payment
Deductions for Uncorrected Work
Changes in the Work
Extension of Time
Clean-Up
Guarantee: Correction of the Work
Claims for Extra Cost
Separate Contracts
Rights of Various Interests
The Owner's Right to Terminate Contract
Contractor's Right to Stop Work or Terminate Contract
Removal of Equipment
Royalties and Patents
Liens
Assignment
Payments Withheld Prior to Final Acceptance of Work
Appeal
Taxes and Fees
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:04
P.05
ARC PURCHRSING
SECTION GC
GENERAL CONDITIONS
GC-01. DEFINITION OF TERMS:
(a) The Contract Documents shall consist of Advertisement for Bids or Notice
to Contractois, Instruction to Bidders, Form of Bid or Proposal, the signed Agreement, the
General and Special Conditions of Contract. the Plans, and the Specifications, including all
modifications thereof incorporated in any of the documents before the execution of the
Agreement.
(b) The OWNER and ~ONTRACTOR shall mean the parties to the
Agreement for the performance of the work covered by these Documents and mentioned as
such in the Agreement. They are treated throughout the Contract Documents as if each were of
the singular number and masculine gender.
(c) The word !NGINEERshall mean the firm, CRANSTON ENGINEERING
GROUP, P.C.. acting through the principals thereof in the capacity of Chief Engineers of the
Owner, or through any properly authorized agents of the principals acting within the scope of the
particular duties entrusted to them.
(d) The phrase "or equal" shall mean an item of material or equipment similar
to that named and which is suited to the same use and capable of performing the same function
as that named. The item proposed to be used shall be submitted to the Engineer for approval
before it is employed in the work.
(e) The Notice to Proceed shall be a special written work order from the
Engineer giving the Contractor notice of the date on which he is to begin prosecution of the work
which he has contracted.
GC.02.EXECUTION. CORRELATION AND INTENT OF DOCUMENTS:
Contractor.
The Contract Documents shall be signed in duplicate by the Owner and the
The Contract Documents are complementary and what is called for by anyone
shall be as binding as if called for by all. In case of conflict between plans and specifications.
the specifications shall govern. The intention of the documents is to include all labor and
materials, equipment and transportation necessary for the proper exeoution of the worK.
Materials or work described in words which so applied have a well-known technical or trade
meaning shall be held to refer to such recognized standards.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:04
ARC PURCHASING
P.06
GC-03.
AUTHORITY OF THE ENGINEER:
The Contractor shall perform all of the work herein specified under the general
direction and to the entire satisfaction, approval and acceptance of the Engineer. The Engineer
shall decide all questions relating to measurement of quantities, the character of the work
performed and on all other matters relating to the execution and progress of the work or the
interpretation of the Contract Documents. He has authority to stop the work whenever such
stoppage may be necessary to insure the proper execution of the contract. He shall also have
authority to reject all work and materials which do not conform to the contract.
GC-04.CONTRACTOR'S OBLIGATIONS;
Contractor shall and will, in good workmanlike manner, do and perform all work
and furnish all supplies and materials, machinery, equipment, facilities and means, except as
herein otherwise expressly speoified, necessary or proper to perform and complete all the work
required by this contract, within the time herein specified, in acoordance with the provisions of
this contract and said specifications and in accordance with the drawings of the work covered by
this contract and in accordance with the directions of the Engineer as given from time to time
during the progress of the work. He shall fumish. erect, maintain, and remove such ~onstruction
plant and such temporary works as may be required. He alone shall be responsible for the
safety, efficiency, and adequacy of his plant, appliances and methods, and for any damage
which may result from their failure or their improper construction. maintenance, or operation.
The Contractor shall observe, comply with, and be subject to all terms, conditions, requirements
and limitations of the Contract and specifications, local Ordinances and State and Federal laws;
and shall do, carry on and complete the entire work to the satisfaction of the Engineer.
The Contractor assumes full responsibility for materials and equipment used in
the construction of the work and agrees to make no claims against the Owner for damages to
such materials and equipment from any cause except negligence or willful act of the Owner.
Until its final acceptance, the Contractor shall be responsible for damage to or destruction of the
project. He shall make good all work damaged or destroyed before acceptance.
The Contractor shall defend, indemnify and save harmless the Owner, its
officers, agents, servants and employees against and from all suits, losses, demands,
payments, actions, recoveries, judgments and costs of every kind and description and from all
damages to which the Owner or any of its officers, agents, servants and employees may be
subjected by reason of injury to the person or property of others resulting from the performance
of the project or through any act or omission on the part of the Contractor or his agents,
employees or servants; and he shall further defend, indemnify and save harmless the Owner, its
officers, agents, servants and employees from all suits and actions of any kind or character
whatsoever which may be brought or instituted by any subcontractor, material man or laborer
who has performed work or furnished materials in or about the Project or by, or on account of,
any claims or amount recovered for an Infringement of patent, trademark or copyright.
GC.05.
INSU~ANce REQUIREMENTS:
The Contractor shall secure and maintain such insurance from an insurance
company authorized to write casualty insurance in the State where the work is located as will
protect himself, his subcontractors and the Owner from claims for bodily injury, death or
property damage which may arise from operations under this contract. The Contractor shall not
commence work under this contract until he has obtained all insurance required under this
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:05
ARC PURCHASING
P.07
paragraph and shall have filed the certificate of insurance or the certified copy of the insurance
policy with the Owner. Satisfactory proof of the carriage of the insurance required shall be
furnished with the executed contract documents. Each insurance policy shall contain a clause
providing that it shall not be canceled by the insurance company without ten (10) days written
notice to the Owner of intention to cancel. The amounts of such insurance shall not be less
than the following:
(a) Workman's C...omoensation and Emolovers Liability Insurance shall be secured
and maintained as required by the state where the work is located.
(b) Public Liabil~ Bodilv Iniury and Procerty Damage:
1. Injury or death of one person....................................................$1 ,000,000
2. Injury to more than one person
in a single accident ... ..... ............... ......... ....... ...... ..... ..........,....... 2,000,000
3. Property Damage - Each accident..............................................1 ,000,000
Aggregate ........................... ............. ....... ..... 2,000,000
(c) Automobile and T[Uck Public Liability. Bodilv Iniury and Property Damage:
1. Injury or death of one person ...................:................... $1 ,000,000
2. Injury to more than one person
In a single accident .....:........................ ................... .......2,000,000
3. Property Damage - Each Accident ................................. 2,000,000
GC-06.
CONTRACTOR'S BREAKDOWN OF LUMP SUM PAYMENT:
The Contractor shall, immediately after the contract has been awarded, submit to
the Engineer for his approval, a breakdown Showing estimates of all costs apportioned to the
major elements of equipment, material and labor comprising the total work included under any
of the lump sum items shown in the proposal. These estimates. approved, will serve as a basis
for estimating payments due on all partial estimates.
GC..o7.SUBCONTRACTlNG:
(a) Contractor may utilize the services of specialty subcontractors on those
parts of the work which, under normal contracting practices. are performed by specialty
subcontractors.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:05
ARC PURCHASING
P.08
Prior to beginning any work or prior to award of contract, if requested, Contractor shall submit
for approval the name of each specialty subcontractor whose bids were used in the preparation
of his proposal and whose services are intended to be employed for the contract work.
(b) Contractor shall not award any work to any subcontractor without prior
written approval of the Engineer, which approval will not be given until the Contractor submits to
the Engineer a written statement concerning the proposed award to the subcontractor, which
statement shall contain such information as the Engineer may require.
(0) Contractor shall be as fully responsible to the Owner for the acts and
omissions of his subcontractors, and of persons either directly or indirectly employed by them,
as he is for the. acts and omissions of persons directly employed by him.
(d) Contractor shall cause appropriate provisions to be inserted in all
subcontracts relative to the work to bind subcontractors to the Contractor by the terms of the
General Conditions and other Contract Documents insofar as applicable to the work of
subcontractors and to give the Contractor the same power as regard terminating any
subcontract that the Owner may exercise over the Contractor under any provision of the
Contract Documents.
(e) Nothing contained in this contract shall create any contractual relation
between any subcontractor and the Owner.
GC-08.
APPI.ICABLE REQUIREMENTS:
The work shall comply with the Contract Documents and with all applicable
codes, laws and regulations of local, state or federal agencies which may have cognizance of
any part of the work. The most stringent requirement of the foregoing documents and codes
shall govern. Except where the prevention of accidents is regulated by local code or ordinance,
compliance is required with the "Manual of Accident Prevention in Construction" of the
Associated General Contractors of America. If Contractor observes that the drawings and
specifications are at a variance therewith, he shall promptly notify the Engineer in writing. If
Contractor performs any work knowing it to be contrary to such laws, ordinances, rules or
regulations and without such notice to the Engineer, he shall bear all costs arising therefrom.
GC-09.PERMITS AND LICENSES:
The Contractor shall obtain and pay for all permits and licenses of a temporary
nature which are required for the execution of the work.
Permits, licenses and easements for permanent structures or permanent
changes in existing facilities shall be secured and paid for by the Owner, unless otherwise
specified.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-1b-~0B8 16:05
ARC PURCHASING
P.09
GC-10.PLANS AND SPECIFICATIONS:
Drawings that comprise the original plans for the Contract are listed in the
Special Conditions. Unless otherwise provided in the Contract Documents, the Engineer will
furnish to the Contractor, free of charge, a reasonable number of drawings and specifications for
the execution of the work.. All drawings, specifications and copies thereof so furnished shall not
be reused on other work, and, with the exception of the signed Contract, all sets are to be
returned to him on request at the completion of the work.
GC-11.
SURVEYS:
Unless otherwise specified, the Owner shall furnish all land surveys. The
Engineer shall establish all base lines for locating the principal component parts of the work
together with a suitable number of bench marks adjacent to the work.. From the information thus
provided, the Contractor shall develop and make all detail surveys needed for construction such
as slope stakes, batter boards, stakes for pipe locations and other working points, lines and
elevations. The Contractor shall employ only Registered Land Surveyors or Registered
Professional Engineers to perfonn all detail surveys.
The Contractor will diligently preserve and maintain the position of all stakes,
reference points and bench mark.s after they are set and, in case of willful or careless
destruction, he shall be charged with the resulting expense and shall be responsible for any
mistakes that may be caused by their unnecessary loss or disturbance.
GC..12.
MATERIALS AND APPLIANCES:
Unless otherwise stipulated, the Contractor shall provide and pay for all
materials, labor, water, tools, equipment, light, power, transportation and other facilities
necessary for the execution and completion of the work. Unless otherwise specified, all
materials incorporated in the permanent work shall be new and both workmanship and materials
shall be of good quality.
Materials of construction, particularly those upon which the strength and
durability of the structure may depend, shall be subject to inspection and testing to establish
conformance with Specifications and suitability for uses, intended. Satisfactory evidence as to
the kind and quality of materials shall be furnished by the Contractor in the form of certificates
from the manufacturer or reports from the testing laboratories. Such inspections and testing, as
well as the obligations for payment thereof, shall be as specified in the respective sections of
the Specifications.
Approval of the Engineer of any materials, plant, equipment, drawings, or of any
other items executed, or proposed by Contractor, shall be construed only to constitute as
approval of general design. Such approval shall not relieve Contractor from the performance of
the work.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:05
ARC PURCHASING
P.10
GC~13.SCHEDULE OF WORK:
(a) Contractor shall, within five (5) days after receipt of the notice to proceed
with the work, prepare and submit to the Engineer for approval, a practicable and feasible
schedule, showing the order in which he proposes to carry on the work, the date which he will
start salient features and the contemplated dates for completing the same. The schedule shall
be in the form of a progress chart of suitable scale to indicate approximately the percentage of
work scheduled for completion at any time. Contractor shall enter on the chart the actual
progress at the end of each week or at such intervals as directed by thefEngineer and shall
deliver three (3) copies thereof with each periodic request for payment.
(b) Contractor shall furnish suffioient forces. construction plant and
equipment, as may be necessary to insure the progress of the work in accordance with the
approved progress schedule. If, in the opinion of the Engineer, the Contractor falls behind the
. progress schedule, the Contractor shall do whatever is necessary to improve his progress, and
the Engineer may require him to increase the number of shifts, days of work week, length of the
daily working period or the amount of the construction plant, all without additional cost to the
Owner.
(c) Failure of Contractor to comply with the requirements of the Engineer
under this provision will be grounds for determination by the Engineer that the Contractor is not
prosecuting the work with such diligence as will insure completion within the specified time
limits. Upon such determination by the Engineer, the Owner may terminate the Contractor's
right to proceed with the work, in accordance with the requirements of paragraph entitled
"Owner's Right to Terminate Contract" of the General Conditions. The attention of the
Contractor is particularly directed to this provision of the Contract because of the absolute
necessity for completion of the work covered by these specifications within the time agreed
upon.
GC..14.
FIELD OFFICE FACILITIES:
The Contractor shall provide, at a point convenient to the work, suitable office
facilities for housing records, plans and contract documents. A telephone shall be provided at
the Contractors office for expediting the work and be made available for the use of the
Engineer. A complete and up-to~date set of the plans and specifications shall be available at
the field office at aU times that the work is in progress.
GC-15.
LANDS FOR WORK:
The Owner shall provide as indicated on the drawings and not later than the date
when needed by the Contractor lands or rights-of-way upon which the work under the Contract
is to be done, rights-of-way for access to same, and such other lands which are designated on
the drawing for the use of the Contractor. Any delay in the furnishing of these lands by the
Owner shall be deemed proper cause for equitable adjustment in both contract price and time of
completion.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:05
/""'.11
RRC PURCHRSING
The Contractor shall provide at his own expense and without liability to the
Owner any additional land and access thereto that may be required for temporary construction
facilities or for storage of materials.
GC-16.
CONTRACTOR'S PERSONNEL:
(a) Supervision: An experienced superintendent and necessary assistants
competent to supervise the particular types of work involved shall be assigned to the project by
the Contractor and shall be available at all times when work is in progress. Communications
given to the superintendent shall be as binding as if given directly to the Contractor.
(b) Workmen: Only persons skilled in the type of work which they. are to
perform shall be employed. The Contractor shall at all times, maintain discipline and good order
among his employees, and shall not employ on the work any unfit person or persons or anyone
unskilled in the work assigned him. Adequate sanitary facilities shall be provided by the
Contractor.
GC-17.
PROTECTION OF THE PUBLIC AND OF WORK AND PROPERTY:
The Contractor shall provide and maintain all necessary watchmen. barricades,
red lights and warning signs and take all necessary precautions for the protection and safety of
the public. He shall continuously maintain adequate protection of all work from damage, and
shall take all reasonable precautions to protect the Owner's property from injury or loss arising...
in connection with this contract. He shall make good any damage, injury or loss to his work and
to the property of the Owner resulting from lack of reasonable protective precautions, except
such as may be due to errors in the Contract Documents, or caused by agents or employees of
the Owner. He shall adequately protect adjacent private or public property, as provided by law
and the contract documents.
In an emergency affecting the safety of life, of the work, or of adjoining property,
the Contractor is, without special instructions or authorization from the Engineer, hereby
permitted to act at his discretion to prevent such threatened loss or injury. He shall also so act,
without appeal, if so authorized or instructed by the Engineer.
Any compensation claimed by the Contractor on account of emergency work,
shall be determined by agreement or by arbitration.
. GC-18.
EXISTING STRUCTURES AND UTILITIES:
The existence and location of structures and underground utilities indicated on
the plans are not guaranteed and shall be investigated and verified in the field by the C.ontractor
before starting work.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:05
ARC PURCHASING
P.12
All existing utilities, both public and private: including sewer, gas. water, electrical,
and telephone services, etc., shall be protected and their operation shall be maintained
throughout the course of the work. Any temporary shutdown of an existing service shall be
arranged between the Contractor and the responsible agency. The Contractor shall assume full
responsibility and hold the Owner harmless from the result of any damage that may occur as a
result of the Contractor's activities.
GC-19.CHANGEO CQNDITIONS:
The Contractor shall promptly, and before conditions are disturbed, notify the
Engineer in writing of: (1) subsurface or latent physical conditions at the site differing materially
from those indicated in the Contract; (2) unknown physical conditions, at the site, of an unusual
nature, differing materially from those ordinarily encountered and generally recognized as
inherent in work of Contractor provided for in the Contract; or (3) unknown physical conditions at
the site which, for any reason, require a variation in the plans and specifications, or an increase
or decrease in the work necessary to satisfy the Contractors' obligations under the Contract.
The Engineer shall promptly investigate the conditions. and if he finds that such conditions do
so materially differ and cause an increase or decrease in the cost of, or the time required for,
performance of the Contract, an equitable adjustment shall be made and the Contract modified
in writing accordingly. Any claim of the Contractor for adjustment hereunder shall not be
allowed unless he has given notice as above required; provided that the Engineer may, if he
determines the facts so justify, consider and adjust any such claims asserted before the date of
final settlement to be made, the dispute shall be determined as provided in Section GC-37
hereof.
If the Contractor, in the course of the work, finds any discrepancy between the
plans and the physical conditions of the locality, or any error or omissions in plans or in the
layout as given by survey points and instructions, he shall immediately inform the Engineer, and
the Engineer shall promptly verify the same. Any work done after such discovery, until
authorized, will be done at the Contractor's risk.
GC-20.INSPECTION OF WORK:
The Owner shall provide sufficient competent engineering personnel for the
inspection of the work.
The Engineer and his representatives shall at all times have access to the work
whenever it is in preparation or progress, and the Contractor shall provide proper facilities for
such access, and for inspection.
. Inspectors shall have the power to stop work on account of a workman's
Incompetency, drunkenness, or willful negligence or disregard of orders. An inspector may stop
the .work entirely if there is not a sufficient quantity of suitable and approved materials or
equipment on
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:06
r..1.-.l
ARC PUkCHH~lNl.:i
the ground to carry it out properly or for any good and sufficient cause. Inspectors may not
accept on behalf of the Owner any material or workmanship which does not conform fully to the
requirements of the contract and they shall give no orders or directions under any possible
circumstances not in accordance with the Specifications. The Contractor shall furnish the
. inspector with all required assistance to facilitate thorough inspection or the culling over or
removal of defective materials or for the thorough examination into any of the work performed or
for any other purpose requiring disoharge of their duties for which service no additional
allowance shall be made. The inspector shall, at all times, have full permission to take samples
of the materials that mayor might be used in the work.
. Any inspection provided by the Engineers is for the purpose of determining
compliance with provisions of the contract specifications and is in no way a guarantee of the
methods or appliances used by the Contractor. or for the safety of the job.
If the specifications, the Engineer's in'structions, laws, ordinances, or any public
authority require any work to be specially tested or approved, the Contractor shall give the
Engineer timely notice of its readiness for inspection, and if the inspection is by an authority
other than the Engineer, of the date fixed for such inspection. Inspections by the Engineer shall
be made promptly, and where practicable at the source of the supply. If any work should be
covered up without approval or consent of the Engineer, it must, if required by the Engineer, be
uncovered for examination and properly restored at the Contractor's expense.
Re-examination of any work may be ordered by the Engineer, and, if.so ordered,
the work must be uncovered by the Contractor. If such work is found to be in accordance with
the Contract Documents, the Owner shall pay the cost of reexamination and replacement. If
suoh work is not in accordance with the Contract Documents, the Contractor shall pay such
cost.
GC-21.
CORRECTION OF WORK BEFORE FINAL PAYMENT:
The Contractor shall promptly remove from the premises all materials
condemned by the Engineer as failing to meet contract requirements, whether incorporated in
the work or not, and the Contractor shall promptly replace and re-execute his own work in
accordance with the contract and without expense to tha Owner and shall bear the expense of
making good all work of other Contractors destroyad or damaged by such removal or
replacement.
If the Contractor does not remove such condemned work and materials within ten
(10) days after written notice, the Owner may remove them and may store the materials at the
expense of the Contractor. If the Contractor does not pay the expense of such removal within
ten (10) day's time thereafter, the Owner may, upon ten (10) days written notice, sell such
materials at auction or at private sale, and shall pay to the Contractor the net proceeds thereof
after deducting all the costs and expenses that should have been borne by the Contractor. .
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:06
ARC PURCHRSING
r'.14
GC-22.0EDUCTIONS FOR UNCORRECTED WORK;
If the Engineer deems it inexpedient to correct work that has been damaged or
that was not done in accordance with the contract, an equitable deduction from the contract
price shall be made therefor.
GC-23.
CHANGES IN THE: WORK:
The Owner may make changes in the plans and specifications of the contract
within the general scope at any time by written order and without notice to the sureties. If such
changes add to or deduct from the extent of the work. the contract shall be adjusted
accordingly. All such work shall be executed under the conditions of the original contract except
that any claim for extension of time caused thereby shall be adjusted at the time of ordering
such change.
In giving instructions, the Engineer shall have authority to make minor changes in
the work not involving extra cost, and not inconsistent with the purposes of the work, but
otherwise, except in an emergency endangering life or property, no extra work or change shall
be made unless in pursuance of a written order by the Engineer, and no claim for an addition to
the contract sum shall be valid unless the additional work was so ordered.
The Contractor shall proceed with the work as changed and the value of any
change which cannot be adjusted by an Increase or a decrease in contract unit items shall be
determined in one of the following ways:
(a) By estimate and acceptance in a lump sum.
(b) The actual cost, by keeping a correct account. Including all vouchers for:
(1 )
(2)
(3)
The actual payroll costs of all workmen, including foreman.
The Contractor's net cost for materials entering permanently into
the work.
The ownership or rental cost of construction plant and equipment
during period of actual use on the extra work.
(4) The charges for extra power and consumable supplies.
. To the cost of items enumerated under (b) above shall be added a fixed fee for
combined overhead and profit, not to exceed twenty percent (20%) of the enumerated items.
!he allo~ance for combined overhead and profit so calculated shall be the only allowance
Included In the total cost to the Owner. Among the items considered overhead are cost for
insurance, social security taxes, bond, superintendence, time keeping, clerical work, watchman,
use of small tools, general office expense and miscellaneous.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:06
r. J....}
RRC j-U<CHH::i 1 NLi
If none of the above methods are agreed upon, the Contractor, providing he
receives an order in writing, shall proceed with the work. In such cases and also under case 2
he shall keep a record of and present in such form as the Engineer may require, a correct
amount of net cost of labor and materials, together with vouchers. In any case, the Engineer
shall certify to the amount, including a reasonable allowance for overhead and profit to the
Contractor. Pending final determination of value, no payment on account of changes shall be
made on any estimate.
GC-24.
EXTENSION OF TIME:
Extension of time stipulated in the contract for completion of the worK will be
made if and as the Engineer may deem proper, when work under change order as herein before
provided is added to the work under this contract: and when the work of the Contractor is
delayed on account of conditions which could not have been foreseen, or which were beyond
the control of the Contractor, and which were not the result of his fault or negligence. Extension
of time for completion shall also be allowed for any delays in the progress of the work caused by
any act or neglect of the Owner or of his employees or by other Contractors employed by the
Owner, or delay due to an act of Government, or by any delay in the furnishing of plans and
necessary information by the Engineer, or by any other cause which in the opinion of the
Engineer entitles the Contractor to an extension of time. Strikes and other labor disputes shall
be cause for an extension of time.
The Contractor shall notify the Engineer promptly of any occurrence or conditions
which in the Contractor's opinion entitle him to an extension of time, Such notice shall be in
writing and shall be submitted in ample time to permit full investigation and evaluation of the
Contractors claim. The Engineer shall acknowledge receipt of the Contractor's notice within
_five (5) days of its receipt. Failure to provide such notice shall constitute a waiver by the
Contractor of any claim.
GC-25.
CLEAN-UP:
Contractor shall keep the premises free from the accumulation of waste material
and rubbish, and upon completion of the work, prior to final acceptance of the completed project
by the Owner, he shall remove from the premises all rubbish, surplus materials, implements,
tools, etc, and leave his work in a clean condition, satisfactory to the Engineer.
GC.26.GUARANTEE: CORRECTION OF THE WO~:
Contractor shall guarantee all items of work to be free from defects in
workmanship and material for a period of one year after final acceptance by the Owner.
Contractor shall re-execute at his own expense, any work that fails to conform to the
requirements of the Contract Documents, including any defects which appear up to one year
after the date of final acceptance of the completed project. Provisions of this article apply to all
work executed by subcontractors, vendors and direct employees of Contractor.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:06
ARC PURCHR:ilNG
r. J.O
GC.27.
CLAIMS FOR EXTRA COS"(:
If the Contractor claims that any instructions by drawings or other media issued
after the date of the Contract involved extra cost under this Contract, he shall give the Engineer
written notice thereof within seven (7) days after the receipt of such instructions, and in any
event before proceeding to exeoute the work, except in emergencies endangering life or
property, and the procedure shall then be as provided for changes in the work. No such claims
shall be valid unless so made.
GC.28.
SEPARATE CONTRACTS:
The Owner reserves the right to let other contracts in connection with this work,
The Contractor shall afford other Contractors reasonable opportunity for the introduction and
storage of their materials and the execution of their work, and shall properly connect and
coordinate his work with theirs.
If any part of the Contractor's work depends for proper execution or results upon
the work of any other Contractor, the Contractor shall inspect and promptly report to the
Engineer any defects in such work that render it unsuitable for such proper execution and
results. His failure so to inspect and report shall constitute an acceptance of the other
Contractor's work as fit and proper for the reception of his work, except as to defects which may
develop in the other Contractor's work after the execution of his work.
To insure the proper execution of his subsequent work the Contractor shall measure
work already in place and shall at once report to the Engineer any discrepancy between the
executed work and the drawings.
GC-29.
RIGHTS OF VARIOUS INTERESTS:
Whenever work being done by the Owner's forces or by other Contractors is
contiguous to work covered by the Contract, the respective rights of the various interests
involved shall be established by the Engineer, to secure the completion of the various portions
of the work in general harmony.
If, through acts of neglect on the part of the Contractor, any other Contractor or
any subcontractor shall suffer loss or damage on the work, the Contractor shall settle with such
other Contractor or Subcontractor by agreement or arbitration if such other Contractor or
Subcontractor will so settle. If such other Contractor or Subcontractor shall assert any claim
against the Owner on account of any damage alleged to have been sustained, the Owner shall
not.ify the Contractor, who shall indemnify and save harmless, the Owner against any such
claIm.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:06
ARC PURCHASING
1-'.1'(
GC-30.
THE OWNER'S RIGHT TO TERMINATE CONTRACT:
If the Contractor should be adjudged bankrupt. or if he should make a general
assignment for the benefit of his creditors, or if a receiver should be appointed on account of his
insolvency, or if he should persistently or repeatedly refuse or should fail, except in cases for
which extension of time is provided, to supply enough properly skilled workmen or proper
materials, or if he should fail to make prompt payments to Subcontractors or for material or
labor, or persistently disregard laws, ordinances or the instructions of the Engineer or otherwise
be guilty of a substantial violation of any provision of the Contract, then the Owner, upon the
certificate of the Engineer that suffioient cause exists to justify such action may, without
prejudice to any other right or remedy and after giving the Contractor seven (7) days written
notice, terminate the employment of the Contractor and take possession of the premises and of
all materials, tools and appliances thereon and finish the work by whatever method he may
deem expedient. In such case the Contractor shall not be entitled to reoeive any further
. payment until the work is finished. If the unpaid balance of the contract price shall exceed the
expense of finishing the work, including compensation for additional managerial and
administrative services, such exoess shall be paid to the Contractor. If such expense shall
exceed such unpaid balance, the Contractor shall pay the difference to the Owner. The
expense incurred by the Owner as herein provided and the damage incurred through the
Contractor's default, shall be oertified by the Engineer.
GC.31.
CONTRACTOR'S RIGHT TO STOP WORK OR TERMINATE CONTRACT:
If the work should be stopped under an order of any court, or other pUblic
authority, for a periOd of three months, through no act or fault of the Contractor or of anyone
employed by him, or if the Engineer should fail to issue any estimate within ten (10) days after it
is due, or if the Owner should fail to pay the Contractor within fifteen (15) days of its maturity
and presentation any sum 9~rtified by the E.ngineer or awarded by arbitrators, then the
Contractor may. upon seven (7) days' written notice to the Owner and the Engineer, stop work
or terminate this contract and recover from the Owner payment for all work executed, plus any
loss sustained upon any plant or materials plus reasonable profit and damages.
GC-32.
REMOVAkOF EQUIPMENT:
In the case of termination of this Contract before oompletion from any cause
whatever, the Contraotor, if notified to do so by the Owner, shall promptly remove any part or all
of his equipment and supplies from the property of the Owner, failing which the Owner shall
have the right to remove such equipment and supplies at the expense of the Contractor.
GC-33.
ROYALTIES AND PATENTS:
The Contractor shall pay all royalties and license fees. He shall defend all suits
or claims for infringement of any patent rights and shall save the Owner harmless from loss on
account thereof except that the Owner shall be responsible for all such loss when a particular
process or the
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
JUL-16-2008 16:07
ARC PURCHASING
P.18
product of a particular manufacturer or manufacturers is speoified unless the Owner has notified
the Contractor prior to the signing of the Contract that the particular process or product is
patented or is believed to be patented.
GC.34.
LIENS:
Neither the final payment nor any part of the retained percentage shall become
due until the Contractor, if required. shall deliver to the Owner a complete release of all liens
arising out of this Contract, or receipts in full in lieu thereof and, if required in either case, an
affidavit which certifies so far as he has knowledge or information that the releases and receipts
include all the labor and materials for which a lien could be filed; but the Contractor may, if any
Subcontractor refuses to furnish a release or receipt in full, furnish a bond satisfactory to the
Engineer, to indemnify the Owner against any such lien. If any lien remains unsatisfied after all
payments are made, the Contractor shall refund to the Owner all monies that the latter may be
compelled to pay in discharging such a lien, including all costs and a reasonable attorney's fee.
GC-35.
ASSIGNMENT:
Neither party to the Contract shall assign the Contract or sublet it as a whole
without the written consent of the other, nor shall the Contractor assign any monies due him
hereunder, except to a bank or financial institution acceptable to the Owner. In case the
Contractor assigns all or any part of any monies due or to become due under this contract, the
instrument of assignment shall contain a clause substantially to the effect that it is agreed that
the right of the assignee in and to any monies due or to become due to the Contractor shall be
subject to prior liens of all persons, firms and corporations for services rendered or materials
supplied for the performance of the work called for in this Contract.
GC-36.
PAYMENTS WlTHHELD PRIOR TO FINAL ACCEPTANCE OF WORK;
The Owner may withhold or, on account of subsequently discovered evidence,
nullify the whole or part of any certificate to such extent as may be necessary to protect himself
from loss on account of:
(a) Defective work not remedied.
(b) Claims filed or reasonable evidence indicating.probablefiling of claims by
other parties against the Contractor.
(c) Failure of the Contractor to make payments properly to Subcontractors or
for material or labor.
(d) Damage to another Contractor.
JUL-16-2008 16:07
ARC PURCHASING
P.19
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
When the above grounds are removed or the Contractor provides a Surety Bond
satisfactory to the Owner which will protect the Owner in the amount withheld, payment shall be
made for amounts withheld, because of them.
GC-37.
APPEAL:
(a) Generp,l: Both parties of the Contract agree that as conditions precedent
to the filing of an action in any court involving the amount or rate of payment of settlement for
work performed by the Contractor under these contract documents, and as a condition
precedent to the liability of the Owner for any amount other than contained in the estimates
approved by the Engineer, any questions at issue involving the amount or rate of settlement of
liability of the Owner for an amount other than as shown by the estimates approved by the
Engineer, shall be referred to arbitration for decision and award. The arbitrator or board of
arbitration shall have authority only to pass upon questions involving compensation to the
Contractor for work actually performed but not allowed by the Engineer, and Its authority shall
not extend to the interpretation of the plans and specifications or the determination of the
qualities of materials or workmanship furnished, nor shall it have authority to set aside or modify
the terms or requirements of the contract. Notwithstanding any provision of this contract, the
Owner shall have the right at any time to file suit for breach of contract, should any of the terms
and conditions of this contract be breached by the Contractor, and that no provision of this
contract shall be so construed as to prevent the Owner from filing suit for breach of contract at
any time the terms and conditions of this contract are breached by the Contractor.
(b) Selection of Arbitrators: The parties may ag ree on one arbitrator;
otherwise a board of arbitration shall consist of three persons, one to be named in writing by
eaoh party to this contract within five (5) days after notice of arbitration is served by either party
upon the other, and the third member chosen by the first two so named within five (5) days after
notice of selection. In determining the award, the majority of the board shall govern. Certified
copies of the findings and award shall be filed with the Owner and the Contractor.
(c) Comoensation: The arbitrator or board of arbitration shall make such
rules as it shall determine equitable to govern itself in the conduct of the investigation and
determination of the award. Said member or members shall fix the amount of the cost of the
proceedings including a fair and reasonable compensation to the arbitrators, and shall
determine how the total cost shall be borne.
GC-38.
TAXES AND FEI:;S:
The Contractor shall pay all sales taxes and other applicable taxes and fees.
Please acknowledge addendum in your submittal.
END ADDENDUM
TOTAL P.19
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
CONTRACT DOCUMENTS AND SPECIFICATIONS
FOR
DIAMOND LAKES
TENNIS COMPLEX
Augusta, Georgia
AUGUST A, RICHMOND COUNTY COMMISSION
The Honorable Deke S. Copenhaver
Mayor
Betty Beard
Marion F. Williams
Joe Bowles
J. R. Hatney
Andy Cheek
Calvin Holland, Sr.
Jimmy Smith
Don A. Grantham
Jerry Brigham
Bernard E. Harper
Frederick L. Russell - City Administrator
Tom F. Beck, Jr.,CPRP - Director, Augusta Recreation & Parks Department
Cranston Engineering Group, P.C.
Engineers - Planners - Surveyors
Augusta, Georgia
May 20, 2008 2006-0066
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
I Invitation for Bids 1
ill Instructions to Bidders 3
P Proposal 9
BB Bid Bond 2
NA Notice of Award 1
A Agreement 4
PB Performance and Payment Bonds 5
NP Notice to Proceed 1
GC-O Index to General Conditions 1
~
GC General Conditions 23
SC-O Index to Special Conditions 1
SC Special Conditions 8
TS-O Index to Technical Specifications 1
TS Technical Specifications 79
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Invitation To Bid
Sealed bids will be received at this office until 3:00 p.m., Wednesday, July 23,2008:
Bid #08-148 Diamond Lakes Tennis Complex for Recreation & Parks
BIDS will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the
offices of:
Geri A. Sams, Director
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30901
706-821-2422
BID documents may be obtained at the office of Augusta, GA Procurement Department, 530 Greene
Street - Room 605, Augusta, GA 30901. Plans and specifications for this project can be made
available upon request to Augusta Blue Print. The fees for the plans and specifications
which are non-refundable is $150.00.
Documents may also be examined during regular business hours at the Augusta Builders
Exchange, 1262 Merry Street, Augusta, GA 30904; F. W. Dodge Plan Room, 1281 Broad Street,
, Augusta, GA 30901. It is the wish of the Owner that all businesses are given the opportunity to
submit on this project. To facilitate this policy the Owner is providing the opportunity to view plans
online (www.auQustablue.com) at no charge through Augusta Blue Print (706 722-6488) beginning
Thursday, June 12,2008. Bidders are cautioned that submitting a package without Procurement of
a complete set are likely to overlook issues of construction phasing, delivery of goods or services,
or coordination with other work that is material to the successful completion of the project. Bidders
are cautioned that sequestration of documents through any other source is not advisable.
Acquisition of documents from unauthorized sources places that bidder at the risk of receiving
incomplete or inaccurate information upon which to base his qualifications.
A MANDATORY Pre-BID Conference will be held on Tuesday, July 8, 2008 at 10:00 a.m. in
Room 605 of the Procurement Department. All questions must be submitted in writing by
Friday, July 11,2008 by 3:00 p.m. to the office of the Procurement Department by fax at 706-
821-2811 or by mail. No bid will be accepted by fax, all must be received by mail or hand
delivered.
No BID may be withdrawn for a period of 90 days after time has been called on the date of opening.
A 10% Bid bond is required to be submitted in a separate envelope so marked along with the
bidders' qualifications; a 100% performance bond and a 100% payment bond will be required
for award.
Bidders will please note that the number of copies requested; all supporting documents including
financial statements and references and such other attachments that may be required by the bid
invitation are material conditions of the bid. Any package found incomplete or submitted late shall
be ejected by the Procurement Office. Any bidder allegedly contending that he/she has been
improperly disqualified from bidding due to an incomplete bid submission shall have the right to
appeal to the appropriate committee of the Augusta Commission. Please mark BID number on the
outside of the envelope.
GERI A. SAMS, Procurement Director
Publish:
Augusta Chronicle
Metro Courier
June 12, 19, 26, July 3, 2008
June 18, 2008
cc:
T ameka Allen
Tom Beck
Ron Houck
Interim Deputy Administrator
Recreation & Parks Department
Recreation & Parks Department
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION IB
INSTRUCTION TO BIDDERS
IB-Ol
GENERAL:
All proposals must be presented in a sealed envelope, addressed to the Owner. The
proposal must be filed with the Owner on or before the time stated in the invitation for bids. Mailed
proposals will be treated in every respect as though filed in person and will be subject to the same
requirements.
Proposals received subsequent to the time stated will be returned unopened. Prior
to the time stated any proposal may be withdrawn at the discretion of the bidder, but no proposal
may be withdrawn for a period of sixty (60) days after bids have been opened, pending the execution
of contract with the successful bidder.
IB-02
EXAMINATION OF WORK:
Each bidder shall, by careful examination, satisfy himself as to the nature and location
of the work, the conformation of the ground, the character, quality and quantity of the facilities
needed preliminary to and during the prosecution of the work, the general and local conditions, and
all other matters which can in any way affect the work or the cost thereof under the contract. No oral
agreement or conversation with any officer, agent, or employee of the Owner, either before or after
the execution of the contract, shall affect or modify any ofthe terms or obligations therein.
IB-03
ADDENDA AND INTERPRETATIONS:
No interpretation of the meaning of plans, specifications or other prebid documents
will be made to any bidder orally.
Every request for such interpretation should be in writing addressed to The Director
of Augusta Recreation and Parks Department c/o Augusta Procurement Department, 530 Greene
Street, Room 605, Augusta, Georgia 30901 and to be given consideration must be received at least
five days prior to the date fixed for the opening of bids. Any and all such interpretations and any
supplemental instructions will be in the form of written addenda to the specifications which, if
issued, will be sent by certified mail with return receipt requested to all prospective bidders (at the
respective addresses furnished for such purposes), not later than three days prior to the date fixed for
the opening of bids. Failure of any bidder to receive any such addendum or interpretation shall not
relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall
become part of the Contract Documents.
IB-04
PREPARATION OF BIDS:
Bids shall be submitted on the forms provided and must be signed by the bidder or
his authorized representative. Any corrections to entries made on bid forms should be initialed by
the person signing the bid.
IE-I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Bidders must quote on all items appearing on the bid forms, unless specific directions
in the advertisement, on the bid form, or in the special specifications allow for partial bids. Failure
to quote on all items may disqualify the bid. When quotations on all items are not required, bidders
shall insert the words "no bid" where appropriate.
Alternative bids will not be considered unless specifically called for.
Telegraphic or telecopier bids will not be considered. Modifications to bids already
submitted will be allowed if submitted by telegraph or facsimile prior to the time fixed in the
Invitation for Bids. Modifications shall be submitted as such, and shall not reveal the total amount
of either the original or revised bids.
Bids by wholly owned proprietorships or partnerships will be signed by all owners.
Bids of corporations will be signed by an officer of the firm and his signature attested by the
secretary thereof who will affix the corporate seal to the Proposal.
NOTE: A 10% Bid Bond is required in all cases.
IB-05
BASIS OF AWARD:
The bids will be compared on the basis of unit prices, as extended, which will include
and cover the furnishing of all material and the performance of all labor requisite or proper, and
completing of all the work called for under the accompanying contract, and in the manner set forth
and described in the specifications.
Where estimated quantities are included in certain items ofthe proposal, they are for
the purpose of comparing bids. While they are believed to be close approximations, they are not
guaranteed and settlement will be made for such items upon the basis of the work as actually
executed at the unit prices in the proposal as accepted. It is the responsibility of the Contractor to
check all items of construction. In case of error in extension of prices in a proposal, unit bid prices
shall govern.
IB-06
BIDDER'S QUALIFICATIONS:
No proposal will be received from any bidder unless he can present satisfactory
evidence that he is skilled in work of a similar nature to that covered by the contract and has
sufficient assets to meet all obligations to be incurred in carrying out the work. He shall submit with
his proposal, sealed in a separate envelope, a FINANCIAL EXPERIENCE AND EQUIPMENT
STATEMENT, giving reliable information as to working capital available, plant equipment, and his
experience and general qualifications. The Owner may make such investigations as are deemed
necessary to determine the ability of the bidder to perform the work and the bidder shall furnish to
him all such additional information and data for this purpose as may be requested. The Owner
reserves the right to reject any bid if the evidence submitted by the bidder or investigation of him
fails to satisfy the Owner that such bidder is properly qualified to carry out the obligations of the
contract and to complete the work contemplated therein. Part of the evidence required above shall
IB-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
consist of a list ofthe names and addresses of not less than five (5) firms or corporations for which
the bidder has done similar work.
IB-07
PERFORMANCE BOND:
At the time of entering into the contract, the Contractor shall give bond to the Owner
for the use ofthe Owner and all persons doing work or furnishing skill, tools, machinery or materials
under or for the purpose of such contract, conditional for the payment as they become due, of all just
claims for such work, tools, machinery, skill and terms, for saving the Owner harmless from all cost
and charges that may accrue on account ofthe doing of the work specified, and for compliance with
the laws pertaining thereto. Said bond shall be for the amount of the contract satisfactory to the
Owner and authorized by law to do business in the State of Georgia.
Attorneys-in-fact who sign bonds must file with each copy thereof a certified and
effectively dated copy of the power of attorney.
IB-08
REJECTION OF BIDS:
These proposals are asked for in good faith, and awards will be made as soon as
practicable, provided satisfactory bids are received. The right is reserved, however to waive any
informalities in bidding, to reject any and all proposals, or to accept a bid other than the lowest
submitted if such action is deemed to be in the best interest of the Owner.
-,
IB-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION P
PROPOSAL
DATE: ij23/0?
Gentlemen:
In compliance with your invitation for bids, the undersigned hereby proposes to furnish all
labor, equipment and materials, and to perfonn all work for the project referred to herein as:
DIAMOND LAKES
TENNIS COMPLEX
in strict accordance with the Contract Documents and in consideration of the amounts shown on the
bid schedule attached hereto and totaling:
FIve. hLlV\..cLv.e.d +:'-~- ~u"v +\l\ou_SCvr..
\
/1 00 doliars r5t.i~ ,0&.3, ')2- )
,
, and -52-
The undersigned hereby agrees that, upon written acceptance of this bid, he will
within 10 days of receipt of such notice execute a fom1al-contract agreement with the O\:vner, and
that he will provide the bond or guarantees required by the contract documents.
The undersigned bereby agrees that, if awarded the contract, he will commence the
work within Ten (lQ) calendar days after the date of written notice to proceed, and that he will
complete the work within One Hundred Eighty (180) calendar days after the date of such notice.
The undersigned ackn)?wledges receipt of the following addenda:
A-ci&e/V\dvlW'- IVo. \
. Encl~sedis a b4i g).ldlltee, consisting of
m the amount of /Oo;D of- j)i
I cfv
Respectfully submitted,
(JoJ'l(-{D ~ GtRi'13 .BnHt..o-i5 CCl/"\sirv-d\'Ofl, l-LG
FIRM NAME
G::l( (CO)lwte.-r pf{)[1.;5vitd=F5 [VOJtS.3~ 30!rD"1
BUSIl\TESS ADDRESS
BY: CJ...J../ \~ -f./d/iAI
TITLE: \A~e PVe<;lde/v,-,~
P-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
BID SCHEDULE
DIAMOND LAKES
TENNIS COMPLEX
2006~0066
TO ACCOMP ANY THE PROPOSAL OF
BIDDER: ().(Jjn10 .'! Getlnj 13r~W' {O",sfrudh LLL
ADDRESS: 0.2( fonder P f;..a ,5,,~ 4:1 :3
8vtLn 5, &.(0/:5 i tl :]onq
..,
.).
Standard Pavement (611 Graded Aggregate Base and 2" 12.5
lUm Superpave Asphaltic. Concrete)
1,812 _ S.Y. @ .$ 20. ?~ IS.Y.
.$
-:?'" 25(1 '"7)"
-' (; / .
4.
TelIDis Court Paving (4" Graded Aggregate Base and 1.5"
9.5mm Superpave Asphaltic Concrete)
2,873 S.Y. @ $ I g. 0 ~ IS.Y.
24" Standard Concrete Curb & Gutter
1,200 L.F. @ $ /3. ~ y; IL.F.
.$
c( i tJ.., 9 5'{-
:..J -rj .... .~ .
5.
$ IGI17~. eoO
6.
Tennis COUli Surfacing (Including Striping)
2,873 S.Y. @ $ 4. (.., 3 IS.Y.
Concrete Sidewalk - 4" Thick
470 S.Y. @ $
$ I 3 I 30 I. c; '1
7.
~I. 31
IS.Y.
.$
1& 83':;. .7[,
(
8.
10.
24" Concrete Curb and Gutter Removal (Median Cut)
Lump Sum
Asphalt Overlay, 2" 12.5 mm Superpave Asphaltic Concrete
505 S.Y. @ $ 1~,c{O IS.Y.
Asphalt Leveling, Installed Complete
35 TON@ $ 10d. IS
.$ 1."lStf.io<t
,
9.
. C' (I b\.l
.$ (..,1 -;:::> l't.
ITON
$
'3 '5-'5. ,;,)5
'. )
11.
4" Aggregate Surface Course
1,980 S.Y. @.$ la. ,-\-\
IS.Y.
$ Il, ~ql. '0>
$ d /3, :l-Ot{!tf'
ell
Subtotal I
P-2
I
I ITEM NO. DESCRIPTION. QUANTITY. UNIT & UNIT PRICE AMOUNT
I II. WATER MAIN AND APPURTENANCES
1. 10" C900 PVC Water Main; Installed Complete (Including
I Fittings and Restraint) $~~ If/1. cD
565 L.p. @ $ 3].. \po IL.F.
') 6" C900 PVC Water Main, Installed Complete (Including
....
I Fittings and Restraint) ; lP t5 3,. 10 I g. ;)t5
205 L.F.@ $ (7. IL.F. $
I 3. 2" PVC Water Main, Installed Complete (Including Fittings
and Restraint) 60
1,170 L.F. @ $ 'f5~ (t6 IL.F. $ IO,d37
I 4. 1" PVC Water Service wi Valve and Valve Box, Installed
Complete i /51 '-f.b (,
I Lump Sum $
. { -
5. Fire Hydrant w/6" Gate Valve, Installed Complete (Including
I Fittings and Restraint) "2- g if I q c{-. 2.f
1 Each @ $ Lt, 10tf. lEach $
J
6. 10" Gate Valve, Including Valve Box, Installed Complete
I 1 Each @ $ i, ~OO. 3'f lEach $ I; {';JO{i. 3 '{
7. 6" Gate Valve, Including Valve Box, Installed Complete
I 1 Each @ $ 't23. ~ I lEach $ g i;( .~ J
L.- _;. ?
8. 2" Gate Valve, , Including Valve Box, Installed Complete
I 1 Each @ $ l.f- ?:/5. 7.3 lEach $ <f-3 ~~. ., 3
9. Frost Proof Hose Bibb, Installed Complete
I 8 Each @ $ "315. '-1 ( lEach $ :2, S;l /. z.g
10. Tie to Existing Water Main
1 Each @ $ L Lf!~. 65 lEach $ -11-- tfl b. 05
I
Subtotal II $ LPI S1 Ie <f0
--:......;;- .
I III. STORM SE\VER
1. 30" R. C.P.
I 557 Sl.g? l'7 (,. z;;or
L.F.@ $ IL.F. $ ':;i,
2. 24" R.C.P. /,'1)
I 220 L.F.@ $ 3cr. q cf IL.F. $ CZS J '7 'i/b .
3. 18" R.C.P.
I 73 L.F.@ $ 30.13 IL.F. $ ;) I G"1 Ct 4J.'J
I .
I P-3
I
I ITEM NO. DESCRIPTION. QUANTITY. UNIT & UNIT PRICE AM 0 UNT
I 4. 2411 C.P.P.
19 L.F. @ $ lj 3.)/ IL.F. $ 'l;.2-0 . if [7
I 5. 18" c.P.P.
571 L.F. @ $ .JL:; . 'l b IL.F. $ I '-f! 7 () t. 96
(;"'-........
I 6. 12" c.P.P. Ib
426 L.F. @ $ ! %-, IL.F. $ ~/73~,.ib
I 7. Yard Drain
5 Each @ :;; I, I t;Lf, 6z. lEach :;; 5; 77). .io
,
I 8. Grate Trap
4 Each @ $ I QO~ 0~ /Each $ /~65, q~'J.....
I 7 .
0 Junction Box
I ./.
2 Each @ $ ;11 /t;O, 7'; /Each $ 4-3 ;).{ . 5D
I
10. St01111 Manhole lY'oi. dO
I 1 Each @ $ I, qt:f? DO /Each $
II. 30" Flared End Section, R.C.P, ~ C3
I 1 Each @ $ q5)... - lEach $ q oS ~ 'd-1
12. Single Wing Trap (0,).
I 3 Each @ $ ;) d-g",. lEach $ L:, I g 5 q . 0;;'1:.
I
13. Single Wing Trap Removal (Median Cut)
I Lump Sum $ (/0/'/,0'1
14. 6" French Drain, Installed Complete, Including Ties To St01111
I Traps
700 L.F.@ $ 11: if IL.F. $ O}JI! 00
J I .
I Subtotal III $ I O<f~ ') '7~., --6
,
IV. MISCELLANEOUS CG
I 1. Soil Erosion and Sedimentation Control, Including
Maintenance and Removal (As Detailed, Including
I Temporary Grassing, Silt Fence, Construction Outlet, Surface
Roughening, Inlet Protection, and Check Dams) . ~ gn't L/-.'l
Lump Sum $ ;)':J) ,
I 2. Silt Fence, Type "C" (Additional Not Shown on Plans, As
Directed in Field)
200 L.F@ $ 2 '\\1. /L.F. $ . (0 C.{1: . (j'D
I ./. cr \
3. Erosion Control Slope Mat l. q~ $ tf I <?1J. --, 0
2,155 S.Y. @ $ IS.Y.
I --.J./-
P-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ITEM NO. DESCRIPTION. QUANTITY. UNIT & UNIT PRICE
4. Stone Dumped Rip Rap, 12", Including Geotextile Fabric
20 S.Y. @ $ (c1. 15 g __ IS.Y.
5. Stone Dumped Rip Rap, 6", Including Geotextile Fabric
15 S. Y. @ $ II. It> D IS. Y.
6.. Permanent Grassing, Bermuda (Est. 9.0 acres)
Lump Sum
7.
"Wheel Stop
1 Each @ $
lEach
r-l, 0':'"
'Of-!.
8.
Handicap Parking (Striping and Signs)
Lump Sum
Access Road Striping, Complete (As Detailed)
Lump Sum
10' P.V.C. Coated Chain Link Fence, Including 4 Standard 3'
Gates (Installed Complete)
990 L.F. @ $ 3lf. l{.-( /L.F.
9.
10.
11.
Double 6' Service Gate, Full Height, Installed Complete (12'
Total Width)
1 Each@ $
12.
! /1S'd-' ~"'D /Each
I
6' Vinyl Coated Polyester Windscreens (Installed Complete)
605 L.F. @ $ 5. 33 IL.F.
13.
42' TelIDis Net, Installed Complete (Including Net Posts)
4 Each @ $ <f3c. I ( lEach
14. Red Cedar - Juniperus Virginiana (3" Caliper)
33 Each @ $ 2. ?/g. If 9 lEach
15. Southern Magnolia - Magnolia, Granifolia (3" Caliper)
18 Each @ $ ~ 55. "3? lEach
16.
Crape MYIile - Lagerstroemia (3" Caliper)
34 Each @ $ ( '3 '-i. '-f f
/Each
17.
Weeping Lovegrass - Eragrostis Curvula
2,000 S.Y. @ $ ../1
IS.Y.
18.
6" Concrete Header Curb (Flush)
85 L.F. @ $ II JL,
IL.F.
19. Removable Bollards, Installed Complete
3 Each @ $ :2/7. 7 g lEach
20.
411 PVC Sleeve
100 L.F. @ $
(.)". ?--,
o IL.F.
P-5
AMOUNT
$ .'~,c1 { , (p D
$
-:!CL oi)
I IT.
$
'0 50i.J. Ub
$
r.:::7 C D
":-1 () .
$. I,Oll5.S&
I
$
3~).~. ~
QO
$ 61ft OGS'
$ It I '?")..., 0:l.
$ "3 Id-d- tf . lc S-
$
I -, d- O. <.f.x/-
I
$
'7/ 5 +0, /7
$
4-, 6-7 ~. 'i'y
$
u'-/CJ,'!1i
'i ':) l:;? 7. f
..., ..., ,-, Ol.;
5; ,,,..~,
$
7b5. ("C)
$
<g"?;3. 3 'LI
$
?{:>-.7.0D
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ITEM NO. DESCRlPTION. QUANTITY. UNIT & UNIT PRICE
AMOUNT
21.
Offsite Disposal of Unsuitable Material (As Required)
500 C.Y. @ $ 1(, g--::J- IC.Y.
$
_.-' ([0
~ / C;!O~._
22.
"Stop" Sign, 24" x 24"
1 Each @ $
9-//. '7<t
lEach
$
.:17"1. -7'2
23.
Lump Sum Construction (Includes, But Is Not Limited To
The Items Listed)
- Construction Staking
- Traffic Control
- Mobilization, Demobilization
- Bonds
- Insurance
- Shoring, If Required
Lump Sum
$
...,'- ., /i; ~,i.
..L 'O( (o~' ./.:.,.
Subtotal IV
$ 13// 73~, 13 C b
$ 55(f, o~ 3, ~;)-
BASE BID GRAND TOTAL
* Any Other Item Without A Specific Pay Item Shall Be Included In "Lump Sum
Construction".
ADDITIVE ALTERNATES
Alternative shall be equal to the amount to be added to the original Base Bid for the additional
Bid Items which are shown. These items will not be additive to existing Bid Items.
AI. Add Altemate #1 - Provide Standard Pavement (6" Graded Aggregate Base and
2" 12.5 mm Superpave Asphaltic Concrete) and 24" Standard Curb & Gutter and
Associated Appurtenances in place of the 4" Aggregate Surface Course for the
Parking Lot (Item 1-11,1,980 S.Y.).
1. Standard Pavement (6" Graded Aggregate Base and 2"
12.5 mm Superpave Asphaltic Concrete) .
1,980 S.Y. @ $ '7.1. ?-Lf IS.Y.
4.
Concrete Side.wa1k - 4" Thick
232 S.Y. @ $
'I "1 (.,.l.-.
- .
IS.Y.
$ L{- d, 0 55. ?-c
$ II Lf 5- g: QW
(
$ I ,")...u ;>-L/.
) .J . \,
$ ~! ~+n. I "'}-
2.
24 II Standard Concrete Curb and Gutter
850 L.F. @ $ /3. '-I r
IL.F.
3.
Class A Concrete Flumes
4 Each @ $
3'?I.OL
lEach
P-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ITEM NO. DESCRIPTION. QUANTITY. UNIT & UNIT PRICE
5. Parking Lot Stripping, Complete as Detailed
Lump Sum
ADD # 1 TOTAL
. AMOUNT
$ Lj.<tJ-1Sb
$ ~ I, b 01 ,1:J-
A2. Add Altemate #2 - Provide four Tem1is Courts in addition to the four provided in
Base Bid.
1.
Temus Court Paving (4" Graded Aggregate Base and 1.5" 9.5
mm Superpave Asphaltic Concrete)
2,873 . S.Y. @ $ I ~,Cj g IS.Y. $
2.
Tennis Court Surfacing (Including Stripping)
2,873 S.Y. @ $ 4. ~ 3 IS.Y.
10' P.V.c. Coated Chain Link Fence, Including 1 Standard 31
Gate (Installed Complete) .
690 . L.F. @ $ 3 i. 4- f IL.F.
3.
4.
6' Vinyl Coated Polyester Windscreens (Installed Complete)
605 L.F. @ $ 5. ?> -; IL.F.
42' Tennis Net, Installed Complete (Including Net Posts)
4 Each @ $ 4.:,D. I ( /Each
5.
Concrete Sidewalk -4" Thick
85 S.Y. @ $
6.
Ilf . 5b-
IS.Y.
-'1 I ./? /)7. ;;;y
5, '::? ~ r
'-----
$ . 3 'J ( Q('1
( ) .:>0 .
I
$
;(3) '7'-b. .9D
$
"';J 'J.. c.f. C c:r
:::> )
$
I . 1 ).. D, 44:
)
$
I ....., ~LL //0
r,)-'T.
ADD #2 TOTAL $ q7 /7 ~3., 7~:
, C C;
A3. Add Alternate #3 - Provide Sergeant Juniper in Place of Weeping Lovegrass
(Item III - 17,2,000 S.Y.).
1.
Sergeant Juniper - Juniperus Chinensis (3 Gallon),
Including Pine Straw
2,000 Each @ $ I ~.13 lEach
ADD #3 TOTAL
$
$
""") -, ',)'D c D
:JP") i7\ i;> .
~, {';
':l ') :;;L bO. \. "
,J -'7
A4. Add Alternate #4 - Provide Sanitary Sewer Facilities as Shown on Plans.
1.
8" Sanitary Sewer, P.Y.C. (Including Type n, No. 57 Stone,
Bedding Material)
1,462 L.F. @
/i~ 5'1
L-.'-" .
IL.F.
$
2.
8" Sanitary Sewer, D.I.P. (Including Type II, No. 57 StOlle,
Bedding Matel1al)
175 L.F. @ $ .5)., C'\"" IL.F.
P-7
$ 30 I 0 ).. 5 zr
I
$ Q {I'.' S7J
r. () ,
I
DESCRIPTION, QUANTITY. UNIT & UNIT PRICE
Sanitary Sewer Manhole, Installed Complete
7 Each @ $ 'J qt);. q fj' lEach
6" Sanitary Se"wer Service, Installed Complete with Cleanout
Lump Sum
Tie to Existing Sanitary Sewer Manhole
1 . Each @. $ I; '- 3, q. (.:. 0 lEach
ADD # 4 TOTAL
r
P-8
AMOUNT
$ 13 30 d, ~
"
$
.- . . {)-:2
61 l.f 3/ , 1::;
$
~ C; "
12;:)7.(;,,0
I
$
S-a J'I.'7 iJ..,
7 ....T . I
/
,
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ADDITIONAL ITEMS OF CONSTRUCTION TO BE PERFORMED IF SO REQUIRED BY
THE ENGINEER:
STATE UNIT PRICES:
1.
Crushed Stone (For subgrade replacement in place)
.-
$ )/;j
;)0
I~
~?.
6D
} ?5
I~
~t;
~1)
3D
IC.Y.
IS.Y.
IC.Y.
IC.Y.
ISack Cement
IC.Y.
IC.Y.
IC.Y.
IC.Y.
ITon
NOTE: FAILURE TO QUOTE RE.4..S0NABLE PRlCES FOR ADDITIONAL ITEMS
MA Y CAUSE THE BID TO BE REJECTED.
2.
Sand-Cemen~ bag Riprap . , .- . . . . . . . . . . . . . . . . . . . . .. $
Bank-run Sand (For sub grade replacement in place) ... $
3.
4.
Washed Sand (For subgrade replacement in place) .... $
5.
Soil-Cement (Stabilized base in place) .............. $
6.
7:
8.
Sand Clay (For sub grade replacement in place) ....... $
Undercut Excavation of Unsuitable Material ......... $
Trench Rock Excavation . . . . . . . . . . . . . . . . . . . . .. . .. $
9.
10.
Mass Rock Excavation .......................... $
Overcut and Clean Stone Bedding ................. $
P-9
I ~, 5 A FEe O'
SAFECO Insurance Company
PO Box 34526
Seattle, WA 98124-1526.
FIRST NATIONAL SURETY
BID BOND
Conforms with The American Institute of
Architects, A.I.A. Document No. A.310
KNOW ALL BY THESE PRESENTS, That we, Garnto & Geariq Bros. Constructon. LLC, 621 Ponder Place Drive'
I
I and the FIRST NATIONAL INSURANCE COMPANY OF AMERICA
I
I
I
Evans. Georgia 30809
as Principal, hereinafter called the Principal,
of 2359 Perimeter Pointe, Suite 160, Charlotte, North Carolina 28208
, a corporation duly organized under
the laws of the State of Washington
, a~ Surety, hereinafter calied the Surety, are held and firmly bound unto
Augusta-Richmond County Commission
as Obligee, hereinafter called the Obligee,
in the sum of 10% of Bid Amount - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - -
Dollars ($ 10% of Bid Amount ) , for the payment of which sum well and truly to be made, the said Principal and the said
Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
I
I
I
I
I
I
I
I
I
I
I
WHEREAS, the Principal has submitted a bid for Diamond Lakes Tennis Complex for Recreation & Parks
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee
in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documents with
good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor arid material furnished in
the prosecution thereof, or in the event of the failure of the Principal to enter such Contract and give such bond or bonds, if the
Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such
larger amount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this
obligation shall be null and void, otherwise to remain in full force and effect.
Signed and sealed this
23rd
day of
JuW 2008
Gamto & Gearig Bros. Constructon, LLC, .
621 Ponder Place Drive (Seal)
Principal
(IP
(h~ f!N,kJJ
Witness
· r~~j PAlt~
V
Title
FIRST NATIONAL INSURANCE COMPANY OF
AMERICA
71/!l.t 'v~.
. / I /,('/)/ c7-' r2.(~~~.....r",--~
{/ -"'v
Witness
By h~ L'(j~o,L
Buck Leigh -
Attorney-in-Fact
S-0054/FNEF 12/00
@ A registered trademark of SAFECO Corporation
FRP
I
I
I
POWER
OF ATTORNEY
First National Insurance Company of America
Saieco Plaza
Seattle, WA 98185
No. 13071
I
KNOW ALL BY THESE PRESENTS:
That FIRST NATIONAL INSURANCE COMPANY OF AMERICA, a Washington corporation, does hereby appoint
..""**""."".""".,,,"'U.THOMAS M. ALBUS; BUCK LEIGH; Columbia, South Carolina..........................................
I
I
its true and lawful attomey(s),in-fact, with full authority to execute on behalf of the company fidelity and surety bonds or
undertakings and other documents of a similar character issued by the company in the course of its business, and to bind FIRST
NATIONAL INSURANCE COMPANY OF AMERICA thereby as fully as if such instruments had been duly executed by its regularty
elected officers at its home office.
IN WITNESS WHEREOF, FIRST NATIONAL INSURANCE COMPANY OF AMERICA has executed and attested these presents
I
this 31st
day of
March
2006
I
~. JJfj'4~
STEPHANIE DALEY-WATSON, SECRETARY
~
I
MIKE PETERS, PRESIDENT, SURETY
I
CERTIFICATE
Extract from the By-Laws of FIRST NATIONAL INSURANCE COMPANY OF AMERICA:
"Article V, Section 13. _ FIDELITY AND SURETY BONDS ... the President, any Vice President, the Secretary, and any Assistant
Vice President appointed for that purpose by the officer in charge of surety operations, shall each have authority to appoint
individuals as attorneys-in-fact or under other appropriate titles with authority to execute on behalf of the company fidelity and surety
bonds and other documents of similar character issued by the company in the course of its business... On any instrument making or
evidencing such appointment, the signatures may be affixed by facsimile. On any instrument conferring such authority or on any bond or
undertaking of the company, the seal, or a facsimile thereof, may be impressed or affixed or in any other manner reproduced;
provided, however, that the seal shall not be necessary to the validity of any such instrument or undertaking."
Extract from a Resolution of the Board of Directors of
FIRST NATIONAL INSURANCE COMPANY OF AMERICA adopted July 28.1970.
"On any certificate executed by the Secretary or an assistant secretary of the Company setting out,
(i) The provisions of Article V, Section 13 of the By-Laws, and
(ii) A copy of the power-of-attomey appointment, executed pursuant thereto, and
(iii) Certifying that said power-of-attomey appointment is in full force and effect,
the signature of the certifying officer may be by facsimile, and the seal of the Company may be a facsimile thereof.'
I
I
I
I
1. Stephanie Daley-Watson , Secretary of FIRST NATIONAL INSURANCE COMPANY OF AMERICA, do hereby certify that the
foregoing extracts of the By-Laws and of a Resolution of the Board of Directors of this corporation, and of a Power of Attomey
issued pursuant thereto, are true and correct, and that both the By-Laws, the Resolution and the Power of Attorney are still in full force
and effect.
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the facsimile seal of said corporation
I
this
2 J~-r;:,
day of ~if
b()f3
S-1049/DF 4/05
~ JJfj))lJU!-/
STEPHANIE DALEY-WATSON, SECRETARY
I
I
Safeco@ and the Safeco logo are registered trademarks of Safeco Corporation.
WEB PDF
I
I
SECTION NA
NOTICE OF AWARD
TO: GARNTO & GEARIG BROTHERS CONSTRUCTION, LLC
PROJECT: DIAMOND LAKES TENNIS COMPLEX
The OWNER has considered the BID submitted by you for the above described 'WORK in
response to its Advertisement for Bids and Information for Bidders.
You are hereby notified that your BID has been accepted, and will include the Base Bid and
Add Alternates 1 & 2, for items in the amount of$713.514.36 .
You are required by the Proposal to execute the Agreement and furnish the required
Contractor's Performance and Payment Bonds within ten (10) calendar days from the date of this
Notice to you.
If you fail to execute said Agreement and to furnish said bonds within ten (10) days from the
date ofthis Notice, said OWNER will be entitled to consider all rights arising out of the OWNER'S
acceptance of your BID as abandoned and as a forfeiture of your Bid Bond. The O\VNER will be
entitled to such other rights as may be granted by law.
.
You are required to return an acknowledged copy of this NOTICE OF AWARD to the
OWNER.
Dated this 4th day of September
,20 08.
CRANSTON ENGINEERmG GROUP, P.c.
BY:OC- V ~~4!'-
TITLE: ?;eCJfe, /JtINII~e~
*** ACCEPTANCE OF NOTICE ***
Receipt of the above NOTICE OF AWARD is hereby
acknowledged by k~,(./J~ ~ ~)../;b{.....-
this the t day of ~20 oS-.
BY: c:J~ J;~ . .
TITLE: /J/C eJ (Jr (.s /dr-1 j
NA-1
I
I
/~_.-.:~:l',".--';........, 4
~_r::~:;;W:-..:.:..ar.~' ~
_~ -.....'---0"..:1.. \.
. I , ,\
I ,~'
Frederick L Russell, Administrator
Office OfTbe Administrator
I
Tameka Allen, Interim Dc::pul)' Admini::trator
Robert Leverett, Interim Deputy Administrator
Room SOl - Municipal 8uilding
530 Greene Street - AUGUSfA, GA. 30'01
(706) S21.2400. FAX (706) 821.2819
www..augus~gi!..gOY
I
I
I
August 19, 2008
I
I
Mr. Tom Beck
Recreation & Parks Director
2027 Lumpkin Road
Augusta, GA 30906
I
Dear Tom:
I
The Augusta-Richmond County Commission, at their regular meeting held on Tuesday August 19. 2008.
approved a contract for con$~ruction of an eight (8) court tennis complex at Diamond Lakes Park to Garnto &
Gearig Brothers Construction, LLC in the amount of $713.514.36. (Approved by Public Services Committee August
ll, 2008)
I
If you have any questions, please contact me.
I
I
I
cc:
Ms. Donna Williams
Ms. Geri Sams
I
08-19-Q8: #9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION A
AGREEMENT
THIS AGREEMENT, made on the of ,~, by and
between AUGUSTA. GEORGIA BY AND THROUGH THE AUGUSTA-RICHMOND
COUNTY COMMISSION, party of the first part, hereinafter called the OWNER, and GARNTO
& GEARIG BROTHERS CONSTRUCTION, LLC, party of the second part, hereinafter called the
CONTRACTOR.
,
WITNESSETH, that the Contractor and the Owner, for the considerations hereinafter
named, agree as follows:
ARTICLE I - SCOPE OF THE WORK
The Contractor hereby agrees to furnish all of the materials and all of the equipment
and labor necessary, and to perform all of the work shown on the plans described in the specifications
for the project entitled:
DIAMOND LAKES TENNIS COMPLEX
and in accordance with the requirements and provisions ofthe Contract Documents as defined in the
General and Special Conditions hereto attached which are hereby made a part of this agreement.
ARTICLE II - TIME OF COMPLETION -- LIOUIDATED DAMAGES
The work to be performed under this Contract shall be commenced within Ten (10)
calendar days after the date of written notice by the Owner to the Contractor to proceed. The work
shall be completed within One-Hundred Eighty (180) calendar days after the date of such notice and
with such extensions of time as are provided for in the General Conditions.
It is hereby understood and mutually agreed, by and between the Contractor and the
Owner, that the date of beginning, rate of progress and the time for completion ofthe work to be done
hereunder are ESSENTIAL CONDITIONS of this Contract. Contractor agrees that said work shall
be prosecuted regularly, diligently, and uninterruptedly at such rate of progress as will insure full
completion thereof within the time specified. It is expressly understood and agreed by and between
the Contractor and the Owner, that the time for the completion of the work described herein is a
reasonable time for the completion of the same, taking into consideration the average climatic range
and construction conditions prevailing in this locality.
IF THE CONTRACTOR SHALL NEGLECT, FAIL OR REFUSE TO COMPLETE
THE WORK WITHIN THE TIME HEREIN SPECIFIED, then the Contractor does hereby agree, as
a part of the consideration for the awarding of this contract, to pay to the Owner the sum of Three
Hundred Dollars ($300.00), not as a penalty, but as liquidated damages for such breach of contract
A-I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
as hereinafter set forth, for each and every calendar day that the Contractor shall be in default after
the time stipulated in the contract for completing the work.
The said amount is fixed and agreed upon by and between the Contractor and the
Owner because of the impracticability and extreme difficulty of fixing and ascertaining the actual
damages the Owner would, in such event, sustain, and said amounts shall be retained from time to
time by the Owner from current periodical estimates.
It is further agreed that time is ofthe essence of each and every portion ofthis contract
and the specifications wherein a definite portion and certain length of time is fixed for the
performance of any act whatsoever; and where under the contract an additional time is allowed for
the completion of any work, the new time limit fixed by extension shall be the essence of the
Contract.
ARTICLE III - PAYMENT
A. THECONTRACTSUM
The Owner shall pay to the Contractor for the performance of the Contract the amount as
stated in the Proposal and Schedule of Items. No variations shall be made in the amount
except as set forth in the specifications attached hereto.
B. PROGRESS PAYMENTS
On not later than the fifth day of every m<;:mth, the Contractor shall submit to the Engineer an
estimate covering the percentage of the total amount of the Contract which has been
completed from the start ofthe job up to and including the last working day ofthe preceding
month, together with such supporting evidence as may be required by the Owner and/or the
Engineer. The estimate shall include only quantities in place and at the unit prices set forth
in the bid schedule.
Within ten (10) days of receiving each Application for Payment, the Engineer shall either
indicate in writing a recommendation of payment and present the application to the Owner,
or return the Application to the Contractor indicating in writing necessary corrections. In the
latter case, the Contractor shall make the corrections and resubmit the application.
On the vendor run following approval of the invoice for payment, the Owner shall after
deducting previous payments made, pay to the Contractor 90 percent of the amount of the
estimate on units accepted in place. The 10 percent retained percentage may be held by the
Owner until the final completion and acceptance of all work under the contract.
ARTICLE IV - ACCEPTANCE AND FINAL PAYMENT
A. Upon receipt of written notice that the work is ready for final inspection and acceptance, the
Engineer shall within 10 days make such inspection, and when he finds the work acceptable
under the Contract and the Contract fully performed he will promptly issue a final certificate,
A-2
I
I
I
I
I
I
I"
I
I
I
I
I
I
I
I
I
I
I
I
over his own signature, stating that the work required by the Contract has been completed and
is accepted by him under the terms and conditions thereof, and the entire balance found to be
due the Contractor, including the retained percentage, shall be paid to the Contractor by the
Owner within 15 days after the date of said final certificate.
B. Before final payment is due the Contractor shall submit evidence satisfactory to the Engineer
that all payrolls, material bills, and other indebtedness connected with the work have been
paid, except that in case of disputed indebtedness or liens the Contractor may submit in lieu
of evidence of payment a surety bond satisfactory to the Owner guaranteeing payment of all
such disputed amounts when adjudicated in cases where such payment has not already been
guaranteed by surety bond.
C. The making and acceptance of the final payment shall constitute a waiver of all claims by the
Owner other than those arising from unsettled liens, from faulty work appearing within 12
months after final payment, from requirements of the specifications, or from manufacturers'
guarantees. It shall also constitute a waiver of all claims by the Contractor except those
previously made and still unsettled.
D. If after the work has been substantially completed, full completion thereof is materially
delayed through no fault of the Contractor, and the Engineer, so certifies, the Owner shall
upon certificate ofthe Engineer, and without terminating the Contract, make payment ofthe
balance due for that portion of the work fully completed and accepted.
Such payment shall be made under the terms and conditions governing final payment, except
that it shall not constitute a waiver of claims.
..~i~'
A-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
IN WITNESS WHEREOF, the parties hereto have executed this Agreement, the day and year
first written above.
(SEAL)
(SEAL)
ATTEST:
~A-J
~~
:51 )/~
Witn
AUGUSTA, GEORGIA
cf2~p-
As its Mayo .
. oh6, 1116
(0 It
GARNTO & GEARIG BROTHERS
CONSTRUCTION, LLC
By: f?JAjAh__ ~~/U-i
Title: 1//c.. <- fY' -r-c; /de/J'?"
Address:
y:1L) Jvx Jt iY
~, 6~ 3oJ'uJ
A-4
I~ 's A FEe O.
I FIRST NATIONAL SURETY
SAFECO Insurance Company
PO Box 34526
Seattle, WA 98124,1526
Bond No.
6105919
PERFORMANCE BOND
Conforms with The American Institute of Architects
A.I.A. document No. A-311
KNOW ALL BY THESE PRESENTS: that Garnto & Gearig Bros. Construction, LLC, 630 Ponder Place Drive
Evans, Georgia 30809 (Here insert full name and address or legal title of Contractor)
as Principal, hereinafter called Contractor, and, FIRST NATIONAL INSURANCE COMPANY OF AMERICA
(Here insert full name and address or legal title of Surety)
4333 Brooklyn Avenue, N.E., Seattle, Washington 98105
as Surety, hereinafter called Surety, are held and firmly bound unto Augusta/Richmond County Commission, 530 Greene St.
Room 605, Augusta, Georgia 30911 (Here insert full name and address or legal title of Owner)
I
as Obligee, hereinafter called Owner, in the amount of Seven Hundred Thirteen Thousand Five Hundred Fourteen and
36/100 - - - - - - - -- - -- - - - - -- - - -- - - - -- - -- - - - - -- -- -- - - - - -- - - -- - -- -- - Dollars ($ 713,514.36 .).
I
for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly
and severally, firmly by these presents.
WHEREAS,
Contractor has by written agreement dated
September 4
2008 , entered into a contract
with Owner for Diamond lakes Tennis Complex
(Here insert full name, address and description of project)
in accordance with Drawings and Specifications prepared by Cranston Engineering Group, P.C.
(Here insert full name and address or legal title of Architect)
"
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
S.1219/FNEF 10/99
Page 1 of 2
@A registered trademark of SAFECO Corporation
FRP
I
PERFORMANCE BOND
6105919
Low, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said
Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
I
The Surety hereby waives notice of any alteration or
extension of time made by the Owner.
I Whenever Contractor shall be, and declared by Owner to be
in default under the Contract, the Owner having performed
lowner's obligations thereunder, the Surety may promptly remedy
he default, or shall promptly
I) Complete the Contract in accordance with its terms and
londitions, or
2) Obtain a bid or bids for completing the Contract in accordance
rith its terms and conditions, and upon determination by Surety of
.he lowest responsible bidder, or, if the Owner elects, upon
determination by the Owner and the Surety jointly of the lowest
treSponsible bidder, arrange for a contract between such bidder and
wner, and make available as Work progresses (even though there
hould be a default or a succession of defaults under the
I
I
I
ISigned and sealed this
I ~!dj/Y~
5th
day of
(Witness)
I
I
I1A?I~r
(Witness)
I
I
I
IS'1219/FNEF 10/99
Page 2 of 2
contract or contracts of completion arranged under this paragraph)
sufficient funds to pay the cost of completion less the balance of the
contract price; but not exceeding, including other costs and damages
for which the Surety may be liable hereunder, the amount set forth
in the first paragraph hereof. The term "balance of the contract
price," as used in this paragraph, shall mean the total amount
payable by Owner to Contractor under the Contract and any
amendments thereto, less the amount properly paid by Owner to
Contractor.
Any suit under this bond must be instituted before the
expiration of two (2) years from the date on which final payment
under the Contract falls due.
No right of action shall accrue on this bond to or for the use of
any person or corporation other than the Owner named herein or the
heirs, executors, administrators or successors of the Owner.
September
2008
, .
Garnto & Gearig Bros. Construction, LLC, 630
Ponder Place Drive
(Seal)
(Principal)
~~
.JL/~.~
(Title)
FIRST NATIONAL INSURANCE COMPANY OF
AMERICA
(Seal)
(Surety)
(Title)
I~ 5 A FEe O'
I FIRST NATIONAL SURETY
SAFECO Insurance Company
PO Box 34526
Seattle, WA 98124,1526
I LABOR AND MATERIAL PAYMENT BOND
Bond No. 6105919
Conforms with The American Institute of Architects
I A.I.A. Document No. A-311
THIS BOND IS ISSUED SIMULTANEOUSLY WITH PERFORMANCE BOND IN FAVOR OF THE
OWNER CONDITIONED ON THE FULL ANO FAITHFUL PERFORMANCE OF THE CONTRACT
I
KNOW ALL BY THESE PRESENTS: that Garnto & Gearig Bros. Construction, LLC, 630 Ponder Place Drive
Evans, Georgia 30809 (Here insert full name and address or legal title of Contractor)
I
I
as Principal, hereinafter called Principal, and, FIRST NATIONAL INSURANCE COMPANY OF AMERICA
(Here insert full name and address or legal title of Surety)
4333 Brooklyn Avenue, N.E., Seattle, Washington 98105
I
as Surety, hereinafter called Surety, are held and firmly bound unto Augusta/Richmond County Commission, 530 Greene St.
I Room 605, Augusta, Georgia 30911 (Here insert full name and address or legallitle of Owner)
I
I
as Obligee, hereinafter called Owner, for the use and benefit of claimants as hereinbelow defined, in the amount of Seven Hundred
Thirteen Thousand Five Hundred Fourteen and 36/100 - - - - - - - - - - - - - - - - - - - - -. Dollars ($ 713,514.36 ).
I
for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents.
I
WHEREAS,
Principal has by written agreement dated
September 4
2008 , entered into a contract
I with Owner for Diamond lakes Tennis Complex
:\'
(Here insert full name, address and description of project)
I
I
in accordance with Drawings and Specifications prepared by Cranston Engineering Group, P.C.
(Here insert full name and address or legal title of Architect)
I
I
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
I S,1220/FNEF 10/99
Page 1 of 2
@ A registered trademark of SAFECO Corporation
FRP
I
LABOR AND MATERIAL PAYMENT BOND
6105919
low, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Principal shall promptly make payment to all claimants as hereinafter
defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall
Iremain in full force and effect, subject, however, to the following conditions:
I. A claimant is defined as one having a direct contract with the
IPrinciPal or with a Subcontractor of the Principal for labor, material, or
both, used or reasonably required for use in the performance of the
Contract, labor and material being construed to include that part of water,
.:as, power, light, heat, oil, gasoline, telephone service or rental of
.equipment directly applicable to the Contract.
2. The above named Principal and Surety hereby jointly and
IseverallY agree with the Owner that every claimant as herein defined, who
has not been paid in full before the expiration of a period of ninety (90)
days after the date on which the last of such claimant's work or labor was
Idone or performed, or materials were furnished by such claimant, may sue
on this bond for the use of such claimant, prosecute the suit to final
judgment for such sum or sums as may be justly due claimant, and have
execution thereon. The Owner shall not be liable for the payment of any
Icosts or expenses of any such suit.
3. No suit or action shall be commenced hereunder by any claimant:
la) Unless claimant, other than one having a direct contract with the
Principal, shall have given written notice to any two of the following: the
IPrinciPal, the Owner, or the Surety above named, within ninety (90) days
after such claimant did or performed the last of the work or labor, or
furnished the last of the materials for which said claim is made, stating
IWith substantial accuracy the amount claimed and the name of the party to
whom the materials
ISigned
5th
I
(Witness)
day of
I
I
I
/117~~
(Witness)
I
I
I S,1220/FNEF 10/99
Page 2 of 2
were furnished, or for whom the work or labor was done or performed.
Such notice shall be served by mailing the same by registered mail or
certified mail, postage prepaid, in an envelope addressed to the Principal,
Owner or Surety, at any place where an office is regularly maintained for
the transaction of business, or served in any manner in which legal process
may be served in the state in which the aforesaid project is located, save
that such service need not be made by a public officer.
b) After the expiration of one (1) year following the date on which Principal
ceased Work on said Contract, it being understood, however, that if any
limitation embodied in this bond is prohibited by any law controlling the
construction hereof such limitation shall be deemed to be amended so as to
be equal to the minimum period of limitation permitted by such law.
c) Other than in a state court of competent jurisdiction in and for the county
or other political subdivision of the state in which the Project, or any part
thereof, is situated, or in the United States District Court for the district in
which the Project, or any part thereof, is situated, and not elsewhere.
4. The amount of this bond shall be reduced by and to the extent of
any payment or payments made in good faith hereunder, inclusive of the
payment by Surety of mechanics' liens which may be filed of record against
said improvement, whether or not claim for the amount of such lien be
presented under and against this bond.
September
2007 .
Garnto & Gearig Bros. Construction, LLC, 630
Ponder Place Drive
(Seal)
(Principal)
~
I
~,
\
z,~ ,1L4~~:;) ,--~
===u- (Title)
FIRST NATIONAL INSURANCE COMPANY OF
AMERICA
(Seal)
(Surety)
{
i
)
\.
Bad. L'll~b.
. Buck Leigh, Attorne -m-Fact
(Title)
I
Western Surety Company
I
POWER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
I
Know All Men By The~e rre~ent~. That WESTERN SURETY COMPANY; a South Dakota corporation, is a duly organized and existing corporation
having .il~ principal office in the City of Sioux Falls, and State of South Dakota, and that it does by virtue of the signature and seal herein affixed hereby
make, constitute and appoint
I
Thomas M Albus, Buck Leigh, Individually
I
I
of Columbia, SC, its true and lawful Attorney(s}-in-f<act with full power and authority hereby confem:d to sign, seal and execute fOI" and on its behalfhonds,
undertakings and other obligatory instruments of similar nature
I
- In Unlimited Amounts-
and to bind it thereby as fully and to the same extent as if such instruments were signed by a duly authorized officer of the corporation and alllhe acts of said
Attorney, pursuant to the authority hereby given, are hereby ratified and confirmed.
I
This Power of Attomey is made and executed pursuant to and by authority of the By-Law printed on the reverse hereof, duly adopted, as indicated, by
the shareholders of the corporation.
I
In Witness Whereof, WESTERN SURETY COMPANY has caused the.se pre.~ents to be signed by its Senior Vice Pre.~ident and its corporate seat to
be hereto affixed on this 17th day of October, 2006.
I
~~'\~S.IEt~~
i!'".............)'''','.
#~"''''. .".0,
~yo~~OI1"1),\)\\
!...((l i'\ ~i
h}.. ~'t Ay/ll
\.~4i"'~D~~~
.~I.HI''''''''
WESTERN SURETY COMPANY
I
/2L~
Paul . Bruflat, Senior Vice President
I
State of South Dakota
County of Minnehaha
} ss
I
On this 17th day of October, 2006, before me personally came Paul T. Bruflat, to me known, who, being by me duly sworn, did depose and say: that
he residc..~ in the City of Sioux Palls, State of South Dakota; that he is the Senior Vice President of WESTERN SURETY COMPANY described in and
which executed the abOve instmmcnt; that he knows the seal of said corporation; that the seal affixed to the said instl1lment is snch corporate seal; that it was
so affixed pursuant to authority given by the Board of Directors of said corporation and thai. he signed his name thereto pursuant to like authority, and
acknowledges same to be the act and deed of said corporation.
I
My commission expires
I
November 30,2012
+~~~~~~~~~~~~~~~~~~~~~~~~+
~ ~
$ D. KRELL ~
$~NOTAAY PUBLIC~~
~~SOUTH DAl(OTA~~
+"'-"""--"'''''''''''''''''~'''f''~~'''~''''Ir"....,.''1lr.,. ~
~
~'" "hi;,
I
CERTIFICATE
I
I, L. Nelson, Assistant Secretary of WESTERN SURETY COMPANY do hereby certify that the Power of Attorney hereinabove set forth I'S "tl'll .
Ii d Ii I .f h ., 111.
orce, an IJrt ler certl y t at the By-Law of the corporation printed on the revel"se hereof is still in force In testinlony h f 11 I .
. . ~ -./.- L . . . w ereo lave lereunto subSCribed
my name and affixed the seal of the said corporatlon this ~~ day of _ S~~~. ~.k.
~
WESTERN
SURETY
COMPANY
I
I
Form f'4280.09-06,..'
g.
~L4~.
L. Nelson, Assistant Secretary
I.
'.
ACORD~
CERTIFICATE OF LIABILITY INSURANCE
OP ID TB I DATE (MMlDDNYYY)
GARNT-1 09/05/08
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DO[.5 NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
PRODUCER
I
Bagwell Insurance Seryices Inc
P. O. Box 211686
Martinez GA 30907
Phone: 706-860-7703
INSURERS AFFORDING COVERAGE
1
1
Garnto & Gearig Bros. Construe
Patsy Weaver
P. O. Box 2684
Evans GA 30809
Auto Owners
Owners Insurance
NAIC#
18988
32700
INSURED
INSURER A:
INSURER B:
INSURER C: .
INSURER D:
INSURER E:
COVERAGES
I
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN. THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS. EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
~~I:rE fMMiDD~E pg}!fErl~~b'"tJ!.9,N I ..
LTRINSR TYPE OF INSURANCE POLICY NUMBER LIMITS
GENERAL LIABILITY EACH OCCURRENCE $ 1000000
- ~~E~~h (Ea occurence)
A X ~ 3MMERCIAL GENERAL LIABILITY 48296265 07/01/08 07/01/09 $ 300000
- CLAIMS MADE [i] OCCUR MED EXP (Anyone person) $ 10000
PERSONAL & ADV INJURY $ 1000000
-
GENERAL AGGREGATE $ 2000000
-
GEN'L AGGREGATE LIMIT APPLIES PER: PRODUCTS, COMP/OP AGG $ 1000000
I POLICY n jr& n LOC
~TOMOBILE LIABILITY COMBINED SINGLE LIMIT $ 1000000
B ~ ANY AUTO 4729626500 07/01/08 07/01/09 (Ea accident)
ALL OWNED AUTOS BODII,Y INJURY
- (Per r '",son) $
- SCHEDULED AUTOS
B ~ HIRED AUTOS BODILY INJURY
$
B ~ NON,OWNED AUTOS (Per accident)
PROPERTY DAMAGE $
(Per accident)
I ~RAGE LIABILITY AUTO ONLY, EA ACCIDENT I $
ANY AUTO OTHER THAN EAACC 1$
AUTO ONLY: AGG $
EXCESS/UMBRELLA LIABILITY EACH OCCURRENCE $ 5000000
A ~ OCCUR D CLAIMS MADE 4729626502 07/01/08 07/01/09 AGGREGATE $ 5000000
$
~ DEDUCTIBLE $
X RETENTION $10000 $
WORKERS COMPENSATION AND X ITORY LIMITS I IOJ~'
B EMPLOYERS' LIABILITY 48487582 07/01/08 07/01/09 $ 500000
ANY PROPRIETORIPARTNER/EXECUTIVE E.L EACH ACCIDENT
OFFICER/MEMBER EXCLUDED? E.L. DISEASE. EA EMPLOYEE $ 500000
If yes, describe under E.L. DISEASE, POLICY LIMIT $ 500000
SPECIAL PROVISIONS below
OTHER
DESCRIPTION OF OPERATIONS / LOCATIONS / VEHICLES / EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
The company will endeavor to give thirty (30) days notice for all
cancellations with the exception of non-payment of premium where statutory
law prescribes ten (10) days notice. Certificate holder is included as
Additional Insured w~th respects to General Liability coverage.
CERTIFICATE HOLDER
CANCELLATION
1
I
I
I
I
I
I
I
I
I
I
CITYO-6 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION
DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL ~ DAYS WRITTEN
The City of Augusta NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO DO SO SHALL
Geri A Sams, Director IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE INSURER, ITS AGENTS OR
Procurement Department
530 Greene Street, Room 605 REPRESENTATIVES.
Augusta GA 30901 ANo;:;:;pEspTA~
ACORD 25 (2001/08)
@ACORD CORPORATION 1988
I
I
I
I,
1
I
1
I
1
1
I
I
.1
1
I.
1
I
I
I
I
I
I
IMPORTANT
If the certificate holder is an ADDITIONAL INSURED, the policy(ies) must be endorsed. A statement
on this certificate does not confer rights to the certificate holder in lieu of such endorsement(s).
If SUBROGATION IS WAIVED, subject to the terms and conditions of the policy, certain policies may
require an endorsement. A statement on this certificate does not confer rights to the certificate
holder in lieu.of such endorsement(s). .
DISCLAIMER
The Certificate of Insurance on the reverse side of this form does not constitute a contract between
the issuing insurer(s), authorized representative or producer, and the certificate holder, nor does it
affirmatively or negatively amend, extend or alter the coverage afforded by the policies listed thereon.
ACORD 25 (2001/08)
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION NP
NOTICE TO PROCEED
DATE
TO
SUBJECT: NOTICE TO PROCEED
PROJECT: DIAMOND LAKES TENNIS COMPLEX
Gentlemen:
You are hereby notified to commence work in accordance with the Agreement, within
Ten (10) calendar days following the date first written above, and you are to complete the work within
One-Hundred Eighty (180) consecutive calendar days after the date of this notice. The date set for
completion of all work is therefore
AUGUSTA-RICHMOND COUNTY COMMISSION
BY:
TITLE:
*** ACCEPTANCE OF NOTICE ***
Receipt of the above NOTICE OF AWARD is hereby
acknowledged by
this the day of ,20_.
TITLE:
1\Tp -1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Section
GC-O 1.
GC-02.
GC-03.
GC-04.
GC-05.
GC-06.
GC-07.
GC-08.
GC-09.
GC-1 O.
GC-11.
GC-12.
GC-13 .
GC-14.
GC-15.
GC-16.
GC-1 7.
GC-18.
GC-19.
GC-20.
GC-21.
GC-22.
GC-23.
GC-24.
GC-25.
GC-26.
GC-27.
GC-28.
GC-29.
GC-30.
GC- 31.
GC-32.
GC-33.
GC-34.
GC-35.
GC-36.
GC-37.
GC-38.
GC-39.
GC-40.
GC-41.
GC-42.
GC-43.
GC-44.
GC-45.
GC-46.
GC-47.
GC-48.
GC-49.
GC-50.
SECTION GC-O
INDEX TO ARTICLES OF GENERAL CONDITIONS
Definitions
Additional Instructions and Detail Drawings
Schedules, Reports and Records
Drawings and Specifications
Shop Drawings
Materials, Services and Facilities
Inspection and Testing
Substitutions
Patents
Surveys, Permits and Regulations
Protection of Work, Property and Persons
Supervision by Contractor
Changes in the Work
Changes in Contract Price
Time for Completion and Liquidated Damages
Correction of Work
Subsurface Conditions
Suspension of Work, Termination and Delay
Payments to Contractor
Acceptance of Final Payment as Release
Insurance
Contract Security
Assignments
Indemnification
Separate Contracts
Subcontracting
Engineer's Authority
Land and Rights-of-Way
Guarantee
Taxes
Work Adjacent to Railway or Other Property
Order and Discipline
Warning Devices and Signs
Special Restrictions
As-Built Drawings
Contractor Not to Hire Employees of the Owner
Drawings
Field Office Facilities
Rights-of-Way
Estimate of Quantities
Existing Structures and Utilities
Contractor's Breakdown of Lump Sum Payment Items
Prior Use By
Cleaning Up
Maintenance of Traffic
Maintenance of Access
Erosion Control and Restoration of Property
Bypassing Sewage
Safety and Health Regulations
Pre-Construction Conference
GC-O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION GC
GENERAL CONDITIONS
GC-Ol.
DEFINITIONS:
Wherever used in the Contract Documents, the following terms shall have the
meanings indicated which shall be applicable to both the singular and plural thereof.
1. ADDENDA: Written or graphic instruments issued prior to the execution of the
Agreement which modify or interpret the Contract Documents, Drawings and
Specifications, by addition, deletion, clarifications or corrections.
2. BID: The offer or proposal of the Bidder submitted on the prescribed form setting
forth the prices for the work to be performed.
3. BIDDER: Any person, firm or corporation submitting a bid for the work.
4. BONDS: Bid, Performance and Payment Bonds and other instruments of security
furnished by the Contractor and his Surety in accordance with the Contract
Documents.
5. CHANGE ORDER: A written order to the Contractor authorizing an addition,
deletion or revision in the work within the general scope of the Contract Documents
or authorizing an adjustment in the contract price or contract time.
6. CONTRACT DOCUMENTS: The contract including Advertisement for Bids,
Information for Bidders, Proposal, Bid Bond, Notice of award, Agreement,
Performance Bond, Payment Bond, Notice to Proceed, Change Order, General
Conditions, Supplemental General Conditions, Special Conditions, Technical
Specifications, Drawings and Addenda.
7. CONTRACT PRICE: The total monies payable to the Contractor under the terms and
conditions of the Contract Documents.
8. CONTRACT TIME: The number of calendar days stated in the Contract Documents
for the completion of the work.
9. LIFE OF THE CONTRACT: The total duration of the contract from Notice to
Proceed to completion of all the work.
10. CONTRACTOR: The person, firm or corporation with whom the Owner has
executed the Agreement.
11. DRAWINGS: The part of the Contract Documents which show the characteristics
and scope ofthe work to be performed and which have been prepared or approved by
the Engineer.
GC-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
20.
21.
22.
23.
24.
12.
ENGINEER: The person, firm or corporation named as such in the Contract
Documents.
13.
FIELD ORDER: A written order effecting a change in the work not involving an
adjustment in the contract price or an extension of the contract time issued by the
Engineer to the Contractor during construction.
14.
NOTICE OF AWARD: The written notice of the acceptance of the Bid from the
Owner to the successful Bidder.
15.
NOTICE TO PROCEED: Written communication issued by the Owner to the
Contractor authorizing him to proceed with the work and establishing the date of
commencement of the work.
16.
OWNER: A public or quasi-public body or authority, corporation, association,
partnership or individual for whom the work is to be performed.
17.
PROJECT: The undertaking to be performed as provided in the Contract Documents.
18.
RESIDENT PROJECT REPRESENTATIVE: The authorized representative of the
Owner who is assigned to the project site or any part thereof.
19.
SHOP DRAWINGS: All drawings, diagrams, illustrations, brochures, schedules, and
other data which are prepared by the Contractor, a Subcontractor, Manufacturer,
Supplier or Distributor, which illustrate how specific portions of the work shall be
fabricated or installed.
SPECIFICATIONS: A part of the Contract Documents conslstmg of written
descriptions of a technical nature or materials, equipment, construction systems,
standards and workmanship.
SUBCONTRACTOR: An individual, firm or corporation having a direct contract
with the Contractor or any other Subcontractor for the performance of a part of the
work at the site.
SUBSTANTIAL COMPLETION: That date as certified by the Engineer when the
construction of the project or a specified part can be utilized for the purposes for
which it is intended.
SUPPLEMENTAL GENERAL CONDITIONS: Modifications and/or additions to the
General Conditions of a specific nature generally aimed at the specific contract of
which it is a part.
SUPPLIERS: Any person, supplier or organization who supplies materials or
equipment for the work, including that fabricated to a special design, but who does not
perform labor at the site.
GC-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
25.
26.
GC-02.
2.
GC-03.
2.
WORK: All labor necessary to produce the construction required by the Contract .
Documents and all materials and equipment incorporated or to be incorporated in the
proj ect.
WRITTEN NOTICE: Any notice to any party of the Agreement relative to any part
of this Agreement in writing and considered delivered and the service thereof
completed, when posted by certified or registered mail to the said party at his last
given address or delivered in person to said party or his authorized representative on
the work.
ADDITIONAL INSTRUCTIONS AND DETAIL DRAWINGS:
1.
The Contractor may be furnished additional instructions and detail drawings, by the
Engineer, as necessary to carry out the work required by the Contract Documents.
The additional drawings and instructions thus supplied will become a part of the
Contract Documents. The Contractor shall carry out the work in accordance with the
additional detail drawings and instructions.
SCHEDULES. REPORTS AND RECORDS:
1.
The Contractor shall submit to the Owner such schedule of quantities and costs,
progress schedules, payrolls, reports, estimates, records and other data as the Owner
may request concerning the work performed or to be performed.
Prior to the first partial payment estimate, the Contractor shall submit schedules
showing the order in which he proposes to carry on the work, including dates at which
he will start the various parts of the work, estimated date of completion of each part
and as applicable:
2.1 the dates at which special detail drawings will be required; and
2.2 respective dates for submission of shop drawings, the beginning of
manufacture, the testing and the installation of materials, supplies and
equipment.
3.
The Contractor shall also submit a schedule of payments that he anticipates he will
earn during the course of the work.
GC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-04.
GC-05.
DRAWINGS AND SPECIFICATIONS:
1.
The intent of the drawings and specifications is that the Contractor shall furnish all
labor, materials, tools, equipment and transportation necessary for the proper
execution of the work in accordance with the Contract Documents and all incidental
work necessary to complete the project in an acceptable manner, ready for us,
occupancy or operation by the Owner.
2.
In case of conflict between the drawings and specifications, the specifications shall
govern. Figure dimensions on drawings shall govern over general drawings.
3.
Any discrepancies found between the drawings and specifications and site conditions
or any inconsistencies or ambiguities in the drawings or specifications shall be
immediately reported to the Engineer, in writing, who shall promptly correct such,
inconsistencies or ambiguities in writing. Work done by the Contractor after his
discovery of such discrepancies, inconsistencies or ambiguities shall be done at the
Contractor's risk.
4.
All work that may be called for in the specifications and not shown on the drawings,
or shown and not called for in the specifications, shall be executed and furnished by
the Contractor as if described in both these ways and should any work or material be
required which is not detailed in the specifications or drawings, either directly or
indirectly, but which is nevertheless necessary for the proper carrying out of the intent
thereof, the Contractor is to understand the same to be implied and required and shall
perform all such work and furnish any such material as fully as if they were
particularly delineated or described.
5.
It is understood and agreed that the Contractor, by careful examination, has satisfied
himself as to the nature and location ofthe work, the conformation ofthe ground, the
character, quality and quantity of the materials to be encountered, the character of
equipment and facilities needed preliminary to and during the prosecution ofthe work, .
the general and local conditions and all other matters which can in any way affect the
work under this contract. No verbal agreement or conversation with any officer, agent
or employee of the Owner, either before or after the execution of this contract, shall
affect or modify any of the terms or obligations herein contained.
SHOP DRAWINGS:
1.
The Contractor shall provide shop drawings as may be necessary for the prosecution
of the work as required by the Contract Documents. The Engineer shall promptly
review all shop drawings. The Engineer's approval of any shop drawings shall not
release the Contractor from responsibility for deviations from the Contract
Documents. The approval of any shop drawing which substantially deviates from the
requirement of the Contract Documents shall be evidenced by a Change Order.
GC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-06.
GC-07.
2.
When submitted for the Engineer's review, shop drawings shall bear the Contractor's
certification that he has reviewed, checked and approved the shop drawings and that
they are in conformance with the requirements of the Contract Documents.
3.
Portions of the work that require shop drawing or sample submission shall not begin
until the shop drawing or submission has been approved by the Engineer. A copy of
each approved shop drawing and each approved sample shall be kept in good order
by the Contractor at the site and shall be available to the Engineer.
. MATERIALS. SERVICES AND FACILITIES:
1.
It is understood. that, except as otherwise specifically stated in the Contract
Documents, the Contractor shall provide and pay for all materials, labor, tools,
equipment, water, light, power, transportation, supervision, temporary construction
of any nature and all other services and facilities of any nature whatsoever necessary
to execute, complete and deliver the work within the specified time.
2.
Materials and equipment shall be so stored as to insure the preservation of their
quality and fitness for the work. Stored materials and equipment to be incorporated
in the work shall be located so as to facilitate prompt inspection.
3.
Manufactured articles, materials and equipment shall be applied, installed, connected,
erected, used, cleaned and conditioned as directed by the manufacturer.
4.
Materials, supplies or equipment shall be in accordance with samples submitted by the
Contractor and approved by the Engineer.
5.
Materials, supplies or equipment to be incorporated into the work and purchased by
the Contractor of the Subcontractor will be subject to a chattel mortgage or under a
conditional sale contract or other agreement by which an interest is retained by the
seller.
INSPECTION AND TESTING:
1.
All materials and equipment used in the construction of the project shall be subject to
adequate inspection and testing in accordance with generally accepted standards.
2.
The Contractor shall provide, at his expense, the necessary testing and inspection
services required by the Contract Documents, unless otherwise provided.
3.
The Owner shall provide all other inspection and testing services required by the
Contract Documents.
4.
If the Contract Documents, laws, ordinances, rules, regulations or orders of any public
authority having jurisdiction require any work to specifically be inspected, tested or
approved by someone other than the Contractor, the Contractor will give the Engineer
GC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-08.
timely notice of readiness. The Contractor will then furnish the Engineer the required
certificates of inspection, testing or approval.
5.
Neither observation by the Engineer nor inspections, tests or approvals by persons
other than the Contractor shall relieve the Contractor from his obligations to perform
the work in accordance with the requirements of the Contract Documents.
6.
The Engineer and his representatives will at all times have access to the work. In
addition, authorized representatives and agents of any participating Federal or State
Agency shall be permitted to inspect all work, materials, payrolls, records of
personnel, invoices of materials and other relevant data and records. The Contractor
will provide proper facilities for such access and observation ofthe work and also for
any inspection or testing thereof.
7.
If any work is covered contrary to the written request of the Engineer, it must, if
requested by the Engineer, be uncovered for his observation and replaced at the
Contractor's expense.
8.
If any work has been covered which the Engineer has not specifically requested to
observe prior to its being covered or ifthe Engineer considers it necessary or advisable
that covered work be inspected or tested by others, the Contractor at the Engineer's
request, will uncover, expose or otherwise make available for observation, inspection
or testing as the Engineer may require, that portion ofthe work in question, furnishing
all necessary labor, materials, tools and equipment. If it is found that such work is
defective, the Contractor will bear all the expenses of such uncovering, exposure,
observation, inspection and testing and of satisfactory reconstruction. If, however,
such work is not found to be defective, the Contractor will be allowed an increase in
the contract price or an extension ofthe contract time, or both, directly attributable to
such uncovering, exposure, observation, inspection, testing and reconstruction and an
appropriate change order shall be issued.
9.
The Contractor shall give the Engineer 24 hours notice of starting any new work. No
work shall be done or materials used without suitable supervision and inspection by
the Engineer. The Contractor shall furnish the Engineer with necessary samples of
material for testing purposes.
SUBSTITUTIONS:
1.
When a material, article or piece of equipment is identified on the drawings or
specifications by reference to brand name or catalogue number, the performance or
other salient requirements and that other products of equal capacities, quality and
function shall be considered. The Contractor may recommend the substitution of a
material, article or piece of equipment of equal substance and function for those
referred to in the Contract Documents by reference to brand name or catalogue
number and if, in the opinion of the Engineer, such material, article or piece of
equipment is of equal substance and function to that specified, the Engineer may
GC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-09.
GC-IO.
GC-ll.
approve its substitution and use by the Contractor. Any cost differential shall be
deducted from the contract price and the Contract Documents shall be appropriately
modified by change order. The Contractor warrants that if substitutes are approved,
no major changes in the function or general design of the project will result.
Incidental changes or extra component parts required to accommodate the substitute
will be made by the Contractor without a change in the contract price or contract time.
PATENTS:
1.
The Contractor shall pay all applicable royalties and license fees. He shall defend all
suits or claims for infringement of any patent rights and save the Owner harmless from
loss on account thereof except that the Owner shall be responsible for any such loss
when a particular process, design or the product of a manufacturer or manufacturers
is specified, but if the Contractor has reason to believe that the design, process or
product specified is an infringement of a patent, he shall be responsible for such loss
unless he promptly gives such information to the Engineer.
SURVEYS. PERMITS AND REGULATIONS:
1.
The Owner shall furnish all land surveys and establish all base lines for locating the
principal component parts of the work together with a suitable number ofbenchmarks
adjacent to the work as shown in the Contract Documents. From the information
provided by the Owner, unless otherwise specified in the Contract Documents, the
Contractor shall develop and make all detail surveys needed for construction such as
slope stakes, batter boards, stakes for pile locations and other working points, lines,
elevations and cut sheets.
2.
The Contractor shall carefully preserve benchmarks, reference points and stakes and
in case of willful or careless destruction, he shall be charged with the_ resulting
expense and shall be responsible for any mistakes that may be caused by their
unnecessary loss or disturbance.
3.
Permits and licenses of a temporary nature necessary for the prosecution of the work
shall be secured and paid for by the Contractor. Permits, licenses and easements for
permanent structures or permanent changes in existing facilities shall be secured and
paid for by the Owner, unless otherwise specified. The Contractor shall give all
notices and comply with all laws, ordinances, rules and regulations bearing on the
conduct of the work as drawn and specified. If the Contractor observes that the
Contract Documents are at variance therewith, he shall promptly notify the Engineer
in writing and any necessary changes shall be adjusted as provided in Section 13,
Changes in the Work.
PROTECTION OF WORK. PROPERTY AND PERSONS:
1.
The Contractor will be responsible for initiating, maintaining and supervising all
safety precautions and programs in connection with the work. He will take all
GC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-12.
necessary precautions for the safety of and will provide the necessary protection to
prevent damage, injury or loss to all employees on the work and other persons who
may be affected thereby, all the work and all materials or equipment to be
incorporated therein, whether in storage on or off the site or other property at the site
or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways,
structures and utilities not designated for removal, relocation or replacement in the
course of construction.
2.
The Contractor will comply with all applicable laws, ordinances, rules, regulations
and orders of any public body having jurisdiction. He will erect and maintain, as
required by the conditions and progress of the work, all necessary safeguards for
safety and protection. He will notify the owners of adj acent utilities when prosecution
of the work may affect them. The Contractor will remedy all damage, injury or loss
to any property caused, directly or indirectly, in whole or in part, by the Contractor,
and subcontractor or anyone directly or indirectly employed by any ofthem or anyone
for whose acts any of them are liable, except damage or loss attributable to the fault
of the Contract Documents or to the acts or omissions of the Owner or the Engineer
or anyone employed by either of them or anyone for whose acts either of them may
be liable and not attributable, directly or indirectly, in whole or in part, to the fault or
negligence of the Contractor.
3.
In emergencies affecting the safety of persons or the work or property at the site or
adjacent thereto, the Contractor, without special instructions or authorization from the
Engineer or Owner, shall act to prevent threatened damage, injury or loss. He will
give the Engineer prompt written notice of any significant changes in the work or
deviations from the Contract Documents caused thereby and a Change Order shall be
issued covering the changes and deviations involved.
4.
The work under this Contract in every respect shall be at the risk of the Contractor
until finished and accepted, except to damage or injury caused directly by the Owner's
agents or employees.
SUPERVISION BY CONTRACTOR:
1.
The Contractor will supervise and direct the work. He will be solely responsible for
the means, methods, techniques, sequences and procedures of construction. The
Contractor will employ and maintain on the work a qualified supervisor or
superintendent who shall have been designated in writing by the Contractor as the
Contractor's representative at the site. The supervisor shall have full authority to act
on the behalf of the Contractor and all communications given to the supervisor shall
be as binding as if given to the Contractor. The supervisor shall be present on the site
at all times as required to perform adequate supervision and coordination of the work.
GC-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-13.
GC-14.
GC-15.
CHANGES IN THE WORK:
1.
The Owner may at any time as the need arises, order changes within the scope of the
work without invalidating the Agreement. If such changes increase or decrease the
amount due under the Contract Documents or in the time required for performance of
the work, an equitable adjustment shall be authorized by Change Order.
2.
The Engineer, also, may at any time, by issuing a field order, make changes in the
details of the work. The Contractor shall proceed with the performance of any
changes in the work so ordered by the Engineer unless the Contractor believes that
such field order entitles him to a change in the contract price or time or both, in which
event he shall give the Engineer written notice thereof within ten (10) days after the
receipt of the ordered change pending the receipt of an executed change order or
further instruction from the Owner.
CHANGES IN CONTRACT PRICE:
1.
The contract price may be changed only by a change order. The value of any work
covered by a change order or of any claim for increase or decrease in the contract price
shall be determined by one or more of the following methods in the order of
precedence listed below:
1.1 Unit prices previously approved.
1.2 An agreed lump sum.
1.3 The actual cost for labor, direct overhead, materials, supplies, equipment and
other services necessary to complete the work. In addition there shall be
added an amount to be agreed upon but not to exceed fifteen (15) percent of
the actual cost of the work to cover the cost of general overhead and profit.
TIME FOR COMPLETION AND LIOUIDATED DAMAGES:
1.
The date ofbeginning and the time for completion ofthe work are essential conditions
of the Contract Documents and the work embraced shall be commenced on the date
specified in the Notice to Proceed.
2.
The Contractor will proceed with the work at such rate of progress to insure full
completion within the contract time. It is expressly understood and agreed, by and
between the Contractor and the Owner, that the contract time for the completion ofthe
work described herein is a reasonable time, taking into consideration the average
climatic and economic conditions and other factors prevailing in the locality of the
work.
3.
Ifthe Contractor shall fail to complete the work within the contract time or extension
oftime granted by the Owner, then the Contractor will pay to the Owner the amount
for liquidated damages as specified in the Agreement for each calendar day that the
Contractor shall be in default after the time stipulated in the Contract Documents.
GC-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-16.
GC-17.
4.
The Contractor shall not be charged with liquidated damages or any excess cost when
the delay in completion of the work is due to the following and the Contractor has
promptly given written notice of such delay to the Owner or Engineer.
4.1 To any preference, priority or allocation order duly issued by the Owner.
4.2 To unforeseeable causes beyond the control and without the fault of
negligence of the Contractor, including but not restricted to, acts of God or of
the public enemy, acts of the Owner, acts of another Contractor in the
performance of a contract with the Owner, fires, floods, epidemics, quarantine
restrictions, strikes, freight embargoes and abnormal and unforeseeable
weather; and
4.3 To any delays of subcontractors occasioned by any of the causes specified in
Paragraphs 4.1 and 4.2 of this Article.
CORRECTION OF WORK:
1.
The Contractor shall promptly remove from the premises all work rejected by the
Engineer for failure to comply with the Contract Documents, whether incorporated in
the construction or not and the Contractor shall promptly replace and re-execute the
work in accordance with the Contract Documents and without expense to the Owner
and shall bear the expense of making good all work of other Contractors destroyed or
damaged by such removal or replacement.
2.
All removal and replacement work shall be done at the Contractor's expense. If the
Contractor does not take action to remove such rejected work within ten (10) days
after receipt of written notice, the Owner may remove such work and store the
materials at the expense of the Contractor.
3.
Any omissions or failure on the part of the Engineer to disapprove or rej ect any work
or material shall not be construed to be an acceptance of any defective work or
material. The Contractor shall remove, at his own expense and shall rebuild and
replace same without extra charge and in default thereof the same may be done by the
Owner at the Contractor's expense or in case the Engineer shall not consider the defect
of sufficient importance to require the Contractor to rebuild or replace any imperfect
work or material, he shall have the power and is hereby authorized to make an
equitable deduction from the stipulated price.
SUBSURFACE CONDITIONS:
1.
The Contractor shall promptly and before such conditions are disturbed, except in the
event of an emergency, notify the Owner by written notice of:
1.1 Subsurface or latent physical conditions at the site differing materially from
those indicated in the Contract Documents.
GC-I0
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-18.
1.2 Unknown physical conditions at the site, of an unusual nature, differing
materially from those ordinarily encountered and generally recognized as
inherent in work of the character provided for in the Contract Documents.
2.
The Owner shall promptly investigate the conditions and if he finds that such
conditions do so materially differ and cause an increase or decrease in the cost of, or
in the time required, for performance of the work, an equitable adjustment shall be
made and the Contract Documents shall be modified by a Change Order. Any claim
of the Contractor for adjustment hereunder shall not be allowed unless he has given
the required written notice; provided that the Owner may, ifhe determines the facts
so justify, consider and adjust any such claims asserted before the date of final
payment.
SUSPENSION OF THE WORK, TERMINATION AND DELAY:
1.
The Owner may, at any time and without cause, suspend the work or any portion
thereof for a period of not more than ninety days or such further time as agreed upon
by the Contractor, by written notice to the Contractor. The Engineer shall fix the date
on which work shall be resumed. The Contractor will resume that work on the date
so fixed. The Contractor will be allowed an increase in the contract price, an
extension of the contract time, or both, directly attributable to any suspension.
2.
If the Contractor is adjudged bankrupt or insolvent, or if he makes a general
assignment for the benefit of his creditors or if a trustee or receiver is appointed for
the Contractor or for any of his property or ifhe files a petition to take advantage of
any debtor's act to reorganize under the bankruptcy or applicable laws or if he
repeatedly fails to supply sufficient skilled workmen or suitable materials or
equipment, or ifhe repeatedly fails to make prompt payments to subcontractors or for
labor, materials or equipment or ifhe disregards laws, ordinances, rules, regulations
or orders of any public body having jurisdiction of the work or if he disregards the
authority ofthe Engineer, or if, in the opinion of the Engineer, the Contractor fails to
make satisfactory progress in prosecuting the work, or if he otherwise violates any
provision of the Contract Documents, then the Owner may, without prejudice to any
other right or remedy and after giving the Contractor and his Surety a minimum often
(10) days from delivery of a written notice, terminate the services of the Contractor
and take possession of the Proj ect and of all materials, equipment, tools, construction
equipment and machinery thereon owned by the Contractor and finish the work by
whatever method he may deem expedient. In such case, the Contractor shall not be
entitled to receive any further payment until the work is finished. If the unpaid
balance of the Contract Price exceeds the direct and indirect costs of completing the
Project, including compensation for additional professional services, such excess shall
be paid to the Contractor. If such costs exceed such unpaid balance, the Contractor
will pay the difference to the Owner. Such costs incurred by the Owner will be
determined by the Engineer and incorporated in a Change Order.
GC-11
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-19.
3.
The Contractor must obtain permission from the Engineer before any equipment can
be removed from the job site. In the event such equipment is removed without the
Engineer's approval, the job will be terminated until such time as the equipment is
returned to the project and any time and money lost by the Contractor as a result of
moving the equipment shall be absorbed by the Contractor.
4.
Where the Contractor's services have been so terminate by the Owner, said
termination shall not affect any right ofthe Owner against the Contractor then existing
or which may thereafter accrue. Any retention or payment of monies by the Owner
due the Contractor will not release the Contractor from compliance with the Contract
Documents.
5.
After ten (1 0) days from delivery of a written notice to the Contractor and the
Engineer, the Owner, may, without cause and without prejudice to any other right or
remedy, elect to abandon the Project and terminate the Contract. In such case, the
Contractor shall be paid for all work executed and any expense sustained plus
reasonable profit.
6.
If, through no act or fault of the Contractor, the work is suspended for a period of
more than ninety (90) days by the Owner or under an order of court or other public
authority ofthe Engineer fails to act on any request for payment within thirty (30) days
after it is submitted or the Owner fails to pay the Contractor substantially the sum
approved by the Engineer within thirty (30) days of its approval and presentation, then
the Contractor may after ten (10) days from delivery of a written notice to the Owner
and the Engineer, terminate the Contract and recover from the Owner payment for all
work executed and all expenses sustained. In addition, and in lieu of terminating the
Contract, ifthe Engineer has failed to act on a request for payment or if the Owner has
failed to make any payment as aforesaid, the Contractor may, upon ten (10) days
notice to the Owner and the Engineer, stop the work until he has been paid all
amounts then due, in which event and upon resumption of the work, Change Orders
shall be issued for adjusting the contract price or extending the contract time or both
to compensate for the costs and delays attributable to the stoppage of the work.
7.
If the performance of all or any portion of the work is suspended, delayed, or
interrupted as a result of a failure of the Owner or the Engineer to act within the time
specified in the Contract Documents, or if no time is specified, within reasonable
time, an adjustment in the contract price or an extension ofthe contract time or both,
shall be made by Change Order to compensate the Contractor for the costs and delays
necessarily caused by the failure of the Owner or the Engineer.
PAYMENTS TO THE CONTRACTOR:
1.
Between the first (lst) and the fifth (5th) of each month, the Contractor will submit
to the Engineer a partial payment estimate filled out and signed by the Contractor on
an approved form covering the work performed during the period covered by the
partial payment estimate and supported by such data as the Engineer may reasonably
GC-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
require. If payment is requested on the basis of materials and equipment not
incorporated in the work but delivered and suitably stored at or near the site, the
partial payment estimate shall also be accompanied by such supporting data,
satisfactory to the Owner, as will establish the Owner's title to the material and
equipment and protect his interest therein, including applicable insurance. The
Engineer will, within ten days after receipt of each partial payment estimate, either
indicate in writing his approval of payment and present the partial payment estimate
to the Owner, or return the partial payment estimate to the Contractor indicating in
writing his reasons for refusing to approve payment. In the latter case, the Contractor
may make the necessary corrections and resubmit the partial payment estimate. The
Owner will, within ten days of presentation to him of an approved partial payment
estimate, pay the Contractor a progress payment on the basis of the approved partial
payment estimate. The Owner shall retain ten (10%) percent of the amount of each
payment until final completion and acceptance of all work covered by the Contract
Documents. The Owner at any time, however, after fifty (50%) percent of the work
has been completed, ifhe finds that satisfactory progress is being made, shall make
payment on the current and remaining estimates, in full, so that the retained
percentage at the completion ofthe work will be approximately five (5%) percent. On
completion and acceptance of a part ofthe work on which the price is stated separately
in the Contract Documents, payment may be made in full, including retained
percentages, less authorized deductions.
2.
The request for payment may also include an allowance for the cost of such major
materials and equipment which are suitably stored either at or near the site.
3.
All work covered by partial payment shall thereupon become the sole property of the
Owner, but this provision shall not be construed as relieving the Contractor ofthe sole
responsibility for the care and protection of the work upon which payments have been
made or the restoration of any damaged work, or as a waiver ofthe right ofthe Owner
to require the fulfillment of all terms of the Contract Documents.
4.
Upon completion and acceptance of the work, the Engineer shall issue a certificate
attached to the final payment request that the work has been accepted by him under
the conditions of the Contract Documents. The entire balance found to be due the
Contractor, including the retained percentages shall be paid to the Contractor, except
such sums as may be lawfully retained by the Owner for saving the Owner or the
Owner's agents harmless from all claims growing out of the lawful demands of
Subcontractors, laborers, workmen, mechanics, materialmen and furnishers of
machinery and parts thereof, equipment, tools and supplies, incurred in the furtherance
of the performance of the work. The Contractor shall, at the Owner's request, furnish
satisfactory evidence that all obligations of the nature designated above have been
paid, discharged, or waived. If the Contractor fails to do so, the Owner may, after
having notified the Contractor, either pay unpaid bills or withhold from the
Contractor's unpaid compensation a sum of money deemed reasonably sufficient to
pay any and all such lawful claims until satisfactory evidence is furnished that all
liabilities have been fully discharged whereupon payment to the Contractor shall be
GC-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-20.
GC-21.
resumed, in accordance with the terms of the Contract Documents, but in no event
shall the provisions of this sentence be construed to impose any obligations upon the
Owner to either the Contractor, his Surety, or any third party. In paying any unpaid
bills of the Contractor, any payment so made by the Owner shall be considered as a
payment made under the Contract Documents by the Owner to the Contractor and the
Owner shall not be liable to the Contractor for any such payments made in good faith.
5.
If the Owner fails to make payment 30 days after approval by the Engineer, in addition
to other remedies available to the Contractor, there shall be added to each such
payment, interest at the maximum legal rate commencing on the first day after said
payment is due and continuing until the payment is received by the Contractor.
ACCEPTANCE OF FINAL PAYMENT AS RELEASE:
1.
The acceptance by the Contractor of final payment shall be and shall operate as a
release to the Owner of all claims and all liability to the Contractor other than claims
in stated amounts as may be specifically excepted by the Contractor for all things done
or furnished in connection with this work and for every act and neglect ofthe Owner
and other relating to or arising out of this work. Any payment, however, final or
otherwise, shall not release the Contractor or his Sureties from any obligations under
the Contract Documents or the Performance Bond and Payment Bonds.
INSURANCE:
1.
The Contractor shall purchase and maintain during the life of this Contract such
insurance as will protect him from claims set forth below which may arise out of or
result from the Contractor's execution ofthe work, whether such execution by himself
or by any Subcontractor or by anyone directly or indirectly employed by any ofthem
or by anyone for whose acts any of them may be liable.
1.1 Claims under Workman's Compensation, disability benefit and other similar
employee benefit acts,
1.2 Claims for damages because of bodily injury, occupational sickness or disease
or death of his employees,
1.3 Claims for damages because of bodily injury, sickness or disease or death of
any person other than his employees,
1.4 Claims for damages insured by usual personal injury liability coverage which
are sustained (1) by any person asa result of an offense directly or indirectly
related to the employment of such person by the Contractor or (2) by any other
person; and
1.5 Claims for damages because of injury to or destruction of tangible property,
including loss of use resulting therefrom.
GC-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2.
Certificates of Insurance acceptable to the Owner shall be filed with the Owner prior
to commencement of the work. These Certificates shall contain a provision that
coverages afforded under the policies will not be canceled unless at least fifteen (15)
days prior written notice has been given to the Owner and Program Manager.
3.
The Contractor shall procure and maintain, at his own expense, during the life of the
Contract, liability insurance as hereinafter specified.
3.1 Contractor's General Public Liability and Property Damage insurance
including vehicle coverage issued to the Contractor and protecting him from
all claims for personal injury, including death, and all claims for destruction
of or damage to property, arising out of or in connection with any operations
under the Contract Documents, whether such operations be by himself or by
any Subcontractor under him or anyone directly or indirectly employed by the
Contractor or by a Subcontractor under him. Insurance shall be written with
a limit of liability of not less than $200,000 for all damages arising out of
bodily injury, including death, at any time resulting therefrom, sustained by
anyone person in anyone accident; and a limit of liability of not less than
$500,000 for any such damages sustained by two or more persons in anyone
accident. Insurance shall be written with a limit of liability of not less than
$100,000 for all property damage sustained by anyone person in anyone
accident; and a limit ofliability of not less than $200,000 for any such damage
sustained by two or more persons in anyone accident. Contractor's insurance
policy shall name Owner and Program Manager as insureds under this policy.
3.2 The Contractor shall acquire and maintain, if applicable, Fire and Extended
Coverage insurance upon the Project to the full insurable value thereof for the
benefit of the Owner, the Contractor and Subcontractor as their interest may
appear. This provision shall in no way release the Contractor or Contractor's
Surety from obligations under the Contract Documents to fully complete the
Project.
4.
The Contractor shall procure and maintain, at his own expense, during the life of the
Contract, in accordance with the provisions of the laws of the state in which the work
is performed, Workman's Compensation Insurance, including occupational disease
provisions, for all of his employees at the site of the project and in case any work is
sublet, the Contractor shall require such Subcontractor similarly to provide
Workman's Compensation Insurance, including occupational disease provision for all
ofthe latter's employees unless such employees are covered by the protection afforded
by the Contractor. In case any class of employees engaged in hazardous work under
this Contract at the site ofthe Project is not protected under Workman's Compensation
statute, the Contractor shall provide and shall cause each Subcontractor to provide
adequate and suitable insurance for the protection of his employees not otherwise
protected.
GC-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-22.
GC-23.
5.
The Contractor shall secure, if applicable, "All Risk" type Builder's Risk Insurance for
work to be performed. Unless specifically authorized by the Owner, the amount of
such insurance shall not be less than the contract price totaled in the bid. The policy
shall cover not less than the losses due to fire, explosion, hail, lightening, vandalism,
malicious mischief, wind, collapse, riot, aircraft and smoke during the contract time
and until the work is accepted by the Owner. The policy shall name as the insured the
Contractor, the Engineer and the Owner.
Contractor shall provide a Builders Risk All Risk insurance policy for the full
replacement value of all Project work including the value of all onsite Owner-
furnished equipment and/or materials associated with Program Manager's services.
Such policy shall include coverage for loss due to defects in materials and
workmanship and errors in design, and will provide a waiver of subrogation as to
Program Manager and the Owner, and their respective officers, employees, agents,
affiliates, and subcontractors.
CONTRACT SECURITY:
1.
The Contractor shall, within ten (10) days after the receipt ofthe Notice of Award,
furnish the Owner with a Performance Bond and a Payment Bond in penal sums equal
to the amount of the contract price, conditioned upon the performance by the
Contractor of all undertakings, covenants, terms, conditions and agreements of the
Contract Documents and upon the prompt payment by the Contractor to all persons
supplying labor and materials in the prosecution ofthe work provided by the Contract
Documents. Such bonds shall be executed by the Contractor and a corporate bonding
company licensed to transact business in the state in which the work is to be
performed and named on the current list of" Surety Companies Acceptable on Federal
Bonds" as published in the Treasury Department Circular Number 570. The expense
of these bonds shall be borne by the Contractor. If at any time a Surety on any such
bond is declared a bankrupt or loses its right to do business in the state in which the
work is to be performed or is removed from the list of Surety Companies accepted on
Federal Bonds, Contractor shall within ten (10) days after notice from the Owner to
do so, substitute an acceptable bond (or bonds) in such form and sum and signed by
such other Surety or Sureties as may be satisfactory to the Owner. The premiums on
such bonds shall be paid by the Contractor. No further payments shall be deemed due
nor shall be made until the new Surety or Sureties shall have furnished an acceptable
bond to the Owner.
ASSIGNMENTS:
1.
Neither the Contractor nor the Owner shall sell, transfer, assign or otherwise dispose
of the Contract or any portion thereof, or his right, title or interest therein, or his
obligations thereunder, without written consent of the other party.
GC-16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-24.
GC-25.
INDEMNIFICATION:
1.
The Contractor will indemnify and hold harmless the Owner and Program Manager
and the Engineer and their agents and employees from and against all claims,
damages, losses and expenses including attorney's fees arising out of or resulting from
the performance of the work, provided that any such claim, damage, loss or expense
is attributable to bodily injury, sickness, disease or death, or to injury to or destruction
of tangible property, including the loss of use resulting therefrom; and is caused in
whole or in part by any negligent or willful act or omission of the Contractor and
Subcontractor, anyone directly or indirectly employed by any of them or anyone for
whose acts any of them may be liable.
2.
In any and all claims against the Owner or the Engineer or any of their agents or
employees, by an employee of the Contractor, Subcontractor, anyone directly or
indirectly employed by any of them, or anyone for whose acts any of them may be
liable, the indemnification obligation shall not be limited in any way by any limitation
on the amount or type of damages, compensation or benefits payable by or for the
Contractor or any Subcontractor under Workman's Compensation acts, disability
benefit acts or other employee benefits acts.
3.
The obligation ofthe Contractor under this paragraph shall not extend to the liability
of the Engineer, his agents or employees arising out ofthe preparation or approval of
maps, drawings, opinions, reports, surveys, change orders, design or specifications.
SEPARATE CONTRACTS:
1.
The Owner reserves the right to let other contracts in connection with this Project.
The Contractor shall afford other contractors reasonable opportunity for the
introduction and storage of their materials and the execution of their work and shall
properly connect and coordinate his work with theirs. If the proper execution or
results of any part of the Contractor's work depends upon the work of any other
Contractor, the Contractor shall inspect and promptly report to the Engineer any
defects in such work that render it unsuitable for such proper execution and results.
2.
The Owner may perform additional work related to the Project by himself or he may
let other contracts containing provisions similar to these. The Contractor will afford
the other Contractors who are parties to such contracts (or the Owner, if he is
performing the additional work himself), reasonable opportunity for the introduction
and storage of materials and equipment and the execution of the work and shall
properly connect and coordinate his work with theirs.
3.
If the performance of additional work by other Contractors or the Owner is not noted
in the Contract Documents prior to the execution of the Contract, written notice
thereof shall be given to the Contractor prior to starting any such additional work. If
the Contractor believes that the performance of such additional work by the Owner or
others involves him in additional expense or entitles him to an extension of the
contract time, he may make a claim therefor as provided in Sections GC-l3 and
GC-14.
GC-17
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-26. .
GC-27.
GC-28.
SUBCONTRACTING:
1.
The Contractor may utilize the services of specialty Subcontractors on those parts of
the work which, under normal contracting practices, are performed by specialty
Subcontractors.
2.
The Contractor shall not award work to Subcontractor(s), in excess of fifty (50%)
percent of the Contract Price, without prior written approval of the Owner.
3.
The Contractor shall be fully responsible to the Owner for the acts and omissions of
his Subcontractors, and of persons either directly or indirectly employed by them, as
he is for the acts and omissions of person directly employed by him.
4.
The Contractor shall cause appropriate provisionscto be inserted in all subcontracts
relative to the work to bind the Subcontractors to the Contractor by the terms of the
Contract Documents insofar as applicable to the work of Subcontractors and to give
the Contractor the same power as regards terminating any subcontract that the Owner
may exercise over the Contractor under any provision of the Contract Documents.
5.
Nothing contained in this Contract shall create any contractual relation between any
Subcontractor and the Owner.
ENGINEER'S AUTHORITY:
1.
The Engineer shall act as the Owner's representative during the construction period.
He shall decide questions which may arise as to quality and acceptability of materials
furnished and work performed. He shall interpret the intent of the Contract
Documents in a fair and unbiased manner. The Engineer will make visits to the site
and determine ifthe work is proceeding in accordance with the Contract Documents.
2.
The Contractor will be held strictly to the intent ofthe Contract Documents in regard
to the quality of materials, workmanship and execution of the work. Inspections may
be made at the factory or fabrication plant or the source of material supply.
3.
The Engineer will not be responsible for the construction means, controls, techniques,
sequences, procedures, or construction safety.
4.
The Engineer shall promptly make decisions relative to interpretation ofthe Contract
Documents.
LAND AND RIGHTS-OF-WAY:
1.
The Owner will furnish all land and rights-of-way necessary for carrying out and for
the completion of the work to be performed pursuant to the Contract Documents. If
all land and rights-of-way are not obtained prior to the issuing of the Notice to
GC-18
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-29.
GC-30.
GC-31.
GC-32.
Proceed, the Contractor shall begin work upon lands and rights-of-way that have been
acquired.
2.
The Owner shall provide to the Contractor information which delineates and describes
the lands owned and rights-of-",:,ay acquired.
3.
The Contractor shall provide at his own expense and without liability to the Owner
any additional land and access thereto that the Contractor may desire for temporary
construction facilities, or for storage of materials.
GUARANTEE:
1.
The Contractor shall guarantee all materials and equipment furnished and work
performed for a period of one (1) year from the date of substantial completion. The
Contractor warrants and guarantees for a period of one (1) year from the date of
substantial completion of the system that the completed system is free from all defects
due to faulty materials or workmanship and the Contractor shall promptly make such
corrections as may be necessary by reason of such defects including the repairs of any
damage to other parts of the system resulting from such defects. The Owner will give
notice of observed defects with reasonable promptness. In the event that the
Contractor should fail to make such repairs, adjustments or other work that may be
necessary by such defects, the Owner may do so and charge the Contractor the cost
thereby incurred. The Performance Bond shall remain in full force and effect though
the guarantee period.
TAXES:
1.
The Contractor will pay all sales, consumer, use and other similar taxes required by
the law of the place where the work is performed.
WORK ADJACENT TO RAILWAY OR OTHER PROPERTY:
1.
Whenever the work embraced in this Contract is near the tracks, structures or
buildings ofthe Owner or of other railways, persons, or property, the work shall be so
conducted as not to interfere with the movement of trains or other operations of the
railway, or, if in any case such interference be necessary, the Contractor shall not
proceed until he has first obtained specific authority and directions therefor from the
proper designated officer of the Owner and has the approval of the Engineer.
ORDER AND DISCIPLINE:
1.
The Contractor shall at all times enforce strict discipline and good order among his
employees and any employee of the Contractor who shall appear to be incompetent,
disorderly or intemperate or in any other way disqualified for or unfaithful to the work
entrusted to him, shall be discharged immediately on the request of the Engineer and
he shall not again be employed on the work with the Engineer's written consent.
GC-19
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-33.
GC-34.
GC-35.
GC-36.
GC-37.
WARNING DEVICES AND SIGNS:
1.
The Contractor shall furnish, erect, paint and maintain warning devices when
construction is on or near public streets for the protection of vehicular and pedestrian
traffic. Such devices will be in accordance with the Georgia Manual on Uniform
Traffic Control Devices for Street and Highways, "Traffic Control for Highway
Construction and Maintenance Operations," latest edition.
2.
A 20" x 30" sign, mounted on a solid post, 8 feet above the ground, indicating the
name and a 24-hour phone number of the Contractor in 4" letters, shall be erected at
prominent locations on the construction site as directed by the Engineer. The
Contractor may remove the sign following the maintenance period.
SPECIAL RESTRICTIONS:
1.
No work shall be allowed after the hours of darkness or on Sunday without permission
of the Owner.
2.
If Contractor wishes to work before 8 a.m. or after 5 p.m. Monday through Friday, on
weekends, or Augusta, Georgia legal holidays refer to Special Condition SC-25.
AS-BUILT DRAWINGS:
1.
The Contractor shall furnish to the Engineer three (3) sets of marked up drawings for
an "As-built" record showing all deviations from the Contract Drawings. The marked
up sets shall include actual dimensions from permanent markers accurately locating
all underground piping.
CONTRACTOR NOT TO HIRE EMPLOYEES OF THE OWNER:
1.
The Contractor shall not employ or hire any of the employees of the Owner.
DRAWINGS:
The Owner will furnish to the Contractor, free of charge, up to five (5) sets of direct
black line prints together with a like number of complete bound specifications for construction
purposes. Location of all features of the work included in the Contract are indicated on the Contract
Drawings. The following drawings comprise the plans for the Contract:
Note:
GC-38.
The Contract Drawings are listed under Special Condition SC-02., LIST OF
DRAWINGS.
FIELD OFFICE FACILITIES:
The Contractor shall provide, at a point convenient to the work, suitable office
facilities for housing records, plans and contract documents. A telephone shall be provided at the
GC-20
I
I
I
I
,
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Contractor's office for expediting the work and be made available for the use of the Engineer. A
complete and up-to-date set of the plans and specifications shall be available at the field office at all
times that the work is in progress.
GC-39.
RIGHTS-OF-WAY:
The Owner will furnish all land and rights-of-way necessary for the carrying out of this
contract and the completion ofthe work herein contemplated and will use due diligence in acquiring
said land and rights-of-way as speedily as possible. But it is possible that all land and rights-of-way
may not be obtained as herein contemplated before construction begins, in which event the Contractor
shall begin his work upon such land and rights-of-way as the Owner may have previously acquired
and no claim for damages whatsoever will be allowed by reason of the delay in obtaining the
remaining lands and rights-of-way. Should the Owner be prevented or enjoined from proceeding with
the work or from authorizing its prosecution, either before the commencement, by reason of any
litigation or by reason of its inability to procure any lands or rights-of-way for the said work, the
Contractor shall not be entitled to make or assert any claim for damage by reason of said delay or to
withdraw from the contract except by consent ofthe Owner; but time for completion ofthe work will
be extended to compensate for the time lost by such delay; such determination to be set forth in
writing and approved by the Owner.
GC-40.
ESTIMATE OF QUANTITIES:
The estimated quantities of work to be done and materials to be furnished under this
contract if shown in any of the documents including the bid are given only for use in comparing bids
and to indicate approximately the total amount of the contract and the right is especially reserved
except as herein otherwise specifically limited to increase or diminish them as may be deemed
reasonably necessary or desirable by the Owner to complete the work contemplated by this contract
and such increase or diminution shall in no way vitiate this contract nor shall any such increase or
diminution give cause for claims or liability for damages.
GC-41.
EXISTING STRUCTURES AND UTILITIES:
The existence and location of structures and underground utilities indicated on the
plans are not guaranteed and shall be investigated and verified in the field by the Contractor before
starting work. The Contractor shall be held responsible for any damage to and for maintenance and
protection of existing utilities and structures.
GC-42.
CONTRACTOR'S BREAKDOWN OF LUMP SUM PAYMENT ITEMS:
The Contractor shall, immediately after the contract has been awarded, submit to the
Engineer for his approval, a breakdown showing estimates of all costs apportioned to the major
elements of equipment, material and labor comprising the total work included under any ofthe lump
sum items shown in the proposal. These estimates as approved will serve as the basis for estimating
of payments due on all progress estimates.
GC-21
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
GC-43.
PRIOR USE BY OWNER:
Prior to completion ofthe work, the Owner may take over the operation and/or use of
the uncompleted project or portions thereof. Such prior use of the facilities by the Owner shall not
be deemed as acceptance of any work or relieve the Contractor from any of the requirements of the
Contract Documents.
GC-44.
CLEANING UP:
The Contractor shall keep the premises free from the arcumulation of waste material
and rubbish and upon completion of the work, prior to final acceptance of the completed project by
the Owner, he shall remove from the premises all rubbish, surplus materials, implements, tools, etc.,
and leave his work in a clean condition, satisfactory to the Engineer.
GC-45.
MAINTENANCE OF TRAFFIC:
In any work within the public right..:of-way, the Contractor shall provide adequate
warning and protection for pedestrian and vehicular traffic from any hazard arising out of the
Contractor's operations and will be held responsible for any damage caused by negligence on his part
or by the improper placing of or failure to display danger signs and road lanterns. All traffic lanes,
sidewalks and driveways will be kept open and clear at all times except as provided below. The
Contractor shall not block traffic on any street more than 30 minutes or without written permission
from such agency. Before leaving the work each night, it shall be placed in such condition as to cause
the least possible hazard therefrom. Should the Contractor fail to comply with the provisions of this
paragraph, the Owner may, with his own forces, provide signs, flagmen, barricades and/or
passageways or clear the pavement and deduct the cost thereof from sums due to the Contractor.
GC-46.
MAINTENANCE OF ACCESS:
The Contractor will be required to maintain access to business establishments during
all time they are open for business, to churches, schools and other institutions during the time they
are open and to all residential and other occupied buildings or facilities at all times. Bridges across
open trenches and work areas will be required to provide vehicular and pedestrian access. Bridges
with handrail protection will be required for crosswalks at street intersections. It is recognized that
it will be necessary to remove bridges and to block cross traffic while equipment is in operation. The
Contractor shall, however, plan and pursue his operations so as to minimize the time that direct
entrance is blocked.
GC-4 7.
EROSION CONTROL AND RESTORATION OF PROPERTY:
The Contractor will be required to schedule his work and perform operations in such
a manner that siltation and bank erosion will be minimized during all phases of construction. Any
areas disturbed during the course of construction shall be restored to a condition equal or better than
the original condition. The Contractor will be required to submit a Soil Erosion and Sedimentation
Control plan that is in compliance with the work site erosion control plan, per the Georgia Department
of Transportation.
GC-22
I
I
I
I
I
I
'I
I
I
I
I
I
I
I
I
I
I
I
I
GC-48.
BYPASSING SEWAGE:
The Contractor will be required to schedule and coordinate construction sequences and
to use temporary construction and other approved methods which will minimize the bypassing of
sewage during construction of the sewer facilities. The diversion of sewerage to open ditches or
streams will not be permitted.
GC-49.
SAFETY AND HEALTH REGULATIONS:
The Contractor shall comply with the Department of Labor Safety and Health
Regulations for construction promulgated under the Occupational and Health Act of1970 (PL31-596)
and under Section 107 of the Contract Work Hours and Safety Standards Act (pL91-54).
GC-SO.
PRECONSTRUCTION CONFERENCE:
A preconstruction conference shall be held at an acceptable time to the Owner and the
Contractor prior to the "Notice to Proceed" to coordinate the work and satisfy all requirements ofthe
Contract Documents. .
GC-23
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION
SC-Ol.
SC-02.
SC-03.
SC-04.
SC-05.
SC-06.
SC-07.
SC-08.
SC-09.
SC-lO.
SC-ll.
SC-12.
SC-13.
SC-14.
SC-15.
SC-16.
SC-17.
SC-18.
SC-19.
SC-20.
SC-21.
SC-22.
SC-23.
SC-24.
SC-25.
SC-26.
SC-27.
SC-28.
SECTION SC-O
INDEX TO SPECIAL CONDITIONS
Scope
List of Drawings
Bonds
Project Sign
Protection of the Environment
Temporary Toilets
Plans and Specifications Furnished
Record Drawings
Shop Drawings
Existing Structures
Salvage Material
Referenced Specifications
Traffic Control
Surveys
Construction Order and Schedule
Site Access
Georgia Prompt Pay Act
Disputes
Interest Not Earned on Retainage
Equivalent Materials
After Hours Inspection
Field Office Facilities
Inspection and Testing of Work
City Acceptance
Specified Materials
Masters Golf Tournament
Compliance with Laws, Codes, Regulations, etc.
Coordination with Jefferson Energy Cooperative
SC-O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION SC
SPECIAL CONDITIONS
-01. SCOPE OF THE WORK:
!
The project referred to in the Agreement shall consist of furnishing all materials, labor,
machinery, etc. necessary to construct a tennis complex consisting of courts, approximately 485 linear
. feet of two lane road, 64 space parking lot, and associated appurtenances.
-02. LIST OF DRAWINGS:
The following drawings, prepared by Cranston Engineering Group, P.e. Augusta,
Georgia, comprise the plans for the project:
DATE
SHEET NO. TITLE ORIGINAL REVISED
1. Cover Sheet 03/14/2008
2. Index to Sheets & General Notes 03/14/2008
3. Grading & Layout Plan 03/14/2008 OS/28/2008
4. Staking & Tree Planting Plan 03/14/2008 OS/28/2008
5. Utility Plan 03/14/2008
6. Offsite Utility Plan 03/14/2008
7. Sanitary Sewer Profiles and Section A-A 03/14/2008
8. Storm Sewer Profiles 03/14/2008
9. Miscellaneous Details 03/14/2008
10. Miscellaneous Details 03/14/2008
11. Miscellaneous Details 03/14/2008
12. Miscellaneous Details 03/14/2008
13. Initial Erosion Control Plan 03/14/2008
14. Intermediate Erosion Control Plan 03/14/2008
15. Final Erosion Control Plan 03/14/2008
16. NPDES Plan 03/14/2008 05/05/2008
17. Erosion Control Details and Notes 03/14/2008 OS/28/2008
SC-03. BONDS:
The Contractor will include in the lump sum payment for mobilization the cost of his
performance and payment bonds.
SC-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SC-04.
PROJECT SIGN:
The Contractor will furnish and install two (2) project signs, one on each end of the
proj ect, on the construction site. The signs will carry in a prominent manner the names ofthe proj ect,
the Owner, the Engineer, the Contractor, and a 24-hour phone number for the Contractor in 4 inch
letters. The sign shall be constructed and erected on wood posts in a substantial manner 8 feet above
the ground. The full size stencil shall be approved along with colors before fabrication. The
Contractor shall include the cost of the project signs in the Lump Sum Construction Bid Item.
SC-05.
PROTECTION OF THE ENVIRONMENT:
The Contractor will carefully schedule his work so that a minimum amount of exposed
earth will be subject to erosion by rainfall or wind, and he will provide means satisfactory to the
Engineer to minimize the transportation of silt and other deleterious material into the stream beds of
water courses adj acent to the proj ect.
All chemicals used during project construction or furnished for project operation,
whether herbicide, pesticide, disinfectant, polymer, reactant or of other classification, must show
approval of either EP A or USDA. Use of all such chemicals and disposal of residues shall be in
conformance with printed instructions.
SC-06.
TEMPORARY TOILETS:
Contractor shall provide temporary toilet facilities on the site for workmen employed
in the construction work. Toilets shall be adequate for the number of men employed and shall be
maintained in a clean and sanitary condition. Workmen shall be required to use only these toilets.
At completion of the work, toilets used by Contractor shall be removed and premises left in the
condition required by the Contract.
SC-07.
PLANS AND SPECIFICATIONS FURNISHED:
The Contractor will be furnished, free of charge, by the Owner one (1) set of direct
black line prints together with a like number of complete bound specifications for construction
purposes. Additional sets of plans and/or specifications will be furnished to the Contractor at the cost
of reproduction upon his written request.
SC-08.
RECORD DRAWINGS:
The Contractor will maintain in his office one complete set of drawings (including any
supplemental sketches) pertaining to the project upon which, at the end of each day's work any
deviations from the construction lines shown thereon and all changes ordered by the Engineer will
be shown accurately in red pencil. If necessary, supplemental drawings will be made to show details
of deviations or changes, and these will be kept with the marked set. The drawings will be available
to the Engineer for inspection during construction. Satisfactory progress toward the preparation of
the record drawings shall be a condition of approval of monthly payment estimates. At the
completion of construction, prior to submitting his estimate for fmal payment, and as a condition for
SC-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
payment thereof, three copies ofthe record drawings, satisfactorily completed, will be transmitted to
the Engineer. If required, as-built drawings will also be provided to the County with a letter of receipt
before final payment will be made.
SC-09.
SHOP DRAWINGS:
The Contractor shall submit to the Engineer for his review shop drawings, cuts,
diagrams, bar lists, steel details and other descriptive data on every item, where shown on the
drawings or specified herein. The Contractor shall check all submittals and so indicate on each copy
thereof.
Five copies of such shop drawings shall be submitted to the Engineer before ordering
of the material. Submittals which have not been checked by the Contractor will not be reviewed by
the Engineer. Reviews by the Engineer of submittals will cover only general conformity with the
project requirements, while responsibility for detailed conformity shall remain with the Contractor.
The Contractor will be notified by mail of the results of the submittal reviews within ten (10) days
of the receipt by the Engineer thereof
SC-lO.
EXISTING STRUCTURES:
Where sidewalks, street signs, private signs, pipelines, walls, sidewalks, fences, etc,
are removed in accomplishing the work, each and every item will be replaced in the same or better
manner or condition than that in which it was before construction began. The Contractor will protect
and hold harmless the Owner from any suit, action, or dispute whatever arising from the Contractor's
work adjacent to private property.
SC-l1.
SALVAGE MATERIAL:
All existing installations to be removed, including but not limited to masonry and
concrete rubble, asphalt, pipe, etc. will be disposed of at an approved location by the Contractor.
SC-12.
REFERENCED SPECIFICATIONS:
Where specifications or standards of trade organizations and other groups are
referenced in these specifications, they are made as much a part ofthese specifications as ifthe entire
standard or specification were reprinted herein. The inclusion of the latest edition or revision of the
referenced specification or standard is intended.
SC-13.
TRAFFIC CONTROL:
Traffic control shall conform to the Manual on Uniform Traffic Control Devices
(MUTCD) of the Federal Highway Administration, latest edition. The Contractor shall give prior
written notification to and shall obtain the approval of the Augusta Fire Department, Police
Department, Emergency Medical Services, and the Augusta Traffic Engineering Department of any
street closures.
SC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SC-14.
SURVEYS:
The Engineer has established a benchmark for locating the principal component parts
of the work. From the information thus provided, the Contractor shall develop and make all detail
surveys needed for construction lines and elevations. The Contractor shall employ only Registered
Land Survevors or Registered Professional Engineer to perform all detail surveys.
The Contractor will diligently preserve and maintain the position of all stakes,
reference points and bench marks after they are set and, in case of willful or careless destruction, he
shall be charged with the resulting expense and shall be responsible for any mistakes that may be
caused by their unnecessary loss or disturbance.
SC':15.
CONSTRUCTION ORDER AND SCHEDULE:
1.
The Contractor shall be responsible for the detailed order, schedule, and methods of
construction activities within the general guidelines specified for maintenance and
protection of highway and pedestrian, traffic; utility lines; drainage ways; adjacent
properties; and as otherwise specified.
2.
After notice to proceed and prior to the first payment on the contract the Contractor
shall submit the following for review:
A. Breakdown of contract price into units of cost for each item required to
complete the total work; this breakdown will be the basis for judging the
percentage complete at any time.
B. A statement of the order of procedure to be followed that will result in the
required protection and completion of the work within the overall contract
time.
C. A bar chart showing the percentage of each item schedules against time and
so scheduled that Contractor's order of construction is clearly shown.
3.
With each request for payment the Contractor shall submit two copies ofthe bar chart
clearly marked to show the work completed at the date of the payment requested.
SC-16.
SITE ACCESS:
In order to minimize damage to existing paving, and landscaping, access to the site for
the Contractor's personnel and equipment will be restricted to the routes designated by the Owner.
The Contractor will be required to use only these routes unless prior written approval is given by the
Owner.
SC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SC-17.
GEORGIA PROMPT PAY ACT:
This Agreement is il}tended by the Parties to, and does, supersede any and all
provisions of the Georgia Prompt Pay Act, O.C.G.A. Section 13-11-1, et seq. In the event any
provision of this Agreement is inconsistent with any provision ofthe Prompt Pay Act, the provision
of this Agreement shall control.
SC-18.
DISPUTES:
All claims, disputes and other matters in question between the Owner and the
Contractor arising out of or relating to the Agreement, or the breach thereof, shall be decided in the
Superior Court of Richmond County, Georgia. The Contractor, by executing this Agreement,
specifically consents to venue in Richmond County and waives any right to contest the venue in the
Superior Court of Richmond County, Georgia.
SC-19.
INTEREST NOT EARNED ON RETAINAGE:
Notwithstanding any provision of the law to the contrary, the parties agree that no
interest shall be due to the Contractor on any sum held as retainage pursuant to this Agreement and
Contractor specifically waives any claim to same.
SC-20.
EQUIVALENT MATERIALS:
Notwithstanding any provision of the general conditions, there shall be no substitution
of materials that are not determined to be equivalent to those indicated or required in the contract
documents without an amendment to the contract.
SC-21.
AFTER HOURS INSPECTION:
Ifthe Contractor opts to work before or after normal working hours, 8 a.m. to 5 p.m.,
Monday through Friday, or on Augusta, Georgia Legal Holidays, then the Contractor must pay for the
cost of inspection by the City of Augusta, Georgia and follow all necessary procedures listed in
"Section 15, Right-of-way Encroachment Guidelines, Part E, Outside of Normal Working Hours,"
of the Augusta-Richmonll County Planning Commission Development Documents dated September,
1999. If inspectors of Augusta;.. Richmond County are needed to work outside normal business hours,
Augusta-Richmond County needs to be notified in advance.
SC-22.
FIELD OFFICE FACILITIES:
No field office facilities will be required. However, one will be allowed should the
Contractor choose to provide it.
SC-23.
INSPECTION AND TESTING OF WORK:
The Owner shall provide sufficient competent engineering personnel for the technical
observation and testing of the work.
SC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The Engineer and his representatives shall at all times have access to the work
whenever it is in preparation or progress, and the Contractor shall provide proper facilities for such
access, and for inspections.
Inspectors shall have the power to stop work on account of a workman's incompetency,
drunkenness, or willful negligence or disregard of orders. An inspector may stop the work entirely
if there is not a sufficient quantity of suitable and approved materials or equipment on the ground to
carry it out properly or for any good and sufficient cause. Inspectors may not accept on behalf of the
Owner any material or workmanship which does not conform fully to the requirements ofthe contract
and they shall give no orders or directions under any possible circumstances not in accordance with.
the Specifications. The Contractor shall furnish the inspector with all required assistance to facilitate
thorough inspection or the culling over or removal of defective materials or for any other purpose
requiring discharge of their duties for which service no additional allowance shall be made. The
inspector shall, at all times, have full permission to take samples ofthe materials that mayor may not
be used in the work.
Any inspection provided by the. Engineers is for the purpose of determining
compliance with provisions of the contract specifications and is in no way a guarantee of the methods
or appliances use by the Contractor, nor for the safety ofthe job.
If the specifications, the Engineer's instructions, laws, ordinances, or any public
authority require any work to be specially tested or approved, the Contractor shall give the Engineer
timely notice of its readiness for inspection, and if the inspection is by an authority other than the
Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be made promptly,
and where practicable at the source of supply. If cm.y work should be covered up without review or
consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and
properly restored at the Contractor's expense.'
Re-examination of any work may be ordered by the Engineer, and, if so ordered, the
work must be uncovered by the Contractor. If such work is found to be in accordance with the
Contract Documents, the Owner shall pay the cost of re-examination and replacement. If such work
is not in accordance with the Contract Documents, the Contractor shall pay such cost.
The Owner will employ a qualified materials testing laboratory, hereinafter referred
to as the Laboratory, to monitor more fully on the Owner's behalf the quality of materials and work,
and to perform such tests as may be required under the Contract Documents as conditions for
acceptance of materials and work. The Laboratory will be solely responsible to and paid separately
by the Owner. The timing of the work of the Laboratory will be coordinated by the Engineer through
his duly authorized inspector.
The Owner will bear the cost of testing a particular material or area of the work once.
Where retesting is required following corrective measures or under other circumstances, the
Contractor shall reimburse the Owner for the cost of additional testing.
SC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SC-24.
CITY ACCEPTANCE:
Notwithstanding any other obligations of the Contractor, he shall complete the work
to the full satisfaction of the Augusta Recreation and Parks Department and the Engineer. This
provision shall not relieve the Contractor of his responsibilities for guarantees.
SC-25.
SPECIFIED MATERIALS:
Attention is drawn to the specification of certain brands or manufacturers of
construction materials on the drawings. Unless the phrase "or equal" appears in the specification
thereon, no substitution or deviation from the product specified will be allowed.
Notwithstanding any provision of the General Conditions, there shall be no
substitution of materials that are not determined to be equivalent to those indicated or required in the
Contract Documents without an Amendment to the Contract.
SC-26.
MASTERS GOLF TOURNAMENT:
Any work planned to be accomplished during or directly before the Masters Golf
Tournament must be submitted to and approved in writing by the Owner. Consideration will be given
only for contract time extensions as a result of delays in accomplishing the work. No consideration
will be given for claims for damages.
SC-27.
COMPLIANCE WITH LAWS. CODES. REGULATIONS. ETC.:
Supplementing the provision ofthe GENERAL CONDITIONS, the successful bidder
awarded this contract by signing the contract acknowledges the following, however, this is not to be
construed as all inclusive or being these only:
A. Underground Gas Pipe Law:
The Contractor signing the contract acknowledges that he is fully aware of the contents and
requirements of "Georgia Laws 1969, Pages 50 and the following, and any amendments and
regulations pursuant thereto", and the Contractor shall comply therewith.
B. High Voltage Act:
The Contractor by signing the contract acknowledges that he is fully aware ofthe contents and
requirements of "Act No. 525, Georgia law 1960, and any amendments thereto, and Rules and
Regulations of the commissioner of Labor pursuant thereto" (the preceding requirements
within quotation marks being hereinafter referred to as the "high voltage act"), and the
Contractor shall comply therewith. The signing of Contract shall also confirm on behalf of
the Contractor that he:
SC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1. has visited the premises and has taken into consideration the location of all electrical
power lines on and adjacent to all areas onto which the contract documents require to .
permit the Contract either to work, to store materials, or to stage operations, and
2. that the Contractor has obtained from the Owner ofthe aforesaid electric power lines
advice in writing as to the amount of voltage carried by the aforesaid lines.
The Contractor agrees that he is the "person or persons responsible for the work to be
done" as referred to in the high voltage act and that accordingly the Contractor is
solely "responsible for the completion of the safety measures which are required by
Section 3 of the high voltage act before proceeding with any work." The Contractor
agrees that prior to the completion of precautionary measures required by the high
voltage act he will neither bring nor permit the bringing of any equipment onto the site
(or onto any area or areas onto which the contract documents require or permit the
Contractor to work, to store materials, or to stage operations) with which it is possible
to come within eight feet of any high voltage line or lines pursuant to operations
arising out of performance of the Contract. The foregoing provisions apply to power
lines located (a) on the site and (b) on any area or areas onto which the contract
documents require or permit the Contractor either to work, to store materials, or to
stage operations, or (c) within working distance for equipment or materials, being
used on (a) and (b) above. These provisions ofthe Contract do not limit or reduce the
duty of the Contractor otherwise owed to the Owner, to other parties, or to both. The
Contractor agrees that the foregoing provisions supplement provisions of the General
Conditions. The Contractor agrees and acknowledges that any failure on his part to
adhere to the high voltage act shall not only be a violation of law but shall also be a
breach of contract and specific violation of the provisions of the General Conditions
which pertains to safety precautions.
C. Occupational Safety & Health Act:
The Contractor by signing the contract acknowledges that he is fully aware ofthe provisions
of the Williams-Steiger Occupational Safety and Health Act of 1970 and he shall comply
therewith.
SC-28.
COORDINATION WITH JEFFERSON ENERGY COOPERATIVE AND
LIGHTNING CONTRACTOR:
The Contractor shall coordinate with Jefferson Energy Cooperative (Charles Mathis,
(706) 547-5007) for the installation of the power service and parking lot lighting and the Lighting
Contractor for the installation ofthe court lighting. The materials and installation of said facilities
will be provided by others; however, any and all costs incurred during this coordination shall be
included in the Lump Sum Construction Pay Item.
SC-8
I
I
I
SECTION
I TS-l
I TS-2
I TS-3
TS-4
I TS-5
TS-6
I TS-7
I TS-8
TS-9
I TS-I0
I TS-ll
TS-12
I TS-13
I TS-14
TS-15
I TS-16
I TS-17
TS-18
I
I
I
I
SECTION TS-O
INDEX TO TECHNICAL SPECIFICATIONS
TITLE
NO. OF PAGES
Clearing and Grubbing
2
Grading
4
Excavating, Trenching and Backfilling for Pipe Lines
4
Sanitary Sewer System
15
Water Distribution
18
Storm Sewer System
4
Graded Aggregate Base Course
1
Graded Aggregate Surface Course
1
Bituminous Paving
3
Concrete Construction
2
Curbs and Gutters, Concrete
4
Erosion, Sedimentation and Pollution Control Measures
6
Grassing (Bermuda and Weeping Lovegrass)
3
Tennis Court Paving
2
Surfacing for Tennis Courts
2
Net and Net Posts
3
Chain Link Fencing
4
Windscreens
1
TS-O-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-l
CLEARING AND GRUBBING
-01.
SCOPE:
Clearing and grubbing shall consist of the removal and disposal of all trees, brush,
stumps, logs, grass, weeds, roots, decayed vegetable matter, posts, fences, stubs, rubbish and all other
objectionable matter resting on or protruding through the original ground surface and occurring
within the construction limits or rights-of-way of any excavation, borrow area, or embankment.
-02. CONSTRUCTION METHODS:
A. CLEARJNG: Clearing shall consist of the felling and cutting up, or the trimming of trees,
and the satisfactory disposal of the trees and other vegetation together with the down timber,
snags, brush and rubbish occurring within the areas to be cleared. Trees and other
vegetation, except such individual trees, groups of trees, and vegetation, as may be indicated
on the drawings to be left standing, and all stumps, roots and brush in the areas to be cleared
shall be cut off one foot above the original ground surface. Individual trees and groups of
trees designated to be left standing within cleared areas shall be trimmed of all branches to
such heights and in such manner as may be necessary to prevent interference with the
construction operations. All limbs and branches required to be trimmed shall be neatly cut
close to the whole of the tree or to main branches, and the cuts thus made shall be painted
with an approved tree wound paint. Individual trees, groups of trees, and other vegetation,
to be left standing, shall be thoroughly protected by barriers or by such other means as the.
circumstances require. Clearing operations shall be conducted so as to prevent damage by
falling trees to trees left standing, to existing structures and installations, and to those under
construction, and so as to provide for the safety of employees and others.
B. GRUBBING: Grubbing shall consist of the removal and disposal of all stumps, roots and
matted roots from the site as indicated on the drawings. In foundation areas, stumps, roots,
logs or other timber, matted roots, and other debris not suitable for foundation purposes shall
be excavated to a depth of not less than 18 inches below any sub grade, shoulder or slope.
All depressions excavated below the original ground surface for or by the removal of stumps
and roots, shall be refilled with suitable material and compacted to make the surface conform
to the surrounding ground surface.
-03. DISPOSAL OF CLEARED AND GRUBBED MATERIAL:
Saw logs, pulp wood, cord wood or other merchantable timber removed incidental
to clearing and grubbing shall become the property of the Contractor and may be sold by him,
provided such disposal is otherwise in accordance with these specifications. All incombustible
matter removed shall be hauled away and deposited at locations approved by the Engineer.
Combustible matter may be burned or may be disposed of as stated above. Burning shall be done
at such time and such manner as to prevent fire from spreading and to prevent any damage to
adjacent cover and shall further be subject to all requirements of Local, State and Federal
TS-l-l
I
I
I
I
I
'I
I
I
I
I
I
I
I
I
I
I
I
I
I
Governments pertaining to the burning. No burning will be allowed on the site unless all fires are
kept under constant attendance by persons having equipment necessary to prevent the spreading of
fire. Such equipment shall include, at the minimum, a bulldozer or front end loader, and an
approved pump and hose connected to an acceptable source of water. Disposal by burning shall be
kept under constant attendance until all fires have burned out or have been extinguished.
-04.
MEASUREMENT AND PAYMENT:
Payment shall be made according to the lump sum price as shown in the bid schedule
for Clearing and Grubbing.
TS-1-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-2
GRADING
-01.
SCOPE:
This section covers grading for the roadways, parking areas, drives and/or walks,
including all excavations, formation of embankments, preparation of sub grade for pavements and
finishing and dressing of graded earth areas, shoulders, and ditches. Work in connection with
excavation, trenching, and backfilling for utility lines is specified under the section entitled
"Excavating, Trenching and Backfilling for Pipe Lines."
-02.
CONSERVATION OF TOPSOIL:
Except where otherwise noted on the plans,. topsoil shall be removed without
contamination with subsoils and spread on areas already graded and prepared for topsoil, or shall be
transported and deposited in storage piles convenient to areas that are to receive application of
topsoil later, or at locations indicated. Topsoil shall be stripped to a depth of3 to 6 inches and, when
stored, shall be kept separate from other excavated materials and piled free of roots, stones, and other
undesirable materials.
-03.
EXCAVATION:
The term "excavation" used hereinafter is defined as "unclassified excavation."
Excavation of every description regardless of material encountered within the grading limits of the
project, shall be performed to the lines and grades indicated. Suitable excavated material shall be
transported to and placed in fill areas within the limits of the work. When directed, unsuitable
material encountered within the limits of the work shall be excavated below the grade shown and
replaced with suitable material. Materials considered unsuitable are those conforming to Classes
PT, OH" CH, MH, OL, CL, or ML as described under the Unified Soil Classification System. Rock
encountered in the grading process that is not gradable using conventional equipment (including
rippers) shall be blasted. Blasted rock shall be field measured and payment will be in accordance
with the per unit price shown in the Bid Schedule. Such material removed and the select material
ordered as replacement shall be included in excavation. Unsuitable and surplus excavation material
not required for fill shall be disposed of in designated waste or spoil areas. During construction,
excavation and filling shall be performed in a manner and sequence that will provide drainage at all
times. Material required for fills in excess ofthat produced by excavation within the grading limits
shall be excavated from the borrow areas indicated or from other approved areas selected by the
Contractor, as specified herein.
-04. SELECTION OF BORROW MATERIAL:
A. GENERAL: Borrow material shall be selected to meet the requirements and conditions of
the particular fill for which it is to be used. The material shall consist of sandy soils or sand-
clay soils capable of being readily shaped and compacted to the required densities and shall
be free of roots, trash and any other deleterious material. Any necessary clearing, grubbing,
TS-2-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
disposal of debris and satisfactory trimming and drainage of the borrow areas shall be
considered incidental to operations of the borrow excavation and shall be performed by the
Contractor at no additional cost to the Owner. Unless specifically provided, no borrow shall
be obtained within the limlts of the project site without written approval.
B. BORROW AREA(S): Borrow material shall be furnished by the Contractor from private
sources selected by the Contractor and shall consist of a suitable material of the type
mentioned above. The Contractor shall obtain from the Owners the right to procure material,
shall pay all royalties and other charges involved, and shall bear all the expenses of
developing the sources, including rights-of-way for hauling.
-05. EXCAVATION OF DITCHES AND GUTTERS:
Ditches and gutters shall be cut accurately to the cross-sections and grades indicated
by the drawings. All roots, stumps, and other foreign matter in the sides and bottom of ditches and
gutters shall be cut one foot below finish grade. Care shall be taken not to over-excavate ditches and
gutters below the grades indicated. Any excessive ditch and gutter excavation due to removal of
roots, stumps, etc., or due to over-excavation shall be backfilled to grade either with suitable
material, thoroughly compacted, or with suitable stone or cobble to form an adequate gutter paving,
as directed. The Contractor shall maintain all ditches and gutters excavated under this specification
free from detrimental quantities ofleaves, sticks, and other debris until final acceptance ofthe work.
Suitable earth material excavated from ditches and channel changes shall be placed in embankments.
Excavated material shall not be deposited within a distance from the edge of any excavation ofless
than 1 Yz times the depth of the excavation. When storm drain pipe terminates in a new ditch, the
headwall or end section together with ditch pavement shall be constructed immediately as called for
on the plans. Ditch slopes and disturbed earth areas shall be grassed as required under the section
entitled "Grassing." The Contractor shall be responsible for maintaining these newly constructed
ditches and take immediate action subject to approval to keep erosion of the ditch bottom and slopes
to a minimum during the life of the contract. No additional compensation will be given to the
Contractor for the required maintenance.
-06.
PROTECTION OF EXISTING SERVICE LINES AND UTILITIES
STRUCTURES;
Existing utility lines that are shown on the drawings or the location of which are made
known to the Contractor prior to excavation that are to be retained, as well as utility lines constructed
during excavation operations, shall be protected from damage during excavation and backfilling, and
if damaged, shall be repaired by the Contractor at his expense. In the event that the Contractor
damages any existing utility lines that are not shown, or the locations of which are not known to the
Contractor, report thereof shall be made immediately to the Engineer. If determined that repairs are
to be made by the Contractor, such repairs will be ordered under the clause of the GENERAL
CONDITIONS of the Contract entitled Changes.
-07.
BACKFILL ADJACENT TO STRUCTURES:
Backfill adjacent to structures shall be placed and compacted uniformly in such
manner as to prevent wedging action or eccentric loading upon or against the structures. Slopes
TS-2-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
bounding or within areas to be backfilled shall be stepped or serrated to prevent sliding of the fill.
During backfilling operations and in formation of the embankments, equipment that will overload
the structure in passing over and compacting these fills shall not be used. Backfill for storm drains
and subdrains, including the bedding, shall conform to the additional requirements as specified.
PREPARATION OF GROUND SURFACE FOR FILL:
-08.
All vegetation, such as roots, brush, heavy sods, heavy growth of grass, and all
decayed vegetable matter, rubbish and other unsuitable material within the area upon which fill is
to be placed shall be stripped or otherwise removed before the fill is started. In no case will
unsuitable material remain in or under the fill area. Sloped ground surfaces steeper than 1 vertical
to 4 horizontal on which fill is to be place shall be plowed, stepped or benched, or broken up as
directed, in such manner that the fill material will bond with the existing surface. Prepared surfaces
on which compacted fill is to be placed shall be wetted or dried as may be required to obtain the
compaction specified.
-09.
FILL:
Fills and embankments shall be constructed at the locations and to lines and grades
indicated. The completed fill shall correspond to the shape ofthe typical section indicated or shall
meet the requirements of the particular case. Suitable material removed from the excavation shall
be used in forming the fill. Fill material shall be reasonably free from roots, other organic material
and trash, and from stones have maximum dimension greater than 6 inches. No frozen material will
be permitted in the fill. Stones having a maximum dimension larger than 4 inches shall not be
permitted in the upper 6 inches of fill or embankment. The material shall be placed in successive
horizontal layers of 8 inches to 12 inches in loose depth for the full width of the cross section and
shall be compacted as required.
-10. COMPACTION:
A. OVERALL OR OVERLOT AREAS: Each layer ofthe fill or embankment, except in areas
indicated as not requiring compaction, shall be compacted by rolling with an approved
tamping roller, heavy rubber-tired roller, three steel wheeled power roller, vibratory roller
or other compaction equipment, whichever is best suited for the types of soil encountered to
at least 95 percent of maximum Standard Proctor density at optimum moisture content.
B. FIELD CONTROL: In all fill areas field density tests will be performed in sufficient number
(minimum of one test on each alternate lift or as recommended by the Engineer) to insure
that the specified density is being obtained. These tests will be made at the expense of the
Contractor and will be in accordance with ASTM D-698.
-11. FINISHED EXCAVATION. FILLS. AND EMBANKMENTS:
All areas covered by the project, including excavated and filled sections and adjacent
transition areas, shall be uniformly smooth graded. The finished surface shall be reasonably smooth,
compacted, and free from irregular surface changes. The degree of finish shall be that ordinarily
obtainable from either bladegrader or scraper operations, supplemented with hand raking and
TS-2-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
finishing, except as otherwise specified. The finished surface shall be not more than 0.10 foot above
or below the established grade or approved cross section. Ditches and gutters shall be finished so
as to permit adequate drainage. The surface of areas to be grassed shall be finished to smoothness
suitable for the application of grassing materials. The surface of embankments or excavated areas
for road construction or other areas to be paved on which a base course or pavement is to be placed
shall not vary more than 0.05 foot from the established grade and approved cross section. In areas
where the bulking of soil as a result of grassing operations will tend to retard surface drainage along
the edge of pavements, the finished grades shall be left 0.1 foot below grade prior to grassing.
-12.
DISPOSAL OF WASTE MATERIAL:
All vegetation, roots, brush, sod, broken pavements, curbs and gutter, rubbish, and
other unsuitable or surplus material stripped or removed from the limits of construction shall be
disposed of offthe site, except where otherwise approved in writing by the Engineer. The material
shall be dumped, spread, and leveled to drain. Surplus excavation shall be hauled to, compacted in
accordance with overall and overlot areas, and sloped to drain in the disposal area where directed.
The unsuitable material shall be leveled to drain and firmed under the normal operation of spreading
and hauling equipment. Any trees, stumps, brush, down timber, etc. in the area to be used for
disposal shall be cleared by cutting (to within six (6) inches of the ground) and shall be disposed of
by burning, removal from the property or a combination of both. Clearing and disposal of trees,
stumps, etc. shall comply with the applicable portions of the clearing and grubbing specifications.
-13.
PLACEMENT OF TOPSOIL:
Topsoil shall be placed on all shoulders, slopes, ditches, and other earth areas graded
under this contract, excluding borrow areas, unless otherwise specified on the plans. Topsoil shall
be uniformly placed on these areas to a compacted depth of not less than three (3) inches or more
than four (4) inches. The material shall be free from clods of soil, matted roots, roots grater than Y2
inch in diameter, and any other objectionable material which might hinder subsequentgrassing and
mowing operations. The material shall be placed, leveled, and lightly compacted with at least one
pass of a cultipacker or light pneumatic-tired roller, to required cross sections, but shall be left one-
tenth (0.10) of a foot below the finished earth grade.
-14.
PROTECTION:
Newly graded areas shall be protected from traffic and from erosion, and any
settlement or washing away that may occur from any cause, prior to acceptance, shall be repaired and
grades re-established to the required elevations and slopes, at no additional expense to the Owner.
-15.
MEASUREMENT AND PAYMENT:
Payment shall be made at the lump sum price for Grading/Excavation as shown in
the bid schedule.
TS-2-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-3
EXCAVATING, TRENCHING AND BACKFILLING FOR PIPE LINES
-01.
SCOPE:
This section covers all excavation, trenching and backfilling for pipe lines, complete.
-02.
EXISTING IMPROVEMENTS:
The Contractor shall maintain in operating condition and protect from damage all
existing improvements including utilities, roads, streets, sidewalks, drives, power and telephone
lines, gas lines, water lines, sewers, gutters and other drains encountered, and repair to the
satisfaction of the Engineer any aerial, surface or subsurface improvements damaged during the
course of the work. Where and if shown on the plans, the locations and existence or nonexistence
of underground utilities are not guaranteed. The Contractor shall contact the various utility
companies to determine and/or verify such information prior to proceeding with the work. He shall
make reasonable and satisfactory provisions for the maintenance of traffic on streets, drives,
walkways and at street crossings and if necessary to provide temporary walkways and bridges for
crossing of the open trench as directed.
-03.
EXCAVATION:
All excavation of every description and of whatever substances encountered shall be
performed to the depths indicated on the drawings or as specified herein. Excavation shall be made
by the open cut method except as otherwise specified or shown on the drawings. Excavation
methods shall comply with codes and ordinances of governing authorities having jurisdiction and
to the requirements of OSHA Health and Safety Standards for Excavations, 29 CPR Part 1926, or
successor regulations.
. All excavated materials not required for fill or backfill shall be removed and wasted
as directed. The banks of shallow trenches shall be kept as nearly vertical as practicable and where
required shall be properly sheeted and braced. Except where otherwise indicated, trench bottoms
shall be not less than 12 inches wider nor more than 16 inches wider than the outside diameter of the
pipe to be laid therein, and shall be excavated true to line, so that a clear space of not less than 6
inches nor more than 8 inches in width is provided on each side of the pipe. The bottom oftrenches
shall be accurately graded to provide uniform bearing and support for each section of the pipe on
undisturbed soil at every point along its entire length, except for portions of the pipe sections where
it is necessary to excavate for bell holes and for the proper sealing of pipe joints. Bell holes shall
be dug after the trench bottom has been graded. Bell holes shall be excavated only to an extent
sufficient to permit accurate work in the making of the joints and to insure that the pipe, for a
maximum of its length will rest upon the prepared bottom of the trench. Depressions for joints other
than mechanical shall be made in accordance with the recommendations of the joint manufacturers
for the particular joint used. Excavation for structures and other accessories shall be sufficient to
leave at least 12 inches in the clear between their outer surfaces and the embankment or timber
which may be used to hold the bank and protect them. Where damage is liable to result from
TS-3-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
withdrawing sheeting, the sheeting will be ordered to be left in place. Except at locations where
excavation of rock from the bottoms of trenches is required, care shall be taken not to excavate
below the depths indicated. Where rock excavation is required, the rock shall be excavated to a
minimum overdepth of 4 inches below the normal required trench depth. The overdepth rock
excavation and all excess trench excavation shall be backfilled with loose, moist earth, thoroughly
tamped. Rock is defined as materials which are so hard or cemented that the excavation of such
material requires blasting. The excavation shall proceed in a conventional manner with satisfactory
effort made to remove hard materials before the Engineer makes a determination of need for blasting.
Predrilling and blasting will be allowed, if the Contractor can provide evidence for the Engineer's
review that boring logs can and will show that the material can or cannot be excavated. Evidence
will be provided for the Engineer's review and approval before predrilling and blasting is undertaken.
The excavation and removal of isolated boulders or rock fragments larger than one cubic yard in
volume encountered in materials of common excavation shall be classified as rock excavation.
Whenever wet or otherwise unstable soil that is incapable of properly supporting the pipe, as
determined by the Engineer or indicated on the drawings, is encountered in the trench bottom, such
soil shall be removed to a depth required for the lengths designated by the Engineer, and the trench
backfilled to trench bottom grade, as herein specified, with coarse sand, fine gravel, or other suitable
material. Backfill with earth under structures will not be permitted and any unauthorized excess
excavation below the levels indicated for the foundation of such structures shall be filled with sand,
gravel, or concrete, as directed.
A. GRADING AND STACKING: All grading in the vicinity of trench excavation shall be
controlled to prevent surface ground water from flowing into the trenches. Any water
accumulated in the trenches shall be removed by pumping or by other approved methods.
During excavation, material suitable for backfilling shall be stored in an orderly manner at
a distance from the edges of trenches to avoid overloading and prevent slides or cave-ins.
Material unsuitable for backfilling, as determined by the Engineer, shall be removed from
the job site and disposed of by the Contractor in a manner as approved by the Engineer.
B. SHORING AND SHEETING: All shoring, sheeting, and bracing required to perform and
protect the excavation and to safeguard employees and the public shall be performed. The
failure of the Engineer to direct the placing of such protection shall not relieve the Contractor
of his responsibility for damage resulting from its omission.
Whenever sheeting is driven to a depth below the elevation of the top ofthe pipe, that portion
of the sheeting below the elevation of the top ofthe pipe shall not be disturbed or removed.
Sheeting left in place shall be cut off not less than 1 foot below finished grade. No sheeting
shall be removed until the excavation is substantially backfilled as hereinafter specified.
C. WATER REMOV AL: Where water is encountered, it shall be prevented from accumulating
in excavated areas by pumping, well-pointing and pumping, or by other means approved by
the Engineer as to capacity and effectiveness. Water removed from excavations shall be
discharged at points where it will not cause injury to public or private property, or the work
completed or in progress. Under no circumstances shall trench bottoms be prepared, pipes
laid, or appurtenances installed in water. Water shall not be allowed to rise in unbackfilled
excavations after pipe or structures have been placed.
TS-3-2
I
I
I
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D. BLASTING: Explosives are to used only within legal limitations. Before explosives are
used, all necessary permits for this work shall be secured and all precautions taken in the
blasting operations to prevent damage to private or public property or to persons. The
Contractor shall assume full liability for any damage that may occur during the use of
explosives. No blast shall be set offwithin 50 feet of pipe already laid in the trench.
E. TREE PROTECTION: Care shall be exercised to protect the roots of trees to be left
standing. Within the branch spread of the tree, trench shall be opened only when the work
can be installed imrtlediately. Injured roots shall be pruned cleanly and backfill placed as
soon as possible.
-04. BACKFILLING:
Trenches and other excavations shall not be backfilled until all required tests are
performed and the work has been approved by the Engineer. The trenches shall be carefully
backfilled with the excavated materials approved for backfilling consisting of earth, loam, sandy
clay, sand and gravel, soft shale, or other approved materials. No material shall be used for
backfilling that contains mulch, other unstable materials, stones, blasted rock, broken concrete or
pavement, or other hard materials having any dimension greater than 4 inches; or large clods of earth,
debris, frozen earth or earth with an exceptionally high void content.
For backfill up to a level 1 foot over the top of pressure pipelines and 2 feet above
the top of gravity pipelines, only selected materials shall be used. Select materials shall be finely
divided material free from debris, organic material and stone, and may be suitable job excavated
material or shall be provided by the Contractor from other sources. The backfill shall be placed in
uniform layers not exceeding 6 inches in depth. Each layer shall be moistened and carefully and
uniformly tamped with mechanical tampers or other suitable tools. Each layer shall be placed and
tamped under the pipe haunches with care and thoroughness so as to eliminate the possibility of
voids or lateral displacement.
The remainder of the backfill material shall then be placed and compacted above the
level specified above. In areas not subject to traffic, the backfill shall be placed in 12 inch layers and
each layer moistened and compacted to a density approximating that of the surrounding earth. Under
roadways, driveways, paved areas, parking lots, along roadway shoulders and other areas subject to
traffic, the backfill shall be placed in 6 inch layers and each layer moistened and compacted to
density at least equal to that ofthe surrounding earth so that traffic can be resumed immediately after
backfilling is completed. Any trenches which are improperly backfilled, or where settlement occurs,
shall be reopened to the depth required for proper compaction, then refilled and compacted with the
surface restored to the required grade compaction. Along all portions of the trenches not located
in roadways, the ground shall be graded to a reasonable uniformity and the mounding over the
trenches left in a neat condition satisfactory to the Engineer.
Sheeting not specified to be left in place shall be removed as the backfilling
progresses. Sheeting shall be removed in such a manner as to avoid caving of the trench. Voids left
by the removal of sheeting and shoring shall be carefully filled and compacted. Where, in the
opinion of the Engineer, damage is liable to result from withdrawing sheeting, the sheeting will be
ordered to be left in place.
TS-3-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-05.
BORING AND JACKING:
Where required by the drawings, the pipeline will be installed in a steel casing, placed
by boring and jacking. Where boring is required under highways, the materials and workmanship
will be in accordance with the standards ofthe State Highway Department or local authority. Boring
and jacking under railroads will be governed by the latest A.R.E.A. standards and those of the
railroad involved. The steel casing shall be in accordance with ASTM A252 to the thicknesses
shown on the drawings.
-06.
PAVEMENT REMOVAL AND REPLACEMENT:
Where necessary existing pavements shall be removed and replaced, the applicable
standards of the State Highway Department or local authority shall govern this work. Joints shall
be sawed, unless joints equally uniform in the opinion of the Engineer result from other means. All
pavement repairs shall consist of a concrete slab no less than 6 inches thick or compacted graded
aggregate at least 9 inches thick, as indicated on the drawings. Where the parent pavement is
concrete, the slab surface shall be smoothly finished flush with the surrounding pavement. Where
the parent pavement is asphalt, the concrete slab shall be raked finished and topped with 1 inch of
surface mix asphalt paving rolled flush with the surrounding pavement.
-07.
MEASUREMENT AND PAYMENT:
Excavation and backfilling for pipelines and appurtenances, except as hereinafter
provided for, will be considered as incidental to the construction of the various elements of the
installation it is associated with, and no separate payment will be made therefor.
TS-3-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-4
SANITARY SEWER SYSTEMS
-01. BASIS FOR DESIGN:
A Professional Engineer registered in the State of Georgia must prepare the plans and
. specifications. Design must conform to the requirements set forth in "Recommended Standards for
Wastewater Facilities" (latest version) published by the Great Lakes-Upper Mississippi River Board
of State and Provincial Public Health and Environmental Managers, and follow EPD guidelines.
Before a sewer is designed, the area to be served should be studied for the purpose of
estimating the type and quantity of flow to be handled. Design should be considered for the ultimate
tributary population. Consideration should be given to the maximum anticipated capacity of
institutions, industrial parks, etc. Where future relief sewers are planned, economic analysis of
alternatives should accompany initial permit application. Design should be based on peak sewage
flows plus the anticipated maximum infiltration/inflow levels under normal open channel flow
conditions.
All food service operations are required to install, operate, clean, and maintain a
sufficiently sized oil and grease separator (grease trap) to prevent obstruction or interference with
the proper operation of the sanitary sewer collection system and treatment plants.
All existing waterworks units, including basins, wells, and treatment units, located within
200 feet of a proposed sewer shall be shown on the engineering plans. Soil conditions within this
200 feet of waterworks shall be determined and shown on the plans.
A professional engineer shall determine force main size, after a study has been completed
ofthe surrounding area with regards to the proposed construction and potential future construction.
A minimum velocity of2 fps within a force main shall be acceptable for prevention of solids settling.
No sanitary sewer lines less than eight (8) inches in diameter may be installed. Sanitary
laterals with clean-outs shall be installed at ALL service tie-ins to the system.
During construction when deviations from approved plans affecting capacity, flow, or
operation are desired, the Augusta Utilities Department's Inspector shall be notified. Revised plans
shall be submitted as soon as possible to the Augusta Utilities Department for approval. Minor
changes not affecting capacities, flows or operation may be allowed in the field during construction
by the Utilities Department's Inspector. The Inspector shall have final authority as to what
constitutes a minor or major change. An approved set of Record Drawings clearly showing any
changes shall be submitted to the Augusta Utilities Department Inspector at the completion of the
work and prior to sign-off of the final plat.
The ContractorlDeveloper is responsible for verifying the exact location, size and
material of any existing sewer facility proposed for connection or use by the project.
TS-4-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-02.
DESIGN STANDARDS FOR SANITARY SEWER LINES:
A. COVER
1. Minimum cover to finished grade over sanitary sewer shall be four (4) feet.
2. Maximum cover shall be 20 feet unless otherwise approved by the Augusta Utilities
Department.
B. HORIZONTAL SEPARATION
1. Ten (10) feet to water lines and storm sewer lines.
2. Fifteen (15) feet to buildings, top of bank oflakes/streams/creeks, other structures
(10 feet absolute minimum - only when unavoidable, and pipe material is required
to be DIP).
3. Ten (10) feet minimum separation to 'gas mains.
4. Ten (10) feet minimum to underground electric cable.
5. All separation distances above are edge to edge.
C. VERTICAL SEPARATION
1. Eighteen (18) inch minimum separation (edge to edge) between all pipes and cables
shall be maintained (6 inch absolute minimum separation with DIP).
D. LAYOUT
1. Sanitary sewer easements shall be a minimum of twenty (20) feet wide with the
sewer line centered in the easement.
2. Individual sewer services shall be a minimum of six (6) inches in diameter and shall
extend from the main and terminate with a clean-out constructed at the edge of right-
of-way. If the main is installed outside of the right-of-way, the services with clean-
outs shall terminate at the edge ofthe permanent easement. All lines eight (8) inches
in diameter and larger shall terminate in a manhole. Sewer lines installed parallel to
lakes/ streams/creeks shall be designed to leave a 25- foot undisturbed buffer along the
edge of the banle The required service lateral with clean-out shall be inspected by
the Augusta Utilities Inspector prior to physical tie-in of private service line. The use
of donuts or tying into the stack pipe of the clean-out is strictly prohibited.
3. Under no circumstances shall house sewer services and water services be laid in the
same trench.
4. All sewers shall be designed and constructed to give a mean velocity of2.0 feet per
second, when flowing full, based on Manning's formula using an "n' of 0.013. The
following are the minimum slopes that should be provided; however, slopes greater
than these are desirable.
TS-4-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Size (inches)
8
10
12
14
15
16
18
21
24
27
30
33
36
39
42
Minimum Slope in Feet
Per 100 Feet
0.40
0.28
0.22
0.17
0.15
0.14
0.12
0.10
0.08
0.067
0.058
0.052
0.046
0.041
0.037
Where velocities greater than 10 feet per second are attained, special provision shall
be made to protect against displacement by erosion and impact.
5. The maximum slope for a sanitary sewer line shall be 20%. All 20% sewers shall be
DIP with concrete collar walls at every joint or alternate restraining system provided
by design engineer. Slopes less than 20% are preferred. If steep slope is necessary,
the Augusta Utilities Department Engineer must approve the design.
6. Buoyancy of sewers shall be considered and flotation ofthe pipe shall be prevented
with appropriate construction where high groundwater conditions are anticipated.
7. Manhole spacing shall not exceed 400 LF for sewers 15 inches in diameter or
smaller, and 500 feet for sewers 18 inches to 30 inches.
8. Manholes shall be located at the junction of sewers and at changes in grade, pipe size,
or alignment. They shall also be installed at all intersections. Sanitary sewer
manholes should not be located where surface water drain into them. When this is not
possible, a watertight cover shall be specified. For this purpose, and also for assisting
in locating manholes across country, the rims shall be set above grade.
9. A drop manhole shall be provided for a sewer entering a manhole at an elevation of
24 inches or more above the manhole invert. Where the difference in elevation
between the incoming sewer and the manhole invert is less than 24 inches the invert
shall be filleted to prevent solids deposition.
10. Minimum angle between influent and effluent sanitary sewer lines at a manhole shall
be ninety (90) degrees.
TS-4-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
11. Both vertical and horizontal alignments shall be reviewed with the Augusta Utilities
Department prior to finalization.
12. All pipes crossing proposed sanitary sewer lines shall be shown as conflicts in plan
and profile views on the sanitary sewer plan sheets (not on detail sheets). Crossings
shall be designated by a letter (A, B, C, etc...) and include information regarding top
of pipe and bottom of pipe elevations. Contact the Augusta Utilities Department for
an example. The design engineer is responsible for identifying all conflicts.
13. Where indicated on the plans, pipe stub-outs for the connection of future sewers shall
be provided during the construction of new manholes. Each stub-out shall be
plugged in the bell end of the stub-out with plug approved by Augusta Utilities.
E. SANITARY SEWER MATERIAL
1. Pipe for sanitary sewers shall be polyvinyl chloride (PVC) or ductile iron pipe (DIP)
as outlined below. However, DIP is considered a remedial measure for special
applications only. Standard pipe lengths not greater than 20 feet shall be used. Force
main pipe shall be of approved C900-CL200 water pipe.
2. PVC pipe shall be manufactured from virgin resin conforming to ASTM D-3034 with
minimum classification of SDR-35. DIP shall be epoxy-lined and conform to
A WW A C 151/ ANSI A2l. 51 (latest revision). Design methods shall conform to
A WW A CI50/ANSI A2l.50. DIP shall be Class 350 for 12 inch and smaller.
3. All fittings shall be of the same quality and material as the pipe to be used. Pipe
classes shall be determined based upon the installation and the use intended. Pipe
shall be appropriately labeled on the drawings. WYE fittings shall be utilized. TEE
fittings and saddles shall not be allowed. All DIP fittings shall be ductile iron or cast
Iron.
4. Aerial pipe shall be mechanical joint DIP or continuous weld, wrapped and coated
steel pipe. Piers shall be placed at every joint directly behind the bell. Site
conditions may dictate construction utilizing more stringent requirements than
indicated in the standard detail. Anchor collars shall be constructed on the pipe
whenever pipe grade is 20% or greater. Restrainers may be used in lieu of collars
when a particular brand and method are determined equivalent.
5. DIP shall be required in the following circumstances:
a. When sanitary sewer line has less than four (4) feet of cover. Minimum
depth of DIP is two (2) feet.
b. When a sanitary sewer line cross over storm pipe (Must be one joint of DIP
centered on the crossing)
TS-4-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c. When a sanitary sewer line passes laterally within one (1) foot of a storm
sewer line (Must be one joint of DIP centered on the crossing).
d. When a sanitary sewer line is to have in excess of eighteen (18) feet of fill.
e. When a sanitary sewer line is at the maximum slope of 20%.
f. For last joint of pipe at all drop manholes greater than three (3) feet.
g. When a sanitary sewer is less than six (6) feet under a street.
6. The Utilities Director may mandate DIP in any instances of off-site or on-site
construction where future abuse to the line is possible due to location or
circumstances, extensive length under pavement, or in private property away from
right-of-way areas.
7. PVC shall be jointed with a rubber gasket and shall conform to ASTM F477 and
manufacturer's recommendations. Solvent weld is prohibited. DIP shall be of the
bell and spigot type with push-on joints conforming to ANSI A21.11 or mechanical
joints.
8. Sewer Pipe Bedding:
a. Bedding requirements shall apply to sanitary sewer lines only. They are not
to be considered minimum bedding requirements and as such, do not relieve
the Engineer/Contractor of the responsibility to provide any additional
bedding necessary for proper construction.
Bedding shall be carefully placed along the full width ofthe trench so that the
pipe is true to line and grade of the pipe barrel. Bell holes shall be provided
so as to relieve pipe bells of all load, but small enough to ensure that support
is provided throughout the length of pipe. Crushed stone embedment
material shall conform to ASTM C33, Graduation #67 (3/4inch to #4).
Bedding material shall be placed underneath and be carried up the sides ofthe
pipe as specified below.
b. Class B Bedding shall be performed by first undercutting the trench an
adequate amount to provide bedding under the pipe bell. The trench shall
then be brought to grade with compacted crushed stone as specified above for
the full width ofthe trench. The bedding material shall be placed in the zone
four (4) inches below the pipe and the pipe laid to line and grade and
backfilled with compacted crushed stone placed the full width ofthe trench
up to one-half the outside diameter of the pipe. Select backfill placed in six
(6) inch layers and compacted shall be the backfill from the springline of pipe
to 18 inches above the pipe. A minimum Class B Bedding shall be used for
all plastic pipes.
TS-4-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c. Class C Bedding shall be performed by first undercutting the trench ail
adequate amount to provide bedding under the pipe bell. The trench shall
then be brought to grade with compacted crushed stone as specified above for
the full width of the trench. The bedding material shall be placed in the zone
four (4) inches below the pipe and the pipe laid to line and grade and
backfilled with compacted crushed stone placed the full width of the trench
up to one- fourth the outside diameter ofthe pipe. Select backfill placed in six
(6) inch layers and compacted shall be the backfill from the bedding material
to 18 inches above the pipe. A minimum Class C Bedding shall be used for
all ductile iron pipes.
9. Jack and Bore Installations:
a. Casing pipe used withj ack and bore shall be in accordance with requirements
of the Georgia Department of Transportation (GDOT) or railway
specifications.
10. New sewers shall be tied-in to the existing sewers at locations indicated on the plans.
No lines smaller than six (6) inches shall be tied to a sewer line or manhole. All tie-
ins to existing manholes shall be cored. The Contractor shall be responsible for
maintaining uninterrupted service ofthe sanitary sewer during tie-in operations. No
connection to existing sanitary sewer shall be allowed until the proposed sewer line
is inspected and approved by the Augusta Utilities Department's Inspector.
11. Side sewers shall be installed where shown on the plans. A side sewer consists of a
sewer extending from a connection to the street or main sewer to its connection to the
house sewer or other point. For new 8inch through 12inch diameter sewers, the side
sewer connection shall be constructed with a wye fitting in the street sewer with a 45-
degree elbow. For new 15inch and larger pipes, or existing sewers, the connection
shall be made by machine made tap and suitable saddle, unless otherwise approved
by the Augusta Utilities Department.
12. Belled pipe shall be laid with the bell end up grade and in general, all pipe laying
shall start and proceed up grade from the point of connection at the street sewer or
other starting point. Pipe shall be laid in a straight line at a uniform grade between
fittings or on a uniform horizontal or vertical curvature achieved by deflecting the
pipe joints within the manufacturer's recommended limits. The maximum deflection
permissible at anyone fitting shall not exceed 45 degrees. The maximum deflection
of any combination of two adjacent fittings shall not exceed 45 degrees unless
straight pipe not less than 2 12 feet in length be installed between such adjacent
fittings or unless one of such fittings is a wye branch with a c1eanout provided on the
straight leg.
13. Material for transition (e.g., PVC to DIP) shall be indicated and specified. Where
offset of DIP is required, mechanical joint DIP shall be installed with mechanical
joint heavy body DIP sleeves at the reconnections.
TS-4-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
14. Sanitary Sewer Manholes:
a. Precast manholes shall conform to ASTM C-478 (five inch wall thickness).
Use six (6) inch wall thickness if manhole exceeds 20 feet in depth. All
holes for incoming and outgoing pipe will, whenever possible, be precast,
with pipe tie-in made using PS 1 0 flexible gasket, manufactured by PressSeal
Gasket Corporation, or approved equal. In the event of the necessity of
cutting new holes, the holes shall be machined cored neatly and carefully so
as not to damage the structural integrity of the manhole and large enough to
allow the insertion of a flexible rubber boot. Precast holes shall be flexible
boot fitted.
b. Barrel joints shall be tongue and groove with performed plastic meeting the
requirements of Federal Specifications SS-S-00210, "Sealing Compound,
Preformed Plastic Pipe Joints" Type I, rope form, also known as "Ram
Neck." Eccentric manholes cones are required. Inverts shall be constructed
of 3,000 psi plant mix. Manhole steps shall be installed in all sections of
each manhole as indicated on the drawings. Frame and covers shall be cast
or ductile iron and set in a bed of mortar on the top of the manhole and
completely grouted outside and wiped smooth. Ring and cover shall be USF-
170 or approved equal. Cover shall read "Sanitary Sewer." Watertight
manhole covers are to be used wherever street runoff or high water may flood
the manhole tops. Locked manhole covers may be may be desirable in
isolated easement locations or where vandalism may be a problem.
c. Where corrosive conditions due to septicity or other causes is anticipated,
consideration shall be given to providing corrosion protection on the interior
of the manholes.
d. The minimum diameter of manholes shall be 48 inches; larger diameters are
required for large diameter sewers. A minimum access diameter of 22- ~
inches shall be provided.
e. Outside drop manholes shall be precast and constructed for incoming lines
having invert 24 inches or more above the invert ofthe manhole outlet, with
DIP and tie rods per Detail No. 13.08. Shallow manholes shall be precast or
Type B slab top precast and shall be constructed in accordance with ASTM
C-478.
f. Drop manholes should be constructed with an outside drop connection. Inside
drop connection (when necessary) shall be secure to the interior wall of the
manhole and provide access for cleaning. Inside drop connections shall be
used only when approved by the Utilities Department Engineering Division.
g. Due to the unequal earth pressure that may result from the backfilling
operation in the vicinity of the manhole, the entire outside drop connection
shall be encased in concrete.
TS-4- 7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-03.
h. A bench shall be provided on each side of any manhole channel when the
pipe diameter(s) are less than the manhole diameter. The bench should be
sloped no less than Y2 inch per foot (4 percent). No lateral sewer, service
connection, or drop manhole pipe shall discharge onto the surface of the
bench.
15. All construction material shall be first quality, not previously used. Repair clamps
are not acceptable. Damaged or faulty pipe and materials must be properly replaced.
All gaskets shall be new. When connecting to existing valves or fittings, gaskets
shall be replaced, not reused.
16. The Engineer shall provide a complete set of shop drawings, which shall indicate the
Augusta Utilities Department's specific material requirements. In general, material
requirements will be guided by the latest revisions ofthe specifications of A WW A
and ASTM.
SANITARY SEWER SYSTEM DESIGN:
A. Design requirements are as follows:
Per Capita Flow, Average:
Minimum velocity in collector sewer:
Maximum velocity in collector sewer:
Minimum collector sewer size:
Infiltration Allowance:
Ratio of Peak to Average flow:
Design depth of flow @ Peak Flow:
Design Period:
Minimum Manning's "n" Factor:
125 gallons per day (gpd)
2.0 feet per second (fps)
10.0 feet per second (fps)
8 inch
100 gpd/in Dia/mile
2.5
0.75 of Full
30 Years
0.013
B. LIFT STATION DESIGN
1. All lift stations shall be installed underground, unless otherwise directed by the
Utilities Director. Wet well size and pump sizing shall be determined by a
professional engineer, after a comparative study has been done of the area
surrounding the proposed construction. Potential future development of the
surrounding area should be incorporated into the design. All potable water services
around sewage pumping facilities shall be provided with an approved reduced
pressure backflow prevention (RPZ) device.
2. All pipes entering the wet well and discharging from the wet well into the valve pit
shall be mechanical joint DIP. PVC pipe will not be permitted. Pipes shall be sized
per the design engineer's calculations and pump data.
3. Pumps, valves, and pipe sizes, shall be designed by a professional engineer.
Calculations for the design shall be submitted to the Augusta Utilities Department
TS-4-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
for review and approval. Pump specifications shall be provided to Augusta Utilities
for review. Valves shall have a minimum of an 18-inch clear zone in all directions.
4. The valve pit shall consist of a precast manhole cone section or a precast concrete
box. The bottom shall have 2-inch diameter pre-drilled holes filled with gravel for
drainage.
A cone section shall be set on a minimum 4-inch thick concrete slab with an open
bottom and gravel for drainage. For proposed piping, the manhole shall have cored
holes fitted with flexible rubber boots. Standard ring and cover shall be installed and
grouted to the cone section. The top of the valve pit shall be a minimum of six (6)
inches above finished grade.
5. Electrical systems and components (e.g., motor, lights, cables, conduits, switch
boxes, control circuits, etc.) in raw wastewater wells, or in enclosed or partially
enclosed spaces where hazardous concentrations of flammable gases or vapors may
be present, shall comply with the National and the City of Augusta Electrical Code
requirements. In addition, equipment located in the wet well shall be suitable for use
under corrosive conditions. Each flexible cable shall be provided with a watertight
seal and separate strain relief. A fused disconnect switch located above ground shall
be provided. For the main power feed for all pumping stations. When such equipment
is exposed to weather it shall meet the requirements of weatherproof equipment. One
such equipment such as the control panel shall be duplex NEMA 4X with audible
and visible alarms. Lightning and surge protection systems should be considered. A
110 volt power receptacle to facilitate maintenance shall be provided inside the
control panel for lift stations that have control panels outdoors. Ground fault
interruption protection shall be provided for all outdoor outlets.
-04. CONSTRUCTION:
A. INSTALLATION
1. Authorization must be obtained from the Augusta Utilities Department to construct,
alter or modify a sanitary sewer line. Construction of sewer infrastructure will be
authorized by the Utilities Department upon approval of submitted plans and
notification of the Augusta Utilities Department at least 24 hours prior to starting
construction (706-772-5503).
2. Installation of sanitary sewer pipe and associated appurtenances shall be in
accordance with current ASTM specifications and manufacturer's requirements for
the specific product. Loading or unloading and storage of pipe, fittings, valves, etc.
shall be done such that to avoid damage. All pipe shall be carefully examined before
it is installed in the trench. Damaged pipe or pipe which does not meet specification
requirements shall be rejected and removed from the work site. The interior of all
pipe, fittings, valves, etc. shall be kept free of dirt and foreign matter at all times. All
piping shall be placed in a dry trench with a stable bottom. Wet trench installation
shall be allowed only upon written approval of the Utilities Director.
TS-4-9
I
I
I"
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. Backfill shall be free of boulders and debris. Sharp or rocky material encountered
in the base shall be replaced with proper bedding. Pipe shall be laid on line and
grade as designed. Pipe joints, gravity blocks, service connections, and conflicts
shall be left exposed until visually inspected and approved by the Augusta Utilities
Department's Inspector.
4. All concrete cradles, saddles, or encasements shall be installed as shown on the plans.
These structures shall be constructed in strict accordance to the details shown on the
plans. Concrete shall have a 28 day compressive strength of3,000 psi when tested
in accordance with ASTM Specification C-39.
5. All manholes indicated on the plans shall be furnished and installed by the Contractor
in strict accordance with the plans. The invert channels shall be smooth and
accurately shaped to the semicircular bottom conforming to the inside ofthe adjacent
sewer sections as shown on the plans. Changes in direction of the sewer and entering
branches shall have as long a radius of the true curvature as the size of the manhole
will permit.
6. The top of manholes shall be topped out with brick as indicated on the plans. The
number of courses will depend on the required elevation ofthe top of the manhole.
The maximum number of brick courses allowed shall be three (3).
7 . New sewer lines shall be inspected through use of camera inspection equipment with
an Augusta Utilities Department Inspector at the time of installation and again before
the one-year warranty expires. The Developer is to provide the Augusta Utilities
Department with a color VHS system videotape of the inside of every reach of
sanitary sewer installed. The tape shall record manhole number to manhole number, ,
date of recording, and distance from start of run. The tape shall include a distance
and location description of every service line connection installed. The manhole
numbering system shall be the same as shown on the approved development plans.
B. Sewer Pipe Laying: The pipe shall be laid with bell or groove end upgrade. Pipe shall
be tested for soundness, clear interior and satisfactory joint surfaces before lowering the
pipe into the trench. Pipe shall be laid in straight lines and on uniform grades between
points where changes in alignment or grade are shown. The pipe barrel shall be
uniformly bedded. The line and invert grade of each pipe shall be checked from a top
line carried on batter boards not over 25 feet apart or by use of a laser beam target
inserted in each joint. Pipes shall be laid to form a smooth, uniform invert. A stopper
shall be installed in the pipe mouth when pipe laying is not in progress.
PVC gravity sewer pipe and force main shall be installed in accordance to ASTM D2321,
latest revision. Ductile iron force main shall be installed in accordance with A WW A
C600, latest revision.
C. Backfilling Around Pipe: As soon as the joint material has set, fine earth shall be
carefully tamped around each j oint, and around and over the pipe to a depth of at least
TS-4-10
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2 feet above the top of gravity pipelines. In addition, all PVC sewer pipe shall be bedded
in selected material from the pipe centerline down to a point 3 to 6 inches below the pipe
invert. Selected materials for this purpose shall be Class I or II soils as specified in
ASTM D2321.
D. Sewer Structures: Appurtenant sewer structures shall be constructed according to one
or more of the following methods:
1. Masonry: Brick for manholes and other sewer structures shall be laid with shove
joints completely filled with mortar. Horizontal joints shall not exceed Yz inch,
vertical joints 1/4 inch on their interior face. In circular structures, all brick shall be
laid as header with joints broken between courses. Interior joints shall be struck or
wiped smooth with the face of the wall. The exterior of sanitary sewer manholes
shall be plastered to a thickness of at least Y2 inch.
2. Laying Brick and Concrete Block Work: Only clean brick or block shall be used.
The brick or block shall be moistened by suitable means, as directed, until they are
neither so dry as to absorb water from the mortar, nor so wet as to be slippery when
laid.
Each brick or block shall be laid in a full bed and joint of mortar without repairing
subsequent grouting, flushing, or filling, and shall be thoroughly bonded as directed.
3. Plastering and Curing Brick or Block Masonry: Outside faces of masonry shall be
plastered with mortar from 1/4 inch to 3/8 inch thick. Ifrequired, the masonry shall
be properly moistened prior to application of the mortar. The plaster shall be
carefully spread and troweled so that all cracks are thoroughly worked out. After
hardening, the plaster shall be carefully checked by being tapped for bond and
soundness. Unbonded or unsound plaster shall be removed and replaced.
Masonry and plaster shall be protected from too rapid drying by the use of burlap
kept moist, or by other approved means, and shall be protected from the weather and
frost, all as required.
4. Manhole Inverts: Manhole flow channels shall be constructed of concrete, sewer
pipe, brick or precast, and shall be of semicircular section. Each manhole shall be
provided with such channels for all connecting sewers.
The inverts shall conform accurately to the size of the adjoining pipes. Side inverts
shall be curved and main inverts (where direction changes) shall be laid out in
smooth curves of the longest possible radius which is tangent to the centerlines of
adjoining sewers.
5. Drop Manholes: Drop inlets shall be provided into manholes on sanitary sewers for
incoming lines having inverts 2 feet or more above the inverts ofthe manhole outlet
lines. Drop pipe and fittings shall be encased in masonry integral with the manhole
TS-4-11
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
and extending from the manhole base to the top ofthe incoming sewer. Diameter of
drop manholes to be four feet at a minimum.
6. Setting Manhole Frames and Covers: Manhole frames shall be set with the tops
conforming accurately to the grade of the pavement or finished concentric with the
top ofthe masonry and in a full bed ofmortar so that the space between the top ofthe
manhole masonry and the bottom flange of the frame shall be completely filled and
made watertight. A thick ring of mortar extending to the outer edge of the masonry
shall be placed all around the bottom flange. The mortar shall be smoothly finished
to be flush with the top ofthe flange and have a slight slope to shed water away from
the frame. Manhole covers shall be left in place in the frames on completion of other
work at the manholes.
7. Setting Precast Manholes Sections: Precast-reinforced concrete manhole sections
shall be set so as to be vertical and with sections and steps in true alignment.
All holes in sections, used for their handling, shall be thoroughly plugged with
mortar. The mortar shall be 1 part cement to 1 Yz parts sand; mixed slightly damp to
the touch until it is dense and an excess of paste appears on the surface; and then
finished smooth and flush with adjoining surfaces.
E. Bulkheads and Flushing: The contractor shall build a tight bulkhead in the pipeline where
new work enters an existing sewer. The bulkhead shall remain in place until its removal
is authorized by the Engineer.
Care shall be taken to prevent earth, water and other materials from entering the pipe, and
when pipe laying operations are suspended, the Contractor shall maintain a suitable
stopper in the end of the pipe and also at openings for manholes. All sanitary sewer,
except building connections shall be flushed with water in sufficient volume to obtain
free flow through each line. All obstructions shall be removed and all defects corrected.
As soon as possible after the pipe and manholes are completed on any line, the
Contractor shall flush out the pipeline using a rubber ball ahead of the water. None of
the flushing water or debris shall be permitted to enter any existing sewer.
F. Temporary Plugs: At all times when pipe laying is not actually in progress, the open
ends of the pipe shall be closed by temporary watertight plugs or by other approved
means. If water is in the trench when work is resumed, the plug shall not be removed
until all danger of water entering the pipe has passed.
G. Joints and Structure Rightness: All pipe joints shall be made as nearly watertight as
practicable. There shall be no visible leakage at the joints and there shall be no sand, silt,
clay, or soil of any description entering the pipelines at the joints.
Leaks in the pipelines which cause infiltration or exfiltration to exceed limits herein
specified shall be repaired by replacing defective pipe. Grouting and/or caulking to
repair pipelines where excessive infiltration or exfiltration is evident will not be
permitted.
TS-4-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
H. Fittings and Stoppers: Branches and fittings shall be laid by the Contractor as indicated
on the drawings and/or as directed by the Engineer. Open ends of pipe and branches
shall be closed with premolded gasket joint stoppers which conform with the same
requirements as pipe being used.
1. Sewer Line Relation to Water Lines: Sewer lines and sewer force mains in relation to
water lines shall conform to "Ten States Standard" Section 29.3 at a minimum. Sewer
lines shall have at least a 10 foot pipe-to-pipe horizontal separation from known or
proposed water mains. When a sewer crosses under a water main, there shall be at least
18 inches from the crown of the sewer line to the bottom of the water main.
In all cases where adequate vertical separation as stated above cannot be achieved (or
whenever sewer lines must be installed to cross above a water main), both the water and
sewer lines shall be constructed of ductile iron pipe a distance of 10 feet on each side of
their intersection with one full length of water main centered on the sewer line.
J. Minimum Cover for Sewer Lines: Gravity sewer lines shall have a minimum of 3 feet
of cover at the crown of the pipe. In cases where this minimum cover cannot be
achieved, ductile iron pipe shall be used.
K. Detectable Tape: Detectable tape as manufactured by Reef Industries of Houston, Texas,
or equal shall be installed during the backfill operation at a point 1 foot below the final
finished grade.
The detectable tape shall be a 5.5 mil composition film containing one layer of me tali zed
foil laminate between two layers of inert plastic film specifically formulated for
prolonged use underground. The tape shall be highly resistant to alkalis, acids and other
destructive agents found in the soils.
The detectable tape shall bear a continuous printed message "Caution Sanitary Sewer
Line Buried Below." The message shall be printed in permanent ink formulated for
prolonged use underground. Letters shall be clearly legible and have a minimum height
of 1.2 inches.
L. Boring and Jacking: Where required by the drawings, the sanitary sewer line will be
installed in a steel casing, placed by boring and jacking.
Where boring is required under highways, the materials and workmanship will be in
accordance with the standards of the State Highway Department or local authority.
Boring and jacking under railroads will be governed by the latest A.R.E.A. Standards,
Part 5, "Pipelines" and those of the railroad involved.
1. Casing Pipe: The casing pipe shall conform to the materials standards of ASTM
Designation A252, with minimum wall thickness of 0.219 inch. Steel pipe will have
TS-4-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
a minimum yield strength of35,000 psi. Casing pipe shall be joined together with
welded joints.
2. Carrier Pipe: The carrier pipe shall be ductile iron as specified herein.
3. Installation: The steel casing shall be installed by the "Dry Bore and Jack" method.
Ifvoids develop or if the bored hole diameter is greater than the outside diameter of
pipe by more than approximately 1 inch, remedial measures will be taken as
approved by the Engineer.
When installing water lines through casing, the Contractor shall mechanical joint
pipe with retainer glands throughout the length ofthe casing. The sanitary sewer line
shall be strapped to treated wooden skids with metal straps throughout the length of
the casing. The empty space shall then be filled with sand and the ends ofthe casing
shall be sealed with brick and mortar.
M. Force Main Installation: In general, sewer force main must be installed in accordance
with the water distribution system specifications.
Polyvinyl chloride (PVC) force main must conform to ASTM D-2241, latest revision.
Ductile iron force main must conform to ASTM A-377, latest revision.
N. Removal and Replacement of Existing Pipe and Equipment: Where indicated on the
drawings or required to properly place the work under this contract, as approved by the
Engineer, the Contractor shall remove and replace such pipe lines and equipment in a
manner as approved by the Engineer.
-05. INSPECTION INFILTRATION/EXFILTRATION LEAKAGE TESTS
Upon completion of a section of the sewer, the Contractor shall dewater it and conduct
a satisfactory test to measure the infiltration or ex filtration for at least three consecutive days. The
amount of infiltration including "Y" branches, and connections shall not exceed 1 00 gallons per inch
diameter per mile of sewer pipe per 24 hours for gravity sewer pipe. The amount of 50 gallons per
inch diameter per mile of sewer per 24 hours shall not be exceeded for ductile iron pipe. The
Contractor shall be responsible for the satisfactory watertightness of the entire section of sewer.
As required, suitable bulkheads shall be installed to permit the test of the sewer. Where
the ground water level is less than 1 foot above the top of the pipe at its upper end, or as directed by
the Engineer, the sewer shall be subjected to ex filtration testing by plugging the pipe at the lower end
and then filling the pipelines and manholes with clean water to a height 4 feet above the top ofthe
sewer at its upper end. The leakage out of the sewer, measured by the volume of the water
necessary to maintain meter level in the highest manhole, shall not exceed 200 gallons per inch
diameter per 24 hours per mile of sewer for gravity sewer pipe. The amount of 50 gallons per inch
diameter per 24 hours per mile of sewer shall not be exceeded for ductile iron pipe.
TS-4-14
I
I.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The sewer shall be tested before any connections are made to buildings or to active
sewers.
The Contractor shall construct such weirs and bulkheads as may be required, shall furnish
all water, labor, test plugs, power, pumps, meters, and other equipment necessary for the test to be
properly made.
The Contractor may use a low pressure . air test as an option to the hydraulic
infiltration/exfiltration leakage test for gravity lines provided the Contractor established a correlation
between the air test results and the quantity of infiltration/ex filtration actually being experienced by
the line and the allowable air pressure drop shall be that corresponding to the allowable hydraulic
leakage specified previously in this section. Such a correlation is to be established according to a
procedure satisfactory to the Engineer. The low pressure air test shall be performed in accordance
with the applicable sections of ASTM C828, latest revision.
Ifthe Contractor opts to use the low pressure air test, leakage tests on manholes shall be
conducted independently ofthe lines by using a hydraulic infiltration/exfiltration test as directed by
the Engineer. The allowable infiltration into the manhole over a 24 hour period is zero and the
allowable exfiltration is also zero when tested by plugging offthe manhole and filling it with water
four feet above the top of the sewer and measuring the water loss over a 24 hour period.
-06. MEASUREMENT AND PAYMENT:
Payment will be made at the unit contract prices as shown in the bid schedule under
Sanitary Sewer.
TS-4-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-5
WATER DISTRIBUTION SYSTEMS
-01.
BASIS FOR DESIGN:
Design shall conform to the requirements as set forth in "Minimum Standards for
Public Water" (latest revision) as published by the Georgia Environmental Protection Division
(www.dnr.state.ga.us/dnr). A Professional Engineerregistered in the State of Georgia must prepare
the plans and specifications.
There shall be no physical connection between a potable water supply and a
questionable water supply which would allow unsafe (contaminated) water to enter the potable water
system by direct pressure, vacuum, gravity or any other means.
Hydraulic designs shall be based upon pressure data applicable to the portion of the
service area, which will serve the proposed facility. Air release valves in vaults shall be provided
at all high points in the water main as required by the Utilities Director.
All water distribution systems shall be looped to the greatest extent possible. Water
mains shall have a minimum nominal inside diameter of 6 inches. Water mains having an inside
diameter of less than 6 inches will not normally be considered.
During construction when deviations from approved plans are desired, the Augusta
Utilities Department's Inspector shall be notified. Revised plans shall be submitted as soon as
possible to the Augusta Utilities Department for approval. Minor changes not affecting capacities,
flows or operation may be allowed in the field during construction by the Utilities Department's
Inspector. The Inspector shall have final authority as to what constitutes a minor or major change.
An approved set of Record Drawings clearly showing any changes shall be submitted to the Augusta
Utilities Department Inspector at the completion of the work and prior to sign-off of the final plat.
The Contractor/Developer is responsible for verifying the exact location, size and
material of any existing water facility proposed for connection or use by the project.
-02.
DESIGN STANDARDS FOR WATER MAINS:
A.
COVER
1. Standard depth of cover is 4 feet below existing and proposed road surface
unless otherwise approved by the Augusta Utilities Department.
2. Minimum cover to finished grade over water mains shall be 36 inches.
Minimum cover under ditch bottoms shall be 24 inches. These must be
approved by the Augusta Utilities Department on a case-by-case basis.
TS-5-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
B.
HORIZONTAL SEP A...~TION
1. Ten (10) feet to any existing or proposed sanitary sewer/force main, storm
sewer or sewer manhole (less than 10 feet requires pipe material to be Ductile
Iron Pipe (DIP) for both Water Main and Sewer/Force Main).
2. Fifteen (15) feet to buildings, top of bank of lakes/streams/creeks, other
structures (10 feet absolute minimum - only when unavoidable, and pipe
material is required to be DIP).
3. Ten (10) feet minimum separation to gas mains.
4. Ten (10) feet minimum to underground electric cable.
5. Current Georgia EPD separation requirements.
6. All separation distances above are edge to edge.
C.
VERTICAL SEPARATION
1. Water main shall cross over other pipes.
2. Eighteen (18) inch minimum separation (edge to edge) between all pipes and
cables shall be maintained (6 inch absolute minimum separation with DIP)
when conforming to Georgia EPD separation requirements.
3. When water mains cross under sewers, additional measures shall be taken.
At least 18 inches of separation between the bottom of the sewer and the top
of the water main shall be provided. Adequate structural support for the
sewer to prevent deflection or settling on the water main. The joint of water
pipe shall be centered at the crossing. Encasement of the water pipe in
concrete shall also be considered.
D.
LAYOUT
1. Normal location of proposed water lines is on the north side of east-west
streets, and the east side of north-south streets.
2. For existing County roads, the proposed water line will generally be located
five (5) feet inside the right-of-way. For existing State roads, the proposed
water line must be located five (5) feet inside the right-of-way. Unusual
circumstances may warrant deviation. The location of the water line will be
determined, also, by the location of the existing lines to be tied into at the
beginning and end of the project.
3. For subdivisions, the proposed water line shall be located four (4) feet from
the back of the curb.
TS-5-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4. Wherever possible, avoid laying water line on the same side ofthe road as the
gas lines.
5. Water service lines for residential development shall be located at the center
of lot.
6. Dead ends shall be minimized by making appropriate tie-ins whenever
practical. Permanent dead ends will not be accepted unless unavoidable.
Dead ends shall be equipped with a fire hydrant. If, under special
circumstances, where water lines smaller than six (6) inches in diameter are
accepted, an approved blowoff shall be required for flushing purposes. A
minimum of two 22-1/2-degree bends shall be required on 6inch and larger
water lines in cul-de-sacs and shall be shown as such on plans.
7. All water mains shall be placed in right-of-way areas or dedicated easements.
All easements shall allow adequate area to construct and maintain the water
line and appurtenances involved. Permanent easements shall be a minimum
of 15 feet wide with line installed in center of easement. Permanent
easements shall be provided as needed to serve adjacent property, even ifthe
water line is not installed at that time. If the line has not been installed to
future serve adjacent property, a larger easement than the minimum may be
required to construct future line. Easement agreements shall be specific to
state that no permanent structures may be constructed within the limits of
permanent easements.
E.
WATER MAIN MATERIAL
1. Water mains shall be either ductile iron pipe (DIP), polyvinyl chloride (PVC),
or galvanized pipe as outlined below.
2. DIP shall be centrifugally cast and shall conform to AWWA C150/ANSI
A21.50 for design and A WW A C 151/ ANSI A21.51 for manufacture. PVC
pipe 6 inch to 12 inch diameter shall conform to A WW A C900. PVC pipe
14 inch to 36 inch diameter shall conform to A WW A C905.
3. For water mains 6 inch through 16 inch, DIP Pressure Class 350 shall be
allowed. For water mains 18 inch through 24 inch, DIP Pressure Class 300
shall be allowed. PVC C900 (most current date), Class 200, SDR-14 with
cast iron equivalent O.D.s, gasket bell end with elastomeric gaskets shall be
allowed for water mains 6 inch through 10 inch (solvent weld joints are not
permitted). Galvanized pipe shall be seamless, American made, Schedule 80
and shall conform with the ASTM Specifications. Flanged DIP shall have
threaded ductile iron flanges and shall conform to the requirements of
AWWA C115. All flanges shall be Ductile Iron Class 150, ANSI B16.5.
Flanges shall be flat faced and all joints shall use 1/8 inch black neoprene
full-faced gaskets. .
TS-5-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4.
Ductile iron pipe and fittings shall have bituminous coating outside and shall
be cement lined in accordance with A WW A C104/ANSI A21.4. DIP shall
have 1/16 inch cement mortar lining with rubber gasket push-on joints or
mechanical joints. Mechanical joint glands shall be ductile iron. Tee bolts
and nuts shall be Cor-Ten steel. Rubber gasket joints shall conform to
A WW A C 111 / ANSI A21.11, and shall be furnished by the pipe manufacturer
with the pipe. A non-toxic vegetable soap lubricant shall be supplied with
the pipe in sufficient quantities for installing the pipe. The lubricant shall be
approved by NSF for use with potable water mains.
5.
Pipe classes designated previously in this standard are minimum allowed.
Actual pipe class shall be determined based upon the installation and the use
intended. Pipe shall be appropriately labeled on the drawings. All PVC pipe
for potable water service shall bear the approved stamp of the National
Sanitation Foundation. Copper wire (12 gauge, bare single strand) shall be
attached along the top of all buried PVC water lines, wrapped around service
corporations and stubbed up into all valves boxes for locating purposes.
6.
DIP shall be required in the following circumstances:
a. Within 10 feet of sanitary and storm pipes.
b. Within 15 feet of structures (near side of concrete footing), or top of
bank of lakes/streams/creeks.
c. Crossings over or under sewers, gas and storm pipes with less than 18
inches separation, with no joint allowed within 10 feet of crossing.
d. Beneath all paved areas, excluding driveways or sidewalks.
e. Within project boundaries of subdivisions with private roads where
the Utilities Department will take over the line for operations and
maintenance.
f. Along all state right-of-ways.
7.
The Utilities Director may mandate DIP in any instances of off-site or on-site
construction where future abuse to the line is possible due to location or
circumstances.
8.
Restrained Joints shall be DIP as follows:
a. For 12-inch and Smaller - Restrained joint shall be U.S. Pipe Field
Lok, American Ductile Iron Pipe Lok- Fast, EBAA Iron Mega-Lug, or
an equivalent product.
TS-5-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
b. For 14- inch Diameter and Larger - Restrained j oint shall be U. S. Pipe
TR Flex, American Ductile Iron Pipe Lok-Ring, or equivalent
product.
c. If inserting in older cast iron pipe, the restrained joint shall be as
approved by the Augusta Utilities Department.
d. Retainer Glands/Mega-Lug shall not be considered a fitting.
e. The restraint method shall be suitable for the pipe size thickness and
test pressure as required for the specified design case. The plans shall
indicate the restrained length of pipe each side of the fittings.
9.
Jack and Bore Installations:
a. Casing pipe used with jack and bore shall be in accordance with
requirements of the Georgia Department of Transportation (GDOT)
or railway specifications and Section 13C Excavation & Backfilling
of these specifications. Carrier pipe shall be restrained joint DIP as
outlined in paragraph -02.E.8.
b. Directional Bore Installations: Directional bores will be considered
as a viable alternative to jack and bore installation under Augusta-
Richmond County roadways. The Utilities Director will review each
case for materials and construction methods.
c. Mains may be tapped as long as the tapping line is smaller than the
tapped line unless otherwise approved by the Augusta Utilities
Department. See Section -02.J. for service tap requirements. Equal
size line connections approved by the Augusta Utilities Department
shall require that a tee be cut into the main where possible. Tees are
also required at locations dictated by the Utilities Director. Tapped
connections in pipe and fittings shall be made in such a manner as to
provide a watertight joint and adequate strength against pull-out.
Tapping Sleeves and Valve shall be ductile iron, mechanical joint.
Tapping sleeves and valves are required for all taps 4 inches and
greater. Taps less than 4 inches shall be provided with a service
saddle meeting the requirements of Section -02.1. Valves shall be
provided on all taps. Tapping sleeves shall be a minimum of 6 feet
from pipe joints.
d. . Schedule 40 PVC shall only be used as sleeves for the installation of
service line tubing under all pavement areas. Use in the water
distribution system or other areas are not acceptable.
TS-5-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
e. Unspecified transitions from DIP to PVC are not allowed. Material
for transition shall be indicated and specified and must be approved
by the Augusta Utilities Department.
f. All construction material shall be first quality, not previously used.
Repair clamps are not acceptable. Damaged or faulty pipe and
materials must be properly replaced. All gaskets shall ~e new. When
c'onnecting to existing valves or fittings, gaskets shall be replaced, not
reused.
g. The Engineer shall provide a complete set of shop drawings, which
shall indicate the Augusta Utilities Department's specific material
requirements. In general, material requirements will be guided by the
latest revisions of the specifications of A WW A, ANSI, ASTM, and
NSF.
F.
WATER MAIN SIZE
1. The minimum size of water main shall be 6 inches unless otherwise approved
by the Utilities Director. However, a professional engineer shall justify the
size of the pipes with a hydraulic network analysis.
2. The new water main shall have the ability to meet maximum daily demands
plus fire flow requirements as mandated by Georgia EPD "Minimum
Standards for Public Water Systems" (latest revision) and the Augusta Fire
Marshal. The residual design pressure under all conditions shall not be less
than 20 psi.
G.
VALVES, FITTINGS AND APPURTENANCES
1. Valving of all water distribution systems shall be designed to facilitate the
isolation of each section of pipeline between intersections of the network.
Generally, the number of valves at an intersection shall be one less than the
number of pipes forming the intersection. Gate valves, 4 inches to 12 inches,
shall be the resilient seat type conforming to A WW A C509 (latest revision).
Valves larger than 12 inches shall be gear operated butterfly valves,
conforming to A WW A C504 (latest revision). Wafer valves shall not be
accepted. Valves shall generally be installed at intervals of not more than
2,000 LF on transmission mains and on all primary branches connected to
these mains. Where possible, a valve shall be installed next to a fire hydrant
for locating purposes. In high density areas (25 dwelling units), valves shall
be installed as necessary to minimize the number of persons affected by a
water main break.
2. The Utilities Director shall determine which mains are distribution or
transmission.
TS-5-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. Valves shall OPEN LEFT if installed south of Gordon Highway (SR 10), or
OPEN RIGHT if installed north of Gordon Highway. Valves shall be
provided with valve stem extensions to within 6 inches of ground surface,
where centerline of pipe to grade is greater than 4 feet.
4. Valve boxes shall be M&H E-2702, Mueller H10364 or approved equal.
Each valve box shall be slip-type to adjust for a minimum cover of 36 inch
bury. The flanged base of the valve box shall be at least six (6) inches above
the pipe so not to stress water lines 4 inches and smaller. Extension pieces
will be required for additional depth over valves. Extensions shall be M&H
E-3120 or Mueller H-10375. Covers shall have "WATER" cast on top.
5. All valves, bends, tees, crosses and dead ends shall be restrained by a
mechanical restraint systems as outlined in Paragraph 13.5.3., or by use of a
concrete thrust block in those instances that warrant such an installation.
Thrust blocks shall be poured-in-place concrete having a minimum
compressive strength of3,OOO psi after 28 days of cure time. Calculations for
restrained joints shall be provided by the design engineer. Soil bearing value
shall be 2,000 psfmaximum. Lower values shall be used when soil is poor
quality. All materials, fittings and appurtenances intended for use in pressure
pipe systems shall be designed and constructed for a minimum working
pressure of 150 psi unless the specific application dictates a higher working
pressure requirement.
6. Standard pressure pipe fittings of size four (4) inch ill and larger shall be
ductile iron conforming to AWWA Cll0, with mechanical joints unless
flanged or restrained joints are required. Gray cast-iron fittings are not
allowed. Ductile iron fittings shall be cement lined in accordance with
A WW A C 1 04. Mechanical joint fittings, 24 inches and smaller shall be rated
for 350 psi working pressure. Flanged joint fittings 24 inches and smaller
shall be rated for 250 psi working pressure. All fittings 30 inches and larger
shall be rated for 250 psi working pressure. For sizes less than four (4) inch
ill, fittings shall be suitable to the pipe material and application. Glands for
mechanical joint fittings shall be ductile iron, and tee bolts and nuts shall be
Cor- Ten steel. Only bolt systems furnished by the manufacturer for
mechanical joints are acceptable; nuts and bolts shall be new, not reused.
Pipe gaskets shall be new as supplied by the pipe manufacturer. All flanges
shall be ductile iron Class 150, ANSI B16.5. All flanges shall be flat faced.
Full face, 1/8 inch black neoprene gaskets shall be used on all flanged joints.
All joints shall conform to A WW A Clll. Bolts, nuts and washers for
flanges shall be hot dip galvanized, except T -bolts shall be Cor-Ten steel.
H.
List of Specifications:
ANSI/A WW A C151/A21.51-96 4-FEB-1996
American National Standard for Ductile-Iron Pipe, Centrifugally Cast, for
TS-5-7
I
I
I
I
'I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Water
ANSI/A WW A C150/A21.50-96 1996
American National Standard for Thickness Design of Ductile-Iron Pipe
ANSI/AWWA C115/A21.15-94 1994
American National Standard for Flanged Ductile-Iron Pipe With Threaded
Flanges
ANSI/AWWA Cll1/A21.11-95 1995
American National Standard for Rubber-Gasket Joints for Ductile-Iron
Pressure Pipe and Fittings
ANSI/AWWA Cll0-98 1998
American National Standard for Ductile-Iron and Gray-Iron Fittings, 3 in.
through 48 in. (75 mm through 1200 mm), for Water and Other Liquids
ANSI/A WW A C104/A21.4-95 1995
American National Standard for Cement-Mortar Lining for Ductile- Iron Pipe
and Fittings for Water
1.
FIRE HYDRANTS
1. Fire hydrants shall be provided in all water mains, transmission and
distribution systems. Accepted models are Mueller #A-24018 or M&H
Figure 29T AWWA Compression Type-Dry Top-Traffic Model 150 psi
working pressure, 300 psi testing pressure. All fire hydrants shall be ordered
safety yellow body with white bonnet and caps. Fire hydrants shall be spaced
such that the radius of protection will not be more than 500 feet. In certain
areas, closer spacing may be required by the Fire Marshal.
2. Each hydrant shall be left turn opening and capable of delivering a flow of at
least 500 gallons per minute with a residual design pressure of not less than
20 psi, or a higher flow as required by the Fire Marshal. Multiple fire
hydrants with looped mains and/or larger main sizes may be required to
provide water for higher flow demand. Flow tests shall be performed to
verify the specified fire flow demand.
3. Fire hydrants shall be of the dry barrel break-away type conforming to
A WW A C502 (latest revision), with two 2Y2 inches threaded hose nozzles
and one 4Y2 inch threaded pumper nozzle. Hose and pumper nozzle threading
shall be national standard. Show connection shall be 6- inch mechanical joint.
The center line of the nozzles shall be 18 inches above the finish grade.
Hydrants shall have a 5~ inch interior valve opening and be restrained from
hydrant to tee at the main. At the discretion of the Utilities Director,
additional protection for fire hydrants shall be provided including but not
limited to concrete filled ductile iron traffic posts.
TS-5-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
4. Fire hydrant branches (from main to hydrant) shall be a minimum of 6 inches
ID. Each branch shall be provided with a resilient seat gate valve located as
close as possible to the main. Hydrants shall be located at or near road right-
of-way lines with pumper nozzle pointing toward the road. A clear zone
around all fire hydrants shall be adhered to, consisting of a 5 foot radius
around the hydrant and 7 feet above the top of the hydrant. Maintain 15 feet
minimum from hydrant to all structures. Placement oflandscaping, fencing,
etc. shall be considered in order to meet this clear zone requirement.
5. List of Specifications:
ANSI/AWWA C500-93 1993
Metal-Seated Gate Valves for Water Supply Service (includes
addendum C500a-95
ANSI! A WW A C502-94 1994
Dry-Barrel Fire Hydrants (includes addendum C502a-95)
ANSI! A WW A C503-97 1997
Wet-Barrel Fire Hydrants
ANSI!AWWA C504-94 1994
Rubber-Sealed Butterfly Valves
ANSI!AWWA C507-99 1-DEC-1999
Ball Valves 6 in. through 48 in. (150 mm through 1200 mm)
ANSI!AWWA C508-93 1993
Swing-Check Valves for Waterworks Service, 2 in. (50mm)
Through 24 in. (600mm) NPS (includes addendum C508a-93
ANSI! A WW A C509-94 1994
Resilient-Seated Gate Valves for Water-Supply Service (includes
addendum C509a-95)
ANSI!AWWA C550-90 1990
Protective Epoxy Interior Coating for Valves and Hydrants
J.
WATER SERVICE LINES AND TAPS
1. Tapping sleeves and tapping crosses shall be of a heavy body ductile iron,
mechanical joint suitable for a working pressure of 200 psi, as approved by
the Augusta Utilities Department.
. 2. No direct service taps shall be allowed. All service line taps shall be
supplied with corporation stops. Service line tubing shall be rolled of soft
TS-5-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
continuous and seamless copper Type K conforming to A WW A C800 and
ASTM B-88.
3. Corporation Stops and Main Connectors:
%inch FB600 - 3 Ford or Equal
linch FB600 - 4 Ford or Equal
Taper Thread Inlet by Flare Copper Outlet
Eighth Bends:
%inch LA02 - 33 Flare 1/8 Bend
%inch LA04 - 33 Compression 1/8 Bend
1 inch LA02 - 44 Flare 1/8 Bend
1 inch LA04 - 44 Compression 1/8 Bend
4. Minimum size for residential use shall be one (1) inch. The service line shall
be laid in a straight line and be of a continuous piece of pipe from corporation
to curb cock. The curb cock shall be located 6 inches behind and 8 inches
below the top of new curb or edge of asphalt. Where service connects to DIP
or any pressure-rated pipe, service saddles must be used. Brass double strap
tapping saddles shall be used. U-bolt type straps are not acceptable. All
water service taps on the main shall be spaced at a minimum distance of 18
inches apart and a minimum of 18 inches from a bell or fitting. If two or
more taps are required at a minimum spacing, they shall be offset 450
alternatively. Services greater than one (1) inch shall be seamless galvanized.
2 inch services shall have two 2 inch 90-degree galvanized elbows per
Augusta Utilities' 2 Inch Water Service detail.
5. Services shall not exceed over 100 feet from the main to the meter. Where
possible, meter shall be placed in unpaved area as close to the water main as
possible.
K.
METER INSTALLATION
1. The Contractor/Developer shall furnish and install an approved meter box at
the termination point of all water services, and maintain until such time as a
meter is installed. Meters will be installed by Augusta Utilities Department
at the time services is required at the stub-out. Each unit within a residential
building (i.e., duplex, triplex, etc.) shall have a separate meter, unless prior
approval is received by the Utilities Director. The proper sizing of service
lines is the responsibility ofthe design engineer. Meters will be available in
the following sizes only: 5/8 x 3/4, 1, 1 Y2., 2, 3, 4-inch, and larger standard
sizes as necessary. Meter boxes for 1 Y2 inch and smaller meters are standard.
2 inch and larger shall be installed in a meter vault. The Augusta Utilities
. Department reserves the right to request historical data for meter sizing.
TS-5-10
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2. Meter boxes shall be Rome type, 10 inch x 19 inch x 10 inch cast iron box
and lid. The top shall have cast ribs on the bottom side with four (4) legs to
prevent sliding movement. The box shall have a minimum weight of3 7Ibs.,
for meters 1 Y2 inch or smaller. Meter and curb stop shall be fully encased by
the meter box. Meter vaults (for meters 2 inch and larger) shall be fabricated
of masonry block or pre-cast reinforced concrete using 3,000 psi concrete and
#4 rebar. The access hatch shall be made of heavy duty aluminum, and shall
be hinged and lockable. The hatch shall be large enough for removal of the
meter but no smaller than 48 inches x 36 inches. Wall dimensions shall
allow 2 feet of working clearance. Vault floors shall be no less than 4 inches
thick with 3,000 psi concrete and #4 rebar, with the meter located no less than
18 inches off the floor.
3. The Augusta Utilities Department assumes no responsibility for undersized
meters and problems associated with it. All meters will be provided and
installed by the Augusta Utilities Department. The meters remain the
property of the Augusta Utilities Department.
4. Meters should generally be placed 18 inches inside the adjacent utility
easement that parallels the right-of-way. Where sidewalk, two feet of
clearance is required between the customer's side of the sidewalk edge and
the meter box. In developments where the property line is not clearly defined
(e.g., condominiums) the meter should be placed for ready access as approved
by the Augusta Utilities Department. Meter and control valves shall be
accessible and unobstructed for 4 feet in all directions. This shall include but
not be limited to transformers, telephone junction boxes, walls, trees, etc.
Meters shall not be placed in areas that can be fenced, such as backyard.
Meter boxes shall not be placed in any asphalt or concrete surfaced areas
(sidewalks, driveways, curbs, etc.) unless approved in writing by Augusta
Utilities. For shopping centers, the developer's engineer should give special
consideration to meter layout so as to satisfy these requirements. When no
alternative is available but to locate in asphalt, the top of box shall be flush
with the asphalt surface. Meters shall not be located in low areas that
normally receive storm water. The box shall also be located outside of
parking stalls. The box and lid should be traffic bearing, but located outside
of a commonly trafficked area.
L.
BACKFLOW PREVENTION DEVICES
1. Backflow prevention devices shall be provided, as required by the Utilities
Director and as set forth in these Standards. All irrigation systems, water
services and fire lines for industrial/office/commercial, schools, mobile home
parks, multi-family residences and any other locations as determined by the
Utilities Director shall require suitable backflow prevention assemblies on the
customer side of service lines (domestic, irrigation, and fire). Backflow
." . devices shall be tested by a certified person and the results furnished to the
TS-5-11
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
M.
Augusta Utilities Department prior to any water use. Residential
development shall install a "Dual Check" Backflow Device on the customer's
side of service line at the point of tie-in to the water meter. The plumber or
builder tying service into the set meter will submit the test results for the
backflow prevention device to the Augusta Utilities Department's Inspector
prior to acceptance and any water use.
2. Backflow prevention device assemblies shall be the latest approved product
of a manufacturer regularly engaged in the production ofthis type equipment.
All assemblies shall be as approved by the America Society of Sanitary
Engineering (ASSE), The American National Standards Institute (ANSI), The
American Water Works Association (AWWA), Foundation for Cross
Connection Control and Hydraulic Research of the University of Southern
California, and the Georgia State Plumbing Code.
3. Type and size of assemblies shall be indicated on the drawings.
4. Backflow prevention device ownership and maintenance responsibilities shall
be as set forth in the appropriate ordinances. The Owner shall document
yearly that the backflow prevention device has been tested annually by a
qualified technician. A copy of the technician's certification must be
attached to the test results and submitted to the Augusta Utilities Director.
Engineer must comply with the Augusta Utilities Department Policies and
Procedures for Backflow Prevention by Containment (latest version). A copy
of this manual is available upon request.
5. List of Specifications:
ANSI! A WW A C51 0-97 1997
Double Check Valve Backflow-Prevention Assembly
ANSI!A WW A C511-97 1997
Reduced-Pressure Principle Backflow-Prevention Assembly
SYSTEM PRESSURES
1. The design engineer shall not assume a pressure greater than 35 psi at the
meter of detector check valve without confirmation from the Augusta
Utilities Department. The design engineer, ifpossible, should field verify the
available pressures prior to finalizing their design. The Augusta Utilities
Department does not guarantee or warrant any pressure or flow above what
the system can furnish. Augusta Utilities reserves the right to limit water
usage for irrigation in the event of drought, or requirement by the Georgia
EPD.
TS-5-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-03.
N.
FIRE LINES
1. All fire lines shall have a detector check valve with a 5/8 inch bypass meter
(to detect low flows) within the right-of-way or dedicated easement. No
exceptions to the bypass meter requirement shall be made regardless of
sprinkler system type, configuration, etc.
CONSTRUCTION:
A.
WATER DISTRIBUTION SYSTEM INSTALLATION
1. Authorization must be obtained from the Augusta Utilities Department to
construct, alter or modify a water line. Construction of water infrastructure
will be authorized by the Utilities Department upon approval of submitted
plans and notification of the Augusta Utilities Department at least 24 hours
prior to starting construction (706-772-5503).
2. Installation of water mains and associated appurtenances shall be in
accordance with current A WW A specifications and manufacturer's
requirements for the specific product. Loading or unloading and storage of
pipe, fittings, valves, etc. shall be done such that to avoid damage. The
interior of all pipe, fittings, valves, etc. shall be kept free of dirt and foreign
matter at all times. All piping shall be placed in a dry trench with a stable
bottom. Wet trench installation shall be allowed only upon written approval
of the Utilities Director.
3. Mechanical restraint systems shall be required at each fitting involving a
change of direction and as specified in the approved plans. Concrete thrust
blocks will be allowed in lieu of mechanical restraint systems.
4. Backfill shall be free of boulders and debris. Sharp or rocky material
encountered in the base shall be replaced with proper bedding. Pipe shall be
laid on line and grade as designed. Pipe joints, gravity blocks, service
connections, and conflicts shall be left exposed until visually inspected and
approved by the Augusta Utilities Department's Inspector.
5. Fire hydrants shall be installed true and plumb with the center ofthe pumper
nozzle facing toward the road. Hydrants shall not be placed in the sidewalk.
The engineer will be responsible for moving hydrants placed in sidewalks.
6. All valves shall be placed according to plans. Valve stems shall be installed
plumb. Valve stem extensions are required as-described in Section -02.G.
Air relief valves shall be installed at all high points in the water main where
air can collect, as shown on the plans or as directed by Augusta Utilities.
TS-5-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
7.
List of Specifications:
ANSI! A WW A C600-93 1993
Installation of Ductile-Iron Water Mains and Their Appurtenances
ANSI!AWWA C605-94 30-JAN-1994
Underground Installation of Polyvinyl Chloride (PVC) Pressure Pipe
and Fittings for Water
ANSI!AWWA C512-92 1992
Air Release, AirN acuum and Combination Air Valves for Water
Works Service
8.
Handling and Storing of Materials: Unload pipe so as to avoid deformation
or other injury thereto. Place no pipe within pipe of a larger size. Store pipe
and fittings on sills above storm drainage level and deliver for laying after the
trench is excavated. Valves shall be drained and so stored as to protect them
from freezing.
9.
Pipe Laying (General): The interior of the pipe shall be clean and joint
surfaces wiped clean and dry when the pipe is lowered into trench. Lower
each pipe, fitting and valve into the trench carefully and lay true to line and
without objectionable breaks in grade. The depth of cover below finished
grade shall be not less than 3 feet, or as shown on the drawings. Give all
pipes a uniform bearing on the trench bottom. Allow no trench water or dirt
to enter the pipe after laying. Insert a watertight plug in the open end of the
piping when pipe laying is not in progress.
10.
Boring and Jacking: Where required by the drawings, the water line will be
installed in a steel casing, placed by boring and jacking. Where boring is
required under highways, the materials and workmanship will be in
accordance with the standards of the State Highway Department or local
authority. Boring and jacking under railroads will be governed by the latest
A.R.E.A. Standards, Part 5, "Pipelines" and those of the railroad involved.
a. Casing Pipe: The casing pipe shall conform to the materials standard
of ASTM Designation A252, with minimum wall thickness of 0.219
inch. Steel pipe will have a minimum yield strength of 35,000 psi.
Casing pipe shall be joined together with welded joints.
b. Carrier Pipe: The carrier pipe shall be ductile iron as specified
herein.
c. Installation: The steel casing shall be installed by the "Dry Bore and
Jack" method. If voids develop or if the bored hole diameter is
greater than the outside diameter of the pipe by more than
TS-5-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
11.
approximately 1 inch, remedial measures will be taken as approved
by the Engineer.
When installing water line through casing, Contractor shall use
mechanical joint pipe with retained glands through length of casing.
The water main shall be strapped to 8 foot long treated wooden skids
with metal straps throughout length of casing. The ends ofthe casing
shall be sealed with brick and mortar.
Reaction Blocking: All plugs, caps, tees, bends and other fittings shall be
provided with adequate reaction blocking as shown on the drawings.
Reaction blocking shall be made to bear directly against the undisturbed
trench wall. Where trench conditions are, in the opinion of the Engineer,
unsuitable for reaction blocking, the Contractor shall provide tied joints to
adequately anchor the piping as shown on the drawings. All the rods and
clamps shall be given a bituminous protective coating.
12.
Pressure and Leakage Testing: Before any work will be accepted for
payment, the Contractor will fill the piping with water, open outlet as
necessary for expelling the entrapped air. No fire hydrant shall be opened full
force during charging operations. Thereafter, furnish the necessary
equipment and test the piping under the supervision of the Engineer for a
period of at least 2 hours at not less than 1.25 times the design pressure in
pounds per square inch, based upon the highest elevation of the section under
test. Pressure testing shall be in accordance with A WW A Standard C600,
Section 4.1. at 1.5 times the working pressure at the point oftesting. Inspect
all joints, and remedy to the satisfaction of the Engineer any defects
discovered. Continue the test until all visible leaks have been eliminated
from the part ofthe system under test, and the pressure remains constant with
a maximum pressure drop of 5 psi for the duration of the test.
Immediately following the pressure test, and before any work will be
accepted for payment, the Contractor shall perform a leakage test. . Leakage
is defined as the quantity of water to be supplied into the newly laid pipe, or
any valved section thereof necessary to maintain the specified leakage test
filled with water to within 5 psi ofthe test pressure. No pipe installation will
be accepted until the leakage is less than the number of gallons per hour as
determined by the formula:
L = SD#
133200
L = Allowable leakage in gallons per hour.
S = The length of pipe in the section tested.
TS-5-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D = The nominal diameter of the pipe in inches.
P = The average test pressure during the leakage test in pounds per square
inch gauge.
The leakage test shall be conducted in accordance with A WW A Standard C-
600, Section 4.1.
13. Connection to Existing System: All connections to existing mains shall be
made under the direct supervision of the Augusta Utilities Department's
Inspector. Valves on existing mains shall be operated by or under direct
supervision of Augusta Utilities Department personnel. Tapping sleeves and
valves shall be pressure tested prior to tapping. If service to existing
customers must be cut off, the Augusta Utilities Department shall be notified
, at least three (3) days in advance to make necessary notifications. The
Contractor shall disinfect and secure appropriate Utilities Department
clearances and samples for any service interruptions which occur as a result
of a Contract request for shut down or error. The clearances shall be obtained
within 72 hours of reactivation.
14. If cut-off of service is required, the Contractor shall be ready to proceed with
as much material pre-assembled as possible at the site to minimize the length
of service interruption. Augusta Utilities reserves the right to postpone
service cut-off if, in the opinion ofthe Utilities DireCtor, the Contractor is not
ready to proceed on schedule. No customer should be without water for more
than four (4) hours. The Owner/Developer shall arrange for temporary
services to Customer if water will be shut off for more than four hours.
15. Local chlorination will be required for all pipe and fittings used to complete
connections with the potable water system. Tapping sleeves and valves shall
be chlorinated in accordance with A WW A requirements. All wet taps shall
be witnessed by the Augusta Utilities Department's Inspector.
B.
CLEANING AND FLUSHING
1. Upon completion of installation, the mains shall be flushed and the water
disposed of without creating a nuisance. Flushing must achieve a minimum
water velocity of 2.5 fps in all portions of the pipe. The duration of the
flushing will be determined by the Augusta Utilities Department's Inspector.
If, in the opinion of the Augusta Utilities Department's Inspector, there is
insufficient water available for proper flushing, the Contractor shall clean the
lines by pigging. No flushing or cleaning shall take place without an Augusta
Utilities representative present. The existing mains that the new mains are
connected to may be required to be flushed under the direction ofthe Augusta
Utilities Department when service is restored.
TS-5-16
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
c.
TESTING AND DISINFECTION
1. All water mains shall be leak tested. The Contractor/Developer shall provide
all equipment, materials and labor necessary for pressure and leak testing.
This test must be observed by an Augusta Utilities Department representative
and the design engineer. A pumping pressure of 200 psi must be supplied at
the expense of the Contractor/Developer. The main tested shall either be
isolated from active potable lines or protected from leakage by a double valve
arrangement. All water used for pressure testing must be potable water with
an adequate chlorine residual. Water lines shall be tested by valve sections.
Maximum allowable leakage shall be as determined in accordance with
current A WW A specifications. The standard duration of test is four (4)
hours. Testing procedures shall meet or exceed A WWA C600 (latest
revision) requirements. Any portions ofthemain which fail the test shall be
replaced or adjusted until the entire new main passes the test criteria. The'
pressure and leakage test shall be done concurrently.
2. Augusta Utilities shall be notified at least 24 hours in advance to schedule
bacteriological testing of water mains. The Contractor shall replace or adjust
components ofthe pipeline which fail the test. Clearance is required from the
Utilities Department before the Augusta Utilities Department will allow the
main to be put into service.
3. All piping complete with fittings and appurtenances shall be sterilized as
specified in the applicable sections of A WW A Specification C651.
"Disinfecting Water Mains." Piping and appurtenances shall be thoroughly
flushed then chlorinated with not less than fifty parts per million (50 ppm).
Calcium hypochlorite can be used. Water from the existing distribution
system or other source of supply should be controlled so as to flow slowly
into the newly laid pipeline during the application of chlorine. The solution
should be retained in the pipeline for not less than 24 hours and a chlorine
residual of 10 ppm should be available at this time. The system shall then be
flushed with potable water and the sampling program started. Sampling taps
and chlorinated water used for disinfection shall be flushed to a location that
will not damage property, persons, etc., and shall be provided by the
Contractor/Developer at the expense of the Contractor/Developer. The
provisions of this paragraph apply equally to new pipe and fittings and to
existing pipelines into which connections have been made or which may have
been otherwise disturbed to the extent that contamination may have occurred.
All requirements ofthe health authorities shall be observed in executing this
work.
4. Two or more successive sets of samples, taken at 24 hour intervals and tested
by a State approved private lab, shall indicate bacteriologically satisfactory
water and the results submitted to the Engineer.
TS-5-17
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-04.
D.
WATER/SEWER SEPARATION:
1. A 10 foot horizontal separation shall be maintained between water and sewer
lines. Where the horizontal separation cannot be met or where water and
sewer lines must cross, an 18 inch vertical separation, water over sewer must
be maintained. Where the above conditions cannot be met, water and sewer
lines shall be cast iron or ductile iron pipe with joints staggered such that
maximum separation between j oints exists. The water line shall be installed
over the sewer line.
E.
AS-BUILT DRAWINGS:
1. As the work progresses, record on one set of utility drawings all changes and
deviations from the contract drawings in sizes, lines or grade. Record also
the exact final location of water lines by offset distances to surface
improvements such as edge of existing pavement or to property lines, etc. at
a maximum interval of 200 feet. Make sufficient measurements to locate
definitely all water lines etc., to permanent points. The drawings will show
references to all valves, fittings, pipe brand changes, etc. Transfer accurately
all such records in red pencil to white prints of the utility drawings and
deliver them to the Engineer with monthly payment estimate.
MEASUREMENT AND PAYMENT:
Payment will be made only for elements in place and tested as follows:
A.
Pipelines will be paid for at the unit contract price, per linear foot, for each size,
type and class installed, complete, including fittings. No deduction will be made
for the laying length of valves and fittings installed within pipelines. .
B.
Valves will be paid for at the unit contract price for each size and type installed.
Payment therefore will include box or vault as shown on the plans.
c.
Fire hydrants will be paid for at the unit contract price for each size installed,
complete with the lead piping, valve, and main tee, in place as shown on the
plans.
D.
Service lines will be paid for at the unit contract price for each size and type installed,
complete as shown on the plans.
TS-5-18
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-6
STORM SEWER SYSTEM
-01.
SCOPE:
This section covers the storm drainage system, including pIpe culverts and
appurtenant structures, complete.
-02. PIPE FOR CULVERTS AND STORM DRAINS:
A. Pipe for culverts may be reinforced concrete pipe of the class or D-Ioad strength indicated
and shall conform to ASTM C76 or AASHTO M 170 with the following additional
requirements. Pipe shall have a readily visible line at least 12 inches in length painted or
otherwise applied on the inside and outside of the pipe at each end by the manufacturer, so
that, when the pipe is laid on its proper position, the lines will be at the top ofthe pipe. The
line shall be accurately located to indicate the position where the pipe reinforcing steel is
nearest to the exterior surface ofthe pipe. Non-reinforced concrete pipe shall conform to the
latest ASTM C-14.
B. Pipe may also be corrugated metal pipe which shall conform to the latest AASHTO M-36,
M274 (Aluminized Steel, Type 2 material) or ASTM B744, B745 & B790 (Aluminum) .
Bituminous coating, where required by the drawings, shall consist of asphalt cement having
a minimum thickness of 0.04 inch measured at the crest of the corrugations. Paved inverts
in corrugated metal pipe, where required by the drawings, shall consist of asphalt cement
applied on the inside ofthe pipe for one quarter of its circumference (bottom of pipe when
installed). The pavement shall have a minimum thickness of 0.50 inch tapering to 0.1 inch
at the sides.
C. Pipe may also be high density polyethylene corrugated plastic pipe which shall conform with
the requirements for test methods, dimensions, and markings found in AASHTO
Designations M252 and M294. Pipe and fittings shall be made from virgin polyethylene
compounds which conform with the requirements of cell class 324420C as defined and
described in ASTM D3350. All sizes shall conform to the AASHTO Classification "Type
SIt (which describes pipe with a smooth waterway). Joints shall be water tight according to
the requirements of ASTM D3212.
-03. TESTS FOR PIPE:
A. RESPONSIBILITY AND CERTIFICATIONS: The Contractor shall be responsible for
having the pipe he proposes to furnish tested to demonstrate conformance to the applicable
specifications. Certified copies of the test reports shall accompany each load of pipe and
shall be delivered to the Engineer for approval before the pipe is installed.
B. Strength tests for reinforced concrete pipe shall be the tests of ASTM C-76.
TS-6-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
C. Strength tests for concrete pipe shall be the tests of ASTM C-14.
D. Strength tests for corrugated metal pipe shall be the tests of AASHTO M-36.
-04. INSTALLATION OF PIPE:
Each pipe shall be carefully examined before being laid, and defective or damaged
pipe shall not be used. Pipe lines shall be laid to the grades and alignment indicated. Proper
facilities shall be provided for lowering sections of pipe into trenches. Under no circumstances shall
pipe be laid in water, and no pipe shall be laid when trench conditions or weather are unsuitable for
such work. Full responsibility for the diversion of drainage and for dewatering of trenches during
construction shall be borne by the Contractor. All pipe in place shall have been approved before
backfilling. When storm drain pipe terminates in a new ditch, the headwall or end section together
with ditch pavement, if specified, shall be constructed immediately as called for on the plans. Ditch
slopes and disturbed earth areas shall be grassed and mulched as required by the section Grassing.
The Contractor will be responsible for maintaining these newly constructed ditches and take
immediate action subject to approval to keep erosion of the ditch bottom and slopes to a minimum
during the life of the contract. No additional compensation will be given to the Contractor for the
required maintenance.
Installation of high density polyethylene corrugated plastic pipe shall be in accordance
with ASTM Recommended Practice D2321.
A JOINTING: Joints for concrete and reinforced concrete shall be ofthe Bell and Spigot type
and installed according to manufacturer's recommendations using Portland cement mortar.
Corrugated metal pipe joints shall be made by riveting or by means of connecting bands with
bolted couplings in accordance with the manufacturer's recommendations.
B. ALIGNMENT: Elliptical concrete pipe with circular reinforcing and circular concrete pipe
with elliptical reinforcing shall be so placed that the reference lines designating the top ofthe
pipes will be not more than 5 degrees from the vertical plane through the longitudinal axis
of the pipe. In all backfilling operations that Contractor shall be responsible for preventing
damage to or misalignment of the pipe.
-05. EXCAVATION AND BACKFILLING FOR DRAINAGE STRUCTURES:
Excavation and backfilling for drainage structures shall conform to the applicable
requirements specified hereinbefore in the section, "Excavation, Trenching and Backfilling for Pipe
Lines." Trenches and pits shall be of sufficient size to permit the placing and removal of forms for
the full width and length of structure footings and foundation, as shown on the drawings. The
dimensions and elevations indicated on the drawings are approximate only and may be changed
when deemed necessary to secure satisfactory foundations. Bracing, sheeting and shoring shall be
provided where required.
TS-6-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-06. DRAINAGE STRUCTURES:
Drainage structures, where indicated in the plans shall be of the following types,
constructed of the materials specified for each type and in accordance with the details shown on the
plans.
A. INLETS: Inlets shall be constructed of reinforced concrete, plain concrete or brick, complete
with frames and covers.
B. HEADW ALLS: Headwalls shall be constructed of brick, reinforced concrete or plain
concrete as indicated.
-07. MATERIALS FOR DRAINAGE STRUCTURES:
A. CONCRETE AND REINFORCED CONCRETE: Concrete and reinforced concrete shall
conform to the requirements specified for Class B concrete designed for a minimum
compressive strength of2,500 pounds in 28 days, based on test cylinders prepared and tested
as specified under the section on CONCRETE CONSTRUCTION of these specifications.
Aggregate shall be as specified in the section on CONCRETE CONSTRUCTION.
Maximum size of coarse aggregate shall be not more than 1 Y2. inches or less than 1 inch.
Forms shall be made of sound lumber and constructed to the shape, form, line, and grade
required, and shall be maintained sufficiently rigid to prevent deformation under load, and
inspected for approval prior to placement of concrete. Water shall be removed from
excavations before concrete is placed. Concrete shall be conveyed from mixer to forms as
rapidly as practicable without segregation or loss of ingredients. Concrete shall be placed
in layers not over 18 inches deep and shall be spaded .and compacted as directed. The
concrete covering over steel reinforcing shall be as shown on the plans, but where not shown,
it shall be not less than 1 inch for covers and not less than 1 Yz inches for walls and flooring.
Concrete deposited directly against the ground shall have a thickness of at least 3 inches
between the steel and the ground. Expansion joint filler shall be preformed bituminous
fiberboard, or wood board except where specifically specified on the drawings. Surfaces
exposed to view shall be a smooth finish with all blemishes removed. All concrete surfaces
shall be cured for at least 7 days by covering with waterproof paper, or kept moist with
cotton mats or burlap as approved.
B. MORTAR: Mortar for connections to drainage structures shall be composed of one part by
volume of Portland cement and two parts of sand. The Portland cement shall conform to
ASTM C-150-65, Type I or II. The sand shall conform to AASHTO Standard M-45, and
shall be of an approved gradation. Hydrated line may be added to the mixture of sand and
cement in an amount equal to 25 percent of the volume of cement used. Hydrated lime shall
conform to Federal Specification SS-L-351, Type M, or ASTM Standard C141-61, Type A.
The quantity of water in the mixture shall be sufficient to produce a stiff workable mortar but
shall in no case exceed 7 gallons of water per sack of cement. Water shall be clean and free
of injurious acids, alkalies, and organic impurities. The mortar shall be used within 30
minutes from the time the ingredients are mixed with water. The inside ofthe joint shall be
wiped clean and finished smooth. In pipe too small for a man to work inside, wiping may
TS-6-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
be done by dragging an approved swab or long-handled brush through the pipe as work
progresses. The mortar bead on the outside shall be protected from air and sun with a proper
covering until satisfactorily cured.
-08.
TESTING:
DISPLACEMENT TEST: Mains will be checked to determine whether any
displacement of the pipe has occurred (a) after the trench has been backfilled to two feet above the
pipe and tamped as specified; and (b) upon completion of the project. The test will be as follows:
A light will be flashed between manholes or, if the manholes have not as yet been constructed,
between locations of the manholes, by means of a flashlight or by reflecting sunlight with a mirror.
Ifthe illuminated interior ofthe pipe shows any misalignment, displaced pipe, or any other defects,
the defects designated by the contracting officer shall be remedied by the contractor at his expense.
-09.
MEASUREMENT AND PAYMENT:
Payment shall be made at the unit contract prices for individual elements as shown
in the Bid Schedule under Storm Sewer.
TS-6-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-7
GRADED AGGREGATE BASE COURSE
-01.
SCOPE:
This section covers a graded aggregate base course to receive bituminous paving
under another section, complete.
-02.
GENERAL SPECIFICATIONS:
The graded aggregate base course shall conform to all applicable specifications of
Section 300 ofthe standard specifications for roads and bridges oftheGeorgia State Department of
Transportation, Latest Edition.
-03.
PREPARATION OF SUBGRADE:
The sub grade to receive the graded aggregate base course shall be constructed in
accordance with requirements of Section 209 ofthe standard specifications for roads and bridges of
the Georgia State Department of Transportation. 'I
-04.
MATERIALS AND CONSTRUCTION FOR BASE COURSE:
Materials and construction for the graded aggregate base course shall be in accordance
with Section 310 of the standard specifications for roads and bridges of the Georgia State
Department of Transportation.
-05.
MEASUREMENT AND PAYMENT:
Payment for Graded Aggregate Base Course is included in the unit price amounts for
Standard and Tennis Court Paving shown in the Bid Schedule and no separate payment will be made
therefor.
TS-7-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-8
GRADED AGGREGATE SURFACE COURSE
-01. SCOPE:
This section covers a graded aggregate surface cours~ for a driveway or parking area.
-02. GENERAL SPECIFICATIONS:
. The graded aggregate surface course shall conform to all applicable specifications of
Section 318 of the Standard Specifications for Roads and Bridges ofthe Georgia State Department
of Transportation, Latest Edition.
-03. PREPARATION OF SUBGRADE:
The sub grade to receive the graded aggregate surface course shall be constructed in
accordance with requirements of Section 209 ofthe Standard Specifications for Roads and Bridges
of the Georgia State Department of Transportation. -
-04. MATERIALS AND CONSTRUCTION FOR SURFACE COURSE:
Materials and construction for the graded aggregate surface course shall be in
accordance with Section 310 of the Standard Specifications for Roads and Bridges of the Georgia
State Department of Transportation.
-05. MEASUREMENT AND PAYMENT:
Payment for Graded Aggregate Surface Course will be made at the unit price as
shown in the Bid Schedule.
TS-8-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-9
BITUMINOUS PAVING
-01.
SCOPE:
This section covers the construction of pavement for all roads, parking lots and tennis
courts, complete.
-02.
GENERAL:
Construction of the sub grade, base course and paving of the roadways and parking
areas shall be undertaken immediately after completion of all storm drain lines and structures, all
curbs and gutters, all yard piping, conduits and other facilities passing beneath paved areas, and all
structural slabs and foundations required within or adjacent to the paved areas.
-03.
SEASONAL LIMITATIONS:
No bituminous mixtures shall be applied for surface treatment between October 21 st
and April 10th, except as directed by the Engineer.
-04.
WEATHER LIMITATIONS:
Bituminous mixtures shall not be produced or placed during rainy weather, when the
sub grade or base course is frozen or shows any evidence of excess moisture nor when the moisture
on the surface to be paved would prevent proper bond nor when the air temperature is less than 45
degrees F. in the shade away from artificial heat.
-05.
APPLICABLE SPECIFICATIONS:
All work and materials required under this section ofthe specifications shall conform
to the applicable sections of the Standard Specifications of the Georgia Department of
Transportation, latest edition.
-06.
SUBGRADE:
The sub grade shall be prepared as specified under the sections of the above
specifications covering sub grade preparation, including but not limited to Section 209.
-07.
CURBS AND GUTTERS:
After the sub grade has been compacted and approved by the Engineer, curbs and
gutters shall be placed where shown on the plans and constructed in accordance with the
requirements of the section, CURBS AND GUTTERS, CONCRETE.
TS-9-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-08.
PRIME COAT:
A prime coat of 0.3 to 0.8 gallons per square yard ofmedium curing cut-back asphalt
(RC-250 or emulsion grades RS-2 or SS-l) shall be applied with a pressure distributor at a
temperature between 80 degrees F. and 140 degrees F. The prime coat shall be applied to the
previously prepared base course when the atmospheric temperature is above 50 degrees F.
-09. SURFACE COURSE:
A. ASPHALT CONCRETE: The asphalt concrete mixture shall conform to the Georgia
Department of Transportation, Standard Specifications for Highway Construction, for Type
E asphalt concrete. The job mix shall be approved by the engineer and no material shall be
used until approved.
B. TRANSPORTATION AND DELIVERY: The mixture shall be transported from the mixing
plant to the point of use in approved vehicles. Loads shall not be of such size or weight as
to interfere with the efficient operation of the spreader. Loads shall not be sent out so late
in the day as to prevent the completion of spreading and compaction ofthe mixture during
daylight, unless artificial light is provided. The mixture shall be delivered at a temperature
between 225 degrees F. and 325 degrees F. and within 20 degrees F. of temperature set at the
mixing plant.
C. SPREADING: Upon arrival at the point of dumping, the mixture shall be dumped into the
hopper and spread by mechanical pavers, true to line, grade and cross section specified and
to the loose depth that will secure the required compacted thickness. The hot mixture shall
be free from lumps and shall be spread while it is in a workable condition.
After the mixture has been screeded and before roller compaction is started, the surface shall
be checked, all fat spots and irregular areas removed and replaced with satisfactory material.
All irregularities in alignment and grade along the outside edge shall also be corrected by the
addition or removal of mixture before the edge is rolled.
D. COMP ACTION: While the mixture is hot, it shall be compacted thoroughly and uniformly
by rolling. The surface of the compacted mixture shall be smooth, and true to crown and
grade. Any mixture that becomes loose or broken, mixed with dirt, or is in any way
defective, shall be removed and replaced with fresh hot mixture which shall be immediately
compacted to conform to the surrounding area. Any area showing an excess of bituminous
materials shall be removed and replaced, and the edges shall be kept to a reasonable straight
line and trimmed.
The density after compaction shall be at least 98 percent" of the laboratory-determined
density.
E. PROTECTION OF PAVEMENT: The newly finished pavement shall be protected from
vehicular traffic of any kind until the pavement has cooled and hardened and in no case less
than 6 hours.
TS-9-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
F. TOLERANCE: The finished surface shall not vary more than Va inch in 10 feet from the true
profile and cross section.
-10. TESTS:
The above work will be subject to thickness and compaction tests as deemed
necessary by the Engineer. Such tests will be at the expense of the Contractor.
-11. < MEASUREMENT AND PAYMENT:
Payment for Bituminous Paving is included in the unit price amounts shown in the
Bid Schedule for Standard and Tennis Court Paving.
TS-9-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-IO
CONCRETE CONSTRUCTION
-01.
SCOPE:
This section covers concrete construction, complete, including reinforcement
thereof.
-02.
FORMS:
Forms shall be of wood, metal, structural hardboard or other suitable material that
will produce the required surface finish. Forms placed for successive pours for continuous
surfaces shall be fitted to accurate alignment to assure a smooth completed surface free from
irregularities, and shall be sufficiently tight to prevent the loss of mortar. No forms shall be left
permanently in place without approval of the Engineer. Holes resulting from removal of form
ties shall be filled solid within 12 hours after removal of forms with cement mortar.
-03.
REINFORCING AND EMBEDDED METALS:
Bar reinforcement shall be intermediate grade new billet steel conforming to the
requirements of the ASTM Designation A15. All bars 3/8 inch and larger shall be deformed bars
conforming to ASTM Designation A305. Detailing, fabrication and tagging of reinforcement
shall be done in accordance with ACI "Manual of Standard Practice for Detailing Reinforced
Concrete Structures" (ACI 315), except that where longer laps are indicated on the design
drawings, the drawings shall govern. Wire fabric reinforcement shall consist of steel wire
conforming to the requirements of ASTM Designation A185. Anchor bolts and structural shapes
shall conform to ASTM Designation A36. Exposed surfaces of embedded steel shall be given
one shop coat of Red Lead Iron Oxide conforming for Federal Specification TT-P-86c, Type IT,
unless otherwise noted on the drawings. Anchor bolts and miscellaneous steel items to be
embedded in concrete shall be accurately placed in accordance with the drawings, and adequately
secured in position to prevent dislodgement during concrete placing operations. Anchor bolts
shall be protected after concrete has been placed and set by daubing with grease, wrapping with
burlap, and covering bolts with wooden boxes.
-04.
CONCRETE:
All concrete shall be equivalent to ready mix concrete manufactured and delivered
in accordance with the requirements of ASTM Designation C94 and having a compressive
strength at 28 days of 3,000 psi, except as noted herein. The concrete manufacturer shall assume
the responsibility of the design of the concrete mix in accordance with Alternate No.2 of ASTM
C94. Air entrained concrete shall be used for all concrete.
A. MATERIALS:
1. Cement: Cement shall be Type I or IA "Portland" cement, all one manufacturer,
conforming to ASTM, C150 or ASTM C175, respectively.
TS-10-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2. Aggregates: Aggregates shall conform to ASTM C33. Coarse aggregate shall be
crushed rock or gravel and graded from % inch to number 4 sieve for mass or
foundation concrete. Fine aggregate shall be natural sand.
3. Water: Mixing water shall be proportioned so that slump when measured with
standard slump cone does not exceed the following:
Slabs on grade
Footings
All others
Max. 4", Min. 3"
Max. 5", Min. 3"
Max. 6", Min. 3"
4. Joint Filler Strips: Premoldedjoint filler strips shall be resilient compressive,
bituminous and fiber materials saturated with at least 35 percent and not over 50
percent by weight of asphalt. Poured type joint composition for expansion joints
shall be elastic compound made up of asphalt and colloidal mineral fillers.
B. PLACING CONCRETE: Runways for wheeled equipment shall be provided to convey
concrete. Runways shall not be supported on the reinforcement. Concrete shall be placed
and compacted in layers not over 24 inches deep. Vibrators may be used provided they
are used under experienced supervision and the mixture is dry enough to prevent
segregation. Form vibrators shall not be used. Vibration shall not be used for
transporting or moving concrete inside forms. No more concrete shall be placed than can
be consolidated and finished the same day as placed. Free fall of concrete shall be limited
so that no segregation of materials occurs.
C. JOINTS: Construction joints not indicated on drawings shall be approved by the
Engineer in advance of pour. Joints in foundation walls shall be keyed. Before
depositing the concrete is resumed, the hardened surface shall be roughened, cleaned of
foreign matter and thoroughly wetted but not saturated. The cleaned and wetted surfaces
shall be slushed with a coating of neat cement grout against which the new concrete shall
be placed before the grout has attained its set.
D. FINISHING: After stripping forms, all voids and honeycombs shall be patched by
chipping and scarifying the defective areas and treating it with an approved bonding
agent. All such voids shall be patched, not merely plastered. Grout mixture shall consist
of one part Portland cement and one part sand. Immediately following removal of forms,
all fins and irregular proj ections shall be removed from all surfaces except from those
which are not to be exposed or waterproofed. Slabs shall be struck-off and consolidated
by approved machine or hand methods, screeding and tamping concrete so that upon
completion, the surface shall be true to grade as shown on drawings and free of surface
voids. All floors shall have a monolithic steel trowel finish unless otherwise indicated on
the drawings. Exterior walls shall be compacted, screeded and floated to a true even
surface with wood floats and then broomed.
-05. MEASUREMENT AND PAYMENT:
Payment for concrete shall be made at the unit prices for individual elements as
shown in the Bid Schedule.
TS-10-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-ll
CURBS AND GUTTERS, CONCRETE
-01.
SCOPE:
This section covers construction of Portland cement concrete curbs and gutters,
complete.
-02.
CONCRETE:
Concrete and the equipment, workmanship and materials therefor shall conform to
the applicable requirements of the CONCRETE CONSTRUCTION section, except as hereinafter
specified. The maximum size of coarse aggregate shall be 1 Y2. inches and not less than 1 inch.
Concrete shall have a slump of nor more than 3 inches. The concrete mixtures shall have an air
content by volume of 4.5 percent, plus or minus 1.5 percent, based on measurement made on
concrete immediately after discharge from the mixer.
-03.
SUBGRADE PREPARATIONS:
The sub grade shall be constructed true to grade and cross section. The sub grade shall
be of materials equal in bearing quality to the sub grade under the adj acent roadway or street and shall
,f
be placed and compacted to conform with applicable requirements of the specifications entitled
"Sand-Clay Base Course" with the following modifications. The sub grade for curb and gutter shall
extend in all cases at least 1 foot in width back of the curb or gutter or valley pavement. The
sub grade shall be tested for grade and cross section by means of a template extending the full width
of the curb, gutter, or combination curb and gutter. The subgrade shall be maintained in a smooth,
compacted condition, in conformity with the required section and established grade until the concrete
is placed. In cold weather, the sub grade shall be prepared and protected so as to produce a subgrade
free from frost when the concrete is deposited.
-04.
FORMS:
Forms shall be of wood or steel, straight, and of sufficient strength to resist springing
during depositing and consolidating the concrete. The outside forms shall have a height equal to the
full depth ofthe curb or gutter. The inside form of curb shall have better as indicated and shall be
securely fastened to and supported by the outside form. Straight forms of wood shall be 2 inch
nominal surface plank, and of steel, shall be of approved section with a flat surface at the top.
Rigid forms shall be provided for curb returns except that benders or thin plank forms
may be used for curb or curb returns with a radius of 10 feet or more, when grade changes occur in
the return, or where the central angle is such that a rigid form with a central angle of 90 degrees
cannot be used. Back forms for curb may be made of Y2. inch benders, for the full height ofthe curb,
cleated together. Curb forms shall be carefully set to alignment and grade and to conform to the
dimensions ofthe curb. Forms shall be held rigidly in place by the use of stakes placed at intervals
not to exceed 4 feet. Clamps, spreaders, and braces shall be used where required to insure rigidity
TS-11-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
in the forms. The forms on the front of the curb shall be removed not less than 2 hours nor more
than 6 hours after the concrete has been placed. Forms back of curb shall remain inplace until the
face and top of the curb have been finished as specified in the Finishing paragraph. Gutter forms
shall not be removed for 12 hours after the concrete has been placed. Forms shall not be removed
while the concrete is sufficiently plastic to slump in any direction. Forms shall be cleaned and
coated with form oil each time before concrete is placed. Wood forms may, instead, be thoroughly
wetted with water before concrete is placed, except that with probable freezing temperatures, oiling
is mandatory.
-05.
JOINTS:
Expansion joints and contractionjoints shall be constructed at right angles to the line
of curb, gutter, and combination curb and gutter. Dowels, tie-bars and reinforcement when required
will be shown on the plans and shall be Installed in accordance with the applicable details.
A. CONTRACTION JOINTS: Contractionjoints shallbe constructed by mean so 1fs inch thick
separators, of a section conforming to the cross section of the curb, gutter, entrance
pavements, and combination curb and gutter. Contraction joints shall be so placed that
monolithic sections between curb returns will not be less than 5 feet nor greater than 15 feet
after the concrete has set sufficiently to preserve the width and shape of the joint. After
separator plates have been removed, all exposed edges of joints shall be rounded with the
proper edging tool to a radius of ~ inch.
B. EXPANSION JOINTS: Expansionjoints shall be formed by means ofpreformed expansion
joint filler material cut and shaped to the cross section of the curb, gutter, entrance, and
combination curb and gutter.
Expansionjoint filler, unless otherwise specified, shall conform to ASTM Standard D 1751-
60 or D1752-60 or shall be resin-impregnated fiberboard conforming to the physical
requirements of ASTM Standard C1752-60. Expansionjoints shall be provided in curb and
combination curb and gutter at the ends of all returns. Expansion joints at least Y2. inch in
width shall be provided at intervals not exceeding 50 feet. Expansion joints shall be
provided in nonreinforced concrete gutter at the locations indicated.
-06. CONSTRUCTION:
A. CURBS AND GUTTERS: Curbs, gutters and combination curb and gutters shall be ofthe
dimensions and sections shown on the drawings.
B. RECONSTRUCTION: Where the plans provide for reconstruction of existing curb,
combination curb and gutter and the limit of new work specified does not fall on ajoint, the
entire section shall be removed and the new curb, combination curb and gutter or entrance
pavement shall join the old curb at the first join line beyond the specified limit.
C. PLACING CONCRETE: The faces and adjacent edges of abutting rigid pavements and
structures shall be painted with an approved bituminous material prior to placing concrete.
TS-11-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D.
Concrete shall be placed in the forms to the specified depth in 6 inch layers and thoroughly
consolidated by tamping and spading to that there are no rock pockets at forms, and mortar
entirely covers the top surfaces. Concrete may be compacted by means of mechanical
vibrators.
FINISHING: The edges of the gutter and top of the curb shall be rounded with an edging
tool to a radius of ~ inch and the surfaces shall be floated and finished with a smooth wood
float until true to grade and section and uniform in texture. The floated surfaces shall then
be brushed with a fine-hair brush with longitudinal strokes. Immediately after removing the
front curb form, the face of the curb shall be rubbed with a wood or concrete rubbing block
and water until blemishes, form marks, and tool marks have been removed. The surface,
while still wet, shall be brushed in the same manner as the gutter and curb top. The top
surface of gutter and entrance shall be finished to grade with a wood float. Except at grade
changes or curves, the finished surfaces shall not vary, from the testing edge of a 10 foot
straightedge, more than 1fa inch for gutter and entrance and ~ inch for top and face of curb.
Irregularities exceeding the above shall be satisfactorily corrected. Visible surfaces and
edges ofthe finished curb, gutter, and combination curb and gutter shall be free ofblemishes
and form and tool marks, and shall be uniform in color, shape, and appearance.
E.
CURB FORMING MACHINES: Use of curb-forming machines for constructing curb and
gutter will be approved based on trial use on the job. Use of the equipment shall be
discontinued at any time during the construction if the equipment produces unsatisfactory
results, and the work shall be removed and reconstructed for the full length between regularly
scheduled joints. Removed portions shall be disposed of as directed.
-07.
CURING AND PROTECTION:
A.
CURING: Immediately after the finishing operations, the exposed concrete surfaces shall
be cured by one of the following methods as the Contractor may elect:
1. Mat Method: The entire exposed surface shall be covered with cotton mats
conforming to Federal Specification CCC-C-467b having a combined weight of 14
ounces or more per square yard when dry. Mats shall overlap each other at least 6
inches. The mat shall be thoroughly wetted with water prior to placing on the
concrete surface and shall be kept continuously in a saturated condition and in
intimate contact with concrete for not less than seven days.
2. Impervious-Sheeting Method: The entire exposed surface shall be wetted with a fine
spray of water and then covered with waterproof paper conforming to ASTM
Standard C171-63, or with wetted polyethylene-coated burlap or polyethylene
sheeting conforming to the water-retention requirements of ASTM Standard C171-
63, polyethylene sheeting and polyethylene film bonded to burlap shall be not less
than 0.004 inch thick.
Sheets shall be laid directly on the concrete surface with a light-colored side up and
overlapped 12 inches when a continuous sheet is not used. The curing medium shall
not be less than 18 inches wider than the concrete surface to be cured and shall be
TS-11-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
securely weighted down by placing a bank of moist earth on the edges just outside
the forms and over the transverse laps of form closed joints. Sheets shall be
satisfactorily repaired or replaced if damaged during curing. The curing medium
shall remain on the concrete surface to be cured for not less than seven days.
3. Membrane-Curing Method: The entire exposed surfaces shall be covered with a
pigmented membrane-forming curing compound. The curing compound shall be
applied in two coats by hand-operated pressure sprayers at the coverage of
approximately 200 square feet per gallon for both coats. The second coat shall be
applied in the direction approximately at right angles to the direction of application
of the first coat. The compound shall form a uniform continuous coherent film that
will not check, crack, orpeel and shall be free from pin-holes or other imperfections.
Concrete surfaces that are subjected to heavy rainfall within three hours after the
during compound has been applied shall be resprayed. by the method and. at the
coverage specified above at no additional cost to the Owner. Joint openings shall be
sealed at the top by inserting moistened paper or fiber rope or covering with strips of
waterproof paper prior to application ofthe curing compound, in a manner to prevent
the curing compound from entering the joint. Concrete surfaces to which membrane-
curing compounds have been applied shall be adequately protected for seven days
from pedestrian and vehicular traffic and from any other action which might disrupt
the continuity of the membrane. Any area covered with curing compound and
damaged by subsequent construction operations within the seven-day period shall be
resprayed as specified above at no additional expense to the Owner.
B. PROTECTION: After curing, debris shall be removed and the backfill shall be placed as
indicated. The completed curb, gutter, and combination curb and gutter shall be protected
from damage until accepted. The Contractor shall repair damaged concrete and clean
concrete discolored during construction. Curb, gutter, and combination curb and gutter that
are damaged shall be removed and reconstructed for the entire length between regularly
scheduled joints, not by refinishing the damaged portion. Removed damaged portions shall
be disposed of as directed.
-08. SEALING JOINTS:
The sealing of expansion j oints in curb and gutter sections will not be required. Any
expansion joint material protruding after the concrete is cured shall be trimmed flush with the
surface. Expansion joints in the valley pavement shall be sealed with an approved joint sealer,
conforming to Federal Specification SS-S-164. The joint opening shall be thoroughly cleaned of all
foreign material before the sealing material is placed. The sealing shall be done in such manner that
the material will not be spilled on the exposed surfaces of the concrete. Any excess material on the
exposed surfaces of the concrete shall be removed immediately and the exposed concrete surfaces
cleaned.
-09.
MEASUREMENT AND PAYMENT:
Payment shall be made at the unit price for 24" Standard Concrete Curb and Gutter
as shown in the Bid Schedule.
TS-11-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-12
EROSION, SEDIMENTATION & POLLUTION CONTROL MEASURES
-01.
GENERAL:
This section covers erosion, sedimentation and storm water pollution control
measures as shown on the plan or required on the job and are intended to comply with the
requirements of the Georgia Environmental Protection Division's General Permit No. GAR 100001,
latest edition. For the purpose ofthis proj ect and as referenced in the General Permit, the Owner and
the Contractor are considered the "Primary Permittee," and the Contractor and all his subcontractors
shall be considered the "Operator."
The measures shown on the plans and specified herein are minimum requirements
and may be augmented by the Engineer if positive control is not established for storm magnitudes
up to and including a 25 year rainfall event. These specifications and the corresponding plans do
not, in any way, relieve the Contractor of any obligations with respect to permits for wetlands, storm
water, stream buffers, flood plains or any other local, state or federal requirements.
-02.
CONSTRUCTION SCHEDULE:
The construction schedule is as shown on the Erosion, Sedimentation and Pollution
Control Plan.
-03.
DEFINITIONS:
All terms used in this section shall be interpreted in accordance with the definitions
set forth in the General Permit, some of which are restated as follows:
A. "Best Management Practices (BMP' s)" means schedule of activities, prohibitions of
practices, maintenance procedures and other management practices to prevent or
reduce the pollution of waters of the state. BMP's also include treatment
requirements, operating procedures and practices to control site runoff, spillage or
leaks, sludge or waste disposal or drainage from raw material storage.
B. "Buffer" means the area ofland immediately adj acent to the banks of state waters in
its natural state of vegetation, which facilitates the protection of water quality and
aquatic habitat.
C. "Construction Activity" means the disturbance of soils associated with clearing,
grading, excavating, filling ofland or other similar activities which may result in soil
erOSIOn.
D. "Final Stabilization" means that all soil disturbing activities on the site have been
completed and that unpaved areas have a minimum of 95% uniform coverage by
permanent vegetation or equivalent permanent stabilization measures such as riprap,
gabions or permanent geotextiles have been employed.
TS-12-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
E.
"Grading" means altering ground surfaces to specified elevations, dimensions and/or
slopes; this includes stripping, cutting, filling, stockpiling and shaping or any
combination thereof.
F.
"Qualified Personnel" means a person who has successfully completed an erosion
and sediment control short course or an equivalent course approved by the
Environmental Protection Division (EPD) and the State Soil and Water Conservation
Commission.
G.
"Waters of the State" means any and all rivers, streams, creeks branches, lakes,
reservoirs, ponds, drainage systems, springs wells, wetlands and all other bodies of
surface or subsurface water, natural or artificial, lying within or forming a part ofthe
boundaries ofthe State ~hich are not entirely confined and retained completely upon
the property of a single individual, partnership or corporation.
-04.
GENERAL PROCEDURES:
The Contractor shall utilize, at a minimum, Best Management Practices, including
sound construction practices to prevent and minimize erosion and resultant sedimentation, which are
consistent with and no less stringent than those practices contained in the "Manual for Erosion and
Sediment Control in Georgia," published by the State Soil and Water Conservation Commission as
of January 1 ofthe year in which the land disturbing activity was permitted, as well as the following:
A. Stripping of vegetation, grading and other development activities shall be conducted
in such a manner as to minimize erosion. Earth areas which are not to be paved shall
be grassed at the earliest possible time during the construction phase, so as to
minimize exposure to rainfall and run-off.
B. Unnecessary cut and fill operations shall be kept to a mlmmum, except that
temporary berms, wherever possible, should be constructed at the end of each day of
grading, in order to contain sediment and slow down erosion, should rainfall occur
during the night. Berms shall also be constructed, where needed, to prevent sediment
from being transported onto areas outside the actual construction limits.
C. Whenever feasible, existing natural vegetation shall be retained, protected and
supplemented.
D. Disturbed areas and the duration of exposure to erosive elements shall be kept to a
practicable minimum.
E. Temporary vegetation and/ormu1ching shall be employed to protect exposed critical
areas during development.
F. Permanent vegetation and structural erosion control measures shall be installed as
soon as practicable.
TS-12-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
G.
To the extent necessary, sediment in run-off water shall be trapped by the use of
debris basins, silt traps, silt barriers, or similar measures until the disturbed area is
stabilized.
H.
Adequate provisions shall be provided to minimize damage from surface water to the
cut face of excavations and the sloping surfaces of fills.
1.
Cuts and fills shall not endanger adjoining property.
J.
Fills shall not encroach upon natural water courses or constructed channels in a
manner so as to adversely affect other property owners.
K.
Construction equipment shall cross flowing streams by means ofbridges or culverts,
except when such methods are not feasible, provided in any case that such crossings
shall be kept to a minimum andprovided that the appropriate stream buffer variances
and wetlands approvals have been obtained from the Environmental Protection
Division (EPD) and the Corps of Engineers, respectively.
L.
Should the specified erosion, sedimentation and pollution control measures prove to
be inadequate, additional measures as directed by Engineer shall be provided for
treatment or control of any source of sediments. Additional adequate sedimentation
control facilities to retain sediments on site or to preclude sedimentation of adj acent .
waters shall be implemented.
M.
Except when a prior variance has been obtained from EPD or where a drainage
structure must be constructed with adequate erosion control measures, no
construction activities shall be conducted within a 25 foot buffer along the tops of
banks on all state waters nor within a 50 foot buffer along the tops of banks on all
state waters classified as "trout streams." If required for construction purposes, a
buffer variance will be applied for by the Owner.
N.
Whenever possible, proposed storm water piping systems and detention ponds shall
be constructed prior to other earth disturbing operations. The storm water piping and
detention system shall then be used as a means to control erosion and sediment on
the site.
o.
Sediment basins of the temporary nature shall be constructed as shown on plans and
as required to retain sediment on the site. All temporary sediment basins shall be
maintained in accordance with the "Manual for Erosion and Sediment Control in
Georgia," latest edition and then removed when final stabilization is attained.
P.
Where erosion due to wind is likely to be of concern, trees or groups of trees and
bushes should be left standing, wherever possible, to serve as windbreaks.
TS-12-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-05.
ELEMENTS OF THE PLAN:
The minimum requirements for the prevention of erosion and sedimentation for this
site are depicted on the plans and specified herein. The elements of the plan are discussed as
follows, and are listed in chronological order, as far as is practical. The construction activities
should proceed in the order listed.
A. Remove all marketable timber from the limits of construction, rights-of-way, utility
easements, designated fill areas, and other areas to be cleared.
. B. Begin clearing and grubbing operations only after silt barriers are installed.
Immediately after the area has been cleared for their placement, install dams, berms
and all other remaining erosion and sedimentation control measures as shown on the
drawings and specified herein. Care shall be taken not to clear and grub beyond the
construction limit.
C. Contractor shall notify Engineer within 24 hours after the installation of the initial
soil erosion control measures so that the Engineer may inspect the measures in
accordance with the EPD General Permit.
D. As grading operations commence, the topsoil shall be stripped and stockpiled in
mounds surrounded by berms. As mentioned above, berms or windrows shall be
constructed each afternoon at approximately 100 foot intervals across the graded
areas, except in the low-lying areas of the project. This action will tend to check
erosion should rainfall be experienced during the night.
E. Construction on the sanitary and storm sewer lines should be commenced as soon as
grading operations have been substantially completed. The disturbed strip along each
line which is located outside of a street right-of-way should be grassed immediately
upon the completion of trench backfilling, as described below.
F. A graded depression around each catch basin on the site shall be used to contain
sediment during construction in accordance with the "Manual for Erosion and
Sediment Control in Georgia," latest edition.
G. As soon as the graded areas which are not to be paved, to be built upon, or receive
underground utilities have been brought to final grade, three or four inches oftopsoil
shall be spread over these areas. Grassing operations should begin immediately, as
described in the grassing specifications. Roadway shoulders and slopes shall receive
a similar treatment as soon as the installation of the utilities are complete.
H. All grassing will be performed in accordance with the section of the specifications
titled "Grassing." Should seasonal limitations prevent the establishment of the
permanent grass cover, the area to be grassed shall be covered with temporary grass
cover; then the permanent grass will be established as soon as its growing season is
. reached.
TS-12-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1.
The hay bale dams and silt fencing described above shall not be removed until the
surrounding pavement base material has been placed and is ready for priming and/or
areas are properly stabilized.
J.
In no instance, shall any pollutants, hazardous waste or solid materials including
petroleum products, building materials, etc. be discharged to waters of the State.
K.
All work shall be in accordance with good grading practice and shall conform to
accepted practices in Erosion ControL
-06.
INSPECTIONS. SAMPLING & MONITORING:
The Contractor shall be aware that the Owner may contract with a third party to
perform additional site inspections of erosion, sedimentation and pollution control measures and also
procure samples of storm water runoff for testing in accordance with the requirements of theEPD
General Permit No. GAR 100001. Third party inspections and samplings shall not relieve the
Contractor of any obligations with respect to these specifications ofthat required by the EPD General
Permit GAR 100001. Should any inspections determine that there are deficiencies in the
Contractor's work, then corrective action will be required as directed by the Engineer or Owner.
A. Contractor's Requirements. With respect to inspections, sampling and monitoring
for compliance with EPD General Permit, the Contractor shall, at a minimum, be
responsible for the following:
1. Each day when any type of construction activity has taken place on site,
qualified personnel provided by the Contractor shall inspect: a) all areas on
the site where petroleum products are stored, used or handled for spills and
leaks from vehicles and equipment; b) all locations on the site where vehicles
enter or exit the site for evidence of off-site sediment tracking; and c) all silt
retention basins, traps, barriers, etc. for evidence of failures, potential failures
or excess silt accumulation.
2. These inspections must also occur after each rainfall event on the site and
must be continued until such time that the proj ect is complete and the site has
achieved final stabilization. The Contractor shall document these daily
inspections on a form provided by or approved by the Engineer and must
submit these forms weekly and after each rainfall event to the Owner's
designated representative. Additionally, should a deficiency in any of the
erosion control measures be noted, the Contractor shall notify the Engineer
within 24 hours.
3. Erosion and sedimentation control measures shall be inspected by a
representative ofthe Owner beginning with the first earth disturbing activity
and continuing through final stabilization of the project site. Storm water
monitoring, sampling and testing will be accomplished by personnel
representing the Owner beginning with the first earth disturbing activity and
TS-12-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
continuing through final stabilization ofthe proj ect site. The Contractor shall
allow the monitoring agency access to the site at all hours of the day by
providing a key to any locked gates and shall also coordinate these services
by notifying the monitoring agency when: a) the first rainfall event of 0.5 inch
or more in 24 hours occurs on the site after the soil erosion and sedimentation
control measures have been installed; and b) whenever a rainfall event greater
than 1 inch in 24 hours occurs on the site thereafter.
B. Subcontractor's Requirements: Subcontractors shall be considered as acting under
the direction of the Contractor in his role as the Operator under the EPD General
Permit. The Contractor shall insure that all subcontractors comply with the Permi~.
Subcontractors shall be responsible, at a minimum, for the following:
1. Each day when any type of construction activity has taken place on his
portion of the site, the Subcontractor shall inspect: a) all areas on the site
where petroleum products are stored, used. or handled for spills and leaks
from vehicles and equipment; b) all locations on the site where vehicles enter
or exit the site for evidence of off-site sediment tracking; and c) all silt
retention basins, traps, barriers, etc. for evidence of failures, potential failures
or excess silt accumulation.
2. These inspections must also occur after each rainfall event on the site and
must be continued until such time that the project is complete and the site has
achieved final stabilization.
3. The Subcontractor shall immediately report any noted deficiencies to the
Contractor, who will take appropriate corrective action.
-07.
MEASUREMENT AND PAYMENT:
Payment for the work specified herein shall be made according to the lump sum price
as shown in the Bid Schedule for Erosion, Sedimentation and Pollution Control, providing inspection
reports have been submitted and approved by the Engineer. Third party inspections and monitoring
on behalf ofthe Owner shall be paid for by the Owner independently of this contract, except that no
additional payment will be made to the Contractor for coordinating third party inspections and
monitoring.
TS-12-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
-02.
-03.
SECTION TS-13
GRASSING (BERMUDA AND WEEPING LOVEGRASS)
GENERAL:
1.
DESCRIPTION
1. This section covers the furnishing of all labor and materials and the performance
of all work required to assure the establishment of a temporary cover of grass
where required on all disturbed areas of the site not intended for paving, and a
dense permanent cover of grass on all disturbed areas of the site owned by the
City of Augusta which are not intended for paving.
PRODUCTS:
1.
MATERIALS
1. The following material shall be as specified by the "Standard Specifications,"
published by the State Department of Transportation of Georgia, latest edition.
Agriculture Lime ................................... Article 882.02
Fertilizer ......................................... Article 891.01
Sod ............................................. Article 890.03
Seed ............................................. Article 890.01
EXECUTION:
1.
CONSTRUCTION
1. GROUND PREPARATION: Final grades shall be as existed prior to
construction. Washes, low spots and hillocks or windrows will be evened and
the bed will be smoothed to facilitate uniform drainage after establishment ofthe
turf. Graded surfaces will be maintained in a smooth and even condition until
the required cover is established.
2. After the areas to be grassed have been brought to an even and smooth grade,
they shall be thoroughly loosened to a depth of at least 6 inches by plowing,
discing, harrowing, or other approved methods until the tillage is acceptable as
suitable for planting. During tillage operation, the surface shall be cleared of all
roots, cable, wire, or other waste material which might hinder final grading,
planting, or subsequent maintenance operations. Any operations of the
Contractor, shall be smoothed our before grassing operations are begun.
TS-13-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
3. APPLICATION OF FERTILIZER AND LIME: Fertilizer shall be distributed
uniformly at a rate of 1500 pounds per acre of commercial 6-12-12 analysis
fertilizer, and shall be incorporated into the soil to a depth of approximately 3
inches by discing, harrowing, or other approved methods. The incorporation of
fertilizer may be a part of the tillage operation specified above, or a part of the
hydro seeding procedure as described below.
4. Immediately following, or simultaneously with, the incorporation of fertilizer,
lime shall be distributed at the rate of 3000 pounds per acre, and shall be
incorporated into the soil to a depth of at least three inches by discing,
harrowing, or other acceptable methods. The incorporation oflime along with
the fertilizer may form a part of the tillage operation specified above.
5. Not less than 30 days after completion of seeding, the Contractor shall furnish
and apply Nitrate of Soda or Ammonium Sulphate to the planted areas. Nitrate
of Soda shall be a commercial product, containing not less than 16 percent
Nitrogen and Ammonium Sulphate not less than 20 percent Nitrogen. The
Nitrogen fertilizer shall be uniformly spread and distributed with approved
equipment at a rate that will give not less than 60 pounds of available Nitrogen
per acre. Other commercial types of nitrogenous material may be substituted at
the option of the Contractor. The time of application shall be limited to the
season of June through August.
2.
PERMANENT SEEDING
1. For areas requiring bermuda seeding:
A. September 15 - February 15, a mixture ofunhulled common bermuda
6lbs.lacre and rye grass seed 28 Ibs/acre applied simultaneously.
B. October 1 - March 1, unhulled common bermuda10 lbs.lacre.
C. April 1 - June 1, hulled common bermuda 10 lbs.lacre.
2. For areas requiring weeping lovegrass seeding:
A. April 15 - July 1, weeping lovegrass 5 Ibs/acre.
3. Seed may be applied by means of a hydro-seeder or other means approved by the
Engineer.
4. Immediately after seeding operations have been completed, the areas shall be
compacted by means of a cultipacker, roller wood float, or other approved
equipment sufficiently weighted, or compacted by hand methods, to reduce air
pockets to a minimum. The complete planted area shall be left with a firm, even
surface, free from abrupt humps and hollows, and to the established grade.
TS-13-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
5. All areas seeded for temporary or permanent grass shall be uniformly mulched
with hay or straw at the rate of2 Y2. tons per acre, except where hydro seeding is
employed using a cellulose mulch mixed with the seed and fertilizer.
3.
TEMPORARY GRASS: Temporary grass shall be used when directed by the Engineer
to control erosion where permanent grassing cannot be planted.
1. Temporary grass shall be a quick growing species such as rye grass suitable to
the area and season. Pasture rye will not be permitted. Seeding shall be done
in accordance with the permanent grassing requirements above, except that
ground preparation shall be the minimum required to provide a seed bed where
further grading will be required. Areas that require no further grading shall be
prepared as described in "GROUND PREPARATION" above. Lime shall be
omitted unless the area will later be planted in permanent grass without further
grading, in which case lime shall be applied as described above. Fertilizer shall
be applied at the rate of 400 pounds per acre. Nitrogen shall be omitted.
2. In March or April ofthe following year, as soon as weather is suitable, all areas
planted in temporary grass which are owned by the City of Augusta shall be
thoroughly plowed up and grassed in accordance with the applicable permanent
grassing method described above.
3. MAINTENANCE: The Contractor shall erect necessary warning signs and
barriers, mow grassed areas, and repair or replace grassed areas failing to show
a uniform growth of grass or damaged by his operations, and shall otherwise
maintain the grass until final acceptance of the contract. Replacement of dried
out or damaged grass shall be at the Contractor's expense.
4.
ACCEPTANCE:
1. Grassed areas will be accepted when a 95% cover by permanent grasses is
obtained and weeds are not dominant.
2. The work may be accepted in whole or in part as determined by the Engineer and
the Owner.
5.
MEASUREMENT AND PAYMENT:
1. Payment for temporary grassing shall made according to the lump sum price as
shown in the Bid Schedule for Erosion, Sedimentation and Pollution Control.
2. Payment for permanent grassing shall be made at the unit prices for Permanent
Grassing, Bermuda and Weeping Lovegrass as shown in the Bid Schedule.
TS-13-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-14
TENNIS COURT PAVING
-01. SLOPE REOUIREMENT:
All excavating, filling, compacting, grading and leveling work required hereunder shall be
" performed so that the finished court surface slopes one foot (1 ') in each one hundred and eight feet
(108') on a true plane from side to side, as indicated on the drawings.
-02. BASE CONSTRUCTION:
A. MATERIAL. A base course of crushed aggregate shall be installed over the subgrade as
indicated on drawings. The specified material shall meet applicable ASTM specifications.
Compacted thickness shall be as shown on drawings to satisfy local soil and climatic
conditions but in no case shall the thickness be less than the equivalent of four inches (4")
of thoroughly compacted crushed stone.
B. SPREADING. The material shall be spread by methods and in a manner proposed by the
Contractor to produce a uniform density and thickness with the grades and dimensions shown
on drawings and elaborated below.
C. COMP ACTION. The'material as thus spread shall be compacted with a powered steel wheel
tandem roller weighing not less than eight (8) nor more than ten (10) tons or by other
equipment producing equivalent density.
D. BASE TOLERANCE. Surface of the base course as thus compacted shall not vary more
than one-half inch (W') in ten feet (10') measured in any direction.
E. Refer to the section of the specifications titled "Graded Aggregate Base Course" for
additional requirements.
-03. ASPHALT SURFACE COURSE:
A surface course of hot plant mix having a maximum aggregate size of three-eighths inch
(3/8") in accordance with specifications of the Asphalt Illstitute shall be constructed over the base
course to a compacted thickness of not less than one and a half inches (1 W') as shown on the
drawings.
A. SPREADING. This hot plant mix shall be spread by methods and in a manner proposed by
the Contractor to meet the tolerances specified herein.
B. COMPACTION. The mix as thus spread shall be thoroughly compacted with a powered
steel wheel tandem roller weighing not less than two (2) nor more than size (6) tons.
C. TOLERANCE. The finished surface of the surface course shall not vary more than one-
eighth inch (1/8") in ten feet (10') when measured in any direction.
TS-14-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
D. The final course of asphalt shall consist of a one and a half thick mixture of asphalt and
aggregate not to exceed three-eighths inch (3/8") in size. This standard is as outlined by the
United States Tennis Court and Track Builders Association (USTC & TBA) and the Untied
States Tennis Association (USTA).
E. Refer to the section of the specifications titled "Bituminous Paving" for additional
requirements.
-04. MEASUREMENT AND PAYMENT:
Payment for Tennis Court Paving shall be made at the unit price as shown in the Bid
Schedule for Tennis Court Paving.
TS-14-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
;..02.
-03.
-04.
A.
B.
SECTION TS-15
SURFACING FOR TENNIS COURTS
GENERAL:
The specification is for the surfacing of a championship tennis court.
SURFACING REOUIREMENTS:
1. Pressure wash if necessary
2. Fill depressions (bird baths) that cover a nickel with acrylic sport patch.
3. Apply two coats of acrylic resurfacer.
4. Apply three coats of acrylic color coating over the entire surface area. Colors to be
used will be blue inside the lines of the playing surface and green outside the lines
of the playing surface. These colors shall closely match the colors used at the 2007
U.S. Open Series.
5. Stripe courts with textured line paint.
6. Contractor is to supply color chart to owner for selection of colors prior to purchasing
materials.
MATERIALS:
1. Acrylic Resurfacer from "Sport Surfaces Int'l, Inc., or approved equal.
2. AcryTech with UV-15 Colorguard from "Sport Surfaces Int'l, Inc., or approved
equal.
3. AcryTech Line Paint from "Sport Surfaces Int'l, Inc., or approved equal.
4. Silica Sand (80-100) mesh
SURFACING:
SURFACE PREPARATION: Surface to be coated must be sound, free of loose dirt, dust,
or other foreign matter. Cracks to be repaired must be cleaned by pressure washer,
compressed air or mechanical device. Under no circumstances should cracks be made wider
by using mechanical routers or saws.
PATCHING AND DEPRESSIONS: The surface should be flooded with water and allowed
to drain for 1 hour. Areas retaining water deeper than the thickness of a nickel should be
patched using acrylic sport patch using the following formula:
Acrylic Sport Patch
Sand
Portland Cement
3 gallons
1001bs.
1 gallon
TS-15-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-05. SURFACER APPLICATION:
Surfacer is to be applied in two coats to a properly scraped and blown surface at a rate of .08
gallons per square yard for two coats.
Acrylic Resurfacer 27 gallons
Sand 250 lbs.
Water 15 gallons
After drying, the surface is to be scraped until free of ridges and excess material.
-06. ACRYLIC COLOR COATING:
Acrytech with UV-15 Colorguard or approved equal shall be applied to a properly scraped
and blown surface at a rate of .04 gallons per square yard per coat. The second and third coat
application should not be made until the surface is thoroughly dry. Coating is to be mixed as
follows:
AcryTech with UV-15 Colorguard
Silica Sand
Water
Y2. drum
200 lbs.
15-18 gallons
-07. LINE PAINT:
Tennis court line primer is to be applied before the application of two (2) coats of AcryTech
White Line Paint, or approved equal.
-08. MEASUREMENT AND PAYMENT:
Payment for Tennis Court Surfacing shall be made at the unit price amount as shown in the
Bid Schedule for Tennis Court Surfacing.
TS-15-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-16
NET AND NET POSTS
-01. POST FOUNDATIONS:
Post foundations shall be eighteen inches (18") in diameter at the top, not less than 36" at the
bottom, and not less than forty-two inches (42") in depth. Foundations shall be situated as to provide
a distance between posts of forty-two feet (42') on double courts. This dimension shall be from
center of post to center of post. Concrete for foundations shall be well-graded rock, gravel or stone
mixed in ratios of six (6) standard 94 pound sacks of cement to not more than six (6) U.S. gallons
of water, attaining a compressive strength of not less than three thousand five hundred (3,500)
pounds per square inch at the twenty-eighth (28th) day after pouring. Foundations shall be so
designed and poured and the posts set so as not to cause cracking or other damage to the finished
court surface.
.' .,~
':'02. NET POSTS AND SLEEVES:
Net posts shall be galvanized steel or aluminum. They shall be installed in sleeves. Tennis
post ground sleeves shall be PVc. Posts shall have an outside diameter of not less than 2 - 7/8". The
net post shall proj ect no more than 1" above the top of the net cord. Minium yield strength is 1,100
lbs., with a minium of 1 ,500 lbs. tensile strength. Mechanical tensioning devices (worm gear, ratchet
reel, or screw-type) are to be limited in the amount of force applied to the net post, not to exceed 1/2
post yield strength. Posts and post sleeves shall be set 42' apart for a doubles court, measured from
the center of one post to the center of the other. Posts shall be set plumb and true so as to support
the net at a height of 42" above the court surface. Posts and sleeves shall be set where indicated on
the drawings.
-03. CENTER STRAP ANCHOR:
The ground anchor shall be made from a strong, non-corrosive metal pipe not less than 10"
in length, 1 5/8" o.d. minimum.
A non corrosive 1/4" o.d. pin is centered through the pipe 1/4" to 3/8" below the opening for
the purposes of attaching a center strap hook.
A center strap anchor shall be set in 'concrete footings measuring twelve inches (12 If) in
diameter at the top and not less than fifteen inches (15") in diameter at the bottom. The top of a
concrete footing set in an asphalt court shall be round to minimize radical cracking. The cross pin
in the ground anchor shall be flush with the court and parallel to the net. The footings shall have a
depth of 20" and a base course of 6".
-04. NET:
A tennis net measuring forty-two feet (42') long and three and one fourth feet (3 14') wide and
otherwise conforming to the regulations of the United States Tennis Association shall be provided
for each court.
TS-16-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
The net is composed of eight distinct parts referred to by various names. For the purpose of
this Guideline, components are called the body, headband, cable, side bindings, bottom bindings,
dowels, tie strings, and lacing twine.
A. BODY: The net body shall be black weather resistant synthetic netting 1 3/4" square mesh
and the tensile strength of the twine shall not be less than 275 lbs.
B. HEADBAND (top binding): The headband shall be made of two pieces or plies, or a single
ply with double thick material, and shall be 2" - 2 1/2" wide. The outer piece shall be
manufactured from a white synthetic material or white canvas, treated for resistance to
sunlight and mildew. Inner and outer headbands shall be folded over the cable' and lock
stitched with four separate rows of stitching the length of the net.
C. CABLE: The cable shall be fabricated from multi-stranded galvanized steel wire rope. It
shall have a minium core diameter of5/32" (excluding coating) and be at least 46' in length.
Its tensile strength shall be not less than 2,600 lbs. The cable may be vinyl coated.
D. SIDE BINDINGS (tapes): Side bindings shall be fabricated of black synthetic material,
treated to prevent deterioration from sunlight. Five nickel or brass grommets shall be placed
equidistantly from top to bottom at each side of the net to accommodate the lacing twine
after forming a pocket to accept dowels.
E. BOTTOM BINDINGS (tape): Bottom bindings shall be made of black abrasion-resistant
synthetic material, treated to prevent deterioration from sunlight.
F. DOWELS: Dowels shall be 3/8" - 5/8" round and a maximum of 40" in length and shall be
made of wood, metal or fiberglass.
G. TIE STRINGS: Tie strings shall be made from black u.V. stabilized, synthetic cord, not less
than 60" long, and having a breaking stain of not less than 275 lbs. One piece is required for
each end of the net headband.
H. LACING TWINE: Lacing twine shall be made from the same material as tie strings, but
shall be not less than 96" inches long. There shall be one such piece for each side binding.
Note: the tie string and lacing twine may be one continuous piece.
*The nets shall be #2002 Edwards #40LS Tennis Nets or approved equal.
-05. TAUTNESS AND CENTER HEIGHT:
Check net tautness by suspending a 14 lb. (6.36 kg) weight from the center of a doubles net
and wind the net slowly to a center height of 36" (914 mm). Install the center strap and adjust it to
maintain the height of 36" (914 mm). Remove the weight. This method produces a net cable
tautness of approximately 500 - 550 lbs (227-250 kg).
TS-16-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-06. CENTER STRAP:
A center strap shall be used to hold the net at the proper height of 36" at its Center. A white
strap no more than 2" wide, made from canvas or synthetic material treated for resistance to sunlight
and mildew, shall be provided. A height adjusting non-corrosive buckle or buckles must prevent
slippage when fully stressed. At the bottom of the strap, a non-corrosive spring loaded hook shall
be used to attach the center strap to the ground anchor pin.
-07. MEASUREMENT AND PAYMENT:
Payment for Net and Net Posts shall be made at the unit price amount shown in the Bid
Schedule for Tennis Net and Net Posts. '
TS-16-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
A.
B.
c.
-02.
A.
B.
c.
I
SECTION TS-17
CHAIN LINK FENCING
CHAIN LINE FENCE FABRIC:
PVC COATED (Fused): Coated over galvanized wire: ASTM F 668, class 2B, 7 mil (0.18
mm) thermally fused polyvinyl chloride in a color to be selected by the owner. Galvanized
steel core wire should meet ASTM A 641, tensile strength 75,000 psi (571 Mpa), 11 gauge
(0.120" [3.05 mm]). Contractor shall supply Owner with color chart for selection of color
prior to purchasing materials.
SIZE: Helically wound and woven to a height of 10.0" (3.048 m). Fabric should be 1 3/4"
(44 mm) diamond mesh of 11 gauge (0.120" [3.05 mm]) core wire and a break load of850
pounds.
SELVAGE: Fabric should be knuckled at the top and at the bottom.
STEEL FENCE FRAMING:
FRAMING TYPES:
1. Type 1: ASTM F 1083, standard weight schedule 40; minimum yield strength of
25,000 psi (170 Mpa); sizes as indicated. Hot-dipped galvanized with minimum
average 1.8 oz/sf (550 glm2) of coated surface area.
2. PVC Coated Finished: In accordance with ASTM F 1043, apply supplemental color
coating of 10-15 mils (0.254 - 0.38 mm) ofthermally fused PVC in a color selected
by the owner, to match the fabric. Contractor shall supply Owner with color chart
for selection of color prior to purchasing materials.
FRAMING SPECIFICATIONS:
Structure
10' Height
End, Corner and Gate Post
Line (Intermediate) Post
Rails & Braces
3.0"OD
3.0"OD
1.580" OD
GATES:
1.
Gates shall be chain link swing gates as specified in ASTM Section 02831 C.
TS-17-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-03.
A.
-04.
-05.
A.
PVC COATED ACCESSORIES:
CHAIN LINK FENCE ACCESSORIES:
1. ASTM F 626: Provide items required to complete fence system. Galvanize each
ferrous metal item and finish to match framing.
2. Post Caps: Formed steel, malleable cast iron, or aluminum alloyweathertight closure
cap for tubular posts. For each line post, provide tops to permit passage oftop rail.
Top Rail and Brace Ends: Formed steel or malleable cast iron for connection of rail
and brace to terminal posts.
3. Top Rail Sleeves: 5" (150 mm) sleeve allowing for expansion and contraction of top
. .
rail.
4. Wire Ties and Clops: 10 gauge (0.135" [3.43 mm]) galvanized steel wire for
attachment of fabric to line posts. Double wrap 13 gauge (0.092" [2.324 mm]) for
rails, and braces. Hog ring ties of12-1/2 gauge (0.0985" [2.502 mm]) for attachment
of fabric to tension wire.
5. Brace and Tension (Stretcher bar):
a. Bands shall be pressed steel.
b. Tension (Stretcher) bars shall be one-piece lengths, equal to 2" (50 mm) less
than full height of fabric with a minimum cross-section of3/16" x 3/4" (4.76
mm x 19 mm) or equivalent, fiberglass rod. Provide tension (stretcher) bars
where chain link fabric meets terminal posts.
6. Bottom Tension Wire: Bottom tension wire should be used except where continuous
bottom rail is specified. Bottom tension wire should be in accordance with ASTM
A 824, with coating to match that selected for the fabric.
7. Truss Rods: Truss rods shall be steel rods with minium diameter of5/16" (7.9 mm).
8. Nuts and Bolts: Nuts and bolts are galvanized but not vinyl coated. Color coat nuts
and bolts with cans ofPVC touch up paint.
SETTINGS MATERIALS:
Concrete, with a minium 28-day compressive strength of3,000 psi (20 Mpa).
EXECUTION:
EXAMINATION:
1. . Verify areas to receive fencing are completed to final grades and elevations.
TS-17-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
B.
C.
D.
E.
F.
G.
H.
-06.
A.
2. Ensure property lines and legal boundaries of work are clearly established.
CHAIN LINK FENCE FRAMING INST ALLA TION:
1. Install chain link fence in accordance with ASTM F 969 and manufacturers'
instructi ons.
2. Locate a terminal post at each fence termination, at each change in horizontal
direction of 300' or more, and at each change in height.
3. Space lines post uniformly at a maximum of 10' (3.04 m) on center. Posts may be
spaced uniformly at a closer distance (for example 8' [2.44 mD for greater strength.
4. Concrete set posts: Drill holes in firm, undisturbed or compacted soil",Holes should
have diameter 4 times greater than outside dimension of post, and depths
approximately 6" (150 mm) deeper than post bottom. Excavate deeper as required
for adequate support in soft and loose soils, and for posts with heavy lateral loads.
Set post bottom 36" (900 mm) below surface when in firm, undisturbed soil. Place
concrete around posts in a continuous pour. Trowel finish around post. Slope to
direct water away from posts.
GATE HARDWARE: Set keepers, stops, sleeves, and other accessories into concrete.
ALIGNMENT: Check each post for vertical and top alignment, and maintain in position
during placement and finishing operations.
BRACING: Install horizontal pipe brace at mid-height, on each side of terminal posts.
Firmly attach with fittings.
TENSION WIRE: Provide tension wire at bottom of fabric (and at top, if top rail is not
specified). Install tension wire before stretching fabric and attach to each post with ties or
clips. Secure tension wire to fabric with 12-1/2 gauge (.09585" [2.502 mmD hog rings 24"
(609.6 mm) on center.
TOP RAIL: Install full 21 ' (640 m) lengths whenever possible. Connect lengths with sleeves
for rigid connections under expansion/contraction conditions. Top rail with swedged ends
may be joined directly.
BOTTOM RAILS: Install bottom rails, where specified, between posts fittings and
accessones.
CHAIN LINK FABRIC INSTALLATION:
FABRIC: Install fabric on the inside toward the playing area, and attach so that fabric
remains in tension after pulling force is released. Leaveapproximately 1" (25 mm) between
finish grade and bottom selvage. Attach fabric with wire ties to line posts at 15" (380 mm)
on center and to rails, braces, and tension wire at 24" (600 mm) on center.
TS-17-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
B. TENSION (Stretcher) BARS: Pull fabric taut; thread tension bar through fabric and attach
to terminal posts with bands or clips spaced maximum of 15" (350 mm) on center.
-07. GATE INSTALLATION:
A. Install gates plumb, level and secure for full opening without interference.
B. Attach hardware by a means which will prevent unauthorized removal.
C. Adjust hardware for smooth operation.
-08. ACCESSORIES:
A. TIE WIRES: Bend ends wire to minimize hazard to persons and clothing.
B. FASTENERS: Install nuts on side offence opposite fabric side for added security.
-09. MEASUREMENT AND PAYMENT:
Payment for chain link fence shall be made at the unit price amount shown in the Bid
Schedule for 10' P.V.C. Coated Chain Link Fence, including 3' gates.
TS-17-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-18
WINDSCREENS
-01. GENERAL:
Windscreens provided shall be 6 feet tall and installed 2 feet from the top and bottom ofthe
fence.
-02. FABRIC:
Windscreens shall be vinyl coated polyester fabric made from polyester material weighing
at least 3.0 ounces per square yard and coated after weaving with a 4.0 ounce per square yard dark
green color vinyl. The vinyl should consist of high quality PVC ingredients for the highest possible
ultraviolet light resistance, abrasion stamina and mildew resistance. Contractor shall provide Owner
with color chart for color selection prior to purchasing materials.
-03. HEMS:
All hems shall be reinforced and have two rows of stitching.
-04. THREAD:
All hems and seams should be sewn with a heavy duty weather and ultraviolet light resistant
polyester thread or equivalent.
-05. GROMMETS:
No.2 or No.3 solid brass grommets with plain washers, 12 inches to 18 inches on center
shall be used to fasten the windscreen to the fence. Use all grommets during installation.
-06. AIR VENTS:
Windscreens shall have air vents which are open and finished with a maximum spacing of
10 feet.
-07. MEASUREMENT AND PAYMENT:
Payment for windscreens shall be made at the unit price amount shown in the Bid Schedule
for 6' Vinyl Coated Polyester Windscreens.
TS-18-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I