HomeMy WebLinkAboutBLAIR CONSTRUCTION SPIRIT CREEK FORCE MAIN
Type "A" Silt Fence
Type "C" Silt Fence
Double Row Type "C" Silt Fence
$3.00ILF
$4.00ILF
$5.50ILF
Addendum No. 1
to the
Contract Documents and Drawings
for the construction . of
PROJECT NO. 80500
SPIRIT CREEK FORCE MAIN
Our File No. 2003-259
September 28, 2005
1. The following questions from the Pre-Bid Conference and subsequent submitted questions have been
. addressed:
A. The Soil Erosion and Sediment Control General Note #2 states as a minimum silt fence
shall be placed continuously along lower side of construction easement. Other silt fence
may be required as directed by engineer and other silt fence is reflected on the
drawings. This makes it very difficult to estimate a lump sum price. Could we get a
specific quantity of silt fence to bid or have a line item added to the bid schedule?
It is anticipated that the silt fence shown on the plans will be adequate for erosion and
sedimentation control. However, should silt fence be required which exceeds the quantity
shown on the contract plans, it will be paid in accordance the unit prices below. The
placement of this additional silt fence must be approved by the Owner's Representative prior
to installation.
B. The Soil Erosion and Sediment Control General Note #3 states that no grubbing nor
grading shall be done until silt barriers are in place. Is stump removal considered
grubbing?
Yes, by definition stump removal is considered grubbing.
C. Will all ductile iron pipe, gravity and force main, have 401 epoxy liner?
Yes, as described in Specification Sub-Section TS-6-0 I.E, all ductile iron pipe supplied for
the purpose of transmitting sanitary sewage shall be lined with Protecto 40 I ceramic epoxy.
B. Ar-e-an-easements-aequir-ed.~
No, there are a few easements acquisitions which are still in progress. It is our expectation
that these will be finalized prior to the Contractor beginning construction.
Addendum No. I Page 1 of 6
Addendum No.1 Page 2 of 6
E. Will there be any Special Condition items added to this project after the bid that may
require additional work or material?
At this time, there are no known Special Conditions relating to easement acquisition which
are not covered by either the contract drawings or contract specifications that would require
additional work or material. However, if conditions arise which require additional work or
materials that cannot be covered by existing pay items, then additional costs will be
negotiated at that time.
F. Will mechanical joint field locks be accepted in lieu of mega lugs?
Yes, as stated in Specification Sub-Section TS-14-04.A.8.a, Field LOK Joints, as
manufactured by U.S. Pipe, will be accepted.
G. Will foreign materials be allowed?
Yes, as long as these materials meet the project specifications and are either listed on the
plans or specifications or approved by the Owner's Representative during the submittal
process, they will be allowed.
H. What are the intentions for abandonment of the existing trunk sewer main downstream
of the tie in?
Currently, the abandoned sewer main will only be plugged as shown on the plans. Should
additional measures be required in the future, the costs for those additional services and/or
materials will be negotiated at that time.
1. Will there be a price break down required for the lump sum items?
The only lump sum item which will require a price breakdown is Lump Sum Construction.
However, this breakdown will not alter the total amount paid to the Contractor; itwill only
provide a means of determining monthly payment of this pay item. The Contractor will still
be paid for the entire lump sum amount as long as the overall scope of the project is not
drastically changed.
J. Will the temporary construction easements need to be cleared?
The Contractor will not be required to dear more temporary easement than is needed for
construction.
K. The statement was made that if the wetlands permit is not obtained prior to notice to
proceed, the contractor should make provisions in his bid for having various sections
of the project unavailable for an undefined period of time. Please confirm and/or
clarify this.
The U.S. Army Corps Nation Wide Permit for this project has been approved.
Addendum No. 1 Page 3 of 6
L. There will not be Railroad Permit, but the contractor is expected to follow any
applicable requirements that may be imposed in the vicinity of the railroad property.
Please derme the requirements, particularly if there is a need for RR insurance or RR
flaggers.
Any required insurance exceeding that which is required by the Contract Documents shall
be paid by the Owner.
It is anticipated that a flagman will not be required because all work and equipment, with the
exception ofthe bore itself, will be outside of the railroad Right-of-Way. However, should
the Contractor need access within the Right-of Way necessitatiQ.g the need of a flagman, the
cost for this flagman shall be the responsibility of the Contractor.
M. It was stated there would not be a cost involved for water needed for testing. Please
confirm.
There will be no cost for water used during testing as long as it is obtained from the Augusta
Utilities Department's System.
N. The EPD - Construction Land Disturbances Fees will be paid by the Owner. Please
confirm.
As stated during the Pre-Bid Conference, the EPD-Construction Land Disturbances Fees will
be paid by the Owner.
n. The following clarifications/amendments have been made to the contract drawings: (No revised
contract drawing sheets will be reissued.)
A. Sheet 42 - Air Release Valve Detail- Add the table and notes as shown on Sheet 4 of this
addendum to the detail.
B. Sheet 44 - Crushed Stone Construction Outlet Detail - Add the following note, "The
construction outlets shown on the plans are shown at anticipated access locations. The
Contractor shall be responsible for determining the exact locations and required quantity of
construction outlets needed. All costs for these construction outlets shall be included in the
Lump Sum Construction Pay Item. No additional payment shall be made for these items."
m. The following items have been revised or added to the contract documents and specifications:
A. Instructions to Bidders - IB-03 - Revise first sentence of second paragraph to "Every request
for such interpretations should be in writing addressed to the Director of Augusta Utilities
Department c/o Augusta Purchasing Department, 530 Greene Street, Room 605, Augusta,
Georgia 30911 and to be given consideration must be received by the deadline set at the Pre-
Bid Conference."
B. Supplementary Conditions - SC-OIO - Add the attached specification on Sheets 5-6 ofthis
addendum.
SHEET 4 OF 6
9/28/05 i
;
APPROXIMA 1E MINIMUM DIRECT
NUMBER CONNECT
LOCATION PRESSURE VENTING
1 76+00 >15 PSI YES
2 78+50 >15 PSI YES
3 92+50 >15 PSI YES
4 100+75 >15 PSI YES
5 103+00 >15 PSI YES
6 110+00 >15 PSI NO
7 155+00 7.5 PSI NO
8 164+00 o PSI NO
9 202+40 1. 5 PSI YES
10 257+60 5.8 PSI YES
11 259+ 75 5.8 PSI YES
12 308+20 4.1 PSI NO
13 336+ 75 1 PSI NO
14 363+50 o PSI NO
15 372+00 o PSI NO
16 400+10 1 PSI NO
17 418+00 o PSI NO
NOTES:
1. ALL AIR RELEASE VALVES SHALL BE 4- VENT-Q-MAT SERIES RGX OR APPROVED EQUAL
2. ALL AIR RELEASE VALVES SHALL BE PROVIDED WITH (2) 1- STAINLESS STEEL BALL VALVES FOR
ISOLATION OF PORTS.
3. VALVES WHICH CALL FOR DIRECT CONNECT VENTING SHALL BE EQUIPPED WITH ALL NECESSARY
PIPING TO CONNECT VENT PIPE DIRECTLY TO VALVE DISCHARGE. THE VENT PIPES FOR THESE
VALVES SHALL BE EXTENDED TO A MINIMUM OF l' ABOVE THE 100 YEAR FLOOD PLAIN.
I
I
AUGUS~c~~~~~~TMENT......1
-SPIRIT CREEK FORCE MAIN- I
PREPARED BY I
.^ Cranston, Robertson & Whitehurst. P.C. i
~. _ EWS SlllEET - P.Q. DRAWER 2!148 - _.... GEIlRllIA 3Ill103 !
~) BGNEERS PH: mi) 7.22-ZSB~ ~cam.uf.mrcs 1
Annpnnnm liIn _ 1 P~VP "i nf fi
RECORD DRAWINGS
(How we expect contractor to handle inthe field)
1. RECORD DRAWINGS
1. Quality Assurance:
1. Furnish qualified and experienced person, whose duty and responsibility shall be
to maintain record drawings.
2. Accuracy of Records:
a. Coordinate changes within record drawings, making legible and accurate
entries on each sheet of Drawings and other documents where such entry
is required to show change.
b: Purpose of Project record drawings is to document factual information
regarding aspects of Work, both concealed and visible, to enable future
modification of Work to proceed Without lengthy and expensive site
. measurement, investigation, and examination.
3. Make entries within 24 hours after receipt of information that a change in Work
has occurred.
4. Prior to submitting each request for progress payment, request
PROFESSIONAL's review and approval of current status of record drawings.
Failure to properly maintain, update, and submit record documents may result in
a deferral by PROFESSIONAL to recommend the whole or any part of the
CONTRACTOR's Application for Payment, either partial or final.
2. PART 3 EXECUTION
1. MAINTENANCE OF RECORD DRAWINGS
A. General:
1. Promptly following commencement of Contract Times, secure from
PROFESSIONAL at no cost to CONTRACTOR, one complete, full size
set of Contract Documents.
2. Label or stamp each record document with title, "RECORD
DOCUMENTS," in neat large printed letters.
3. Record information concurrently with construction progress and within
24 hours after receipt of information that a change has occurred. Do not
cover or conceal Work until required information is recorded.
B. Preservation:
1. Maintain documents in a clean, dry, legible condition .and in good order.
Do not use record drawings for construction purposes.
2. Make drawings available at all timesfor observation by
PROFESSIONAL.
C. Making Entries on Drawings:
1. trsmg an erasaDteco1oreo-JYenci1(norinkOTimieiibIe-penciiJ~clearly
describe change by graphic line and note as required.
I'
I
I
a. Color Coding:
1. Green when showing information deleted from
Drawings.
2. Red when showing information added to Drawings.
3. Blue and circled in blue to show notes.
2. Date entries.
3. Call attention to entry by "cloud" drawn around area or areas affected.
4. Legibly mark to record actual changes made during construction,
including, but not limited to:
a. Horizontal and vertica11ocations of existing and new
Underground Utilities and appurtenances, and other underground
structures, equipment, or Work. Reference to at least two
measurements to permanent surface features such as light poles,
fIre hydrants, storm inlets boxes, edges of pavement, etc. Such
locations shall be recorded at intervals no greater than 200 feet
b. Locate existing piping and items critical to the interface between
existing physical conditions or construction and new
construction.
I-
I
I
I'
I
I
I
c. Changes made by Addenda and Field Orders, Work Change
Directive, Change Order, Written Amendment, and
PROFESSIONAL's written interpretation and clarification using
consistent symbols for each and showing appropriate document
tracking number.
I
I
I
I
I
I
I
I
I
Arlrl<>nrl..... l\Tn
1)"'...... ~ no.;' ~
FOR
CONTRACT DOCUMENTS AND SPECIFICATIONS
BOND PROJECT NO. 80500
SPIRIT CREEK FORCE MAIN
Augusta, Georgia
AUGUSTA-RICHMOND COUNTY COMMISSION
The Honorable William H. Mays, Mayor
Betty Beard
Marion F. Williams
Barbara Sims
Richard Colclough
Bobby G. Hankerson
Andy Cheek
Tommy Boyles
Jimmy Smith
Freddie Handy
Don A. Grantham
Frederick L. Russell
Administrator
Max Hicks
Director, Augusta Utilities Department
Cranston, Robertson & Whitehurst, P.c.
Engineers - Planners - Surveyors
Augusta, Georgia
August 2005
TABLE OF CONTENTS
SECTION TITLE NO. OF PAGES
I Invitation for Bids 1
ill Instructions to Bidders 3
P Proposal 6
BB Bid Bond 2
NA Notice of Award I
A Agreement 3
PB Performance and Payment Bonds 5
NP Notice to Proceed 1
GC-O Index to General Conditions I
GC General Conditions 64
SC-O Index to Supplemental Conditions 1
SC Supplemental Conditions 12
TS-O Index to Technical Specifications 1
TS Technical Specifications 137
Invitation To Bid
Sealed bids will be received at this office until 3:00 p.m., Wednesday, October 5, 2005: This project will include approximately
37,000 L.F. of a 20" diameter ductile iron force main that will start at the new Spirit Creek Pump Station and will terminate at the
James B. Messerly Waste Treatment WPCP. This project will include the following services: land clearing and excavation, laying
pipe, jacking and boring, backfilling, testing and installation of air vents.
Bid #05-132
Spirit Creek Force Main for Augusta Utilities
BID's will be received by Augusta, GA Commission hereinafter referred to as the OWNER at the offices of:
Geri A. Sams
Procurement Department
530 Greene Street - Room 605
Augusta, Georgia 30911
706-821-2422
BID documents may be obtained at the office of Augusta, GA Procurement Department, 530 Greene Street- Room 605, Augusta, GA
30911 for $150 non-refundable per set. Documents may be examined by appointment only during regular business hours at the offices
of Augusta, GA Procurement Department, Augusta Dodge Room 1281 Broad Street, Augusta, GA 30901 or Augusta Builders
Exchange, 1262 Merry Street, Augusta, GA 30904.
A Mandatory Pre-Bid Meeting will be held on Tuesday, September 20, 2005 @ 10:00 a.m. in the conference room of the Procurement
Department Room 605. The last day for questions will be Friday, September 23, 2005 @ 4:00 p.m.
No bid will be accepted by fax, all must be received by mail or hand delivered.
It is the wish of the Owner that minority businesses are given the opportunity to BID on the various parts of the work. This desire on
the part of the Owner is not intended to restrict or limit competitive bidding or to increase the cost of the work. The Owner supports a
healthy free market system that seeks to include responsible businesses and provide ample opportunity for business growth and
development.
No BID may be withdrawn for a period of 60 days after time has been called on the date of opening. A 10% Bid bond is required to be
submitted in a separate envelope so marked along with the bidders' qualifications; a 100% performance bond and a 100% payment
bond will be required for award.
Bidders will please note that the number of copies requested; all supporting documents including financial statements and references
and such other attachments that may be required by the bid invitation are material conditions of the bid. Any package found incomplete
or submitted late shall be rejected by the Procurement Office. Any bidder allegedly contending that he/she has been improperly
disqualified from bidding due to an incomplete bid submission shall have the right to appeal to the appropriate committee of the
Augusta Commission. Please mark BID number on the outside of the envelope.
Bidders are cautioned that sequestration of BID documents through any source other than the office of the Procurement Department is
not advisable. Acquisition of BID documents from unauthorized sources placed the bidder at the risk of receiving incomplete or
inaccurate information upon which to base his qualifications.
Augusta has a Link Deposit program designed to provide loans to eligible local Small, Minority and Women Owned Businesses. For
more information about this program Human Resources Department at 706-821-2303.
GERI A. SAMS, Procurement Director
Publish:
Augusta Chronicle
Metro Courier
August 25, September 1, 8, 15,2005
August 31, 2005
cc:
Tameka Allen
Yvonne Gentry
Max Hicks
Doug Cheek
Augusta, GA Interim Deputy Administrator
Augusta, GA DBE
Augusta, GA Utilities
Augusta, GA Utilities
Revision Date
October, 2001
SECTION IB
INSTRUCTION TO BIDDERS
IB-01
GENERAL
All proposals must be presented in a sealed envelope, addressed to the Owner. The
proposal must be filed with the Owner on or before the time stated in the invitation for bids. Mailed
proposals will be treated in every respect as though filed in person and will be subject to the same
requirements.
Proposals received subsequent to the time stated will be returned unopened. Prior
to the time stated any proposal may be withdrawn at the discretion of the bidder, but no proposal
may be withdrawn for a period of sixty (60) days after bids have been opened, pending the execution
of contract with the successful bidder.
IB-02
EXAMINATION OF WORK
Each bidder shall, by careful examination, satisfy himself as to the nature and location
of the work, the conformation of the ground, the character, quality and quantity of the facilities
needed preliminary to and during the prosecution of the work, the general and local conditions, and
all other matters which can in any way affect the work or the cost thereof under the contract. No oral
agreement or conversation with any officer, agent, or employee of the Owner, either before or after
the execution of the contract, shall affect or modify any of the terms or obligations therein.
IB-03
ADDENDA AND INTERPRETATIONS
No interpretation of the meaning of plans, specifications or other prebid documents
will be made to any bidder orally.
Every request for such interpretation should be in writing addressed to the Director
of Augusta Utilities Department c/o Augusta Purchasing Department, 530 Greene Street, Room 605,
Augusta, Georgia 30911 and to be given consideration must be received at least five days prior to
the date fixed for the opening of bids. Any and all such interpretations and any supplemental
instructions will be in the form of written addenda to the specifications which, if issued, will be sent
by certified mail with return receipt requested to all prospective bidders (at the respective addresses
furnished for such purposes), not later than three days prior to the date fixed for the opening of bids.
Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder
from any obligation under his bid as submitted. All addenda so issued shall become part of the
Contract Documents.
IB-04
PREPARATION OF BIDS
Bids shall be submitted on the forms provided and must be signed by the bidder or
his authorized representative. Any corrections to entries made on bid forms should be initialed by
the person signing the bid.
IE-I
Revision Date
October, 2001
Bidders must quote on all items appearing on the bid forms, unless specific directions
in the advertisement, on the bid form, or in the special specifications allow for partial bids. Failure
to quote on all items may disqualify the bid. When quotations on all items are not required, bidders
shall insert the words "no bid" where appropriate.
Alternative bids will not be considered unless specifically called for.
Telegraphic bids will not be considered. Modifications to bids already submitted will
be allowed if submitted by telegraph prior to the time fixed in the Invitation for Bids. Modifications
shall be submitted as such, and shall not reveal the total amount of either the original or revised bids.
Bids by wholly owned proprietorships or partnerships will be signed by all owners.
Bids of corporations will be signed by an officer of the firm and his signature attested by the
secretary thereof who will affix the corporate seal to the proposal.
NOTE: A 10% Bid Bond is required in all cases.
IB-OS
BASIS OF AWARD
The bids will be compared on the basis of unit prices, as extended, which will include
and cover the furnishing of all material and the performance of all labor requisite or proper, and
completing of all the work called for under the accompanying contract, and in the manner set forth
and described in the specifications.
Where estimated quantities are included in certain items of the proposal, they are for
the purpose of comparing bids. While they are believed to be close approximations, they are not
guaranteed. It is the responsibility of the Contractor to check all items of construction. In case of
error in extension of prices in a proposal, unit bid prices shall govern.
IB-06
BIDDER'S OUALIFICATIONS
No proposal will be received from any bidder unless he can present satisfactory
evidence that he is skilled in work of a similar nature to that covered by the contract and has
sufficient assets to meet all obligations to be incurred in carrying out the work. He shall submit with
his proposal, sealed in a separate envelope, a FINANCIAL EXPERIENCE AND EQUIPMENT
STATEMENT, giving reliable information as to working capital available, plant equipment, and his
experience and general qualifications. The Owner may make such investigations as are deemed
necessary to determine the ability of the bidder to perform the work and the bidder shall furnish to
him all such additional information and data for this purpose as may be requested. The Owner
reserves the right to reject any bid if the evidence submitted by the bidder or investigation of him
fails to satisfy the Owner that such bidder is properly qualified to carry out the obligations of the
contract and to complete the work contemplated therein. Part of the evidence required above shall
consist of a list of the names and addresses of not less than five (5) firms or corporations for which
the bidder has done similar work.
lB-2
Revision Date
October, 2001
IB-07
PERFORMANCE BOND
At the time of entering into the contract, the Contractor shall give bond to the Owner
for the use of the Owner and all persons doing work or furnishing skill, tools, machinery or materials
under or for the purpose of such contract, conditional for the payment as they become due, of all just
claims for such work, tools, machinery, skill and terms, for saving the Owner harmless from all cost
and charges that may accrue on account of the doing of the work specified, and for compliance with
the laws pertaining thereto. Said bond shall be for the amount of the contract satisfactory to the
Owner and authorized by law to do business in the State of Georgia.
Attorneys-in-fact who sign bonds must file with each copy thereof a certified and
effectively dated copy of the power of attorney.
IB-08
REJECTION OF BIDS
These proposals are asked for in good faith, and awards will be made as soon as
practicable, provided satisfactory bids are received. The right is reserved, however to waive any
informalities in bidding, to reject any and all proposals, or to accept a bid other than the lowest
submitted if such action is deemed to be in the best interest of the Owner.
ffi-09
MINORITY AND ECONOMICALLY DISADVANTAGED BUSINESS
SUPPORT
It is the intent of the Augusta-Richmond County Commission to increase the
involvement of qualified minority and economically disadvantaged businesses in the contracted work
of County Government.
In an effort to support this intention, this project is offered to all qualified firms. The
bids will be evaluated based on qualifications, price and construction time. With all other items
being considered equal, the contract, if awarded will be awarded to a minority and economically
disadvantaged firm or a firm that has included such firms as subcontractors on this project.
The bidders are required to submit a statement of qualifications for themselves and
a list of qualified subcontractors (including local vendors) and all minority or economically
disadvantaged firms with their bid package. If the firm does not fall into this category, no
information is necessary.
IB-3
DATE:
(/c:.A:::, her'
~ Zoo S-
f
COpy
SECTION P
PROPOSAL
Gentlemen:
In compliance with your invitation for bids, the undersigned hereb~fl proposes to furnish all
labor, equipment and materials, and to perform all work for the project referred to herein as:
BOND PROJECT NO. 80500
SPIRIT CREEK FORCE MAIN.
The undersigned hereby agrees that, upon written acceptance of this bid, he will
within 10 days of receipt of such notice execute a formal contract agreement with the Owner, and
that he will provide the bond or guarantees required by the contract documents.
The undersigned hereby agrees that, if awarded the contract, he will commence the
work within Ten ClQ) calendar days after the date of written notice to proceed, and that he will
complete the work within Two Hundred. Seventy (270) calendar days after the date of such notice.
The undersigned acknowledges receipt of the following addenda:
,No. I duAed 9'1?o;/o~
I /
Enclosed is a bid guarantee, consisting of ~ '-E)I~I '73-"7d
in the amount of ( 100/0 <:>/J- bd) I 5'~81 S-/4-.:!2-
Respectfully submitted,
L3/c-/- Cr;s.II'-e--.f-;o-?, ~c-.
I
FIRM NAME
?o. /3o)C. 7)0 &.:;...v?>/ G# 3080'7
/
BUSINESS ADDRESS
BY: uJ.., .oa ~/\~ ~~--A
TITLE:
~esfde---f-
P-1
BID SCHEDULE
TO ACCOMPANY THE PROPOSAL OF
BOND PROJECT NO. 80500
SPIRIT CREEK FORCE MAIN
BIDDER: 01.:-:.- C::::O__.frv'c_l-;c~.., / ~L ,
,
ADDRESS: '--;:<0. /3c;;"rc- //0
&_'>, GA- 3oZ;5o"?-
I
ITEM NO. DESCRIPTION. QUANTITY. UNIT & UNIT PRICE
I. SANITARY SEWER AND APPURTENANCES
S-l 30" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
10' to 14', Including Type IT (No. 57 Stone) Bedding Material
75 LF @ $ nCf ~ ILF $ /3 9--4S- ?.-=-
S-2A
S-2B
S-2C
S-2D
S-3A
36" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
10' to 12', Including Type IT (No. 57 Stone) Bedding Material
70 LF @ $ 2o~.~ ILF $
36" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
12' to 14', Including Type IT (No. 57 Stone) Bedding Material
470 LF @ $ 20S:-:!!- ILF $
36" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
14' to 16', Including Type IT (No. 57 Stone) Bedding Material
400 LF @ $ 205 'E- ILF $
36" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
16' to 18', Including Type IT (No. 57 Stone) Bedding Material
30 LF @ $ ZoS-::!!- ILF $
48" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
8' to 10', Including Type IT (No. 57 Stone) Bedding Material
490 LF @ $ 2--73 ~ ILF $
AMOUNT
70
/4-4-/3 -
?=
'7'&:> '7")) -
&2..3&>4- oC>
&/7/ 3D
BO
1:337"77" -
S-3B 48" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
10' to 12', including Type IT (No. 57 Stone) Bedding Material 2,0
860 LF @ $ 2/3 ~ ILF $ 234-7cr7-
S-3C
S-3D
S-3E
48" Diameter Ductile Iron Sanitary Sewer Pipe, Class.250, Depth
12' to 14', Including Type IT (No. 57 Stone) Bedding Material
400 LF @ $ k/3~. ILF $
48" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
14' to 16', Including Type IT (No. 57 Stone) Bedding Material
300 LF @ . $ 2,73 ~ ILF . $
48" Diameter Ductile Iron Sanitary Sewer Pipe, Class 250, Depth
16' to 18', Including Type IT (No. 57 Stone) Bedding Material
225 LF @ $ 2-),3 ~ ILF
P-2
00
/ocr 2-08 -
DO
g/9o(.:; -
$
tb/4z <=;-
5"0
-
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
ITEM NO.
S-14
S-I5
S-16
S-17
S-18
S-19
S-20
S-21
S-22
S-23
S-24
II.
W-l
DESCRIPTION. QUANTITY. UNIT & UNIT PRICE AMOUNT
Additional Sanitary Manhole Depth, Type L Class 2 (84"
Diameter). ..,,:.-. 10
35 VF @ $ /7'/:::::- /LF $. &>tP'74--
Pre-Cast Sanitary Manhole Depth, GA DOT STD. IOIIA, Type
II, Depth 0: to 6' (120" Diameter), Including Vacuum Testing 4-
9 EA'@ $ tRioS- ~ lEA $ S-4-/t/-8 ~
Additional Sanitary Manhole Depth, Type II, Class 2 (120"
Diameter) 2-/ . 90
90 VF @ $ "'4:> - NF $ B&!) g -
20" In-Line Plug Valve, Including 60" Diameter Precast Concrete
Manhole, Installed Complete, Open Left
. ~o
1 EA @ $ /3 34-') - lEA
$ /3 '34-)
<,!-O
-.
4" AirNacuum Valve Including 72" Diameter Precast Concrete
. Manhole, Installed Complete
17. EA @ $ /8940 ~ lEA
$ 32-1 9'7's'
,0
-
Flow Monitoring Manhole (72" Diameter), Installed Complete
(Not Including Flowmeter) Cf7
6 EA @ $ 4crcrl - lEA
8Z-
$ Z 9' 7'-:;- I
22-c- 0'0
$ D-
oc>
$ 2/~D-
00
$ '77'7'2- -
$ //2-')t/- ~
Cut & Plug Existing Sewer, 36" Diameter
1 EA@ $ 2?oo~ lEA
Asbestos Cement Water Main Crossing 00
5 EA @ $ 42-7'0 - lEA
Ductile Iron Pipe Polyethylene Encasement, Diameters Vary
3,400 LF @ $ 2- ~ ILF .
Concrete Encasement of Sanitary Sewer (Creek Crossings, Etc...)
75 CY @ $ /5D ~ ICY
oC>
1/7'78 -
4-1
4;&2-2,5"4-g -
,
WATER MAIN
New Long Side Water Service, Installed Complete, Including Re-
Connection os- 70
2 HA @ $ /4--er"'/ ~ lEA $ 2'77'7-
P-4
ITEM NO. DESCRIPTION. OUANTITY. UNIT & UNIT PRICE
W-2 Cut & Plug Existing Water Line
1 EA @ $ 1/2~ ~ lEA
AMOUNT
$ ICf2.--S- ~
Subtotal IT $ 4-;9'24- ~
,
ID.
P-I
PAVEMENT STRUCTURES
Asphalt Overlay, Type F, 1-112" Thick
11,550 SY @ $ 3 tf::!.-
.~D
$ /!--03o'7'-
ISY
P-2
2" Asphalt Pavement Replacement, Including Saw Cuts
(Driveway and Parking Lots)
2,250 SY @ $
c:>0
$ 24-7-:>0 - .
/I~
ISY
P-3
Pavement Patch (101/2" Graded Aggregate Base and 2-1/2"
Asphalt Patch 7' Wide Including Removal of 2-1/2" GAB and
Placement of Bituminous Tact Coat)
425 SY @ $ 2-~ !5:- /SY
s-=
$ /D&7Co")-
P-4
Asphalt Pavement Leveling
100 TN @ $
rrN
$ 5'/'7'7" ~
5"/ ~.
P-5
6" Thick Concrete Driveway Replacement, Replace in Kind,
3,000 PSI Mix
100
$ 33 '7'7'
0=
SY @ $
33 !.!-
/SY
P-6
Concrete Curb and Gutter Removal and Replacement, Replace in
Kind (As Appropriate and Necessary)
600 LF @ $ lev ~ ILF $
0=
'7co/2- -
P-5
ITEM NO.
M-6
DESCRIPTION. QUANTITY. UNIT & UNIT PRICE
SOD
500
$ 3cf.-<o5 ~
AMOUNT
~:;
~-
/SY
SY @
$
M-7 Stone Dumped Rip Rap, Type 3, 12" Including Geotextile Fabric . 7-S-
225 SY @ $ Z'7 ~ /SY $ ,~Ce:- '" & -
M-8
Stone Dumped Rip Rap, Type I, 18" Including filter Blanket and
Geotextile Fabric (Creek Crossing) 9".' .
500 SY @ $ 40!- /SY
0=
$ ;3.0 4-'7'S- -
Subtotal IV $ 3510 4-)<1- ~
f'-
v.
*LS-l
LUMP SUM CONSTRUCTION
Lump Sum Construction (Including but not Limited to the Items
. Listed Below)
Mobilization, Demobilization
Bonds, Insurance
Gabion Retaining Walls
Remove and Reset Fences, all Types
Remove and Reset Gates, all Types
Remove and Reset Storm Sewer and Headwalls, Lengths and Sizes Vary
Remove and Reset Light Poles and Electrical Poles, Type Varies
Remove and Reconnect Water Services, Complete
Remove and Reconnect Sanitary Sewer Services, Complete
Reconstruct Retaining Wall, Height V ari~s
Remove and Reset Signs, Type Varies
Remove and Reset Water Sprinkler Systems, Complete
Remove and Reset Water Valve, Size Varies
Remove and Reset Yard Lainps, Type Varies
Remove and Reset Mailboxes, Type Varies
Erosion and Sediment Control (Temporary Grassing, Construction Exits, Check Dams,
Sediment Traps and Miscellaneous Erosion Control Measures)
Silt Fence, Type "A"
Silt Fence, Type "C"
Property Restoration and Permanent Grassing
Shoring, if Required
Traffic Control
Miscellaneous Grading
Raise/Lower Manhole Tops and Valve Boxes to Grade
Remove and Reset Existing Fire Hydrants and Valves
30
/l 1/-0 ~ crfJ'1 :-- ,
LS
Subtotal V
Total
30
403. ergCf-
$ /
S- 4-8~ I~~ ~
$ / / '
, ,
*
All items which must be removed by the contractor during construction, and which are not
specifically shown to be paid for otherwise are to be removed without additional payment. All
costs for this removal or removal and resetting shall be included in the pay item "Lump Sum
Construction. " -
P-6
w;;t, ~ ~, rv7.~c.:r;~_
. '.Af ~r
Name: u?~_ .. ~ Ryr~-..I__
Date:
/o/~/p~
1 I
"6/~i -,- C::::O""",./-;'ve;.-I.o-r
I
:::c..~ L r
I
I
I
I
I
I
I
I
I
I
I
I
I
I
1
1
1
1
I.
(9) Service availability may be considered in determining the most responsible bid, and the bidders shall
be required to submit information concerning their ability to service and maintain the product of the
equipment.
A ward to other than low bidder. When the award is not given to the lowest bidder, a full and complete
statement of the reasons for placing the purchase order or other contract elsewhere shall be prepared and
signed by the Procurement Director and/or Administrator and made part of the record file for audit
proposes.
It is the wish of the Owner that minority businesses are given the opportunity to BID on the various parts
of the work. This desire on the part of the Owner is not intended to restrict or limit competitive bidding
or to increase the cost of the work. The Owner supports a healthy free market system that seeks to
include responsible businesses and provide ample opportunity for business growth and development.
The Disadvantaged Business Enterprise Language for bids has been included. Please note that all
DBEforms are required to be included as part of your bid package.
EMPLOYEE CONFLICT OF INTEREST:
It shall be unethical for any City of Augusta business or participant directly or indirectly in a procurement
contract when the employee or official knows that:
(a) the employee or official or any member oithe employee's or official's immediate family
has a substantial interest or financial interest pertaining to the procurement contract, except
that the purchase of goods and services from businesses which a member of the
Commission or other City of Augusta employee has a financial interest is authorized as per
O.C.G.A. 36-1-14, or the procurement contract is awarded pursuant to O.C.G.A. 45-10-22
and 45-10-24, or the transaction is excepted from said restrictions by O.C.G.A. 45-10-25;
(b) Any other person, business, or organization with whom the employee or official of any
member of an employee's or officials immediate family is negotiating or has an
arrangement concerning prospective employment is involved in the procurement contract.
Any employee or official or any member of an employee's or official immediate family who
holds a substantial interest or financial interest in a disclosed blind trust shall not be deemed
to have a conflict of interest with regard to matters pertaining to that substantial interest or
financial interest.
USE OF CONFIDENTIAL INFORMATION 1-10-15
It shall be unethical for any Augusta, GA County employee or official to lmowingly use confidential
information for actual or anticipated personal gain, or for the actual or anticipated gain for any other
person.
Title:
r~1:;-.:je-"7~
Company:
TillS SHEET IS REQUIRED TO BE IN SUBMITTAL.
BID BOND
Conforms with The American Institute of
Architects, A.I.A. Document No. A-310
KNOW ALL BY THESE PRESENTS, That we, Blair Construction, Inc. , P. O. Box 770, Evans, Georgia 30908
as Principal, hereinafter called the Principal,
and the Western Surety Company
of CNA Plaza, Chicago, III 60685
, a corporation duly organized under
the laws of the State of
South Dakota
, as Surety, hereinafter called the Surety, are held and firmly bound unto
Augusta-Richmond County Commission, 530 Greene St., Room 605, Augusta,
Georgia 30911
as Obligee, hereinafter called the Obligee,
in the sum of 100/0 of bid - - - - - - - - - - - - - - - - - - - - - - - - - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Dollars ($ 10% of bid ) , for the payment of which sum well andtruly to be made, the said Principal and the said
Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitted a bid for Spirit Creek Force Main
NOW, THEREFORE, if the Obligee shall accept the bid ofthe Principal and the Principal shall enter into a Contract with the Obligee
in accordance with the terms_ of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documents with
good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in
the prosecution thereof, or in the event of the failure of the Principal to enter such Contract and give such bond or bonds, if the
Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such
larger amount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this
obligation shall be null and void, otherwise to remain in full force and effect.
Signed and sealed this
5th
2005
day of
October
Blair Construction, Inc.
POBox 770, Evans, Georgia30809
{Sea!}
Principal
t
~~<S.~~
u~~.,;~ ,e~:
---;?ej ;c!e--7+- .
Title
Witness
~o :XZA?J;~
Western Surety Company
Witness
D'<yB/l J A.A~ip~q;(.L
Buck Leigh f Attorney-in-Fact
J054/GEEF 12/00
I=RP
My commission expires
+t.:.r"!l"'f""'''~~..,c.,Iloo,''''l.)l.o:'l~'''~J:o,~r."t.o:lt.,'''''':l of-
J D. KREL.L :f
$~/I10r:AAY PUBI.IC~S"'~ ,r
.r~SOUnl DAKOTA "",1. j:
~ . ,
+~~~~~~~~~~~~~~~~~~~~~~~+
-~
~P"bH'
Western SUrety Company
rOVVER OF ATTORNEY APPOINTING INDIVIDUAL ATTORNEY-IN-FACT
Know All Men By These Prescnt~, That WESTERN SURETY COMPANY, a SOUt]l DakotH cOI1)Oralion, is a duly organized and existing corporation
having it~ ptillcipal office in the City of Sioux Falls, a.nd State of South Dakota, llnd that it does by virtue of tbe signature and seal herein affixed bel'eby
make, constitute and appoint
Tbomas M Albus, Buck Leigh, Individually
of Columbia, SC, it~ true and lawful Attorney(s)-in-Paet with full power And aut.hOl;ly het'eby confen'ed to sigl1, seal and execute for and on its behalf bonds,
undertakings and other obligatory instrumenw of similar natl.!re
- In Unlimited Amounts _
Anc! to bind it ,hereby as fully and to the same extent as it sueh instruments were signed by a duly 8uthOlized officer of the corporation and all the acts of slIid
Attorney, purSUAnt to the authority herehy given, are hereby mtified and confirmed,
111is Power of Attorney is made and exec.uted pursuant to and by iJ.llfJlority of r.he By-Law printed on the reverse hereof, duly adopted, a.~ indicated, by
the shareholdel's of the corpomtiol1,
In 'Wit:ne.~s Whe.'cor, 'llESTERN SURETY COMPANY ha.~ caused these presents to be signed by its Senior Vice PresideJlt and its corpornte seal to
be hereto affixed on this 26th dllY of February, 2004.
""~"1.
"\?~~
~!~i
oS !:or1
'.""~... E:A....../~i
.". o"l'~-"";l:li:I1$~
JI"~'~:~'I'l'l\\"
WESTERN
SURETY COMPANY
State of South D"kot~
County of Minnehaha
} S5
-~
Paul ,Bruflat, Senior Vice President
On thi.~ 26th day of February, 2004, before me personally came Paul T. Bruflat, tOl1le known, who, being by me duly Sworn, did depose and say: tl1at
he resides in the City of Sioux Falls, State of South Dakota; th:.1t hc is the Senior Vice Presidcnl of WESTERN SURETY COMPANY descl'ibed in and
which executed the above instrument; that he knows the seal of said corporation; that the seal affixed to the said instrUl11ent is such corporate seal; tllnt it wa~
so affixed pursuanl. to authol'ity given by the Board of Directors of said CO!llol'atiOll and that he signf~d his 1U1me tbereto pUrS1.lal1l to like authority, and
acknowledges same to be the acl and deed of.saiel cOl'poraHon,
_~11bcr ~O, 2006
I, L Nclson, Assistant Secretary of WESTERN SURETY COMPANY do hereby certify that thc Power of Attomey he~einabove set forth is still in
force, BJld further certl(y tbat the By-Law of the corpr".:::,don print(~c1 on the rever,qe here~f i~ fill in force Tn t~ilofl!lY wl ' .[11 1
. 5th '. . '. .LJ..AJ:J.. , le! eo lave lereUl1to suhseribed
my nDme and affix.ed the .e"l of the .aiel corporatiOI1 thi.5 _____ clay of _ .
Crm.1'IFICA 'AE
~\~ll 1.11111
~~v' ,.....(,',j~
#t~/ AI"'~
~:;:rCA ~\~~
~~t .:~l
\':r.\~ C A ':,"',f'
~t~e~,' riror=i(~,>""
I~jllrftfll'lll"-:
~----'
WESTERN SURETY COMPANY
1'011111"4280-01.02
~'~
--- . .....0 '", ," ;:- ",,' " ,.,~
-_......:- . ... ..... ~---
. L Nelson, Assistant Secretary
Contractor By
Please sign and return one copy of this Notice of Award Acknowledgement to:
Augusta Utilities Department
Attn: Program Managers
Title
NOTICE OF AWARD
DATE: 11/16/2005
CONTRACTOR:
Blair Construction, Inc.
ADDRESS: P.O. Box 770
Evans
City
GA
Stale
30809
lip Code
PROJECT: Spirit Creek Force Main
PROJECT NO: 80500
At a meeting of the Augusta-Richmond County Commission held on 11/15/2005 you were awarded a Contract for
the above noted Project.
Enclosed please find 5
copies of the Contract Documents for your execution. Please complete the
pages, affixing signatures, dates, notary andlor corporate seals, etc. where necessary and return to this office
10 days from the date of this letter, excluding Legal Holidays.
The Certificate of Insurance must be complete.
Power of Attorney must be submitted in triplicate; an original and two copies is permissible.
Very truly yours,
Augusta Program Management Team
4rl~oo~
Reciept of this NOTICE OF AWARD is hereby acknowledged this, the / ~ day of
I
'tl_,"r Ce?-7S .f.._c-.t,~--r ~~ S ~~
1~-tJav - ()~
!love>..... t-e .,. 2005
?"k, e.t- &s 1;.-.. -.....fo.-
360 Bay Street, Suite 180
Augusta, GA 30901
80500 BLAIR NOTICE OF AWARD 05_11_16.DOT
SECTION A
AGREEMENT
THIS AGREEMENT, made on the 15th of November, 2005, by and between
AUGUSTA, GEORGIA BY AND THROUGH THE AUGUSTA-RICHMOND COUNTY
COMMISSION, party of the first part, hereinafter called the OWNER, and Blair Construction, Inc.,
party of the second part, hereinafter called the CONTRACTOR.
WITNESSETH, that the Contractor and the Owner, for the considerations hereinafter
named, agree as follows:
ARTICLE I - SCOPE OF THE WORK
The Contractor hereby agrees to furnish all of the materials and all of the equipment
and labor necessary, and to perform all of the work shown on the plans described in the specifications
for the project entitled:
BOND PROJECT 80500
SPIRIT CREEK FORCE MAIN
and in accordance with the requirements and provisions of the Contract Documents as defined in the
General and Special Conditions hereto attached which are hereby made a part of this agreement.
ARTICLE IT - TIME OF COMPLETION -- LIOUIDATED DAMAGES
The work to be performed under this Contract shall be commenced within ten ClQ)
calendar days after the date of written notice by the Owner to the Contractor to proceed. The work
shall be completed within Two Hundred Seventy (270) calendar days after the date of such notice and
with such extensions of time as are provided for in the General Conditions.
It is hereby understood and mutually agreed, by and between the Contractor and the
Owner, that the date of beginning, rate of progress and the time for completion of the work to be done
hereunder are ESSENTIAL CONDITIONS of this Contract. Contractor agrees that said work shall
be prosecuted regularly, diligently, and uninterruptedly at such rate of progress as will insure full
completion there of within the time specified. It is expressly understood and agreed by and between
the Contractor and the Owner, that the time for the completion of the work described herein is a
reasonable time for the completion of the same, taking into consideration the average climatic range
and construction conditions prevailing in this locality.
IF THE CONTRACTOR SHALL NEGLECT, FAIL OR REFUSE TO COMPLETE
THE WORK WITHIN THE TIME HEREIN SPECIFIED, then the Contractor does hereby agree, as
a part of the consideration for the awarding of this contract, to pay to the Owner the sum of Five
Hundred ($500.00), not as a penalty, but as liquidated damages for such breach of contract as
hereinafter set forth, for each and every calendar day that the Contractor shall be in default after the
time stipulated in the contract for completing the work.
A-I
A-2
The said amount is fixed and agreed upon by and between the Contractor and the
Owner because of the impracticability and extreme difficulty of. fixing and ascertaining the actual
damages the Owner would, in such event, sustain, and said amounts shall be retained from time to time
by the Owner from current periodical estimates.
It is further agreed that time is of the essence of each and every portion of this contract
and the specifications wherein a definite portion and certain length of time is fixed for the performance
of any act whatsoever; and where under the contract an additional time is allowed for the completion
of any work, the new time limit fixed by extension shall be the essence of the Contract.
ARTICLE ill - PAYMENT
(A) THE CONTRACT SUM
The Owner shall pay to the Contractor for the performance of the Contract the amount
as stated in the Proposal and Schedule ofItems. No variations shall be made in the amount except as
set forth in the specifications attached hereto.
(B) PROGRESS PAYMENTS
On no later than the fifth day of every month, the Contractor shall submit to the Owner
an estimate covering the percentage of the total amount of the Contract which has been completed
from the start of the job up to and including the last working day of the preceding month, together with
such supporting evidence as may be required by the Owner and/or the Engineer. This estimate shall
include only quantities in place and at the unit prices set forth in the bid schedule.
On the vendor run following approval of the invoice for payment, the Owner shall after
deducting previous payments made, pay to the Contractor 90% of the amount of the estimate on units
accepted in place. The 10% retained percentage may be held by the Owner until the final completion
and acceptance of all work under the Contract.
ARTICLE IV - ACCEPTANCE AND FINAL PAYMENT
(A) Upon receipt of written notice that the work is ready for final inspection and
acceptance, the Engineer shall within 10 days make such inspection, and when he finds the work
acceptable under the Contract and the Contract fully performed he will promptly issue a final
certificate, over his own signature, stating that the work required by the Contract has been completed
and is accepted by him under the terms and conditions thereof, and the entire balance found to be due
the Contractor, including the retained percentage, shall be paid to the Contractor by the Owner within
15 days after the date of said final certificate.
(B) Before final payment is due the Contractor shall submit evidence satisfactory to
the Engineer that all payrolls, material bills, and other indebtedness connected with the work have been
paid, except that in case of disputed indebtedness of liens of evidence of payment of all such disputed
amounts when adjudicated in cases where such payment has not already been guaranteed by surety
bond.
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(C) The making and acceptance of the final payment shall constitute a waiver of all
claims by the Owner other than those arising from unsettled liens, from faulty work appearing within
12 months after final payment, from requirements of the specifications, or from manufacturers'
guarantees. It shall also constitute a waiver of all claims by the Contractor except those previously
made and still unsettled.
(D) If after the work has been substantially completed, full completion thereof is
materially delayed through no fault of the Contractor, and the Engineer, so certifies, the Owner shall
upon certification of the Engineer, and without terminating the Contract, make payment of the balance
due for that portion of the work fully completed and accepted.
Each payment shall be made under the terms and conditions governing final payment,
except that it shall not constitute a waiver of claims.
IN WITNESS WHEREOF, the parties hereto have executed this Agreement in three
(3) counterparts, each of which shall be deemed an original, in the year and day first mentioned above.
~-=-frJ L
Witn~ ~. I
(SEAL)
ATTEST:
yY)~!:!J J+
Secretary
7~
,.
6.~~
Witness
. APPUSTA, GEORGIA
By: U!~~
1(!r As its MaJl r
By:
CONTRACTOR: ~l...,-.... L04S/-,....c--I-,-e>-?/ ::::z::;:?.c......
:z!&~ /. ~<J'-rn~~/
As itsV.c.e. 'res'de"'?+-
Address:
~o. /30')<: /')0
&-.-?~ I &.4-
f
fO~D9
-
-,
A-3
Contractor has by written agreement dated
Nov \5
200)
,
entered into a contract
I
.'"
I
I
Bond No. 929 368 597
I
PERFORMANCE BOND
Conforms with The American Institute of Architects
A.I.A. document No. A-311
I
KNOW ALL BY THESE PRESENTS: that Blair Construction, Inc., PO Box 770, Evans, Georgia 30809
(Here insert full name and address or legal title of Contractor)
I
I
as Principal, hereinafter called Contractor, and, Western Surety Company, CNA Plaza. Chicago. Illinois 60685
(Here insert full name and address or legal title of Surety)
I
as Surety, hereinafter caIIed Surety, are held and firmly bound unto Augusta-Richmond County Commission, 530 Greene
I SUMunicipal Building, Augusta, Georgia 30911 (Here insert full name and address or legal title of Owner)
I
I
as Obligee, hereinafter called Owner, in the amount of Five Million Four Hundred Eighty Five Thousand One Hundred Forty
Nine and 66/100 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - DoIIars ($ 5,485,149.66 .).
I
for the payment whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly
and severaIIy, firmly by these presents.
I
WHEREAS,
I with Owner for Spirit Creek Force Main, City of Augusta, GA
(Here insert full name, address and description of project)
I
I
in accordance with Drawings and Specifications prepared by
(JI2A~.J TOrJ t;tJBEn-'i..50tJ ~ Wl-!fT6Hu{LS1
(
(Here insert full name and address or legal title of Architect)
I
I
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
IS-1219/GEEF 10/99
Page 1 of 2
I
~
"
,.
PERFORMANCE BOND
929 368 597
INOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Contractor shall promptly and faithfully perform said
Contract, then this obligation shall be null and void; otherwise it shall remain in full force and effect.
I
The Surety hereby waives notice of any alteration or
extension of time made by the Owner.
I
Whenever Contractor shall be, and declared by Owner to be
in default under the Contract, the Owner having performed
lowner.s obligations thereunder, the Surety may promptly remedy
the default, or shall promptly
1) Complete the Contract in accordance with its terms and
Iconditions, or
2) Obtain a bid or bids for completing the Contract in accordance
IWith its terms and conditions, and upon determination by Surety of
the lowest responsible bidder, or, if the Owner elects, upon
determination by the Owner and the Surety jointly of the lowest
Iresponsible bidder, arrange for a contract between such bidder and
Owner, and make available as Work progresses (even though there
should be a default or a succession of defaults under the
I
I
I
ISigned and sealed this
2-- 3 ::!
day of
;..10 ve -- te.--
, Zoos-'.
,-
I
~~ $.~~
(Witness)
I
I
~u*-t!~/
(Witness)
I
I
I
CIS by Georgia Resident Agent
IS-1219/GEEF 10/99
contract or contracts of completion arranged under this paragraph)
sufficient funds to pay the cost of completion less the balance of the
co~tract price; but not exceeding, including other costs and damages
for which the Surety may be liable hereunder, the amount set forth
in the first paragraph hereof. The term "balance of the contract
price," as used in this paragraph, shall mean the total amount
payable by Owner to Contractor under the Contract and any
amendments thereto, less the amount properly paid by Owner to
Contractor.
Any suit under this bond must be instituted before the
expiration of two (2) years from the date on which final payment
under the Contract falls due.
- No right of action shall accrue on this bond to or for the use of
any person or corporation other than the Owner named herein or the
heirs, executors, administrators or successors of the Owner.
,(
'1
J
~.
Blair Construction, Inc., PO Box 770, Evans,
Georgia 30809
(Seal)
(Principal)
~L ht/L~~
\Ice. ~,..e~ 'de"7-1-
(Title)
r(
'j
'l
II
I.
Western Surety Company, CNA Plaza,
Chicago, Illinois 60685
(Seal)
(Surety)
:s '"~ t.'ft!...
Buck Leigh, Attorney- -Fact
(Title)
~~~-~~~
Page 2 of 2
Principal has by written agreement dated
, entered into a contract
I
I
I LABOR AND MATERIAL PAYMENT BOND
Conforms with The American Institute of Architects
A.I.A. Document No. A-311
Bond No. 929 368 597
I
THIS BOND IS ISSUED SIMULTANEOUSLY WITH PERFORMANCE BOND IN FAVOR OF THE
OWNER CONDITIONED ON THE FULL AND FAITHFUL PERFORMANCE OF THE CONTRACT
I
KNOW ALL BY THESE PRESENTS: that Blair Construction, Inc., PO Box 770, Evans, Georgia 30809
(Here insert full name and address or legal title of Contractor)
I
I
as Principal, hereinafter called Principal, and, Western Surety Company, CNA Plaza, ChicaQo, Illinois 60685
(Here insert full name and address or legal title of Surety)
I
as Surety, hereinafter called Surety, are held and firmly bound unto Augusta-Richmond County Commsission, 530 Greene
I St./Municipal Building, Augusta, Georgia 30911 (Here insert full name and address or legal title of Owner)
I
I
as Obligee, hereinafter called Owner, for the use and benefit of claimants as hereinbelow defined, in the amount of Five Million Four
Hundred Eighty Five Thousand One Hundred Forty Nine and 66/100 - - - - - - - - - - - - Dollars ($ 5,485,149.66 .).
I
for the payment whereof Principal and Surety bind themselves, their heirs, executors, administrators, successors and assigns, jointly and
severally, firmly by these presents.
I
WHEREAS, .
I with Owner for Spirit Creek Force Main, City of Augusta, GA
(Here insert full name, address and description of project)
I
I
in accordance with Drawings and Specifications prepared by
(Here insert full name and address or legal title of Architect)
I
I
which contract is by reference made a part hereof, and is hereinafter referred to as the Contract.
I S-1220/GEEF 10/99
Page 1 of 2
I
LABOR AND MATERIAL PAYMENT BOND
929 368 597
INOW, THEREFORE, THE CONDITION OF THIS OBLIGATION is such that, if Principal shall promptly make payment to all claimants as hereinafter
defined, for all labor and material used or reasonably required for use in the performance of the Contract, then this obligation shall be void; otherwise it shall
I remain in full force and effect, subject, however, to the following conditions:
1. A claimant is defined as one having a direct contract with the
I Principal or with a Subcontractor of the Principal for labor, material, or
both, used or reasonably required for use in the performance of the
Contract, labor and material being construed to include that part of water,
gas, power, light, heat, oil, gasoline, telephone service or rental of
I equipment directly applicabl~ to the Contract.
2. The above named Principal and Surety hereby jointly and
I severally ag. ree with the Owner that every claimant as herein defined, who
has not been paid in full before the expiration of a period of ninety (90)
days after the date on which the last of such claimant's work or labor was
done or performed, or materials were furnished by such claimant, may sue
Ion this bond for the use of such claimant, prosecute the suit to final
judgment for such sum or sums as may be justly due claimant, and have
execution thereon. The Owner shall not be liable for the payment of any
I costs or expenses of any such suit.
3. No suit or action shall be commenced hereunder by any claimant:
I a) Unless claimant, other than one having a direct contract with the
Principal, shall have given written notice to any two of the following: the
I Principal, the Owner, or the Surety above named, within ninety (90) days
after such claimant did or performed the last of the work or labor, or
furnished the last of the materials for which said claim is made, stating
I with substantial accuracy the amount claimed and the name of the party to
whom the materials
I Signed and sealed this
2-3d
were furnished, or for whom the work or labor was done or performed.
Such notice shall be served by mailing the same by registered mail or
certified mail, postage prepaid, in an envelope addressed to the Principal,
Owner or Surety, at any place where an office is regularly maintained for
the transaction of business, or served in any manner in which legal process
may be served in the state in which the aforesaid project is located, save
that such service need not be made by a public officer.
b) After the expiration of one (1) year following the date on which Principal
ceased Work on said Contract, it being understood, however, that if any
limitation embodied in this bond is prohibited by any law controlling the
construction hereof such limitation shall be deemed to be amended so as to
be equal to the minimum period of limitation permitted by such law.
c) Other than in a state court of competent jurisdiction in and for the county
or other political subdivision of the state in which the Project, or any part
thereof, is situated, or in the United States District Court for the district in
which the Project, or any part thereof, is situated, and not elsewhere.
4. The amount of this bond shall be reduced by and to the extent of
any payment or payments made in good faith hereunder, inclusive of the
payment by Surety of mechanics' liens which may be filed of record against
said improvement, whether or not claim for the amount of such lien be
presented under and against this bond.
day of
Nove.-....be.-
zPoS-.
I
r
;-~
r
$' , ~4--
I
(Witness)
I
I
~?l~~<
(Witness)
I
I
I S-1220/GEEF 10/99
Page 2 of 2
(,
J
~)
Blair Construction, Inc., PO Box 770, Evans,
Georgia 30809
(Seal)
(Principal)
~ -
\. ,. ..
~ ./A/L. >>7//~0h~
v, -;'e ----pres;d8..,.+_
(Title)
(
,I
'j
t
Western Surety Company, CNA Plaza,
Chicago, Illinois 60685
(Seal)
(Surety)
l3ad~"-
Buck Leigh, Attorn n-Fact
. (Title)
I
I
I
I
I
I
I
.NQ.1~IGE
In accordance witb the Terrorism Risk Insurance Act of 2,002, we are providing this
diselosure notice for bonds and certain insurance polici... on which one or more of the
Writing Companies identified bl:.~.low is the 8Ul^wl;y or inslu'er.
To principals 0>1 bonde and insureds on certain insurance policies written by anyone Or
more of the fOllowing companies (collectively the "Writing Companies") a. surety or
insurer: Western Surety Company, Universal Suret.y of Ame.r;ca, Surety Bonding
Company of America, Continental Casualty COmpany. National Fire Insurance Campau],
of Hartford, American Casnalty Company of Reading, PA The Firemen's Insurance
Company of Newark, NJ, and The Coutinental Insurance Company.
DIS CLOs...UR1;LQ:EJ~RElkfIJJM
~-'_"~_~_M'~_
I The preminm att.ributable to coverage for terrorist. act.s certified under the Act was Zero
Dollars ($0.00).
I P~~~'i~:!LE QE~f'JillERAL_~T.l.C.teA':rlO_N W~A~.1:i--T_O~RQ1QSJ\4:
.c:=:_______...__.
IThe' United Stat.e~ will pay ninety pel'Cent (90%) of covered terrorism losses exceeding the
app l1cable 81.lrety/u1811rer ded uctlble.
I
I
I
I
I
I
17310
I
I
I
~7,,~
-------.-----'t:~_"._L
Paul
I
\,!\estern Surety Company
I
POWJi~R OF ATTORNEY APPOIN'rING INDIVIDUAL AT1'ORNEY-lN-.FACT
I
Know All Men By These Presents, ThaI: WESTERN SURETY COMP A NY, n South DakotH cO'1lOrs,tion, is a duly organiz",.d and existing COl1lol'll.tion
having its principal office in the City of Sioux Falls, and State of South Dakota, fll1rJ that it dOI)S by virtu<) of t.he signll1ure and sea] herein affixed herehy
make, constitute and appoint
I
Thomas M Albus:, Buck Leigb, hulivMuaUy
I
I
ofColul11bin, SC, irs true and lawful Attorney(s)-in-Pact win, full power nlld o\1fhol'ily hercby conf~.rred to "ign, seal ami execute for and on its behalfhonds,
ll11dcrtakings and other ohligntory inMTumcms of similar nature
-In U.dimHed Amounts -
I
and 10 bind ittherchy as fully and to the Sflmc extcnt as if such instruments were signcd hy a duly atlthol'i7.edofficel' of the col1)Omtion and all the ~CI:S of said
Attomcy, pUr,~1Jflnt to tl,c authnrity hereby given, arc. hereby I'Ill:ificcl flnd confirmed.
I
'11is Power of Attorney is made and exceuted pursuflnt to and by atlthol'ity of tJlt: nl'..Law printed 011 the reverSe het'eof, duly adopted, as indicated, by
the shareholders of the corporation,
I
In Witl"l(,"~s Wherl'.of, WESTERN SURETY COMPANY has caused these pre~ents 10 be signed by it.~ Senior Vice Pmsidcl1t ~nd its eorpo1"Rte seal to
be hereto n.ffixcd 011 this 26th dill' of February, 2004.
I
...,\,\\\\~*IF.'T~1111
~" ~'"''.'''!''''' oJ''''t,
~?O!?"l~\\\
?Ill?'
" !:~ffi
.~'!
..,......~
WESTERN SURETY COMPANY
State of South Dnkota
County of Minnchaha
} ss
I
Ol1tl1is 26th day of February, 2004, before me perSOnally c.ame PaLlI T Fll'uflal to 111e known who bl'in" by l11e (lll1y '''o.rn ']'1 d n h
' .,. , , ..' r" , ,.Hi., < I( epose an say: t at
he residc.~ in the City of Sioux Falls, StMe of South Dakota; that he is the Scnior Vice Pre"I','Cl1! ,')f "'E1S'J'!~RN 811R""y COMPANY I 'I. I.
'. . . .. ,>.. " . VI.. ..' . ,t. c! .' , ' (eSCI"I le( In and
whieh executed I:he above instrument; that he knows the seal of said CIlrporal.iol1' Ihal fhe ~('fll nffi1(f'd to the OOl'(ll'llO!.I'lllllent. . I .. I I .'
,. " . ,<., .,..., 0" ,', , . IS sue 1 corporate sea; t lallt Wlt~
so affixed pUl'suanl to authority given hy the Board of Direc.tOI's of sail) COlpol'al.iOTl and thlll he si"ncd his n~tl~A '.11('1"'10 l'Ul'~I'll[ tl I." tl' d
. . >'.'" C ""."~'.' 0",. t I^eau.lonty,an
acknowledges same to be the act ann decd of said corporation.
I
I
My commission <~xjJire~s
f~~~0~~~~~~~~~~~~~~~~~~~~+
,r r
~ O. I<RELL J.
:t NOTARY PI,lSI.IC ~\:~
f SlOUn" DAKOTA ~~J
+~~~~~~~~~~~~~~~~~~~~~~~:
I
_ Noy"e:~ber :!.Q.tfOO,~___
I
CIi:I~nFICA TJi:
~~~_~4
D. KI'el~fJiZ
I, L. Nelson, Assista11l. Sccrctmy of WESTERN SURETY COMPANY I I" '1,.' '. .
(0 ,,,I e )y cu 11 fy d ,al. the Power of A t1:orney herein' b . f' ')' , ,
force, and further cerli(v thill:, the By-Law of the corporation pl'inl('d )n tl" .) . r '. ' , . . , <lOve Sel:ort 1 IS sttll 111
. . .' ( ,K I evelse lereo IS :11111111 forN:, In testimony \ J .', f 11 I, ,
my I1nme and affixed I:hc seal t1r Ihe said cmporlll:iol1 this ----...!if:.!t._....._.___ clay of _.__tfq_'{~_~.~.:::::_.______, _ z.:,~~, . laVe leJClInto 911h,Qenhcd
I
WESTERN SURETY COMPANY
I
F01T1l F4280..01-02
~....~I
-..-...--_. , '..,. . A . .' ...'., '. ' '
-....--~".., ._- ',' ','
-.----- . . -L Nelson, AS8i;;mf~;;;;:;;t;;;:Y
I
111/17/2005 4:07 PM
9,17068681855
002
ACORQ
CERTIFICATE OF LIABILITY INSURANCE
DATE (MMlDDiYYYV)
11/17/2005
THIS CERTIFICATE IS ISSUED AS A MAHER OF INFORMATION
ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE
HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR
ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW.
1 PRODUCER (770)246-8300 FAX (770)246-8301
Sutter, Mclellan & Gilbreath, Inc.
1424 North Brown Road
Suite 300
1 lawrenceville, GA 30043-8107
I~SURED Bl air Const ruct i on, Inc.
P.O. Box 770
Evans, GA 30809
INSURERS AFFORDING COVERAGE
NAIC#
I"
Natinnal Trust Insurance
FCCL.Insurance Group
18290
INSURER A:
INSURER B:
INSURER C:
INSURER D:
INSURER E:
1 COVERAGES
THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING
ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR
MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS, EXCLUSIONS AND CONDITIONS OF SUCH
POLICIES. AGGREGATE LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. .
I~f: ~~?;I: 1YPE OF INSURANCE POLICY NUMBER POLICY EFFECTlVE Pgl!fJ~~~~N LIMITS
DATE
GENERAL LIABILITY CPPOO04476 02/14/2005 02/14/2006 EACH OCCURRENCE $ 1,000 000
I-- DAMAGE TO RENTED 50,000
COMMERCIAL GENERAL LIABILITY $
I CLAIMS MADE ~ OCCUR MED EXP (Any one person) $ 5,000
A PERSONAL & ADV INJURY $ 1,000,000
I--
GENERAL AGGREGATE $ 2,000,000
I--
GEN'L AGGREGATE LIMIT APPLIES PER: , PRODUCTS.COM~OPAGG $ 2,000,000
n n PRO- nLOC
POLICY JECT
AUTOMOBILE LIABILITY CA 0005458 02/14/2005 02/14/2006 COMBINED SINGLE LIMIT
X ANY AUTO (Ea accident) $
-
ALL OWNED AUTOS BODILY INJURY
- $
SCHEDULED AUTOS (Per person) 1,000,000
B -
X HIRED AUTOS BODILY INJURY
X $
NON-OWNED AUTOS (Per accident)
-
- PROPERlY DAMAGE $
(Per accident)
GARAGE LIABILITY AUTO ONLY - EA ACCIDENT $
==1 ANY AUTO OTHER THAN EA ACC $
AUTO ONLY: AGG $
EXCESSJUMBRELLA LIABILITY UMBOO02841 02/14/2005 02/14/2006 EACH OCCURRENCE $ 5,000,000
~ OCCUR o CLAIMS MADE .. AGGREGATE $ 5,000,000
B $
==1 DEDUCTIBLE $
RETENTION $ $
WORKERS COMPENSATION AND 010-WC05A-54981 02/14/2005 02/14/2006 X I WC STATU. I 10TH.
EMPLOYERS' LIABILITY TORY LIMITS ER
A ANY PROPRIETORlPARTNERlEXECUTIVE EL EACH ACCIDENT $ 1,000,000
OFFICERlMEMBER EXCLUDED? EL DISEASE - EA EMPLOYEE $ 1,000,000
~ yes. describe under 1,000,000
SPECIAL PROVISIONS below EL DISEASE - POLICY LIMIT $
OTHER
~.ESC~IPTlON Of O~ERATIONS I LOCATIONS IVEHICL~S I EXCLUSIONS ADDED BY ENDORSEMENT I SPECIAL PROVISIONS
rOJ: Splrlt Creek Force Maln, Augusta, GA Contract Amount $5,485,149.66
-
1
1
1
1
1
1
1
1
I
1
1
I
I
I CERTIFICATE HOLDER
CANCELLATION
SHOULD ANY OF THE ABove DESCRIBED POLICIES BE CANCELLED BEFORE THE
I
Augusta GA Commission
Room 605, Municipal Building
August, GA 30911
EXPIRATION DATE THEREOF, THE ISSUING INSURER WILL ENDEAVOR TO MAIL
~ DAYS WRlTIEN NOTICE TO THE CERTlFICATE HOLDER NAMED TO THE LEFT,
BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY
OF AtN KIND UPON THE INSURER, ITS AGENTS OR REPRESENTATIVES.
AUTHORIZED REPRESENTATlVE
I
Mark Ja
-/o/'-k c h--
ACORD 25 (2001/08)
@ACORDCORPORATION 1988
a corporation organized and existing under the laws of the State of
, with its
SECTION PB
PERFORMANCE BOND
(NOTE:
THIS BOND IS ISSUED SIMULTANEOUSL YWITHPA YMENTBOND ON PAGE
PB-3, IN FAVOR OF THE OWNER CONDIDONED FOR THE PAYMENT OF
LABOR AND MATERIAL.)
KNOW ALL MEN BY THESE PRESENTS:
That
as Principal,
hereinafter called Contractor, and
principal office in the City of , State of , as Surety,
hereinafter called Surety, are held and firmly bound unto AUGUSTA, GEORGIA BY AND
THROUGH THE AUGUSTA-RICHMOND COUNTY COMMISSION as Obligee, hereinafter called
the Owner, in the penal amount of Dollars
($ ) for the payment whereof Contractor and Surety bind themselves, their heirs,
executors, administrators, successors, and assigns, jointly and severally, firmly by these presents for
the faithful performance of a certain written agreement.
WHEREAS, Contractor has by said written agreement dated entered
into a contract with Owner for the construction of BOND PROJECT NO. 80500 SPIRIT CREEK
FORCE MAIN, Augusta, Georgia, in accordance with the drawings and specifications issued by the
Augusta Utilities Department and the Augusta-Richmond County Commission, which contract is by
reference made a part hereof, and is hereinafter referred to as the CONTRACT.
NOW, THEREFORE, the condition of this obligation is such that, if Contractor shall
promptly and faithfully perform said CONTRACT, then this obligation shall be null and void;
otherwise it shall remain in full force and effect.
The Surety hereby waives notice of any alteration or extension of time made by the
Owner.
Whenever Contractor shall be, and declared by Owner to be in default under the CONTRACT,
the Owner having performed Owner's obligations thereunder, the Surety may promptly remedy the
default, or shall promptly
(1) Complete the CONTRACT in accordance with its terms and conditions, or
(2) Obtain a bid or bids for completing the Contract in accordance with its terms and
conditions, and upon determination by Surety of the lowest responsible bidder, or, if
the Owner elects, upon determination by the Owner and the Surety jointly of the lowest
responsible bidder, arrange for a contract between such bidder and Owner, and make
available as Work progresses (even though there should be a default or a succession of
defaults under the contract or contracts of completion arranged under this paragraph)
PB-1
Attest
By
(Seal)
sufficient funds to pay the cost of completion less the balance of the contract price; but
not exceeding, including other costs and damages for which the Surety may be liable
hereunder, the amount set forth in the first paragraph hereof. The term "balance of the
contract price," as used in this paragraph, shall mean the total amount payable by
Owner to Contractor under the Contract and any amendments thereto, less the amount
properly paid by Owner to Contractor.
Any suit under this bond must be instituted before the expiration of two (2) years from
the date on which final payment under the CONTRACT falls due.
No right of action shall accrue on this bond to or for the use of any person or
corporation other than the Owner named herein or the heirs, executors, administrators or successors
of the Owner.
Signed and sealed this
day of
A.D. 20_.
Witness
(Seal)
(Contractor)
Attest
By
(Seal)
(Title)
Witness
(Seal)
(Surety)
(Title)
PB-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION PB
LABOR AND MATERIAL PAYMENT BOND
(NOTE:
THIS BOND IS ISSUED SIMULTANEOUSL YWITH PERFORMANCE BOND ON
PAGE PB.:1, IN FAVOR OF THE OWNER CONDIDONED FOR THE
PERFORMANCE OF THE WORK.)
KNOW ALL MEN BY THESE PRESENTS:
That
as Principal,
hereinafter called Contractor, and
a corporation organized and existing under the laws of the State of
, with its
principal office in the City of , State of , as Surety,
hereinafter called Surety, are held and firmly bound unto AUGUSTA, GEORGIA BY AND
THROUGH THE AUGUSTA-RICHMOND COUNTY COMMISSION, as Obligee, hereinafter called
the Owner, for the use and benefit of claimants as hereinbelow defined in the amount of
Dollars ($ ) for the payment
whereof Contractor and Surety bind themselves, their heirs, executors, administrators, successors, and
assigns, jointly and severally, firmly by these presents.
WHEREAS, Contractor has by written agreement dated entered
into a contract with Owner for the construction of BOND PROJECT NO. 80500 SPIRIT CREEK
FORCE MAIN, in accordance with drawings and specifications issued by the Augusta Utilities
Department and Augusta-Richmond County Commission, which contract is by reference made a part
hereof, and is hereinafter referred to as the CONTRACT.
NOW, THEREFORE, the condition of this obligation is such that, if the Contractor
shall promptly make payment to all claimants as hereinafter defined, for all labor and material used
or reasonably required to use in the performance of the CONTRACT, then this obligation shall be
void; otherwise it shall remain in full force and effect, subject, however, to the following conditions:
(1) A claimant is defined as one having a direct contract with the Contractor or with a
subcontractor of the Contractor for labor, material, or both, used or reasonably required
for use in the performance of the contract, labor and material being construed as to
include that part of water, gas, power, light, heat, oil, gasoline, telephone service or
rental of equipment directly applicable tothe CONTRACT.
(2) The above named Contractor and Surety hereby jointly and severally agree with the
Owner that every claimant as herein defined, who has not been paid in full before the
expiration of a period of ninety (90) days after the date on which the last of such
claimant's work or labor was done or performed, or materials were furnished by such
claimant, may sue on this bond for the use of such claimant, prosecute the suit to final
PB-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(3)
judgement for such sum or sums as may be justly due claimant, and have execution
thereon. The Owner shall not be liable for the payment of any costs or expenses of any
such suit.
No suit or action shall be commenced hereunder by any claimant,
(a) Unless claimant, other than one having a direct contract with the Contractor,
shall have given written notice to any two of the following: The Contractor, the
Owner, or the Surety above named, within ninety (90) days after such claimant
did or performed the last of the work or labor, or furnished the last of the
materials for which said claim is made, stating with substantial accuracy the
amount claimed and the name of the party to whom the materials were
furnished, or for whom the work or labor was done or performed. Such notice
shall be served by mailing the same by registered mail or certified mail, postage
prepaid, in an envelope addressed to the Contractor, Owner or Surety, at any
place where an office regularly maintained for the transaction of business, or
served in any manner in which legal process may be served in the state in which
the aforesaid project is located, save that such service need not be made by a
public officer.
(b) After the expiration of one. (1) year following the date on which Contractor
ceased work on said CONTRACT, it being understood, however, that if any
limitation embodied in this bond is prohibited by any law controlling the
construction hereof, such limitation shall be deemed to be amended so as to be
equal to the minimum period of limitation permitted by such law.
(c) Other than in a state court of competent jurisdiction in and for the county or
other political subdivision of the state in which the project, or any part thereof,
is situated, or in the United States District Court for the district in which the
project, or any part thereof, is situated, and not elsewhere.
(4)
The amount of this bond shall be reduced by and to the extent of any payment or
payments made in good faith hereunder, inclusive of the payment by Surety of
mechanics' liens which may be filed of record against said improvement, whether or
not claim for the amount of such lien be presented under and against this bond.
PB-4
NOTICE TO PROCEED
TO: Blair Construction. Inc.
P.O. Box 770
Evans. GA 30809
Attn: William Mutimer
PROJECT: Spirit Creek Pump Station
You are hereby notified to commence WORK in accordance with the Agreement dated
on or before
, and you are to complete the WORK within 270
December 19, 2005
consecutive calendar days thereafter. The date of completion of all WORK is therefore
Very truly yours,
Augusta Program Management Team
Project Engineer
~nhl'>rt n I-h,rmnn P ~
Receipt of this NOTICE TO PROCEED is hereby acknowledged
This, the
day of
, 2005
Contractor: Blair Construction. Inc.
By:
Title:
Please siqn and return one COpy of this Notice to Proceed Acknowledqement to:
Augusta Utilities Department
Attn: ProQram ManaQers
360 Bav Street. Suite 180
AUQusta. GA 30901
DATE:
PROJECT NO:
80501
November 15, 2005
September 15. 2006.
80500 BLAIR NOTICE TO PROCEED. DOC
I
I
I
I ARTICLE
I -01.
-02.
-03.
I -04.
-05.
-06.
I -07.
-08.
-09.
I -10.
-11.
-12.
I -13.
I -14.
-15.
-16.
I -17.
I
I
I
I
I
I
I
I
SECTION GC
INDEX TO GENERAL CONDITIONS
Definitions
Preliminary Matters
Contract Documents: Intent, Amending, Reuse
Availability of Lands, Physical Conditions, Reference Points
Bonds and Insurance
Contractor's Responsibilities
Other Work
Owner's Responsibilities
Professional's Status During Construction
Changes In The Work
Change of Contract Price
Change of Contract Time
Warranty and Guarantee; Tests and Inspections: Correction, Removal or Acceptance
of Defective Work
Payments to Contractor and Completion
Suspension of Work and Termination
Dispute Resolution
Miscellaneous
GC-O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
SECTION GC
GENERAL CONDITIONS
ARTICLE I--DEFINITIONS
Wherever used in these General Conditions or in the other Contract Documents the following terms
have the meanings indicated, which are applicable to both the singular and plural thereof:
Addenda-Any changes, revisions or clarifications of the Contract Documents which have been duly
issued by OWNER to prospective Bidders prior to the time of opening of Bids.
Agreement- The written agreement between OWNER and CONTRACTOR covering the Work to be
performed; other Contract Documents are attached to the Agreement and made a part thereof as
provided therein.
Application for Payment-The form. accepted by PROFESSIONAL which is to be used by
CONTRACTOR in requesting progress or final payments and which is to include such supporting
documentation as is required by the Contract Documents.
Bid-The offer or proposal of the bidder submitted on the prescribed form setting forth the price(s) for
the Work to be performed.
Bonds-Bid, performance and payment bonds and other instruments of security furnished by
CONTRACTOR and its Surety in accordance with the Contract Documents.
Change Order-- A document recommended by PROFESSIONAL, which is signed by CONTRACTOR
and OWNER, and authorizes an addition, deletion or revision in the Work, or an adjustment in the
Contract Price or the Contract Time, issued on or after the Effective Date of the Agreement.
Contract Documents-The Agreement: Addenda (which pertain to the Contract Documents);
CONTRACTOR's Bid (including documentation accompanying the Bid and any post-Bid
documentation submitted prior to the Notice of Award) when attached as an exhibit to the Agreement;
the Bonds; these General Conditions; the Supplementary Conditions; the Plans, Specifications and the
Drawings as the same are more specifically identified in the Agreement; Certificates of Insurance;
Notice of Award; and Change Order duly delivered after execution of Contract together with all
amendments, modifications and supplements issued pursuant to paragraphs 3.3 and 3.5 or after the
Effective Date of the Agreement.
Contract Price-The moneys payable by OWNER to CONTRACTOR under the Contract Documents
GC-l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
as stated in the Agreement (subject to the provisions of paragraph 11.9.1 in the case of Unit Price
Work).
Contract Time-The number of days (computed as provided in paragraph 17.2.1) or the date stated in
the Agreement for the completion of the Work.
CONTRACTOR-The person, firm or corporation with whom OWNER has entered into the Agreement.
COUNTY-Richmond County, Georgia, or Augusta, Georgia, political subdivisions of the State of
Georgia, the Augusta-Richmond County Commission, and its authorized designees, agents, or
employees.
Day-Either a working day or calendar day as specified in the bid documents. If a calendar day shall fall
on a legal holiday, that day will be omitted from the computation. Legal Holidays: New Year's Day,
Martin Luther King Day, Memorial Day, 4th of July, Labor Day, Veterans Day, Thanksgiving Day and
the following Friday, and Christmas Day.
Defective-An adjective which, when modifying the word Work, refers to Work that is unsatisfactory,
faulty or deficient, does not conform to the Contract Documents, or does not meet the requirements
of any inspection, reference standard, test or approval referred to in the Contract Documents, or has
been damaged prior to PROFESSIONAL's recommendation of final payment, unless responsibility for
the protection thereof has been assumed by OWNER at Substantial Completion (in accordance with
paragraph 14.8 or 14.10).
Drawings-The drawings which show the character and scope of the Work to be performed and which
have been prepared or approved by PROFESSIONAL and are referred to in the Contract Documents.
Effective Date of the Agreement-The date indicated in the Agreement on which it becomes effective,
but if no such date is indicated it means the date on which the Agreement is signed by the Mayor of
Augusta, Georgia.
Field Order-A written order issued by PROFESSIONAL that modifies Drawings and Specifications,
but which does not involve a change in the Contract Price or the Contract Time.
General Requirements-Sections of Division I of the Specifications.
Laws or Regulations-Laws, rules, regulations, ordinances, codes and/or orders.
GC-2
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Notice of Award-The written notice by OWNER to the apparent successful bidder stating that upon
compliance by the apparent successful bidder with the conditions precedent enumerated therein, within
the time specified, OWNER will sign and deliver the Agreement.
Notice to Proceed-A written notice given by OWNER to CONTRACTOR (with a copy to
PROFESSIONAL) fixing the date on which the Contract Time will commence to run and on which
CONTRACTOR shall start to perform CONTRACTOR'S obligations under the Contract Documents.
OWNER- Augusta, Georgia, and the Augusta-Richmond County Commission.
Partial Utilization-Placing a portion of the Work in service for the purpose for which it is intended
or for a related purpose) before reaching Substantial Completion for all the Work.
PROFESSIONAL-The ArchitecturallEngineering firm or individual or in-house licensed person
designated to perform the design and/or resident engineer services for the Work.
PROGRAM MANAGER - The professional firm or individual designated as the representative or the
OWNER who shall act as liaison between OWNER and both the PROFESSIONAL and
CONTRACTOR when project is part of an OWNER designated program.
Project-The total construction of which the Work to be provided under the Contract Documents may
be the whole, or a part, as indicated elsewhere in the Contract Documents.
Project Area-The area within which are the specified Contract Limits of the improvements
contemplated to be constructed in whole or in part under this Contract.
Project Manager-The professional in charge, serving OWNER with architectural or engineering
services, his successor, or any other person or persons, employed by said OWNER, for the purpose of
directing or having in charge the work embraced in this Contract.
III
j
Resident Project Representative-The authorized representative of PROFESSIONAL as PROGRAM
MANAGER who is assigned to the site or any part thereof.
I
I
I
I
I
Shop Drawings-All drawings, diagrams, illustrations, schedules and other data which are specifically
prepared by or for CONTRACTOR to illustrate some portion of the Work and all illustrations,
brochures, standard schedules, performance charts, instructions, diagrams and other information
prepared by a Supplier and submitted by CONTRACTOR to illustrate material or equipment for some
portion of theW ork.
Specifications- Those portions of the Contract Documents consisting of written technical descriptions
GC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
of materials, equipment, construction systems, standards and workmanship as applied to the Work and
certain administrative details applicable thereto.
Subcontractor-An individual, firm or corporation having a direct contract with CONTRACTOR or
with any other SUBCONTRACTOR for the performance of a part of the Work at the site.
Substantial Completion-The Work (or a specified part thereof) has progressed to the point where, in
the opinion of PROFESSIONAL as evidenced by PROFESSIONAL's definitive certificate of
Substantial Completion, it is sufficiently complete, in accordance with the Contract Documents, so that
the Work (or specified part) can be used for the purposes for which it is intended, or if there be no such
certificate issued, when final payment is due in accordance with paragraph 14.13. The terms
"substantially complete" and "substantially completed" as applied to any Work refer to Substantial
Completion thereof.
Supplementary Conditions-The part of the Contract Documents which amends or supplements these
General Conditions.
Supplier-A manufacturer, fabricator, supplier, distributor, materialman or vendor.
Underground Facilities-All pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels
or other such facilities or attachments, and any encasement containing such facilities which have been
installed underground to furnish any of the following services or materials: electricity, gases, steam,
liquid petroleum products, telephone or other communications, cable television, sewage and drainage
removal, traffic or other control systems, or water.
Unit Price Work-Work to be paid for on the basis of unit prices.
Work-The entire completed construction or the various separately identifiable parts thereof required
to be furnished under the Contract Documents. Work is the result of performing services, furnishing
labor and furnishing and incorporating materials and equipment into the construction, and furnishing
documents, all as required by the Contract Documents.
Work Change Directive-A written directive to CONTRACTOR, issued on or after the Effective Date
of the Agreement and signed by OWNER and recommended by PROFESSIONAL, ordering an
addition, deletion or revision in the Work, or responding to differing or unforeseen physical conditions
under which the Work is to be performed as provided in paragraph 4.2 or 4.3 or to emergencies under
paragraph 6.22. A Work Change Directive may not change the Contract Price or the Contract Time but
is evidence that the parties expect that the change directed or documented by a Work Change Directive
will be incorporated in a subsequently issued Change Order following negotiations by the parties as
to its effect, if any, on the Contract Price or Contract Time as provided in Article 10.
GC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Written Amendment-A written amendment of the Contract Documents, signed by OWNER and
CONTRACTOR on or after the Effective Date of the Agreement and normally dealing with the non-
engineering or non-technical rather than strictly Work-related aspects of the Contract Documents.
GC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 2-PRELIMINARY MATTERS
Delivery of Bonds:
2.1. When CONTRACTOR delivers the executed Agreements to OWNER, CONTRACTOR
shall also deliver to OWNER such Bonds as CONTRACTOR may be required to furnish in accordance
with these Contract Documents.
Copies of Documents:
2.2. After the award of the Contract, OWNER shall furnish CONTRACTOR, at no cost, one
(1) complete set of the Contract Documents for execution of the work. Additional sets of the project
manual and drawings and/or individual pages or sheets of the project manual or drawings will be
furnished byCOUNTY upon CONTRACTOR's request and at CONTRACTOR's expense, which will
be OWNER's standard charges for printing and reproduction.
Commencement of Contract Time, Notice to Proceed:
2.3. The Contract Time shall commence as established in the Notice to Proceed. A Notice to
Proceed may be given at any time after the Effective Date of the Contract.
Starting the Project:
2.4. CONTRACTOR shall begin the Work on the date the Contract Time commences. No
Work shall be done prior to the date on which the Contract Time commences. Any Work performed
by CONTRACTOR prior to date on which Contract Time commences shall be at the sole risk of
CONTRACTOR.
Before Starting Construction:
2.5. Before undertaking each part of the Work, CONTRACTOR shall carefully study and
compare the Contract Documents and check and verify pertinent figures shown thereon and all
applicable field measurements. CONTRACTOR shall promptly report in writing to PROFESSIONAL
any conflict, error, ambiguity, or discrepancy which CONTRACTOR may discover and shall obtain
a written interpretation or clarification from PROFESSIONAL before proceeding with any Work
affected thereby. CONTRACTOR shall be liable to OWNER for failure to report any conflict, error,
ambiguity or discrepancy in the Contract Documents, if CONTRACTOR knew or reasonably should
have known thereof.
2.6. Within ten days after the Effective Date of the Agreement (unless otherwise specified in
the General Requirements), CONTRACTOR shall submit to PROFESSIONAL and OWNER for
reVIew:
GC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
2.6.1. an estimated progress schedule indicating the starting and completion dates of the
various stages of the Work:
2.6.2. a preliminary schedule of Shop Drawing and Sample submissions, and
2.6.3. a preliminary schedule of values for all of the Work which will include quantities and
prices of items aggregating the Contract Price and will subdivide the Work into component parts in
sufficient detail to serve as the basis for progress payments during construction. Such prices will
include an appropriate amount of overhead and profit applicable to each item of Work which will be
confirmed in writing by CONTRACTOR at the time of submission.
2.7. Before any Work at the site is started, CONTRACTOR shall deliver to OWNER, with
copies to each additional insured identified in the Supplementary Conditions, an original policy or
certified copies of each insurance policy (and other evidence of insurance which OWNER may
reasonably request) which CONTRACTOR is required to purchase and maintain in accordance with
Article 5.
Pre-construction Conference:
2.8. Before any Work atthe site is started, a conference attended by CONTRACTOR, OWNER
, PROFESSIONAL and others as appropriate will be held to establish a working understanding among
the parties as to the Work and to discuss the schedules referred to in 2.6 as well as procedures for
handling Shop Drawings and other submittals, processing applications for payment and maintaining
required records.
Finalizing Schedules:
2.9. At least ten days before submission of the first Application for Payment, a conference
attended by CONTRACTOR, PROFESSIONAL and OWNER and others as appropriate will be held
to finalize the sche,dules submitted in accordance with paragraph 2.6. CONTRACTOR shall have an
additional ten (10) calendar days to make corrections and adjustments and to complete and resubmit
the schedules. No progress payment shall be made to CONTRACTOR until the schedules are
submitted and acceptable to OWNER and PROFESSIONAL as provided below. The finalized progress
schedule will be acceptable to OWNER and PROFESSIONAL as providing an orderly progression
of the Work to completion within any specified Milestones and the Contract Time, but such
acceptance will neither impose on PROFESSIONAL responsibility for the sequencing, scheduling or
progress of the Work nor interfere with or relieve CONTRACTOR from full responsibility therefor.
The finalized schedule of Shop Drawing submissions and Sample submissions will be acceptable to
PROFESSIONAL as providing a workable arrangement forreviewing and processing the submissions.
CONTRACTOR's schedule of values shall be approved by PROFESSIONAL as to form and
substance.
GC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
~
I
Revision Date
August 2001
CONTRACTOR, in addition to preparing an initially acceptable schedule, shall be responsible
for maintaining the schedule, including updating schedule. Schedule updates shall include progression
of work as compared to scheduled progress on work. Schedule updates shall accompany each pay
request.
GC-8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 3-CONTRACT DOCUMENTS; INTENT,
AMENDING, REUSE
Intent:
3.1. The Contract Documents comprise the entire agreement between OWNER and
CONTRACTOR concerning the Work. The Contract Documents are complementary: what is called
for by one is as binding as if called for by all. The Contract Documents will be construed in
accordance with the law of the State of Georgia.
3.2. It is the intent of the Contract Documents to describe a functionally complete Project (or
part thereof) to be constructed in accordance with the Contract Documents. Any Work, materials or
equipment that may reasonably be inferred from the Contract Documents. or from prevailing custom
or trade usage as being required to produce the intended result will be supplied whether or not
specifically called for. When words or phrases which have a well-known technical or construction
industry or trade meaning are used to describe Work, materials or equipment, such words shall be
interpreted in accordance with that meaning.
3.3. Except as otherwise specifically stated in the Contract Documents or as may be provided
by amendment or supplement thereto issued by one of the methods indicated in 3.6 or 3.7, the
provisions of the Contract Documents shall take precedence in resolving any conflict, error, ambiguity
or discrepancy between the provisions of the Contract Documents and the provisions of any such
standard, specification, manual, code or instruction (whether or not specifically incorporated by
reference in the Contract Documents) and the provisions of any such Laws or Regulations applicable
to the performance of the Work (unless such an interpretation of the provisions of the Contract
Documents would result in violation of such Law or Regulation). Clarifications and interpretations of
the Contract Documents shall be issued by PROFESSIONAL as provided in paragraph 9.4.
3.4. Reference to standards, specifications, manuals or codes of any technical society,
organization or association, or to the Laws or Regulations of any governmental authority, whether such
reference be specific or by implication, shall mean the latest standard, specification, manual, code or
Laws or Regulations in effect at the time of opening of Bids (or on the Effective Date of the
Agreement if there were no Bids), except as may be otherwise specifically stated in the Contract
Documents.
3.5. If, during the performance of the Work, CONTRACTOR discovers any conflict, error,
ambiguity or discrepancy within the Contract Documents or between the Contract Documents and any
provision of any such Law or Regulation applicable to the performance of the Work or of any such
standard, specification, manual or code or of any instruction of any Supplier referred to in 6.7,
CONTRACTOR shall so report to PROFESSIONAL in writing at once and before proceeding with
the Work affected thereby and shall obtain a written interpretation or clarification from
GC-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
PROFESSIONAL; however, CONTRACTOR shall not be liable to OWNER or PROFESSIONAL
for failure to report any conflict, error, ambiguity or discrepancy in the Contract Documents unless
CONTRACTOR had actual knowledge thereof or should reasonably have known thereof.
Amending and Supplementing Contract Documents:
3.6. The Contract Documents may be amended to provide for additions, deletions and revisions
in the Work or to modify the terms and conditions thereof in one or more of the following ways:
3.6.1. a formal Written Amendment,
3.6.2. a Change Order (pursuant to paragraph 10.3), or
3.6.3. a Work Change Directive (pursuant to paragraph 10.4).
As indicated in paragraphs 11.2 and 12.1, Contract Price and Contract Time may only be changed by
a Change Order or a Written Amendment.
3.7. In addition, the requirements of the Contract Documents maybe supplemented, and minor
variations and deviations in the Work may be authorized in one or more of the following ways:
3.7.1. a Field Order (pursuant to paragraph 9.5).
3.7.2. PROFESSIONAL's approval of a Shop Drawing or sample (pursuant to paragraphs 6.24
and 6.26), or
3.7.3. PROFESSIONAL's written interpretation or clarification (pursuant to paragraph 9.4).
Reuse of documents:
3.8. Neither CONTRACTOR nor any Subcontractor or Supplier or other person or organization
performing or furnishing any of the Work under a direct or indirect contract with OWNER shall have
or acquire any title to or OWNERSHIP rights in any of the Drawings, Specifications or other documents
(or copies of any thereof) prepared by or bearing the seal of PROFESSIONAL or PROFESSIONAL's
consultant; and they shall not reuse such Drawings, Specifications or other documents (or copies of
any thereof) on extensions of the Project or any other project without written consent of OWNER and
PROFESSIONAL and specific written verification or adaptation by PROFESSIONAL.
GC-lO
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 4-A V AILABILITY OF LANDS, PHYSICAL
CONDITIONS; REFERENCE POINTS
Availability of Lands:
4.1.. OWNER shall furnish, as indicated in the Contract Documents, the lands upon which the
Work is to be performed, rights-of-way and easements for access thereto, and such other lands which
are designated for the use of CONTRACTOR. Necessary easements or rights-of-way will be obtained
and expenses will be borne by OWNER. If CONTRACTOR and OWNER are unable to agree on
entitlement to or the amount or extent of any adjustments in the Contract Price or the Contract Times
as a result of any delay in OWNER's furnishing these lands, rights-of-way or easements, the
CONTRACTOR may make a claim therefor as provided in Articles 11 and 12. The CONTRACTOR
shall provide for all additional lands and access thereto that may be required for temporary
construction facilities or storage of materials and equipment.
Physical Conditions:
4.2.1. Explorations and Reports: Reference is made to the Supplementary Conditions for
identification of those reports of explorations and tests of subsurface conditions at or contiguous to
the site that have been utilized in preparing the Contract Documents and those drawings of physical
conditions in or relating to existing surface or subsurface structures at or contiguous to the site (except
Underground Facilities) that have been utilized in preparing the Contract Documents.
4.2.2. CONTRACTOR may rely upon the general accuracy of the "technical data" contained
in such reports and drawings. Such "technical data" is identified in the Supplementary Conditions.
Except for such reliance on such "technical data," CONTRACTOR may not rely upon or make any
claim against OWNER, PROFESSIONAL, or any of PROFESSIONAL's Consultants with respect to:
4.2.2.1. the completeness of such reports and drawings for CONTRACTOR's purposes,
including but not limited to, any aspects of the means, methods, techniques, sequences and procedures
of construction to be employed by CONTRACTOR and safety precautions and programs incident
thereto, or
4.2.2.2. other data, interpretations, opinions and information contained in such reports or shown
or indicated in such drawings, or
4.2.2.3. any CONTRACTOR interpretation of or conclusion drawn from any "technical data"
or any such data, interpretations, opinions or information.
4.2.3. If conditions are encountered, excluding existing utilities, at the site which are (1)
GC-11
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
subsurface or otherwise concealed physical conditions which differ materially from those indicated
in the Contract Documents or (2) unknown physical conditions of an unusual nature, which differ
materially from those ordinarily found to exist and generally recognized as inherent in construction
activities of the character provided for in the Contract Documents, then CONTRACTOR shall give
OWNER notice thereof promptly before conditions are disturbed and in no event later than 48 hours
after first observance of the conditions.
4.2.4. The OWNER and PROFESSIONAL shall promptly investigate such conditions, and,
if they differ materially and cause an increase or decrease in CONTRACTOR's cost of, or time
required for, performance of any part of the Work, the OWNER and PROFESSIONAL shall
recommend an equitable adjustment in the Contract Price or Contract Time, or both. If the OWNER
and PROFESSIONAL determine that the conditions at the Site are not materially different from those
indicated in the Contract Documents or are not materially different from those ordinarily found and
that no change in the terms of the Contract is justified, the PROFESSIONAL shall notify
CONTRACTOR of the determination in writing. The Work shall be performed after direction is
provided by the PROFESSIONAL.
Physical Conditions-Underground Facilities:
4.3.1. Shown or Indicated: The information and data shown or indicated in the Contract
Documents with respect to existing Underground Facilities at or contiguous to the site is based on
information and data furnished to OWNER or PROFESSIONAL by OWNER'S of such Underground
Facilities or by others. Unless it is otherwise expressly provided in the Supplementary Conditions:
4.3.1.1. OWNER and PROFESSIONAL shall not be responsible for the accuracy or
completeness of any such information or data; and
4.3.1.2. The cost of all of the following will be included in the Contract Price and
CONTRACTOR shall have full responsibility for reviewing and checking all such information and
data for locating all Underground Facilities shown or indicated in the Contract Documents, for
coordination of the W orkwith the OWNER'S of such Underground Facilities during construction, for
the safety and protection thereof as provided in paragraph 6.20 and repairing any damage thereto
resulting from the Work, the cost of all of which will be considered as having been included in the
Contract Price.
4.3.2. Not Shown or Indicated. If an Underground Facility is uncovered or revealed at or
contiguous to the site which was not shown or indicated in the Contract Documents and which
CONTRACTOR could not reasonably have been expected to be aware of, CONTRACTOR shall,
promptly after becoming aware thereof and before performing any Work affected thereby except in
an emergency as permitted by paragraph 6.22, identify the OWNER of such Underground Facility and
give written notice thereof to that OWNER and to OWNER and PROFESSIONAL. PROFESSIONAL
will promptly review the Underground Facility to determine the extent to which the Contract
GC-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Documents should be modified to reflect and document the consequences of the existence of the
Underground Facility, and the Contract Documents will be amended or supplemented to the extent
necessary. During such time, CONTRACTOR shall be responsible for the safety and protection of
such Underground Facility as provided in paragraph 6.20. CONTRACTOR shall be allowed an
increase in the Contract Price or an extension of the Contract Time, or both, to the extent that they are
attributable to the existence of any Underground Facility that was not shown or indicated in the
Contract Documents and which CONTRACTOR could not reasonably have been expected to be aware
of. If the parties are unable to agree as to the amount or length thereof, CONTRACTOR may make
a claim therefor as provided in Articles II and 12.
Reference Points:
4.4. OWNER shall provide Engineering surveys to establish reference points for construction
which in PROFESSIONAL's judgment are necessary to enable CONTRACTOR to proceed with the
Work. CONTRACTOR shall be responsible for laying out the Work (unless otherwise specified in
the General Requirements), shall protect and preserve the established reference points and shall make
no changes or relocations without the prior written approval of OWNER. CONTRACTOR shall report
to PROFESSIONAL whenever any reference point is lost or destroyed or requires relocation because
of necessary changes in grades or locations, and shall be responsible for the accurate replacement or
relocation of such reference points by professionally qualified personnel.
Asbestos, PCBs, Petroleum, Hazardous Waste or Radioactive Material:
4.5 OWNER shall be responsible for any Asbestos, PCBs, Petroleum, Hazardous Waste or
Radioactive Material uncovered or revealed at the site which was not shown or indicated in Drawings
or Specifications or identified in the Contract Documents to be within the scope of the Work and
which may present a substantial danger to persons or property exposed thereto in connection with the
Work at the site. OWNER shall not be responsible for any such materials brought to the site by
CONTRACTOR, Subcontractor, Suppliers or anyone else for whom CONTRACTOR is responsible.
4.6 CONTRACTOR shall immediately: (i) stop all work in connection with such hazardous
condition and in any area affected thereby (except in an emergency as required by 6.22), and (ii) notify
OWNER and PROFESSIONAL (and thereafter confirm such notice in writing). OWNER shall
promptly consult with PROFESSIONAL concerning the necessity for OWNER to retain a qualified
expert to evaluate such hazardous condition or take corrective action, if any. CONTRACTOR shall
not be required to resume Work in connection with such hazardous condition or in any such affected
area until after OWNER has obtained any required permits related thereto and delivered to
CONTRACTOR special written notice (i) specifying that such condition and any affected area is or
has been rendered safe for the resumption of Work, or (ii) specifying any special conditions under
which such Work may be resumed safely. If OWNER and CONTRACTOR cannot agree as to
entitlement to or the amount or extent of an adjustment, if any, in Contract Price or Contract Times
as a result of such Work stoppage or such special conditions under which Work is agreed by
GC-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
CONTRACTOR to be resumed, either party may make a claim therefor as provided in Articles 11 and
12.
4.7 If after receipt of such special written notice, CONTRACTOR does not agree to resume
such Work based on a reasonable belief it is unsafe, or does not agree to resume such Work under such
special conditions, then CONTRACTOR may order such portion of the Work that is in connection
with such hazardous conditions or in such affected area to be deleted from the Work. If OWNER and
CONTRACTOR cannot agree as to entitlement to or the amount or extent of an adjustment, if any, in
Contract Price or Contract Times as a result of deleting such portion of the Work, then either party may
make a claim therefor as provided in Articles 11 and 12. OWNER may have deleted such portion of
the Work performed by OWNER's own forces or others in accordance with Article 7.
4.7.1 The provisions of 4.2 and 4.3 are not intended to apply to Asbestos, PCBs, Petroleum,
Hazardous Waste or Radioactive Material uncovered or revealed at the site.
GC-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 5-BONDS AND INSURANCE
Performance and Other Bonds:
5.1. CONTRACTOR shall furnish performance and payment Bonds, each in an amount at least
equal to the Contract Price as Security for the faithful performance and payment of all
CONTRACTOR's obligations under the Contract Documents. These Bonds shall remain in effect at
least until one year after the date when final payment becomes due, except as otherwise provided by
Law or Regulation or by the Contract Documents. CONTRACTOR shall also furnish such other
Bonds as are required by the Supplementary Conditions. All Bonds shall be in the forms prescribed
by Law or Regulation or by the Contract Documents and be executed by such sureties as are named
in the current list of "Companies Holding Certificates of Authority as Acceptable Sureties on Federal
Bonds, and as Acceptable Reinsuring Companies" as published in Circular 570 (amended) by the
Audit Staff Bureau of Accounts, U.S. Treasury Department. All Bonds signed by an agent must be
accompanied by a certified copy of the authority to act.
Licensed Sureties and Insurers; Certificates of Insurance
5.2.1 All bonds and insurance required by the Contract Documents to be purchased and
maintained by CONTRACTOR shall be obtained from surety or insurance companies that are duly
licensed or authorized in the State of Georgia to issue bonds or insurance policies for the limits and
coverages so required. All bonds signed by an agent must be accompanied by a certified copy of
authority to act. Such surety and insurance companies shall also meet such additional requirements and
qualifications as may be provided in the Supplementary Conditions.
5.2.2. CONTRACTOR shall deliver to OWNER, with copies to each additional insured
identified in 5.3, an original or a certified copy of the complete insurance policy for each policy
required, certificates of insurance (and other evidence of insurance requested by OWNER or any other
additional insured) which CONTRACTOR is required to purchase and maintain in accordance with
5.3.
5.2.3. If the surety on any Bond furnished by CONTRACTOR is declared bankrupt or
becomes insolvent or its right to do business is terminated in any state where any part of the Project
is located or it ceases to meet the requirements of paragraph 5.1, CONTRACTOR shall within five
days thereafter substitute another Bond and Surety, both of which must be acceptable to OWNER.
CONTRACTOR's Liability Insurance:
5.3. CONTRACTOR shall purchase and maintain such comprehensive general liability and
other insurance as is appropriate for the Work being performed and furnished and as will provide
GC-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
protection from claims set forth below which may arise out of or result from CONTRACTOR's perfor-
mance and furnishing of the Work and CONTRACTOR's other obligations under the Contract
Documents, whether it is to be performed or furnished by CONTRACTOR, by any Subcontractor, by
anyone directly or indirectly employed by any of them to perform or furnish any of the Work, or by
anyone for whose acts any of them may be liable:
5.3.1. Claims under workers' or workmen's compensation, disability benefits and other similar
employee benefit acts;
5.3.2. Claims for damages because of bodily injury, occupational sickness or disease, or death
of CONTRACTOR's employees;
5.3.3. Claims for damages because of bodily injury, sickness or disease, or death of any person
other than CONTRACTOR's employees;
5.3.4. Claims for damages insured by personal injury liability coverage which are sustained (a)
by any person as a result of an offense directly or indirectly related to the employment of such person
by CONTRACTOR, or (b) by any other person for any other reason;
5.3.5. Claims for damages, other than to the Work itself, because of injury to or destruction
of tangible property wherever located, including loss of use resulting therefrom;
5.3.6. Claims arising out of operation of Laws or Regulations for damages because of bodily
injury or death of any person or for damage to property; and
5.3.7. Claims for damages because of bodily injury or death of any person or property damage
arising out of the OWNERSHIP, maintenance or use of any motor vehicle.
The insurance required by this paragraph 5.3 shall include the specific coverage's and be written for
not less than the limits of liability and coverage's provided in the Supplementary Conditions, or
required by law, whichever is greater. The comprehensive general liability insurance shall include
completed operations insurance. All of the policies of insurance so required to be purchased and
maintained (or the certificates or other evidence thereof) shall contain a provision or endorsement that
the coverage afforded will not be canceled, materially changed or renewal refused until at least thirty
days prior written notice has been given to OWNER, PROGRAM MANAGER, and PROFESSIONAL
by certified mail. All such insurance shall remain in effect until final payment and at all times
thereafter when CONTRACTOR may be correcting, removing or replacing defective Work in
accordance with paragraph 13.12. In addition, CONTRACTOR shall maintain such completed
operations insurance for at least two years after final payment and furnish OWNER with evidence of
continuation of such insurance at final payment and one year thereafter.
GC-I6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Contractual Liability Insurance:
5.4. The comprehensive general liability insurance required by paragraph 5.3 will include
contractual liability insurance applicable to CONTRACTOR's obligations under paragraphs 6.32 and
6.33.
OWNER's Liability Insurance:
5.5. OWNER shall be responsible for purchasing .and maintaining OWNER's own liability
insurance, and/or Risk Retention Program, and, at OWNER's option, may purchase and maintain such
insurance as will protect OWNER against claims which may arise from operations under the Contract
Documents.
Property Insurance:
5.6. Unless otherwise provided in the Supplementary Conditions, OWNER shall purchase and
maintain property insurance upon the Work at the site to the full insurable value thereof (subject to
such deductible amounts as may be provided in the Supplementary Conditions or required by Laws
and Regulations). This insurance shall include the interests of OWNER, CONTRACTOR,
Subcontractors, PROGRAM MANAGER, PROFESSIONAL and PROFESSIONAL's consultants in
the Work, all of whom shall be listed as insureds or additional insured parties, shall insure against the
perils of fire and extended coverage and shall include "all risk" insurance for physical loss and damage
including theft, vandalism and malicious mischief, collapse and water damage, and such other perils
as may be provided in the Supplementary Conditions, and shall include damages, losses and expenses
arising out of or resulting from any insured loss or incurred in the repair or replacement of any insured
property (including but not limited to fees and charges of PROFESSIONALs, architects, attorneys and
other PROFESSIONALs). If not covered under the "all risk" insurance or otherwise provided in the
Supplementary Conditions, CONTRACTOR shall purchase and maintain similar property insurance
on portions of the Work stored on and off the site or in transit when such portions of the Work are to
be included in an Application for Payment.
5.7. OWNER shall purchase and maintain such boiler and machinery insurance or additional
property insurance as may be required by the Supplementary Conditions or Laws and Regulations
which will include the interests of OWNER, CONTRACTOR, Subcontractors, PROFESSIONAL
AND PROFESSIONAL's consultants in the Work, all of whom shall be listed as insured or additional
insured parties.
5.8. All the policies of insurance (or the certificates or other evidence thereof) required to be
purchased and maintained by OWNER in accordance with paragraphs 5.6 and 5.7 will contain a
provision or endorsement that the coverage afforded will not be canceled or materially changed or
renewal refused until at least thirty days prior written notice has been given to CONTRACTOR by
certified mail and will contain waiver provisions in accordance with paragraph of 5.11.2.
GC-17
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
5.9. OWNER shall not be responsible for purchasing and maintaining any property insurance
to protect the Interests of CONTRACTOR, Subcontractors or others in the Work to the extent of any
deductible amounts that are provided in the Supplementary Conditions. The risk of loss within the .
deductible amount will be borne by CONTRACTOR, Subcontractor or others suffering any such loss,
and if any of them wishes property insurance coverage within the limits of such amounts, each may
purchase and maintain it at the purchaser's own expense.
5.10. If CONTRACTOR requests in writing that other special insurance be included in the
property insurance policy, OWNER shall, if possible, include such insurance, and the costthereof will
be charged to CONTRACTOR by appropriate Change Order or Written Amendment. Prior to com-
mencement of the Work at the site, OWNER shall in writing advise CONTRACTOR whether or not
such other insurance has been procured by OWNER.
Waiver of Rights:
5.11.1. OWNER and CONTRACTOR waive all rights against each other for all losses and
damages caused by any of the perils covered by the policies of insurance provided in response to
paragraphs 5.6 and 5.7 and other property insurance applicable to the Work, and also waive all such
rights against the Subcontractors, PROFESSIONAL, PROFESSIONAL's consultants and all other
parties named as insureds in such policies for losses and damages so caused. As required by paragraph
6.11, each subcontract between CONTRACTOR and a Subcontractor will contain similar waiver
provisions by the Subcontractor in favor of OWNER, CONTRACTOR, PROFESSIONAL, PROF-
ESSIONAL's consultants and all other parties named as insureds. None of the above waivers shall
extend to the rights that any of the insured parties may have to the proceeds of insurance held by
OWNER as trustee or otherwise payable under any policy so issued.
5.11.2. OWNER and CONTRACTOR intend that policies provided in response to paragraphs
5.6 and 5.7 shall protect all of the parties insured and provide primary coverage for all losses and
damages caused by the perils covered thereby. Accordingly, all such policies shall contain provisions
to the effect that in the event of payment of any loss or damage the insurer will have no rights of
recovery against any of the parties named as insureds or additional insureds, and if the insurers require
separate waiver forms to be signed by PROFESSIONAL or PROFESSIONAL's consultant, OWNER
will obtain the same, and if such waiver forms are required of any Subcontractor, CONTRACTOR will
obtain the same.
Receipt and Application of Proceeds:
5.12. Any insured loss under the policies of insurance required by paragraphs 5.6 and 5.7 will
be adjusted with OWNER and made payable to OWNER as trustee for the insureds, as their interests
may appear, subject tothe requirements of any applicable mortgage clause and of paragraph 5.13.
OWNER shall deposit in a separate account any money so received and shall distribute it in
GC-I8
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
accordance with such agreement as the parties in interest may reach. If no other special agreement is
reached, the damaged Work shall be repaired or replaced, the moneys so received applied on account
thereof, and the Work and the cost thereof covered by an appropriate Change Order or Written
Amendment.
Receipt and Application of Insurance Proceeds
5.13. OWNER, as trustee, shall have power to adjust and settle any loss with the insurers
unless one of the parties in interest shall object in writing within fifteen days after the occurrence of
loss to OWNER's exercise of this power. If such objection be made, OWNER, as trustee, shall make
settlement with the insurers in accordance with such agreement as the parties in interest may reach.
If required in writing by any party in interest, OWNER as trustee shall, upon the occurrence of an
insured loss, give bond for the proper performance of such duties.
Acceptance of Insurance:
5.14. If OWNER has any objection to the coverage afforded by or other provisions of the
insurance required to be purchased and maintained by CONTRACTOR in accordance with paragraphs
5.3 and 5.4 on the basis of its not complying with the Contract Documents, OWNER shall notify
CONTRACTOR in writing thereof within ten days of the date of delivery of such certificates to
OWNER in accordance with paragraph 2.7. If CONTRACTOR has any objection to the coverage
afforded by or other provisions of the policies of insurance required to be. purchased and maintained
by OWNER in accordance with paragraphs 5.6 and 5.7 on the basis of their not complying with the
Contract Documents, CONTRACTOR shall notify OWNER in writing thereof within ten days of the
date of delivery, of such certificates to CONTRACTOR in accordance with paragraph 2.7. OWNER
and CONTRACTOR shall each provide to the other such additional information in respect of
insurance provided by each as the other may reasonably request. Failure by OWNER or
CONTRACTOR to give any such notice of objection within the time provided shall constitute
acceptance of such insurance purchased by the other as complying with the Contract Documents.
Partial Utilization-Property Insurance:
5.15. If OWNER finds it necessary to occupy or use a portion or portions of the Work prior
to Substantial Completion of all the Work, such use or occupancy may be accomplished in accordance
with paragraph 14.10 provided that no such use or occupancy shall commence before the insurers
providing the property insurance have acknowledged notice thereof and in writing effected the changes
in coverage necessitated thereby. The insurers providing the property insurance shall consent by
endorsement on the policy or policies, but the property insurance shall not be canceled or lapse on
account of any such partial use or occupancy.
Indemnification
GC-19
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
5.16.1. CONTRACTOR shall indemnify and hold harmless OWNER, PROGRAM
MANAGER, and its employees and agents from and against all liabilities, claims, suits, demands,
damages, losses, and expenses, including attorneys' fees, arising out of or resulting from the
performance of its Work, provided that any such liability, claim, suit, demand, damage, loss, or
expense (a) is attributable to bodily injury, sickness, disease or death, or injury to or destruction of
tangible property, including the loss of use resulting therefrom and (b) is caused in whole or in part
by an act or omission of CONTRACTOR, any Subcontractor, anyone directly or indirectly employed
by any of them, or anyone for whose acts any of them may be liable, whether or not it is caused in
whole or in part by the negligence or other fault of a party indemnified hereunder.
5.16.2. In any and all claims against OWNER or any of its agents or employees by any
employee of CONTRACTOR, any SUBCONTRACTOR, anyone directly or indirectly employed by
any of them, or anyone for whose acts any of them may be liable, the indemnification obligation under
the previous paragraph shall not be limited in any way as to the amount or type of damages,
compensation or benefits payable by or for CONTRACTOR or any SUBCONTRACTOR under
workmen's compensation acts, disability benefit acts, or other employee benefit acts.
5.16.3. CONTRACTOR shall indemnify and hold harmless OWNER and anyone directly or
indirectly employed by it from and against all claims, suits, demands, damages, losses expenses
(including attorneys' fees) arising out of any infringement on patent or copyrights held by others and
shall defend all such claims in connection with any alleged infringement of such rights.
GC-20
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 6--CONTRACTOR'S RESPONSffiILITIES
6.1. CONTRACTOR shall supervise and direct the Work competently and efficiently,
devoting such attention thereto and applying such skills and expertise as may be necessary to perform
the Work in accordance with the Contract Documents. CONTRACTOR shall be solely responsible
for the means, methods, techniques, sequences and procedures of construction, but CONTRACTOR
shall not be responsible for the negligence of others in the design or specification of a specific means,
method, technique, sequence or procedure of construction which is shown or indicated in and expressly
required by the Contract Documents. CONTRACTOR shall be responsible to see that the finished
Work complies accurately with the Contract Documents.
6.2. CONTRACTOR shall keep on the Work, at all times during its progress, a competent
resident superintendent, who shall not be replaced without written notice to OWNER and
PROFESSIONAL except under extraordinary circumstances. The superintendent will be
CONTRACTOR's representative at the site and shall have authority to act on behalf of CON-
TRACTOR. All communications to the superintendent shall be as binding as if given to
CONTRACTOR.
Labor, Materials and Equipment:
6.3. CONTRACTOR shall provide competent, suitably qualified personnel to survey and lay
out the Work and perform construction as required by the Contract Documents. CONTRACTOR shall
at all times maintain good discipline and order at the site. Except in connection with the safety or
protection of persons or the Work or property at the site or adjacent thereto, and except as otherwise
indicated in the Contract Documents, all Work at the site shall be performed during regular working
hours, and CONTRACTOR will not permit evening work or the performance of Work on Saturday,
Sunday or any legal holiday without OWNER's written consent given after prior written notice to
PROFESSIONAL.
6.4. Unless otherwise specified in the General Requirements, CONTRACTOR shall furnish
and assume full responsibility for all materials, equipment, labor, transportation, construction
equipment and machinery, tools, appliances, fuel, power, light, heat, telephone, water, sanitary
facilities, temporary facilities and all other facilities and incidentals whether temporary or permanent
necessary for the execution, testing, initial operation, and completion of the Work as required by the
Contract Documents.
6.5. All materials and equipment shall be of good quality and new, except as otherwise
provided in the Contract Documents. If required by PROFESSIONAL, CONTRACTOR shall furnish
satisfactory evidence (including reports of required tests). as to the kind and quality of materials and
equipment. All materials and equipment shall be applied, installed, connected, erected, used, cleaned
and conditioned in accordance with the instructions of the applicable Supplier except as otherwise
GC-2l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
provided in the Contract Documents; but no provision of any such instructions will be effective to
assign to PROFESSIONAL, or any of PROFESSIONAL's consultants, agents or employees, any duty
or authority to supervise or direct the furnishing or performance of the Work or any duty or authority
to undertake responsibility contrary to the provisions of paragraph 9.14 or 9.15.
Adjusting Progress Schedule:
6.6. CONTRACTOR shall submit to PROFESSIONAL for acceptance to the extent indicated
in paragraph 2.9 adjustments in the progress schedule to reflect the impact thereon of new
developments; these will conform generally to the progress schedule then in effect and additionally
will comply with any provisions of the General Requirements applicable thereto.
Substitutes or "Or-Equal" Items:
6.7.1. Whenever materials or equipment are specified or described in the Contract Documents
by using the name of a proprietary item or the name of a particular Supplier, the naming of the item
is intended to establish the type, function and quality required. Unless the name is followed by words
indicating that no substitution is permitted, materials or equipment of other Suppliers may be accepted
by PROFESSIONAL if sufficient information is submitted by CONTRACTOR to allow
PROFESSIONAL to determine that the material or equipment proposed is equivalent or equal to that
named. The procedure for review by PROFESSIONAL will include the following as supplemented
in the General Requirements. Requests for review of substitute items of material and equipment will
not be accepted by PROFESSIONAL from anyone other than CONTRACTOR. If CONTRACTOR
wishes to furnish or use a substitute item of material or equipment, CONTRACTOR shall make wri-
tten application to PROFESSIONAL for acceptance thereof, certifying that the proposed substitute will
perform adequately the functions and achieve the results called for by the general design, be similar
and of equal substance to that specified and be suited to the same use as that specified. The application
will state that the evaluation and acceptance of the proposed substitute will not prejudice
CONTRACTOR's achievement of Substantial Completion on time, whether or not acceptance of the
substitute for use in the Work will require a change in any of the Contract Documents (or in the
provisions of any other direct contract with OWNER for work on the Project) to adapt the design to
the proposed substitute and whether or not incorporation or use of the substitute in connection with
the Work is subject to payment of any license fee or royalty. All variations of the proposed substitute
from that specified will be identified in the application and available maintenance, repair and
replacement service will be indicated. The application will also contain an itemized estimate of all
costs that will result directly or indirectly from acceptance of such substitute, including costs of
redesign and claims of other contractors affected by the resulting change, all of which shall be
considered by PROFESSIONAL. In evaluating the proposed substitute, PROFESSIONAL may
require CONTRACTOR to furnish, at CONTRACTOR's expense, additional data about the proposed
substitute.
GC-22
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
6.7.2. If a specific means, method, technique, sequence or procedure of construction is
indicated in or required by the Contract Documents, CONTRACTOR may furnish or utilize a
substitute means, method, sequence, technique or procedure of construction acceptable to
PROFESSIONAL, if CONTRACTOR submits sufficient information to allow PROFESSIONAL to
determine that the substitute proposed is equivalent to that indicated or required by the Contract
Documents. The procedure for review by PROFESSIONAL will be similar to that provided in
paragraph 6.7.1 as applied by PROFESSIONAL and as may be supplemented in the General
Requirements.
6.7.3. PROFESSIONAL will be allowed a reasonable time within which to evaluate each
proposed substitute. PROFESSIONAL will be the sole judge of acceptability and no substitute will
be ordered, installed or utilized without PROFESSIONAL's prior written acceptance which will be evi-
denced by either a Change Order or an approved Shop Drawing. OWNER may require
CONTRACTOR to furnish, at CONTRACTOR's expense, a special performance guarantee or other
surety with respect to any substitute. PROFESSIONAL will record time required by PROFESSIONAL
and PROFESSIONAL's consultants in evaluating substitutions proposed by CONTRACTOR and in
making changes in the Contract Documents occasioned thereby. Whether or not PROFESSIONAL
accepts a proposed substitute, CONTRACTOR shall reimburse OWNER for the charges of
PROFESSIONAL and PROFESSIONAL's consultants for evaluating each proposed substitute.
Concerning Subcontractors, Suppliers and Others:
6.8.1. CONTRACTOR shall not employ any Subcontractor, Supplier or other person or
organization (including those acceptable to OWNER and PROFESSIONAL as indicated in paragraph
6.8.2) whether initially or as a substitute, against whom OWNER or PROFESSIONAL may have
reasonable objection. CONTRACTOR shall not be required to employ any Subcontractor, Supplier
or other person or organization to furnish or perform any of the Work against whom CONTRACTOR
has reasonable objection.
6.8.2. If the Supplementary Conditions require the identity of certain Subcontractors, Suppliers
or other persons or organizations including those who are to furnish the principal items of materials
and equipment to be submitted to OWNER prior to the Effective Date of the Agreement for
acceptance by OWNER and PROFESSIONAL and if CONTRACTOR has submitted a list thereof in
accordance with the Supplementary Conditions, OWNER's or PROFESSIONAL's acceptance (either
in writing or by failing to make written objection thereto by the date indicated for acceptance or objec-
tion in the bidding documents or the Contract Documents) of any such Subcontractor, Supplier or other
person or organization so identified may be revoked on the basis of reasonable objection after due
investigation, in which case CONTRACTOR shall submit an acceptable substitute, the Contract Price
will be increased by the difference, and the cost occasioned by such substitution and an appropriate
Change Order will be issued or Written Amendment signed. No acceptance by OWNER or
PROFESSIONAL of any such Subcontractor, Supplier or other person or organization shall constitute
a waiver of any right of OWNER or PROFESSIONAL to reject defective Work.
GC-23
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
6.9. CONTRACTOR shall be fully responsible to OWNER and PROFESSIONAL for all acts
and omissions of the Subcontractors, Suppliers and other persons and organizations performing or
furnishing any of the Work under a direct or indirect contract with CONTRACTOR just as
CONTRACTOR is responsible for CONTRACTOR's own acts and omissions. Nothing in the Contract
Documents shall create any contractual relationship between OWNER or PROFESSIONAL and any
such Subcontractor, Supplier or other person or organization, nor shall it create any obligation on the
part of OWNER or PROFESSIONAL to payor to see to the payment of any moneys due any such
Subcontractor, Supplier or other person or organization except as may otherwise be required by Laws
and Regulations.
6.10. The divisions and sections of the Specifications and the identifications of any Drawings
shall not control CONTRACTOR in dividing the Work among Subcontractors or Suppliers or
delineating the Work to be performed by any specific trade.
6.11. All Work performed for CONTRACTOR by a Subcontractor will be pursuant to an
appropriate agreement between CONTRACTOR and the Subcontractor which specifically binds the
Subcontractor to the applicable terms and conditions of the Contract Documents for the benefit of
OWNER and PROFESSIONAL and contains waiver provisions as required by paragraph 5.11.
CONTRACTOR shall pay each Subcontractor a just share of any insurance moneys received by
CONTRACTOR on account of losses under policies issued pursuant to paragraphs 5.6 and 5.7.
Patent Fees and Royalties:
6.12. CONTRACTOR shall pay all license fees and royalties and assume all costs incident to
the use in the performance of the Work or the incorporation in the Work of any invention, design,
process, product or device which is the subject of patent rights or copyrights held by others.
CONTRACTOR shall indemnify and hold harmless OWNER and PROFESSIONAL and anyone
directly or indirectly employed by either of them from and against all claims, damages, losses and
expenses including attorneys' fees and court and arbitration costs arising out of any infringement on
patent rights or copyrights incident to the use in the performance of the Work or resulting from the
incorporation in the Work of any invention, design, process, product or device not specified in the
Contract Documents, and shall defend all such claims in connection with any alleged infringement of
such rights.
Permits:
6.13. CONTRACTOR shall obtain and pay for all construction permits, licenses, governmental
charges and inspection fees, and all public utility charges which are applicable and necessary for the
execution of the Work. All permit costs shall be included in the base bid. Permits, if any, that are
provided and paid for by OWNER are listed in the Supplementary Conditions. Any delays associated
with the permitting process will be considered for time extensions only and no damages or additional
GC-24
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
compensation for delay will be allowed.
Laws and Regulations:
6.14.1. CONTRACTOR shall give all notices and comply with all Laws and Regulations
applicable to furnishing and performance of the Work. Except where otherwise expressly required by
applicable Laws and Regulations, neither OWNER nor PROFESSIONAL shall be responsible for
monitoring CONTRACTOR's compliance with any Laws or Regulations.
6.14.2. If CONTRACTOR observes that any of the Contract Documents are contradictory to
such laws, rules, and regulations, it will notify the Project Manager promptly in writing. Any
necessary changes shall then be adjusted by an appropriate Change Order. If CONTRACTOR
performs any Work that it knows or should have known to be contrary to such laws, ordinances, rules,
and regulations and without such notice to the Project Manager, it shall bear all related costs.
Taxes:
6.15. CONTRACTOR shall pay all sales, consumer, use and other similar taxes required to
be paid in accordance with the Laws and Regulations of the place of the Project which are applicable
during the performance of the Work.
Use of Premises:
6.16. CONTRACTOR shall confine construction equipment, the storage of materials and
equipment and the operations of workers to the Project site and land and areas identified in and
permitted by the Contract Documents and other land and areas permitted by Laws and Regulations,
rights-of-way, permits and easements. CONTRACTOR shall not unreasonably encumber the premises
with construction equipment or other materials or equipment. Any loss or damage to
CONTRACTOR's or any Subcontractor's equipment is solely at the risk of CONTRACTOR.
CONTRACTOR shall assume full responsibility for any damage to any such land or area, or to the
OWNER or occupant thereof or of any land or areas contiguous thereto, resulting from the
performance of the Work. Should any claim be made against OWNER or PROFESSIONAL by any
such OWNER or occupant because of the performance of the Work, CONTRACTOR shall promptly
attempt to settle with such other party by agreement or otherwise resolve the claim by arbitration or
at law. CONTRACTOR shall, to the fullest extent permitted byLaws and Regulations, indemnify and
hold OWNER harmless from and against all claims, damages, losses and expenses (including, but not
limited to, fees of PROFESSIONALs, architects, attorneys and other professionals and court and
arbitration costs) arising directly, indirectly or consequentially out of any action, legal or equitable,
brought by any such other party against OWNER to the extent based on a claim arising out of
CONTRACTOR's performance of the Work.
6.17. During the progress of the Work, CONTRACTOR shall keep the premises free from
GC-25
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
accumulations of waste materials, rubbish and other debris or contaminants resulting from the Work.
At the completion of the Work, CONTRACTOR shall remove all waste materials, rubbish and debris
from and about the premises as well as all tools, appliances, construction equipment and machinery,
and surplus materials, and shall leave the site clean and ready for occupancy by OWNER. CON-
TRACTOR shall restore to original condition all property not designated for alteration by the Contract
Documents.
6.18. CONTRACTOR shall not load nor permit any part of any structure to be loaded in any
manner that will endanger the structure, nor shall CONTRACTOR subject any part of the Work or
adjacent property to stresses or pressures that will endanger them.
Record Documents:
6.19. Contractor shall keep at the site and in good order one record copy of the Contract
Documents and all Drawings and Specifications. These documents shall be annotated on a continuing
basis to show all changes made during the construction process. These shall be available to
PROFESSIONAL and the Project Manager and shall be submitted with the Application for Final
Payment.
Safety and Protection:
6.20. CONTRACTOR shall be responsible for initiating, maintaining and supervising all
safety precautions and programs in connection with the Work. CONTRACTOR shall assume all risk
of loss for stored equipment or materials, irrespective of whether CONTRACTOR has transferred the
title of the stored equipment or materials to OWNER. CONTRACTOR shall take all necessary
precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or
loss to:
6.20.1. all employees on the Work and other persons and organizations who may be affected
thereby;
6.20.2. all the Work and materials and equipment to be incorporated therein, whether in
storage on or off the site; and
6.20.3. other property at the site or adjacent thereto, including trees, shrubs, lawns, walks,
pavements, roadways, structures, utilities and Underground Facilities not designated for removal,
relocation or replacement in the course of construction.
CONTRACTOR shall comply with all applicable Laws and Regulations of any public body having
jurisdiction for the safety of persons or property or to protect them from damage, injury or loss; and
shall erect and maintain all necessary safeguards for such safety and protection. CONTRACTOR shall
notify OWNERs of adjacent property and of Underground Facilities and utility OWNERs when
GC- 26
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
prosecution of the Work may affect them, and shall cooperate with them in the protection, removal,
relocation and replacement of their property. All damage, injury or loss to any property referred to in
paragraph 6.20.2 or 6.20.3 caused, directly or indirectly, in whole or in part, by CONTRACTOR, any
Subcontractor, Supplier or any other person or organization directly or indirectly employed by any of
them to perform or furnish any of the Work or anyone for whose acts any of them may be liable, shall
be remedied by CONTRACTOR (except damage or loss attributable to the fault of Drawings or
Specifications or to the acts or omissions of OWNER or PROFESSIONAL or anyone employed by
either of them or anyone for whose acts either of them may be liable, and not attributable, directly or
indirectly, in whole or in part, to the fault or negligence of CONTRACTOR). CONTRACTOR's duties
and responsibilities for the safety and protection of the Work shall continue until such time as all the
Work is completed and PROFESSIONAL has issued a notice to OWNER and CONTRACTOR in
accordance, with paragraph 14.13 that the Work is acceptable (except as otherwise expressly provided
in connection with Substantial Completion).
6.21. CONTRACTOR shall designate a responsible member of its organization whose duty shall be
the prevention of accidents at the site. This person shall be CONTRACTOR's superintendent unless
otherwise designated in writing by CONTRACTOR to the Project Manager.
Emergencies:
6.22. In emergencies affecting the safety or protection of persons or the Work or property at
the site or adjacent thereto, CONTRACTOR, without special instruction or authorization from
PROFESSIONAL or OWNER, is obligated to act to prevent threatened damage, injury or loss.
CONTRACTOR shall give PROFESSIONAL prompt written notice if CONTRACTOR believes that
any significant changes in the Work or variations from the Contract Documents have been caused
thereby. If PROFESSIONAL determines that a change in the Contract Documents is required because
of the action taken in response to an emergency, a Work Change Directive or Change Order be issued
to document the consequences of the changes or variations.
6.22.1. CONTRACTOR shall immediately notify PROFESSIONAL of all events involving
injuries to any person on the Site, whether or not such person was engaged in the construction of the
Project, and shall file a written report on such person(s) and any other event resulting in property
damage of any amount within five (5) days of the occurrence.
6.22.2. If PROFESSIONAL determines that a change in the Contract Documents is required
because of the action taken by CONTRACTOR in response to such an emergency, a Change Order
will be issued to document the consequences of such action.
Shop Drawings and Samples:
GC-27
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
6.23. After checking and verifying all field measurements, CONTRACTOR shall promptly
submit to PROFESSIONAL for approval, in accordance with the accepted schedule of submittals, all
submittals and samples required by the Contract Documents. All submittals and samples shall have
been checked by and stamped with the approval of CONTRACTOR and identified as
PROFESSIONAL may require. The data shown on or with the submittals will be complete with
respect to dimensions, design criteria, materials and any other information necessary to enable
PROFESSIONAL to review the submittal as required. At the time of each submission,
CONTRACTOR shall give notice to PROFESSIONAL of all deviations that the submittal or sample
may have from the requirements of the Contract Documents.
6.24. PROFESSIONAL shall review and approve submittals and samples. Professional's
review and approval shall be only for conformance with the design concept of the Project and
compliance with the information given in the Contract Documents. The approval of a separate item
as such will not indicate approval of the assembly in which the item functions. CONTRACTOR will
make any corrections required by PROFESSIONAL and resubmit the required number of corrected
copies until approved. CONTRACTOR's stamp of approval on any submittal or sample shall
constitute its representation to PROFESSIONAL and OWNER that CONTRACTOR has determined
and verified all quantities, dimensions, field construction criteria, materials, catalog numbers, and
similar data, and that each submittal or sample has been reviewed or coordinated with the requirements
of the Work and the Contract Documents.
6.24.1. No Work requiring a submittal or sample submission shall commence until the
submission has been approved by PROFESSIONAL. A copy of each approved submittal and each
approved sample shall be kept in good order by CONTRACTOR at the site and shall be available to
PROFESSIONAL and OWNER. Any delays associated with the submittal process will be considered
for time extensions only, and no damages or additional compensation for delay will be allowed.
6.24.2. Before submission of each Shop Drawing or sample, CONTRACTOR shall have
determined and verified all quantities, dimensions, specified performance criteria, installation
requirements, materials, catalog numbers and similar data with respect thereto and reviewed or
coordinated each Shop Drawing or sample with other Shop Drawings and samples and with the
requirements of the Work and the Contract Documents.
6.24.3. At the time of each submission, CONTRACTOR shall give PROFESSIONAL specific
written notice of each variation that the Shop Drawings or samples may have from the requirements
of the Contract Documents, and, in addition, shall cause a specific notation to be made on each Shop
Drawing submitted to PROFESSIONAL for review and approval of each such variation.
6.26. PROFESSIONAL will review and approve with reasonable promptness Shop Drawings
and samples, but PROFESSIONAL's review and approval will be only for conformance with the
design concept of the Project and for compliance with the information given in the Contract
Documents and shall not extend to means, methods, techniques, sequences or procedures of
GC-28
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
construction (except where a specific means, method, technique, sequence or procedure of construction
is indicated in or required by the Contract Documents) or to safety precautions or programs incident
thereto. The review and approval of a separate item as such will not indicate approval of the assembly
in which the item functions.
6.27. PROFESSIONAL's approval of submittals or samples shall not relieve CONTRACTOR
from responsibility for any variation from the requirements of the Contract Documents unless
CONTRACTOR has, in writing, called PROFESSIONAL's attention to each such variation at the time
of submission and the OWNER has given written approval to the specific deviation; any such approval
by PROFESSIONAL shall not relieve CONTRACTOR from responsibility for errors or omissions in
the submittals.
6.28. Where a shop drawing or sample is required by the Contract Documents or the schedule
of shop drawings and sample submissions accepted by PROFESSIONAL as required, any related
work performed prior to PROFESSIONAL's review and approval of the pertinent submittal will be
at the sole expense and responsibility of CONTRACTOR.
Continuing the Work:
6.30. CONTRACTOR shall carry on the Work and adhere to the progress schedule during all
disputes or disagreements with OWNER. No Work shall be delayed or postponed pending resolution
of any disputes or disagreements, except as permitted by paragraph 15.6 or as CONTRACTOR and
OWNER may otherwise agree in writing.
Cleaning Up:
6.31. CONTRACTOR shall maintain the site free from accumulations of waste materials,
rubbish, and other debris or contaminants resulting from the work on a daily basis or as required. At
the completion of the work, CONTRACTOR shall remove all waste materials, rubbish, and debris
from the site as well as all tools, construction equipment and machinery, and surplus materials and will
leave the Site clean and ready for occupancy by OWNER. All disposal shall be in accordance with
applicable Laws and Regulations. In addition to any other rights available to OWNER under the
Contract Documents, CONTRACTOR's failure to maintain the site may result in withholding of any
amounts due CONTRACTOR. CONTRACTOR will restore to original condition those portions of
the site not designated for alteration by the Contract Documents.
Indemnification:
6.32. To the fullest extent permitted by Laws and Regulations, CONTRACTOR shall
indemnify and hold harmless OWNER, PROGRAM MANAGER and PROFESSIONAL and their
GC-29
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
consultants, agents and employees from and against all claims, damages, losses and expenses, direct,
indirect or consequential (including but not limited to fees and charges of PROGRAM MANAGER,
PROFESSIONALs, architects, attorneys and other PROFESSIONALs and court and arbitration costs)
arising out of or resulting from the performance of the Work, provided that any such claim, damage,
loss or expense (a) is attributable to bodily injury, sickness, disease or death, or to injury to or
destruction of tangible property (other than the Work itself) including the loss of use resulting
therefrom and (b) is caused in whole or in part by any negligent act or omission of CONTRACTOR,
any Subcontractor, any person or organization directly or indirectly employed by any of them to
perform or furnish any of the Work or anyone for whose acts any of them may be liable, regardless of
whether or not it is caused in part by a party indemnified hereunder or arises by or is imposed by Law
and Regulations regardless of the negligence of any such party.
6.33. In any and all claims against OWNER, PROGRAM MANAGER or PROFESSIONAL
or any of their consultants, agents or employees by any employee of CONTRACTOR, any
Subcontractor, any person or organization directly or indirectly employed by any of them to perform
or furnish any of the Work or anyone for whose acts any of them may be liable, the indemnification
obligation under paragraph 6.32 shall not be limited in any way by any limitation on the amount or
type of damages, compensation or benefits payable by or for CONTRACTOR or any such
Subcontractor or other person or organization under workers' or workmen's compensation acts,
disability benefit acts or other employee benefit acts.
6.34. The obligations of CONTRACTOR under paragraph 6.32 shall not extend to the liability
of PROFESSIONAL, PROFESSIONAL's consultants, agents or employees arising out of the
preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, designs or
specifications.
GC- 30
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 7---0THER WORK
Related Work at Site:
7.1. OWNER may perform other work related to the Project at the site by OWNER's own
forces, have other work performed by aided OWNERs or let other direct contracts therefor which shall
contain General Conditions similar to these. If the fact that such other work is to be performed was not
noted in the Contract Documents, written notice thereof will be given to CONTRACTOR prior to
starting any such other work, and, 'if CONTRACTOR believes that such performance will involve
additional expense to CONTRACTOR or requires additional time and the parties are unable to agree
as to the extent thereof, CONTRACTOR may make a claim therefor as provided in Articles 11 and
12.
7.1.2. CONTRACTOR shall afford each utility OWNER and other contractor who is a party
to such a direct contract for OWNER, if OWNER is performing the additional work with OWNER's
employees, proper and safe access to the site and a reasonable opportunity for the introduction and
storage of materials and equipment and the execution of such work, and shall properly connect and
coordinate the Work with theirs. CONTRACTOR shall do all cutting, fitting and patching of the Work
that may be required to make its several parts come together properly and integrate with such other
work. CONTRACTOR shall not endanger any work of others by cutting, excavating or otherwise
altering their work and will only cut or alter their work with the written consent of PROFESSIONAL
and the others whose work will be affected. The duties and responsibilities of CONTRACTOR under
this paragraph are for the benefit of such utility OWNERs and other contractors to the extent that there
are comparable provisions for the benefit of CONTRACTOR in said direct contracts between OWNER
and such utility OWNERs and other contractors.
7.2. If any part of CONTRACTOR's Work depends for proper execution or results upon the
work of any such other contractor or utility OWNER (or OWNER), CONTRACTOR shall inspect and
promptly report to PROFESSIONAL in writing any delays, defects or deficiencies in such work that
render it unavailable or unsuitable for such proper execution and results. CONTRACTOR's failure so
to report will constitute an acceptance of the other work as fit and proper for integration with
CONTRACTOR's Work except for latent or nonapparent defects and deficiencies in the other work.
Coordination:
7.4. If OWNER contracts with others for the performance of other work on the Project at the
site, the person or organization who will have authority and responsibility for coordination of the
activities among the various prime contractors will be identified in the Supplementary Conditions, and
the specific matters to be covered by such authority and responsibility will be itemized, and the extent
of such authority and responsibilities will be provided in the Supplementary Conditions. Unless
otherwise provided in the Supplementary Conditions, neither OWNER nor PROFESSIONAL shall
have any authority or responsibility in respect of such coordination.
GC-31
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 8---0WNER'S RESPONSIBILITIES
8.1. Except as otherwise provided in these General Conditions, OWNER shall issue all
communications to CONTRACTOR through the PROGRAM MANAGER or PROFESSIONAL.
8.2. In case of termination of the employment of PROFESSIONAL, OWNER shall appoint
a PROFESSIONAL against whom CONTRACTOR makes no reasonable objection, whose status
under the Contract Documents shall be that of the former PROFESSIONAL. Any dispute in
connection with such appointment shall be subject to arbitration.
8.3. OWNER shall furnish the data required of OWNER under the Contract Documents
promptly and shall make payments to CONTRACTOR promptly after they are due as provided in
paragraphs 14.4 and 14.13.
8.4. OWNER's duties in respect of providing lands and easements and providing Engineering
surveys to establish reference points are set forth in paragraphs 4.1 and 4.4. Paragraph 4.2 refers to
OWNER's identifying and making available to CONTRACTOR copies of reports of explorations and
tests of subsurface conditions at the site and in existing structures which have been utilized by
PROFESSIONAL in preparing the Drawings and Specifications.
8.5. OWNER's responsibilities in respect of purchasing and maintaining liability and property
insurance are set forth in paragraphs 5.5 through 5.8.
8.6. OWNER is obligated to execute Change Orders as indicated in paragraph 10.3.
8.7. OWNER's responsibility in respect of certain inspections, tests and approvals is set forth
in paragraph 13.4.
8.8. In connection with OWNER's right to stop Work or suspend Work, see paragraphs 13.10
and 15.1. Paragraph 15;2 deals with OWNER's right to terminate services of CONTRACTOR under
certain circumstances.
GC-32
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 9---PROFESSIONAL'S STATUS DURING
CONSTRUCTION
OWNER's Representative:
9.1. PROFESSIONAL will be OWNER's representative during the construction period. The
duties and responsibilities and the limitations of authority of PROFESSIONAL as OWNER's
representative during construction are set forth in the Contract Documents and shall not be extended
without written consent of OWNER and PROFESSIONAL.
Visits to Site:
9.2. PROFESSIONAL will make visits to the site at intervals appropriate to the various stages
of construction to observe the premises and quality of the executed Work and to determine, in general,
if the Work is proceeding in accordance with the Contract Documents. PROFESSIONALwill not be
required to make exhaustive or continuous on-site inspections to check the quality or quantity of the
Work. PROFESSIONAL's efforts will be directed toward providing for OWNER a greater degree of
confidence that the completed Work will conform to the Contract Documents. On the basis of such
visits and on-site observations as an experienced and qualified design PROFESSIONAL,
PROFESSIONAL will keep OWNER informed ofthe progress of the Work and will endeavor to guard
OWNER against defects and deficiencies in the Work.
Project Representation:
9.3. If OWNER and PROFESSIONAL agree, PROFESSIONAL will furnish a Resident
Project Representative to assist PROFESSIONAL in observing the performance of the Work. The
duties, responsibilities and limitations of authority of any such Resident Project Representative and
assistants will be as provided in the Supplementary Conditions. If OWNER designates another agent
to represent OWNER at the site who is not PROFESSIONAL's agent or employee, the duties,
responsibilities and limitations of authority of such other person will be as provided in the
Supplementary Conditions.
Clarifications and Interpretations:
9.4. PROFESSIONAL shall issue such written clarifications or interpretations ofthe Contract
Documents (in the form of Drawings or otherwise) as may be determined necessary, or as reasonably
requested by CONTRACTOR, which shall be consistent with or reasonably inferable from the overall
intent of the Contract Documents. If CONTRACTOR believes that a written clarification and
interpretation entitles it to an increase in the Contract Price and/or Contract Time, CONTRACTOR
may make a claim as provided for in Articles 11 or 12.
GC-33
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Authorized Variations in Work:
9.5. PROFESSIONAL may authorize minor variations in the Work from the requirements of
the Contract Documents which do not involve an adjustment in the Contract Price or the Contract
Time and are consistent with the overall intent of the Contract Documents. These may be
accomplished by a Field Order and will be binding on OWNER and also on CONTRACTOR who
shall perform the Work involved promptly. If CONTRACTOR believes that a Field Order justifies an
increase in the Contract Price or an extension of the Contract Time and the parties are unable to agree
as to the amount or extent thereof, CONTRACTOR may make a claim therefor as provided in Article
11 or 12.
Rejecting Defective Work:
9.6. PROFESSIONAL will have authority to disapprove or reject Work which
PROFESSIONAL believes to be defective and will also have authority to require special inspection
or testing ofthe Work as provided in paragraph 13.9, whether or not the Work is fabricated, installed
or completed.
Shop Drawings, Change Orders and Payments:
9.7. In connection with PROFESSIONAL's responsibility for Shop Drawings and samples, see
paragraphs 6.23 through 6.29 inclusive.
9.8. In connection with PROFESSIONAL's responsibilities as to Change Orders, see Articles
10, 11 and 12.
9.9. In connection with PROFESSIONAL's responsibilities in respect of Applications for
Payment, etc., see Article 14.
Determinations for Unit Prices:
9.10. PROFESSIONAL will determine the actual quantities and classifications of Unit Price
Work performed by CONTRACTOR. PROFESSIONAL will review with CONTRACTOR
PROFESSIONAL's preliminary determinations on such matters before rendering a written decision
thereon (by recommendation of an Application for Payment or otherwise). PROFESSIONAL's written
decisions thereon will be final and binding upon OWNER and CONTRACTOR, unless, within ten
days after the date of any such decision, either OWNER or CONTRACTOR delivers to the other party
to the Agreement and to PROFESSIONAL written notice of intention to appeal from such a decision.
Decisions on Disputes:
9.11. PROFESSIONAL will be the initial interpreter of the requirements of the Contract
Documents and judge of the acceptability of the Work thereunder. Claims, disputes and other matters
GC-34
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
relating to the acceptability of the Work or the interpretation of the requirements of the Contract
Documents pertaining to the performance and furnishing of the Work and claims under Articles II and
12 in respect of changes to the Contract Price or Contract Time will be referred initially to
PROFESSIONAL in writing with a request for a formal decision in accordance with this paragraph,
which PROFESSIONAL will render in writing within a reasonable time. Written notice of each such
claim, dispute and other matter will be delivered by the claimant to PROFESSIONAL and the other
party to the Agreement promptly (but in no event later than thirty days after the occurrence of the event
giving rise thereto) and written supporting data will be submitted to PROFESSIONAL and the other
party within sixty days after such occurrence unless PROFESSIONAL allows an additional period of
time. to ascertain more accurate data in support of the claim.
9.12. When functioning as interpreter and judge under paragraphs 9.10 and 9.11,
PROFESSIONAL will not show partiality to OWNER or CONTRACTOR and will not be liable in
connection with any interpretation or decision rendered in good faith in such capacity. The rendering
of a decision by PROFESSIONAL pursuant to paragraphs 9.10 and 9.11 with respect to any such
claim, dispute or other matter (except any which have been waived by the making or acceptance of
final payment as provided in paragraph 14.16) will be a condition precedent to any exercise by
OWNER or CONTRACTOR of such rights or remedies as either may otherwise have under the
Contract Documents or by Laws or Regulations in respect of any such claim, dispute or other matter.
Limitations on PROFESSIONAL's Responsibilities:
9.13. Neither PROFESSIONAL's authority to act under this Article or elsewhere in the
Contract Documents nor any decision made in good faith to exercise such authority shall give rise to
any duty or responsibility of PROFESSIONAL to CONTRACTOR, any Subcontractor, any of their
agents or employees.
9.14. PROFESSIONAL shall not be responsible for the construction means, methods,
techniques, sequences, or procedures or the safety precautions and programs used. PROFESSIONAL
shall not be responsible for CONTRACTOR's failure to perform the Work in accordance with the
Contract Documents.
9.15. PROFESSIONAL shall not be responsible for the acts or omissions of CONTRACTOR,
any Subcontractors, any agents or employees, or any other persons performing any of the Work.
GC-35
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 10--CHANGES IN THE WORK
10.1. Without invalidating the Contract, OWNER may at any time or from time to time order
additions, deletions, or revisions in the Work. The OWNER shall provide CONTRACTOR with a
proposal request, identifying the Work to be added, deleted or revised. Upon receipt, CONTRACTOR
shall promptly submit a written proposal for the changed work prepared in accordance with Articles
II and 12. If the proposal request calls only for the deletion of Work, the OWNER may order the
partial suspension of any Work related to the proposed deletion, in which case CONTRACTOR must
cease performance as directed; CONTRACTOR shall not be entitled to claim lost profits on deleted
work. All changed Work shall be executed under the applicable conditions of the Contract
Documents.
10.2. Additional Work performed by CONTRACTOR without authorization of a Change Order
will not entitle CONTRACTOR to an increase in the Contract Price or an extension of the Contract
Time, except in the case of an emergency as provided in Article 6. The effect of this paragraph shall
remain paramount and shall prevail irrespective of any conflicting provisions contained in these
Contract Documents.
10.3. Upon agreement as to changes in the Work to be performed, Work performed in an
emergency as provided in Article 6, and any other claim of CONTRACTOR for a change in the
Contract Time or the Contract Price, PROFESSIONAL will prepare a written Change Order to be
signed by PROFESSIONAL and CONTRACTOR and submitted to OWNER for approval.
10.4. In the absence of an agreement as provided in 10.3, OWNER may, at its sole discretion,
issue a Work Change Directive to CONTRACTOR. Pricing of the Work Change Directive will be in
accordance with Section 11.3. The Work Change Directive will specify a price, and if applicable a
time extension, determined to be reasonable by OWNER. If CONTRACTOR fails to sign such Work
Change Directive, CONTRACTOR may submit a claim in accordance with Articles II and 12, but
CONTRACTOR shall nevertheless.be obligated to fully perform the work as directed by the Work
Change Directive.
10.5. CONTRACTOR shall proceed diligently with performance of the Work as directed by
OWNER, regardless of pending claim actions, unless otherwise agreed to in writing.
10.6. If notice of any change affecting the general scope of the Work or the provisions of the
Contract Documents (including, but not limited to, Contract Price or Contract Time) is required by the
provisions of any Bond to be given to a surety, the giving of any such notice will be CONTRACTOR's
responsibility, and the amount of each applicable Bond will be adjusted accordingly.
GC-36
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE ll-CHANGE OF CONTRACT PRICE
11.1. The Contract Price constitutes the total compensation (subject to written authorized
adjustments) payable to CONTRACTOR for performing the Work. All duties, responsibilities and
obligations assigned to or undertaken by CONTRACTOR shall be at CONTRACTOR's expense
without change in the Contract Price.
11.2. The Contract Price may only be changed by a Change Order or by a Written Amendment.
Any claim for an increase or decrease in the Contract Price shall be based on written notice delivered
by the party making the claim to the other party and to PROFESSIONAL promptly (but in no event
later than thirty days) after the occurrence of the event giving rise to the claim and stating the general
nature of the claim. Notice of the amount of the claim with supporting data shall be delivered within
sixty days after such occurrence (unless PROFESSIONAL allows an additional period of time to
ascertain more accurate data in support of the claim) and shall be accompanied by claimant's written
statement that the amount claimed covers all known amounts (direct, indirect and consequential) to
which the claimant is entitled as a result of the occurrence of said event. All claims for adjustment in
the Contract Price shall be determined by PROFESSIONAL in accordance with paragraph 9.11 if
OWNER and CONTRACTOR cannot otherwise agree on the amount involved. No claim for an
adjustment in the Contract Price will be valid if not submitted in accordance with this paragraph 11.2.
11.3. The value of any Work covered by a Change Order or of any claim for an adjustment in
the Contract Price will be determined by the following procedures:
11.3.1. Designated Unit Price (Field Measure). CONTRACTOR and OWNER recognize and
acknowledge that the quantities shown for those items designated in the Bid Proposal as unit price
items are approximations prepared by OWNER for bid purposes and that the actual compensation
payable to CONTRACTOR for the utilization of such items is based upon the application of unit prices
to the actual quantities of items involved as measured in the field and required to complete the Work
as originally defined in the Contract Documents.
11.3.2. When it is determined by OWNER that an addition, deletion, or revision to the Work,
as defined in these Contract Documents, is required and affects the quantities required for items
designed in the Bid Proposal as unit price items, CONTRACTOR and OWNER agree that the
compensation payable to CONTRACTOR for such unit price items shall be adjusted accordingly by
a Change Order based upon the application of the appropriate unit prices shown in the Bid Proposal
to the quantity of the unit price item required to complete the Work as defined in the Contract
Documents.
11.3.3. Other Unit Prices. For items not designated in the bid proposal as unit prices, OWNER
and CONTRACTOR may establish unit prices as agreed on by Change Order.
GC-37
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
11.3.4. Lump Sum. When it is determined by OWNER that an addition, deletion or revision
to the Work is required which results in a change in Work designated in the Bid Proposal as a lump
sum item, the amount of increase or decrease in the lump sum price shall be established by mutual
agreement of the parties.
11.3.5. If the pricing methods specified in 11.3 are inapplicable, or if the parties are unable to
agree on a price for the changed work, a reasonable price for the same shall be established by OWNER
in accordance with 11.4 and 11.5. OWNER shall then process a unilateral Change Order, specifying
the said reasonable price, in accordance with 11.4 through 11.6. CONTRACTOR shall perform the
Work as directed in the Change Order.
11.3.6. Failure on the part of CONTRACTOR to construct any item to plan or authorized
dimensions within the specification tolerances shall result in: reconstruction to acceptable tolerances
at no additional costs to OWNER; acceptance at no pay; or acceptance at reduced final pay quantity
or reduced unit price, all at the discretion of OWNER. Determinations of aggregate monetary change
for items identified as lump sum quantities shall be made by OWNER based upon an analysis of the
scope of CONTRACTOR's failure to construct to plan or authorized dimensions.
Cost of the Work:
11.4. The term Cost of the Work means the sum of all costs necessarily incurred and paid by
CONTRACTOR in the proper performance of the Work. Except as otherwise may be agreed to in
writing by OWNER, such costs shall be in amounts no higher than those prevailing in the locality of
the Project, shall include only the following items and shall not include any of the costs itemized in
paragraph 11.5:
11.4.1. Payroll costs for employees in the direct employ of CONTRACTOR in the
performance of the Work under schedules of job classifications agreed upon by OWNER and
CONTRACTOR. Payroll costs for employees not employed full time on the Work shall be apportioned
on the basis of their time spent on the Work. Payroll costs shall include, but not be limited to, salaries
and wages plus the cost of fringe benefits which shall include social security contributions,
unemployment, excise and payroll taxes, workers' or workmen's compensation, health and retirement
benefits, bonuses, sick leave, vacation and holiday pay applicable thereto. Such employees shall
include superintendents and foremen at the site. The expenses of performing Work after regular
working hours, on Saturday, Sunday or legal holidays, shall be included in the above to the extent
authorized by OWNER.
11.4 .2. Cost of all materials and equipment furnished and incorporated in the Work, including
costs of transportation and storage thereof, and Suppliers' field services required in connection
therewith. All cash discounts shall accrue to CONTRACTOR unless OWNER deposits funds with
CONTRACTOR with which to make payments, in which case the cash discounts shall accrue to
OWNER. Trade discounts, rebates and refunds and all returns from sale of surplus materials and
GC-38
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
equipment shall accrue to OWNER, and CONTRACTOR shall make provisions so that they may be
obtained.
11.4.3. Payments made by CONTRACTOR to the Subcontractors for Work performed by
Subcontractors. If required by OWNER, CONTRACTOR shall obtain competitive bids from
Subcontractors acceptable to CONTRACTOR and shall deliver such bids to OWNER who then
determines, with the advice of PROFESSIONAL, which bids will be accepted. If a subcontract
provides that the Subcontractor is to be paid on the basis of Cost of the Work Plus a Fee, the
Subcontractor's Cost of the Work shall be determined in the same manner as CONTRACTOR's Cost
of the Work. All subcontracts shall be subject to the other provisions of the Contract Documents
insofar as applicable.
11.4.4. Costs of special consultants (including but not limited to engineers, architects, testing
laboratories, surveyors, attorneys and accountants) employed for services specifically related to the
Work.
11.4.5. Supplemental costs including the following:
11.4.5.1. The proportion of necessary transportation, travel and subsistence expenses of
CONTRACTOR's employees incurred in discharge of duties connected with the Work.
11.4.5.2. Cost, including transportation and maintenance, of all materials, supplies, equipment,
machinery, appliances, office and temporary facilities at the site and hand tools not owned by the
workers, which are consumed in the performance of the Work, and cost less market value of such
items used but not consumed which remain the property of CONTRACTOR.
11.4.5.3. Rentals of all construction equipment and machinery and the parts thereof whether
rented from CONTRACTOR or others in accordance with rental agreements approved by OWNER
with the advice of PROFESSIONAL, and the costs of transportation, loading, unloading, installation,
dismantling and removal thereof-all in accordance with terms of said rental agreements. The rental of
any such equipment, machinery or parts shall cease when the use thereof is no longer necessary for the
Work.
11.4.5.4. Sales, consumer, use or similar taxes related to the Work, and for which
CONTRACTOR is liable, imposed by Laws and Regulations.
11.4.5.5. Deposits lost for causes other than negligence of CONTRACTOR, any Subcontractor
or anyone directly or indirectly employed by any of them or for whose acts any of them may be liable,
and royalty payments and fees for permits and licenses.
11.4.5.6. Losses and damages (and related expenses), not compensated by insurance or
GC-39
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
otherwise, to the Work or otherwise sustained by CONTRACTOR in connection with the performance
and furnishing of the Work (except losses and damages within the deductible amounts of property
insurance established by OWNER in accordance with paragraph 5.6) provided they have resulted from
causes other than the negligence of CONTRACTOR, any Subcontractor, or anyone directly or
indirectly employed by any of them or for whose acts any of them may be liable. Such losses shall
include settlements made with the written consent and approval of OWNER. No such losses, damages
and expenses shall be included in the Cost of the Work for the purpose of determining CONTRAC-
TOR's Fee. If, however, any such loss or damage requires reconstruction and CONTRACTOR is
placed in charge thereof, CONTRACTOR shall be paid for services a fee proportionate to that stated
in paragraph 11.6.2.
11.4.5.7. The cost of utilities, fuel and sanitary facilities at the site.
11.4.5.8. Minor expenses such as telegrams, long distance telephone calls, telephone service
at the site, expressage and similar petty cash items in connection with the Work.
11.4.5.9. Cost of premiums for additional Bonds and insurance required because of changes
in the Work and premiums of property insurance coverage within the limits of the deductible amounts
established by OWNER in accordance with paragraph 5.6.
11.5. The term Cost of the Work shall not include any of the following:
11.5.1. Payroll costs and other compensation of CONTRACTOR's officers, executives,
principals (of partnership and sole proprietorships), general managers, engineers, architects, estimators,
attorneys, auditors, accountants, purchasing and contracting agents, expeditors, timekeepers, clerks
and other personnel employed by CONTRACTOR whether at the site or in CONTRACTOR's
principal or a branch office for general administration of the Work and not specifically included in the
agreed upon schedule of job classifications referred to in paragraph 11.4.1 or specifically covered by
paragraph 1I.4.4-all of which are to be considered administrative costs covered by CONTRACTOR's
Fee.
11.5.2. Expenses of CONTRACTOR's principal area branch offices other than
CONTRACTOR's office at the site.
11.5.3. Any part of CONTRACTOR's capital expenses, including interest on
CONTRACTOR'S capital used for the Change Order Work and charges against CONTRACTOR for
delinquent payments.
11.5.4. Cost of premiums for all Bonds and for all insurance whether or not CONTRACTOR
is required by the Contract Documents to purchase and maintain the same (except for the cost of
premiums covered by subparagraph 11.4.5.9 above).
GC-40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
11.5.5. Costs due to the negligence of CONTRACTOR, any Subcontractor, or anyone directly
or indirectly, employed by any of them or for whose acts any of them may be liable, including but not
limited to, the correction of defective Work, disposal of materials or equipment wrongly supplied and
making good any damage to property.
11.5.6. Other overhead or general expense costs of any kind and the costs of any item not
specifically and expressly included in paragraph 11.4.
CONTRACTOR's Fee:
11.6. CONTRACTOR's Fee allowed to CONTRACTOR for overhead and profit shall be
determined as follows:
11.6.1. a mutually acceptable fixed fee, or if none can be agreed upon;
11.6.2. a fee based on the following percentages of the various portions of the Cost of the
Work:
11.6.2.1. for costs incurred under paragraphs 11.4.1 and 11.4.2, CONTRACTOR's Fee shall
be fifteen percent,
11.6.2.2. for costs incurred under paragraph 11.4.3, CONTRACTOR's Fee shall five percent;
and if a subcontract is on the basis of Cost of the Work Plus a Fee, the maximum allowable to
CONTRACTOR on account of overhead and profit of all Subcontractors shall be fifteen percent,
11.6.2.3. no fee shall be payable on the basis of costs itemized under paragraphs 11.4.4, 11.4.5
and 11.3,
11.6.2.4. the amount of credit to be allowed by CONTRACTOR to OWNER for any such
change which results in a net decrease in cost will be the amount of the actual net decrease plus a
deduction in CONTRACTOR's Fee by an amount equal to ten percent of the net decrease, and
11.6.2.5. when both additions and credits are involved in anyone change, the adjustment in
CONTRACTOR's Fee shall be computed on the basis of the net change in accordance with paragraphs
11.6.2.1 through 11.6.2.4, inclusive.
11.7. For all changes, CONTRACTOR shall submit an itemized cost breakdown, together with
supporting data in such detail and form as prescribed by the Project Manager. When a credit is due,
the amount of credit to be allowed by CONTRACTOR to OWNER for any such change which results
in a net decrease in cost will be the amount of the actual net decrease in direct cost as determined by
the Project Manager, plus the applicable reduction in overhead and profit. When both additions and
credits are involved in any change, the combined overhead and profit shall be calculated on the basis
GC-41
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
of the net change, whether an increase or decrease. In any event, the minimum detail shall be an
itemization of all man-hours required by discipline/trade with the unit cost per man-hour and total
labor price, labor burden, equipment hours and rate for each piece of equipment, material by units of
measure and price per unit, other costs specifically itemized, plus the overhead and profit markup.
Cash Allowances:
11.8. It is understood that CONTRACTOR has included in the Contract Price all allowances
so named in the Contract Documents and shall cause the Work so covered to be done by such
Subcontractors or Suppliers and for such sums within the limit of the allowances as may be acceptable
to PROFESSIONAL CONTRACTOR agrees that:
11.8.1. The allowances include the cost to CONTRACTOR (less any applicable trade
discounts) of materials and equipment required by the allowances to be delivered at the site and all
applicable taxes; and
11.8.2. CONTRACTOR's costs for unloading and handling on the site, labor, installation costs,
overhead, profit and other expenses contemplated for the allowances have been included in the
Contract Price and not in the allowances. No demand for additional payment on account of any thereof
will be valid.
Prior to final payment, an appropriate Change Order will be issued as recommended by
PROFESSIONAL to reflect actual amounts due CONTRACTOR on account of Work covered by
allowances, and the Contract Price shall be correspondingly adjusted.
Unit Price Work:
11.9.1. Where the Contract Documents provide that all or part of the Work is to be Unit Price
Work, initially the Contract Price will be deemed to include for all Unit Price Work an amount equal
to the sum of the established unit prices for each separately identified item of Unit Price Work times
the estimated quantity of each item as indicated in the Agreement. The estimated quantities of items
of Unit Price Work are not guaranteed and are solely for the purpose of comparison of Bids and
determining an initial Contract Price. Determinations of the actual quantities and classifications of Unit
Price Work performed by CONTRACTOR will be made by PROFESSIONAL in accordance with
Paragraph 9.10.
11.9.2. Each unit price will be deemed to include an amount considered by CONTRACTOR
to be adequate to cover CONTRACTOR's overhead and profit for each separately identified item.
11.9.3. Where the quantity of any item of Unit Price Work performed by CONTRACTOR
differs materially and significantly from the estimated quantity of such item indicated in the Agreement
GC-42
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
and there is no corresponding adjustment with respect to any other item of Work and.. if
CONTRACTOR believes that CONTRACTOR has incurred additional expense as a result thereof,
CONTRACTOR may make a claim for an increase in the Contract Price in accordance with Article
11 if the parties are unable to agree as to the amount of any such increase.
GC-43
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 12--CHANGE OF CONTRACT TIME
12.1. The Contract Time may only be changed by a Change Order. Any request for an
extension in the Contract Time shall be made in writing and delivered to PROFESSIONAL and
OWNER within seven (7) calendar days of the occurrence first happening and resulting in the claim.
Written supporting data will be submitted to PROFESSIONAL and OWNER within fifteen (15)
calendar days after such occurrence unless the OWNER allows additional time. All claims submitted
by CONTRACTOR for adjustments to the Contract Time must set forth in detail the reasons for and
causes of the delay and clearly indicate why the subject delay was beyond CONTRACTOR's control
or fault.
12.2. If CONTRACTOR is delayed at any time in the performance, progress, commencement,
or completion of the Work by any act or neglect of OWNER or PROFESSIONAL, or by an employee
of either, or by any separate CONTRACTOR employed by OWNER, or by changes ordered in the
Work, or by labor disputes, fire, unavoidable casualties, utility conflicts which could not have been
identified or foreseen by CONTRACTOR using reasonable diligence, or any causes beyond
CONTRACTOR's control or fault, then the Contract Time shall be extended by Change Order for such
reasonable time as OWNER may determine. CONTRACTOR shall be entitled to an extension of time
for such causes only for the number of days of delay which OWNER may determine to be due solely
to such causes and only to the extent such occurrences actually delay the completion of the Work and
then only if CONTRACTOR shall have strictly complied with all the requirements of the Contract
Documents. Provided, however, notwithstanding anything in the Contract Documents to the contrary,
no interruption, interference, inefficiency, suspension or delay in the performance, progress,
commencement or completion of the Work for any cause whatsoever, including those for which
OWNER or PROFESSIONAL may be responsible in whole or in part, shall relieve CONTRACTOR
of its duty to perform or give rise to any right to damages or additional compensation from OWNER.
CONTRACTOR's sole and exclusive remedy against OWNER for interruption, interference,
inefficiency, suspension or delay of any aspect of the Work shall be the right to seek an extension to
the Contract Time in accordance with the procedures set forth herein.
GC-44
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 13--W ARRANTY AND GUARANTEE; TESTS AND INSPECTIONS:
CORRECTION, REMOVAL OR ACCEPTANCE OF DEFECTIVE WORK
Warranty and Guarantee:
13.1. CONTRACTOR warrants and guarantees to OWNER that all materials and equipment
will be new unless otherwise specified and that all work will be of good quality, performed in a
workmanlike manner, free from faults or defects, and in accordance with the requirements of the
Contract Documents and any inspections, tests, or approvals referred to in this Article. All
unsatisfactory Work, all faulty Work and all Work not conforming to the requirements of the Contract
Documents or such inspections, tests, approvals, or all applicable building, construction and safety
requirements shall be considered defective. Notice of all defects shall be given to CONTRACTOR
by PROFESSIONAL. All defective work, whether or not in place, may be rejected, corrected, or
accepted as provided in this Article.
Access to Work:
13 .2. For the duration of the Work, PROFESSIONAL and its representatives, other designated
representatives of OWNER, and authorized representatives of any regulatory agency shall at all times
be given access to the Work. CONTRACTOR shall provide proper facilities for such access and
observation of the Work and also for any inspection or testing by others.
Tests and Inspections:
13.3. If the Contract Documents, laws, ordinances, rules, regulations or orders of any public
authority having jurisdiction require any Work to specifically be inspected, tested, or approved by
someone other than CONTRACTOR, CONTRACTOR shall give PROFESSIONAL timely notice of
readiness therefore.
13.4. The testing firm(s) (if assigned by OWNER to this Work) and all such inspections, tests,
or approvals provided for by OWNER shall be identified in writing by PROFESSIONAL to
CONTRACTOR. All other inspections, tests or approvals shall be at CONTRACTOR's expense
including additional expenses for inspection and tests required as a result of delays by CONTRACTOR
or hours worked in excess of 40 hours per week. For all required inspections, tests, and approvals on
any Work prepared, performed, or assembled away from the site, CONTRACTOR will furnish
PROFESSIONAL with the required Certificates of Inspection, testing, or approval. All such tests will
be in accordance with the methods prescribed by the American Society for Testing and Materials or
such other applicable organizations as may be required by law or the Contract Documents. Materials
or Work in place that fail to pass acceptability tests shall be retested at the direction of
PROFESSIONAL and at CONTRACTOR's expense.
GC-45
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
13.5. All inspections, tests or approvals other than those required by Laws or Regulations of
any public body having jurisdiction shall be performed by organizations acceptable to OWNER and
CONTRACTOR (or by PROFESSIONAL if so specified).
13.6. If any Work (including the work of o1thers) that is to be inspected, tested or approved is
covered without written concurrence of PROFESSIONAL, it must, if requested by PROFESSIONAL,
be uncovered for observation. Such uncovering shall be at CONTRACTOR's expense unless
CONTRACTOR has given PROFESSIONAL timely notice of CONTRACTOR's intention to cover
the same and PROFESSIONAL has not acted with reasonable promptness in response to such notice.
13.7. Neither observations by PROFESSIONAL or Project Manager nor inspections, tests, or
approvals by persons other than CONTRACTOR shall relieve CONTRACTOR of its obligations to
perform the Work in accordance with the requirements of the Contract Documents.
Uncovering Work:
13.8. If any Work required to be inspected, 1tested or approved is covered prior thereto without
the prior written approval of PROFESSIONAL, or if any Work is covered contrary to the request of
PROFESSIONAL, the Work shall, if requested by PROFESSIONAL, be uncovered for observation,
inspection, testing or approval and replaced at CONTRACTOR's expense.
13.9. If PROFESSIONAL considers it necessary or advisable that covered Work be observed
by PROFESSIONAL or inspected or tested by others, CONTRACTOR, at PROFESSIONAL's request,
shall uncover, expose or otherwise make available for observation, inspection or testing as
PROFESSIONAL may require, that portion of the Work in question, furnishing all necessary labor,
material and equipment. If it is found that such W or]c is defective, CONTRACTOR shall bear all direct
and consequential costs of such uncovering, exposure, observation, inspection and testing and of
satisfactory reconstruction (including but not limited to fees and charges of PROFESSIONALs,
architects, attorneys and other PROFESSIONALs), and OWNER shall be entitled to an appropriate
decrease in the Contract Price and, if the parties are unable to agree as to the amount thereof, OWNER
may make a claim therefor as provided in Article 11. If, however, such Work is not found to be
defective, CONTRACTOR shall be allowed an increase in the Contract Price or an extension of the
Contract Time, or both, directly attributable to such uncovering, exposure, observation, inspection,
testing and reconstruction, and, if the parties are unable to agree as to the amount or extent thereof,
CONTRACTOR may make a claim therefor as provided in Articles II and 12.
OWNER May Stop the Work:
13.10. When Work is defective or when CONTRACTOR fails to supply sufficient skilled
workmen or suitable materials or equipment or make prompt payments to Subcontractors for labor,
materials, or equipment or if CONTRACTOR violates any provisions of these Contract Documents,
GC--46
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
OWNER may order CONTRACTOR to stop the Work until the cause for such order has been
eliminated. However, this right of OWNER to stop the Work shall not give rise to any duty on the part
of OWNER to exercise this right for the benefit of CONTRACTOR or any other party.
CONTRACTOR shall have no right to claim an increase in the Contract Price or Contract Time or
other damages for a stop work order under this paragraph.
Correction or Removal of Defective Work:
13.11. When directed by PROFESSIONAL, CONTRACTOR shall promptly, without cost to
OWNER and as specified by PROFESSIONAL, either correct the defective Work whether fabricated,
installed, or completed, or remove it from the site and replace it with non-defective Work. If
CONTRACTOR does not correct such defective Work or remove and replace such defective Work
within a reasonable time, as specified in a written notice from PROFESSIONAL, OWNER may have
the deficiency corrected. All direct and indirect costs of such correction shall be paid by
CONTRACTOR or deducted from payment to CONTRACTOR. CONTRACTOR will also bear the
expense of correcting or removing and replacing all Work of others destroyed or damaged by the
correction, removal, or replacement of the defective Work.
One Year Correction Period:
13 .12. If, after approval of final payment and prior to the expiration of one year after the date
of substantial completion or such longer period of time as may be prescribed by law or by the terms
of any applicable special guarantee required by the Contract Documents, any Work or materials are
found to be defective, incomplete, or otherwise not in accordance with the Contract Documents,
CONTRACTOR shall promptly, without cost to OWNER and in accordance with OWNER's written
instructions, either correct such defective Work or if it has been rejected by OWNER, remove it from
the Site and replace it with non-defective Work. If CONTRACTOR does not promptly comply with
the terms of such instructions, OWNER may have the defective Work corrected, removed, or replaced.
All direct, indirect and consequential costs of such removal and replacement (including but not limited
to fees and charges of engineers, architects, attorneys and other professionals) will be paid by
CONTRACTOR.
Acceptance of Defective Work:
13.13. If, instead of requiring correction or removal and replacement of defective Work,
OWNER (and, prior to PROFESSIONAL's recommendation of final payment, PROFESSIONAL)
prefers to accept it, OWNER may do so. CONTRACTOR shall bear all direct, indirect and
consequential costs attributable to OWNER's evaluation of and determination to accept such defective
Work (such costs to be approved by PROFESSIONAL as to reasonableness and to include but not be
limited to fees and charges of engineers, architects, attorneys and other professionals). If any such
acceptance occurs prior to PROFESSIONAL's recommendation of final payment, a Change Order will
be issued incorporating the necessary revisions in the Contract Documents with respect to the Work,
GC-47
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the parties are
unable to agree as to the amount thereof, OWNER may make a claim therefor as provided in Article
II. If the acceptance occurs after such recommendation, an appropriate amount will be paid by
CONTRACTOR to OWNER.
OWNER May Correct Defective Work:
13.14. If CONTRACTOR fails within a reasonable time after written notice of
PROFESSIONAL to proceed to correct defective Work or to remove and replace rejected Work as
required by PROFESSIONAL in accordance with paragraph 13.11, or if CONTRACTOR fails to
perform the Work in accordance with the Contract Documents, or if CONTRACTOR falls to comply
with any other provision of the Contract Documents, OWNER may, after seven days' written notice
to CONTRACTOR, correct and remedy any such deficiency. In exercising the rights and remedies
under this paragraph, OWNER shall proceed expeditiously, to the extent necessary to complete
corrective and remedial action. OWNER may exclude CONTRACTOR from all or part of the site, take
possession of all or part of the Work, and suspend CONTRACTOR's services related thereto, take
possession of CONTRACTOR's tools, appliances, construction equipment and machinery at the site
and incorporate in the Work all materials and equipment stored at the site or for which OWNER has
paid CONTRACTOR but which are stored elsewhere. CONTRACTOR shall allow OWNER,
OWNER's representatives, agents and employees such access to the site as may be necessary to enable
OWNER to exercise the rights and remedies under this paragraph. All direct, indirect and con-
sequential costs of OWNER in exercising such rights and remedies will be charged against
CONTRACTOR in an amount approved as to reasonableness by PROFESSIONAL, and a Change
Order will be issued incorporating the necessary revisions in the Contract Documents with respect to
the Work, and OWNER shall be entitled to an appropriate decrease in the Contract Price, and, if the
parties are unable to agree as to the amount thereof, OWNER may make a claim therefor as provided
in Article 11. Such direct, indirect and consequential costs will include, but not be limited to, fees and
charges of engineers, architects, attorneys and other professionals, all court costs and all costs of repair
and replacement of work of others destroyed or damaged by correction, removal or replacement of
CONTRACTOR's defective Work. CONTRACTOR shall not be allowed an extension of the Contract
Time because of any delay in performance of the Work attributable to the exercise by OWNER of
OWNER's rights and remedies hereunder.
Neglected Work by CONTRACTOR
13.15. If CONTRACTOR neglects to execute the Work in accordance with the Contract
Documents, including any requirements of the progress schedule, PROFESSIONAL may direct
CONTRACTOR to submit a recovery plan and take specific corrective actions including, but not
limited to, employing additional workmen and/or equipment, and working extended hours and
additional days, all at no cost to OWNER in order to put the Work back on schedule. If
CONTRACTOR fails to correct the deficiency or take appropriate corrective action, OWNER may
terminate the contract or CONTRACTOR's right to proceed with that portion of Work and have the
GC-48
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Work done by others. The cost of completion under such procedure shall be charged against.
CONTRACTOR. A Change Order shall be issued incorporating the necessary revisions in the
Contract Documents, including an appropriate reduction in the Contract Price. If the payments due
CONTRACTOR are not sufficient to cover such amount, CONTRACTOR shall pay the difference to
OWNER.
13.16. Should CONTRACTOR work overtime, weekends or holidays to regain the schedule,
all costs to OWNER of associated inspection, construction management and resident engineers shall
be identified to CONTRACTOR and the Contract Price reduced by a like amount via Change Order.
GC-49
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 14-PA YMENTS TO CONTRACTOR AND COMPLETION
Schedule of Values:
14.1. The schedule of values established as provided in 2.9 will serve as the basis for progress
payments and will be incorporated into a form of application for Payment acceptable to Project
Manager. Progress payments on account of Unit Price Work will be based on the number of units
completed.
Application for Progress Payment:
14.2. At least twenty (20) calendar days before the date established for each progress payment
(but not more often than once a month), CONTRACTOR shall submit to PROFESSIONAL for review
an application for Payment filled out and signed by CONTRACTOR covering the work completed as
of the date of the application and accompanied by such supporting documentation as is required by the
Contract Documents. If payment is requested on the basis of materials and equipment not incorporated
in the Work but delivered and suitably stored at the site or at another location agreed to in writing, the
Application for Payment shall also be accompanied by a bill of sale, invoice or other documentation
warranting that OWNER has received the materials and equipment free and clear of all liens and
evidence that the materials and equipment are covered by appropriate property insurance and other
arrangements to protect OWNER's interest therein, all of which will be satisfactory to OWNER.
Payment is subject to a ten percent (10%) retainage that will be held until the final payment or
acceptance by OWNER. The amount of retainage with respect to progress payments will be as
stipulated in the Agreement.
CONTRACTOR's Warranty of Title:
14.3. CONTRACTOR warrants and guarantees that title to all Work, materials and equipment
covered by any Application for Payment, whether incorporated in the Project or not, will pass to
OWNER no later than the time of payment free and clear of all Liens.
Review of Applications for Progress Payment:
14.4. PROFESSIONAL will, within ten (10) calendar days after receipt of each Application
for Payment, either indicate in writing a recommendation of payment and present the application to
OWNER, or return the application to CONTRACTOR indicating in writing PROFESSIONAL's
reasons for refusing to recommend payment. In the latter case, CONTRACTOR may make the
necessary corrections and resubmit the application. OWNER shall, within thirty-one calendar days of
presentation to him of the application for payment with PROFESSIONAL's recommendation of the
amount for payment, pay CONTRACTOR amount recommended.
GC-50
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
14.5. PROFESSIONAL's recommendation of any payment requested in an Application for
Payment will constitute a representation by PROFESSIONAL to OWNER, based on PROF-
ESSIONAL's on-site observations of the Work in progress as an experienced and qualified design
PROFESSIONAL and on PROFESSIONAL's review of the Application for Payment and the
accompanying data and schedules, that the Work has progressed to the point indicated; that, to the best
of PROFESSIONAL's knowledge, information and belief, the quality of the Work is in accordance
with the Contract Documents subject to an evaluation of the Work as a functioning whole prior to or
upon Substantial Completion, to the results of any subsequent tests called for in the Contract
Documents, to a final determination of quantities and classifications for Unit Price Work under
paragraph 9.10, and to any other qualifications stated in the recommendation; and that CONTRAC-
TOR is entitled to payment of the amount recommended. However, by recommending any such
payment, PROFESSIONAL will not thereby be deemed to have represented that exhaustive or
continuous on-site inspections have been made to check the quality or the quantity of the Work beyond
the responsibilities specifically assigned to PROFESSIONAL in the Contract Documents or that there
may not be other matters or issues between the parties that might entitle CONTRACTOR to be paid
additionally by OWNER or OWNER to withhold payment to CONTRACTOR.
14.6. PROFESSIONAL's recommendation of final payment will constitute an additional
representation by PROFESSIONAL to OWNER that the conditions precedent to CONTRACTOR's
being entitled to final payment as set forth in paragraph 14.13 have been fulfilled.
14.7. PROFESSIONAL may refuse to recommend the whole or any part of any payment if,
in PROFESSIONAL's opinion, it would be incorrect to make such representations to OWNER.
PROFESSIONAL may also refuse to recommend any such payment, or, because of subsequently
discovered evidence or the results of subsequent inspections or tests, nullify any such payment
previously recommended, to such extent as may be necessary in PROFESSIONAL's opinion to protect
OWNER from loss because:
14.7.1. the Work is defective, or completed Work has been damaged requiring correction or
replacement.
14.7.2. the Contract Price has been reduced by Written Amendment or Change Order.
14.7.3. OWNER has been required to correct defective Work or complete Work in accordance
with paragraph 13.14. or
14.7.4. of PROFESSIONAL's actual knowledge of the occurrence of any of the events
enumerated in paragraphs 15.2.1 through 15.2.9 inclusive.
OWNER may refuse to make payment ofthe full amount recommended by PROFESSIONAL because
claims have been made against OWNER on account of CONTRACTOR's performance or furnishing
of the Work or Liens have been filed in connection with the Work or there are other items entitling
GC-51
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
OWNER to a off-set against the amount recommended, but OWNER must give CONTRACTOR
immediate written notice (with a copy to PROFESSIONAL) stating the reasons for such action.
Substantial Completion:
14.8. When CONTRACTOR considers the entire Work ready for its intended use,
CONTRACTOR shall notify OWNER and PROFESSIONAL in writing that the entire Work is
substantially complete (except for items specifically listed by CONTRACTOR as incomplete) and
request that PROFESSIONAL issue a certificate of Substantial Completion. Within a reasonable time
thereafter, OWNER, CONTRACTOR and PROFESSIONAL shall make an inspection of the Work
to determine the status of completion. If PROFESSIONAL does not consider the Work substantially
complete, PROFESSIONAL will notify CONTRACTOR in writing giving the reasons therefor. If
PROFESSIONAL considers the Work substantially complete, PROFESSIONAL will prepare and
deliver to OWNER a tentative certificate of Substantial Completion which shall fix the date of
Substantial Completion. There shall be attached to the certificate a tentative list of items to be
completed or corrected before final payment. OWNER shall have seven days after receipt of the
tentative certificate during which to make written objection to PROFESSIONAL as to any provisions
of the certificate or attached list. If, after considering such objections, PROFESSIONAL concludes that
the Work is not substantially complete, PROFESSIONAL will, within fourteen days after submission
of the tentative certificate to OWNER notify CONTRACTOR in writing stating the reasons therefor.
If, after consideration of OWNER's, objections, PROFESSIONAL considers the Work substantially
complete, PROFESSIONAL will within said fourteen days execute and deliver to OWNER and
CONTRACTOR a definitive certificate of Substantial Completion (with a revised tentative list of
items to be completed or corrected) reflecting such changes from the tentative certificate as
PROFESSIONAL believes justified after consideration of any objections from OWNER. At the time
of delivery of the tentative certificate of Substantial Completion, PROFESSIONAL will deliver to
OWNER and CONTRACTOR a written recommendation as to division of responsibilities pending
final payment between OWNER and CONTRACTOR with respect to security, operation, safety,
maintenance, heat, utilities, insurance and warranties. Unless OWNER and CONTRACTOR agree
otherwise in writing and so inform PROFESSIONAL prior to PROFESSIONAL's 'issuing the
definitive certificate of Substantial Completion, PROFESSIONAL's aforesaid recommendation will
be binding on OWNER and CONTRACTOR until final payment.
14.9. OWNER shall have the right to exclude CONTRACTOR from the Work after the date
of Substantial Completion, but OWNER shall allow CONTRACTOR reasonable access to complete
or correct items on the tentative list.
Partial Utilization:
14.10. Use by OWNER at OWNER's option of any substantially completed part of the Work
which (i) has specifically been identified in the Contract Documents, or (ii) OWNER,
PROFESSIONAL, and CONTRACTOR agree constitutes a separately functioning and usable part of
GC-52
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
the Work that can be used by OWNER for its intended purpose without significant interference with
CONTRACTOR's performance of the remainder of the Work, may be accomplished prior to
Substantial Completion of all the Work subject to the following:
14.10.1. OWNER at any time may request CONTRACTOR in writing to permit OWNER to
use any such part of the Work which OWNER believes to be ready for its intended use and
substantially complete. If CONTRACTOR agrees, CONTRACTOR will certify to OWNER and
PROFESSIONAL that said part of the Work is substantially complete and request PROFESSIONAL
to issue a certificate of Substantial Completion for that part of the Work. CONTRACTOR at any time
may notify OWNER and PROFESSIONAL in writing that CONTRACTOR considers any such part
of the Work ready for its intended use and substantially complete and request PROFESSIONAL to
issue a certificate of Substantial Completion for that part of the Work. Within a reasonable time after
either such request, OWNER, CONTRACTOR and PROFESSIONAL shall make an inspection of that
part of the Work to determine its status of completion. If PROFESSIONAL does not consider that part
of the Work to be substantially complete, PROFESSIONAL will notify OWNER and
CONTRACTOR, in writing, giving the reasons therefor. If PROFESSIONAL considers that part of
the Work to be substantially complete, the provisions of paragraphs 14.8 and 14.9 will apply with
respect to certification of Substantial Completion of that part of the Work and the division of
responsibility in respect thereof and access thereto.
14.10.2. OWNER may at any time request CONTRACTOR, in writing, to permit OWNER
to take over operation of any such part of the Work although it is not substantially complete. A copy
of such request will be sent to PROFESSIONAL and, within a reasonable time thereafter, OWNER,
CONTRACTOR and PROFESSIONAL shall make an inspection of that part ofthe Work to determine
its status of completion, and PROFESSIONAL will prepare a list of the items remaining to be
completed or corrected thereon before final payment. If CONTRACTOR does not object in writing
to OWNER and PROFESSIONAL that such part of the Work is not ready for separate operation by
OWNER, PROFESSIONAL will finalize the list of items to be completed or corrected and will deliver
such list to OWNER and CONTRACTOR together with a written recommendation as to the division
of responsibilities pending final payment between OWNER and CONTRACTOR with respect to
security, operation, safety, maintenance, utilities, insurance, warranties and guarantees for that part of
the Work which will become binding upon OWNER and CONTRACTOR at the time when OWNER
takes over such operation (unless they shall have otherwise agreed in writing and so informed
PROFESSIONAL). During such operation and prior to Substantial Completion of such part of the
Work, OWNER shall allow CONTRACTOR reasonable access to complete or correct items on said
list and to complete other related Work.
14.10.3. No occupancy or separate operation of part of the Work will be accomplished prior
to compliance with the requirements of paragraph 5.15 in respect of property insurance.
14.10.4. OWNER, may at its discretion, reduce the amount of retain age subject to Beneficial
GC-53
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
Occupancy.
Final Inspection:
14.11. Upon written notice from CONTRACTOR that the entire Work or an agreed upon
portion thereof is complete, PROFESSIONAL will make a final inspection with OWNER and CON-
TRACTOR and will notify CONTRACTOR in writing of all particulars in which this inspection
reveals that the Work is incomplete or defective. CONTRACTOR, shall immediately take such
measures as are necessary to remedy such deficiencies.
Final Application for Payment:
14.12. After CONTRACTOR has completed all such corrections to the satisfaction of
PROFESSIONAL and OWNER and delivered in accordance with the Contract Documents all
maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence
of insurance required by 5.2, certificates of inspection, marked-up record documents and other
documents, CONTRACTOR may make application for final payment following the procedure for
progress payments. The final Application for Payment shall be accompanied (except as previously
delivered) by: (i) all documentation called for in the Contract Documents, including but not limited
to the evidence of insurance required, (ii) consent of the surety, if any, to final payment, and (iii)
complete and legally effective releases or waivers (satisfactory to OWNER) of all liens arising out of
or filed in connection with the Work. In lieu of such releases or waivers of liens and as approved by
OWNER, CONTRACTOR may furnish receipts or release in full and an affidavit of CONTRACTOR
that (i) the releases and receipts include all labor, services, material and equipment for which a lien
could be filed, and (ii) all payrolls, material and equipment bills and other indebtedness connected with
the Work for which OWNER or OWNER's property might in any way be responsible have been paid
or otherwise satisfied. If any Subcontractor or supplier fails to furnish such a release or receipt in full,
CONTRACTOR may furnish a bond or other collateral satisfactory to OWNER to indemnify OWNER
against any lien.
14.12.1. No application for final payment will be accepted by OWNER until approved as-built
documents by CONTRACTOR are accepted and approved by PROFESSIONAL.
14.12.2. Notwithstanding any other provision of these contract documents to the contrary,
OWNER and PROFESSIONAL are under no duty or obligation whatsoever to any vendor, materials
provider, Subcontractor, laborer or other party to ensure that payments due and owing by
CONTRACTOR to any of them are or will be made. Such parties shall rely only on
CONTRACTOR's surety bonds for remedy of nonpayment by him. CONTRACTOR agrees to defend
and resolve all claims made by Subcontractors, indemnifying OWNER and PROFESSIONAL for all
claims arising from or resulting from Subcontractor or supplier or material men or laborer services in
connection with this project.
GC-54
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
14.12.3. General Indemnity: CONTRACTOR shall indemnify OWNER and PROFESSIONAL
for any damages sustained, including lost profits, resulting from CONTRACTOR's failure or refusal
to perform the work required by these contract documents.
Final Payment and Acceptance:
14.13. If, on the basis of PROFESSIONAL' s observation of the Work during construction and
final inspection and PROFESSIONAL's review of the final Application for Payment and
accompanying documentation as required by the Contract Documents, PROFESSIONAL is satisfied
that the Work has been completed and CONTRACTOR's other obligations under the Contract
Documents have been fulfilled, PROFESSIONAL will, within ten (10) working days after receipt of
the final Application for Payment, indicate in writing PROFESSIONAL's recommendation of payment
and present the Application to OWNER for payment. At the same time PROFESSIONAL will also
give written notice to OWNER and CONTRACTOR that the Work is acceptable subject to the
provisions of 14.6. Otherwise, PROFESSIONAL will return the application to CONTRACTOR,
indicating in writing the reasons for refusing to recommend final payment, in which case
CONTRACTOR shall make the necessary corrections and resubmit the Application. After the
presentation to OWNER of the application and accompanying documentation, in appropriate form and
substance and with PROFESSIONAL's recommendation and notice of acceptability, the amount
recommended by PROFESSIONAL will become due and will be paid by OWNER to
CONTRACTOR.
14.14. If, through no fault of CONTRACTOR, final completion of the Work is significantly
delayed and if PROFESSIONAL so confirms, OWNER shall, upon receipt of CONTRACTOR' s final
Application for Payment and recommendation of PROFESSIONAL and without terminating the
Agreement, make payment of the balance due for that portion of the Work fully completed and
accepted. If the remaining balance to be held by OWNER for Work not fully completed or corrected
is less than the retainage stipulated in the Contract and if bonds have been furnished as required in
Article 5, the written consent of the surety to the payment of the balance due for that portion of the
Work fully completed and accepted shall be submitted by CONTRACTOR to PROFESSIONAL with
the application for such payment. Such payment shall be made under the terms and conditions
governing final payment, except that it shall not constitute a waiver of claims.
CONTRACTOR's Continuing Obligation:
14.15. CONTRACTOR's obligation to perform and complete the Work in accordance with
the Contract Documents shall be absolute. Neither recommendation of any progress or
final payment by PROFESSIONAL, nor the issuance of a certificate of Substantial
Completion, nor any payment by OWNER to CONTRACTOR under the Contract
Documents, nor any use or occupancy of theW ork or any part thereof by OWNER, nor
any act of acceptance by OWNER nor any failure to do so, nor any review and approval
of a Shop Drawing or sample submission, nor the issuance of a notice of acceptability
GC-55
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
by PROFESSIONAL pursuant to paragraph 14.13, nor any correction of defective Work
by OWNER will constitute an acceptance of Work not in accordance with the Contract
Documents or a release of CONTRACTOR's obligation to perform the Work in
accordance with the Contract Documents (except as provided in paragraph 14.16).
Waiver of Claims:
14.16. The making and acceptance of final payment will constitute:
14.16.1. A waiver of all claims by OWNER against CONTRACTOR, except
claims arising from unsettled liens, from defecti ve Work appearing after final inspection
pursuant to 14.11, from failure to comply with the Contract Documents or the terms of
any special guarantees specified therein, or from CONTRACTOR's continuing
obligations under the Contract Documents; and
14.16.2. A waiver of all claims by CONTRACTOR against OWNER other than
those previously made in writing and still unsettled.
GC-56
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 15--SDSPENSION OF WORK AND
TERMINATION
OWNER May Suspend Work:
15.1. OWNER may, at any time and without cause, suspend the Work or any portion thereof for a
period of not more than ninety days by notice in writing to CONTRACTOR and PROFESSIONAL
which will fix the date on which Work will be resumed. CONTRACTOR shall resume the Work on
the date so fixed. CONTRACTOR shall be allowed an adjustment in the Contract Price or an extension
of the Contract Time, or both, directly attributable to any suspension if CONTRACTOR makes an
approved claim therefor as provided in Articles II and 12.
Termination For Cause:
15.2. Upon the occurrence of anyone or more of the following events:
15.2. 1. if CONTRACTOR commences a voluntary case under any chapter of the Bankruptcy
Code (Title 11, United States Code), as now or hereafter in effect, or if CONTRACTOR takes any
equivalent or similar action by filing a petition or otherwise under any other federal or state law in
effect at such time relating to the bankruptcy or insolvency;
15.2.2. if a petition is filed against CONTRACTOR under any chapter ofthe Bankruptcy Code
as now or hereafter in effect at the time of filing, or if a petition is filed seeking any such equivalent
or similar relief against CONTRACTOR under any other federal or state law in effect at the time
relating to bankruptcy or insolvency;
15.2.3. if CONTRACTOR makes a general assignment for the benefit of creditors;
15.2.4. if a trustee, receiver, custodian or agent of CONTRACTOR is appointed under
applicable law or under contract, whose appointment or authority to take charge of property of
CONTRACTOR is for the purpose of enforcing a Lien against such property or for the purpose of
general administration of such property for the benefit of CONTRACTOR's creditors;
15.2.5. if CONTRACTOR admits in writing an inability to pay its debts generally, asthey
become due;
15.2.6. if CONTRACTOR fails to perform the Work in accordance with the Contract
Documents (including, but not limited to, failure to supply sufficient skilled workers or suitable
materials or equipment or failure to adhere to the progress schedule established under paragraph 2.9
as revised from time to time);
GC-57
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
15.2.7. if CONTRACTOR disregards Laws or Regulations of any public body having
jurisdiction;
15.2.8. if CONTRACTOR disregards the authority of PROFESSIONAL; or
15.2.9. if CONTRACTOR otherwise violates in any substantial way any provisions of the
Contract Documents,
OWNER may, after giving CONTRACTOR (and the surety, ifthere be one) seven days' written notice
and to the extent permitted by Laws and Regulations, terminate the services of CONTRACTOR,
exclude CONTRACTOR from the site and take possession of the Work and of all CONTRACTOR's
tools, appliances, construction equipment and machinery at the site and use the same to the full extent
they could be used by CONTRACTOR (without liability to CONTRACTOR for trespass or
conversion), incorporate in the Work all materials and equipment stored at the site or for which
OWNER has paid CONTRACTOR but which are stored elsewhere, and finish the Work as OWNER
may deem expedient. In such case CONTRACTOR shall not be entitled to receive any further payment
until the Work is finished. If the unpaid balance of the Contract Price exceeds the direct, indirect and
consequential costs of completing the Work (including but not limited to fees and charges of
PROFESSIONALs, architects, attorneys and other PROFESSIONALs and court and arbitration costs)
such excess will be paid to CONTRACTOR. If such costs exceed such unpaid balance,
CONTRACTOR shall pay the difference to OWNER. Such costs incurred by OWNER will be
approved as to reasonableness by PROFESSIONAL and incorporated in a Change Order, but when
exercising any rights or remedies under this paragraph, OWNER shall not be required to obtain the
lowest price for the Work performed.
15.3. In the event OWNER terminates the contract for cause and it is subsequently judicially
determined that there was no cause for termination, the termination for convenience provision will be
the means for disposition of the balance of the contract obligations.
Termination for Convenience
15.4. Upon seven working days' written notice to CONTRACTOR and PROFESSIONAL,
OWNER may, without cause and without prejudice to any other right or remedy of OWNER, elect to
terminate the Contract. In such case, CONTRACTOR shall be paid (without duplication of any items):
15.4.1. For completed and acceptable Work executed in accordance with the Contract
Documents prior to the effective date of termination, including fair and reasonable sums for overhead
and profit on such Work;
15.4 .2. For expenses sustained prior to the effective date of termination in performing services
and furnishing labor, materials or equipment as required by the Contract Documents in connection
with uncompleted Work, plus fair and reasonable sums for overhead and profit on such expenses;
GC-58
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
15.4.3. For all claims, costs, losses and damages incurred in settlement of terminated contracts
with Subcontractors, suppliers and others; and
15.4.4. For reasonable expenses directly attributable to termination.
CONTRACTOR shall not be paid on account of loss of anticipated profits or revenue or other
economic loss arising out of or resulting from such termination.
15.5. Where CONTRACTOR's services have been so terminated by OWNER, the
termination will not affect any rights or remedies of OWNER against CONTRACTOR then existing
or which may thereafter accrue. Any retention or payment of moneys due CONTRACTOR by
OWNER will not release CONTRACTOR from liability.
CONTRACTOR May Stop Work or Terminate:
15.6. If through no act or fault of CONTRACTOR, the Work is suspended fora period of
more than ninety calendar days by OWNER or under an order of court or other public authority, or
PROFESSIONAL fails to act on any Application for Payment within thirty days after it is submitted
or OWNER fails for thirty-one days to pay CONTRACTOR any sum finally determined to be due,
then CONTRACTOR may upon seven working days' written notice to OWNER and
PROFESSIONAL and provided OWNER or PROFESSIONAL did not remedy such suspension or
failure within that time, terminate the Agreement and recover from OWNER payment on the same
terms as provided in 15.2. In lieu of terminating the Agreement and without prejudice to any other
right or remedy, if PROFESSIONAL has failed to act on an Application for Payment within thirty days
after it is submitted or OWNER has failed for thirty-one calendar days after it is submitted to pay
CONTRACTOR any sum finally determined to be due, CONTRACTOR may upon seven days' written
notice to OWNER and PROFESSIONAL stop the Work until receipt of payment of all such amounts
due CONTRACTOR, including interest thereon. The provisions of this paragraph are not intended
to preclude CONTRACTOR from making claim under Articles 11 and 12 foran increase in Contract
Price or Contract Time or otherwise for expenses or damage directly attributable to CONTRACTOR's
stopping Work as permitted by this paragraph. The provisions of this paragraph shall not relieve
CONTRACTOR of the obligations under paragraph 6.30 to carry on the Work in accordance with the
progress schedule and without delay during disputes and disagreements with OWNER.
GC-59
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 16-.;DISPUTE RESOLUTION
16.1. All disputes arising under this Contract or its interpretation whether involving law or
fact or both, or extra work, and all claims for alleged breach of contract shall within ten (10) working
days of the commencement of the dispute be presented by CONTRACTOR to OWNER for decision.
All papers pertaining to claims shall be filed in quadruplicate. Such notice need not detail the amount
of the claim but shall state the facts surrounding the claim in sufficient detail to identify the claim,
together with its character and scope. In the meantime, CONTRACTOR shall proceed with the Work
as directed. Any claim not presented within the time limit specified in this paragraph shall be deemed
to have been waived, except that if the claim is ofa continuing character and notice of the claim is not
given within ten (10) working days of its commencement, the claim will be considered only for a
period commencing ten (10) working days prior to the receipt by OWNER of notice thereof. Each
decision by OWNER will be in writing and will be mailed to CONTRACTOR by registered or
certified mail, return receipt requested, directed to his last known address.
16.2 All claims, disputes and other matters in question between OWNER and
CONTRACTOR arising out of, or relating to, the Contract Documents or the breach thereof shall be
decided under Georgia Law in the Superior Court of Richmond County, Georgia. CONTRACTOR by
execution of the Contract consents to jurisdiction and venue in the Superior Court of Richmond
County, Georgia, and waives any right to contest same.
GC-60
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
ARTICLE 17-MISCELLANEODS
Giving Notice:
17.1. Whenever any provision of the Contract Documents requires the giving of written
notice, it will be deemed to have been validly given if delivered in person to the individual or to a
member of the firm or to an officer of the corporation for whom it is intended, or if delivered at or sent
by registered or certified mail, postage prepaid, to the last business address known to the giver of the
notice.
Computation of Time:
17.2.1. When any period of time is referred to in the Contract Documents by days, it will be
computed to exclude the first and include the last day of such period. If the last day of any such period
falls on a Saturday or Sunday or on a day made a legal holiday by the law of the applicable jurisdiction,
such day will be omitted from the computation.
17.2.2. A calendar day of twenty-four hours measured from midnight to the next midnight shall
constitute a day.
General:
17.3. Should OWNER or CONTRACTOR suffer injury or damage to person or property
because of any error, omission or act of the other party or of any of the other party's employees or
agents or others for whose acts the other party is legally liable, claim should be made in writing to the
other party within a reasonable time of the first observance of such injury or damage. The provisions
of this paragraph 17.3 shall not be construed as a substitute for or a waiver of the provisions of any
applicable statute of limitations or repose.
17.4. The duties and obligations imposed by these General Conditions and the rights and
remedies available hereunder to the parties hereto, and, in particular but without limitation, the
warranties, guarantees and obligations imposed upon CONTRACTOR by paragraphs 6.32,13.1,13.12,
13.14,14.3 and 15.2 and all of the rights and remedies available to OWNER and PROFESSIONAL
thereunder, are in addition to, and are not to be construed in any way as a limitation of, any rights and
remedies available to any or all of them which are otherwise imposed or available by Laws or
Regulations, by special warranty or guarantee or by other provisions of the Contract Documents, and
the provisions of this paragraph will be as effective as if repeated specifically in the Contract
Documents in connection with each particular duty, obligation, right and remedy to which they apply.
All representations, warranties and guarantees made in the Contract Documents will survive final
payment and termination or completion of the Agreement.
GC-6l
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
17.5. CONTRACTOR shall keep adequate records and supporting documentation applicable
to this Work and Contract. Said records and documentation shall be retained by CONTRACTOR for
a minimum of five (5) years from the date of final completion or termination of this Contract.
OWNER shall have the right to audit, inspect, and copy all such records and documentation as often
as OWNER deems necessary during the period of the Contract and for a period of five (5) years
thereafter provided, however, such activity shall be conducted only during normal business hours.
OWNER, during this period oftime, shall also have the right to obtain a copy of and otherwise inspect
any audit made atthe direction of CONTRACTOR as concerns the aforesaid records and supporting
documentation.
17.6. The Contract Documents are intended by the Parties to, and do, supersede any and all
provisions of the Georgia Prompt Pay Act, o.c.G.A. Section 13-11-1, et seq. In the event any
provision of the Contract Documents are inconsistent with any provision of the Prompt Pay Act, this
provision of the Contract Documents shall control.
17.7. Notwithstanding any provision of the law to the contrary, the parties agree that no
interest shall be due Contractor on any sum held as retainage pursuant to the Contract Documents and
CONTRACTOR specifically waives any claim to same.
Substitutions:
17.8. Notwithstanding any provISIon of these general conditions, there shall be no
substitutions of materials that are not determined to be equivalent to those indicated or required in the
contract documents without an amendment to the contract.
Sanitary Sewer Overflow Prevention:
17.9. Procedures to Prevent Overflows During Sanitary Sewer Construction:
17.9.1 The CONTRACTOR is hereby notified that the discharge of any untreated wastewater
to waters of the State is a violation of Georgia Water Quality Regulations and is prohibited.
17.9.2 The CONTRACTOR will submit an Emergency Response Plan prior to beginning work.
This plan will include a list of key personnel with 24-hour contact information who will respond
during an emergency situation. The ERP will include estimates of mobilization time for a response
crew to arrive onsite. Any changes to the Emergency Response Plan will be submitted to the
RESIDENT PROJECT REPRESENTATIVE prior to implementation.
17.9.3 In the event bypass pumping is required to facilitate new sewer construction, bypassing
plans and supporting calculations must be submitted to the Augusta Utilities Department for review
prior to establishment of the bypass. All bypass systems will include complete redundancy in pumping
GC-62
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
systems, if failure of the primary pumping system could result in a discharge of untreated wastewater
to waters of the State.
17.9.4 Bypass pumping will be monitored continuously by a person knowledgeable in pump
operation and maintenance if the failure of the bypass pump could result in the discharge of untreated
wastewater to waters of the State.
17.9.5 In the event of a discharge of untreated wastewater, the CONTRACTOR will take the
following actions:
18. Take immediate steps to. eliminate or minimize the discharge of untreated wastewater.
19. Immediately notify the Utilities Department dispatcher (706.796.5000) and the RESIDENT
PROJECT REPRESENTATIVE (contact information will be provided at the
preconstruction conference).
20. Maintain a chronicle of relevant information regarding the incident including specific
actions taken by the CONTRACTOR and estimates of the discharge volume.
17.9.6 The RESIDENT PROJECT REPRESENTATIVE will coordinate notification of the
Georgia Environmental Protection Division (800.241.4113) and the Augusta Emergency Management
Agency if appropriate.
17.9.7 If, in the opinion of the RESIDENT PROJECT REPRESENTATIVE and the OWNER,
the CONTRACTOR is not responding to an emergency situation in an appropriate manner, the
Utilities Department will undertake necessary actions to abate an overflow situation. The cost of these
actions will be the responsibility of the CONTRACTOR.
17.9.8 Following a discharge of untreated wastewater, a downstream inspection will be
conducted by the Utilities Department to assess potential mitigation measures that may be required of
the CONTRACTOR.
PROGRAM MANAGER:
17.10 The PROGRAM MANAGER for the project is CH2M HILL, 360 Bay Street, Suite 100
Augusta, GA 30901.
The presence or duties of PROGRAM MANAGER's personnel at the construction site, whether as
on site representatives or otherwise, do not make PROGRAM MANAGER or PROGRAM
MANAGER's personnel in any way responsible for those duties that belong to OWNER and / or the
CONTRACTOR or other entities, and do not relieve the CONTRACTOR or any other entity of their
obligations, duties, and responsibilities, including, but not limited to, all construction methods, means,
techniques, sequences, and procedures necessary for coordinating and completing all portions of the
construction work in accordance with the construction Contract Documents and any health and safety
precautions required by such construction work.
GC-63
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Revision Date
August 2001
PROGRAM MANAGER and PROGRAM MANAGER's personnel have no authority to exercise any
control over any construction contractor or other entity or their employees in connection with their
work or any health or safety precautions and have no duty of inspecting, noting, observing, correcting,
or reporting on health or safety deficiencies of the CONTRACTOR(s) or other entity or any other
persons at the site except PROGRAM MANAGER's own personnel.
The presence of PROGRAM MANAGER's personnel at the construction site is for the purpose of
providing to OWNER a greater degree of confidence that the completed construction work will
conform generally to the construction documents and that the integrity of the design concept as
reflected in the construction documents has been implemented and preserved by the construction
contractor(s). PROGRAM MANAGER neither guarantees the performance of the construction
contractor(s) nor assumes responsibility for construction contractor's failure to perform work in
accordance with the construction documents.
For this AGREEMENT only, construction sites include places of manufacture for materials
incorporated into the construction work, and construction contractors include manufacturers of
materials incorporated into the construction work
GC-64
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION
SC-O 1.
SC-02.
SC-03.
SC-04.
SC-05.
SC-06.
SC-07.
SC-08.
SC-09.
SC-lO.
SC-l1.
SC-12.
SC-13.
SC-14.
SC-15.
SC-16.
SC-17 .
SC-18.
SC-19.
SC-20.
SC- 21.
SC-22.
SC-23.
SC-24.
SC-25.
SC-26.
SC-27.
SC-28.
SC-29.
SC-30.
SC-31.
SECTION SC-O
INDEX TO SUPPLEMENTARY CONDITIONS
Scope of the Work
List of Drawings
Bonds
Contractor's Liability Insurance
Project Sign
Protection of the Environment
Temporary Toilets
Plans and Specifications Furnished
Record Drawings
Shop Drawings
Existing Structures
Salvage Material
Referenced Specifications
Traffic Control
Surveys
Construction Order and Schedule
Consulting Engineers
Inspection and Testing of Work
Georgia Prompt Pay Act
City Acceptance
Disputes
Specified Materials
Interest Not Earned on Retainage
Basis of Payment
Compliance with Laws, Codes, Regulations, Etc.
Equivalent Materials
After Hours Inspection
Masters Golf Tournament
Bush Field Access
Coordination with Pump Station Contractor
Railroad Right-of-Way Coordination
SC-O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION SC
SUPPLEMENTARY CONDITIONS
-01. SCOPE OF THE WORK:
The project referred to in the Agreement shall consist of furnishing all materials, labor,
machinery, etc. necessary to install approximately 36,500 feet of 20" ductile iron sewer force main,
3,300 feet of 30",36" and 48" ductile iron gravity sewer and related appurtenances.
-02. LIST OF DRA WINGS:
The following drawings, prepared by Cranston, Robertson & Whitehurst, P.c. comprise
the plans for the project.
DATE
SHEET NO. TITLE ORIGINAL REVISED
1. Cover Sheet 08/12/05
2. Index to Sheets 08/12/05
3. General Notes 08/12/05
4. Detailed Estimate 08/12/05
5. Plan/Profile Sheet 08/12/05
6. Plan/Profile Sheet 08/12/05
7. Plan/Profile Sheet 08/12/05
8. Plan/Profile Sheet 08/12/05
9. Plan/Profile Sheet 08/12/05
10. Plan/Profile Sheet 08/12/05
11. Plan/Profile Sheet 08/12/05
12. Plan/Profile Sheet 08/12/05
13. Plan/Profile Sheet 08/12/05
14. Plan/Profile Sheet 08/12/05
15. Plan/Profile Sheet 08/12/05
16. Plan/Profile Sheet 08/12/05
17. Plan/Profile Sheet 08/12/05
18. Plan/Profile Sheet 08/12/05
SC-l
I
I
SHEET NO. TITLE
I 19. Plan/Profile Sheet
20. Plan/Profile Sheet
I 21. Plan/Profile Sheet
22. Plan/Profile Sheet
I 23. Plan/Profile Sheet
24. Plan/Profile Sheet
I 25. Plan/Profile Sheet
26. Plan/Profile Sheet
I 27. Plan/Profile Sheet
28. Plan/Profile Sheet
I 29. Plan/Profile Sheet
30. Plan/Profile Sheet
31. Plan/Profile Sheet
- 32. Plan/Profile Sheet
I 33. Plan/Profile Sheet
34. Plan/Profile Sheet
35. Plan/Profile Sheet
I 36. Plan/Profile Sheet
37. Plan/Profile Sheet
I 38. Gravity Sewer Plan/Profile Sheet
39. Gravity Sewer Plan/Profile Sheet
I 40. Gravity Sewer Plan/Profile Sheet
41. Detail Sheet
I 42. Detail Sheet
43. Erosion, Sedimentation and Pollution Control Plan
I 44. Erosion, Sedimentation and Pollution Control Details
I
I
I SC-2
I
DATE
ORIGINAL REVISED
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
08/12/05
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-03.
BONDS:
The Contractor will include in the lump sum payment for Lump Sum Construction the
cost of his performance and payment bonds.
-04.
CONTRACTOR'S LIABILITY INSURANCE:
Insurance shall be written with limits of liability shown below or as required by law,
whichever is greater:
Commercial General Liability (per occurrence) Each Occurrence
General Aggregate
Products
Personal & Adv Injury
Fire Damage
Automobile Liability (any auto) Combined Single Limit
Excess Liability (any auto) Each Occurrence
Workers Compensation
Employer Liability
$
$
$
$
$
$
$ 5,000,000
Statutory Limits
$ 1,000,000
1,000,000
2,000,000
2,000,000
1,000,000
500,000
1,000,000
-05.
PROJECT SIGN:
The Contractor will provide and install two (2) project signs at prominent locations on
the construction site as directed by the Engineer. The signs will carry in a prominent manner the
names of the project, the Owner, and the names of the Contractor and the Engineer and a 24-hour
phone number for the Contractor in 4-inch letters. The sign shall be constructed and erected on wood
posts in a substantial manner 8- feet above the ground. The full size stencil shall be approved along
with colors before fabrication. The Contractor shall include the cost of the project signs in his Lump
Sum Construction bid item.
-06.
PROTECTION OF THE ENVIRONMENT:
The Contractor will carefully schedule his work so that a minimum amount of the
exposed earth will be subject to erosion by rainfall or wind, and he will provide means satisfactory to
the Engineer to minimize the transportation of silt and other deleterious material from the project area
onto adjacent properties or into adjacent water courses.
All chemicals used during project construction or furnished for project operation,
whether herbicide, pesticide, disinfectant, polymer, reactant or of other classification, must show
approval of either EPA or USDA. Use of all such chemicals and disposal of residues shall be in
conformance with printed instructions.
-07.
TEMPORARY TOILETS:
Contractor shall provide temporary toilet facilities on the site for workmen employed
in the construction work. Toilets shall be adequate for the number of men employed and shall be
maintained in a clean and sanitary condition. Workmen shall be required to use only these toilets. At
SC-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
completion of the work, toilets used by Contractor shall be removed and premises left in the condition
required by the Contract.
-08.
PLANS AND SPECIFICATIONS FURNISHED:
The Contractor will be furnished, free of charge, by the Owner up to five (5) sets of
direct black line prints together with a like number of complete bound specifications for construction
purposes. Additional sets of plans and/or specifications will be furnished to the Contractor at the cost
of reproduction upon his written request.
-09.
RECORD DRAWINGS:
The Contractor will maintain in his office one complete set of drawings (including any
supplemental sketches) pertaining to the project upon which, at the end of each day's work any
deviations from the construction lines shown thereon and all changes ordered by the Engineer will be
shown accurately in red pencil. If necessary, supplemental drawings will be made to show details of
deviations or changes, and these will be kept with the marked set. The drawings will be available to
the Engineer for inspection during construction and at the completion of construction. Prior to
submitting his estimate for final payment, as-built drawings are to be prepared and submitted by the
contractor to the engineer. As-built drawings shall include tap locations and manholes located to a
minimum of two separate surface features.
-010. SHOP DRAWINGS:
The Contractor shall submit to the Engineer for his review shop drawings, cuts,
diagrams, bar lists, steel details and other descriptive data on every item, where shown on the drawings
or specified herein. The Contractor shall check all submittals and so indicate on each copy thereof.
Five copies of such shop drawings shall be submitted to the Engineer before ordering
of the material. Submittals which have not been checked by the Contractor will not be reviewed by
the Engineer. Reviews by the Engineer of submittals will cover only general conformity with the
project requirements, while responsibility for detailed conformity shall remain with the Contractor.
The Contractor will be notified by mail of the results of the submittal reviews within ten (10) days of
the receipt by the Engineer thereof.
-011. EXISTING STRUCTURES:
Where sidewalks, street signs, private signs, walls, fences, pipelines, etc. are removed
in accomplishing the work, each and every item will be replaced in the same or better manner or
condition than that in which it was before construction began. The Contractor will protect and hold
harmless the Owner from any suit, action, or dispute whatever arising from the Contractor's work
adjacent to private property.
-012. SALVAGE MATERIAL:
All existing installations to be removed, including but not limited to masonry and
concrete rubble, asphalt, pipe, etc. will be disposed of at an approved location by the Contractor.
SC-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-013. REFERENCED SPECIFICATIONS:
Where specifications or standards of trade organizations and other groups are referenced
in these specifications, they are made as much a part of these specifications as if the entire standard
or specification were reprinted herein. The inclusion of the latest edition or revision of the referenced
specification or standard is intended.
-014. TRAFFIC CONTROL:
Traffic control shall conform to the Manual on Uniform Traffic Control Devices
(MUTCD) of the Federal Highway Administration, latest edition. The Contractor shall give prior
written notification to and shall obtain the approval of the Augusta Fire Department, Police
Department, Emergency Medical Services, and the Augusta Traffic Engineering Department of any
street closures.
-015. SURVEYS:
The Engineer has established base lines for locating the principal component parts of
the work, together with a suitable number of bench marks adjacent to the work. From the information
thus provided, the Contractor shall develop and make all detail surveys needed for construction lines
and elevations. The Contractor shall employ only Registered Land Surveyors or Registered
Professional Engineer to perform all detail surveys.
The Contractor will diligently preserve and maintain the position of all stakes, reference
points and bench marks after they are set and, in case of willful or careless destruction, he shall be
charged with the resulting expense and shall be responsible for any mistakes that may be caused by
their unnecessary loss or disturbance.
-016. CONSTRUCTION ORDER AND SCHEDULE:
A. The Contractor shall be responsible for the detailed order, schedule, and
methods of construction activities within the general guidelines specified for
maintenance and protection of highway and pedestrian, traffic; utility lines;
drainage ways; adjacent properties; and as otherwise specified.
B. After notice to proceed and prior to the first payment on the contract the
Contractor shall submit the following for review:
(1) Breakdown of contract price into units of cost for each item required to
complete the total work; this breakdown will be the basis for judging
the percentage complete at any time.
(2) A statement of the order of procedure to be followed that will result in
the required protection and completion of the work within the overall
contract time.
(3) A bar chart showing the percentage of each item schedules against time
SC-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
and so scheduled that Contractor's order of construction is clearly
shown.
c.
With each request for payment the Contractor shall submit two copies of the
bar chart clearly marked to show the work completed at the date of the payment
requested.
D.
Progress Schedule Requirements
(1) Bar Chart Schedule: Prepare on maximum 11 inch by 17 inch sheet size
for each separate stage of Work as specified and shown, to include at
least:
(a) Identification and listing in chronological order of those
activities reasonably required to complete work, including, but
not limited to, subcontract work, major equipment design,
factory testing and startup activities, project close out and
cleanup and specified work sequences, constraints, and
milestones, including Substantial Completion date(s). Listings
to be identified by Specification section number.
(b) Identify: (i) horizontal time frame by year, month, and week, (ii)
duration, early-start, and completion of each activity and sub-
activity and (iii) critical activities and Project float.
(c) Provide sub-schedules to further define critical portions of the
work.
(d) Monthly schedule submissions: show overall percent complete,
projected and actual, and completion progress by listed activity
and sub-activity.
(e) Identify the critical path on the schedule.
(2) General:
(a) Schedule(s) shall reflect work logic sequences, restraints,
delivery windows, review times, contract times and milestones
set forth in the Agreement, and shall begin with the date of
Notice to Proceed and conclude with the date of Final
Completion.
(b) The schedule requirement herein is the minimum required.
Contractor may prepare a more sophisticated schedule if such
work will aid Contractor in execution and timely completion of
work.
SC-6
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
(c) Base schedule on standard 5-day work week.
(d) When bar chart or network analysis schedules are specified, use
Primavera Project Planner, latest version, SureTrak latest
version or a compatible and approved software.
(e) Adjust or confirm schedules on a monthly basis as follows:
Contractor shall submit to Engineer for acceptance proposed
adjustments in the progress schedule that will not change the
contract times (or milestones). Such adjustments will conform
generally to the progress schedule then if effect and additionally
will comply with any provisions of the General Requirements
applicable thereto.
Proposed adjustments in the progress scheduled that will
change the contract times (or milestones) may only be a Change
Order.
Use of float suppression techniques such as preferential
sequencing or logic, special leadllag logic restraints, and
extended activity times are prohibited, and use of float time
disclosed or implied by use of alternate float-suppression
techniques shall be shared to proportionate benefits to Owner
and Contractor.
Pursuant to above float-sharing requirement, no time extensions
will be granted nor delay damages paid until a delay occurs
which (i) impacts project's critical path, (ii) extends work
beyond contract completion date.
-017. CONSULTING ENGINEERS:
The Owner has engaged consulting engineers to assist the Director of Utilities, defined
herein as the Engineer, by preparing plans and specifications for the work and by providing certain
services during the bidding and construction phases of the project. The consulting engineer, Cranston,
Robertson & Whitehurst, P.c. are authorized to represent the Director of Utilities within the limits of
the various duties delegated and assigned to the firm by the Director. Nevertheless the Director of
Utilities remains the final authority hereunder and is the "Engineer" as used throughout the Contract
Documents. The Program Manager for the project is CH2M Hill, 360 Bay Street, Suite 100, Augusta,
Georgia 30901. The Program Manager's representative on the site will serve as the Resident Project
Representative (RPR) for the project.
The presence or duties of Program Manager's personnel at the construction site,
whether as onsite representatives or otherwise, do not make Program Manager or Program Manager's
personnel in any way responsible for those duties that belong to Owner and/or the Contractor or other
SC-7
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
entities, and do not relieve the Contractor or any other entity of their obligations, duties, and
responsibilities, including, but not limited to, all construction methods, means, techniques, sequences,
and procedures necessary for coordinating and completing all portions of the construction work in
accordance with the construction Contract Documents and any health and safety precautions required
by such construction work.
Program Manager and Program Manager's personnel have no authority to exercise any control over
any construction contractor or other entity or their employees in connection with their work or any
health or safety precautions and have no duty of inspecting, noting, observing, correcting, or reporting
on health or safety deficiencies of the Contractor(s) or other entity or any other persons at the site
except Program Manager's own personnel.
The presence of Program Manager's personnel at the construction site is for the purpose
of providing to Owner a greater degree of confidence that the completed construction work will
conform generally to the construction documents and that the integrity of the design concept as
reflected in the construction documents has been implemented and preserved by the construction
contractor(s). Program Manager neither guarantees the performance of the construction contractor(s)
nor assumes responsibility for construction contractor's failure to perform work in accordance with
the construction documents.
For this Agreement only, construction sites include places of manufacture for materials
incorporated into the construction work, and construction contractors include manufacturers or
materials incorporated into the construction work.
-018. INSPECTION AND TESTING OF WORK:
The Owner shall provide sufficient competent engineering personnel for the technical
observation and testing of the work.
The Engineer and his representatives shall at all times have access to the work
whenever it is in preparation or progress, and the Contractor shall provide proper facilities for such
access, and for inspections.
Inspectors shall have the power to stop work on account of a workman's incompetency,
drunkenness, or willful negligence or disregard of orders. An inspector may stop the work entirely if
there is not a sufficient quantity of suitable and approved materials or equipment on the ground to carry
it out properly or for any good and sufficient cause. Inspectors may not accept on behalf of the Owner
any material or workmanship which does not conform fully to the requirements of the contract and
they shall give no orders or directions under any possible circumstances not in accordance with the
Specifications. The Contractor shall furnish the inspector with all required assistance to facilitate
thorough inspection or the culling over or removal of defective materials or for any other purpose
requiring discharge of their duties for which service no additional allowance shall be made. The
inspector shall, at all times, have full permission to take samples of the materials that mayor may not
be used in the work.
SC-8
SC-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
Any inspection provided by the Engineers is for the purpose of determining compliance
with provisions of the contract specifications and is in no way a guarantee of the methods or appliances
use by the Contractor, nor for the safety of the job.
If the specifications, the Engineer's instructions, laws, ordinances, or any public
authority require any work to be specially tested or approved, the Contractor shall give the Engineer
timely notice of its readiness for inspection, and if the inspection is by an authority other than the
Engineer, of the date fixed for such inspection. Inspections by the Engineer shall be made promptly,
and where practicable at the source of supply. If any work should be covered up without review or
consent of the Engineer, it must, if required by the Engineer, be uncovered for examination and
properly restored at the Contractor's expense.
Re-examination of any work may be ordered by the Engineer, and, if so ordered, the
work must be uncovered by the Contractor. If such work is found to be in accordance with the
Contract Documents, the Owner shall pay the cost of re-examination and replacement. If such work
is not in accordance with the Contract Documents, the Contractor shall pay such cost.
The Owner will employ a qualified materials testing laboratory, hereinafter referred to
as the Laboratory, to monitor more fully on the Owner's behalf the quality of materials and work, and
to perform such tests as may be required under the Contract Documents as conditions for acceptance
of materials and work. The Laboratory will be solely responsible to and paid separately by the Owner.
The timing of the work of the Laboratory will be coordinated by the Engineer through his duly
authorized inspector.
The Owner will bear the cost of testing a particular material or area of the work once.
Where retesting is required following corrective measures or under other circumstances, the Contractor
shall reimburse the Owner for the cost of additional testing.
-019. GEORGIA PROMPT PAY ACT:
This Agreement is intended by the Parties to, and does, supersede any and all provisions
of the Georgia Prompt Pay Act, O.C.G.A. Section 13-11-1, et seq. In the event any provision of this
Agreement is inconsistent with any provision of the Prompt Pay Act, the provision of this Agreement
shall control.
-020. CITY ACCEPTANCE:
Notwithstanding any other obligations of the Contractor, he shall complete the work
to the full satisfaction of the Augusta Utilities Department and the Engineer. This provision shall not
relieve the Contractor of his responsibilities for guarantees.
-021. DISPUTES:
All claims, disputes and other matters in question between the Owner and the
Contractor arising out of or relating to the Agreement, or the breach thereof, shall be decided in the
Superior Court of Richmond County, Georgia. The Contractor, by executing this Agreement,
SC-lO
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
specifically consents to venue in Richmond County and waives any right to contest the venue in the
Superior Court of Richmond County, Georgia.
-022. SPECIFIED MATERIALS:
Attention is drawn to the specification of certain brands or manufacturers of
construction materials on the drawings. Unless the phrase "or equal" appears in the specification
thereon, no substitution or deviation from the product specified will be allowed.
Notwithstanding any provision of the general conditions, there shall be no substitution
of materials that are not determined to be equivalent to those indicated or required in the contract
documents without an amendment to the contract.
-023. INTEREST NOT EARNED ONRETAINAGE:
Notwithstanding any provision of the law to the contrary, the parties agree that no
interest shall be due to the Contractor on any sum held as retainage pursuant to this Agreement and
Contractor specifically waives any claim to same.
-024. BASIS OF PAYMENT:
As explained in the section "Instructions to Bidders" and paragraphs 11.91, 11.92 and
11.93 ofthe General Conditions, payment for all items of construction will be made at the total ofthe
actual number of units installed at the unit prices stated in the Bid Schedule to the Proposal. Partial
payments will be made based on the actual number of units of work completed during the month and
in-place at the unit prices stated in the Bid Schedule.
-025. COMPLIANCE WITH LAWS. CODES. REGULATIONS. ETC.:
Supplementing the provision of the GENERAL CONDmONS, the successful bidder
awarded this contract by signing the contract acknowledges the following, however, this is not to be
construed as all inclusive or being these only:
1. Underground Gas Pipe Law:
The Contractor signing the contract acknowledges that he is fully aware of the contents
and requirements of "Georgia Laws 1969, Pages 50 and the following, and any
amendments and regulations pursuant thereto", and the Contractor shall comply
therewith.
2. High Voltage Act:
The Contractor by signing the contract acknowledges that he is fully aware of the
contents and requirements of "Act No. 525, Georgia law 1960, and any amendments
thereto, and Rules and Regulations of the commissioner of Labor pursuant thereto" (the
preceding requirements within quotation marks being hereinafter referred to as the
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
"high voltage act"), and the Contractor shall comply therewith. The signing of
Contract shall also confirm on behalf of the Contractor that he:
A. has visited the premises and has taken into consideration the location of all
electrical power lines on and adjacent to all areas onto which the contract
documents require to permit the Contract either to work, to store materials, or
to stage operations, and
B. that the Contractor has obtained from the Owner of the aforesaid electric power
lines advice in writing as to the amount of voltage carried by the aforesaid
lines.
The Contractor agrees that he is the "person or persons responsible for the work
to be done" as referred to in the high voltage act and that accordingly the
Contractor is solely "responsible for the completion of the safety measures
which are required by Section 3 of the high voltage act before proceeding with
any work." The Contractor agrees that prior to the completion of precautionary
measures required by the high voltage act he will neither bring nor permit the
bringing of any equipment onto the site (or onto any area or areas onto which
the contract documents require or permit the Contractor to work, to store
materials, or to stage operations) with which it is possible to come within eight
feet of any high voltage line or lines pursuant to operations arising out of
performance of the Contract. The foregoing provisions apply to power lines
located (a) on the site and (b) on any area or areas onto which the contract
documents require or permit the Contractor either to work, to store materials,
or to stage operations, or (c) within working distance for equipment or
materials, being used on (a) and (b) above. These provisions of the Contract
do not limit or reduce the duty of the Contractor otherwise owed to the Owner,
to other parties, or to both. The Contractor agrees that the foregoing provisions
supplement provisions of the General Conditions. The Contractor agrees and
acknowledges that any failure on his part to adhere to the high voltage act shall
not only be a violation of law but shall also be a breach of contract and specific
violation of the provisions of the General Conditions which pertains to safety
precautions.
3. Occupational Safety & Health Act:
The Contractor by signing the contract acknowledges that he is fully aware of the
provisions of the Williams-Steiger Occupational Safety and Health Act of 1970 and he
shall comply therewith.
-026. EOmV ALENT MATERIALS:
Notwithstanding any provision of the general conditions, there shall be no substitution
of materials that are not determined to be equivalent to those indicated or required in the contract
documents ,without an amendment to the contract.
SC-l1
SC-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-027. AFTER HOURS INSPECTION:
If the Contractor opts to work before or after normal working hours, 8 a.m. to 5 p.m.,
Monday through Friday, or on Augusta, Georgia Legal Holidays, then the Contractor must pay for the
cost of inspection by the City of Augusta, Georgia and follow all necessary procedures listed in
"Section 15, Right-of-way Encroachment Guidelines, Part E, Outside of Normal Working Hours," of
the Augusta-Richmond County Planning Commission Development Documents dated September,
1999. If inspectors of Augusta-Richmond County are needed to work outside normal business hours,
Augusta-Richmond County needs to be notified in advance.
-028. MASTERS GOLF TOURNAMENT:
Any work planned to be accomplished during or directly before the Masters Golf
Tournament must be submitted to and approved in writing by the Owner. Consideration will be given
only for contract time extensions as a result of delays in accomplishing the work. No consideration
will be given for claims for damages.
-029. BUSH FIELD ACCESS:
The Contractor must coordinate all work on the airport property with the airport
administration (706-798-3236). The Contractor will be expected to comply with any security
requirements set forth by the administration, which may include contracting a certified security
professional. Any and all costs incurred during this coordination and compliance shall be included in
the Lump Sum Construction Pay Item.
-030. COORDINA TION WITH PUMP STATION CONTRACTOR:
The Contractor must coordinate the gravity sewer tie at S.R.56 and Spirit Creek with
the pump station contractor. The flow from the existing 36" sanitary sewer shall not be diverted to the
new gravity sanitary sewer until the pump station has reached substantial completion and is ready to
receive sewage. Any and all costs incurred during this coordination shall be included in the Lump
Sum Construction Pay Item.
-031. RAILROAD RIGHT -OF - WAY COORDINATION:
The Contractor must coordinate work within Railroad Right-of-Way with Railroad
Administration. The Contractor will be expected to comply with any requirements set forth by the
administration, which may include contracting a certified flagman. Any and all costs incurred during
this coordination and compliance shall be included in the Lump Sum Construction Pay Item.
SECTION TS
INDEX TO TECHNICAL SPECIFICATIONS
SECTION TITLE NO. OF PAGES
TS-l Clearing and Grubbing 1
TS-2 Excavation Support Systems 2
TS-3 Excavation and Backfilling 4
TS-3 APPENDIX A - GEOTECHNICAL REPORT 56
TS-4 Dewatering 4
TS-5 Temporary Bypass Pumping Systems 5
TS-6 Sanitary Sewer System 17
TS-7 Graded Aggregate Base Course 1
TS-8 Bituminous Paving 2
TS-9 Curbs and Gutters, Concrete 4
TS-lO Concrete Construction 2
TS-ll Grassing (Bermuda) 3
TS-12 Erosion, Sedimentation & Pollution Control Measures 6
TS-13 Plowable Fill 2
TS-14 Water Distribution System 18
TS-15 Graded Aggregate Surface Course 1
TS-16 Storm Sewer System 4
TS-17 Measurement and Payment 5
TS-O
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-l
CLEARING AND GRUBBING
-01.
SCOPE:
Clearing and grubbing shall consist of the removal and disposal of all trees, brush, stumps,
logs, grass, weeds, roots, decayed vegetable matter, posts, fences, stubs, rubbish and all other objectionable
matter resting on or protruding through the original ground surface and occurring within the construction
limits or rights-of-way of any excavation, borrow area, or embankment.
-02.
CONSTRUCTION METHODS:
1. CLEARING: Clearing shall consist of the felling and cutting up, or the trimming of trees, and the
satisfactory disposal of the trees and other vegetation together with the down timber, snags, brush
and rubbish occurring within the areas to be cleared. Trees and other vegetation, except such
individual trees, groups of trees, and vegetation, as may be indicated on the drawings to be left
standing, and all stumps, roots and brush in the areas to be cleared shall be cut off one foot above
the original ground surface. Individual trees and groups of trees designated to be left standing
within cleared areas shall be trimmed of all branches to such heights and in such manner as may
be necessary to prevent interference with the construction operations. All limbs and branches
required to be trimmed shall be neatly cut close to the whole of the tree or to main branches, and
the cuts thus made shall be painted with an approved tree wound paint. Individual trees, groups
of trees, and other vegetation, to be left standing, shall be thoroughly protected by barriers or by
such other means as the circumstances require. Clearing operations shall be conducted so as to
prevent damage by falling trees to trees left standing, to existing structures and installations, and
to those under construction, and so as to provide for the safety of employees and others.
2. GRUBBING: Grubbing shall consist of the removal and disposal of all stumps, roots and matted
roots from the site as indicated pn the drawings. In foundation areas, stumps, roots, logs or other
timber, matted roots, and other debris not suitable for foundation purposes shall be excavated to
a depth of not less than 18 inches below any sub grade, shoulder or slope. All depressions
excavated below the original ground surface for or by the removal of stumps and roots, shall be
refilled with suitable material and compacted to make the surface conform to the surrounding
ground surface.
-03.
DISPOSAL OF CLEARED AND GRUBBED MATERIAL:
Saw logs, pulp wood, cord wood or other merchantable timber removed incidental to
clearing and grubbing shall become the property of the Contractor and may be sold by him, provided such
disposal is otherwise in accordance with these specifications. All incombustible matter removed shall be
hauled away and deposited at locations approved by the Owner. Combustible matter may be burned or
may be disposed of as stated above. Burning shall be done at such time and such manner as to prevent fire
from spreading and to prevent any damage to adjacent cover and shall further be subject to all
requirements of Local, State and Federal Governments pertaining to the burning. No burning will be
allowed on the site unless Contractor obtains all necessary permits and all fires are kept under constant
attendance by persons having equipment necessary to prevent the spreading of fire. Such equipment shall
include, at the minimum, a bulldozer or front end loader, and an approved pump and hose connected to
an acceptable source of water. Disposal by burning shall be kept under constant attendance until all fires
have burned out or have been extinguished.
END OF SECTION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
SECTION TS-2
EXCAVATION SUPPORT SYSTEMS
-01. GENERAL
A. Submittals:
1. Layout drawings for excavation. support system and other data prepared by, or under the
supervision of, a qualified professional engineer. System design and calculations must
be acceptable to local or federal authorities having jurisdiction.
B. Quality Assurance:
1. Engineer Qualifications: A professional engineer must be legally authorized to practice
in jurisdiction where Project is located, and experienced in providing successful
engineering services for excavation support systems similar in extent to those required for
this Project.
2. Supervision: Engage and assign supervision of excavation support system to a qualified
professional engineer foundation consultant.
3. Regulations: Comply with codes and ordinances of governing authorities having
jurisdiction and to the requirements of OSHA Health and Safety Standards for
Excavations, 29 CFR Part 1926, or successor regulations.
C. Job Conditions:
1. Before starting work, verify governing dimensions and elevations. Verify condition of
adjoining properties. Take photographs to record any existing settlement or cracking of
structures, pavements, and other improvements. Prepare a list of such damages,'verified
. by dated photographs, and signed by Contractor and others conducting investigation.
D. Existing Utilities:
1. Protect existing active sewer, water, gas, electricity and other utility services and
structures.
2. Notify municipal agencies and service utility companies having jurisdiction. Comply with
requirements of governing authorities and agencies for protection, relocation, removal,
and discontinuing of services.
TS-2-1
TS-2-2
-02. PRODUCTS
A. Materials:
1. General: Provide adequate shoring and bracing materials which will support loads
imposed. Materials need not be new, but should be in serviceable condition.
2. Structural Steel: ASTM A 36.
3. Steel Sheet Piles: ASTM A 328.
4. Timber Lagging: Any species, rough-out, mixed hardwood, nominal 3 inches thick,
minimum.
-03. EXECUTION
A. Shoring:
1. Wherever shoring is required, locate the system to clear permanent construction and to
permit access for performing the work. Provide shoring system adequately anchored and
braced to resist earth and hydrostatic pressures.
2. Shoring systems retaining earth on which the support or stability of existing structures is
dependent must be left in place at completion of work.
B. Bracing:
1. Locate bracing to clear columns, floor framing construction, and other permanent work.
If necessary to move a brace, install new bracing prior to removal of original brace.
2. Do not place bracing where it will be cast into or included in permanent concrete work,
except as otherwise acceptable to Architect.
3. Install internal bracing, if required, to prevent spreading or distortion of braced frames.
4. Maintain bracing until structural elements are supported by other bracing or until
permanent construction is able to withstand lateral earth and hydrostatic pressures.
5. Remove sheeting, shoring, and bracing in stages to avoid disturbance to underlying soils
and damage to structures, pavements, facilities, and utilities.
6. Repair or replace, as acceptable to Architect, adjacent work damaged or displaced
through installation or removal of shoring and bracing work.
END OF SECTION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
SECTION TS-3
EXCA VA TION AND BACKFILLING
-01.
SCOPE:
This section covers all excavation, trenching and backfilling for pipe lines and structures,
complete.
-02.
EXISTING IMPROVEMENTS:
The Contractor shall maintain in operating condition and protect from damage all
existing improvements including utilities, roads, streets, sidewalks, drives, power and telephone
lines, gas lines, water lines, sewers, gutters and other drains encountered, and repair to the
satisfaction of the Engineer any aerial, surface or subsurface improvements damaged during the
course of the work. Where and if shown on the plans, the locations and existence or nonexistence
of underground utilities are not guaranteed. The Contractor shall contact the various utility
companies to determine and/or verify such information prior to proceeding with the work. He shall
make reasonable and satisfactory provisions for the maintenance of traffic on streets, drives,
walkways and at street crossings and if necessary to provide temporary walkways and bridges for
crossing of the open trench as directed. Work shall not commence within Augusta right -of-way until
a Right-of-Way Encroachment Permit is obtained from the Public Works Department.
-03.
EXCAVATION:
All excavation of every description and of whatever substances encountered shall be
performed to the depths indicated on the drawings or as specified herein. Excavation shall be made
by the open cut method except as otherwise specified or shown on the drawings. Excavation
methods shall generally meet or exceed Occupational Safety and Health Administration (OSHA)
construction industry standards.
All excavated materials not required for fill or backfill shall be removed and wasted
as directed. The banks of shallow trenches shall be kept as nearly vertical as practicable and where
required shall be properly sheeted and braced. Except where otherwise indicated, trench bottoms
shall be not less than 12 inches wider nor more than 16 inches wider than the outside diameter of the
pipe to be laid therein, and shall be excavated true to line, so that a clear space of not less than 6
inches in width is provided on each side of the pipe. The bottom of trenches shall be accurately
graded to provide uniform bearing and support for each section of the pipe on undisturbed soil at
every point along its entire length, except for portions of the pipe sections where it is necessary to
excavate for bell holes and for the proper sealing of pipe joints. Bell holes shall be dug after the
TS- 3-1
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
trench bottom has been graded. Bell holes shall be excavated only to an extent sufficient to permit
accurate work in the making of the joints and to insure that the pipe, for a maximum of its length will
rest upon the prepared bottom of the trench. Depressions for joints other than mechanical shall be
made in accordance with the recommendations of the joint manufacturers for the particular joint
used. Excavation for structures and other accessories shall be sufficient to leave at least 12 inches
in the clear between their outer surfaces and the embankment or timber which may be used to hold
the bank and protect them. Where damage is liable to result from withdrawing sheeting, the sheeting
will be ordered to be left in place. Except at locations where excavation of rock from the bottoms
of trenches is required, care shall be taken not to excavate below the depths indicated. Where rock
excavation is required, the rock shall be excavated to a minimum overdepth of 4 inches below the
normal required trench depth. The overdepth rock excavation and all excess trench excavation shall
be backfilled with loose, moist earth, thoroughly tamped. Rock is defined as materials which are so
hard or cemented that the excavation of such material requires blasting. The excavation shall
proceed in a conventional manner with satisfactory effort made to remove hard materials before the
Engineer makes a determination of need for blasting. Pre drilling and blasting will be allowed, if the
Contractor can provide evidence for the Engineer's review that boring logs can and will show that
the material can or cannot be excavated. Evidence will be provided for the Engineer's review and
approval before predrilling and blasting is undertaken. The excavation and removal of isolated
boulders or rock fragments larger than one cubic yard in volume encountered in materials of
common excavation shall be classified as rock excavation. Whenever wet or otherwise unstable soil
that is incapable of properly supporting the pipe, as determined by the Engineer or indicated on the
drawings, is encountered in the trench bottom, such soil shall be removed to a depth required for the
lengths designated by the Engineer, and the trench backfilled to trench bottom grade, as herein
specified, with coarse sand, fine gravel, or other suitable material. Backfill with earth under
structures will not be permitted and any unauthorized excess excavation below the levels indicated
for the foundation of such structures shall be filled with sand, gravel, or concrete, as directed.
A. Grading and Stacking: All grading in the vicinity of trench excavation shall be
controlled to prevent surface ground water from flowing into the trenches. Any water
accumulated in the trenches shall be removed by pumping or by other approved
methods. During excavation, material suitable for backfilling shall be stored in an
orderly manner a minimum distance of one and one-half times the depth of the
excavation back from the edges of trenches to avoid overloading and prevent slides
or cave-ins. Material unsuitable for backfilling, as determined by the Engineer, shall
be removed from the job site and disposed of by the Contractor in a manner as
approved by the Engineer.
B. Shoring and Sheeting: All shoring, sheeting, and bracing required to perform and
protect the excavation and to safeguard employees and the public shall be performed.
The failure of the Engineer to direct the placing of such protection shall not relieve
the Contractor of his responsibility for damage resulting from its omission.
TS-3-2
Trenches and other excavations shall not be backfilled until all required tests are
performed and the work has been approved by the Engineer. The trenches shall be carefully
backfilled with the excavated materials approved for backfilling consisting of earth, loam, sandy
clay, sand and gravel, soft shale, or other approved materials. No material shall be used for
backfilling that contains mulch, other unstable materials, stones, blasted rock, broken concrete or
pavement, or other hard materials having any dimension greater than 4 inches; or large clods of earth,
debris, frozen earth or earth with an exceptionally high void content. Backfilling within Augusta
right-of-way shall conform to Georgia Department of Transportation and City of Augusta
specifications.
For backfill up to a level 1 foot over the top of pressure pipelines and 2 feet above
the top of gravity pipelines, only selected materials shall be used. Select materials shall be finely
divided material free from debris, organic material and stone, and may be suitable job excavated
material or shall be provided by the Contractor from other sources. The backfill shall be placed in
I
I
I
I
I
f
I
I
I
I
I
I
I
I
I
I
I
I
I
C.
D.
E.
-04.
April, 2001
Whenever sheeting is driven to a depth below the elevation of the top of the pipe, that
portion of the sheeting below the elevation of the top of the pipe shall not be
disturbed or removed. Sheeting left in plac~ shall be cut off not less than 1 foot
below finished grade. No sheeting shall be removed until the excavation is
substantially backfilled as hereinafter specified.
Water Removal: Where water is encountered, it shall be prevented from
accumulating in excavated areas by pumping, well-pointing and pumping, or by other
means approved by the Engineer as to capacity and effectiveness. Water removed
from excavations shall be discharged at points where it will not cause injury to public
or private property, or the work completed or in progress. All efforts to prevent
sedimentation shall be made. Under no circumstances shall trench bottoms be
prepared, pipes laid, or appurtenances installed in water. Water shall not be allowed
to rise in unbackfilled excavations after pipe or structures have been placed.
Blasting: Explosives are to used only within legal limitations. Before explosives are
used, all necessary permits for this work shall be secured and all precautions taken
in the blasting operations to prevent damage to private or public property or to
persons. The Contractor shall assume full liability for any damage that may occur
during the use of explosives. No blast shall be set off within 50 feet of pipe already
laid in the trench.
Tree Protection: Care shall be exercised to protect the roots of trees to be left
standing. Within the branch spread of the tree, trench shall be opened only when the
work can be installed immediately. Injured roots shall be pruned cleanly and backfill
placed as soon as possible.
BACKFILLING:
TS-3-3
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
uniform layers not exceeding 8 inches in depth. Each layer shall be moistened and carefully and
uniformly tamped with mechanical tampers or other suitable tools. Each layer shall be placed and
tamped under the pipe haunches with care and thoroughness so as to eliminate the possibility of
voids or lateral displacement.
The remainder of the backfill material shall then be placed and compacted above the
level specified above. In areas not subject to traffic, the backfill shall be placed in 12 inch layers and
each layer moistened and compacted to a density approximating that of the surrounding earth. Under
roadways, driveways, paved areas, parking lots, along roadway shoulders and other areas subject to
traffic, the backfill shall be placed in 8 inch layers and each layer moistened and compacted to
density at least equal to that ofthe surrounding earth so that traffic can be resumed immediately after
backfilling is completed. Any trenches which are improperly backfilled, or where settlement occurs,
shall be reopened to the depth required for proper compaction, then refilled and compacted with the
surface restored to the required grade compaction. Along all portions of the trenches not located
in roadways, the ground shall be graded to a reasonable uniformity and the mounding over the
trenches left in a neat condition satisfactory to the Engineer.
Sheeting not specified to be left in place shall be removed as the backfilling
progresses. Sheeting shall be removed in such a manner as to avoid caving of the trench. Voids left
by the removal of sheeting and shoring shall be carefully filled and compacted. Where, in the
opinion of the Engineer, damage is liable to result from withdrawing sheeting, the sheeting will be
ordered to be left in place.
-05. BORING AND .TACKING:
Where required by the drawings, the pipeline will be installed in a steel casing, placed
by boring and jacking. Where boring is required under highways, the materials and workmanship
will be in accordance with the standards of the Georgia Department of Transportation or local
authority. Boring and jacking under railroads will be governed by the latest A.R.E.A. standards and
those of the railroad involved. The steel casing shall be in accordance with ASTM A252 to the
thicknesses shown on the drawings.
-06. PAVEMENT REMOVAL AND REPLACEMENT:
Where necessary existing pavements shall be removed and replaced, the applicable
specifications of the Georgia Department of Transportation or local authority shall govern this work.
Joints shall be sawed, unless joints equally uniform in the opinion of the Engineer result from other
means. Refer to Augusta-Richmond County Right -of-Way Encroachment Guidelines for pavement
removal and replacement.
END OF SECTION
TS-3-4
prepared by
TS-3 APPENDIX "A"
Report of Geotechnical Exploration
Spirit Creek Force Main Project
Richmond County, Georgia
prepared for the
Augusta-Richmond County
GRAVES ENGINEERING SERVICES, INC.
Project No. G-05l23l
1220 West Wheeler Parkway, Suite F
Augusta, Georgia 30909
706-651-9922
Fax 706-651-0810
1\
I
11
J
11
.J
~
~.
~
tl
o
Il
d
I]
.J
IJ
o
o
b
b
b
b
b
U
GRAVES
ENGINEERING SERVICES, INC.
1220 W. Wheeler Parkway
Suite F
Augusta, GA 30909
(706) 651-9922
February 15,2005
Augusta-Richmond County
C/o Cranston, Robertson & Whitehurst, P.c.
452 Ellis Street
P.O. Drawer 2546
Augusta, Georgia 30903
ATTENTION:
Mr. Scott Williams/Mr.Dennis Welch
SUBJECT:
Report of Geotechnical Exploration
Spirit Creek Force Main Project
Richmond County, Georgia
Graves Engineering Project No. G-051231
Gentlemen:
Graves Engineering Services, Inc. is pleased to submit this report of our exploration services for the
proposed project. Our services were provided in accordance with our proposal no. P-04999 which was
authorized by Augusta-Richmond County purchase order on January 6, 2005. This report presents a
review of the information provided to us, a discussion of the site and subsurface conditions, and our
earthwork recommendations. The appendix contains the results of our field and laboratory testing.
Project Information
The project consists of the Spirit Creek Force Main sanitary sewer project in Richmond County, Georgia.
The project consists of a force main sewer line that starts from a proposed pump station off of Bennock
Mill Road and extends approximately 43,000 linear feet to the north-northwest to the treatment plant
located on Highway 56 Loop. We understand that a section of gravity sewer will also extend from the
pump station to near the intersection with Highway 56. The route is shown on preliminary plan drawings
prepared by and provided to us by Cranston, Robertson & Whitehurst, P.C.. The route had been
surveyed by Cranston, Robertson & Whitehurst, P.c. and the centerline of the easements were staked in
the field.
The route crosses several roads, entrance drives and a Seaboard Coastline Railroad. The route also
crosses Butler, Little Spirit and Spirit Creeks. The major road crossings will be bored and jacked such
that the pavement sections will remain intact. The force main is generally to be constructed within 8 to 15
feet of existing grades. The proposed pump station is planned to extend to a depth of approximately 40
to 50 feet. The pump station is anticipated to be supported by a mat foundation. -
Purpose Of Exploration
The purpose of this exploration was to obtain specific subsurface data at the site and to provide earthwork
recommendations for the proposed project.
I
I
,
I
i
I
,
I
I
I
i
I
I
l
,
.J
Ii
I
)
I:
II
"J
II
J
11
..1
Ii
J
I,
J
II
.J
II
-,
II
II
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.C.
February 15,2005
-Page 2-
Site Conditions
We conducted a site reconnaissance to observe and document surface conditions at the site. Information
gathered was used to help us interpret the subsurface data and to detect conditions which could affect our
recommendations. .
The main easement initially runs adjacent or parallel to Spirit Creek or to Little Spirit Creek. The route
has rolling topography with approximately 50 to 60 feet of topographic relief. Based on ~e information
contained on the preliminary Plan and Profile drawings, the existing ground surface elevatIons along the
route range from approximately 120 to 180 feet MSL. The route extends through several wetland areas.
Surface water was noted at numerous locations along the route and generally correspond to the locations
of creeks and associated wetland areas.
Most of the site is located just off roadways(Highway 56, 56 Loop and International Boulevard) or
railroad easements and these areas are generally cleared of vegetation and were covered with gravel,
grassed or had surface soils exposed. Surface soils exposed consist of a sandy organic topsoil or sands
of the coastal plain.
Intermittent portions of the route extend through areas that are moderately to heavily wooded with
hardwoods and pine. Some clearing was performed and an adverse terrain vehicle was utilized to provide
access to boring locations. Surface soils exposed consist of a sandy, loamy organic topsoil in wooded
areas.
Site Geologic Conditions
The site is located near the fall line which is the contact area of the Upper Coastal Plain Province and the
Piedmont Province. The Coastal Plain soils were deposited during inundation by the ancient oceans and
consist of random layers of fine sands and silts interbedded with lenses of clay. The Georgia Piedmont
Province is a broad plateau gently sloping from the Blue Ridge Mountains to the Coastal Plain, covering a
distance of approximately one hundred miles in this area. The soil overburden of this area is residuum
formed by in-place weathering of the parents rocks. A typical upland soil profile consists of thin topsoil
underlain by a few feet of clayey soils that transition with increasing depth into less clayey, coarser
grained silts and sands with varying mica content. Separating the completely weathered soil overburden
from the unaltered parent rock is a transition zone of residuum with penetration resistances of more than
100 blows per foot (bpf) which is locally described as partially weathered rock(PWR). Partially
weathered rock retains much of the appearance and fabric of the parent rock formations, and may consist
of thinly interlayered very hard or dense soil and rock.
Th~ weatheri~g proc~sses that f?rmed the overburden soils and partially weathered rock were extremely
vana?~e. DIfferentIal weathenng of the rock mass has resulted in erratically varying subsurface
con~ItlOn.s, evidenced by abrupt changes in soil type and consistency in relatively short horizontal and
vertI~al dIstances. Although no rock outcrops were noted at the surface, depths to rock can be irregular,
and Isolated boulders, discontinuous rock layers, or rock pinnacles can be present within the overburden
transition zones.
~ased on published literature, the site is underlain by Coastal Plain sediments consisting of interbedded
SlIts, sands, and clays. Th~se soils overlay residual soils and crystalline rocks of the Piedmont.
I
I
I
I
I
1
1
!
I
i
I
I
J
l
I
)
~
J
Ii
I
.1
II
J
11
I
.I
I.
J
II
J
II
I
u)
II
J
Ii
I
"",-,J
Ii
I
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.c.
February 15,2005
-Page 3-
Subsurface Conditions
The subsurface conditions were explored with widely spaced soil test borings drilled according to the
procedures presented in the appendix. The boring locations and depths were selected by Cranston,
Robertson & Whitehurst, P.C.. and Graves Engineering. The boring locations are indicated by station
number on the attached boring records. The actual field boring locations were determined by our field
crew from staked locations on the route. Boring elevations were obtained by interpolation between
contours on the drawing provided to us. The boring elevations shown in the appendix should be
considered accurate only to the degree implied by the method used.
The subsurface conditions encountered at the boring locations are shown on the Test Boring Records in
the Appendix. These Boring Records represent our interpretation of the subsurface conditions based on
the field logs, visual examination of field samples by an engineer and tests of the field samples. The lines
designating the interface between various strata on the Boring Records represent the approximate
interface location. In addition, the transition between strata may be gradual. Water levels shown on the
Boring Records represent the conditions only at the time of our exploration.
A total of 46 soil test borings were drilled along the route to depths ranging from 10 to 60 feet below the
ground surface. The soil test borings revealed a subsurface profile generally consisting of typical coastal
plain deposits of interbedded sands, silts and clays. These soils were encountered to the boring
termination depths. The surficial layer consisted of loamy and sandy, organic topsoils. The surficial layer
was generally encountered to a depths ranging from 3 to 12 inches below the ground surface.
The coastal plain soils typically consisted of sands with varying fine grained particle content(SP to SC)
interbedded with fine grained clayey silts. The sandy soils were generally loose to dense in consistency
with standard penetration resistance's ranged from 5 to 41 blows per foot with an average of
approximately 18. The coastal plain clayey silts were recorded to be generally soft to very hard in
consistency with standard penetration resistance's of 2 to 91 blows per foot recorded. Borings B-I, B-2,
B-3, B-7 B-45 encountered lenses of a soft, fine sandy, clayey siltCmuck" with layers of fiberous
organics(peat)) at depths ranging from 12 to 27 feet. Standard penetration resistance's ranged from 2 to 9
blows per foot. This material was generally encountered very near the adjacent wetland areas.
Groundwater Conditions
Groundwater was encountered in many of the borings at depths ranging from 2.5 to over 20.0 feet at over
24-hours after drilling. In silty sands the water levels can usually be determined accurately near the time
of drilling. In fine grained soils and clayey sands, it may take several days for water levels to stabilize. In
addition, fluctuations in the groundwater level can occur due to variations in rainfall, evaporation,
construction activity, surface runoff, and other site specific factors. The highest groundwater levels are
generally encountered in early spring and the lowest in late summer.
The likelihood of groundwater in the near surface soils at some locations can be expected to increase
follo:-ving periods wet weather. This is due to rain water infiltration through the upper sands at those
locatIOns. The water can then become "perched" on top of the clayey sands and silts below.
I
I
I
I
I
I
I
I
I
I
I
I
J
I
i
I
j
I
I
)
!
~
J
Ii
J
II
J
Ii
,J
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.C.
February 15,2005
- Page 4-
Utility Construction Considerations
The construction of the pump station will require excavations on the order of 40 to 50 feet. Based on our
review of the project drawings, the force main piping is generally to be constructed within 8 to 15 feet of
existing grades. We have not reviewed the project drawings for the gravity flow, sanitary sewer piping.
However, we understand that it will be installed to depths up to 20 feet. In addition, at the road and
railroad crossings, we understand that the bore and jack pits will be excavated to depths of 10 to IS feet.
The soils encountered along the route should be amiable to excavation with normal excavation equipment
and should not interfere with boring and jacking operations. The deeper cuts are to be extended below the
groundwater level, especially near the pump station and the wetlands in the initial sections of the route.
Some of these areas are underlain by layers of relatively clean fine to coarse sands. This will likely
require wellpoint dewatering as the excavation proceeds(please see the construction water control section
of this report).
We recommend that the excavations be shored, sloped or benched as required to provide stability and a
safe work environment. For the soils encountered, we recommend that cut slopes of 2H: I V be utilized.
This may require a wider temporary easement at some locations. All excavations should comply with
applicable local, state and federal safety regulations including the current OSHA Excavation and Trench
Safety Standards. It is our understanding that these regulations are strictly enforced and if they are not
closely followed, the owner and contractor could be liable for substantial penalties.
Heavy construction equipment and materials removed from the excavations should not be placed within 5
to 10 feet of the top of the excavation. We understand that the bore and jack pits may be shored with the
use of driven sheetpiling. Please see the wall and retaining structure section of this report for a more
detailed discussion.
Since preliminary plans call for the pipe at several locations to be installed below the groundwater table,
we recommend that 12 to 18 inches of clean stone be utilized for pipe bedding in wet areas. Compaction
of pipe backfill at several locations may be extremely difficult due to the anticipated wet conditions. In
addition, wet clayey soils removed from the excavations will require significant drying time prior to
reutilization as fill. Therefore, construction planning should assume that significant volumes of select
stone bedding and imported initial pipe backfill will be required.
Foundation Recommendations
We anticipate that a mat foundation will be utilized to support the pump station structure. As stated
previously, the foundation is anticipated to vary in depth from 40 feet to 50 feet below existing grades.
Therefore, the slab will likely bear in either the firm to very firm sands(SW-SM). Mat foundations
bearing. in this material can be designed for maximum allowable net bearing pressures of up to 3000 psf,
The ~Oll parameter used in the analysis and design of mat foundations is the modulus of sub grade
reactlOn(Ks). Based on the data obtained in our exploration, we recommend a design modulus of
subgrade reaction of 300 kips per cubic foot.
The ma~imum net allowable bearing pressures recommended are based on our previous experience and
correlat,lOn1s made previously between standard penetration test resistance's and the performance of
foundatlOns supported by soils similar to those at this site. We expect total settlements on the order of 1
inch and differential settlements of up to 1/2 inch.
I
,
I
I
I
i
~
I
,
I
,
I
J
I:
i
II
i
11
)
IJ
!1
II
J
II
.J
II
_J
II
.-'
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.C.
February 15,2005
-Page 5-
If possible, foundation concrete should be placed the same day that excavations are dug. If the bearing
soils are softened by surface water intrusion or exposure, the softened soils must be reI?oved from tt:e
foundation excavation bottom immediately prior to placement of concrete. If the excavatIOn must remam
open overnight or if rainfall becomes imminent while the bearing soils are exposed, we recommend that a
2 to 4-inch thick "mud-mat" of "lean" (2000 psi) concrete be placed on the bearing soils before the
placement of reinforcing steel.
We recommend that the minimum widths for individual column and continuous wall footings be 24 and
16 inches, respectively. The minimum widths are recommended to provide a margin of safety against a
local or punching shear failure of the foundation soils. Exterior footings should bear at least 18 inches
below final exterior grade. The depths of interior footings should be a minimum of 12 inches below the
top of the floor slab. This embedment is necessary to provide adequate confinement of the bearing soils
and to achieve the recommended bearing pressure.
We recommend that the geotechnical engineer observe the mat area excavations immediately prior to
placing concrete. He should compare the soils exposed with those encountered in the soil test borings
and document the results. Any significant differences should be brought to the attention of the owners!
representative along with appropriate recommendations. The foundation bearing area should be level or
suitably benched. It should also be free of loose soil, ponded water and debris prior to the inspection.
Compacted Fill Recommendations
We recommend that soils to be used as trench backfills be free of debris and have less than 2% by weight
fibrous organic material. They should have a liquid limit less than 50 and a plasticity index less than 20.
Before filling operations begin, representative samples of each proposed fill material should be collected.
The samples should be tested to determine the maximum dry density, optimum moisture content, natural
moisture content, gradation and plasticity of the soil. These tests are needed for quality control during
compaction and also to determine if the fill material is acceptable.
We have conducted laboratory testing and visually inspected soil samples obtained from the site. We
expect that most of the sands and silts encountered in the borings are acceptable for use as compacted
backfill. The organic soils encountered predominately near the wetland areas are not be acceptable for
use as compacted fill due to organic and moisture content. In addition, as stated previously, wet
soils(especially clayey soils) removed from the excavations may require significant drying time prior to
reutilization as fill.
II
",,)
We recommend that all compacted fill be constructed by spreading acceptable soil in loose layers not
more than 10 inches thick. The fill should be compacted in thin lifts to at least 95 percent of the Standard
Proctor maximum dry density (ASTM D-698). The upper 12 inches of fill beneath pavements should be
compacted to at least 100 percent of the Standard Proctor maximum dry density,
The moisture content of the fill soils should be maintained within +3 and -3 percentage points of the
optimum moisture content as determined from the Proctor compaction test. This provision may require
the contractor to dry the soils during periods of wet weather or wet the soils during the hot summer
months.
II
~J
I
I
,
I
!
,
I
I
I
J
l,
i
j
l
,
I
I
11
!
11
!
II
J
1\
I
J
II
J
II
I
~j
II
~J
II
.'.<1
I,
i
~~j
Ii
!
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.c.
February 15,2005
- Page 6-
We recommend that the backfill placement and compaction be observed and documented by the
geotechnical engineer. Significant deviations, either from specifications or good practice, should be
brought to the attention of the owner's representative, along with appropriate recommendations. At least
one field density test should be performed for every 100 to 200 linear feet of trench for each lift.
Retaining Structures
We understand that sheetpiling may be utilized as shoring for the excavations for the bore and jack pits.
The sheetpiling will act as a below grade walls when the pits are excavated. These sheetpi1e walls must be
designed to resist soil pressures imposed on them. Walls which are permitted to rotate at the top, such as
sheetpiling walls, should be designed to resist "active" lateral earth pressure. Typically, a top rotation of
about 1 inch per 10 feet height of wall is sufficient to develop active pressure conditions in soils similar to
those encountered at the site. The pump station walls should be designed to resist "at rest" lateral earth
pressure since the top of the walls will be braced from movement.
To account for the "at rest and active" lateral pressures of retained earth, we recommend that the
temporary retaining system design assume that the soils behind the bracing system will apply a triangular
stress distribution based on the excavation depth and the following strength parameters for the natural
soils at this site:
ANGLE of INTERNAL
MATERIAL UNIT WEIGHT(PCF) FRICTION(Degrees) COHESION(PSF)
Firm SW -SM 115 33 0
Very Loose SP-SM 95 27 0
Loose SP-SM lOa 29 0
Very Loose SM 95 25 0
Loose SM 100 27 0
Firm SM 110 29 0
Very Firm SM 115 30 0
Dense SM 120 32 0
Loose SC 105 28 150
Firm SC lIS 30 300
Very Firm SC 120 32 700
V.Soft Clayey ML 85 10 lOa
Soft Clayey ML 90 11 300
Firm Clayey ML 95 12 800
Stiff Clayey ML 100 13 1500
Very Stiff Clayey ML 105 15 3000
The compacted mass unit weight of the soil'should be used with the above soil parameters to calculate the
cOl!~sponding earth pressure coefficients and lateral earth pressures. The above values are actual
antICIpated values and do not contain any safety factors. If dewatering systems are not provided, then the
walls should be designed to resist the full hydrostatic head in addition to the lateral earth pressures in
areas below the water table.
.,,;
,
I
~
I
I
I
I
~
~
I
(i
!
}
Ii
I
i
Ii
J
11
I
j
1\
I
J
~
11
I
0.1
II
J
11
I
II
J
Ii
i
.,.J
II
_J
I!
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.c.
February 15,2005
-Page 7-
The lateral pressures developed by surcharge loads fro~ slopes, heavy construction equip~ent, stored
material, stockpiled soils, etc. near the top of the excavatlOn must be added to the lateral sOlI stresses to
determine the horizontal loads which must be resisted. In addition, transient loads imposed on the walls
by construction equipment during construction should be considered. .Excess~vely heavy equipm~nt (that
could impose temporary excessive pressures or long term exceSSIve reSIdual pressures agamst the
constructed walls) should not be allowed within about 5 feet (horizontally) of the walls.
Construction Water Control
We expect that groundwater control will be required for portions of the alignment due to the presence of
shallow groundwater. Since the excavations will extend several feet below the groundwater level, we
anticipate that a wellpoint dewatering system will be required at some locations. Wellpoints are small
diameter wells that are jetted or driven into the soil(at 3 to 10 foot spacings depending upon soil type) and
are placed in straight lines along the area to be drained. They are connected at the top to a horizontal
suction pipe called a header and then connected to pump specifically designed for dewatering work. The
wellpoints may require staging at various levels as the excavation proceeds to provide the required
drawdown of the water table. We recommend that the design of the dewatering system be performed by
a specialty contractor that is experienced with similar conditions. We also recommend that pumping
continue until the trench is completely backfilled such that backfilling can be completed in as dry a
condition possible.
Basis For Recommendations
The recommendations provided are based in part on project information provided to us and they only
apply to the specific project and site discussed in this report. If the project information section in this
report contains incorrect information or if additional information is available, you should convey the
correct or additional information to us and retain us to review our recommendations. We can then modify
our recommendations if they are inappropriate for the proposed project.
Regardless of the thoroughness of a geotechnical exploration, there is always a possibility that conditions
between borings will be different from those at specific boring locations and that conditions will not be as
anticipated by the designers or contractors. In addition, the construction process ,may itself alter soil
conditions. Therefore, experienced geotechnical personnel should observe and document the construction
procedures used and the conditions encountered. Unanticipated conditions and inadequate procedures
should be reported to the design team along with timely recommendations to solve the problems created.
We recommend that the owner retain Graves Engineering to provide this service based upon our
familiarity with the project, the subsurface conditions and the intent of the recommendations.
We recommend that this complete report be provided to the various design team members, the contractors
and the project owner. Potential contractors should be informed of this report in the "instructions to
bidders 11 section of the bid documents.
We wish to remind you that our exploration services include storing the samples collected and making
them available for inspection for 60 days. The samples are then discarded unless you request otherwise.
I
l
I
,
,
,
!
~
J
I
!
~
J
II
I
.J
Ii
I
)
~
Ii
I
.j
I,
~j
I]
II
J
~
Ij
11
J
I:
!
~'^!
Augusta-Richmond County
c/o Cranston, Robertson & Whitehurst, P.C.
February 15,2005
-Page 8-
We will be happy to discuss our recommendations with you and would welcome the opportunity to
provide the additional studies or services necessary to complete this project. We appreciate the
opportunity to provide our professional services and look forward to working with you on the remainder
of this project and on future projects. If you have any questions concerning this report or wish to have
further discussions, please contact us at (706) 651-9922.
Respectfully Submitted, .. "~::~.. '.. . .,. . '.
GRA V ENGINEERIN~.(.";S~ "",\ - .:}..fNC.........
.J ~_<-"'" t'>... ,.
..'J,:~. ~ .\'~
lr _. .,,",,' .i'.
Jj 7 ~.... .' '::;'::.~'. ;~ 1
'I ~::; " "I' .... m~\H
W~ n. "'..~. PROt'E css.'m..w.../...;<...."...!~
\~:'; '4:~.,' . ~~'! It-
Y. ..... It, '" ',e... II
ichard W. Swanson, p.E~K~~~ "'GJN~!...",;:7~>1
Principa~ Eng.ineer / Presideh~.:e ~? . ~~~dY
Ga. Registration No. 22223 -....;.:;::z:::::::::-;:,:::'.::;;>,
Attachments: Test Boring Records
Field and Laboratory Testing Procedures
BORING NO. B-1
SOIL TEST BORING RECORD
GRAVES
ENGINEERING SERVICES
Page 1 of 2
DATE COMPLETED: 12/27/04
PROJECT: Spirit Creek Force Main
LOCATION: Northwest Quadrant of Pump Station - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 132' 1 DRILLING METHOD: 2.25" J.D. AUGER
It
~~
C)
U.S.C.S. Soil Classification
J:
I-
a.
w
o
,
)
I
i
I
]
I
]
)
11
I
.i
II
I]
1\
!
.J
1\
I
.)
II
:J
II
J
II
,
...01
11
I
,J
:.::;:.:..;:.:..;:.:: 0-3" Topsoil
.:.:::.:.:::-:.~:.:.:: Firm, Brown-Tan, Silty Fine to Medium
:::::~:::::}::}:: Sand(SM)
.... -------
.:.:::::::.:::::::.:::::::.::: Very Firm, Gray-Tan, Clayey, Silty Fine to
_ '::.:<".:<:.:':::. Medium Sand(SC)
05 .:::::::::::::::::::::::/:
Very Stiff to Hard, Gray-Tan-Brown, Fine
Sandy, Clayey Silt(ML)
10
:::::?::?::?:: Firm, Tan-Brown-Gray, Slightly Silty Fine to
:::~::::.:::::.:~:.:.: Coarse Sand(SW -SM) with thin clayey silt
1 5 _ {t:}:::r::: seams . .
:.:.:~:.:.:;:.:.:;:.:.: Note: 7.3% Passmg 200 SIeve on Sample #5.
:::::~:::::~::~~:::::
':. ':. ':.':
...........
':. ':. ':.':
...........
':. .... .....:
...........
':. ':. '.'.':
20 -'t!jl!
':":.':.','
...........
.:..:..:....
...........
':.':. .....:
25 - :::::?::?::?::
.....,.....
':..:. .......
::::: ~::::: ~ ::::: ~:::::
:.::~:.::;:.:..;:.::
" "
, , " Soft to Very Soft, Dark Grey, Fine to Medium
,... ~ ~ ~ ~ Sandy, Clayey Silt(ML)
30-""
, , , ,
, '" Note: 78.1 % Passing 200 Sieve on Sample #9.
~ ~ ~ ~ LL=43, PI=15 on Sample #9.
""
""
""
""
35-""
""
, " ,
.::::?::?~?:: Firm to Very Firm, Orange-Brown-Gray-Tan,
.::.:::.:.:::.:.:::.:~ Sl.ightly Silty Fine to Coarse Sand(SW -SM)
::~:\:t?~:\:~t wIth gravel
11
I
,
Ii
40
I~
'Ip'
i~
o
Standard Penetration Resistances
w
_ ::l
z~
>
10 20 30 40 50 60 70 60 90
55
55
55
55
55
55
55
..
/
,/
55
c:c:
.
1II
18
29
~
It
II
.J
V
34
27
18
14
19
04
02
17
I
I
I
~
t
I
i
I
j
,
~
J
~
.J
I
,
.,
I
,
,
..)
I
.J
i
j
I]
II
J
11
I
._J
II
_J
II
I
,J
BORING NO. B-lA
SOIL TEST BORING RECORD
Page 2 of 2
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Northwest Quadrant of Pump Station - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 132' I DRILLING METHOD: 2.25" J.D. AUGER
DATE COMPLETED: 12/27/04
(f.
J:
I-
a.
w
o
i~
Cl
60
65 -
70 -
75-
II
j
80
1m i~ w
Standard Penetration Resistances - =>
Z;;!
>
0 10 20 30 40 50 60 70 80 90
\
55 III 21
,
U.5.C.S. Soil Classification
55
55
55
Boring Terminated At 60.0 Feet.
Groundwater encountered at 18.5 feet at the
time of boring and at 17.0 feet at several days
after boring.
SS - Split Spoon Sample
LL - Liquid limit
PI - Plasticity Index
29
/
.I
13
:.::::.:.):~:.:: Firm to Very Firm, Orange-Brown-Gray-Tan,
.:.:::-:.:::.:.:::-:.:: Slightly Silty Fine to Coarse Sand(SW -SM)
:.::::.::::.::~:.:.. with gravel
':. ':. .:....
...........
45 - ~i~~i~
...........
.... ':.':.':
..........
.... .:......:
..........
':. .... ':. ,,'
..........
.... ':.':.','
...........
':. ':. .....,'
...........
.:..:......,'
50 - ::.;:.::::.:.<:..
':. .... .....:
..........
.... .... .:....
...........
.... .... ':.',
55 J~!~i~
':.',0.':.':
..........
':. .... .:..,.
..........
':.':.'''.':
..........
':. ':. ':.',
..........
.,'. ':. .:..o'
..........
.... .... ':'"
..........
.... ':. .:..,'
..........
':. .:. ':.':
..........
.... .....:..:
I.~
12
I
I
,
I
I
I
~
I
~
I
I
I
I
I
J
Ii
j
I
"J
Ii
I
.'
II
,
,.J
I,
.J
I;
I
.J
II
"J
11
..J
II
I
~J
BORING NO. B-2
SOIL TEST BORING RECORD
Page I of 1
GRA YES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main & Gravity Sewer
LOCATION: Station 69+70(at MH#lO) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
1 GROUND SURFACE ELEVATION: 120' 1 DRll..LING METHOD: 2.25" LD. AUGER
DATE COMPLETED: 12/30/04
(S
J:
f-
0..
W
Q
i~
(!l
U.S.C.S. Soil Classification
........... 03" T .1
.:.>:.>::::.::. - OpSOl
tifjti~ Finn, Gray, Silty Fine to Medium Sand(SM)
05 - i~iiiii
10 - " .
-------
Loose, Tan-Brown, Slightly Silty Fine to
Coarse Sand(SW -SM) with gravel
~ Firm, Black, Fine Sandy, Clayey Silt(ML)
~~::::~::: with layers of organics and peat
ls-I~~
~""",
X...'Io.....
, , ,
... .. .. ..
./:.:.:::-:.::;.:.:: Firm, Tan-Orange-Brown, Silty Fine to
~~~~rI~t~i~I Medium Sand(SM)
20
2S-
30-
3S-
II
I
40
Boring Terminated At 20.0 Feet.
Groundwater encountered at 3 feet the time of
boring and at 2.5 feet at several days after
boring.
SS - Split Spoon Sample
I~
.....
~~
o
55
55
S5
55
55
55
~t
.I
,
Standard Penetration Resistances
w
. :;)
Z'l!
>
10 20 30 40 50 60 70 80 90
r
17
.
13
12
os
.l.
,
09
~
16
BORING NO. B-3
SOIL TEST BORING RECORD
Page 1 of 1
GRA YES
BVGINEERING SERVICES
PROJECT: Spirit Creek Force Main & Gravity Sewer
LOCATION: Station 75+50(Between MH #7& 8) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 120' I DRILLING METHOD: 2.25" 1.D. AUGER
DATE COMPLETED: 12/30/04
it
J:
I-
a.
w
o
i~
<!l
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\ '\ '\ '\
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
05 - '\ '\ '\ '\
'\'\'\
55 ~
'\
55 h .
U.S.C.S. Soil Classification
I~
i~
0-3" Topsoil
Soft to Very Soft, Gray, Fine Sandy, Clayey
Silt(ML)
.....
55
:.:::~:.:::~:.::/~: Firm, Tan-Brown-Gray, Slightly Silty Fine to
lililil Coarse Sand(SW-SM) with gravel
10 - :::::::::::
.... .:. .....:
...........
.:..:........
...........
.....,'..:....
...........
'o'. .,'. .....:
...........
" ....,
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
15-,\ '\ '\ '\
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
'\'\'\'\
. . . .
. . . .
20
. . . .
. . . .
I
J
~
j
!
!
Ii
~
~
.J
Ii
I
.J
25-
30-
35-
40
..
I
J
55
55
Very Soft, Gray, Fine Sandy, Clayey Silt(ML)
i
Loose, Tan, Fine to Medium Sand(SP)
- -
Boring Terminated At 20.0 Feet.
Groundwater encountered at 3.5 feet the time
of boring and at 2.5 feet at several days after
boring.
55
SS - Split Spoon Sample
Standard Penetration Resistances
W
.::l
z;t
>
o
10 20 30 40 50 60 70 80 90
04
02
12
12
02
,
.
07
I
I
I
I
,
,
,
i
J
I
J
I
j
~
,
~
l
J
!
~
J
t
.J
t
I
.J
iii
j
Ii
..J
BORING NO. B-4
SOIL TEST BORING RECORD
Page 1 of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main & Gravity Sewer
LOCATION: Station 86+65(at MH #4) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
~
DATE COMPLETED: 01/11/05
GROUND SURFACE ELEVATION: 120' DRILLING METHOD: 2.25" I.D. AUGER
J:
l-
ll.
W
o
i~
C)
05
10
15
20
25
30
35
40
U.S.C.S. Soil Classification
I~
i~
Standard Penetration Resistances
w
-=>
z<i
>
'0 20 30 40 50 60 70 6090
SS
........... '11 .
.::::.::::.::>:: 0-6 TOpSOIl
:::.::::.::::.::::. Firm, Gray, Slightly Clayey, Silty Fine to
\i~:i.: Medium Sand(SM) wiili snme gravel
::~r::~:::/::.
...........
.'"" ,"
------
::::::::.:::::::.:::::::.:::: Very Firm to Firm, White-Tan-Gray, Clayey,
.:::":':::..:.:::..:>:' Silty Fine to Medium Sand(SC)
>!::}:~::~:::}~:: Note: 37.4% Passing 200 Sieve on Sample #4.
tl
55
55
5S
Stiff to Very Stiff, Gray-White, Fine Sandy,
Clayey Silt(ML)
....
55
Boring Terminated At 20.0 Feet.
Groundwater encountered at 14.5 feet the time
of boring. Hole dry and caved(with cans) at
3.5 feet at several days after boring.
55
SS - Split Spoon Sample
11
13
24
19
12
29
I
I
I
I
I
I
I
r
I
I
I
I
,
I
I
I
I
J
!
I
J
Ii
I,
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-5
PROJECT: Spirit Creek Force Main
LOCATION: Station 95+65(at East SR 56 Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 122' I DRllLING METHOD: 2.25" I.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/11/05
~
:I:
Ii:
w
o
i~
(!J
i~
1m
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 80 90
. . .
........... 0-3" Topsoil
: :: Loose, Gray-Tan, Silty Fine to Medium
>>>:. Sand(SM)
55
\
. . . .
. . . .
....
. . . .
. . . .
. . . .
. . . .
05 - . . .
55
. . . .
. . . .
-------
:.::;:.:.:;:.:.:;:.:.: Firm to Loose, Tan-Brown, Slightly Silty Fine
iiiiiii to Coarse Sand(SW-SM) with gravel
10 - :.:::.:::.:::.:
........ ':.':
...........
.:..... ':.':
...........
.....0'. ':.':
...........
........ ':.':
...........
55
55
~ Soft to Firm, Gray to Orange, Fine Sandy,
,,_~ Clayey Silt(ML)
I
20
55
55
I.
Boring Terminated At 20.0 Feet.
Groundwater encountered at 10 feet the time of
boring and at 3.0 feet at 2 days after boring.
25-
SS - Split Spoon Sample
30-
35-
I
I
40
w
- ::>
Z;i
>
06
09
15
08
03
05
I
I
I
I
I
I
I
I
I
I
I
!
I
J
I
I
j
!
l
j
!
I
j
GRA YES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-6
PROJECT: Spirit Creek Force Main
LOCATION: Station 97+70(at West SR 56 Bore) - Richmond Co., Georgia
GRA YES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 123' I DRll...LING METHOD: 2.25" I.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/11/05
.
~
J:
f-
0..
W
o
i~
~
i~
~m
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 60 90
:.:.:~:.:.:~:.:.:~:.:.: 0-4" Topsoil
::.:.~::.:.~::.:.~::.:. Possible Fill-Firm, Orange-Tan-Brown,
:::::~:::::~:::::~::::: Clayey, Silty Fine to Medium Sand(SC)
....... -------
.:.:::.:.:::-:.:::.:.:: Firm, Brown, Silty Fine to Medium Sand(SC)
05 _ :.:<.:.<:<.:: with slight organic content
.:.:::':.:::.:.::;.:.::,
IStiff, Gray, Fine Sandy, Clayey Silt(ML)
.::~:.:::::.:::::.:::. Firm, Gray-Tan, Silty Fine to Medium
10 - :.::~:.:.<:<:: Sand(SM)
':.-:. ':.':
...........
':. ':. ':.':
...........
'o'. .... .....:
;1!~!~j
15
55 ,
55 ~
..... /
-
55 .
55 ~.
55
..
Boring Termi;a,ted At 15.0 Feet
Groundwater encountered at 13 feet the time of
boring. Hole moist and caved at 5.5 feet at 5-
days after boring.
20-
SS - Split Spoon Sample
25-
30 -
I
J
Ii
I
"!
Ii
I
j
35-
40
w
-=>
Z;a!
>
19
15
10
18
15
GRAVES
SOIL TEST BORING RECORD
BVGINEERING SERVICES
BORING NO. B-7
PROJECT: Spirit Creek Force Main
LOCATION: Station 101+00(at Spirit Creek) - Richmond Co., Georgia
GRA VES PROJECT NO.: G-051231
T GROUND SURFACE ELEVATION: 120'1 DRILLING METHOD: 2.25" LD. AUGER
Page I of 1
DATE COMPLETED: 01/11/05
~ i~
J:
f-
a.
w (!)
0
. .
I~ i~
U.S.C.S. Soil Classification
Standard Penetration Resistances
o
10
20 30 40 50 60 70 80 90
. . .
..:.:.:. 0-6" Topsoil
. .. Loose, Brown-Grey, Slightly Clayey, Silty
. .. Fine to Medium Sand(SM)
~ Firm, Tan-Orange, Fine Sandy, Clayey
05_~~~ Silt(ML)
~
~~~ ~
. . . .
. . .
>>>:. Loose, Tan-Brown Fine to Coarse Sand(SW)
.\:-::-: with gravel
55
4
55
.
.....
55
-\
a
. . . .
. . . .
. . . .
. . . .
10- . . .
55
. . . .
. . . ,
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
.
. . . .
. . . .
II
;
~ Soft to Very Soft, Black, Fine Sandy, Clayey
15 - ~ Silt(ML) with many layers of peat
~
~
20
55 .
55
4
II
i
11
.I
Boring Termi-;ated At 20.0 Feet
Groundwater encountered at 6 feet the time of
boring and at several days after boring.
II
I
I
Ii
..J
!
Ii
J
II
j
II
j
Ii
J
25-
SS - Split Spoon Sample
30-
35-
40
w
. ::J
Z<i!
>
06
07
08
10
03
02
I
I
I
I
I
I
I
I
I
!
I
I
,
I
)
I
!
!
!
!
Ii
I
I
..J
BORING NO. B-8
SOIL TEST BORING RECORD
Page 1 of I
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 111+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 132' I DRILLING METHOD: 2.25" I.D. AUGER
DATE COMPLETED: 01/13105
~
:I:
f-
a.
w
a
i~
<!l
U.S.C.S. Soil Classification
:.:<.:<.:<.; 0_3" Topsoil
::.:<.:.~::.:<.; Firm, Tan-Brown-Red, Slightly Clayey, Silty
fr~r~~}~~~~ Fine to Medium Sand(SM)
...........
.:. .........",
05 - ::{::::;::{~::
:-::~"lI[". -------
;~~~~~~~ Dense, Red- Tan- White, Clayey, Silty Fine to
~~:'-::'-::". Medium Sand(SC)
~~:.-::.-::.~
~~~(-t-:.t~
;.~:.-::.-::.~
~~:.-::.-c:.~
.rC:'-::."~~
10 - -
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time. of
boring. Hole dry and caved at 5.5 feet at 5-days
after boring.
15-
20-
25-
30-
35-
40
SS - Split Spoon Sample
~~
i~
o
55
55
55
55
Standard Penetration Resistances
w
.:=>
Z;i
>
10 20 30 40 50 60 70 80 90
,
15
.
'~
18
37
39
1
I
1
I
,
J
I
I
I
~
)
~
J
Ii
I
I
t:
I
BORING NO. B-9
SOIL TEST BORING RECORD
Page 1 of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 120+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 125' I DRilLING METHOD: 2.25" I.D. AUGER
DATE COMPLETED: 01/13/05
:.:..;~::;:.:..;:.:.. 0-9" Topsoil
::.:.::::.;::.:.~:~:. Firm, Tan-Brown-Gray, Clayey, Silty Fine to
.:::/:::.:::::.:::: Medium Sand(SC)
05 Ji:~ii
...........
. -------
.:.:::.:;.:::.::..:::.:::.::: Very Firm, Tan-White, Silty Fine to Medium
............... S d(SM)
:.::.:.::.::.::::.::.::::.::.: an
~~~~~~~~~~~~:;~~~~~:~~~~~~~
10
~
J:
l-
ll.
W
o
15-
20-
II
J
II
11
!
Ij
~
J
25-
30-
35-
II
~,.I
40
~~
Cl
U.S.C.s. Soil Classification
1m
i~
o
55
55
55
......
55
Boring Terminated At 10.0 Feet.
Groundwater encountered at 8 feet the time of
boring. Hole dry and caved at 3.5 feet at
several days after boring.
SS - Split Spoon Sample
Standard Penetration Resistances
w
- ::>
z~
10 20 30 40 50 60 70 80 90
~
14
.
"
15
26
.
27
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-IO
PROJECT: Spirit Creek Force Main
LOCATION: Station 130+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRll..LING METHOD: 2.25" J.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/13/05
II
:z:
f-
a.
w
o
~~
(!)
~~
I~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 6090
............ 03" T .l
:.:::.:::.:::.: - OpSOl
::.::~::.::~::.::~::.; Stiff, Red-Tan, Fine Sandy, Clayey Silt(ML)
.:............
...........
::::<::.~::::.~:::; Note: 63.8% Passing 200 Sieve on Sample #2.
:?::?::?:::~ LL=40, PI=12 on Sample #2.
05 ..::.::.::. _
~~~~~~$~ Very~, Tan, Slightly Silty ~to-
~."."."I .
~~::::.~~~ MedIUm Sand(SP-SM)
~~:.~:.!~~
~-::,-::,rC~~
~-::.-::.'C~..
~-::.-::.-:~..
.~:.'~:.-:~..
tt~~-::.!:':~
10
55
~
55
...
\
~
~
55
55
Boring Term~ated At 10.0 Feet
No groundwater encountered at the time of
boring. Hole dry and caved at 2.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- ;:)
z~
>
11
13
21
26
BORING NO. B-ll
SOIL TEST BORING RECORD
Page 1 of 1
GRA YES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 140+00 - Richmond Co., Georgia
GRA YES PROJECf NO.: G-051231
I GROUND SURFACE ELEVATION: 136' I DRll...LING METHOD: 2.25" J.D. AUGER
DATE COMPLETED: 01/13/05
~
~~
(!)
J:
I-
0..
.W
o
U.S.C.S. Soil Classification
I~
i~
o
Standard Penetration Resistances
W
. ::>
z<f
>
10 20 30 40 50 60 70 8090
........... 09" T .l
.::::.::>::::.::. - OpSOl
:::.~:::.~:::.~:::. Firm to Very Firm, Tan, Silty Fine to Medium
05 _ ~i~1i~ Sand(SM)
...........
~
J
Ii
I
Ii
i
10
15-
II
11
J
11
J
II
II
J
II
J
Ii
I
.,
20-
25-
30-
35-
II
I
.J
II
I
i
,e,J
40
55 ~
... 55 'a.
- ~........
55 "" 'U
55 ~
Very Hard, White, Fine Sandy, Clayey
Silt(11L)
Boring Terminated At 10.0 Feet.
Groundwater encountered at 9 feet the time of
boring and at 5.0 feet at several days after
boring.
SS - Split Spoon Sample
11
25
70
74
I
1
I
I
I
I
I
i
,
I
I
,
I
i
I
I
I
;
I
I
)
I
j
!
!
I
J
II
i
Ii
GRA VES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-12
PROJECT: Spirit Creek Force Main
LOCATION: Station 150+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 141' I DRll...LING METHOD: 2.25" J.D. AUGER
Page 1 of I
DATE COMPLETED: 01/13/05
~
J:
f-
a.
UJ
a
i~
Cl
~~
I~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 8090
........... 06" T .l
:::::::::::::.: - OpSOl
::::.~::?::::.~::::. Firm, Brown-Tan, Clayey, Silty Fine to
::::::::::::::. Medium Sand(SC)
........... - - - - - --
::?::?::?:::~ Firm, Tan-Brown, Silty Fine to Medium
::.:::::.:::::.:::::.:: Sand(SM)
05 - :'::::'::~:'::::':: _ _ _ _ _ _ _ ...
::.:;::.::::.:;::: Firm, Tan, Fine to Medium Sand(SP)
...........
:.:..;:.:..;:.:..;:.:.,
.....:. ':.':
...........
.:. .... .:....
...........
':. .... ':.':
...........
.... .:. .....o'
...........
10 .:............
88
u
88
~.
88
.
88
~~
Boring Terminated At 10.0 Feet.
Groundwater encountered at 6 feet the time of
boring. Hole moist and caved at 3.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
i
"J
UJ
_ ::l
Z..:
>
16
16
12
13
BORING NO. B-13
SOIL TEST BORING RECORD
Page 1 of 1
GRA YES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 159+25(at West SR 56 Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 172' I DRilLING METHOD: 2.25" J.D. AUGER
DATE COMPLETED: 01/13/05
.;
J:
f-
n.
w
o
1O-@1
15
20-
l
J
!
!
\
II
J
II
j
II
j
.
25-
30-
35-
40
i~
C>
U.S.C.S. Soil Classification
I~
i~
o
Standard Penetration Resistances
W
.::>
z~
10 20 30 40 50 60 70 80 90
55
\
\
::.::..:::.::..:::.::..:::.::. 0-3" Topsoil
.::.:::../:..::.:::..::.: Firm to Very Firm, Tan-Red-Brown, Slightly
:::.:.::,':.:.::.-:.:~:,':.: Clayey, Silty Fine to Medium Sand(SM)
05-~1
~
55
Very Stiff, Gray, Fine Sandy, Clayey Silt(ML)
55
Very Firm, Gray-Tan, Clayey, Silty Fine to
Medium Sand(SC)
55
Hard, Gray-Pink-Tan, Fine Sandy, Clayey
Silt(ML)
- -
Boring Terminated At 15.0 Feet.
Groundwater encountered at 8 feet the time of
boring and at 4.5 feet at several days after
boring.
55
SS - Split Spoon Sample
16
27
4.
28
l~
28
\
\[\
58
.
I
I
I
J
I
I
I
I
~
J
l
I
~
j
!
Ii
J
!
!I
11
J
~
1\
I
.J
II
j
SOIL TEST BORING RECORD
GRA VES
ENGINEERING SERVICES
BORING NO. B-14A* PROJECT: Spirit Creek Force Main
LOCATION: Station 160+60(at East SR 56 Bore) - Richmond Co., Georgia
Page 1 of I GRAVES PROJECT NO.: G-051231
DATE COMPLETED: 01/13-20/05 I GROUND SURFACE ELEVATION: 173' I DRILLING METHOD: 2.25" I.D. AUGER
~
J:
t
w
o
~~
Cl
U.S.C.S. Soil Classification
I~
i~
o
Standard Penetration Resistances
w
- ~
z~
>
10 20 30 40 50 60 70 80 90
, , , . 0" Topsoil
Possible Fill - Very Loose, Tan-Red-Gray-
Brown, Clayey, Silty Fine to Medium
Sand(SC)
-------
:.:.r:.:;:.:.).: Firm to Very Firm, Gray-Tan-Orange, Clayey,
::.:'~:.':':::.:.). Silty Fine to Medium Sand(SC)
. ,', .
.:..... ':.':
...........
.... .... .o'....
...........
.... .:. .....:
...........
10 - :.:::,:::.:::.:
':":. ':.':
...........
.:. ':. ':. 0,'
...........
.,'......:..:
...........
0'.,." "
15 -
Boring Terminated At 15.0 Feet.
Groundwater encountered at 10 feet the time of
boring and at 4.0 feet at several days after
boring.
05 - . . . .
20-
25-
30-
35-
40
55 4
....
55
4
\
\.
\
\
55
55
Hard, Gray-Tan, Fine Sandy, Clayey Silt(ML)
55
*Note: First attempt to drill hole encontered
refusal to utility line at 6.5 feet.
SS - Split Spoon Sample
04
04
11
21
38
I
I
i
I
I
I
I
I
i
I
,
I
I
I
l
I
;
Ii
I
,i
Ii
)
BORING NO. B-15
SOIL TEST BORING RECORD
GRAVES
ENGINEERING SERVICES
Page 1 of 1
DATE COMPLETED: 01/13/05
PROJECT: Spirit Creek Force Main
LOCATION: Station 170+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 157' I DRILLING METHOD: 2.25" I.~. AUGER
~
:x::
6:
w
o
10
15-
Ii
!
I'
I
!
,)
1\
I
~
I,
_I
II
-~
20-
25-
30-
I:
J
35-
Ii
-'
Ii 40 I
j
~~
(!)
U.S.C.S. Soil Classification
I~
~~
Standard Penetration Resistances
w
. ::l
Z<l
>
10 20 30 40 50 60 70 80 90
55
\
:.:.:~:.:.>:.:;:.:.: 0-4" Topsoil
::.:-:::.:.;::.:.;::.:. Firm to Very Firm, Brown-Tan-Gray, Slightly
f}I::I:::~:: Clayey, Silty Fine to Medium Sand(SM)
.....:......:
05 - :::::?::?::?::
.........'.
.....
55
Hard, White-Gray-Tan, Fine Sandy, Clayey
Silt(ML)
Note: 79.3% Passing 200 Sieve on Sample #3.
LL=48, PI=16 on Sample #3.
Boring Termhi'ated At 10.0 Feet
Groundwater encountered at 6 feet the time of
boring and at 4.5 feet at several days after
boring.
55
55
SS - Split Spoon Sample
15
a
"
"
.I
21
42
33
BORING NO. B-16
SOIL TEST BORING RECORD
GRAVES
Bl/GINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 180+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 137' I DRILLING METHOD: 2.25" LD. AUGER
Page 1 of 1
DATE COMPLETED: 01/13/05
(f. ~~
J:
f-
a.
w <!l
0
U.S.C.S. Soil Classification
I~ i ~
05
. . .
'.:.:.:. 0" Topsoil
: :: Possible Fill-Loose, Brown-Tan-Red, Clayey,
.' .. ... Silty Fine to Medium Sand(SC)
-------
.:.::;::.::~::.~;::.; Firm, Dark Brown, Silty Fine to Medium
::::::.::::.::::': Sand(SM)
...........
.........:.... - - - - - --
:.:..;:.:..;:.:..;:.:.. Firm, Brown-Tan, Clayey, Silty Fine to
.:.:::.:.:::.:.~:.:.~ Medium Sand(SC)
. .t' ,0."
Very Stiff, Gray-Tan, Fine Sandy, Clayey
Silt(ML)
".
1 0
Boring Term~ated At 10.0 Feet
Groundwater encountered at 9 feet the time of
boring. Hole dry and caved at 0.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
Standard Penetration Resistances
w
. ::l
Ze;!
>
o
10
20 30 40 50 60 70 80 90
55
,
r'.
15
07
55
55
I~I
~
17
13
55
I
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-17
PROJECT: Spirit Creek Force Main
LOCATION: Station 190+00- Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 137' I DRll...LING METHOD: 2.25" J.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/13/05
[
i~
C!l
i~
I~
:I:
I-
tl.
W
Cl
U.S.C.S. Soil Classification
Standard Penetration Resistances
05
:.:.:?<.:.:;:.:.: 0-3" Topsoil
::::<::.~::::<:: Firm, Red-Brown-Tan, Clayey, Silty Fine to
:.,::.,::...::: Medium Sand(SM)
:::::~:::{:::~::::: Note: 30.5% Passing 200 Sieve on Sample #1
Very Stiff, Brown-Gray-Tan-Red, Fine
Sandy, Clayey Silt(ML)
o
10 20 30 40 50 60 70 80 90
10
Boring Termi-;ated At 10.0 Feet
Groundwater encountered at 8.5 feet the time
of boring and at 5.0 feet at several days after
boring.
S5 \
..... S5 ~
- \
55 .
S5 J
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
. ::l
Z;;!
>
15
22
29
23
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-18
PROJECT: Spirit Creek Force Main
LOCATION: Station 192+20(at RR Bore) - Richmond Co., Georgia
ORA VES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 140' I DRILLING METHOD: 2.25" J.D. AUGER
Page 1 of 1
DATE COMPLETED: 01113/05
~
:I:
f-
a..
w
o
~~
Cl
i~
I~
U.S.C.S. Soil Classification
Standard Penetration Resistances
o
10 20 30 40 50 60 70 BO 90
........... II
:::::::::;:::.' 0-6 Large Gravel
::.:.;::.:.~::.:.;::.: Firm, Red-Brawn-Tan, Clayey, Silty Fine to
::.::::.::::.::::.. Medium Sand(SC)
...........
Il'~~ Firm, Gray-Tan-Brown, Fine Sandy, Clayey
'~~ Silt(ML) c .
... "" .. ...
05 - ..:..:..:..
.. ... .. ..
-------
Very Stiff, Gray-Brown, Fine Sandy, Clayey
Silt(ML)
ss /"
...... ss
- ",
ss
ss \.
10
Boring Termi"";ated At 10.0 Feet
Groundwater encountered at 9 feet the time of
boring and at 5.0 feet at several days after
boring.
15-
SS - Split Spoon Sample
20-
Note: 67.1 % Passing 200 Sieve on Sample #2.
LL=39, PI=ll on Sample #2.
25-
I]
,
ij 30-
I
J
j 35-
I I
.J
I I I 40 I I ,
I
J
w
. ::l
Z;a!
:>
15
05
18
23
GRAVES
SOIL TEST BORING RECORD
BVGINEERING SERVICES
BORING NO. B-19
Page 1 of 1
DATE COMPLETED: 01/18/05
PROJECT: Spirit Creek Force Main
LOCATION: Station 200+00 - Richmond Co., Georgia
ORA VES PROJECT NO.: G-051231
~
~~
(9
15
20
25
30
J
J 35
40
GROUND SURFACE ELEVATION: 141' DRILLING METHOD: 2.25" J.D. AUGER
U.S.C.S. Soil Classification
~~ i ~
Standard Penetration Resistances
w
.=>
z;t
>
o
10
20 30 40 50 60 70 80 90
0-6" Topsoil
Very Stiff, Yellow-Oray-Tan-Brown, Fine
Sandy, Clayey Silt(ML)
55
15
SS
19
Very Hard, Brown-Gray, Fine Sandy, Clayey
Silt(ML)
55
57
Boring Terminated At 10.0 Feet
No groundwater encountered at the time of
boring or at everal days after boring.
55
91
SS - Split Spoon Sample
BORING NO. B-20
SOIL TEST BORING RECORD
Page 1 of I
PROJECT: Spirit Creek Force Main
LOCATION: Station 210+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
(f.
DATE COMPLETED: 01/18/0S
GROUND SURFACE ELEVATION: 136' DRll..LING METHOD: 2.2S" l.D. AUGER
~~
(!J
15
20
25
I
'I
I
I
1
.J
30
II
'i
.J
,
I
I) 35
J
1\
~
I 40
U.S.C.S. Soil Classification
I~ i~
o
10
Standard Penetration Resistances
GRAVES
ENGINEERING SERVICES
20 30 40 50 60 70 60 90
0-3" Topsoil
Very Hard, Yellow-Gray-Tan-Brown-Red,
Fine Sandy, Clayey Silt(ML)
S5
S8
88
Boring Terminated At 10.0 Feet
No groundwater encountered at the time of
boring or at everal days after boring.
88
SS - Split Spoon Sample
,....,---- -..".....:.....~
w
.::J
z~
>
43
78
56
55
GRA YES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-2!
PROJECT: Spirit Creek Force Main
LOCATION: Station 220+00 - Richmond Co., Georgia
ORA VES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRILLING METHOD: 2.25" LD. AUGER
Page I of I
DATE COMPLETED: 01118/05
~ i~
tb (.!)
Cl
~ 0-6" Topsoil
_ Firm to Stiff, Gray-Tan-Brown, Fine Sandy,
05 __ Clayey Silt(ML)
.:.:::-:.:::.:.:::-:.:: Firm, Gray, Silty Fine Sand(SM)
...........
':. ':. ':.':
...........
.:.:::.:.:::-:.:::-:.:: Note: 17.3% Passing 200 Sieve on Sample #3
...........
.............:
...........
.:. ':. ':.':
...........
':. .... ':.':
...........
10 .:............
~~
a:...J
~~
Standard Penetration Resistances
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 80 90
55
,
'e
,
55
".
55
4~
5S
o
Boring Terminated At 10.0 Feet.
Groundwater encountered at 8.5 feet the time
of boring. Hole moist and caved at 7.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
]
j
J
30-
35-
40
ill
_ ::l
Z<;!
>
08
12
17
16
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-22
Page 1 of 1
DATE COMPLETED: 01/18/05
PROJECT: Spirit Creek Force Main
LOCATION: Station 229+75 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 132' I DRilLING METHOD: 2.25" J.D. AUGER
~
J:
b:
w
Cl
05
Ii'
10
15-
20-
25-
30-
35-
40
~~
(!l
U.S.C.S. Soil Classification
~.~ i~ w
Standard Penetration Resistances - ;:)
~ Z;;!
>
0 10 20 30 40 50 60 70 80 90
55 ~ 18
55 1\ 25
0-6" Topsoil
Very Stiff, Gray-Tan-Brown, Fine Sandy,
Clayey Silt(ML)
Very Firm, Gray-Tan, Clayey, Silty Fine to
Medium Sand(SC)
55
4~
IJ
22
28
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.5 feet at
several days after boring.
55
SS - Split Spoon Sample
GRAVES
SOIL TEST BORING RECORD
avGlNEERING SERVICES
BORING NO. B-23
PROJECT: Spirit Creek Force Main
LOCATION: Station 240+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRILLING METHOD: 2.25" I.D. AUGER
Page 1 of I
DATE COMPLETED: 01/18/05
if.
J:
Ii:
w
o
~~
(!)
i~
I~
U.S.C.S. Soil Classification
Standard Penetration Resistances
10 20 30 40 50 60 70 8090
. . .
..:.:.:. 0-6" Topsoil
. .. Loose, Gray-Brown-Tan, Clayey, Silty Fine to
. .. Medium Sand(SC)
~~ Firm, Gray-Tan-Brown, Fine Sandy, Clayey
~~~~ Silt(ML)
05 -r-':~":":"
~~, .. '"
. . .
>>>:. Very Loose to Loose, Red-Brawn-Tan,
.::-\:-: Clayey, Silty Fine to Medium Sand(SC)
55 ,/"
..... 55
- ""
55
55 \.
10
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Groundwater encountered at 5.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- ::!
Z;;!
>
08
05
04
09
GRA YES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-24
PROJECT: Spirit Creek Force Main
LOCATION: Station 250+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 130' I DRilLING METHOD: 2.25" I.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/18/05
~
J:
l-
e..
w
o
10-3" Topsoil
~ Stiff, Tan-Gray-Brown, Fine Sandy, Clayey
>-: Si1t(ML)
.:.::;.:.:::.:.:::.:.:: Firm, Gray-Tan, Clayey, Silty Fine Sand(SC)
o 5 - ~:~:t:{:~:{:~i
i~
C!l
i~
I~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 60 90
55
4
~l
55
10
....... -------
i:;::::::::::: Firm, Gray-Tan, Silty Fine to Medium
;]~:~i~ Sand(SM)
55
..
55
~t
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- =>
z~
>
10
15
13
14
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-25
PROJECT: Spirit Creek Force Main
LOCATION: Station 260+00 - Richmond Co., Georgia
ORA YES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRll....LINGMETHOD: 2.25"I.D.AUGER
Page I of I
DATE COMPLETED: 01/18/05
~
i~
C)
i~
. 0
I~
Standard Penetration Resistances.
J:
I-
a.
w
o
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 80 90
~ ~ 0-6" Topsoil
:~ I Stiff, Tan-Brown, Fine Sandy, Clayey
rs: Silt(ML)
::?::?::?::::: Firm, Tan, Clayey, Silty Fine Sand(SC)
05 - :~;~:::::~:::::~:::~
..:...... ",
....... -------
::.::::.::::.::::.: Firm, Tan, Slightly Silty Fine to Medium
ijijij Sand(SP-S~
10 - _
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 7.0 feet at
several days after boring.
5S
\
55
55
1
J
55
15-
SS - Split Spoon Sample
20-
25-
.
30-
35-
40
w
z~
>
11
19
15
11
GRA VES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-26
PROJECT: Spirit Creek Force Main
LOCATION: Station 270+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRILLING METHOD: 2.25" J.D. AUGER
Page 1 of 1
DATE COMPLETED: 01/20/05
ff.
I
f-
a.
W
o
i~
(!J
i~
I~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 60 90
":',',",':','. I .
" ':, .:......:. 0-3 ' TOpSOIl
Very Firm to Dense, Gray-Tan, Clayey, Silty
Fine to Medium Sand(SC)
05 -
S5
4
55
.
10
...........
...........
':. .... .....:
...........
:{i{~1{:1{~
--
/It
~
Firm, Tan, Silty Fine Sand(SM)
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring or at several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
. ;;:)
Z;;!
>
,',
29
27
33
14
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-27
PROJECT: Spirit Creek Force Main
LOCATION: Station 280+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 130' I DRilLING METHOD: 2.25" LD. AUGER
Page I of 1
DATE COMPLETED: 01/20/05
[
u
I~
(!)
i~
~~
;:...J
Standard Penetration Resistances
J:
f-
a.
w
a
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 6090
:....:....:....:: 06" T .l
.....:..:.::..:...:...::: - OpSOl
:::::.:::::::.:::::::.:::::::. Very Firm, Brown-Gray, Clayey, Silty Fine
::.-:..::.->.:..:'.::..: Sand(SC)
Very Stiff, Brown-Gray, Fine Sandy, Clayey
Silt(ML)
55
.
55
~
\
).
.I
05
10
.::.:.:..::.:.:..::.:.:..::.; Very Firm, Gray-Tan, Clayey, Silty Fine to
:::::::::::::::::::::::::::::: Medium Sand(SC)
'..:'.':..':'.' - - - - - --
:~~~}IrI::I Firm, Gray-Tan, Fine to Medium Sand(SP)
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25 -
30 -
35-
40
w
- ::>
Z...J
~
28
25
30
14
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-28
PROJECT: Spirit Creek Force Main
LOCATION: Station 290+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 130' I DRILLING METHOD: 2.25" I.D. AUGER
Page I of I
DATE COMPLETED: 01120105
(f. !.2
~ ~ ~
it CJ
o 10-311 Topsoil
Stiff, Yellow-Gray-Brown-Red, Fine Sandy,
Clayey Silt(ML)
:.::.::.:.::.::.:.::.::.:.::.: Firm, Gray-Tan, Clayey, Silty Fine to
:::::::::::::::/::::::::: Medium Sand(SC)
05 -::.::',:::,::,,:::.::-,:::,::.
~~
CI:...J
~~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 8090
55
'f\.
V
!
55
-------
::)::::.}:.:::::. Firm, Gray-Tan,Fine to Medium Sand(SP)
.:..:......,'
. . " "
55
10
.:......:..,'
........ ,',
.,'. ':. .:....
...........
.:..:..:....
...........
.:..:..:....
...........
':":":.','
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- ::>
Z;i
>
11
28
19
11
BORING NO. B-29
SOIL TEST BORING RECORD
Page I of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 296+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 131' I DRILLING METHOD: 2.25" J.D. AUGER
DATE COMPLETED: 01/20/05
~
J:
t
w
o
u
~~
(!)
...........
...........
':":.':.','
10-:':<':'<:.<::
':.':.':.':
...........
',0.':.':.':
...........
.:..........,'
..... ......
.........:..:
...........
.....:. .....:
...........
.,0. .:. .....:
'..........
.:. .... .....:
...........
':. ':. .:..,.
...........
::':::':::':,':'
15
20-
25-
30-
35-
40
U.S.C.S. Soil Classification
~~
:5:-'
~~
o
Standard Penetration Resistances
w
. ::>
z<i!
>
10 20 30 40 50 60 70 8090
55
55
t
<
l
........... 09" T 'l
:::::::::::::.: - OpSOl
::.:-:::.:.:::.:.:::.:. Firm, Tan-Gray-Brown, Clayey, Silty Fine to
iiiiiji Medium Sand(SC) with thin ML lenses
05 - :::::::::::
':: :':: :',,::'::
~::::~:::::~}j:::::
.... ':. ':.':
...........
':. ':. ':.',
. " " "
55
-------
Firm, Gray-Tan Fine to Medium Sand(SP)
55
55
J
Boring Terminated At 15.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 11.0 feet at
several days after boring.
SS - Split Spoon Sample
14
20
11
19
12
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-30
PROJECT: Spirit Creek Force Main
LOCATION: Station 303+00(at RR Bore) - Richmond Co., Georgia
ORA YES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 134' I DRILLING METHOD: 2.25" LD, AUGER
Page 1 of I
DATE COMPLETED: 01/20105
~
::r:
t-
o..
W
o
Q
I~
(!l
i~
a:-,
~~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 8090
........... 06" T '1
::::::::::::::: - OpSOl
::.:.~::.:.~::.:.;::.:. Firm, Gray-Tan, Clayey, Silty Fine to Medium
.:::::.:::::.:::::.::; Sand(SC)
Hard, Yellow-Gray-Brown, Fine Sandy,
Clayey Silt(ML)
.
55
55
05
10
}:?::?::?:: Very Firm to Firm, Yellow-Brown-Gray,
::::)::?/:::: Silty Fine Sand(SM)
{:r~:~r:~:?~: Note: 14.2% Passing 200 Sieve on Sample #4.
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 5.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- :;)
z-'
~
14
36
22
16
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-31
Page 1 of I
PROJECT: Spirit Creek Force Main
LOCATION: Station 304+00(at RR Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
1 GROUND SURFACE ELEVATION: 134' I DRILLING METHOD: 2.25" LD. AUGER
DA TE COMPLETED: 01/20/05
:.:.:;:.:.:;:.:.:;:.:.: Firm, YeIlow-Brown-Gray-Red, Silty Fine
~iiii~~ Sand(SM)
~
:r
f-
a.
w
o
05
10
15-
20-
25-
30-
35-
40
u
~~
<!l
i~
CI:..J
~~
Standard Penetration Resistances
w
. ::J
Z<i!
>
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 8090
0-6" Topsoil
Hard to Very stiff, Yellow-Brown-Gray, Fine
Sandy, Clayey Silt(ML)
Note: 74.9% Passing 200 Sieve on Sample #2.
.
j
/
4~
55
31
55
25
55
18
55
..
17
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 5.5 feet at
several days after boring.
.
SS - Split Spoon Sample
BORING NO. B-32
SOIL TEST BORING RECORD
Page I of I
PROJECT: Spirit Creek Force Main
LOCATION: Station 310+00 - Richmond Co., Georgia
GRA YES PROJECT NO.: G-051231
GRAVES
ENGINEERING SERVICES
.
~
DATE COMPLETED: 01/20/05
I GROUND SURFACE ELEVATION: 135' I DRILLING METHOD: 2.25" LD. AUGER
:r:
ti:
w
o
05
10
15-
20-
25-
30-
35-
40
i~
<!l
U.S.C.S. Soil Classification
OC-J
~~
~~
o
Standard Penetration Resistances
UJ
- ::>
z<i!
>
'0 20 30 40 50 60 70 8090
0-9" Topsoil
Stiff to Very stiff, Yellow-Brown-Gray, Fine
Sandy, Clayey SiltCML)
55
,
::::<::<::<::. Firm, Yellow-Brown-Gray-Red, Silty Fine
:.:::.:::.:::.: Sand(SM)
.:........,.:
...........
.... ':. ':.':
55
~
">
./
:-.:
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.0 feet at
several days after boring.
SS - Split Spoon Sample
12
10
25
11
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-33
PROJECT: Spirit Creek Force Main
LOCATION: Station 316+00(at 56 Loop Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEV ATION: 135' I DRILLING METHOD: 2.25" LD. AUGER
Page I of I
DATE COMPLETED: 01120105
~
:I:
f-
a..
w
Cl
i~
(!)
i~
CI:-,
~~
5:-'
Standard Penetration Resistances
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 80 90
0-9" Topsoil
Very Stiff to Hard, Gray-Brown-Tan-Red, Fine
Sandy, Clayey Silt(ML)
55
05
5S
~-::,:c:.-:~~ Dense, Tan-Gray-Brown, Clayey, Silty Fine
."......:~
~~':...':...~: to Medium Sand(SC)
1_...........
....JO.....
~~-::::;.~~.
I'!o..........
..........
55
v~
.~
-------
Very Firm, Gray-Tan-Brown, Silty Fine to
10 - Medium Sand(SM)
55
15
55
1lI~
Boring Terminated At 15.0 Feet.
; No groundwater encountered at the time of
boring. Hole dry and caved and at 10.0 feet at
several days after boring.
20-
SS - Split Spoon Sample
25-
30-
35-
40
w
- ~
Z<f
>
23
38
41
23
21
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-34
PROJECT: Spirit Creek Force Main
LOCATION: Station 318+40(at East 56 Loop Bore) - Richmond Co., Georgia
ORA VES PROJECT NO.: G-051231
I GROUND SURFACE ELEV ATION: 138' I DRilLING METHOD: 2.25" LD. AUGER
Page I of I
DATE COMPLETED: 01/18/05
i6.
~~
C!l
~~
a:...J
~~
J:
b:
w
o
U.S.C.S. Soil Classification
Standard Penetration Resistances
o
10 20 30 40 50 60 70 80 90
0-9" Topsoil
Very stiff, Red-Brown-Gray, Fine Sandy,
Clayey Silt(ML)
55
05
55
:::::.:::::::.:::::::.:::::::. Very Firm, Gray-Tan, Clayey,Silty Fine to
::::::::::::::::::::::::::::~ Medium Sand(SC)
.0,0,0,0
55
-------
::.::~::.::~::.:::::.:: Firm , Gray-Tan, Silty Fine to Medium
10 - ~i~:~rand(SM)
:.:.<:<.:..;:.:: Firm, Tan-:Bro"Wn, Fine tOMedium Sand(SP)
.::::.::::.::::.:; with gravel
15 - :::::}::}::}::
':. .... ':.'o'
...........
':. ':. ':.'o'
...........
...............
...........
''''':. .....:
...........
.............:
...........
~~:~: 1 ~~:~~ ~ { ~ ~I
20 - _
55
55
55
.
Boring Terminated At 20.0 Feet.
No groundwater encountered at the time of
boring. Hole moist and caved and at 15.0 feet
at several days after boring.
25-
SS - Split Spoon Sample
30-
35-
40
w
- ::>
Z;;;!
>
18
16
26
17
1 1
15
GRA YES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-35
PROJECT: Spirit Creek Force Main
LOCATION: Station 335+20(at Airport Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEV ATION: 147' I DRILLING METHOD: 2.25" J.D. AUGER
Page I of I
DATE COMPLETED: 01/19/05
i:S
:I:
I-
Cl.
w
o
i~
C!l
i~
I~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 8090
:.:.:~:-:.:::.:.:~:.:.: 0-6" Topsoil
::.:<.:<.:.~::.:. Firm, Yellow-Brown, Clayey, Silty Fine to
::.::::.::::.::::.: Medium Sand(SM)
::::<::<::.;::::. Note: 82.7% Passing 200 Sieve on Sample #l.
Very stiff, Yellow-Brown-Gray, Fine Sandy,
05 Clayey Silt(ML)
55
~~
SS
55
v
10
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- ::>
Z;;!
>
14
29
26
20
BORING NO. B-36
SOIL TEST BORING RECORD
Page 1 of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 336+30(at Airport Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 147' I DRILLING METHOD: 2.25" LD. AUGER
DATE COMPLETED: 01/19/05
~
:I:
Ii:
w
o
i~
(!)
U.S.C.S. Soil Classification
a::.J
~~
:S:.J
i~
Standard Penetration Resistances
w
- ::>
Z;;!
>
::<.:<.:<.:.. 0-6" Topsoil
/:::.:::::.:::::.:: Firm, Yellow-Brown, Clayey, Silty Fine to
::~::(::j::):{ Medium Sand(SM)
Very stiff, Yellow-Brown-Gray, Fine Sandy,
05 Clayey Silt(ML)
10
15-
20-
25-
.
30-
35-
40
55
55
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 5.5 feet at
several days after boring.
SS - Split Spoon Sample
10 20 30 40 50 60 70 8090
~i'.
/
~.
11
30
24
.
28
GRAVES
BORING NO. B-37
SOIL TEST BORING RECORD
ENGINEERING SERVICES
Page 1 of 1
PROJECT: Spirit Creek Force Main
LOCATION: Station 349+50(at Airport Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 148' I DRilLING METHOD: 2.25" J.D. AUGER
Q;
DATE COMPLETED: 01/19/05
I
I-
0-
W
o
u
I~
(!J
05
U.S.C.S. Soil Classification
0-6" Topsoil
Stiff to Very Stiff, Yellow-Brown-Gray-Red,
Fine Sandy, Clayey Silt(ML)
i!i:i:i Firm, Yellow-Brown, Silty Fine Sand(SM)
':. ':. .....:
..,........
':.':.':.','
...........
';.':.';.','
10
15-
20-
25 -
30-
35-
40
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole moist and caved and at 6.0 feet at
several days after boring.
SS - Split Spoon Sample
I~
~~
10 20 30 40 50 60 70 60 90
Standard Penetration Resistances
w
- ::>
Z<;!
>
55
13
55
24
55
13
55
18
BORING NO. B-38
SOIL TEST BORING RECORD
Page 1 of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 350+60(at Airport Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 148' I DRILLING METHOD: 2.25" I.D. AUGER
DATE COMPLETED: 01/19/05
~
J:
b::
lJ.J
o
u
i~
(!)
05
U.S.C.S. Soil Classification
a:-,
~~
S:-'
~~
0-6" Topsoil
Stiff to Very Stiff, Yellow-Brown-Gray-Red,
Fine Sandy, Clayey Silt(ML)
:.:.:;:.:.:;:.:.:;:.:.: Firm, Yellow-Brown, Silty Fine Sand(SM)
rt::t::t::: Note: 17.5% Passing 200 Sieve'on Sample #3.
':":":.','
..,..... ,',
.,'..:........
...........
.... ':. ':.':
10
15-
20-
25-
30-
35-
I 40
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Groundwater encountered at 6.0 feet at
several days after boring.
SS - Split Spoon Sample
Standard Penetration Resistances
w
. =>
Z;i
>
10 20 30 40 50 60 70 80 90
11
27
13
20
BORING NO. B-39
SOIL TEST BORING RECORD
Page I of 1
GRAVES
w
-::>
Z;a!
>
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 360+00(at Airport Bore) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
DATE COMPLETED: 01/19/05
GROUND SURFACE ELEVATION: 148' DRILLING METHOD: 2.25" I.D. AUGER
is
:I:
t
w
Cl
i~
(!)
U.S.C.S. Soil Classification
0-6" Topsoil
Very Stiff to Hard, Yellow-Brown-Gray-Red,
Fine Sandy, Clayey Silt(ML)
::::::{~:/::}) Very Firm, Brown-Tan, Clayey, Silty Fine
::::::::::::::::::}:::::::: S and(SC)
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Groundwater encountered at 6.5 feet at
several days after boring.
10
15
20
25
30
35
40
SS - Split Spoon Sample
~~
5:"'"
i~
o
55
55
T
5S
SS
Standard Penetration Resistances
'0 20 30 40 50 60 70 80 90
24
22
44
29
GRAVES
ENGINEERING SERVICES
SOIL TEST BORING RECORD
BORING NO. B-40
PROJECT: Spirit Creek Force Main
LOCATION: Station 370+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 144' I DRilLING METHOD: 2.25" LD. AUGER
Page I of 1
DATE COMPLETED: 01/19/05
~
:I:
Ii:
w
o
i~
(!)
~~
w
- :::>
Z...J
<(
>
OC...J
~~
Standard Penetration Resistances
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 8090
o
. ........... 09" T 'l
::::::::::::::: - OpSOl
::.:<.:<.:.~::.:. Firm, Yellow-Brown-Red Clayey, Silty Fine
.:::::.:::::.:::::.:::: Sand(SC)
Hard, Yellow-Tan-Gray-Brown, Fine Sandy,
Clayey Silt(ML)
i\-...
/
.
S5
11
23
55
05
20
55
~?::::/::/::: Firm, Red-Tan, Slightly Clayey, Silty Fine to
:~~:r~r~:1:~:~: Medium Sand(SM)
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.5 feet at
several days after boring.
~
18
55
10
15-
SS - Split Spoon Sample
20-
25-
30-
35-
!,
!I
I'
J
40
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-41
PROJECT: Spirit Creek Force Main
LOCATION: Station 380+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 146' I DRILLING METHOD: 2.25" I.D. AUGER
Page I of 1
DATE COMPLETED: 01/19/05
~
J:
f-
lL
W
Q
I.< ..
i~
Cl
~~
i~
Standard Penetration Resistances
U.S.C.S. Soil Classification
o
10 20 30 40 50 60 70 80 90
........... 09" T .l
.::::.::>:.->::: - OpSOl
:::.::::<.:<::. Firm, Brown-Red-Tan, Slightly Clayey, Silty
.:>:>:::::.:::. Fine to Medium Sand(SM)
Hard, Pink-Tan-Gray, Fine Sandy, Clayey
Silt(ML)
55
"
'-
/
I
.I
55
05
10
:::::?::?::?:: Very Firm to Firm, Red-Tan, Slightly Silty
1111, Fine to Medium Sand(SP-SM)
55
55
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Groundwater encountered at 6.5 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40
w
- :;)
Z;;!
>
15
37
24
15
GRAVES
BORING NO. B-42
SOIL TEST BORING RECORD
ENGINEERING SERVICES
Page I of I
PROJECT: Spirit Creek Force Main
LOCATION: Station 386+00(at water main) - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
DATE COMPLETED: 01/19/05
GROUND SURFACE ELEVATION: 139' DRILLING METHOD: 2.25" LD. AUGER
~ i~ I~ i~ w
J: U.S.C.S. Soil Classification Standard Penetration Resistances . ::>
f- Z;;!
0-
W <!l >
a 0 10 20 30 40 50 60 70 8090
0-6" Topsoil
Possible Fill - Loose, Tan-Brown, Clayey,
Silty Fine to Medium Sand(SC) 55 06
05 Very Stiff to Hard, Gray-Brown-Tan-Red, 55 20
Fine Sandy, Clayey Silt(ML)
Note: 87.2% Passing 200 Sieve on Sample #3. 28
LL=49, PI=20 on Sample #3. 55
10 55 32
15
20
25
30
35
40
Boring Terminated At 15.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 10.0 feet at
several days after boring.
55 24
SS - Split Spoon Sample
BORING NO. B-43
SOIL TEST BORING RECORD
Page I of 1
GRAVES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 394+40(offset 50' west) - Richmond Co., Georgia
GRAVES PROJECTNO.: G-051231
I GROUND SURFACE ELEVATION: 130' I DRILLING METHOD: 2.25"I.D.AUGER
DATE COMPLETED: 01/19/05
[f..
I
f-
a.
w
o
u
i~
<!J
U.S.C.S. Soil Classification
........... 09" T 'l
::::::::::::::: - OpSOl
::.:.~::.:<<.:. Firm, Grey-Brown, Clayey, Silty Fine to
::::::::::::::: Medium Sand(SC)
:t\:~:~~1{?~~
05 - :::::?::?::?::
:.::;:.::;:.::;:.::
-------
Very Stiff to Stiff, Gray-Brown-Tan-Red, Fine
Sandy, Clayey Silt(ML)
10_
15-1
I
I
I
J
~
II
Ii
J
IJ
II
>,~J
11
J
IJ
I]
J
1\
.",,';
Ii
~.
:.:<.;.::.:<.:: FIrm to Loose, Tan-Brown, Slightly Silty
::?::?:::::~::::: Fine to Coarse Sand(SW -SM) with gravel
20 - ::{:rt?~:?~: Note: 6.4% Passing 200 Sieve on Sample #5.
~{~t: l~:~:: j~:~::
':.':.':.':
...........
.:......:..,'
...........
':. ':. .....:
...........
25 ':.':.':.':
30-
35-
40
Boring Terminated At 25.0 Feet.
Groundwater encountered at 19 feet the time of
boring and at 16.0 feet at 2 days after boring.
SS - Split Spoon Sample
tr...J
~~
i~
Standard Penetration Resistances
w
.::>
Z:,!
>
55
55
55
55
55
T
55
55
'0 20 30 40 50 60 70 8090
u
1II
\
~
I
n
..
.
15
14
21
11
12
13
13
GRAVES
SOIL TEST BORING RECORD
ENGINEERING SERVICES
BORING NO. B-44
PROJECT: Spirit Creek Force Main
LOCATION: Station 410+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: 129' I DRILLING METHOD: 2.25" LD. AUGER
Page I of I
DATE COMPLETED: 01/19/05
(S
:I:
t;:
W
o
~
I~
(!)
~~
CI:...J
~~
::...J
Standard Penetration Resistances
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 8090
:.:<.:.:~:.:.:~:.:.: 0-6" Topsoil
;.:.~::-:<.<.:. Firm, Tan-Gray, Clayey, Silty Fine to Medium
::.::::.::::.::-::.: Sand(SC)
::/::?::::./. Note: 32.4% Passing 200 Sieve on Sample #1.
Very Stiff to Stiff, Brown-Gray, Fine Sandy,
05 - Clayey Silt(ML)
55
\
r.
(
55
~
55
10 -
55
..
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 7.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
20-
25-
30-
35-
40 I
I
I I
w
- ::;)
Z;i
>
16
22
12
10
BORING NO. B-45A *
SOIL TEST BORING RECORD
Page I of 1
GRA YES
ENGINEERING SERVICES
PROJECT: Spirit Creek Force Main
LOCATION: Station 420+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: N/A I DRILLING METHOD: 2.25" I.D. AUGER
DATE COMPLETED: 01/20/05
~
:c
b:
w
o
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
. . . .
os
. . . .
. . . .
I.l
I~
Cl
U.S.C.S. Soil Classification
I~
0-9" Topsoil
Possible Fill - Loose, Gray-Tan, Clayey, Silty
Fine to Medium Sand(SC)
Stiff, Black-Grey, Fine Sandy, Clayey
Silt(ML) with organics
~~~~t~~~~~:~~~~~t~::~~~ Very Firm, Tan Fine to Medium Sand(SP)
10
1S-
20-
2S-
30-
3S-
40
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 7.0 feet at
several days after boring.
SS - Split Spoon Sample
*Note: First attempt to drill hole encontered
refusal to utility line at 6.0 feet. Hole moved 5
feet with auger probe to 6 feet.
i~
55
55
55
55
o
Standard Penetration Resistances
w
- :::>
z-'
<t
>
10 20 30 40 50 60 70 8090
4'
.I
\
,,~
07
os
11
24
.
I
~
I
I
,
,
,
,
l
I
J
~
Ii
J
GRAVES
ENGINEERING SERVICES
SOIL TEST BORING RECORD
BORING NO. B-46
PROJECT: Spirit Creek Force Main
LOCATION: Station 430+00 - Richmond Co., Georgia
GRAVES PROJECT NO.: G-051231
I GROUND SURFACE ELEVATION: N/A I DRILLING METHOD: 2.25" I.D. AUGER
Page I of 1
DATE COMPLETED: 01/20/05
(f.
J:
Ii:
w
o
u
I~
Cl
i~
CI:-l
~~
~':':l
w
. ::>
z<i!
>
Standard Penetration Resistances
U.S.C.S. Soil Classification
10 20 30 40 50 60 70 8090
........... 09" T '1
:::::::::::::.: - OpSOl
.::.;.::.;.::.;.::. Firm, Gray-Brown, Clayey, Silty Fine to
.:::::-:::::.:::::.::; Medium Sand(SC)
Stiff, Gray-Brown, Fine Sandy, Clayey
SiltCML)
4'
55
18
ta
\
~t
17
55
05
.::::~.::>::>:::: Very Firm, Gray-Tan" Silty Fine to Medium
:::::/:::::::::::::: Sand(SM)
::(\?:::/:: Note: 22.3% Passing 200 Sieve on Sample #4.
24
55
..
22
55
10
Boring Terminated At 10.0 Feet.
No groundwater encountered at the time of
boring. Hole dry and caved and at 6.0 feet at
several days after boring.
15-
SS - Split Spoon Sample
fI
,J
20-
J]
I'
.J
'J
I]
IJ
J]
11
-,)
25-
30 -
35-
40
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
A.
B.
c.
D.
SECTION TS-4
DEWATERING
GENERAL
RELATED DOCUMENTS
1. Drawings and general proVIsIOns of the Contract, including General and
Supplementary Conditions and Division 1 Specification Sections, apply to this
Section.
SUMMARY
1. This Section includes construction dewatering.
2. Related Sections include the following:
a. TS-3 Section "Excavation and Backfilling."
PERFORMANCE REQUIREMENTS
1. Dewatering Performance: Design, furnish, install, test, operate, monitor, and
maintain dewatering system of sufficient scope, size, and capacity to control
ground-water flow into excavations and permit construction to proceed on dry, stable
subgrades.
a. Maintain dewatering operations to ensure erosion control, stability of
excavations and constructed slopes, that excavation does not flood, and that
damage to subgrades and permanent structures is prevented.
b. Prevent surface water from entering excavations by grading, dikes, or other
means.
c. Accomplish dewatering without damaging existing buildings adjacent to
excavation.
d. Remove dewatering system when no longer needed.
QUALITY ASSURANCE
1. Regulatory Requirements: Comply with Augusta, Georgia requirements for erosion
control with regard to water disposal.
TS-4-1
I
I
I
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
E.
F.
-02.
-03.
A.
PROJECT CONDIDONS
1. Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or
others unless permitted in writing by Engineer and then only after arranging to
provide temporary utility services according to requirements indicated.
Survey adjacent structures and improvements, employing a qualified professional engineer
or land surveyor, establishing exact elevations at fixed points to act as benchmarks. Clearly
identify benchmarks and record existing elevations.
1. During dewatering, regularly resurvey benchmarks , maintaining an accurate log of
surveyed elevations for comparison with original elevations. Promptly notify
Engineer if changes in elevations occur or if cracks, sags, or other damage is evident
in adjacent construction.
PRODUCTS (Not Used)
EXECUTION
PREPARATION
1. Protect structures, utilities, sidewalks, pavements, and other facilities from damage
caused by settlement, lateral movement, undermining, washout, and other hazards
created by dewatering operations.
a. Prevent surface water and subsurface or ground water from entering
excavations, from ponding on prepared subgrades, and from flooding site and
surrounding area.
b. Protect subgrades and foundation soils from softening and damage by rain or
water accumulation.
c. Protect all soil stock piles from damage due to rain or water accumulation.
2. Install dewatering system to ensure minimum interference with roads, streets, walks,
and other adjacent occupied and used facilities.
a. Do not close or obstruct streets, walks, or other adjacent occupied or used
facilities without permission from Owner. Provide alternate routes around
closed or obstructed traffic ways.
B.
INSTALLATION
1. Install dewatering system utilizing wells, well points, or similar methods complete
with pump equipment, standby power and pumps, filter material gradation, valves,
TS-4-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
appurtenances, water disposal, and surface-water controls where such system is
needed to control water.
2. Before excavating below ground-water level, place system into operation to lower
water to specified levels. Operate system continuously until drains, sewers, and
structures have been constructed and fill materials have been placed, or until
dewatering is no longer required.
3. Provide an adequate system to lower and control ground water to permit excavation,
construction of structures, and placement of fill materials on dry subgrades. Install
sufficient dewatering equipment to drain water-bearing strata above and below
bottom of foundations, drains, sewers, and other excavations.
a. Do not permit open-sump pumping that leads to loss of fines, soil piping,
sub grade softening, and slope instability.
4. Reduce hydrostatic head in water-bearing strata below sub grade elevations of
foundations, drains, sewers, and other excavations.
a. Maintain piezometric water level a minimum of 24 inches below surface of
excavation.
5. Dispose of water removed by dewatering in a manner that avoids endangering public
health, property, and portions of work under construction or completed. Dispose of
water in a manner that avoids inconvenience to others. Provide sumps,
sedimentation tanks, and other flow-control devices as needed.
6. Provide standby equipment on-site, installed and available for immediate operation,
to maintain dewatering on continuous basis if any part of system becomes inadequate
or fails. If dewatering requirements are not satisfied due to inadequacy or failure of
dewatering system, restore damaged structures and foundation soils at no additional
expense to Owner.
a. Remove dewatering system from Project site on completion of dewatering.
Plug or fill well holes with sand or cut off and cap wells a minimum of 36
inches below overlying construction.
7. Damages: Promptly report and repair damages to adjacent facilities caused by
dewatering operations.
c.
OBSERVATION WELLS
1. Provide, take measurements, and maintain observation wells or piezometers as may
be required to provide reliable information as to the effectiveness of the dewatering
system.
TS-4-3
TS-4-4
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
2. Observe and record daily elevation of ground water and piezometric water levels in
observation wells.
3. Repair or replace, within 24 hours, observation wells that become inactive, damaged,
or destroyed. Suspend construction activities in areas where observation wells are
not functioning properly until reliable observations can be made. Add or remove
water from observation-well risers to demonstrate that observation wells are
functioning properly.
4. Fill observation wells, remove piezometers, and fill holes when dewatering is
completed.
END OF SECTION
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
-01.
A.
B.
A.
SECTION TS-5
TEMPORARYBVPASSPUMPINGSYSTEMS
SCOPE
Under this item the Contractor is required to furnish all materials, labor, equipment, power,
maintenance, etc. to implement a temporary pumping system for the purpose of diverting the
existing flow around the work area for the duration of the project.
The design, installation and operation of the temporary pumping system shall be the
Contractor's responsibility. The Contractor shall employ the services of a vendor who can
demonstrate to the engineer that he specializes in the design and operation of temporary
bypass pumping systems. The vendor shall provide at least five (5) references of projects
of a similar size and complexity as this project performed by his firm within the past three
years. The bypass system shall meet the requirements of all codes and regulatory agencies
having jurisdiction.
-02.
REOUIREMENTS FOR SUBMITTING BIDS
The Contractor shall submit to the Engineer detailed plans and descriptions outlining all
provisions and precautions to be taken by the Contractor regarding the handling of existing
wastewater flows. This plan must be specific and complete, including such items as
schedules, locations, elevations, capacities of equipment, materials and all other incidental
items necessary and/or required to insure proper protection of the facilities, including
protection of the access and bypass pumping locations from damage due to the discharge
flows, and compliance with the requirements and permit conditions specified in these
Contract Documents. No construction shall begin until all provisions and requirements have
been reviewed by the Engineer.
B.
The plan shall include but not limited to details of the following:
1. Staging areas for pumps;
2. Sewer plugging method and types of plugs;
3. Number, size, material, location and method of installation of suction piping;
4. Number, size, material, method of installation and location of installation of discharge
pIpmg;
5. Bypass pump sizes, capacity, number of each size to be on site and power
requirements;
6. Calculations of static lift, friction losses, and flow velocity (pump curves showing
pump operating range shall be submitted);
7. Standby power generator size, location;
8. Downstream discharge plan;
TS-5-1
TS-5-2
9. Method of protecting discharge manholes or structures from erosion and damage;
10. Thrust and restraint block sizes and locations;
11. Sections showing suction and discharge pipe depth, embedment, select fill and special
backfill;
12. Method of noise control for each pump and/or generator;
13. Any temporary pipe supports and anchoring required;
14. Design plans and computation for access to bypass pumping locations indicated on the
drawings;
15. Calculations for selection of bypass pumping pipe size;
16. Schedule for installation of and maintenance of bypass pumping lines;
17. Plan indicating selection location of bypass pumping line locations.
-03.
EOUIPMENT
A.
All pumps used shall be fully automatic self-priming units that do not require the use of
footvalves or vacuum pumps in the priming system. The pumps may be electric or diesel
powered. All pumps used must be constructed to allow dry running for long periods of time
to accommodate the cyclical nature of effluent flows.
1. The Contractor shall provide the necessary stop/start controls for each pump.
2. The Contractor shall include one stand-by pump of each size to be maintained on site.
Back-up pumps shall be on-line, isolated from the primary system by a valve.
3. Discharge Piping - In order to prevent the accidental spillage of flows all discharge
systems shall be temporarily constructed of rigid pipe with positive, restrained joints.
Under no circumstances will aluminum "irrigation" type piping or glued PVC pipe be
allowed. Discharge hose will only be allowed in short sections and by specific
permission from the Augusta Utilities Department.
-04.
SYSTEM DESCRIPTION
A.
Design Requirements:
1. Bypass pumping systems shall have sufficient capacity to pump a peak flow of 10,000
gpm. The Contractor shall provide all pipeline plugs, pumps of adequate size to
handle peak flow, and temporary discharge piping to ensure that the total flow of the
main can be safely diverted around the section to be repaired. Bypass pumping system
will be required to be operated 24 hours per day.
2. The Contractor shall have adequate standby equipment available and ready for
immediate operation and use in the event of an emergency or breakdown. One standby
TS-5-3
pump for each size pump utilized shall be installed at the mainline flow bypassing
locations, ready for use in the event of primary pump failure.
3. Bypass pumping system shall be capable of bypassing the flow around the work area
and of releasing any amount of flow up to full available flow into the work area as
necessary for satisfactory performances of work.
4. The Contractor shall make all arrangements for bypass pumping during the time when
the main is shut down for any reason. System must overcome any existing force main
pressure on discharge.
B.
Performance Requirements:
1. It is essential to the operation of the existing sewerage system that there be no
interruption in the flow of sewage throughout the duration of the project. To this end,
the Contractor shall provide, maintain and operate all temporary facilities such as
dams, plugs, pumping equipment (both primary and back-up units as required),
conduits, all necessary power, and all other labor and equipment necessary to intercept
the sewage flow before it reaches the point where it would interfere with his work,
carry it past his work and return it to the existing sewer downstream of his work.
2. The design, installation and operation of the temporary pumping system shall be the
Contractor's responsibility. The bypass system shall meet the requirements of all codes
and regulatory agencies having jurisdiction.
3. The Contractor shall provide all necessary means to safely convey the sewage past the
work area. The Contractor will not be permitted to stop or impede the main flows
under any circumstances.
4. The Contractor shall maintain sewer flow around the work area in a manner that will
not cause surcharging of sewers, damage to sewers and that will protect public and
private property from damage and flooding.
a. The Contractor shall protect water resources wetlands and other natural
resources.
-05.
FIELD QUALITY CONTROL AND MAINTENANCE
A.
Test:
1. The Contractor shall perform leakage and pressure tests of the bypass pumping
discharge piping using clean water prior to actual operation. The engineer will be
given 24 hours notice prior to testing.
TS-5-4
2. Inspection:
a. Contractor shall inspect bypass pumping system every two hours to ensure that
the system is working correctly.
3. Maintenance Service:
a. The Contractor shall insure that the temporary pumping system is properly
maintained and a responsible operator shall be on hand at all times when pumps
are operating.
4. Extra Materials:
a. Spare parts for pumps and piping shall be kept on site as required.
b. Adequate hoisting equipment for each pump and accessories shall be maintained
on the site.
-06.
PREPARATION
A.
Precautions
1. Contractor is responsible for locating any existing utilities in the area the Contractor
selects to locate the bypass pipelines. The Contractor shall locate his bypass pipelines
to minimize any disturbance to existing utilities and shall obtain approval of the
pipeline locations from the City and the Engineer. All costs associated with relocating
utilities and obtaining all approvals shall be paid by the Contractor.
2. During all bypass pumping operation, the Contractor shall protect the Pumping Station
and main and all local sewer lines from damage inflicted by any equipment. The
Contractor shall be responsible for all physical damage to the Pumping Station and
main and all local sewer lines caused by human or mechanical failure.
-07.
INSTALLATION AND REMOVAL
A.
The Contractor shall remove manhole sections or make connections to the existing sewer
and construct temporary bypass pumping structures only at the access location indicated on
the Drawings and as may be required to provide adequate suction conduit.
B.
Plugging or blocking of sewage flows shall incorporate primary and secondary plugging
device. When plugging or blocking is no longer needed for performance and acceptance or
work, it is to be removed in a manner that permits the sewage flow to slowly return to
normal without surge, to prevent surcharging or causing other major disturbances
downstream.
TS-5-5
C. When working inside manhole or force main, the Contractor shall exercise caution and
comply with OSHA requirements when working in the presence of sewer gases, combustible
oxygen-deficient atmospheres, and confined spaces.
D. The installation of the bypass pipelines is prohibited in all saltmarsh/wetland areas. The
pipeline must be located off streets and sidewalks and on shoulders of the roads. When the
bypass pipeline crosses local streets and private driveways, the contractor must place the
bypass pipelines in trenches and cover with temporary pavement. Upon completion of the
bypass pumping operations, and after the receipt of written permission from the engineer, the
Contractor shall remove all the piping, restore all property to pre-construction condition and
restore all pavement. The Contractor is responsible for obtaining any approvals for
placement of the temporary pipeline within public ways from the City.
END OF SECTION
April, 2001
SECTION TS-6
SANITARY SEWER SYSTEM
-01.
STANDARDS FOR SANITARY SEWER LINES:
A. COVER
1. Minimum cover to finished grade over sanitary sewer shall be four (4)
feet unless otherwise approved by the Augusta Utilities Department.
2. Maximum cover shall be 20 feet unless otherwise approved by the
Augusta Utilities Department.
B. HORIZONTAL SEPARATION
1. Ten (10) feet to water lines and storm sewer lines.
2. Fifteen (15) feet to buildings, top of bank of lakes/streams/creeks,
other structures (10 feet absolute minimum - only when unavoidable,
and pipe material is required to be DIP).
3. Ten (10) feet minimum separation to gas mains.
4. Ten (10) feet minimum to underground electric cable.
5 . All separation distances above are edge to edge.
C. VERTICAL SEPARATION
Eighteen (18) inch minimum separation (edge to edge) between all pipes and
cables shall be maintained (6 inch absolute minimum separation with DIP)
D. LA YOUT
1. The Contractor is responsible for verifying the exact location, size
and material of any existing sewer facility proposed for connection or
use by the project.
2. Individual sewer services shall be a minimum of six (6) inches in
diameter and shall extend from the main and terminate with a clean-
out constructed at the edge of right-of-way. If the main is installed
outside of the right-of-way, the services with clean-outs shall
terminate. at the edge of the permanent easement. Sewer lines
installed parallel to lakes/streams/creeks shall leave a 25-foot
undisturbed buffer along the edge of the bank. The required service
lateral with clean-out shall be inspected by the Augusta Utilities
TS-6-1
April, 2001
Inspector prior to physical tie-in of private service line. The use of
donuts or tying into the stack pipe of the clean-out is strictly
prohibited.
3. Under no circumstances shall house sewer services and water services
be laid in the same trench.
4. A drop manhole shall be provided for a sewer entering a manhole at
an elevation of 24-inches or more above the manhole invert. Where
the difference in elevation between the incoming sewer and the
manhole invert is less than 24-inches, the invert shall be filleted to
prevent solids deposition.
5. Where indicated on the plans, pipe stub-outs for the connection of
future sewers shall be provided during the construction of new
manholes. Each stub-out shall be plugged in the bell end of the stub-
out with plug approved by Augusta Utilities.
E.
SANITARY SEWER MATERIAL
1. Pipe for sanitary sewers shall be polyvinyl chloride (PVC) or ductile
iron pipe (DIP) as outlined below. Standard pipe lengths not greater
than 20 feet shall be used. Force main pipe shall be DIP in
accordance with the "Water Distribution System" Section and
PROTECTO 401 lined.
2. PVC pipe shall be manufactured from virgin resin conforming to
ASTM D-3034 (latest version) with minimum classification of SDR-
35. All ductile iron pipe and fittings shall be delivered to the job with
an internal lining of PROTECTO 401 ceramic epoxy applied in
accordance with the latest published specification for PROTECTO
401. Design methods shall conform to A WW A C ISO/ANSI A21.50
(latest version). DIP shall be Class 350 for 12" and smaller and Class
250 for 14" and larger.
3. All fittings shall be of the same quality and material as the pipe to be
used. Pipe classes shall be determined based upon the installation
and the use intended. Pipe shall be appropriately labeled on the
drawings. WYE fittings shall be utilized. TEE fittings and saddles
shall not be allowed. All DIP fittings shall be ductile iron or cast
Iron.
TS-6-2
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
4.
Aerial pipe shall be mechanical joint DIP or continuous weld,
wrapped and coated steel pipe. Piers shall be placed at every joint
directly behind the belL Site conditions may dictate construction
utilizing more stringent requirements than indicated in the standard
detaiL Anchor collars shall be constructed on the pipe whenever pipe
grade is 20% or greater. Restrainers may be used in lieu of collars
when a particular brand and method are determined equivalent.
a. DIP shall be required in the following circumstances:
1) When sanitary sewer line has less than four (4) feet of
cover. Minimum depth of DIP is two (2) feet.
2) When a sanitary sewer line cross over storm pipe
(Must be one joint of DIP centered on the crossing)
3) When a sanitary sewer line passes laterally within one
(1) foot of a storm sewer line (Must be one joint of
DIP centered on the crossing).
4) When a sanitary sewer line is to have in excess of
eighteen (18) feet of filL
5) When a sanitary sewer line is at the maximum slope
of 20%.
6) For last joint of pipe at all drop manholes greater than
three (3) feet.
7) When a sanitary sewer is less than six (6) feet under
a street.
8) The Utilities Director may mandate DIP in any
instances of off-site or on-site construction where
future abuse to the line is possible due to location or
circumstances, extensive length under pavement, or in
private property away from right-of-way areas.
b. PVC shall be jointed with a rubber gasket and shall conform
to ASTM F477 (latest version) and manufacturer's
recommendations. Solvent weld is prohibited. DIP shall be
of the bell and spigot type with push-on joints conforming to
ANSI A21.11 (latest version) or mechanical joints.
c. Sewer Pipe Bedding:
1) Bedding requirements shall apply to sanitary sewer
lines only. They are to be considered minimum
bedding requirements and as such, do not relieve the
TS-6-3
April, 2001
2)
Contractor of the responsibility to provide any
additional bedding necessary for proper construction.
Bedding shall be carefully placed along the full width
of the trench so that the pipe is true to line and grade
of the pipe barrel. Bell holes shall be provided so as
to relieve pipe bells of all load, but small enough to
ensure that support is provided throughout the length
of pipe. Crushed stone embedment material shall
conform to ASTM C33, Graduation #57 (3/4" to #4).
Bedding material shall be placed underneath and be
carried up the sides of the pipe as specified below.
3)
Class B Bedding shall be performed by first
undercutting the trench an adequate amount to provide
bedding under the pipe bell. The trench shall then be
brought to grade with compacted crushed stone as
specified above for the full width of the trench. The
bedding material shall be placed in the zone four (4)
inches below the pipe and the pipe laid to line and
grade and backfilled with compacted crushed stone
placed the full width of the trench up to one-half the
outside diameter of the pipe. Select backfill placed in
six (6) inch layers and compacted shall be the backfill
from the springline of pipe to 18 inches above the
pipe. A minimum Class B Bedding shall be used for
all plastic pipes.
4)
Class C Bedding shall be performed by first
undercutting the trench an adequate amount to provide
bedding under the pipe bell. The trench shall then be
brought to grade with compacted crushed stone as
specified above for the full width of the trench. The
bedding material shall be placed in the zone four (4)
inches below the pipe and the pipe laid to line and
grade and backfilled with compacted crushed stone
placed the full width of the trench up to one-fourth the
outside diameter of the pipe. Select backfill placed in
six (6) inch layers and compacted shall be the backfill
from the bedding material to 18 inches above the pipe.
A minimum Class C Bedding: shall be used for all
ductile iron pipes.
TS-6-4.
April, 2001
d. Jack and Bore Installations:
1) Casing pipe used with jack and bore shall be in
accordance with requirements of the Georgia
Department of Transportation (GDOT) or railway
specifications.
e. New sewers shall be tied-in to the existing sewers at locations
indicated on the plans. No lines smaller than six (6) inches
shall be tied to a sewer line or manhole. All tie-ins to existing
manholes shall be cored. The Contractor shall be responsible
for maintaining uninterrupted service of the sanitary sewer
during tie-in operations. No connection to existing sanitary
sewer shall be allowed until the proposed sewer line is
inspected and approved by the Augusta Utilities Department's
Inspector.
f.
Side sewers shall be installed where shown on the plans. A
side sewer consists of a sewer extending from a connection to
the street or main sewer to its connection to the house sewer
or other point. For new 8" through 12" diameter sewers, the
side sewer connection shall be constructed with a wye fitting
in the street sewer with a 45-degree elbow. For new 15" and
larger pipes, or existing sewers, the connection shall be made
by machine made tap and suitable saddle, unless otherwise
approved by the Augusta Utilities Department.
Belled pipe shall be laid with the bell end up grade and in
general, all pipe laying shall start and proceed up grade from
the point of connection at the street sewer or other starting
point. Pipe shall be laid in a straight line at a uniform grade
between fittings or on a uniform horizontal or vertical
curvature achieved by deflecting the pipe joints within the
manufacturer's recommended limits. The maximum
deflection permissible at anyone fitting shall not exceed 45
degrees. The maximum deflection of any combination of two
adjacent fittings shall not exceed 45 degrees unless straight
pipe not less than 2 Yz feet in length be installed between such
adjacent fittings or unless one of such fittings is a wye branch
with a clean out provided on the straight leg.
TS-6-5
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
g.
Material for transition (e.g., PVC to DIP) shall be indicated
and specified. Where offset of DIP is required, mechanical
joint DIP shall be installed with mechanical joint heavy body
DIP sleeves at thereconnections.
h.
Sanitary Sewer Manholes:
1) Precast manholes shall conform to the latest edition of
ASTM C-478 (five inch wall thickness). Use six (6)
inch wall thickness if manhole exceeds 20 feet in
depth. All holes for incoming and outgoing pipe will,
whenever possible, be precast, with pipe tie-in made
using PS 10 flexible gasket, manufactured by
PressSeal Gasket Corporation, or approved equal. In
the event of the necessity of cutting new holes, the
holes shall be machined cored neatly and carefully so
as not to damage the structural integrity of the
manhole and large enough to allow the insertion of a
flexible rubber boot. Precast holes shall be flexible
boot fitted.
2) Round manhole bases shall be sized to allow for
proper seat of the pipe to manhole connectors,
conforming to ASTM C923. Minimum round
manhole diameters shall be as follows:
Pipe <24 24"
30" 36" 42" 48" 54"
PVC/DIP 48" 60"
72" 84" 96" 120" 120"
3) Tindall T-Series bases or other approved similar type
alternative base configurations that have been
previously utilized for comparable applications may
be an acceptable alternative to the round bases
specified above for gravity sewer lines.
4) Barrel joints shall be tongue and groove with
performed plastic meeting the requirements of Federal
Specifications SS-S-00210, "Sealing Compound,
Preformed Plastic Pipe Joints" Type I, rope form, also
known as "Ram Neck." Eccentric manholes cones are
TS-6-6
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
I
I
I
April, 2001
required. Inverts shall be constructed of 3,000 psi
plant mix. Manhole steps shall be installed in all
sections of each manhole as indicated on the
drawings. Frame and covers shall be cast or ductile
iron and set in a bed of mortar on the top of the
manhole and completely grouted outside and wiped
smooth. Ring and cover shall be as shown on plans or
approved equal. Cover shall read "Sanitary Sewer."
Bolted, watertight manhole covers are to be used.
5)
The minimum diameter of manholes shall be 48
inches; larger diameters are required for large
diameter sewers. A minimum access diameter of 22-
% inches shall be provided.
6)
Outside drop manholes shall be precast and
constructed for incoming lines having invert 24 inches
or more above the invert of the manhole outlet, with
DIP and tie rods per Augusta Utilities Department
Detail No. 14.08. Shallow manholes shall be precast
or Type B slab top precast and shall be constructed in
accordance with ASTM C-478 (latest version).
7)
Drop manholes should be constructed with an outside
drop connection. Inside drop connection (when
necessary) shall be secure to the interior wall of the
manhole and provide access for cleaning. Inside drop
connections shall be used only when approved by the
Utilities Department Engineering Division.
8)
Due to the unequal earth pressure that may result from
the backfilling operation in the vicinity of the
manhole, the entire outside drop connection shall be
encased in concrete.
9)
A bench shall be provided on each side of any
manhole channel when the pipe diameter(s) are less
than the manhole diameter. The bench should be
sloped no less than lf2 inch per foot (4 percent). No
lateral sewer, service connection, or drop manhole
pipe shall discharge onto the surface of the bench.
TS-6-7
(
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
a) All construction material shall be first quality,
not previously used. Repair clamps are not
acceptable. Damaged or faulty pipe and
materials must be properly replaced. All
gaskets shall be new. When connecting to
existing valves or fittings, gaskets shall be
replaced, not reused.
b) The Contractor shall provide a complete set of
shop drawings, which shall indicate the
Augusta Utilities Department's specific
material requirements. In general, material
requirements will be guided by the latest
versions of the specifications of A WW A and
ASTM.
-02.
CONSTRUCTION:
A. INSTALLATION
Authorization must be obtained from the Augusta Utilities Department to
construct, alter or modify a sanitary sewer line. Construction of sewer
infrastructure will be authorized by the Utilities Department upon approval
of submitted plans and notification of the Augusta Utilities Department at
least 24 hours prior to starting construction (706-772-5503). Where sewer
lines will encroach public right-of-way, a Right-of-Way Encroachment
Permit approved by the Public Works Department is required prior to
construction. ARight -of-Way Encroachment Permit application is available
through the Public Works Depart!llent (706-821-1706).
Installation of sanitary sewer pipe and associated appurtenances shall be in
accordance with current ASTM specifications and manufacturer's
requirements for the specific product. Loading or unloading and storage of
pipe, fittings, valves, etc. shall be done such that to avoid damage. All pipe
shall be carefully examined before it is installed in the trench. Damaged pipe
or pipe which does not meet specification requirements shall be rejected and
removed from the work site. The interior of all pipe, fittings, valves, etc.
shall be kept free of dirt and foreign matter at all times. All piping shall be
placed in a dry trench with a stable bottom. Wet trench installation shall be
allowed only upon written approval of the Utilities Director.
TS-6-8
April, 2001
Backfill shall be free of boulders and debris, and shall conform to Georgia
Department of Transportation Specifications. Sharp or rocky material
encountered in the base shall be replaced with proper bedding. Pipe shall be
laid on line and grade as designed. Pipe joints, gravity blocks, service
connections, and conflicts shall be left exposed until visually inspected and
approved by the Augusta Utilities Department's Inspector.
All concrete cradles, saddles, or encasements shall be installed as shown on
the plans. These structures shall be constructed in strict accordance to the
details shown on the plans. Concrete shall have a 28 day compressive
strength of 3,000 psi when tested in accordance with ASTM Specification C-
39.
All manholes indicated on the plans shall be furnished and installed by the
Contractor in strict accordance with the plans. The invert channels shall be
smooth and accurately shaped to the semicircular bottom conforming to the
inside of the adjacent sewer sections as shown on the plans. Changes in
direction of the sewer and entering branches shall have as long a radius of the
true curvature as the size of the manhole will permit.
The top of manholes shall be topped out with brick as indicated on the plans.
The number of courses will depend on the required elevation of the top of the
manhole. The maximum number of brick courses allowed shall be three (3).
The camera inspection of new sewer lines will not be required, either at
installation or within the warranty period, unless the Owner deems it
necessary for problematic evaluation. For problematic evaluation, the Owner
may request that any amount or all of the new sewer line be inspected, either
during project construction or in the warranty period. The cost of all
requested camera inspections will be incurred by the Contractor. Upon the
Owner's request, sewer lines shall be inspected through the use of camera
inspection equipment with an Augusta Utilities Department inspector present.
The Contractor is to provide the Augusta Utilities Department with a color
VHS system videotape of the inside of every reach of the sanitary sewer
inspected. The tape shall record the manhole number to manhole number,
date of recording, and distance from start of run. The tap shall include a
distance, and location description of every service line. The cost of vacuum
testing each manhole should be included in the unit price for each manhole.
1. Installation:
a. Sewer Pipe Laying: The pipe shall be laid with bell or groove
TS-6-9
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
end upgrade. Pipe shall be tested for soundness, clear interior
and satisfactory joint surfaces before lowering the pipe into
the trench. Pipe shall be laid in straight lines and on uniform
grades between points where changes in alignment or grade
are shown. The pipe barrel shall be uniformly bedded. The
line and invert grade of each pipe shall be checked from a top
line carried on batter boards not over 25 feet apart or by use
of a laser beam target inserted in each joint. Pipes shall be
laid to form a smooth, uniform invert. A stopper shall be
installed in the pipe mouth when pipe laying is not in
progress.
PVC gravity sewer pipe and force main shall be installed in
accordance to ASTM D2321, latest version. Ductile iron
force main shall be installed in accordance with A WW A
C600, latest version.
b.
Backfilling Around Pipe: As soon as the joint material has
set, fine earth shall be carefully tamped around each joint, and
around and over the pipe to a depth of at least 2 feet above the
top of gravity pipelines. In addition, all PVC sewer pipe shall
be bedded in selected material from the pipe centerline down
to a point 3 to 6 inches below the pipe invert. Selected
materials for this purpose shall be Class I or II soils as
specified in ASTM D2321. Reconstruction of any roadway
section or right-of-way shall be in accordance with the
Georgia Department of Transportation and City of Augusta
Specifications.
c.
Sewer Structures: Appurtenant sewer structures shall be
constructed according to one or more of the following
methods:
1) Masonry: Brick for manholes and other sewer
structures shall be laid with shove joints completely
filled with mortar. Horizontal joints shall not exceed
1/2 inch, vertical joints 1/4 inch on their interior face.
In circular structures, all brick shall be laid as header
with joints broken between courses. Interior joints
shall be struck or wiped smooth with the face of the
wall. The exterior of sanitary sewer manholes shall be
plastered to a thickness of at least 1/2 inch.
TS-6-1O
I
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
I
April, 2001
2)
Laying Brick and Concrete Block Work: Only clean
brick or block shall be used. The brick or block shall
be moistened by suitable means, as directed, until they
are neither so dry as to absorb water from the mortar,
nor so wet as to be slippery when laid.
Each brick or block shall be laid in a full bed and joint
of mortar without repairing subsequent grouting,
flushing, or filling, and shall be thoroughly bonded
directed.
3)
Plastering: and Curing Brick or Block Masonry:..
Outside faces of masonry shall be plastered with f
mortar from 1/4 inch to 3/8 inch thick. If required, the: t
masonry shall be properly moistened pnor to.
application of the mortar. The plaster shall be
carefully spread and troweled so that all cracks are
thoroughly worked out. After hardening, the plaster
shall be carefully checked by being tapped for bond
and soundness. Unbonded or unsound plaster shall be
removed and replaced.
Masonry and plaster shall be protected from too rapid
drying by the use of burlap kept moist, or by other
approved means, and shall be protected from the
weather and frost, all as required.
4)
Manhole Inverts: Manhole flow channels shall be
constructed of concrete, sewer pipe, brick or precast,
and shall be of semicircular section. Each manhole
shall be provided with such channels for all
connecting sewers.
The inverts shall conform accurately to the size of the
adjoining pipes. Side inverts shall be curved and
main inverts (where direction changes) shall be laid
out in smooth curves of the longest possible radius
which is tangent to the centerlines of adjoining
sewers.
5)
Drop Manholes: Drop inlets shall be provided into
manholes on sanitary sewers for incoming lines
TS-6-11
I
I
I
I
I
I
I
I
I
I
I
1
I
I
I
I
I
I
I
April, 2001
having inverts 2 feet or more above the inverts of the
manhole outlet lines. Drop pipe and fittings shall be
encased in masonry integral with the manhole and
extending from the manhole base to the top of the
incoming sewer. Diameter of drop manholes to be
four feet at a minimum.
6) Setting: Manhole Frames and Covers: Manhole
frames shall be set with the tops conforming
accurately to the grade of the pavement or finished
concentric with the top of the masonry and in a full
bed of mortar so that the space between the top of the
manhole masonry and the bottom flange of the frame
shall be completely filled and made watertight. A
thick ring of mortar extending to the outer edge of the
masonry shall be placed all around the bottom flange.
The mortar shall be smoothly finished to be flush with
the top of the flange and have a slight slope to shed
water away from the frame. Manhole covers shall be
left in place in the frames on. completion of other
work at the manholes.
7) Setting Precast Manholes Sections: Precast-
reinforced concrete manhole sections shall be set so as
to be vertical and with sections and steps in true
alignment.
All holes in sections, used for their handling, shall be
thoroughly plugged with mortar. The mortar shall be
1 part cement to 1 1/2 parts sand; mixed slightly damp
to the touch until it is dense and an excess of paste
appears on the surface; and then finished smooth and
flush with adjoining surfaces.
d.
Bulkheads and Flushing: The contractor shall build a tight
bulkhead in the pipeline where new work enters an existing
sewer. The bulkhead shall remain in place until its removal
is authorized by the Engineer.
Care shall be taken to prevent earth, water and other materials
from entering the pipe, and when pipe laying operations are
suspended, the Contractor shall maintain a suitable stopper in
TS-6-12
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
the end of the pipe and also at openings for manholes. All
sanitary sewer, except building connections shall be flushed
with water in sufficient volume to obtain free flow through
each line. All obstructions shall be removed and all defects
corrected. As soon as possible after the pipe and manholes
are completed on any line, the Contractor shall flush out the
pipeline using a rubber ball ahead of the water. None of the
flushing water or debris shall be permitted to enter any
existing sewer.
e.
Temporary Plugs: At all times when pipe laying is not
actually in progress, the open ends of the pipe shall be closed
by temporary watertight plugs or by other approved means.
If water is in the trench when work is resumed, the plug shall
not be removed until all danger of water entering the pipe has
passed.
f.
Joints and Structure Rightness: All pipe joints shall be made
as nearly watertight as practicable. There shall be no visible
leakage at the joints and there shall be no sand, silt, clay, or
soil of any description entering the pipelines at the joints.
Leaks in the pipelines which cause infiltration or exfiltration
to exceed limits herein specified shall be repaired by
replacing defective pipe. Grouting and/or caulking to repair
pipelines where excessive infiltration or exfiltration is evident
will not be permitted.
g.
Fittings and Stoppers: Branches and fittings shall be laid by
the Contractor as indicated on the drawings and/or as directed
by the Engineer. Open ends of pipe and branches shall be
closed with premolded gasket joint stoppers which conform
with the same requirements as pipe being used.
h.
Sewer Line Relation to Water Lines: Sewer lines and sewer
force mains in relation to water lines shall conform to "Ten
States Standard" Section 29.3 at a minimum. Sewer lines
shall have at least ala foot pipe-to-pipe horizontal separation
from known or proposed water mains. When a sewer crosses
under a water main, there shall be at least 18 inches from the
crown of the sewer line to the bottom of the water main.
TS-6-13
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
In all cases where adequate vertical separation as stated above
cannot be achieved (or whenever sewer lines must be installed
to cross above a water main), both the water and sewer lines
shall be constructed of ductile iron pipe a distance of 10 feet
on each side of their intersection with one full length of water
main centered on the sewer line.
1.
Minimum Cover for Sewer Lines: Gravity sewer lines shall
have a minimum of 4 feet of cover at the crown of the pipe.
In cases where this minimum cover cannot be achieved,
ductile iron pipe shall be used.
J.
Boring and Jacking: Where required by the drawings, the
sanitary sewer line will be installed in a steel casing, placed
by boring and jacking.
Where boring is required under highways, the materials and
workmanship will be in accordance with the standards of the
Georgia Department of Transportation or local authority.
Boring and jacking under railroads will be governed by the
latest A.R.E.A. Standards, Part 5, "Pipelines" and those of the
railroad involved.
1) Casing Pipe: The casing pipe shall conform to the
materials standards of ASTM Designation A252, with
minimum wall thickness of 0.219 inch. Steel pipe
will have a minimum yield strength of 35,000 psi.
Casing pipe shall be joined together with welded
joints.
2) Carrier Pipe: The carrier pipe shall be ductile iron as
specified herein.
3) Installation: The steel casing shall be installed by the
"Dry Bore and Jack" method. If voids develop or if
the bored hole diameter is greater than the outside
diameter of pipe by more than approximately 1 inch,
remedial measures will be taken as approved by the
Engineer.
TS-6-14
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
When installing water lines through casing, the
Contractor shall mechanical joint pipe with retainer
glands throughout the length of the casing. The
sanitary sewer line shall be strapped to treated wooden
skids with metal straps throughout the length of the
casing. The empty space shall then be filled with sand
and the ends of the casing shall be sealed with brick
and mortar.
k. Force Main Installation: In general, sewer force main must be
installed in accordance with the water distribution system
specifications.
Polyvinyl chloride (PVC) force main must conform to ASTM
D-2241, latest version.
Ductile iron force main must conform to ASTM A-377, latest
version.
1. Removal and Replacement of Existing Pipe and Equipment:
where indicated on the drawings or required to properly place
the work under this contract, as approved by the Engineer, the
Contractor shall remove and replace such pipe lines and
equipment in a manner as approved by the Engineer.
2.
SEWER LINE AND MANHOLE TESTING:
a. Sewer Lines:
Upon completion of a section of the sewer, the Contractor
shall dewater it and conduct a satisfactory test to measure the
infiltration or exfiltration for at least three consecutive days.
The amount of infiltration including "Y" branches, and
connections shall not exceed 1 00 gallons per inch diameter
per mile of sewer pipe per 24 hours for gravity sewer pipe.
The amount of 50 gallons per inch diameter per mile of sewer
per 24 hours shall not be exceeded for ductile iron pipe. The
Contractor shall be responsible for the satisfactory
watertightness of the entire section of sewer.
The sewer shall be tested before any connections are made to
buildings or to active sewers.
TS-6-15
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
I
April, 2001
The Contractor shall use a low pressure air test as the
hydraulic infiltration/exfiltration leakage test for gravity lines
and provided a correlation between the air test results and the
quantity of infiltration/exfiltration actually being experienced
by the line and the allowable air pressure drop shall be that
corresponding to the allowable hydraulic leakage specified
previously in this section. Such a correlation is to be
established according to a procedure satisfactory to the
Engineer. The low pressure air test shall be performed in
accordance with the applicable sections of the Uni-Bell UNI-
B-6-98, latest version.
b. Vacuum Testing Manholes:
All manholes shall be free of visible leakage and shall successfully
complete a vacuum test prior to acceptance.
Plugging all inlets and outlets: Plug all inlets and outlets, excluding
the manhole top access, using pneumatic or mechanical plugs. Plugs
shall be rated for the pressure required in the test. The Engineer or
Authorized Engineers representative shall be notified at least 48 hours
before tests are conducted.
Testing Equipment and Procedure: Contractor is to furnish all
necessary testing equipment and perform tests in a manner
satisfactory to the Engineer. Provide an arrangement of testing
equipment which will provide observable and accurate measurements
of air leakage under specified conditions. Gauges for the vacuum
testing shall be calibrated with a standardized testing gauge prior to
testing. The calibration shall either be witnessed by the Engineer or
Certified as being calibrated by licensed calibration technician.
After all of the plugs are in place and securely blocked, install the
manhole tester on the ring of the manhole and attach the vacuum
pump assembly suction hose to the manhole tester. Start the vacuum
pump and allow the pre-set rpm to stabilize. Open the inlet/outlet
valve and allow the vacuum pump to evacuate the manhole to five
pounds per square inch (5 psigv) or (10 inches Hg). Close the
inlet/outlet valve and monitor the vacuum for the test period specified
on the following table. The manhole will be considered acceptable
if the vacuum drops less than one half per square inch (0.5 psigv) or
(1 inch Hg) within the given test time.
TS-6-16
END OF SECTION
April, 2001
DEPTH TIME TIME TIME TIME
FEET SECONDS SECONDS SECONDS SECONDS
48-inch diam. 6O-inch diam. 72-inch diam. 120-inch diam.
8 20 26 33 65
10 25 33 41 79
12 30 39 49 93
14 35 46 57 107
16 40 52 65 121
18 45 59 73 135
20 50 65 81 149
22 55 72 89 163
24 59 78 97 177
26 64 85 105 191
28 69 91 113 205
30 74 98 121 219
Time of Testing: The vacuum test shall be conducted after all the
pipes and manholes have been backfilled, all final grading is
complete, and the base layer of asphalt has been spread.
Repairs: Repair or replace and retest, in a manner approved by the
Engineer, any manhole not meeting the vacuum test requirements, at
no cost to the Owner.
Subsequent Failure: Infiltration of groundwater, following a
successful vacuum test as specified, should be considered good
evidence that the original test was in error or that subsequent failure
of the manhole has occurred. The Contractor will correct such
failures in a manner approved by the Engineer and at no cost to the
Owner should this occur within the I-year warranty period.
TS-6-17
SECTION TS-7
GRADED AGGREGATE BASE COURSE
-01. SCOPE:
This section covers a graded aggregate base course to receive bituminous paving
under another section, complete.
-02. GENERAL SPECIFICATIONS:
The graded aggregate base course shall conform" to all applicable specifications of
Section 300 of the Standard Specifications for Roads and Bridges of the Georgia State Department
of Transportation, Latest Edition.
-03. PREPARATION OF SUBGRADE:
The sub grade to receive the graded aggregate base course shall be constructed in
accordance with requirements of Section 209 of the Standard Specifications for Roads and Bridges
of the Georgia State Department of Transportation.
-04. MATERIALS & CONSTRUCTION FOR BASE COURSE:
Materials and construction for the graded aggregate base course shall be in accordance with Section
310 of the Standard Specifications for Roads and Bridges of the Georgia State Department of
Transportation.
END OF SECTION
TS- 7-1
SECTION TS-8
BITUMINOUS PAVING
-01.
SCOPE:
This section covers the replacement of pavement for sewer line cuts in roads and
driveways, complete and asphalt overlay of existing roadways.
-02.
GENERAL:
After installation of the sanitary sewer lines and compaction requirements are met,
10" of graded aggregate base shall be installed and compacted in accordance with Section TS-7.
The top 2" of the graded aggregate base material shall be removed and replaced with Type "B"
asphalt binder upon installation of the asphalt cap. A 1-112" overlay of Type "F" asphalt will be
applied for a 50' width along transverse cuts and for the width of street in longitudinal cuts.
Asphalt driveway patches will be 2 inches thickon compacted subgrade. This also
applies to cuts through asphalt valley gutters.
-03.
SEASONAL LIMIT A TIONS:
No bituminous mixtures shall be applied for surface treatment between October 21 st
and April 10th, except as directed by the Engineer.
-04.
WEA THER LIMITATIONS:
Bituminous mixtures shall not be produced or placed during rainy weather, when the
sub grade or base course is frozen or shows any evidence of excess moisture nor when the moisture
on the surface to be paved would prevent proper bond nor when the air temperature is less than 45
degrees F. in the shade away from artificial heat.
-05.
APPLICABLE SPECIFICATIONS:
All work and materials required under this section of the specifications shall conform
to the applicable sections of the Standard Specifications of the Augusta Utilities Department
-06.
SUB GRADE:
The sub grade shall be prepared as specified under the sections of the above
specifications covering sub grade preparation.
-07.
SURFACE COURSE:
1. ASPHALT CONCRETE: The asphalt concrete mixture shall conform to the Georgia
Department of Transportation, Standard Specifications for Highway Construction, for Type
B asphalt binder for pavement patches and Type F asphalt concrete for pavement overlays.
The job mix shall be approved by the engineer and no material shall be used until approved.
2. TRANSPORTATION AND DELIVERY: The mixture shall be transported from the mixing
plant to the point of use in approved vehicles. Loads shall not be of such size or weight as
TS-8-1
TS-8-2
to interfere with the efficient operation of the spreader. Loads shall not be sent out so late
in the day as to prevent the completion of spreading and compaction of the mixture during
daylight, unless artificial light is provided. The mixture shall be delivered at a temperature
between 225 degrees F. and 325 degrees F. and within 20 degrees F. of temperature set at the
mixing plant.
3. SPREADING: Upon arrival at the point of dumping, the mixture shall be dumped into the
hopper and spread by mechanical pavers, true to line, grade and cross section specified and
to the loose depth that will secure the required compacted thickness of 1-1/2 inches. The hot
mixture shall be free from lumps and shall be spread while it is in a workable condition.
After the mixture has been screeded and before roller compaction is started, the surface shall
be checked, all fat spots and irregular areas removed and replaced with satisfactory material.
All irregularities in alignment and grade along the outside edge shall also be corrected by the
addition or removal of mixture before the edge is rolled.
4. COMPACTION: While the mixture is hot, it shall be compacted thoroughly and uniformly
by rolling. The surface of the compacted mixture shall be smooth, and true to crown and
grade. Any mixture that becomes loose or broken, mixed with dirt, or is in any way
defective, shall be removed and replaced with fresh hot mixture which shall be immediately
compacted to conform to the surrounding area. Any area showing an excess of bituminous
materials shall be removed and replaced, and the edges shall be kept to a reasonable straight
line and trimmed.
The density after compaction shall be at least 98 percent of the laboratory-determined
density.
5. PROTECTION OF PAVEMENT: The newly finished pavement shall be protected from
vehicular traffic of any kind until the pavement has cooled and hardened and in no case less
than 6 hours.
6. TOLERANCE: The finished surface shall not vary more than 1fa inch in 10 feet from the true
profile and cross section.
-10.
TESTS:
The above work will be subject to thickness and compaction tests as deemed
necessary by the Engineer. Such tests will be at the expense of the Contractor.
END OF SECTION
SECTION TS-9
CURBS AND GUTTERS, CONCRETE
-01.
SCOPE:
This section covers construction of Portland cement concrete curbs and gutters,
complete.
-02.
CONCRETE:
Concrete and the equipment, workmanship and materials therefor shall conform to
the applicable requirements of the CONCRETE CONSTRUCTION section, except as hereinafter
specified. The maximum size of coarse aggregate shall be 1 Y2 inches and not less than 1 inch.
Concrete shall have a slump of nor more than 3 inches. The concrete mixtures shall have an air
content by volume of 4.5 percent, plus or minus 1.5 percent, based on measurement made on
concrete immediately after discharge from the mixer.
-03.
SUB GRADE PREPARATIONS:
The sub grade shall be constructed true to grade and cross section. The sub grade shall
be of materials equal in bearing quality to the sub grade under the adjacent roadway or street and shall
be placed and compacted to conform with applicable requirements of the specifications entitled
"Sand-Clay Base Course" with the following modifications. The sub grade for curb and gutter shall
extend in all cases at least 1 foot in width back of the curb or gutter or valley pavement. The
sub grade shall be tested for grade and cross section by means of a template extending the full width
of the curb, gutter, or combination curb and gutter. The sub grade shall be maintained in a smooth,
compacted condition, in conformity with the required section and established grade until the concrete
is placed. In cold weather, the sub grade shall be prepared and protected so as to produce a subgrade
free from frost when the concrete is deposited.
-04.
FORMS:
Forms shall be of wood or steel, straight, and of sufficient strength to resist springing
during depositing and consolidating the concrete. The outside forms shall have a height equal to the
full depth of the curb or gutter. The inside form of curb shall have better as indicated and shall be
securely fastened to and supported by the outside form. Straight forms of wood shall be 2 inch
nominal surface plank, and of steel, shall be of approved section with a flat surface at the top.
Rigid forms shall be provided for curb returns except that benders or thin plank forms
may be used for curb or curb returns with a radius of 10 feet or more, when grade changes occur in
the return, or where the central angle is such that a rigid form with a central angle of 90 degrees
cannot be used. Back forms for curb may be made of Yz inch benders, for the full height of the curb,
cleated together. Curb forms shall be carefully set to alignment and grade and to conform to the
dimensions of the curb. Forms shall be held rigidly in place by the use of stakes placed at intervals
not to exceed 4 feet. Clamps, spreaders, and braces shall be used where required to insure rigidity
in the forms. The forms on the front of the curb shall be removed not less than 2 hours nor more
than 6 hours after the concrete has been placed. Forms back of curb shall remain inplace until the
face and top of the curb have been finished as specified in the Finishing paragraph. Gutter forms
shall not be removed for 12 hours after the concrete has been placed. Forms shall not be removed
while the concrete is sufficiently plastic to slump in any direction. Forms shall be cleaned and
TS-9-1
TS-9-2
coated with form oil each time before concrete is placed. Wood forms may, instead, be thoroughly
wetted with water before concrete is placed, except that with probable freezing temperatures, oiling
is mandatory.
-05.
.TOINTS:
Expansion joints and contraction joints shall be constructed at right angles to the line
of curb, gutter, and combination curb and gutter. Dowels, tie-bars and reinforcement when required
will be shown on the plans and shall be installed in accordance with the applicable details.
1. CONTRACTION JOINTS: Contractionjoints shall be constructed by mean so Va inch thick
separators, of a section conforming to the cross section of the curb, gutter, entrance
pavements, and combination curb and gutter. Contraction joints shall be so placed that
monolithic sections between curb returns will not be less than 5 feet nor greater than 15 feet
after the concrete has set sufficiently to preserve the width and shape of the joint. After
separator plates have been removed, all exposed edges of joints shall be rounded with the
proper edging tool to a radius of 14 inch.
2. EXPANSION JOINTS: Expansionjoints shall be formed by means of preformed expansion
joint filler material cut and shaped to the cross section of the curb, gutter, entrance, and
combination curb and gutter.
Expansion joint filler, unless otherwise specified, shall conform to ASTM Standard D 1751-
60 or D1752-60 or shall be resin-impregnated fiberboard conforming to the physical
requirements of ASTM Standard C1752-60. Expansionjoints shall be provided in curb and
combination curb and gutter at the ends of all returns. Expansion joints at least Y2 inch in
width shall be provided at intervals not exceeding 50 feet. Expansion joints shall be
provided in nonreinforced concrete gutter at the locations indicated.
-06.
CONSTRUCTION:
1. CURBS AND GUTTERS: Curbs, gutters and combination curb and gutters shall be of the
dimensions and sections shown on the drawings.
2. RECONSTRUCTION: Where the plans provide for reconstruction of existing curb,
combination curb and gutter and the limit of new work specified does not fall on a joint, the
entire section shall be removed and the new curb, combination curb and gutter or entrance
pavement shall join the old curb at the first join line beyond the specified limit.
3. PLACING CONCRETE: The faces and adjacent edges of abutting rigid pavements and
structures shall be painted with an approved bituminous material prior to placing concrete.
Concrete shall be placed in the forms to the specified depth in 6 inch layers and thoroughly
consolidated by tamping and spading to that there are no rock pockets at forms, and mortar
entirely covers the top surfaces. Concrete may be compacted by means of mechanical
vibrators.
4. FINISHING: The edges of the gutter and top of the curb shall be rounded with an edging
tool to a radius of 14 inch and the surfaces shall be floated and finished with a smooth wood
float until true to grade and section and uniform in texture. The floated surfaces shall then
be brushed with a fine-hair brush with longitudinal strokes. Immediately after removing the
front curb form, the face of the curb shall be rubbed with a wood or concrete rubbing block
TS-9- 3
and water until blemishes, form marks, and tool marks have been removed. The surface,
while still wet, shall be brushed in the same manner as the gutter and curb top. The top
surface of gutter and entrance shall be finished to grade with a wood float. Except at grade
changes or curves, the finished surfaces shall not vary, from the testing edge of a 10 foot
straightedge, more than 1fe inch for gutter and entrance and 1,4 inch for top and face of curb.
Irregularities exceeding the above shall be satisfactorily corrected. Visible surfaces and
edges of the finished curb, gutter, and combination curb and gutter shall be free of blemishes
and form and tool marks, and shall be uniform in color, shape, and appearance.
5. CURB FORMING MACHINES: Use of curb-fOI;ming machines for constructing curb and
gutter will be approved based on trial use on the job. Use of the equipment shall be
discontinued at any time during the construction if the equipment produces unsatisfactory
results, and the work shall be removed and reconstructed for the full length between regularly
scheduled joints. Removed portions shall be disposed of as directed.
-07.
CURING AND PROTECTION:
1. CURING: Immediately after the finishing operations, the exposed concrete surfaces shall
be cured by one of the following methods as the Contractor may elect:
A. Mat Method: The entire exposed surface shall be covered with cotton mats
conforming to Federal Specification CCC-C-467b having a combined weight of 14
ounces or more per square yard when dry. Mats shall overlap each other at least 6
inches. The mat shall be thoroughly wetted with water prior to placing on the
concrete surface and shall be kept continuously in a saturated condition and in
intimate contact with concrete for not less than seven days.
B. Impervious-Sheeting: Method: The entire exposed surface shall be wetted with a fine
spray of water and then covered with waterproof paper conforming to ASTM
Standard C171-63, or with wetted polyethylene-coated burlap or polyethylene
sheeting conforming to the water-retention requirements of ASTM Standard C171-
63, polyethylene sheeting and polyethylene film bonded to burlap shall be not less
than 0.004 inch thick.
Sheets shall be laid directly on the concrete surface with a light-colored side up and
overlapped 12 inches when a continuous sheet is not used. The curing medium shall
not be less than 18 inches wider than the concrete surface to be cured and shall be
securely weighted down by placing a bank of moist earth on the edges just outside
the forms and over the transverse laps of form closed joints. Sheets shall be
satisfactorily repaired or replaced if damaged during curing. The curing medium
shall remain on the concrete surface to be cured for not less than seven days.
C. Membrane-Curing: Method: The entire exposed surfaces shall be covered with a
pigmented membrane-forming curing compound. The curing compound shall be
applied in two coats by hand-operated pressure sprayers at the coverage of
approximately 200 square feet per gallon for both coats. The second coat shall be
applied in the direction approximately at right angles to the direction of application
of the first coat. The compound shall form a uniform continuous coherent film that
will not check, crack, or peel and shall be free from pin-holes or other imperfections.
Concrete surfaces that are subjected to heavy rainfall within three hours after the during compound has been applied shall be resprayed by the method and at the
TS-9-4
coverage specified above at no additional cost to the Owner. Joint openings shall be
sealed at the top by inserting moistened paper or fiber rope or covering with strips of
waterproof paper prior to application of the curing compound, in a manner to prevent
the curing compound from entering the joint. Concrete surfaces to which membrane-
curing compounds have been applied shall be adequately protected for seven days
from pedestrian and vehicular traffic and from any other action which might disrupt
the continuity of the membrane. Any area covered with curing compound and
damaged by subsequent construction operations within the seven-day period shall be
resprayed as specified above at no additional expense to the Owner.
2. PROTECTION: After curing, debris shall be removed and the backfill shall be placed as
indicated. The completed curb, gutter, and combination curb and gutter shall be protected
from damage until accepted. The Contractor shall repair damaged concrete and clean
concrete discolored during construction. Curb, gutter, and combination curb and gutter that
are damaged shall be removed and reconstructed for the entire length between regularly
scheduled joints, not by refinishing the damaged portion. Removed damaged portions shall
be disposed of as directed.
-08.
SEALING .TOINTS:
The sealing of expansion joints in curb and gutter sections will not be required. Any
expansion joint material protruding after the concrete is cured shall be trimmed flush with the
surface. Expansion joints in the valley pavement shall be sealed with an approved joint sealer,
conforming to Federal Specification SS-S-164. The joint opening shall be thoroughly cleaned of all
foreign material before the sealing material is placed. The sealing shall be done in such manner that
the material will not be spilled on the exposed surfaces of the concrete. Any excess material on the
exposed surfaces of the concrete shall be removed immediately and the exposed concrete surfaces
cleaned.
END OF SECTION
SECTION TS-lO
CONCRETE CONSTRUCTION
-01.
SCOPE:
This section covers concrete construction, complete, including reinforcement thereof.
-02.
FORMS:
Forms shall be of wood, metal, structural hardboard or other suitable material that
will produce the required surface finish. Forms placed for successive pours for continuous surfaces
shall be fitted to accurate alignment to assure a smooth completed surface free from irregularities,
and shall be sufficiently tight to prevent the loss of mortar. No forms shall be left permanently in
place without approval of the Engineer. Holes resulting from removal of form ties shall be filled
solid within 12 hours after removal of forms with cement mortar.
-03.
REINFORCING AND EMBEDDED METALS:
Bar reinforcement shall be intermediate grade new billet steel conforming to the
requirements of the ASTM Designation A15. All bars 3fa inch and larger shall be deformed bars
conforming to ASTM Designation A305. Detailing, fabrication and tagging of reinforcement shall
be done in accordance with ACI "Manual of Standard Practice for Detailing Reinforced Concrete
Structures" (ACI 315), except that where longer laps are indicated on the design drawings, the
drawings shall govern. Wire fabric reinforcement shall consist of steel wire conforming to the
requirements of ASTM Designation A185. Anchor bolts and structural shapes shall conform to
ASTM Designation A36. Exposed surfaces of embedded steel shall be given one shop coat of Red
Lead Iron Oxide conforming for Federal Specification IT -P-86c, Type IT, unless otherwise noted on
the drawings. Anchor bolts and miscellaneous steel items to be embedded in concrete shall be
accurately placed in accordance with the drawings, and adequately secured in position to prevent
dislodgement during concrete placing operations. Anchor bolts shall be protected after concrete has
been placed and set by daubing with grease, wrapping with burlap, and covering bolts with wooden
boxes.
-04.
CONCRETE:
All concrete shall be equivalent to ready mix concrete manufactured and delivered
in accordance with the requirements of ASTM Designation C94 and having a compressive strength
at 28 days of 3,000 psi, except as noted herein. The concrete manufacturer shall assume the
responsibility of the design of the concrete mix in accordance with Alternate No.2 of ASTM C94.
Air entrained concrete shall be used for all concrete.
TS-1O-1
Slabs on grade
Footings
All others
Max. 4", Min. 3"
Max. 5", Min. 3"
Max. 6", Min. 3"
1. MATERIALS:
A. Cement: Cement shall be Type I or IA "Portland" cement, all one manufacturer,
conforming to ASTM, C150 or ASTM C175, respectively.
B. Aggregates: Aggregates shall conform to ASTM C33. Coarse aggregate shall be
crushed rock or gravel and graded from % inch to number 4 sieve for mass or
foundation concrete. Fine aggregate shall be natural sand.
c. Water: Mixing water shall be proportioned so that slump when measured with
standard slump cone does not exceed the following:
D. Joint Filler Strips: Premolded joint filler strips shall be resilient compressive,
bituminous and fiber materials saturated with at least 35 percent and not over 50
percent by weight of asphalt. Poured type joint composition for expansion joints
shall be elastic compound made up of asphalt and colloidal mineral fillers.
2. PLACING CONCRETE: Runways for wheeled equipment shall be provided to convey
concrete. Runways shall not be supported on the reinforcement. Concrete shall be placed
and compacted in layers not over 24 inches deep. Vibrators may be used provided they are
used under experienced supervision and the mixture is dry enough to prevent segregation.
Form vibrators shall not be used. Vibration shall not be used for transporting or moving
concrete inside forms. No more concrete shall be placed than can be consolidated and
finished the same day as placed. Free fall of concrete shall be limited so that no segregation
of materials occurs.
3. JOINTS: Construction joints not indicated on drawings shall be approved by the Engineer
in advance of pour. Joints in foundation walls shall be keyed. Before depositing the concrete
is resumed, the hardened surface shall be roughened, cleaned of foreign matter and
thoroughly wetted but not saturated. The cleaned and wetted surfaces shall be slushed with
a coating of neat cement grout against which the new concrete shall be placed before the
grout has attained its set.
4. FINISHING: After stripping forms, all voids and honeycombs shall be patched by chipping
and scarifying the defective areas and treating it with an approved bonding agent. All such
voids shall be patched, not merely plastered. Grout mixture shall consist of one part Portland
cement and one part sand. Immediately following removal of forms, all fins and irregular
projections shall be removed from all surfaces except from those which are not to be exposed
or waterproofed. Slabs shall be struck-off and consolidated by approved machine or hand
methods, screeding and tamping concrete so that upon completion, the surface shall be true
to grade as shown on drawings and free of surface voids. All floors shall have a monolithic
steel trowel finish unless otherwise indicated on the drawings. Exterior walls shall be
compacted, screeded and floated to a true even surface with wood floats and then broomed.
END OF SECTION
TS-1O-2
-01.
A.
-02.
-03.
SECTION TS-ll
GRASSING (BERMUDA)
GENERAL:
DESCRIPTION
1. This section covers the furnishing of all labor and materials and the
performance.of all work required to assure the establishment of a temporary
cover of grass where required on all disturbed areas of the site not intended
for paving, and a dense permanent cover of grass on all disturbed areas of the
site owned by the City of Augusta which are not intended for paving.
PRODUCTS:
A.
MATERIALS
1. The following material shall be as specified by the "Standard Specifications,"
published by the State Department of Transportation of Georgia, latest
edition.
Agriculture Lime ................................. Article 882.02
Fertilizer ....................................... Article 891.01
Sod ........................................... Article 890.03
Seed ........................................... Article 890.01
EXECUTION:
A.
CONSTRUCTION
1. GROUND PREPARATION: Final grades shall be as existed prior to
construction. Washes, low spots and hillocks or windrows will be evened
and the bed will be smoothed to facilitate uniform drainage after
establishment of the turf. Graded surfaces will be maintained in a smooth
and even condition until the required cover is established.
2. After the areas to be grassed have been brought to an even and smooth grade,
they shall be thoroughly loosened to a depth of at least 6 inches by plowing,
discing, harrowing, or other approved methods until the tillage is acceptable
as suitable for planting. During tillage operation, the surface shall be cleared
of all roots, cable, wire, or other waste material which might hinder final
grading, planting, or subsequent maintenance operations. Any operations of
the Contractor, shall be smoothed our before grassing operations are begun.
TS-ll-l
3. APPLICATION OF FERTILIZER AND LIME: Fertilizer shall be distributed
uniformly at a rate of 1500 pounds per acre of commercial 6-12-12 analysis
fertilizer, and shall be incorporated into the soil to a depth of approximately
3 inches by discing, harrowing, or other approved methods. The
incorporation of fertilizer may be a part of the tillage operation specified
above, or a part of the hydro seeding procedure as described below.
4. Immediately following, or simultaneously with, the incorporation of fertilizer,
lime shall be distributed at the rate of 3000 pounds per acre, and shall be
incorporated into the soil to a depth of at least three inches by discing,
harrowing, or other acceptable methods. The incorporation of lime along
with the fertilizer may form a part of the tillage operation specified above.
5 . Not less than 30 days after completion of seeding, the Contractor shall furnish
and apply Nitrate of Soda or Ammonium Sulphate to the planted areas.
Nitrate of Soda shall be a commercial product, containing not less than 16
percent Nitrogen and Ammonium Sulphate not less than 20 percent Nitrogen.
The Nitrogen fertilizer shall be uniformly spread and distributed with
approved equipment at a rate that will give not less than 60 pounds of
available Nitrogen per acre. Other commercial types of nitrogenous material
may be substituted at the option of the Contractor. The time of application
shall be limited to the season of June through August.
B.
PERMANENT SEEDING
1. November 1 - February 1, a mixture of Unhulled Common Bermuda 6
lbs.lacre and rye grass seed 28 lbs.lacre applied simultaneously. Pasture rye
will not be permitted.
2. February 15 - July 1, Hulled Common Bermuda 10 lbs.lacre.
3. Seed may be applied by means of a hydro-seeder or other means approved by
the Engineer.
4. Immediately after seeding operations have been completed, the areas shall be
compacted by means of a cultipacker, roller wood float, or other approved
equipment sufficiently weighted, or compacted by hand methods, to reduce
air pockets to a minimum. The complete planted area shall be left with a
firm, even surface, free from abrupt humps and hollows, and to the
established grade.
5. All areas seeded for temporary or permanent grass shall be uniformly
mulched with hay or straw at the rate of 2 Y2 tons per acre, except where
hydro seeding is employed using a cellulose mulch mixed with the seed and
fertilizer.
TS-1l-2
TS-II-3
C. TEMPORARY GRASS: Temporary grass shall be used when directed by the
Engineer to control erosion where permanent grassing cannot be planted.
1. Temporary grass shall be a quick growing species such as rye grass suitable
to the area and season. Pasture rye will not be permitted. Seeding shall be
done in accordance with the permanent grassing requirements above, except
that ground preparation shall be the minimum required to provide a seed bed
where further grading will be required. Areas that require no further grading
shall be prepared as described in "GROUND PREP ARA TION" above. Lime
shall be omitted unless the area will later be planted in permanent grass
without further grading, in which case lime shall be applied as described
above. Fertilizer shall be applied at the rate of 400 pounds per acre. Nitrogen
shall be omitted.
2. In March or April of the following year, as soon as weather is suitable, all
areas planted in temporary grass which are owned by the City of Augusta
shall be thoroughly plowed up and grassed in accordance with the applicable
permanent grassing method described above.
3. MAINTENANCE: The Contractor shall erect necessary warning signs and
barriers, mow grassed areas, and repair or replace grassed areas failing to
show a uniform growth of grass or damaged by his operations, and shall
otherwise maintain the grass until final acceptance of the contract.
Replacement of dried out or damaged grass shall be at the Contractor's
expense.
D. ACCEPTANCE
1. Grassed areas will be accepted when a 95% cover by permanent grasses is
obtained and weeds are not dominant.
2. The work may be accepted in whole or in part as determined by the Engineer
and the Owner.
END OF SECTION
I
I
I
I
I
I
I
I
I
I
I
I
I"
I
I
I
I
I
I
SECTION TS-12
EROSION, SEDIMENTATION & POLLUTION CONTROL MEASURES
-01.
GENERAL:
This section covers erosion, sedimentation and storm water pollution control
measures as shown on the plan or required on the job and are intended to comply with the
requirements of the Georgia Environmental Protection Division's General Permit No. GAR 100002,
latest edition. For the purpose of this project and as referenced in the General Permit, the Owner and
the Contractor are considered the "Primary Permittee," and the Contractor and all his subcontractors
shall be considered the "Operator."
The measures shown on the plans and specified herein are minimum requirements
and may be augmented by the Engineer if positive control is not established for storm magnitudes
up to and including a 25 year rainfall event. These specifications and the corresponding plans do
not, in any way, relieve the Contractor of any obligations with respect to permits for wetlands, storm
water, stream buffers, flood plains or any other local, state or federal requirements.
-02.
CONSTRUCTION SCHEDULE:
The construction schedule is as shown on the Erosion, Sedimentation and Pollution
Control Plan.
-03.
DEFINITIONS:
All terms used in this section shall be interpreted in accordance with the definitions
set forth in the General Permit, some of which are restated as follows:
A. "Best Management Practices (BMP' s)" means schedule of activities, prohibitions of
practices, maintenance procedures and other management practices to prevent or
reduce the pollution of waters of the state. BMP's also include treatment
requirements, operating procedures and practices to control site runoff, spillage or
leaks, sludge or waste disposal or drainage from raw material storage.
B. "Buffer" means the area of land immediately adjacent to the banks of state waters in
its natural state of vegetation, which facilitates the protection of water quality and
aquatic habitat.
C. "Construction Activity" means the disturbance of soils associated with clearing,
grading, excavating, filling of land or other similar activities which may result in soil
erOSIOn.
D. "Final Stabilization" means that all soil disturbing activities on the site have been
completed and that unpaved areas have a minimum of 95% uniform coverage by
permanent vegetation or equivalent permanent stabilization measures such as riprap,
gabions or permanent geotextiles have been employed.
TS-12-1
TS-12-2
E.
"Grading" means altering ground surfaces to specified elevations, dimensions and/or
slopes; this includes stripping, cutting, filling, stockpiling and shaping or any
combination thereof.
F.
"Qualified Personnel" means a person who has successfully completed an erosion
and sediment control short course or an equivalent course approved by the
Environmental Protection Division (EPD) and the State Soil and Water Conservation
Commission.
G.
"Waters of the State" means any and all rivers, streams, creeks branches, lakes,
reservoirs, ponds, drainage systems, springs wells, wetlands and all other bodies of
surface or subsurface water, natural or artificial, lying within or forming a part of the
boundaries of the State which are not entirely confined and retained completely upon
the property of a single individual, partnership or corporation.
-04.
GENERAL PROCEDURES:
The Contractor shall utilize, at a minimum, Best Management Practices, including
sound construction practices to prevent and minimize erosion and resultant sedimentation, which are
consistent with and no less stringent than those practices contained in the "Manual for Erosion and
Sediment Control in Georgia," published by the State Soil and Water Conservation Commission as
of January 1 ofthe year in which the land disturbing activity was permitted, as well as the following:
A. Stripping of vegetation, grading and other development activities shall be conducted
in such a manner as to minimize erosion. Earth areas which are not to be paved shall
be grassed at the earliest possible time during the construction phase, so as to
minimize exposure to rainfall and run-off.
B. Unnecessary cut and fill operations shall be kept to a rmmmum, except that
temporary berms, wherever possible, should be constructed at the end of each day of
grading, in order to contain sediment and slow down erosion, should rainfall occur
during the night. Berms shall also be constructed, where needed, to prevent sediment
from being transported onto areas outside the actual construction limits.
C. Whenever feasible, existing natural vegetation shall be retained, protected and
supplemented.
D. Disturbed areas and the duration of exposure to erosive elements shall be kept to a
practicable minimum.
E. Temporary vegetation and/or mulching shall be employed to protect exposed critical
areas during development.
F. Permanent vegetation and structural erosion control measures shall be installed as
soon as practicable.
G. To the extent necessary, sediment in run-off water shall be trapped by the use of
debris basins, silt traps, silt barriers, or similar measures until the disturbed area is
stabilized.
-05.
H.
Adequate provisions shall be provided to minimize damage from surface water to the
cut face of excavations and the sloping surfaces of fills.
I.
Cuts and fills shall not endanger adjoining property.
1.
Fills shall not encroach upon natural water courses or constructed channels in a
manner so as to adversely affect other property owners.
K.
Construction equipment shall cross flowing streams by means of bridges or culverts,
except when such methods are not feasible, provided in any case that such crossings
shall be kept to a minimum and provided that the appropriate stream buffer variances
and wetlands approvals have been obtained from the Environmental Protection
Division (EPD) and the Corps of Engineers, respectively. '
L.
Should the specified erosion, sedimentation and pollution control measures prove to
be inadequate, additional measures as directed by Engineer shall be provided for
treatment or control of any source of sediments. Additional adequate sedimentation
control facilities to retain sediments on site or to preclude sedimentation of adjacent
waters shall be implemented.
M.
Except when a prior variance has been obtained from EPD or where a drainage
structure must be constructed with adequate erosion control measures, no
construction activities shall be conducted within a 25 foot buffer along the tops of
banks on all state waters nor within a 50 foot buffer along the tops of banks on all
state waters classified as "trout streams." If required for construction purposes, a
buffer variance will be applied for by the Owner.
N.
Whenever possible, proposed storm water piping systems and detention ponds shall
be constructed prior to other earth disturbing operations. The storm water piping and
detention system shall then be used as a means to control erosion and sediment on
the site.
o.
Sediment basins of the temporary nature shall be constructed as shown on plans and
as required to retain sediment on the site. All temporary sediment basins shall be
maintained in accordance with the "Manual for Erosion and Sediment Control in
Georgia," latest edition and then removed when final stabilization is attained.
P.
Where erosion due to wind is likely to be of concern, trees or groups of trees and
bushes should be left standing, wherever possible, to serve as windbreaks.
ELEMENTS OF THE PLAN:
The minimum requirements for the prevention of erosion and sedimentation for this
site are depicted on the plans and specified herein. The elements of the plan are discussed as
follows, and are listed in chronological order, as far as is practical. The construction activities
should proceed in the order listed.
A. Remove all marketable timber from the limits of construction, rights-of-way, utility
easements, designated fill areas, and other areas to be cleared.
TS-12-3
B.
c.
D.
E.
-06.
Begin clearing and grubbing operations only after silt barriers are installed.
Immediately after the area has been cleared for their placement, install dams, berms
and all other remaining erosion and sedimentation control measures as shown on the
drawings and specified herein. Care shall be taken not to clear and grub beyond the
construction limit.
Contractor shall notify Engineer within 24 hours after the installation of the initial
soil erosion control measures so that the Engineer may inspect the measures in
accordance with the EPD General Permit.
As grading operations commence, the topsoil shall be stripped and stockpiled in
mounds surrounded by berms. As mentioned above, berms or windrows shall be
constructed each afternoon at approximately 100 foot intervals across the graded
areas, except in the low-lying areas of the project. This action will tend to check
erosion should rainfall be experienced during the night.
Construction on the sanitary and storm sewer lines should be commenced as soon as
grading operations have been substantially completed. The disturbed strip along each
line which is located outside of a street right-of-way should be grassed immediately
upon the completion of trench backfilling, as described below.
F.
A graded depression around each catch basin on the site shall be used to contain
sediment during construction in accordance with the "Manual for Erosion and
Sediment Control in Georgia," latest edition.
G.
As soon as the graded areas which are not to be paved, to be built upon, or receive
underground utilities have been brought to final grade, three or four inches of topsoil
shall be spread over these areas. Grassing operations should begin immediately, as
described in the grassing specifications. Roadway shoulders and slopes shall receive
a similar treatment as soon as the installation of the utilities are complete.
H.
All grassing will be performed in accordance with the section of the specifications
titled "Grassing (Bermuda)." Should seasonal limitations prevent the establishment
of the permanent grass cover, the area to be grassed shall be covered with temporary
grass cover; then the permanent grass will be established as soon as its growing
season is reached.
I.
The hay bale dams and silt fencing described above shall not be removed until the
surrounding pavement base material has been placed and is ready for priming and/or
areas are properly stabilized.
J.
In no instance, shall any pollutants, hazardous waste or solid materials including
petroleum products, building materials, etc. be discharged to waters of the State.
K.
All work shall be in accordance with good grading practice and shall conform to
accepted practices in Erosion Control.
INSPECTIONS. SAMPLING & MONITORING:
The Contractor shall be aware that the Owner may contract with a third party to
TS-12-4
TS-12-5
perform additional site inspections of erosion, sedimentation and pollution control measures and also
procure samples of storm water runoff for testing in accordance with the requirements of the EPD
General Permit No. GAR 100002. Third party inspections and samplings shall not relieve the
Contractor of any obligations with respect to the plans, these specifications or that required by the
EPD General Permit GAR 100002. Should any inspections determine that there are deficiencies in
the Contractor's work, then corrective action will be required as directed by the Engineer or Owner.
A. Contractor's Requirements. With respect to inspections, sampling and monitoring
for compliance with EPD General Permit, the Contractor shall, at a minimum, be
responsible for the following:
1. Each day when any type of construction activity has taken place on site,
qualified personnel provided by the Contractor shall inspect: a) all areas on
the site where petroleum products are stored, used or handled for spills and
leaks from vehicles and equipment; b) all locations on the site where vehicles
enter or exit the site for evidence of off-site sediment tracking; and c) all silt
retention basins, traps, barriers, etc. for evidence of failures, potential failures
or excess silt accumulation.
2. These inspections must also occur after each rainfall event on the site and
must be continued until such time that the project is complete and the site has
achieved final stabilization. The Contractor shall document these daily
inspections on a form provided by or approved by the Engineer and must
submit these forms weekly and after each rainfall event to the Owner's.
designated representative. Additionally, should a deficiency in any of the
erosion control measures be noted, the Contractor shall notify the Engineer
within 24 hours.
3. Erosion and sedimentation control measures shall be inspected by a
representative of the Owner beginning with the first earth disturbing activity
and continuing through final stabilization of the project site. Storm water
monitoring, sampling and testing will be accomplished by personnel
representing the Owner beginning with the first earth disturbing activity and
continuing through final stabilization of the project site. The Contractor shall
allow the monitoring agency access to the site at all hours of the day by
providing a key to any locked gates and shall also coordinate these services
by notifying the monitoring agency when: a) the first rainfall event of 0.5 inch
or more in 24 hours occurs on the site after the soil erosion and sedimentation
control measures have been installed; and b) whenever a rainfall event greater
than 1 inch in 24 hours occurs on the site thereafter.
B. Subcontractor's Requirements: Subcontractors shall be considered as acting under
the direction of the Contractor in his role as the Operator under the EPD General
Permit. The Contractor shall insure that all subcontractors comply with the Permit.
Subcontractors shall be responsible, at a minimum, for the following:
1. Each day when any type of construction activity has taken place on his
portion of the site, the Subcontractor shall inspect a) all areas on the site
where petroleum products are stored, used or handled for spills and leaks
TS-12-6
from vehicles and equipment; b) all locations on the site where vehicles enter
or exit the site for evidence of off-site sediment tracking; and c) all silt
retention basins, traps, barriers, etc. for evidence of failures, potential failures
or excess silt accumulation.
2. These inspections must also occur after each rainfall event on the site and
must be continued until such time that the project is complete and the site has
achieved final stabilization.
3. The Subcontractor shall immediately report any noted deficiencies to the
Contractor, who will take appropriate corrective action.
END OF SECTION
SECTION TS-13
FLOW ABLE FILL
-01. SCOPE:
The work covered by this section of specifications consists of furnishing all labor,
equipment, appliances, and materials, and in performing all operations in connection with the
installation of flow able fill work, complete, in strict accordance with this specification and the
applicable drawings, and subject to the terms and conditions of the Contract.
-02. FLOW ABLE FILL MIX DESIGN:
The mixes fall into the categories of "very flow able" and "less flowable," which is
controlled by the amount of water that is added. The less flow able mix should be used when it is
desirable to put traffic back on a roadway quickly (usually 8 to 10 hours) or when being used to
backfill pipes which could "float" out of position due to the buoyant effect of the very flowable fill
mix. This mix will still self-consolidate around pipes without any "honeycomb" areas. Adding
water to flow able fill to obtain the desired plastic characteristics will not compromise the quality of
the hardened flow able fill.
Less Plowable Mix (Mix 1)
Weiehts Volume
Min. 50 Ibs Cement 0.25
Min. 600 lbs. Ply Ash 4.24
SSD 2500 Ibs Sand 15.17
55gal. 458 lbs Chlorides Water 7.34
Total Cubic Feet 27
Reference
ASTM C150, Type I or II
ASTM C618, Class C
Clean, potable, < 500 ppm
Above values are based on specific gravities - cement 3.15, fly ash 2.27, sand 2.64,
and water .1.00. Anticipated unconfined compressive strength is 80 psi at 28 days and 150 psi at 56
days. For "very flow able" fill (Mix 2), add 1 0 gallons of water per cubic yard of Mix 1.
-03.
INSTALLATION OF FLOW ABLE FILL:
The trench shall be prepared and the pipe joints placed as normal. There should be
at least 6 inches of flow able fill above any utility line. Once the pipe is covered, it will be
sufficiently anchored and if directed by the Owner's representative, water may be added to the
remaining flow able fill to ease placement without danger of floating the pipe. If it is important to
quickly return traffic to the roadway, the flow able fill mixture shall not be altered by the addition of
water.
TS-13-1
TS-13-2
The flowable fill may be discharged from the ready-mix truck into the space to be
filled, or by other methods approved by the Utilities Department representative. The mix may be
placed in part depth or full depth as conditions at the site dictate. Formed walls or other bulkheads
shall be constructed to withstand the mounded soil rather than wood or metal forms. When
backfilling utility lines, flowable fill shall be distributed evenly to prevent movement of the line.
The material is self-consolidating and there is no need to use vibrators. Finishing can
be accomplished with a square shovel if the fill surface is at the bottom of pavement or with a wood
float if the surface will be temporarily used as a finished surface.
Once the flowable fill is in the trench, the self-consolidating material displaces the
extra water not needed for maximum density. Provision shall be made for this "bleed water' to run
off and away from the surface of the hardening flowable fill (use of vapor barriers sue as plastic
sheets is not desired). The material will usually support foot traffic within an hour after the bleeding
ends. Typically, full traffic can be allowed on the hardened flowable fill within 8 to 20 hours
(depending on site conditions, volume to be backfilled, etc.). Without damage to the fill or any
structures below. If it is necessary to return traffic in less than 8 hours, or if there is concern that
traffic flow will "rut" the hardening flowable fill, steel plates shall be used to bridge over the
hardening flow able fill as directed by the Utilities Department representative. If the filled cavity is
too wide to bridge, steel plates shall be placed on top of the hardening flowable fill as soon as it is
able to support foot traffic (one hour after bleeding ends), and full traffic can be allowed without
damage to the fill or structure below.
As the extra water is displace from the consolidating flowable fill, there will be an
initial subsidence of about one-eighth (1/8) of an inch per vertical foot. Once the flow able fill
hardens, there will not be future settlement. The hardened flow able fill can be shaped to grade the
next day to allow the patch thickness required. The patch may be applied directly to the cured
flow able fill.
It will be the responsibility of the Contractor to furnish the necessary information to
obtain approval of the mix design and to use the necessary construction techniques to assure that the
finished material will perform as intended.
END OF SECTION
SECTION TS-14
WATER DISTRIBUTION SYSTEM
-01. SCOPE:
This section covers all work associated with the water distribution system.
-02. GENERAL:
The Contractor/Developer is responsible for verifying the exact location, size and
material of any existing water facility proposed for connection or use by the project.
All work that occurs in the public right-of-way shall comply with the Augusta-
Richmond County Planning Commission "Development Documents" (latest version) and Public
Works Department's Right-of-Way Encroachment Guidelines (latest version). Any field changes
that occur in thepublic right-of-way and are not specifically related to water or sewer items shall be
coordinated with the Public Works Department.
-03. STANDARDS FOR WATER MAINS:
A. COVER
1. Standard depth of cover is 4 feet below existing and proposed road
surface (and areas designed for normal traffic loading) unless
otherwise approved by the Augusta Utilities Department.
2. Minimum cover to finished grade over water mains shall be 36
inches. Minimum cover under ditch bottoms shall be 24 inches.
These must be approved by the Augusta Utilities Department on a
case-by-case basis.
B. HORIZONTAL SEPARATION
1. Ten (10) feet to any existing or proposed sanitary sewer/force main,
storm sewer or sewer manhole (less than 10 feet requires pipe
material to be Ductile Iron Pipe (DIP) for both Water Main and
Sewer/Force Main).
2. Fifteen (15) feet to buildings, top of bank of lakes/streams/creeks,
other structures (10 feet absolute minimum - only when unavoidable,
and pipe material is required to be DIP).
3. Ten (10) feet minimum separation to gas mains.
4. Ten (10) feet niinimum to underground electric cable.
TS-14-1
TS-14-2
5. Current Georgia EPD separation requirements.
6. All separation distances above are edge to edge.
C. VERTICAL SEPARATION
1. Water main shall cross over other pipes.
2. Eighteen (18) inch minimum separation (edge to edge) between all
pipes and cables shall be maintained (6 inch absolute minimum
separation with DIP) when conforming to Georgia EPD separation
requirements.
3. When water mains cross under sewers, additional measures shall be
taken. At least 18 inches of separation between the bottom of the
sewer and the top of the water main shall be provided. Adequate
structural support for the sewer to prevent deflection or settling on the
water main. The joint of water pipe shall be centered at the crossing.
Encasement of the water pipe in concrete shall also be considered.
-04. PRODUCTS:
A. WATER MAIN MATERIAL
1. Water mains shall be either ductile iron pipe (DIP), polyvinyl chloride
(PVC), or galvanized pipe as outlined below. Any pipe, solder and
flux used during installation of the water lines and services must be
"lead-free" with not more than 8% lead in pipe and fittings, and not
more than 0.2% lead in solders and flux.
2. DIP shall be centrifugally cast and shall conform to A WW A
CI50/ANSI A21.50 (latest version) for design and AWWA
CI51/ANSI A21.51 (latest version) for manufacture. PVC pipe 6
inch to 12 inch diameter shall conform to A WW A C900 (latest
version). PVC pipe 14 inch to 36 inch diameter shall conform to
A WW A C905 (latest version).
3. For water mains 6" through 16", DIP Pressure Class 350 shall be
allowed. For water mains 18" through 24", DIP Pressure Class 300
shall be allowed. PVC C900 (most current date), Class 200, SDR-14
with cast iron equivalent o.D.s, gasket bell end with elastomeric
gaskets shall be allowed for water mains 6" through 10" (solvent
weld joints are not permitted). Galvanized pipe shall be seamless,
American made, Schedule 80 and shall conform with the ASTM
Specifications. Flanged DIP shall have threaded ductile iron flanges
and shall conform to the requirements of A WW A C 115 (latest
TS-14-3
version). All flanges shall be Ductile Iron Class 150, ANSI B16.5
(latest version). Flanges shall be flat faced and all joints shall use 1/8
inch black neoprene full-faced gaskets.
4. Ductile iron pipe and fittings shall have bituminous coating outside
and shall be cement lined in accordance with A WW AC 104/ ANSI
A21.4 (latest version). DIP shall have 1/16" cement mortar lining
with rubber gasket push-on joints or mechanical joints. Mechanical
joint glands shall be ductile iron. Tee bolts and nuts shall be Cor-Ten
steel. Rubber gasket joints shall conform to A WW A C III/ANSI
A21.11 (latest version), and shall be furnished by the pipe
manufacturer with the pipe. A non-toxic vegetable soap lubricant
shall be supplied with the pipe in sufficient quantities for installing
the pipe. The lubricant shall be approved by NSF for use with
potable water mains.
5. Pipe classes designated previously in this standard are minimum
allowed. Actual pipe class shall be determined based upon the
installation and the use intended. Pipe shall be appropriately labeled
on the drawings. All PVC pipe for potable water service shall bear
the approved stamp of the National Sanitation Foundation. Copper
wire (12 gauge, bare single strand) shall be attached along the top of
all buried PVC water lines, wrapped around service corporations and
stubbed up into all valves boxes for locating purposes.
6. DIP shall be required in the following circumstances:
a. Within 10 feet of sanitary and storm pipes.
b. Within 15 feet of structures (near side of concrete footing), or
top of bank of lakes/streams/creeks.
c. Crossings over or under sewers, gas and storm pipes with less
than 18 inches separation, with no joint allowed within 10
feet of crossing.
d. Beneath all paved areas, excluding driveways or sidewalks.
e. Within project boundaries of subdivisions with private roads
where the Utilities Department will take over the line for
operations and maintenance.
f. Along all state right-of-ways.
TS-14-4
7. The Utilities Director may mandate DIP in any instances of off-site
or on-site construction where future abuse to the line is possible due
to location or circumstances.
8. Restrained Joints shall be DIP as follows:
a. For 24-inch and Smaller - Restrained joint shall be U.S. Pipe
Field Lok, American Ductile Iron Pipe Fast Grip, EBAA Iron
Mega-Lug, or an equivalent product.
b. For 24-inch Diameter and Larger - Restrained joint shall be
U.S. Pipe TR Flex, American Ductile Iron Pipe Lok-Ring, or
equivalent product.
c. If inserting in older cast iron pipe, the restrained joint shall be
as approved by the Augusta Utilities Department.
Retainer Glands/Mega-Lug shall not be considered a fitting.
The restraint method shall be suitable for the pipe size
thickness and test pressure as required for the specified design
case.
d. Jack and Bore Installations:
Casing pipe used with jack and bore shall be in accordance
with requirements of the Georgia Department of
Transportation (GDOT) or railway specifications and
"Excavation and Backfilling" ofthese specifications. Carrier
pipe shall be restrained joint DIP as outlined in these
specifications.
Directional Bore Installations: Directional bores will be
considered as a viable alternative to jack and bore installation
under Augusta-Richmond County roadways. The Utilities
Director will review each case for materials and construction
methods.
e. Mains may be tapped as long as the tapping line is smaller
than the tapped line unless otherwise approved by the
Augusta Utilities Department. Equal size line connections
approved by the Augusta Utilities Department shall require
that a tee be cut into the main where possible. Tees are also
required at locations dictated by the Utilities Director.
TS-14-5
Tapped connections in pipe and fittings shall be made in such
a manner as to provide a watertight joint and adequate
strength against pull-out.
Tapping Sleeves and Valve shall be ductile iron, mechanical
joint. Tapping sleeves and valves are required for all taps 4
inches and greater. Taps less than 4 inches shall be provided
with a service saddle meeting the requirements of these
specifications Valves shall be provided on all taps. Tapping
sleeves shall be a minimum of 6 feet from pipe joints.
f. Schedule 40 PVC shall only be used as sleeves for the
installation of service line tubing under all pavement areas.
Use in the water distribution system or other areas are not
acceptable.
g. Unspecified transitions from DIP to PVC are not allowed.
Material for transition shall be indicated and specified and
must be approved by the Augusta Utilities Department.
h. All construction material shall be first quality, not previously
used. Repair clamps are not acceptable. Damaged or faulty
pipe and materials must be properly replaced. All gaskets
shall be new. When connecting to existing valves or fittings,
gaskets shall be replaced, not reused.
B. V ALVES, FflTlNGS AND APPURTENANCES
1. Gate valves, 4 inches to 16 inches, shall be the resilient seat type
conforming to A WW A C509 (latest version). Valves larger than
16inches shall be gear operated butterfly valves, conforming to
A WW A C504 (latest version). Wafer valves shall not be accepted.
2. Valves shall OPEN LEFT if installed south of Gordon Highway (SR
10), or OPEN RIGHT if installed north of Gordon Highway. Valves
shall be provided with valve stem extensions to within 6 inches of
ground surface, where centerline of pipe to grade is greater than 4
feet.
3. Valve boxes shall be M&H E-2702, Mueller HI0364 or approved
equal. Each valve box shall be slip-type to adjust for a minimum
cover of 36" bury. The flanged base of the valve box shall be at least
six (6) inches above the pipe so not to stress water lines 4" and
smaller. Extension pieces will be required for additional depth over
TS-14-6
valves. Extensions shall be M&H E-3120 or Mueller H-I0375.
Covers shall have "W A TER" cast on top.
4. All valves, bends, tees, crosses and dead ends shall be restrained by
a mechanical restraint systems as outlined in these specifications, or
by use of a concrete thrust block in those instances that warrant such
an installation. Thrust blocks shall be poured-in-place concrete
having a minimum compressive strength of 3,000 psi after 28 days of
cure time. All materials, fittings and appurtenances intended for use
in pressure pipe systems shall be constructed for a minimum working
pressure of 150 psi unless the specific application dictates a higher
working pressure requirement.
5. Standard pressure pipe fittings of size four (4) inch ill and larger shall
be ductile iron conforming to A WW A C153 (latest version), with
mechanical joints unless flanged or restrained joints are required.
Gray cast-iron fittings are not allowed. Ductile iron fittings shall be
cement lined in accordance with A WW A C104 (latest version).
Mechanical joint fittings, 24 inches and smaller shall be rated for 350
psi working pressure. Flanged joint fittings 24 inches and smaller
shall be rated for 250 psi working pressure. All fittings 30 inches and
larger shall be rated for 250 psi working pressure. For sizes less than
four (4) inch ill, fittings shall be suitable to the pipe material and
application. Glands for mechanical joint fittings shall be ductile iron,
and tee bolts and nuts shall be Cor-Ten steel. Only bolt systems
furnished by the manufacturer for mechanical joints are acceptable;
nuts and bolts shall be new, not reused. Pipe gaskets shall be new as
supplied by the pipe manufacturer. All flanges shall be ductile iron
Class 150, ANSI B 16.5. All flanges shall be flat faced. Full face, 1/8
inch black neoprene gaskets shall be used on all flanged joints. All
joints shall conform to A WW A Clll (latest version). Bolts, nuts and
washers for flanges shall be hot dip galvanized, except T -bolts shall
be Cor-Ten steel.
List of Specifications:
ANSI/AWWA CI51/A21.51-96 4-FEB-1996 or latest version
American National Standard for Ductile-Iron Pipe, Centrifugally
Cast, for Water
ANSI/A WW A CI50/A21.50-96 1996 or latest version
American National Standard for Thickness Design of Ductile-Iron
Pipe
TS-14-7
ANSI!A WW A CI15/A21.15-94 1994 or latest version
American National Standard for Flanged Ductile-Iron Pipe With
Threaded Flanges
ANSI! A WW A C 111/ A21.11-95 1995 or latest version
American National Standard for Rubber-Gasket Joints for Ductile-
Iron Pressure Pipe and Fittings
ANSI!A WW A C153-98 1998 or latest version
American National Standard for Ductile-Iron and Gray-Iron
Fittings, 3 in. through 48 in. (75 mm through 1200 mm), for Water
and Other Liquids
ANSI! A WW A C 104/ A21.4-95 1995 or latest version
American National Standard for Cement-Mortar Lining for
Ductile-Iron Pipe and Fittings for Water
C. FIRE HYDRANTS
1. Fire hydrants shall be provided in all water mains, transmission and
distribution systems. Accepted models are Mueller # A- 24018, M&H
Figure 29T A WW A Compression Type-Dry Top-Traffic Model 150
psi working pressure, 300 psi testing pressure. Kennedy K-81D will
also be accepted. All fire hydrants shall be ordered safety yellow
body with white bonnet and caps. Fire hydrants shall be spaced such
that the radius of protection will not be more than 500 feet. In certain
areas, closer spacing may be required by the Fire Marshal.
2. Each hydrant shall be left turn opening and capable of delivering a
flow of at least 500 gallons per minute with a residual design pressure
of not less than 20 psi, or a higher flow as required by the Fire
Marshal. Multiple fire hydrants with looped mains and/or larger main
sizes may be required to provide water for higher flow demand. Flow
tests shall be performed to verify the specified fire flow demand.
3. Fire hydrants shall be.of the dry barrel break-away type conforming
to A WW A C502 (latest version), with two 2 Y2 inches threaded hose
nozzles and one 4 Y2 inch threaded pumper nozzle. Hose and pumper
nozzle threading shall be national standard. Show connection shall
be 6- inch mechanical j oint. The center line of the nozzles shall be 18
inches above the finish grade. Hydrants shall have a 5 1,4 inch interior
valve opening and be restrained from hydrant to tee at the main. At
the discretion of the Utilities Director, additional protection for fire
hydrants shall be provided including but not limited to concrete filled
ductile iron traffic posts.
TS-14-8
4. Fire hydrant branches (from main to hydrant) shall be a minimum of
6 inches ID. Each branch shall be provided with a resilient seat gate
valve located as close as possible to the main. Hydrants shall be
located at or near road right-of-way lines with pumper nozzle
pointing toward the road. A clear zone around all fire hydrants shall
be adhered to, consisting of a 5 foot radius around the hydrant and 7
feet above the top of the hydrant. Maintain 15 feet minimum from
hydrant to all structures. Placement oflandscaping, fencing, etc. shall
be considered in order to meet this clear zone requirement.
List of Specifications:
ANSI! A WW A C500-93 1993 or latest version
Metal-Seated Gate Valves for Water Supply Service (includes
addendum C500a-95
ANSI! A WW A C502-94 1994 or latest version
Dry-Barrel Fire Hydrants (includes addendum C502a-95)
ANSI! A WW A C503-97 1997 or latest version
Wet-Barrel Fire Hydrants
ANSI!A WW A C504-94 1994 or latest version
Rubber-Sealed Butterfly Valves
ANSI! A WW A C507 -991-DEC-1999 or latest version
Ball Valves 6 in. through 48 in. (150 mm through 1200 mm)
ANSI! A WW A C508-93 1993 or latest version
Swing-Check Valves for Waterworks Service, 2 in. (50mm) Through
24 in. (600mm) NPS (includes addendum C508a-93
ANSI! A WW A C509-94 1994 or latest version
Resilient-Seated Gate Valves for Water-Supply Service (includes
addendum C509a-95)
ANSI! A WW A C550-90 1990 or latest version
Protective Epoxy Interior Coating for Valves and Hydrants
D. WATER SERVICE LINES AND TAPS
1. Tapping sleeves and tapping crosses shall be of a heavy body ductile
iron, mechanical joint suitable for a working pressure of 150 psi for
sleeves and crosses larger than 14-inch (200 psi for sleeves and
TS-14-9
crosses equal to or less than 14-inch), as approved by the Augusta
Utilities Department.
2. No direct service taps shall be allowed. All service line taps shall be
supplied with corporation stops. Service line tubing shall be rolled
of soft continuous and seamless copper Type K conforming to
A WW A C800 and ASTM B-88 (latest version).
3. Corporation Stops and Main Connectors:
3,4" FB600 - 3 Ford or Equal
1" FB600 - 4 Ford or Equal
Taper Thread Inlet by Flare Copper Outlet
Eighth Bends:
3,4" LA02 - 33 Flare 1/8 Bend
3,4" LA04 - 33 Compression 1/8 Bend
1" LA02 - 44 Flare 1/8 Bend
1" LA04 - 44 Compression 1/8 Bend
4. Minimum size for residential use shall be one (1) inch. The service
line shall be laid in a straight line and be of a continuous piece of pipe
from corporation to curb cock. The curb cock shall be located 6
inches behind and 8 inches below the top of new curb or edge of
asphalt. Where service connects to DIP or any pressure-rated pipe,
service saddles must be used. Brass double strap tapping saddles
shall be used. U-bolt type straps are not acceptable. All water service
taps on the main shall be spaced at a minimum distance of 18 inches
apart and a minimum of 18 inches from a bell or fitting. If two or
more taps are required at a minimum spacing, they shall be offset 450
alternatively. Services greater than one (1) inch shall be seamless
galvanized. 2" services shall have two 2" 90-degree galvanized
elbows per Augusta Utilities' 2 Inch Water Service detail.
Services shall not exceed over 100 feet from the main to the meter.
Where possible, meter shall be placed in unpaved area as close to the
water main as possible.
E. METER INSTALLATION
1. The Contractor shall furnish and install an approved meter box at the
termination point of all water services, and maintain until such time
as a meter is installed. Meters will be installed by Augusta Utilities
Department at the time services is required at the stub-out. Each unit
TS-14-1O
within a residential building (i.e., duplex, triplex, etc.) shall have a
separate meter, unless prior approval is received by the Utilities
Director. Meter boxes for 1 Y2 inch and smaller meters are standard.
2-inch and larger shall be installed in a meter vault.
2. Meter boxes shall be Rome type, 10" x 19" x 10" cast iron box and
lid. The top shall have cast ribs on the bottom side with four (4) legs
to prevent sliding movement. The box shall have a minimum weight
of 37 Ibs., for meters 1 Y2 inch or smaller. Meter and curb stop shall
be fully encased by the meter box. Meter vaults (for meters 2 inch
and larger) shall be fabricated of masonry block or pre-cast reinforced
concrete using 3,000 psi concrete and #4 rebar. The access hatch
shall be made of heavy duty aluminum, and shall be hinged and
lockable. The hatch shall be large enough for removal of the meter
but no smaller than 48" x 36". Wall dimensions shall allow 2 feet of
working clearance. Vault floors shall be no less than 4 inches thick
with 3,000 psi concrete and #4 rebar, with the meter located no less
than 18 inches off the floor. All meters will be provided and installed
by the Augusta Utilities Department. The meters remain the property
of the Augusta Utilities Department.
3. Meters should generally be placed 18 inches inside the adjacent utility
easement that parallels the right-of-way. Where sidewalk, two feet
of clearance is required between the customer's side of the sidewalk
edge and the meter box. In developments where the property line is
not clearly defined (e.g., condominiums) the meter should be placed
for ready access as approved by the Augusta Utilities Department.
Meter and control valves shall be accessible and unobstructed for 4
feet in all directions. This shall include but not be limited to
transformers, telephone junction boxes, walls, trees, etc. Meters shall
not be placed in areas that can be fenced, such as backyard. Meter
boxes shall not be placed in any asphalt or concrete surfaced areas
(sidewalks, driveways, curbs, etc.) unless approved in writing by
Augusta Utilities. For shopping centers, the developer's engineer
should give special consideration to meter layout so as to satisfy these
requirements. When no alternative is available but to locate in
asphalt, the top of box shall be flush with the asphalt surface. Meters
shall not be located in low areas that normally receive storm water.
The box shall also be located outside of parking stalls. The box and
lid should be traffic bearing, but located outside of a commonly
trafficked area.
TS-14-11
F. BACKFLOW PREVENTION DEVICES
1. Backflow prevention devices shall be provided, as required by the
Utilities Director and as set forth in these Standards. All irrigation
systems, water services and fire lines for dustrialloffice/commercial
industrial/office/commercial, schools, mobile home parks, multi-
family residences and any other locations as determined by the
Utilities Director shall require suitable backflow prevention
assemblies on the customer side of service lines (domestic, irrigation,
and fire). Backflow devices shall be tested by a certified person and
the results furnished to the Augusta Utilities Department prior to any
water use. Residential development shall install a "Dual Check"
Backflow Device on the customer's side of service line at the point
of tie-in to the water meter. The plumber or builder tying service into
the set meter will submit the test results for the backflow prevention
device to the Augusta Utilities Department's Inspector prior to
acceptance and any water use.
2. Backflow prevention device assemblies shall be the latest approved
product of a manufacturer regularly engaged in the production of this
type equipment. All assemblies shall be as approved by the America
Society of Sanitary Engineering (ASSE), The American National
Standards Institute (ANSI), The American Water Works Association
(A WW A), Foundation for Cross Connection Control and Hydraulic
Research of the University of Southern California, and the Georgia
State Plumbing Code.
3. Type and size of assemblies shall be indicated on the drawings.
4. Backflow prevention device ownership and maintenance
responsibilities shall be as set forth in the appropriate ordinances.
The Contractor shall document that the backflow prevention device
has been tested by a qualified technician. A copy ofthetechnician's
certification must be attached to the test results and submitted to the
Augusta Utilities Director.
List of Specifications:
ANSI! A WW A C51 0-97 1997 or latest version
Double Check Valve Backflow-Prevention Assembly
ANSI! A WW A C511-97 1997 or latest version
Reduced-Pressure Principle Backflow-Prevention Assembly
TS-14-12
G. FIRE LINES
1. All fire lines shall have a detector check valve with a 5/8 inch by-
pass meter (to detect low flows) within the right-of-way or
dedicated easement. No exceptions to the by-pass meter
requirement shall be made regardless of sprinkler system type,
configuration, etc.
-05.
EXECUTION
A. CONSTRUCTION
1. WATER DISTRIBUTION SYSTEM INSTALLATION
a. Authorization must be obtained from the Augusta Utilities
Department to construct, alter or modify a water line.
Construction of water infrastructure will be authorized by the
Utilities Department upon approval of submitted plans and
notification of the Augusta Utilities Department at least 24
hours prior to starting construction (706-772-5503). Where
water lines will encroach public right -of-way, aRight -of-Way
Encroachment Permit approved by the Public Works
Department is required prior to construction. ARight -of-Way
Encroachment Permit application is available through the
Public Works Department (706-821-1706).
b. Installation of water mains and associated appurtenances shall
be in accordance with current A WW A specifications and
manufacturer's requirements for the specific product.
Loading or unloading and storage of pipe, fittings, valves, etc.
shall be done such that to avoid damage. The interior of all
pipe, fittings, valves, etc. shall be kept free of dirt and foreign
matter at all times. All piping shall be placed in a dry trench
with a stable bottom. Wet trench installation shall be allowed
only upon written approval of the Utilities Director.
c. Mechanical restraint systems shall be required at each fitting
involving a change of direction and as specified in the
approved plans. Concrete thrust blocks will be allowed in
lieu of mechanical restraint systems.
d. Backfill shall be free of boulders and debris, and shall
comform to Georgia Department of Transportation
TS-14-13
Specifications. Sharp or rocky material encountered in the
base shall be replaced with proper bedding. Pipe shall be laid
on line and grade as designed. Pipe joints, gravity blocks,
service connections, and conflicts shall be left exposed until
visually inspected and approved by the Augusta Utilities
Department's Inspector.
e. Fire hydrants shall be installed true and plumb with the center
of the pumper nozzle facing toward the road. Hydrants shall
not be placed in the sidewalk. The contractor will be
responsible for moving hydrants placed in sidewalks.
f. All valves shall be placed according to plans. Valve stems
shall be installed plumb. Valve stem extensions are required
as described in these specifications. Air relief valves shall be
installed at all high points in the water main where air can
collect, as shown on the plans or as directed by Augusta
Utilities.
List of Specifications:
ANSI! A WW A C600-93 1993 or latest version
Installation of Ductile-Iron Water Mains and Their
Appurtenances
ANSI!AWWA C605-94 30-JAN-1994 orlatest version
Underground Installation of Polyvinyl Chloride (PVC)
Pressure Pipe and Fittings for Water
ANSI! A WW A C512-92 1992 or latest version
Air Release, AirN acuum and Combination Air Valves for
Water Works Service
g. Handling and Storing of Materials: Unload pipe so as to
avoid deformation or other injury thereto. Place no pipe
within pipe of a larger size. Store pipe and fittings on sills
above storm drainage level and deliver for laying after the
trench is excavated. Valves shall be drained and so stored as
to protect them from freezing.
h. Pipe Laying (General): The interior ofthe pipe shall be clean
and joint surfaces wiped clean and dry when the pipe is
lowered into trench. Lower each pipe, fitting and valve into
When installing water line through casing, Contractor
shall use mechanical joint pipe with retained glands
through length of casing. The water main shall be
strapped to 8 foot long treated wooden skids with
metal straps throughout length of casing. The ends of
the casing shall be sealed with brick and mortar.
the trench carefully and lay true to line and without
objectionable breaks in grade. The depth of cover below
finished grade shall be not less than 3 feet, or as shown on the
drawings. Give all pipes a uniform bearing on the trench
bottom. Allow no trench water or dirt to enter the pipe after
laying. Insert a watertight plug in the open end of the piping
when pipe laying is not in progress.
1. Boring and Jacking: Where required by the drawings, the
water line will be installed in a steel casing, placed by boring
and jacking. Where boring is required under highways or
city/county roads, the materials and workmanship will be in
accordance with the standards of the Georgia Department of
Transportation or local authority. Boring and jacking under
railroads will be governed by the latest AR.E.A Standards,
Part 5, "Pipelines" and those of the railroad involved.
(1) Casing 'Pipe: The casing pipe shall conform to the
materials standard of ASTM Designation A252, with
minimum wall thickness of 0.219 inch. Steel pipe
will have a minimum yield strength of 35,000 psi.
Casing pipe shall be joined together with welded
joints.
(2) Carrier Pipe: The carrier pipe shall be ductile iron as
specified herein.
(3) Installation: The steel casing shall be installed by the
"Dry Bore and Jack" method. If voids develop or if
the bored hole diameter is greater than the outside
diameter of the pipe by more than approximately 1
inch, remedial measures will be taken as approved by
the Engineer.
(4) Reaction Blocking: All plugs, caps, tees, bends and
other fittings shall be provided with adequate reaction
blocking as shown on the drawings. Reaction
blocking shall be made to bear directly against the
undisturbed trench wall. Where trench conditions are,
TS-14-14
in the opinion of the Engineer, unsuitable for reaction
blocking, the Contractor shall provide tied joints to
adequately anchor the piping as shown on the
drawings. All the rods and clamps shall be given a
bituminous protective coating.
J. Connection to Existing System: All connections to existing
mains shall be made under the direct supervision of the
Augusta Utilities Department's Inspector. Valves on existing
mains shall be operated by or under direct supervision of
Augusta Utilities Department personnel. Tapping sleeves and
valves shall be pressure tested prior to tapping. If service to
existing customers must be cut off, the Augusta Utilities
Department shall be notified at least three (3) days in advance
to make necessary notifications. The Contractor shall
disinfect and secure appropriate Utilities Department
clearances and samples for any service interruptions which
occur as a result of a Contract request for shut down or error.
The clearances shall be obtained within 72 hours of
reactivation.
If cut-off of service is required, the Contractor shall be ready
to proceed with as much material pre-assembled as possible
at the site to minimize the length of service interruption.
Augusta Utilities reserves the right to postpone service cut-off
if, in the opinion of the Utilities Director, the Contractor is
not ready to proceed on schedule. No customer should be
without water for more than four (4) hours. The
Owner/Developer shall arrange for temporary services to
Customer if water will be shut off for more than four hours.
Local chlorination will be required for all pipe and fittings
used to complete connections with the potable water system.
Tapping sleeves and valves shall be chlorinated in accordance
with A WW A requirements. All wet taps shall be witnessed
by the Augusta Utilities Department's Inspector.
B. CLEANING AND FLUSHING
1. Upon completion of installation, the mains shall be flushed and the
water disposed of without creating a nuisance. Flushing must achieve
a minimum water velocity of 2.5 fps in all portions of the pipe. The
duration of the flushing will be determined by the Augusta Utilities
Department's Inspector. If, in the opinion of the Augusta Utilities
Department's Inspector, there is insufficient water available for
proper flushing, the Contractor shall clean the lines by pigging. No
TS-14-15
TS-14-16
flushing or cleaning shall take place without an Augusta Utilities
representative present. The existing mains that the new mains are
connected to may be required to be flushed under the direction of the
Augusta l!tilities Department when service is restored.
C. TESTING AND DISINFECTION
1. Pressure and Leakage Testing: Before any work will be accepted for
payment, the Contractor will fill the piping with water, open outlet as
necessary for expelling the entrapped air. No fire hydrant shall be
opened full force during charging operations. Thereafter, furnish the
necessary equipment and test the piping under the supervision of the
Engineer for a period of at least 4 hours at not less than 1.25 times the
design pressure in pounds per square inch, based upon the highest
elevation of the section under test. Pressure testing shall be in
accordance with the latest A WW A Standard C600, Section 4.1. at 1.5
times the working pressure at the point of testing. Inspect all joints,
and remedy to the satisfaction of the Engineer any defects discovered.
Continue the test until all visible leaks have been eliminated from the
part of the system under test, and the pressure remains constant with
a maximum pressure drop of 5 psi for the duration of the test.
2. All water mains shall be leak tested. The Contractor shall provide all
equipment, materials and labor necessary for pressure and leak
testing. This test must be observed by an Augusta Utilities
Department representative and the design engineer. A pumping
pressure of 200 psi must be supplied at the expense ofthe Contractor.
The main tested shall either be isolated from active potable lines or
protected from leakage by a double valve arrangement. All water
used for pressure testing must be potable water with an adequate
chlorine residual. Water lines shall be tested by valve sections.
Maximum allowable leakage shall be as determined in accordance
with current A WW A specifications. The standard duration of test is
four (4) hours. Testing procedures shall meet or exceed A WW A
C600 (latest version) requirements. Any portions of the main which
fail the test shall be replaced or adjusted until the entire new main
passes the test criteria. The pressure and leakage test shall be done
concurrently.
3. Augusta Utilities shall be notified at least 24 hours in advance to
schedule bacteriological testing of water mains. The Contractor shall
replace or adjust components of the pipeline which fail the test.
Clearance is required from the Utilities Department before the
Augusta Utilities Department will allow the main to be put into
servIce.
L = SDfP
133200
4. Immediately following the pressure test, and before any work will be
accepted for payment, the Contractor shall perform a leakage test.
Leakage is defined as the quantity of water to be supplied into the
newly laid pipe, or any valved section thereof necessary to maintain
the specified leakage test filled with water to within 5 psi of the test
pressure. No pipe installation will be accepted until the leakage is
less than the number of gallons per hour as determined by the
formula:
L = Allowable leakage in gallons per hour.
S = The length of pipe in the section tested.
D = The nominal diameter of the pipe in inches.
P = The average test pressure during the leakage test in pounds
per square inch gauge.
The leakage test shall be conducted in accordance with A WW A
Standard C-600, Section 4.1 (latest version).
5. All piping complete with fittings and appurtenances shall be sterilized
as specified in the applicable sections of A WW A Specification C651
(latest version) "Disinfecting Water Mains." Piping and
appurtenances shall be thoroughly flushed then chlorinated with not
less than fifty parts per million (50 ppm). Calcium hypochlorite can
be used. Water from the existing distribution system or other source
of supply should be controlled so as to flow slowly into the newly laid
pipeline during the application of chlorine. The solution should be
retained in the pipeline for not less than 24 hours and a chlorine
residual of 10 ppm should be available at this time. The system shall
then be flushed with potable water and the sampling program started.
Sampling taps and chlorinated water used for disinfection shall be
flushed to a location that will not damage property, persons, etc., and
shall be provided by the Contractor at the expense of the Contractor.
The provisions of this paragraph apply equally to new pipe and
fittings and to existing pipelines into which connections have been
made or which may have been otherwise disturbed to the extent that
contamination may have occurred. All requirements of the health
authorities shall be observed in executing this work. The disposal of
heavily chlorinated water (following disinfection) must be
accomplished in accordance with the latest editions of the A WW A
Standard C651 and the EPD's Minimum Standards for Public Water
Systems.
TS-14-17
TS-14-18
Two or more successive sets of samples, taken at 24 hour intervals
and tested by a State approved private lab, shall indicate
bacteriologically satisfactory water and the results submitted to the
Engineer and the Augusta Utilities Department.
D. WATER/SEWER SEPARATION:
1. A 10 foot horizontal separation shall be maintained between water
and sewer lines. Where the horizontal separation cannot be met or
where water and sewer lines must cross, an 18 inch vertical
separation, water over sewer must be maintained. Where the above
conditions cannot be met, water and sewer lines shall be cast iron or
ductile iron pipe with joints staggered such that maximum separation
between joints exists. The water line shall be installed over the sewer
line.
E. AS-BUILT DRAWINGS:
1. As the work progresses, record on one set of utility drawings all
changes and deviations from the contract drawings in sizes, lines or
grade. Record also the exact final location of water lines by offset
distances to surface improvements such as edge of existing pavement
or to property lines, etc. at a maximum interval of 200 feet. Make
sufficient measurements to locate definitely all water lines etc., to
permanent points. The drawings will show references to all valves,
fittings, pipe brand changes, etc. Transfer accurately all such records
in red pencil to white prints of the utility drawings and deliver them
to the Engineer with monthly payment estimate.
END OF SECTION
SECTION TS-15
GRADED AGGREGATE SURFACE COURSE
-01. SCOPE:
This section covers a graded aggregate surface course for a driveway or parking area.
-02. GENERAL SPECIFICATIONS:
The graded aggregate surface course shall conform to all applicable specifications of
Section 318 of the Standard Specifications for Roads and Bridges of the Georgia State Department
of Transportation, Latest Edition.
-03. PREPARATION OF SUBGRADE:
The sub grade to receive the graded aggregate surface course shall be constructed in
accordance with requirements of Section 209 of the Standard Specifications for Roads and Bridges
of the Georgia State Department of Transportation.
-04. MATERIALS & CONSTRUCTION FOR SURFACE COURSE:'
Materials and construction for the graded aggregate surface course shall be in
accordance with Section 310 of the Standard Specifications for Roads and Bridges of the Georgia
State Department of Transportation.
END OF SECTION
TS-15-1
SECTION TS-16
STORM SEWER SYSTEM
-01. GENERAL:
This section covers the storm drainage system, including pipe culverts and appurtenant
structures, complete.
-02. MATERIALS:
. A. PIPE MATERIALS FOR CULVERTS AND STORM DRAINS:
1. Pipe for Culverts and Storm Drains: Pipe for culverts shall be reinforced
concrete pipe of the class or D-load strength indicated and shall conform to
ASTM C76 or AASHO M 170 with the following additional requirements. Pipe
shall have a readily visible line at least 12 inches in length painted or otherwise
applied on the inside and outside of the pipe at each end by the manufacturer, so
that, when the pipe is laid in its proper position, the lines will be at the top of the
pipe. The line shall be accurately located to indicate the position where the pipe
reinforcing steel is nearest to the exterior surface of the pipe. Non-reinforced
concrete pipe shall conform to the latest ASTM C-14.
2. Pipe may also be corrugated metal pipe which shall conform to the latest
AASHO M-36. Bituminous coating, where required by the drawings, shall
consist of asphalt cement having a minimum thickness of 0.04 inch measured at
the crest of the corrugations. Paved inverts in corrugated metal pipe, where
required by the drawings, shall consist of asphalt cement applied on the inside
of the pipe for one quarter of its circumference (bottom of pipe when installed).
The pavement shall have a minimum thickness of 0.50 inch tapering to 0.1 inch
at the sides.
B. MATERIALS FOR DRAINAGE STRUCTURES
1. Drainage structures, where indicated in the plans shall be of the following types,
constructed of the materials specified for each type and in accordance with the
details shown on the plans.
a. Inlets shall be constructed of reinforced concrete, plain concrete or brick
complete with frames and covers.
b. Headwalls shall be constructed of brick, reinforced concrete or plain
concrete as indicated.
TS-16-1
TS-16-2
2. Concrete and reinforced concrete shall conform to the requirements specified
under the section on "Concrete Construction" of these specifications. Aggregate
shall be as specified in the section on "Concrete Construction" Forms shall be
made of sound lumber and constructed to the shape, form, line, and grade
required, and shall be maintained sufficiently rigid to prevent deformation under
load, and inspected for approval prior to placement of concrete. Water shall be
removed from excavations before concrete is placed. Concrete shall be conveyed
from mixer to forms as rapidly as practicable without segregation or loss of
ingredients. Concrete shall be placed in layers not over 18 inches deep and shall
be spaded and compacted as directed. The concrete covering over steel
reinforcing shall be as shown on the plans, but where not shown, it shall be not
less than 1 inch for covers and not less than 1-1/2 inches for walls and flooring.
Concrete deposited directly against the ground shall have a thickness of at least
3 inches between the steel and the ground. Expansion joint filler shall be
preformed bituminous fiberboard, or wood board except where specifically noted
on the drawings. Surfaces exposed to view shall be a smooth finish with all
blemishes removed. All concrete surfaces shall be cured for at least 7 days by
covering with waterproof paper, or kept moist with cotton mats or burlap as
approved.
3. Mortar for connections to drainage structures shall be composed of one part by
volume of Portland cement and two parts of sand. The Portland cement shall
conform to ASTM CI50-65, Type I or II. The sand shall conform to AASHO
Standard M 45, and shall be of an approved gradation. Hydrated lime may be
added to the mixture of sand and cement in an amount equal to 25 percent of the
volume of cement used. Hydrated lime shall conform to Federal Specification
SS-L-351, TypeM, or ASTM StandardCI41-61, Type A. The quantity of water
in the mixture shall be sufficient to produce a stiff workable mortar, but shall in
no case exceed 7 gallons of water per sack of cement. Water shall be clean and
free of injurious acids, alkalies and organic impurities. The mortar shall be used
within 30 minutes from the time the ingredients are mixed with water. The
inside of the joint shall be wiped clean and finished smooth. In pipe too small
for a man to work inside, wiping may be done by dragging an approved swab or
longhandled brush through the pipe as work progresses. The mortar bead on the
outside shall be protected from air and sun with a proper covering until
satisfactorily cured.
-03.
EXECUTION:
A. EXCAVATION AND BACKFILLING FOR DRAINAGE STRUCTURES
1. Excavation and backfilling for drainage structures shall conform to the
applicable requirements specified herein-before in the section, "Excavation and
TS-16-3
Backfilling." Trenches and pits shall be of sufficient size to permit the placing
and removal of forms for the full width and length of structure footings and
foundations, as shown on the drawings. The dimensions and elevations indicated
on the drawings. are approximate only and may be changed when deemed
necessary to secure satisfactory foundations Bracing, sheeting and shoring shall
be provided where required.
B. INSTALLATION OF PIPE
1. Each pipe shall be carefully examined before being laid, and defective or
damaged pipe shall not be used. Pipe lines shall be laid to the grades and
alignment indicated. Proper facilities shall be provided for lowering sections of
pipe into trenches. Under no circumstances shall pipe be laid in water, and no
pipe shall be laid when trench conditions or weather are unsuitable for such
work. Full responsibility for the diversion of drainage and for dewatering of
trenches during construction shall be borne by the Contractor. All pipe in place
shall have been approved before backfilling. When storm drain pipe terminates
in a new ditch, the headwall or end section, together with ditch pavement, if
specified, shall be constructed immediately as called for on the plans. Ditch
slopes and disturbed earth areas shall be grassed and mulched as required by the
section "Grassing (Bermuda)." The Contractor will be responsible for
maintaining these newly constructed ditches and take immediate action subject
to approval to keep erosion of the ditch bottom and slopes to a minimum during
the life of the contract. No additional compensation will be given to the
Contractor for the required maintenance.
a. Jointing: For concrete and reinforced concrete pipe, joints shall be of the
Bell and Spigot type and installed according to manufacturer's
recommendations using Portland cement mortar. Corrugated metal pipe
joints shall be made by riveting or by means of connecting bands with
bolted couplings in accordance with the manufacturer's recommendations.
b. Alignment: Elliptical concrete pipe with circular reinforcing and circular
concrete pipe with elliptical reinforcing shall be so placed that the reference
lines designating the top of the pipes will be not more than 5 degrees from
the vertical plane through the longitudinal axis ofthe pipe. In all backfilling
operations that Contractor shall be responsible for preventing damage to or
misalignment of the pipe.
C. TESTS FOR PIPE
1. Responsibility and Certifications: The Contractor shall be responsible for having
the pipe he proposes to furnish tested to demonstrate conformance to the
TS-16-4
applicable specifications. Certified copies of the test reports shall accompany
each load of pipe and shall be delivered to the Engineer for review before the
pipe is installed.
2. Strength tests for reinforced concrete pipe shall be the tests of ASTM C-76.
3. Strength tests for concrete pipe shall be the tests of ASTM-C-14.
4. Strength tests for corrugated metal pipe shall be the tests of AASHO 'M-36.
D. TESTING
1. Displacement Test: Mains will be checked to determine whether any
displacement of the pipe has occurred ( a) after the trench has been backfilled to
two feet above the pipe and tamped as specified; and (b) upon completion of the
project. The test will be as follows: A light will be flashed between manholes
or, if the manholes have not as yet been constructed, between the locations ofthe
manholes, by means of a flashlight or by reflecting sunlight with a mirror. If the
illuminated interior of the pipe shows any misalignment, displaced pipe, or any
other defects, the defects designated by the engineer shall be remedied by the
Contractor at his expense.
END OF SECTION
4MOREVISED MAY 2002
SECTION TS-17
MEASUREMENT AND PAYMENT
-01. SCOPE:
This section describes the methods for measurement and payment of all contract bid
items.
-02. MEASUREMENT AND PAYMENT:
The following item numbers correspond to the contract bid items in the proposal
section of these contract documents.
I. SANITARY SEWER AND APPURTENANCES
ITEMS S-1 throueh S-3 - All gravity piping line items shall be measured
in linear feet and shall include costs for piping and installation, trench excavation, trench box,
dewatering, asphalt cutting, normal joints and gaskets, normal backfill, infiltration and exfiltration
testing, mandrel pulling, and CCTV camera inspection as required. Linear measurements shall be
taken through manholes but not through special structures. Camera inspection shall include all costs
for closed circuit camera inspection of the sanitary sewer system, including mobilization,
demobilization, inspection, video tape copies, and field reports. No additional payment shall be
made for these items.
ITEMS S~4 throueh S-7 - All force main piping line items shall be measured
in linear feet and shall include costs for piping and installation, trench excavation, trench box,
dewatering, asphalt cutting, normal or restrained joints and gaskets, normal backfill, pressure and
leakage testing, and pipe flushing. No additional payment shall be made for these items.
ITEMS S-8 throueh S-10 - Jack and bore line items shall be measured in
linear feet and shall include costs for casing piping, carrier piping, installation, blasting, asphalt
cutting, restrained joints and gaskets, end seals, and normal backfill. No additional payment shall
be made for these items.
ITEM S-11 - Select backfill shall be measured in cubic yards and shall
include costs for the backfill and installation as well as all transportation and stockpiling charges.
The volume of material included shall be the actual measured "in-place" volume. The maximum
trench width used to calculate the volume will be 7 feet for force main piping and 10 feet for gravity
piping. No additional payment shall be made for these items.
TS-17-1
REVISED MAY 2002
ITEM S-12 - Miscellaneous pipe fittings and connections shall be measured
in pounds and included costs for all fittings and installation including normal joints and gaskets,
mechanical j oint restraint, etc., regardless of material. No additional payment shall be made for these
items.
ITEMS S-13 and S-15 - Pre-cast manholes shall be measured individually
(each) and shall include costs for manholes up to six feet in depth, excavation, dewatering, asphalt
cutting, collars and boots, grouting and/or other connections, installation, normal backfill, and
vacuum testing as specified. Manhole vacuum testing shall include all costs for testing equipment,
testing labor, mobilization, demobilization and reporting. Manholes failing testing shall be retested
at Contractor's expense. Repairs to failing manholes shall be made external to the manhole utilizing
a method approved by the Augusta Utilities Department. No additional payment shall be made for
these items.
ITEMS S-14 and S-16 - Additional sanitary manhole depth line items shall
be measured by vertical foot and shall include costs for excavation, dewatering, and backfill as
specified by type and class. No additional payment shall be made for these items. Type 1 manholes
shall be connected to pipe 42" or less in diameter, and Type 2 manhole shall be connected to pipe
48" to 84" in diameter. Class 1 additional depth shall apply to each manhole greater then 6-feet but
not more than 10-feet in depth. Payment for Class 1 shall be the actual depth between 6-feet and 10-
feet. Class 2 additional depth shall apply to each manhole greater than 10-feet in depth, but not
exceeding 20-feet in depth. Payment for Class 2 shall be the actual depth of the manhole between
6-feet and 20-feet. Class 3 additional depth shall apply to each manhole exceeding 20-feet in depth,
but not exceeding 30-feet in depth. Payment for Class 3 shall be the actual depth of the manhole
between 6-feet and 30-feet.
ITEMS S-17 and S-18 - All valve line items shall be measured individually
(each) and shall include costs for valve, valve boxes/vaults, manholes, valve extensions, excavation,
dewatering, asphalt/concrete cutting, all associated fittings, installation, normal backfill, and testing.
No additional payment shall be made for these items.
ITEM S-19 - Flow monitoring manholes shall be measured individually
(each) and shall include the costs for manhole, excavation, dewatering, asphalt/concrete cutting, all
associated valves and fitting, installation, normal backfill, and testing. No additional payment shall
be made for these items.
ITEM S-20 - Cut and plug manholes shall be measured individually (each)
and shall include costs for cutting of existing pipelines, plugging of existing pipelines, excavation,
dewatering, asphalt/concrete cutting, and normal backfill. No additional payment shall be made for
these items.
ITEM S-21 - Asbestos cement (AC) water main crossings shall be measured
individually (each) and shall include costs for AC pipe cutting, removal, disposal, excavation, ductile
TS-17-2
REVISED MAY 2002
iron piping, Hy-Max couplings, backfill, and property restoration. No additional payment shall be
made for these items.
ITEM S-22 - Polyethylene pipe encasement shall be measured in linear feet
and shall include costs for pipe wrap materials and installation. No additional payment shall be
made for these items.
ITEM S-23 - Concrete pipe encasement shall be measured in cubic yards and
shall include costs for concrete, installation, excavation, dewatering, soil stabilization, pipe
stabilization, asphalt cutting, and normal backfill. No additional payment shall be made for these
items.
ITEM S-24 - Miscellaneous Class A concrete shall be measured in cubic
yards and shall include costs for concrete, reinforcing steel, embeds, form work, installation,
excavation, dewatering, soil stabilization, pipe stabilization, asphalt cutting, and normal backfill.
No additional payment shall be made for these items.
II. WATER MAIN AND APPURTENANCES
ITEM W -1 - Long side water service connections shall be measured
individually (each) and shall include costs for piping, water meter connection, dewatering,
asphalt/concrete cutting (including service markings), installation, normal backfill, and property
restoration. This line item shall include the cost of reconnection of any existing services, if required.
No additional payment shall be made for these items.
ITEM W -2 - Cut and plug existing water line shall be measured individually
(each) and shall include all costs associated with cutting into an existing line and plugging it as
detailed in the plans and specifications. No additional payment shall be made for these items.
III. PAVEMENT STRUCTURES
ITEM P-l - Asphalt overlay shall be measured in square yards and shall
include costs for asphalt materials and installation, temporary striping and permanent striping
(replaced in kind), and markers (both temporary and permanent). No additional payment shall be
made for these items.
ITEM P-2 - Asphalt driveway/parking lot replacement shall be measured in
square yards and shall include costs for existing asphalt removal and disposal, asphalt, installation,
and site preparation. Existing asphalt shall be removed to the nearest joint as directed by the project
representative. No additional payment shall be made for these items.
ITEM P-3 - Aggregate base (10 Y2" thick) and asphalt patch (2 W' thick) shall
be measured in square yards and shall include costs for all aggregates (regardless of type), 2.5"
TS-17-3
REVISED MAY 2002
aggregate removal and disposal, bituminous tack coat, asphalt, installation, excavation, striping (both
temporary and permanent), and markers (both temporary and permanent). The measurement
calculation shall be based upon a maximum trench width of seven (7) feet for payment purposes.
No additional payment shall be made for these items.
ITEM P-4 - Asphalt pavement leveling shall be measured in tons and shall
include costs for all asphalt (regardless of type) used to create a level road surface prior to asphalt
overlay as authorized by the project representative. The payment shall be based upon confirmed
delivery tickets. No additional payment shall be made for these items.
ITEMS P-5 - Concrete driveways shall be measured in square yards and shall
include costs for removal and disposal. of existing concrete, 3000 psi concrete, installation, site
preparation, formwork, and finishing. Existing concrete shall be removed to the nearest joint as
directed by the project representative. No additional payment shall be made for these items.
ITEM P-6 - Curb and/or gutter removal and replacement shall be measured
in linear feet and shall include costs for removal and disposal of existing curb and gutter, concrete
or asphalt, installation, site preparation, formwork, and finishing. No additional payment shall be
made for these items.
ITEM P-7 - Aggregate surface course shall be measured in square yards and
shall include the costs for all labor, materials and equipment for the site preparation, sub grade and
installation of an aggregate surface in accordance with Georgia Department of Transportation
Specification Sections 318 and 815. Thickness of aggregate surface course shall match existing and
shall be 4-inch minimum.
IV. NUSCELLANEOUS
ITEM M-l - Flowable fill shall be measured in cubic yards and shall include
costs for all materials, labor, equipment, and excess materials. No additional payment shall be made
for these items.
ITEM M-2 - Rock excavation shall be measured in cubic yards and shall
include costs for blasting, labor, equipment, and material removal and disposal. The volume of
material included shall be the actual measured "in-place" volume. The maXimum trench width used
to calculate the volume will be 7 feet for force main piping and 10 feet for gravity piping. No
additional payment shall be made for these items.
ITEM M-3 - Foundation backfill shall be measured in cubic yards and shall
include costs for the backfill and installation as well as all transportation and stockpiling charges.
Quantities shall be verified by trench volume calculation up to maximum trench width of 7 feet for
force main piping and 10 feet for gravity piping. No additional payment shall be made for these
items.
TS-17-4
REVISED MAY 2002
ITEM M -4 - Clearing and grubbing shall be measured as a lump sum and
shall include costs for vegetation removal, stockpiling, disposal and any required permitting. No
additional payment shall be made for these items.
ITEM M-5 - Bypass pumping operations shall be measured as a lump sum
and shall include the cost for all delivery charges, site preparation, pumps, piping, fittings, and labor
necessary to install, operate, maintain and remove the various bypass pumping operations needed
to install the proposed sewer lines and structures. No additional payment shall be made for these
items.
ITEM M-6 - Sod shall be measured in square yards and shall include costs
for materials, installation, transportation, stockpiling, soil stabilization and soil amendments
(fertilizer, etc.) as required. No additional payment shall be made for these items.
ITEM-7 and M-8 - Stone dumped riprap shall be measured in square yards
of accepted material of the specified thickness and shall include costs for riprap, filter blanket,
geotextile fabric, grout or cushioning sand (if required) and installation. Area measurements will
be made parallel to the surface on which the material is place. No additional payment shall be made
for these items.
LUMP SUM CONSTRUCTION
ITEM LS-l- Lump sum construction includes, but is not limited to, the items
described in the bid schedule under Lump Sum Construction. No separate or additional payment
shall be made for these items.
TS-17-5