Date: February 12,2004
Change Order Number: ONE
Project Title 4 -H Club
Original Contract Date: 6-02-03
Owner: ARC
Contractor: Blair Construction
Project Number: 324-06-201060011
P.O. Number: 76968
Justification:
See (Page Two)
TOTAL AMOUNT OF THIS CHANGE ORDER $ (4,560.91)
Ac.~ $+ l~ z.003.
The new contract completion date as a result of this change order is ..u.11)' , 2984 r
Original Contract Amount $ 54,874.59
Previous Change Order
(Increased / Decreased)
This Change Order
(Inereasedl]t Decreased)
$
0.00
$ (4.560.91)
TOT AL CONTRACT WITH CHANGE ORDER(S)
* * * * * * * * * * * * *
Requested By:
n
Submitted By:
Recommended By:
Approved By:
Accepted By:
$ 50,313.68
tllA
Date: 2 - 2 S- -01-
Date: O-o/fJ f/o <I
Date: --:;? / ~ / oL/-
I
Date: 3
Date:
Date: C:;'d-.?- () &t
COPIES: Errick Thompson, P.E., Assistant Director-Engineering
Purchasing, Geri Sams
Kakoli Basu, Accountant - PWE
Pre Construction File
~
\
4-H
CLUB
DRIVE
CHANGE ORDER NO.1
EXPLANATION:
ORIGINAL CONTRACT PRICE ........... $54,874.59
UNDERRUNS .............................. ....... $9,560.91
OVERRUNS(This Change Order) ......(-)$5,000.00*
FINAL PROJECT COST .................... $50,313.68
*This Change Order includes $4,500.00 for additional clearing,
etc. and $500.00 for removal and replacement of a masonry
wall and gates which were not included in the original contract.
The following is a listing which items overran/underran:
TOTALUNDERRUNS OVERRUNS UNDERRUNS
Baled Straw......... .......... ............ .......... ... ..... .$850.00
Silt Fence.......................... I....................... ....$350.00
Agg Surface Cs...................................... ..... ..$675.00
GAB......................................................... ..$2,608.28
Asphalt E Mix............................................ ..$3,268.12
Tack Coat.. ... II .... II .... ..... II I' ..... ... II II ... ..... I' ......$437.50
12" D I Pipe .........................$180.00
Underdr. Pipe............................................. .$1,552.00
TOTALS $9,740.90 (-) $180.00 $9,560.91