Change Order Form
Change Order Number: Seven
Project Title Stevens Creek Road
Original Contract Date: 2-06-03
Owner: ARC
Contractor: Mabus Brothers Construction
Date: 05/17/04
Project Number: 323-04-296823235
P.O. Number: P53950
The following change order is hereby made to the proposal for the above project:
See Attached
TOTAL AMOUNT OF TillS CHANGE ORDER
$ 15,291.81
The date of completion including this change order is
10/8/03
Original Contract Amount
$ 1.157,552.20
Previous Change Order
(Inoreased I Decreased)
This Change Order
(Increased I Deereased)
$ (8,605.10)
$ 15.291.81
TOTAL CONTRACT WITH CHANGE ORDER(S) $ 1.164.238.91
*************
Funding Source/Account Number: 323041
/,/
Requested By:
Date:
Submitted
Date: ()
Date: <;:"l& (I.>y
Date: ~ Iq loLJ
I I /
Date: 7j,/OY
.
Date: ,ire;
I
Recommended B
Approved By:
Accepted By:
CaplES: Enick Tho son, P.E. Assistant Director-Engineering
Purchasing, Geri Sams
Kakoli Basu, Accountant, Public Works
Pre Construction File
...
,'"
Change Order Form Attachment
Stevens Creek Road Improvement Project
Change Order Number Seven
Project No.: 323-04-296823235
EXPLANATION:
Construction of this project was delayed approximately 228 days after the contract was
executed. During this time, there were significant increases in asphalt prices. The
contractor has requested increases in the unit prices of the asphalt contract items. There
were also ground-mounted signs omitted from the original contract as well at a cost of
$400.00. The increases in asphalt prices ($14,891.81) are documented and verified and
the total amount of the change order is $15,291.81. All work is completed on the project.