HomeMy WebLinkAboutSpirit Creek Wastewater Treatment Plant
DOCUMENT NAME:
DOCUMENT TYPE:
YEAR: 1 ql1 w
BOX NUMBER: \
Augusta Richmond GA
5?,'y\\- &ee-"?-
'p ,~{\ t-
CPO-'i\~ DdUl
FILE NUMBER: J 9--l-P ~ \
NUMBER OF PAGES: (0
wGSi e- W.....-t-u I ~+ \'l') ex\.+-
CHANGE ORDER No. 1
NAME OF PROJECT: Engineering Services regarding the Sanitary
Sewer Lift Station and Force Main from the
Horseshoe Sewer Extension to the Industrial
Sewer Line at Allen Station Road.
OWNER: Augusta Richmond County Commission/Council
ENGINEER: Southern Partners, Inc.
The following additions where hereby made to the original scope of
work to be performed:
Provide Field Survey and drawing for the proposed route of
proposed water line at a Lump Sum Cost of, $3,810.00.
Original CONTRACT PRICE:
Change to CONTRACT PRICE:
$46,400.00
$3,810.00
,
The "new" CONTRACT PRICE will be:
$50,210.00
There will be Q additional days required to complete changes.
Requested By:
~.~
~4A~ )').tJ /11 (
,
Date
Ge rge McElveen, Director
Water & Sewerage Department
Approved By:
Augusta Richmond County
Engineering Services Committee
Date
Approved By:
%tYe'1b
Z E 1i35 Telfair Street
Ted W, Ellis, P,E" Chm, of Board, Emeritus rii Augusta, Georgia 30901.2494
J, J, Tankersley, P,E., President E N GIN E E R S
J, R, Armstrong, P,E" Vice-President
Jorge E, Jimenez, P,E" Secretary
J, T, Eubanks, P,E" Treasurer
C. D, Drown, P,E,
ZIMMERMAN, EVANS AND LEOPOLD, INC.
(706) 724-5627
March 18, 1996
9206
Mr. George McElveen, Director
Augusta-Richmond County Utilities Dept.
2760 Peach Orchard Rd,
Augusta, GA 30906
Re: Change Order #2
Spirit Creek Wastewater Treatment Plant
Dear George:
As we discussed last week, four copies of Change Order #2 for the Spirit Creek
Wastewater Treatment Plant are enclosed for signature,
This change order work was completed between August 8 and August 15, 1995, The
work was performed in accordance with a job site decision necessitated by the discovery
that the existing 24" line was out of round, In order to install the new added valve, it was
necessary to purchase adapter rings and to hold the excavation open until delivery of the
necessary materials,
We have checked the Contractor's support data and recommend this change order be
added to the contract. Please return two signed copies to us, one of which will be sent to
the contractor,
Very truly yours,
ZIMMERMAN, EVANS AND LEOPOLD, INC,
~~E
JRA/nt
Enclosures: 4 copies CO#2
~. .
9206-001.DOC
CHANGE ORDER
Order No, 2
Date March 7, 1996
Agreement Date December 7, 1993
PROJECT:
SPIRIT CREEK WASTEWATER TREATMENT F AClUTlES, PHASE II
OWNER:
BOARD OF COUNCIL-COMMISSIONERS OF AUGUST A-RICHMOND COUNTY,
GEORGIA
CONTRACTOR: G,E, MOORE DIVISION OF M.B, KAHN CONSTRUCTION, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION:
Because the existing 24" ductile iron pipe was out-oi-round, installation of a valve in the line -between Pond lA
& IE required installation of adapter rings; also closing the excavation was delayed by the time needed to obtain
the appropriate rings,
CHANGE TO CONTRACT PRICE:
Original CONTRACT PRICE
$1,488,000,00
Current CONTRACT PRICE adjusted
by previous CHANGE ORDERS
$1,488,562,00
The CONTRACT PRICE due to this
CHANGE ORDER will be (increased)
by:
$ 10,903,73
New CONTRACT PRICE including this CHANGE ORDER
$ 1,499,465,73
CHANGE TO CONTRACT TIME:
The CONTRACT TIME will be (increased) by -1L calendar days,
Requested by M,B, Kalm Construction Co,
The date for completion of all work:
Ordered by
Accepted by
Augusta-Richmond County W&S System
Signature
Date
CQ-2
CHANGE ORDER
Order No, 2
Date March 7, L996
Agreement Date December 7, L 993
PROJECT:
SPIRIT CREEK W ASTEW A TER TREATMENT F ACILlTIES, PHASE II
OWNER:
BOARD OF COUNCIL-COMMISSIONERS OF AUGUSTA-RiCHMOND COUNTY,
GEORGIA
CONTRACTOR: G.E MOORE DIVISION OF M,8, KAHN CONSTRUCTION, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION:
Because the existing 24" ductile iron pipe was out-of-round, installation of a valve in the line between Pond I A
& 18 required installation of adapter rings; also closing the excavation was delayed by the time needed to obtain
the appropriate rings,
CHANGE TO CONTRACT PRICE:
OriginaL CONTRACT PRICE
$1.488,000,00
Current CONTRACT PRICE adjusted
by previous CHANGE ORDERS
$ 1.488,562,00
The CONTRACT PRICE due to this
CHANGE ORDER will be (increased)
by:
$ 10,903,73
New CONTRACT PRiCE including this CHANGE ORDER
$ L499A65,73
CHANGE TO CONTRACT TIME:
The CONTRACT TIME will be (increased) by ~ calendar days,
The dale for completion of all work:
Januarv 26, 199_5._
Requested by M,B, Kahn Construction Co,. Inc,
Ordered by
Accepted by
Augusta-Richmond Countv W&S System
Signature
Date
CQ-2
CHANGE ORDER
Order No, 2
Date March 7, 1996
Agreement Date December 7. 1993
PROJECT:
SPIRIT CREEK W ASTEW A TER TREATMENT FACILITIES, PHASE II
OWNER:
BOARD OF COUNCIL-COMMISSIONERS OF AUGUST A-RICHMOND COUNTY,
GEORGIA
CONTRACTOR: G,E, MOORE DIVISION OF M,8. KAHN CONSTRUCTION. INC.
The foUowing changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION:
Because the existing 24" ductile iron pipe was out-of-round, instaUation of a valve in the line between Pond IA
& IB required instaUation of adapter rings: also closing the excavation was delayed by the time needed to obtain
the appropriate rings,
CHANGE TO CONTRACT PRICE:
Original CONTRACT PRICE
$1.488.000,00
Current CONTRACT PRICE adjusted
by previous CHANGE ORDERS
$1.488,562,00
The CONTRACT PRICE due to this
CHANGE ORDER ,,,ill be (increased)
by:
$ 10.903,73
New CONTRACT PRICE including this CHANGE ORDER
$ 1.499.465,73
CHANGE TO CONTRACT THvlE:
The CONTRACT TIME will be (increased) by ~ calendar days,
Requested by M,B, Kahn Construction Co,
The date for completion of all work: n Jan!!ElI 26;..J,2~i.-:.",,,
Ordered by
Accepted by
Augusta-Richmond.Countv W&S Svstem
Signature
Date
CO-2
, .
CHANGE ORDER
Order No, 2
Date March 7. 1996
Agrcement Date Deccmber 7, 1993
PROJECT:
SPIRIT CREEK W ASTEW A TER TREA TtvlENT F ACILlTIES, PHASE II-
OWNER:
BOARD OF COUNCIL-COtvlMISSIONERS OF AUGUSTA-RICHMOND COUNTY,
GEORGIA
CONTRACTOR: G.E, MOORE DIVISION OF M.B, KAHN CONSTRUCTION, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION:
Because the existing 24" ductile iron pipe was out-of-round. installation of a vah'e in the line between Pond 1A
& IB required installation of adapter rings: also closing the excavation was delayed by the time needed to obtain
the appropriate rings,
CHANGE TO CONTRACT PRICE:
Original CONTRACT PRICE
$1.488,000,00
Current CONTRACT PRICE adjusted
by previous CHANGE ORDERS
$1.-n~8,562,OO
The CONTRACT PRICE due to this
CHANGE ORDER will be (increased)
by:
$ 10,903,73
New CONTRACT PRICE including this CHANGE ORDER
S U9l),465,73
CHANGE TO CONTRACT TltvlE:
The CONTRACT TItvlE will be (increased) by ----'..::L- calendar days,
Requested by tvl.B, Kahn Construction Co.. 1nc,
Januarv 26, 1995
The date for completion of all work:
Ordered by
- / -?-~
3/rBff (
Accepted by
Augusta-Richmond Countv W&S S\'stem
Signature
Date
CO-2