HomeMy WebLinkAboutSMITH FENCE CO CHANGE ORDER TWO
~
DISTRIBUTION:
CHANGE ORDER
Owner
FAA Atlanta ADO
Contractor
LPA - Columbia
McMillan Enterprises
No.
TWO (2)
PROJECT:
Augusta Regional Airport
Augusta, Georgia
Augusta Aviation Commission
1501 Aviation Way
Augusta, Georgia 30906
Smith Industries DBA Smith Fence Co.
4699110 Ave North
Clearwater, FL 33762
DATE OF ISSUANCE:
May 31,2006
OWNER:
(Name,
Address)
CONTRACTOR:
OWNER'S Project No.
ENGINEER:
THE LPA GROUP INCORPORATED
P.O. Box 5805
Columbia, SC 29250
CONTRACT FOR:
FAA. A.I.P. Project No. 3-13-0011-25 and 26
Perimeter Fencing Improvements
ENGINEER'S Project No.
CC209026.4e
You are directed to make the following changes in the Contract Documents.
Description: See Attachment 'A'
Purpose of Change Order:
See Attachment 'A'
CHANGE IN CONTRACT PRICE:
Attachment 'A' Summary of Final Quantities
The LPA Group Inc. letter dated March 31, 2006
Smith Fence email dated May 5, 2006
CHANGE IN CONTRACT TIME:
Original Contract Time
Attachments: (List documents supporting change)
Original Contract price
$
885,102.12
180 Calendar Days
days or date
Net change from previous Change Orders
Previous Change Orders No.
o
to No.
1
$
44,287.02
21 Calendar Days
days
Contract Time Prior to this Change Order
Contract Price prior to this Change Order
$
929,389.14
201 Calendar Days
Net Increase ('<lwl,,-Me) of this Change Order
Net Increase (inrillu) of this Change Order
$
2,964.90
81 Calendar Days
days
Contract Time with all approved Change Orders
Contract Price with all approved Change Orders
$
932,354.04
282 Calendar Days
nATF'
Engineer
s-h//o~
APPROVED' tj--
~y U --::(4 .
nAn'. '( ( ,-J~ f.
RECO~ND~ ~
YA--~UJ1 --
by
nATF' l.A'l-')..yoll
ATTACHMENT "A"
CHANGE ORDER NO.2
Augusta Regional Airport
FAA. A.I.P. Project No. 3-13-0011-25 and 26
,Perimeter Fencing Improvements Project
The purpose of this change order is to add the pay items and unit prices as described below and to adjust all quantities
to reflect the as-built final quantities as paid in the final pay request and as shown on the attached Summary of Final
Quantities. This change order also adjusts the contract time for weather related delays (rain and dry out days),
and additional time for change order work.
Item No. 22
In lieu of providing two new 24' Single Leaf Cantilevered Gates the existing gates were modified in the field at a
savings of $5,167.35 to the project.
CHANGE:
FROM
ITEM NO.
22
F-162N
DESCRIPTION
24' Single Leaf Cantilevered Slide
Gate
QUANTITY
2
UNIT
EACH
UNIT PRICE
$5,067.00
AMOUNT
$10,134.00
TO
ITEM NO.
22
F-162N
C.O.#2
DESCRIPTION
Field Modification of 24' Single
Leaf Cantilevered Slide Gate
QUANTITY
2
UNIT
EACH
UNIT PRICE
$2,483.33
AMOUNT
$4,966.65
Net Change of Item No. 22
($5,167.35)
Item No. 32
During the course of construction and in conjunction with the terminal project the route of the fence line was altered to
run around the terminal contractor's laydown yard. This eliminated the need to clear and grub a section of fence line
that was to run along Doug Barnard Parkway.
ADD
ITEM NO.
32
C.O.#2
DESCRIPTION
Credit for Elimination of Clearing
and Grubbing
QUANTITY
1
UNIT
L.S.
UNIT PRICE
($900.00)
AMOUNT
($900.00)
Item No. 33
Additonal wildlife ditch treatment was added to the smaller ditch crossings that run along Doug Barnard
Parkway. The original bid item was lump sum for the two ditch crossings shown in the drawings. This
items pays for the remaining three minor ditch crossings.
ADD
ITEM NO.
33
C.O.#2
DESCRIPTION
Additional Wildlife Ditch Treatment
QUANTITY
1
UNIT
L.S.
UNIT PRICE
$1,084.00
AMOUNT
$1,084.00
TOTAL INCREASE DUE TO CHANGE ORDER NO.2
($4,983.35)
ATTACHMENT "A"
CHANGE ORDER NO.2
Augusta Regional Airport
FAA. A.I.P. Project No. 3-13-0011-25 and 26
Perimeter Fencing Improvements Project
SUMMARY OF CONSTRUCTION COSTS
Original Contract Amount
Change Order No. 1 Amount
Contract Amount thru Change Order No.1
Change Order No.2 Amount New and Revised Items
Change Order NO.2 Final Quantity Adjustment
Change Order No.2 Total Amount
FINAL AS-BUILT CONTRACT AMOUNT
SUMMARY OF CONSTRACT TIME AND EXTENSIONS
Original Contract Time
Change Order No.1 Time Extension
Contract Time Thru Change Order NO.1
Chanae Order No.2 Time Extensions
Weather Extensions
Delay in Change Order 1 and Additional Mow Strip
Extension for dry out from water released onsite
by Augusta Utilities
FINAL CONTRACT TIME
$885,102.12
$44,287.02
$929,389.14
($4,983.35)
$7,948.25
$2,964.90
$932,354.04
180
21
201
37
30
14
282
FINAL QUANTITIES
Augusta Regional Airport
Perimeter Fencing Improvements ProjeCt
Item Spec.
No. No. Description Unit QTY Unit Price Final Amount
I 00800 Supplementary Insurance Provision 1 $21,467.00 $21,467.00
2 01000 Mobilization 1.00 $24,666.66 $24,666.66
3 S-140A Remove Existing Six-Strand Barbed Wire and Arms 17,141 $0.20 $3,428.20
4 S-140B Remove Existing Chain Link Fence (5'-6') 17,141 $1.40 $23,997.40
5 S-140C Remove Existing Single Leaf Manual Swing Gate (3'-14') 13 $53.34 $693.42
6 S-140D Remove Existing Dual Leaf Manual Swing Gate (12'-24') 7 $106.67 $746.69
7 S-140E Remove Existing Electric Gate (12'-24') 3 $160.00 $480.00
8 S-140F Remove Existing Wooden Fence (5'-6') 16 $6.67 $106.72
9 S-140G Remove Existing Concertina Wire 16 $6.67 $106.72
10 F-162A 7' Chain Link Fence 33,354.00 $11.59 $386,572.86
II F-162B Mow Strip/lntrusion Barrier 'A' For New Fence 35,276 $8.50 $299,846.00
12 F-162C Mow Strip/lntrusion Barrier 'B' For Existing Fence 0 $8.50 $0.00
13 F-162D 24' Dual Leaf Manual Swing Gate 3 $1,066.70 $3,200.10
14 F-162E 20' Dual Leaf Manual Swing Gate 6 $1,034.00 $6,204.00
15 F-162F 16' Dual Leaf Manual Swing Gate 9 $1,034.00 $9,306.00
16 F-162G 14' Dual Leaf Manual Swing Gate 0 $1,034.00 $0.00
17 F-162H 12' Single Leaf Manual Swing Gate 3 $867.00 $2,601.00
18 F-162J 4' Pedestrian Gate 9 $1,334.00 $12,006.00
19 F-162K 24' Dual Leaf Electric Swing Gate I $25,334.00 $25,334.00
20 F-162L 20' Dual Leaf Electric Swing Gate 1 $25,334.00 $25,334.00
21 F-162M 12' Single Leaf Electric Swing Gate 1 $15,334.00 $15,334.00
22 F-162N 24' Single Leaf Cantilevered Slide Gate 2 $2,483.33 $4,966.65
23 F-162P Six-Strand Barbed Wire 35,672 $0.30 $10,701.60
24 F-162Q Wildlife Ditch Treatment 1 $2,000.00 $2,000.00
25 Plans Pedestrian Gate Sign 20 $36.00 $720.00
26 Plans Electric Gate Sign 4 $36.00 $144.00
27 Plans Padlock Gate Sign 10 $36.00 $360.00
28 Plans Door Sign 20 $36.00 $720.00
29 Plans Restricted Area Sign 190 $36.00 $6,840.00
30 CO#1 Relocate Gate W 1 $500.00 $500.00
31 CO#I Install Fence at ASR on Angle to match existing fence 2,318 $18.89 $43,787.02
32 CO#2 Credit for Elimination of Clearing and Grubbing I -$900.00 -$900.00
33 CO#2 Additional Wildlife Ditch Treatment I $1,084.00 $1,084.00
TOTAL CONSTRUCTION $932,354.04
L_. ~~;o~~n ~~S~~ INCORPORATED
March 31, 2006
700 HUGER STREET. P.O. BOX 5805. COLUMBIA, SC 29250.803-254-2211 . FAX 803-779-8749
Mr. Raymond Smith
President
Smith Industries dba Smith Fence Co.
4699 110 Ave. North
Clearwater, FL 33762
VIA EMAIL AND USPS
I'
Eliminating two (2) 24' Single Leaf Cantilevered Slide Gates,
Sleeving fence posts for new fence in pavement in lieu of having to install temporary fence, augering
and installing new fence posts in concrete (approximately 700 linear feet),
Elimination of clearing and grubbing of fence line along Doug Barnard Parkway at entrance to Air
Cargo Facility, and the
Elimination of the wildlife intrusion barrier in the mow strip around the buildings and in pavement.
i
I
I
l
~.
I.
l
I.
RE: Perimeter Fencing Improvements Project
Augusta Regional Airport
FAAA.I.P. Project No. 3-13-0011-25&26
Dear Mr. Smith:
Please provide us a cost credit for the following items:
Also, your last pay application requested five (5) wildlife ditch treatments at $2,000 for a total of $10,000. The
pay item in the contract is a lump sum pay item of $2,000.00 for the two large ditch treatments that are shown
on the drawings, a total of 155 linear feet which equates to $12.90 per linear foot. Three additional ditch
treatments totaling 84 linear feet were added in the field at the request of the Owner which based on $12.90 per
linear foot is $1,084. In the fmal change order we will include a pay item for this additional work for the lump
sum price of $1,084.
I.
i.
r
If you should have any questions or concerns regarding this matter, please do not hesitate to contact us at (803)
254-2211
Sincerely,
I
i.
THE LPA GROUP INCORPORATED
~ A~/~ ---=:::-.
Tom Lochstampfor
Construction Manager
cc: Mr. Tim Weegar
Mr. Andy Busbee
Mr. David McMillan
File: CC209026.lg
ATLANTA. BATON ROUGE. CHARLESTON. CHARLOTTE. COLUMBIA. GREENSBORO. GULFPORT . JACKSONVILLE
KNOXVILLE . UTTLE ROCK . MOBILE . ORLANDO . RALEIGH . SARASOTA . TAllAHASSEE . TAMPA . WEST PALM BEACH
.
.
CREDITS MARCH 31 ST LETTER
Page 1 of 1
Lochstampfor, Tom
From: Ray Smith [rsmith@smithfence.com]
Sent: Friday, May 05, 200611:01 AM
To: Lochstampfor, Tom; Ray Smith
Subject: CREDITS MARCH 31ST LETTER
Tom,
In reply to your March 31st letter.
1. The elimination of the two 24' gate. We reworked the two gates to make them adaptable to the higher fence installation. We
removed both gates, welded the extensions on them and then reworked with new material. The revised total for the two gates
should be $4,966.65.
2.The area for the sleeved fence. In fairness, I feel this should be a wash. The Owner was concerned that all of the
underground was not locatable, that the damage to the area would be disruptive. On SFC part, we had to purchase much larger
fence material to adapt to the existing material. We held off on this area for a long time waiting for the final decision from the
Owner and then waiting for the extra material causing out of sequence work.
3.Elimination of the clearing and grubbing. The area is approximately .30 of an acre. Clearing and grubbing is approximatly
$3000/ acre which equates to a $900 Credit due the Owner.
4.The elimination of the wildife intrusion barrier in the mow strip should be a wash also. This area around the buildings was not
shown on the plans and was added. Do not believe that mow stip was ever shown in the paved areas. The area which was
poured is completely chopped up with short runs causing a much longer time and cost for the installation.
5. In regards to the wildlife ditch treatments I am in agreement with the change order relfecting an additional $1,084.00
If you have any questions or concerns please contact me.
Thanking you in advance.
Ray Smith
R,,~
cfw~ f"...
~@~.HIl
25fHH"~
121-57J-5HO