Change Order Form
Change Order Number: One
Project Title Raes Creek Sec III
Original Contract Date: 06-07-04
Owner: ARC
Contractor: Blair Construction Company.
Date: 10-14-04
Project Number:326-04-288811357 ~
P.O. Number: P95005
. The following change order is hereby made to the proposal for the above project:
See Attached
TOTAL AMOUNT OF THIS CHANGE ORDER
$ 9,840.00
The Contract time will be increased by ~ calendar days from the notice to proceed
date.
Original Contract Amount
$ 897,894.80
This Change Order
(Increased / Decreased)
$ 9,840.00
TOTAL CONTRACT WITH CHANGE ORDER(S)
$ 907.734.80
*************
Requested By: Date: /~/19/dY
/ I
Submitted By, Date: 10 p,Sfu L(
Finance Endorsement: Date: tv I ~rl 0 r
Recommended By: Date: / "/l.//t:. ~
,
Approved By: Date:
Accepted By: Date: Iv -jf- t> r
,
COPIES: Errick Thompson, P,E. Assistant Director-Engineering
Purchasing, Geri Sams
Kakoli Basu, Accountant, PWE
Pre Construction File
.".
';;
Project :Raes Creek. Sec. II
Project No.: 326-04-288811357
An existing 30" corrugated metal pipe located undemeath the roadway at station 8+83 in
the Willow Creek subdivision needs replacement due to extensive pipe corrosion, 30"
RCP storm drain pipe will be used to replace the existing corrugated metal pipe. 15" RCP
storm drain pipes where suggested to be placed at station 4+76 to help relieve flood
waters if flooding should accure.
Item No. Added Items Unit Q1Y: Unit Price Total
550-1150 Storm Drain Pipe, LF 40 $38.25 $1,530.00
RCP, 15 IN, HI -10
550-1300 Storm Drain Pipe, LF 60 $90,00 $5,400.00
RCP, 30 IN, H 1-10
550-4215 Flared End Section, EA 2 $525,00 $1,050.00
15 IN
550-4230 Flared End Section, EA 2 $930.00 $1.860.00
30 IN
Total: $9,840.00
(
~.
0C~.08'2004 08:10 7068681855
BLAIR CONSTRUCTION
#4737 P,002l002
..
..'
.:.\
9JlaiJt fomtJtudio.n, inc.
P.o. Box 770
Evans, Georgia 30809 Ph.one (706) 868~1.950 Fax (706) 868-1855
October 7,2004
AUGUSTA PUBLfC WORKS & ENGINEERING DEPARTMENT
1615 Marvin Griffin Road
Augusta, GA 30906
Attn: Rlcl<y I_a Brew
Re: Rae's Creel< Section III
Project No. 326-04-288811357
Mr, La8rew,
Your department has requested a quote from uS for the installation of additional rlJns of 12" St.orm Drain
and 30" Storm Drain for t.he above noted project. Our supplier has advised that 15" Is the smallest
diameter tlley produce,
We respectfully sIJbmlt the below itemized quotes for the furnislling and installing (If:
. 60 LF of 30" RCP Storm Drain @ $90,00 per LF ,... ..... .,...... ".. $5,~OO.OO
. 2 Each of 30" Flared End Sections @ $930.00 per Each .......... $1,860.00
. 40 f_F of 15" RCP Storm Drain @ $38.26 per LF ... .,..... '......... $1,530,00
. :2 Eech of 15" Flared End Sections @ $525.00 per F-acl, ........... $1,050,00
Gre~d Total: ................~.:......:...$9,840,OO
If above worl< is accepted, we would require a contract time extension of three (3) weeks.
Sincerely, JIi~./
W~,<, ",.. .;r ...
William R. Mutlmer Jr.
Project Manager
rc: file