HomeMy WebLinkAboutMCKNIGHT CONSTRUCTION CO CHANGE ORDER NO20 $150,000.00
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELD
CHANGE ORDER NO. - 20
June 15,2008
MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS:
See Attached Change Order #20 Summary
Original Contract Sum ...................................$
25254.193.00
Change by Previous Change Order.... .. .. . . .. .. .. .....$
1.099.682.66
Contract Sum Prior to this Change Order. . . . . . . . . . . ..$
26.353.875.66
This Change Order........ ............................ ...$
150.000.00
New Contract Sum .................................... ...$
26.503 .875.66
Contract Time will be as follows: 0 Calendar Days are added to the duration of the Proiect
Signed by:
~ JCKnight Construction Co., Inc.
~~
-
7.1".0<\
DATE
The LP A Group, Inc.
U~A.~
Mayor of August
ct/1lcR ~~~
DATE at:~
Must be signed bv Construction Manager. Architect. Owner. Mayor and Contractor
Cc: All Signers
Item No.
Item Description
A
Exterior Signage Package
Change Order #20 Summary
May 1, 2008
Quantity
Unit
Unit Cost ($)
LS
$150,000.00
Total
$150.000.00
Total ($)
$150,000.00
$150,000.00
Time Extension
(Days)
o
o
S:ICM FileslCa 20
Augusta Regional Airport
Exterior Sign Package
Sign Type
A-1
A-2
A-4
8-1
8-2
8-3
Quantity
2
Unit Cost Total Cost
$34,937.00 $34,937.00
$17,888.00 $35,776.00
$13,640.00 $13,640.00
$4,394.00 $39,546.00
$2,301.00 $13,806.00
$849.00 $2,547.00
$473.00 $946.00
Sub-Total $141,198.00
McKnight Mark-Up (7%) $9,883.86
Total $151,081.86
USE NOT-TO-EXCEED $150,000.00
9
6
3
2
. '
Augusta Regional Airport
Exterior Signage Package
April 24, 2008
Background
The Augusta Regional Airport Terminal Construction Project was bid as a base bid
package with a total oftwo (2) Additive Alternates. The first additive alternate included
an Exterior and Site Signage Program. The second additive alternate was for Long Term
Parking Expansion. The purpose for including these alternates was to add either or both
of the alternate packages as the bid results permitted. The bid results received did not
permit acceptance of either of the additive alternates, so neither was exercised as a part of
the Terminal Contract.
As the project has progressed, the Airport Administration and the Aviation Commission
determined a certain portion of the Exterior and Site Signage Program would be required.
These signs were primarily located on the curbside drop-off and pick-up areas of the
Terminal and along the main entry road to the Terminal. These signs were fabricated and
installed in time for the Terminal opening in December of2007.
Over the past several months of operation, the Airport Administration has determined
that additional directional signage would add to the clarity to traveling public. The
signage would be of the same design and fabrication as the signs of the Terminal
curb front and unify the entire package from entry to the airport grounds until they depart
the facility.
The Exterior and Site Signage Program was initially bid at a cost of$296,639.00. The
Construction Manager on behalf of the Aviation Commission and the Airport has gone
through a value engineering process. This process included identifying specific signs that
would be required in the final Exterior Signage Package presented. In addition,
discussions were conducted with the signage fabricator and the signage designer to
develop ways to construct the signs and minimize the end costs of the signs. This process
has resulted in the sign types shown on the attached spreadsheet. The signs shown
represent signage on the main loop to the Terminal and then back to Doug Barnard
Parkway.
The final quantity, types and value of all signs will be negotiated by the airport staff and
the Contractor. The total cost will not exceed $150,000.00.
Office Of1he Administrator
Frederick l. Russell, Administraror
Room 801 . Municipal Building
530 Greene Street - AUGUSTA, GA. 30901
(706) 821-2400. FAX (7(6) 821-281'
www.lIugUSQlgll.gOV
TlImeka Allen, Interim Deputy Administr..ror
Robert Leverett, Interim Deputy Administrllror
May 20, 2008
Ms. Tammy Strange
Interim Director - Augusta Regional Airport
1501 AViation Way
Augusta, GA 30906
Dear Tammy:
The Augusta-Richmond County Commission, at their regular meeting held on Tuesday, May 20,2008, took
action on the following items.
10. Approved the reclassification of the Airport Oirector's position. The change in job description and
classification upgrades the position to a pay grade 65 from a pay grade 61.
- -- --
20. fApproved Termin,al Construction Project Change Order #20 - Exterior-Signage~Package;-(Approved. b>q
c..public Services Committee May 12, 2008) f
L J~
29. Approved to adopt ;:I proposed ordinance to regulate off airport rental car concessions at the Augusta
Regional Airport; to amend the Augusta-Richmond County Code; to repeal all ordinances and partS of
ordinances in conflict therewith; to provide for severability; to provide an effective date therefore and for
other purposes as stated In said ordinance. (Approved by Finance Committee May 12, 2008)
If you have any Questions, please contact me.
Yours truly,
Frederick l. Russell
Administrator
cc: Ms. Donna Williams
Ms. Gerl Sams
Mr. Mike Blanchard
05-20-Q8: 1110, '20, #29