HomeMy WebLinkAboutMCKNIGHT CONSTRUCTION CO CHANGE ORDER NO 21 $22,844.87 ._-; '-, TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 21 June 25, 2008 MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: See Attached Change Order #21 Summary Original Contract Sum ...................................$ 25.254,193.00 Change by Previous Change Order.................. ...$ 1,099.682.66 Contract Sum Prior to this Change Order... . . . . . . . . ..$ 26.503.875.66 This Change Order................. ....... ...............$ 22.844.87 ~ New Contract Sum.......................................$ 26.526.720.53 Contract Time will be as follows: 0 Calendar Days are added to the duration of the Proiect Signed by: ~ V McKnight Construction Co., Inc. ~- The LP A Group, Inc. 1.'bl~fS DATE 11 260>> DATE Cj)~.~ Mayor of Aug ta 1,/ ~/o~ J I DATE~\% Must be signed by Construction Manager. Architect. Owner. Mayor and Contractor Cc: All Signers