HomeMy WebLinkAboutMCKNIGHT CHANGE ORDER 7
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELD
CHANGE ORDER NO. - 7
June 28, 2006
MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS:
See Attached Change Order #7 Summary
Original Contract Sum ................................. ..$
25,254,192.45
Change by Previous Change Order.................. ...$
131.022.16
Contract Sum Prior to this Change Order. . . . . . . . . . . ....$
25,385,214.61
This Change Order. . . . . . . . . .. . . . . . . .. .. . . . .. . .. . . . . . . . .. . $
49,494.94
New Contract Sum '" ..... ..... ..... ...... ...............$
25,434.709.55
Contract Time will be as follows: 12 Calendar Days are added to the duration of Phase 3
and the Total Contract Duration
Signed by:
~) J rI1llnA 4\~ltI" ~ ~
r MciUM'@On~!o;:; Co., Inc. DAlE
JuoJe 2~ ~O~
DATE
~'2G).O~
DATE
DATE
C L-e:-~ rz a F l cJ.I""' cI-1. : \ >-. f ""'
onstruction Mana er. Architect Owner Ma or and Contractor
Cc: All Signers
6/28/2006
1:40 PM
Change Order #7 Summary
Item No Item Description Quantity Unit Unit Cost ($) Total ($) Time Extension
(Days)
A Lower Ceiling Heights LS 58,436.46 58,436.46 0
B Furnish & Install LS 5,100.00 5,100.00 0
Weathervane
C Install Temp. Acoustical LS 11,648.07 11,648.07 0
Ceiling in Connector Hallway
D Additional Fire Pump Startup LS 1,312.89 1,312.89 0
E Credit for Type 10 Glass LS (44,374.34) (44,374.34) 0
F Provide Power to Re-circulation LS 625.52 625.52 0
Pumps WH2, WH4 & WH5
G Credit for Type N LS (2,626.80) (2,626.80) 0
Light Fixture
H --Provide Power to Exit Si9ns @ LS 423.05 423.05 0
Holding Room Ramps
Provide Doors/Hardware for LS 10,187.26 10,187.26 0
Emergency Egress @ Ramps
J Patch Existing Walls in USAir LS 3,023.82 3,023.82 0
Building
K Rental Car Trailer"Mods LS 2,861.11 2,861.11 0
L Power to Battery Charger LS 790.10 790.10 0
@ Gate 4
M Power to Java Hut LS 1,840.35 1,840.35 0
N Communications Conduit LS 247.45 247.45 0
for Jetways
0 Phase 2 Early Completion 12
Total $ 49,494.94 $ 49,494.94 12
(Share Directory)\Z:\CM Files\CO 7
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 7, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport
Augusta, GA
PR 19 (Revised)
Gentlemen:
The following is a revised cost proposal for the summary of costs associated with the change in
IR93, IR95, IR100, IRI03, and IN-17.
Sl!b IR -93 IR-lOO IN-17 Subtotal
Smith 9,890.79 9,890.79
CI Electric 12,130.94 6,722.43 18,853.37
Simplex ~"llql.3.0't ~~,1~5.'6\ ~'lIDY8.8S
Bonitz 5,250.00 1,200.00 1,200.00 -7,650.00
AFP 3,472.00 3,472.00
Mastercraft 4,572.50 4,572.50
Davis Paint 1,475.00 (349.00) 1,126.00
5'i ("1~.SI
$30,166.70 $23,124.73 $4,672.00 ~
McKnight 7% OIP $~,&t.q5
Total ~
~ ~(g~jr\W~1ffi
ml JUN 0 9 2006 JW
BY: ____________________
t~~'01'I3(,,~
---------------..---~-
. 1\ \
1\0 )VSIt-.-\E.~'T~ RE.VIE.ufP ~ 1-\G..l'i..cE.D )
. wt ft>o.,,\" r"'::n:\C..K. DN o{,(28[ot-. I
'~
03 06 10:45a
UJIU~/~UVO UI.~'
McKnight Const~uction Co. 706-772-82~~
Ot:.l.jO.J. 'j'.L.l:'O I ~V.L=> if-U.N I J.1'i\:2
F.e
r-1-t1..:Jc:.. CJ.L
\ R.- q ~
P.O. Box 6097
North Augusta,SC. 29861
Ph: 803-441-6464
Fax:803-819-1257
Davis Painting.
Contractors,InC.
\
Change In Scope
To: Lee Mooney
Fax: 772-8283
From: Richard Littleton
Phone: 772-8282
.Pr'!lect Augusta Regional Airport
Pages: One
Date: March 2, 2006
o Urgent 0 For Revkw 0 Please Connnent 0 Please Reply 0 Please: Recycle
. Comments:
Lee,
The following i~ the additive amount for the additional painting and walJ
covering work to occur in the area previously noted as Room 127 as
outlined in IR- 93 :
Labor ------ ---$733.00
Materials -- ---- 742.00
Total Add $1,475.00
If you have any questions please do Dot hesitate to contact me.
-Sincerely,
Davis Painting ContractorS, Inc.
.~~
Richard Littleton, Vice president
___J~JQ__?~__}iat__~Jyi~!L.___
_._____.._~__ ~: t f.vv~
--r-}- ( .- ._--:~-_.._.-----_._--...._--.- '. ,/
.______.____.___.~~.~..~__~l_l~_. l)V
. . -..-----.------...-- '''''
rR~loo
P.O. Box 6097
North Augusta, SC. 29861
Ph: 803-441-6464
Fax:803-819-1257
- Davis Painting
Contractors,InC.
Change In Scope
To: Lee Mooney
From: Richard Littleton
Fax:
Pages: 0 r--e.
Date: S / J I / 0 /:;
Phone:
Projecp. Augusta Regional Airport
Additional Work Reauested: Ce; \ 'J I,..... f20ov-<, A I d Q, A I;)],
I~ \d. b J, A \;2,!S" wo.5 I uvv-<r/J S' del e,-h^..5. s~
r- c..s (A \,...~^ h.l: del lYe. c! 0 c C ur'C tJ
r r-- +h u c..r-.. to.. p r- I u-r 'k> f\ 0 -h f,e c. ~ Uv1 orb c ~
The following -8fe the additional eAarges for the work as herein described:
I ~ C iLd I' t -
Labor Cost---
4- ~ II b . U'\)
lo3.CV
Material Cost
Subtotal
--f J l/ '7 I 6V .
Overhead and Profit --
Cr-c cf j't' .
TOTAL extr-cr-eMrge--------
<$ J</~.0\)
Please fax confirmation to our office if this change is accepted.
Sincerely,
Richard Littleton
;2 t~K
~ 111.-\00
Smith Bros. Mechanical Contractors, Inc.
Post Office Box 15547 . Telephone (706) 733-9473
AUGUSTA, GEORGIA 30919-1547
February 14,2006
McKnight Construction
1503 Cargo Rd.
Augusta,Ga, 30906
Re: AugusUs Regional Airport
Gentlemen:
Following is the price to relocate (5) V A Y tenninals to accommodate the lower ceilings in A 122,
A123, A126, and AI2S at the above referenced project.
Work by subcontractors-
Ductwork and ductwork labor
Controls
Insulation
Subtotal
Overhead and profit (1'(.\
Subtotal
$4097,00
2500.00
9S0.QJl
$7547.00
528.29
.--...---.-........-..--..- .------~..~---_.-_..- ..---- _..-'..*--- .__.-
...--...-.--.-.--...-...--..-----.--.".---.. _.. -. .-,',-.
$8075.29
-..--.---.--.-.....-.-------.-- -'--. -.---....:-.---.... .-.-'
Work by Smith Brothers -
------..-------- -----------.---.---.-- ..._._-.-~ ---~-- --...-."
DiscOlUlect controls labor
Seismic cable for (4) terminals
Seismic cable labor
. Labor burden
Subtotal
Overhead and profit (lS'/.)
Subtotal
$ 220.00
481.50
624.00
253.20
$1578.70
236.RO
.---- --'-'.-- -- ..--- r-oo--...------.-.. ..-..-.--..--'
._Pz::~~~_=L"f~:_ _~~f+ ,1w./~~\fw l
~ :'r. - ------....-.-...--. -... .-- ---
-1' yo'Q7 l.~ .....
-----------~---~-------_._-- - -----...- ..-._.__...._._..~.
Total
$1815.50
$9890.79
If you have any questions, please call me.
Sincerely,
t:-~
Ken Smith
,~/~4/28e3 18:37
70F;s:,r2::JeJ9fl'3
~,NSLE'i ELlCTRII::
1'r.r3E 01
ANSLEY ELECTRICAL CONTRACTORS, INC.
65 ALBECLAUS DRIVE
AUGUSTA, GEORGIA 30901
PHONE (706) 823-G404
FAX (706) 823-0909
. i. ~'. ..'
:..:.., ,"
:~ .~. ~:~,.:-.
';":', ::
: I.
",.' ,"
. :. to'" .',.
. '!' .,' "':"','
" ,"l :'
'.. ;:: I :....>.
~; ,'" ~ l,'
.~ ;
.....
;'
.1 :,"
~
AUGUSTA REGIONAL~IRPORT
'. \ ~. ". . . I.
" . "
.....-. " ,',-
, ....
. . . . .:. ,
MATERIAL - $400.00
LABOR - 1800.00
LIFT - 300.00
S2500.00
20 hours @ $60.00
20 hours @ $30.00
LIFT
- 1200.00
600.00
300.00
$2100.00
400.00
$2500.00
MATERIAL -
. MOVE (5) VAVHO)(J::S - kt::WIRl:: INTO NEW POSITION
:i;
. ',I
. . ~ : ~ :"
. ,';,'
,":',
. ~ .
", MlGIfML'
I,".
'I. ,
".:: ",'
',. "..,1
. . ~ :' . I - ~,
;: . ~
~.':'..J---':'~I.~..ItJ
---u~
'.
AUGUSTA ENVtROKMElfTAL COIn'RACTUfG. INC.
Bid Proposal
1463 &.ro.d Street
P.O. Box 1633
^up....GA 30901
l'tIDDc: '106-124--6457
Faa: 7()6..724-1211
f'ebruuy 14, 2\;106
S..ulh B~nMechaDica.\
PO Box 15547
AUpsla. GA 3()H09
RE: AUlUlla Ilerta... Airport TermUlaI ArK ImpnwCIDeIIU
To Whom It .M.\)' Concern:
Aupm EDvilo:omr:Il~ II CODttac;tiag,. me. is pleased to quote labor and ~teriak to lower box as per yoar
insuuction.!l.
Should YO\l have my questions or conccms: pleaa(t give Jolm E. Moms a call at 706-724-,1.22.
Sillccrely.
John 'E. ;Morris
John E. M~
,-,J. !~:~.~.!!-7J~~
/. .
" I. ,'! ,
;. . ""l':.
. ..:;.:~:";~~::
.'. . ".:i:;:~'~~
....;.,'..;,j..',~~
. . ': J:~S:~1~
....r....~'''l,
. '; ::\ &i'~.~
I~' .~ ~:..'!~~;/
", ... ::.,'"
'.'; .:? .~)~rii
';,,:I'~~j!",',
....f.;.~!~
,. -, ,..:),;I..~
. '.i, ..~/II#~~'~~'1
. '~7' '~~j ~~t"
.' '~ ~~~l~~~:
.: ~~;. \~~f~.
;l!l~
',1 ,'; ~~ i~'~~
.; ~':~~ ..Jf
;1 :.:: .~~f'
,'. ~ '\..
" Il,~ ').i''$t,'':
. ....:.,." ,~"l\'
'~ !,'~~i~l'
.. . ...... j.t'..
'. :~'''~~':~i~~
.. :~ f. vr.i~~~
t :". ~~:t:~
:; .i;it~
.. .' ~"""t'~.c
'. ..--1 ....J~I'
. . to!..:.:.,!...... .t.
...... ,_..,"J,,:",,'''~
. . .~ ~"~f
. ... '.i~~ \~:~.
: . :;j~.:'r
.'.~.;~
." . .~. .:r.-:;~i
\.:. - r:~-f.:;;~~
. ....:..,.~!.i~~~:
. . .;;:.I,!.~~
: .' ~l';": t~J'~j!
\'~} {~'l'~
.~,.,i,1~
,,' :~/~~...~~
., ':.. r'I"~r.~;.
~.~,:.~lb.:t~
: ';~>~~~
. .,,:', ..~.~Ji~~.
.' ! .,.~,j.:r. Il.;
, '. .::: !:'..~~<;. ~
, . " .., ,~.,:i~<fItf
:. .::.::..~:~;~~~;
" ':~":~~1
." .~ ....
, i~:":; \.' J~:
.... rl\;
.' ;.: ::.~ :,~~o/.t
. :.;:'::..{i\:
. :',: r,:l'.
.~. . :';:':~i1::
, ,'. ,::' :,1'
I ,~. f, ,
" . I ~;::~~I
~ ., ... 't.ij.;~
.; ~ \~~:~.(.~
. ....tl.l".y:
.~ I.V'~
5:/uel ffletaf ~t~in.eerJl Jnc.
~8J TOWEr.' Ji'(),.iD . RO. BOX 204627 . MARfINEZ. CeORGIA :1091 ,""Q:!:: · l"j,/ONi: (7;)6) i4c.3"\.\.~75 · fA.X (;"06) lJ63-1I:'! 1(1
F~bruary 8. 2006
Smith Brothers Mechwcal Contractors
1711 North LegCuurt
Augu!>ta. GA 30909
:\ttn: Ken Sinith
RE~ Augusta R.e~QDal Airport
SME Job 1IS96S
Ken.
As discussed witb l..c:e with McKnilCht Construction Co. below is a b~down lor
)uwerinr, V A V Buxes (TI~5. Tl-tl, T2-3. '1"2..4, und 1'2-6) and ductwork on the above
rderenced j<<'b.
We will not proceed without wrillen authorizati(ln fhr: a ch.mgc to our cOT1Lrl1ct
Material '~
lO'-16"0~ 10'-10"0; :20'-14"0 Spiral pipe &. 2-l4"-~5"cJlb
2 -. 14:\ 14-. 4S) ells
1 - 14 X \4 duct 59"
~-1(j}\ IO-450clJs
2 - lOx JO duct 5~)"
$ 541.00
60.00
4~.O()
50.00
,70.00
Field Labor
35 n\an hOUlS to lake out and fe-install
Labor Burden
Lill nmu.1
Subtot.al
O....erhc:ld & Profit
Tut..)
~incerely,
$ 910.00
273.00
_620.00
$2 569.00
.-2J;4.,OQ
$3,083;00
,/....;...--.... -_.._-~~. ;:;::::::-~--".,
// '.,
/ 01" I 5" 1:C D. 00 \,
~"lbl>Y 1';'I..,/(.i..., lff, &-,IJO \
\ L; IC~ . __,_' v.o. o.'-~.~,_. I'
-~ y" q . ~(J f '
\",---~~~~~
Chri!> Godwirl
TOTFIL P. 1a2
~UGUSTA ~~m~i~~~~;~TION, INC.
109 Commercial Blvd.
~~.~~(~~prgia 30907
(706) 863~r4J @J~~:f)
FEB 2 4 2005
AFPCR No. - 869-03
February 22, 2006
McKNIGHT CONSTRUCTION Co
P.O. Box 204718
Augusta. GA 30917
Attn.: Pat Patrick
Project Manager
Re: Augusta Regional Airport
Augusta GA
Gentlemen: . -'
Because of additions and/or changes in the work covered by the above referenced
contract, it is hereby agreed that the sum of Three Thousand Four Hundred and Seventy Two
Dollars ($3,472.00) to be added to the total amount of the contract according to the terms and
conditions of the contract.
PROVIDE ADDITIONAL PIPING AND LABOR TO LOWER SPRINKLER HEADS FROM 1 6'4
TO 11'-0 IN ROOMS A 122,A 123,A 1 26,A 128 AND ADDING A CEILING
IN ROOM A 127 PER
IN 17
This work is not provided for by the base or previously revised contract documents and,
therefor, is additional work that would not have been part of the original or previously
modified scope of work. This change order is for Augusta Fire Protection to remove existing
fittings with upright sprinklers in room A 127 and install new fittings with 1" outlets and drop
pipes to attach 9 new flexheads. Also to remove shorts drops and install longer drops for
rooms listed above that have had the ceilings lowered. See the attached Breakdown for
additional information.
Sincerely,
:::~O~ON' Ino.
Project Manager
CGK/wfw
cc: file
Revision No,
Imcumbrace Record
McKnight Project #
PM
DESCRIPTION OF COSTS
1 Material from Pa e 2
2 Consumables and Scra
3 Subtotal: Item 1 + 2
4 Sales tax
5 Local Deliveries & Frei ht
6 Material Return and Cancellation Costs
7 Subtotal Material Cost: Item 3 throu h 6
8 Desi n & Coordination Costs from a e 3
9 E ui ment Rental & Small Tools from Pa e 3
10 Sales tax on Line 9
11 Labor Cost from a e 3 item 27-A
12 Payroll Tax & Insurance (from page 3 item 27-B)
13 Subtotal of Labor, Equipment and Material
14 TOTAL COSTS BEFORE SUBCONTRACTS
15 Overhead/Profit of line 14 Above
16 Subtotal of Direct Costs
17 Net Subcontractor Costs (from page 3)
18 Subtotal of Direct and Subcontractor's Costs
19 Overhead on Subcontractors of line 17 Above
20 Home Office Overhead on line 16 above
21 Profit on line 18 above
22 TOTAL COSTS AND PROFITS BEFORE BONDS & OTHER COSTS '
23 Bonds, Performance and pa ment
24 S eciallnsurance or Other Char es
25 Extended Overhead (From Page 4,if provided)
26 TOTAL PRICE OF CHANGE PROPOSAL
27 Extension of Time for this change order in Workdays 4
to be a lied in ro er Schedule Se uence to each Cate 0 of work,
28 This Pro osal is based on X Strai ht Time Overtime Shift Work
29 This Proposal is void unless a written Change Order or written Notification to Proceed is
received b. 45 calendar da s if no date shown)
30 Extended Overhead Cost: Includ X Deferred*. . NotA licable
AUGUSTA FIRE PROTECTION
CHANGE PROPOSAL COST SUMMARY
:PCR #
869-03
Contract: McKnioht Construction Co. ,Inc
P,O, 204718
Augusta GA 30917
roject Auqusta Reqional Airport
.ttn: Pat Patrick
lescription of Change: Reworkinq of pipe to facilliate lowerinq of ceilinqs
in rooms A122.A123,A126,A127,A128 and addinq ceilinq to A127
7%
7%
$1,335.69
$223.51
$1,960,96\
15%
Submitted By:
Approved By:
Signature
* If deferred, cover letter should describe
_ ~ _& "l
Date Submitted:
MATERIAL
$989.22
$989.22
$69,25
$1,058.47
$1,058.47
Field Crew Size 2
SDPCrew Size 1
-D-
IN 17
J-430
GK
22-Feb-06
$3,019.43
$452.91
$3,472.35
$3,472.35
$3,472,35
$3,472.00
Date:
22-Feb-06
Date:
Date Printed: 2/22/2006
Augusta Fire Protection, Inc.
COST BREAKDOWN
PROJECT: McKnioht Construction CO..lnc
Description: Reworkinq of pipe to facilliate lowerino of ceilinqs
in rooms A122,A123,A126,A127,A128 and addinq ceilinq to A127
QUANTITY
31 ea
9 ea
9 ea
DESCRIPTION
MATERIAL
UNIT TOTAL
1" x sch 40 pipe w/elbow pre fabricated
1 %x1 Y.x1 tee
60" flex drops for rm A 127
$11,92
$6.44
$62.41
.'
Labor to remove old tees and install new tees
and lower piping in other rooms
Totals - ThisPage
n...,.....">,,,f"l
AFPCR #
Imcumbrace Record
McKnight Project #
$369,57
$57,94
$561.71
$989.22
769-01
IN 17
J-430
LABOR HOURS
UNIT TOTAL
20,00
31.00
51.00
Date Printed: 2/22/2006
-I
0
~
en
c
C"
(')
0
~
OJ -
(')
0'
~
n
0
~
~
....
0
0
0
1) '" '" '" ~
. .... ~'" ~="'9>!J'A
0
. ro--l oenzenen
'" ro
III III e. ffi'WO"O"C
s:. '" '" !!!. ~~~~.~
lI> '"
-n <-ill C:oa~ii"
0 0 0'
-1::cn;-I:r~Q "Ccna.3:-'
~~~~~~ =r l='~!2.:!!
0 ~ ~ g. ~
1'>':;:::1 1'>-<3 !:; en"'''
S;oJ:S;olll '" !!!or-is
~ III g ~ OJ :J (DGJmc:
J:~ij;::I:ars: .;;: g:J ;:
-c~a.
gag 0 E; a :5":;"
"'"3 ~3" <C 100
;o'P ;O<D Q; 3
!!!.> 3 "0
!!!.ro ..
lI> > lI> > 3" 10
"Tl0' -nO' III
0 0 0 0 "2- ~
<: <: iii'
3 lI> 3 lI> 3
~ ~ CIl
W w ::>
a, :l- iE
> > ci'
0' 0' ::>
0 0
<: <:
lI> l.nll>
0
:R
0
Q.
,...
S'
lI>
'"
0
>
...., 0-
0
.... .,,<: ."
"T1 ....wll> .... '" <:>
(j) 0>'" wo 0
' W 0,0 0
c: 0> 0 <D 0> #.
,
..
C' J:
0 0
... '" '" c.n ~ c
n l.n 0> 00 00 0 ;0
0 l.n tnOOO 00 00 en
~ 0 0000 00 00
0
.
ii' .... J:
:? ..... ;00
t... ." '" PC
s- O) l.n
ii' ... '" ~ --l;o
'" w '" m,...
'" en en <> -<
'" '" c.n ....
~
;::; --IJ:
0
0 $;0
0> .... ""
...., ~ ." ""C
...., W ~ _;0
... N Z""
~ ~ U, cn-<
~
Z m
n z
m Cl
--l Z
, m
m m
< ;0
m Z
0 , Cl
<> <:
#. <:> --I
;0 m
m " ('J
< iii' J:
0 iii 0: z
lI> :E :;l C'i
'"
Q '0' };
~ .. z
0' @ --I
::I ~
<
m
r
m
x
en "0
c m
z
lD en
C'l m
0 en
z
-l 0
~ J:
C'l 0
-I !:;
0 C'l ..
c 0 @
III
=. en
~ -I
en
-I
o
~
c
~
()
o
!e.
o
III
'"
fii
::I
n ",
o
'"
---=--
o
o
o
'"
-l
0 ....
[ ..
0 .... ....
..... 0 0
:... 6 6
'" 0 0
"Tlen en 0
lI>
0"0 ,,"0 '" <-
@ ~. _. ::!. n
3 ~ ro_ ::I >~ g. 0>
~ "'"
.. ~ ~
::I 0'
::I
", '"
'" ~
w Ol
CD c.n
0 0
'" '"
.... N
c.n c.n
0 CD
;0 III
II> OJ Ol
iD '"
III
:!;'
~' ....
III
III
"0 :;l
.. 0)
~ <:
~
;oJ:--l
~g2.(O
C'D ::l. OJ
"",-
'"
-
0
0
,
)>
tIJ
0 ..
;0 w
'"
en W
c: 0
=:
=:
)>
;0
-<
~
'"
'"
'"
w
W
Ol
..
o
o
....
'"
o
o
CD
.... .... "
en en C'i ~
c.n .. c.n 0
#. ;j!. >
iv
Ol
.... ....
iD iD CJl
#. ;j!. " C
1'>"" I'> C --l ::
Ol", Ol --l >
'" W iv :> I'>
;j!. w ;j!.
:;- c: m
III
0 0 c: .. x ~
"" ~6't ~ iil g g '"
0 ::I ~ '"
0 0 n '"
6 6 '"
0 0
C/)>o
=rlll
o ' ""
"0 g' ;:::
S?..;:::
'" Ql
:;: ::I
~. ~
"0 ..
,.
"0
..
~
0'
::I
o
3
ro
,.
..
"'"
a.
o
:;:
::I
'"
w
o
o
o
J:--l
g> ~ ~
CT-<,"-
--I;oi'f
~.~ ;
en
~ b> g>~ S? S? S? S? :!! \? 15
nQO'"~~~~~~n"'C
=r a. 3 .. -, -, -, -, c:_
g: :i'::::,c5il5.5 g>~ C1
S!!!.!!!. n I I I I <1 ::I 0
rC O'I'>C'l""Tl:>"O'!!;;:;
Q)::J)>m-.~..._.....
~ 0-5 oeD m g.2.I'T1~:O
a.-i2f:-""tJ"'U_""O~m>
~~~~.ao~w~.~::
5i-~g~~~:JE~o
'" "01Ilg.g'!!!. (1g~
~ ::)::J~ gQ::
i:i n~n &.~z
~ g!e.:9 S'~Cl
VI =:-mo :J="
Q.3c: l/Io:o
Ul (J) ::J ~ m
Qo 5r "'C
;u >
iA :0
III >
... --I
co _
o
z
i;:J 0
O.::laOONO~=:::l
."
.... '"
~ '" ~
'" Ol 0 0 0
:." - 6 6 <> <>
C> - 0 0 0 0
,J:
o
c
;0
,
-<
~
-l
m
en
:,:,:,:,:,:,:,:,:,:::,:,:,CJ>
:~::tI::::::t:::::: ~
..........................-
illllllli:lll!l!l:i!I!!1 f
:;:;:::;:;:;:;:;:;:;:;:;::
I
I.
;:::::::::::::::::::::;:::
.;.;.:.:.:.:.:.:.:.:.:.:.:
-0
00
00
00
....OOCDOCDOOO_C
oooaoooo=,oz
gggggggg.=5=i
0000
0000
0000
--I
o
--I
:>-
r
J:
~ 0
~~~~~p~
ggggggcn
~~o:!!? "0
l;l iill~ , J: < :0 S!
"T1=::::r n "'~-'-,<:
g Q.. CD Qj" (JJ ~ ~\.~!!:
-a.::OI;:;~ Q) Q)~'-i
~=j"CDr< r- r:: 5..0.0
mlCi::J -CD =0(..)0
=' Qj-<o<o_
c: -3!e..~r:n~CDO
::- Q CoD 3 IV 0 Q)
:s:: '6g;:: ~
Dl -o-'!!!-
..' r?:
m ::. ~ ~ 0
~ CD 0 0 ='
~=::T
~'0 ~'
o
o
<:
~
C
:::r
5'
..
a.
~'
0000
0000
0000
0000
0000
0000
c: c: c:: c:
2.2.2. =.
iniiiintn'
c c: c c:
2. 2. 2. 2.
U;tnij)~
."
~
.w <A .... "" <&'t i:A 4A fA
W "'tn.... 0> <1><0
-l <I> ....0>0 "->t.n-....l1\J
0 en moo CnoCnw
?i <D co 0 0 to 0 te....
ro ~'al:il~ ~~~~
m III
.c .. ~ ~ ~ r2,
r: (l) :;: :;: :: ::
-0 ,... t<-<:gR- III III '" (l)
Ql III III (l) "
3 0- "'" ~ ^ ^^
'" Q
a ()
Qo 0
~
-l
0
~
C'l
0
~
:;-
.. --I --I -i
!:; Ql 0 ~ 0
<A '" .. x [ w .... '" t;tt.l't-b't~ ~~t.'ttr'f ~
::I "" o.
0> w n 0 0 0 '" 0 0 0 00
~ U, III 0 0 6 6 0 6 6 0 00
CD <D 0 0 0 0 0 0 0 0 00
c
z
::;
(J)
J:
o
c
;0
en
c
2-
in
C1
~
1J
~
i5"
a.
o
m
CJl
Gi
z
01J
~ ;0
Q 0
"E:ffi
5'C'l
?~
5' ;U :s::
o~9;
o 0 :::r
~~Q:
>15 ;;>;
",Q.~
~Ii~
-c=;'
"'-<=
won
:> - =,
~ ~. g
Ol=.n
>~9
~o~
>~
N :::.
CDi'l
III 0
:::r _
c'n
Q) !!.
a. -:
9,i'l
Ii5 ..
"
~
~~
0'
~
N
....
o
m
CJl
Gi
z
o
m
<
m
r
o
"0
m
:;:
m
z
-I
n
o
CJl
--I
Q
c
:c
=:
m
z
-I
Qo
-l
o
o
,
CJl
;:::3
~g
:::r 3
-, 0-
<C ~
=rill
-0
"0"'>
~. ~:g
~gg
;;c.:u:
<-_....
l..z~
w-.
0",,0
()
o
(f)
-f
OJ
::0
m
p
^
o
o
~
z
~
C
G)
C
CJ)
--I
~
-n
-
:::0
m
-0
:::0
o
--I
m
n
--I
-
o
z
IVIQ~Lul '-'I ""'... . ."''''... .~
REGAN TilE, INC.
1"- - -1-'
4189 Crosstowne Court
Evans, Georgia 30809
(706) 860-6379
FAX (706) 855-7167
Fax Transmittal
Date:
MAY 30, 2008
Page 1 of
2
Attention:
LEE
Company Name:
MCKNIGHT CONSTRUCTION
Company Fax #:
?p(," 77'Z- - ez.B~
From:
TIM REGAN
RE:
ARA IR;.93 TEMP SECURITY AREA
. If you did not receive all the pages indicated. or if you have any questions, please call (706) 880-6379. Thank you
Comments:
LEE,
THE ADDITIONAL COST TO INSTAU 95 YARDS OF CARPET AND 175 UF OF BASE IS AS FOLLOWS:
CARPET,ADHESNE,FREI3HT
LABOR, LABOR BURDEN
RUBBER BASE, ADHESIVE
LABOR, LABOR BURDEN
OVERHEAD/PROFIT
15%
$3,227 .25
$451.25
$176.00
$122.50
$596.50
$4,572.50
THANK YOU
TIM
CC: PAT PATRICK
Regan Tile, Inc. dba Master Craft Flooring
TOTRL P. 01
SimplexGrinnel1
3243 Sunset Blvd
West Columbia, SC 29169-3427
(803) 476-0000
FAX: (803) 476-0039
www.simplexgrinnell.com
SimplexGrinnell Quotation
TO:
Mcknight Construction Co.
POBox 204718
Augusta, GA 30917
..~ CI'-
'-'r'./ I ,/
.:J.. ,-
. . \- ""J
I
Project: Augusta Reg - IR93 Data Drops
Customer Reference:
SimplexGrinnel1 Reference: 216404047
Date: OS/24/06
Page 1 of 3
SimplexGrinnell is pleased to offer for your consideration this quotation for the above project,
QUANTITY
MODEL NUMBER
DESCRIPTION
1
Add Data Drops Security
Add Data Drops Security
DPSUB Data Drops for Security Lane
District Services - Add Data Drops Security . _
PM LAB PROJECT/CONSTRUCTION MGMT
3
Total net selling price, FOB shipping point, ~6
:# t.{/1.z~.a-t - 'Si:C AO)0~lC.O
Comments t6~1 '01Z.6t....,K..Cbw"-\
Equipment, Wire & Device Installation, and Commissioning
_ ~\f~(J{E:.:O
This quotation includes the equipment, transportation charges, wire and device installation,
programming, test of the system by a factory trained technical representative, all applicable taxes, and
a one year warranty.
The price does not include conduit or 120 V AC power wiring to control or sub-panels,
Thank you for the opportunity of quoting and we hope to have the pleasure of serving you,
THIS QUOTATION AND ANY RESULTING CONTRACT SHALL BE SUBJECT TO THE GENERAL TERMS AND CONDITIONS ATTACHED HERETO.
Fire, Security, Communications, Sales & Service
Offices & Representatives in Principal Cities throughout North America
IR93 - Data Drop Change Order Worksheet
Cummins Communication - Quote to SimplexGrinnell
Description '
Data Cabinet W/Fans
Cat 6 Wire
Cat 6 Jacks
Cat 6 Patch Panel
Face Plates
Qty Rate
1 1,845,00
1600 0,38
10 4,65
1 265,00
10 1,75
labor to Install and Test
SUBTOTAL
6% Sales Tax
% Labor Burden
Totals
15% Overhead
15% Profit
Totals
The total ADD for this change order is
$4,900.08
Total change
$4,900.08
SimplexGrinnell Quote To McKnight Construction
Materials
$1,845.00
$608.00
$46,50
$265.00
$17,50
$2,782. 00
$166.92
$2,948.92
$442.34
$508.69
$3,899.95
MfHours labor Rate Total Labor
4 $22,00 $88.00
22 $22.00 $484,00
2 $22.00 $44,00
3 $22,00 $66.00
1 $22,00 $22.00
$704.00
$161.92
$865.92
$43.30
$90,92
$1,000.14
Labor Burden MlHours
2,60
Project Management
Cummins
Totals
15% Overhead
15% Profit
$3,899.95
$3,899.95
$584,99
$672.74
Mix Rate Total Labor
3 $25.00 $195,00
$1,000,14
$1,195,14
$179.27
$206.16
Totals
$1,580.57
Total Charge
$5,157.68
l $6,738.261
$implexGrinnell
9. INSURANCE 08L1GA TIONS: II is W1derslood and agreed by the Purchaser thai 'SG' is rol an
Insurer and Ihalilis lhe Purchaser's obligalion to oblainandmaintainanyinsw.mcecoveringanylosses
10 property 01 personal injury or any olher damage which may occur at !he premises whefe the 'SG'
Product, Software 01 SelVices, which form the basis of this Agreement, are delIVered, assembled,
Inslalled, used, or performed. The Purchaser agrees 10 lisl'SG' as an additional insured on all such
policies and 10 pro\l1de 'SG' a copy of the Cer1incate of tnsur<r1Ce upon requesl Purchaser further
agrees thatlhe Certificale of Insurance shall containaprovision IhalCO\leragealfordedunderlhepolicies
will not be canceled or materially altered until alleast thirty (30) days aflerWlitien rouce is given to
'SG'
10. WAIVER OF SUBROGATION: Purchaser does hereby for itSelf and all other parties claiming under
il release and discharge' SG' from and agamsl all hazards covered by Purchasers insurance, it being
expressly agreed and underslood that no insurance company, insurer, 01 any other third paiywill have
any righl of subrogation againsl'SG'
11. LIMITATION ON ACTIONS: The Purchaser hefeby agrees that no claim, suilor action of any kind
shall be brought against'SG" its agents, employees, andJor officers mare1han one year after 1he
claim arises, whether known or unknown when Ihe claim arises, provided however, thai ff there is a
claim, sui I, or causeof action arising lI'1der the Warranty, itmustbe brought ifalall, withinsixmonlhsof
expiration of the Warranty period stated above. This clause is in no way to be inlerpreted as an
extension of the Express Warranty stated in paragraph 6 above.
12. DRAWINGS: All drawings and wire diagrams provided by 'SG' in connection wi1h this
Agreement are protected under United Slates Copyright Laws and intmded solely fa-!he use of 1he
installing contraclor as a general guide for the installation of !he System. lhase ""wings and wire
diagrams are prepared in accordance with !he project plans and specifica6cns available to 'SG' at
the time of !he bid and are NOT intended to be System design or approval doc1menIs. 'SG' is not a
design professional. Under ro circumstn:es is any clause In IIis A!1eement... any actions laken by
'SG' to be construed in such a way as to impose l4JOll 'SG' the <iltias or tiabilities of a design
professional.
13. CHANGE ORDERS: This Agreement can be modified, amended or altered only by an Agreement in
writing, signed by bolh parlies or their duly aJthorized representatives.
14. SOFTWARE LICENSE AND USE: Soflwaoe Pr_ provided by 'SG' are Ii<ensed, not sold.
to the Customer. Customer has only a non-<xclusive, non-lransferable rlClll1Se to use the Soflr.e
('License'). 'SG' retains all righ\.-fiUe and interest to !he Safbr.R, In some cases, "SG' may
have a right to relieense the Software. 'Software' shall mean lIlY part of Soflware prOllided by'SG"
in machine readable form indicated on this Agreement or contained in any'SG' PrDlU:tindcated on
lhisAgreementororderedsubsequenlly,anymodifiedversionsandaUrelateddoctmentatioo.Cuslllmer
shall use the Software only on the Product and at the ProductSitelistedhefein. Any Soflwarerecsived
by Customer at any time is subject to ilis AgreemenL The Ucense term ~ l4JOll defi""'Yof the
Software and continues W1til!he last use of Ihe SOflwa"e with the Product.lS1Iess terminated. 'SG"
may terminate this Ucense If Customer: (1) fails to perlorm any ob~galion Lnder the A!1eement; (2)
ceases to do business as agoing con<em; or (3) has its asselsassignedorattachedbylaw. Wi1hinfive
(5) days aflertheLicense terminales, Cuslomer shall, alits expense, rehm the Soflwareto 'SG' and
destroy all copies of the Software, including memory or storage copies.
15. PROTECTION AND NON-DISCl.OSURE: Customer shall maintain !he Soflwae. in shiel
con1idence and shall disclose it only to its empioyees requiring access. Customer shat implement
adequate procedures controlling access to and use of the Software consistent with the prolection of
'SG's'rights. Customer may duplicate Software only for internal use on the Pro<iJct accorcfing to
'SG' instructions. The 'SG' legend restricting Software use must appear on lIlY copies of the
Software. Customer shall not reverse compile the Software.
Offered By:
SimplexGrinnell LP License#:
3243 Sunsel Blvd
West Columbia. SC 29169-3427
Telephone: (803) 476-0000
Rl3pr.sSlilntativ43"
Project: Augusta Reg - IR93 Data Drops
Customer Reference:
SimplexGrinnell Reference: 216404047
Date: OS/24/06
Page 3 of 3
16. FORCE MAJEURE: 'SG' shall not be liable for any loss or damage of any kind resulting from
delay, inabiUly to deliver, or inslall, or 10 perform any other work under this Agreement on account of fire,
flood, labor problems, access 10 premises, accidents, acts of civil or military aulhorities, acts of God, or
from any other causes beyond 'SG's' controi.
17. TAXES, LICENSES AND PERMITS: The Purchaser is responsible for obtaining all hcenses, and
permits and for paying all applicable taxes and fees unless otherwise agreed to in wribng.
18. tNSTAUATlON: The installation of any Product is NOT INCLUDED unless speciiically provided
lor in this Agreement.
19. DRUG FREE WORKPLACE POLICY: 'SG' has a writien drug free workpiace policy available
for review by Wlitien requesl
20. EXPORT COMPLIANCE: All sales hereunder shall at all bmes be subject to the export control
taws and regJlations of !he Goverrrnent of the United Slales. Purchaser agrees that it shall not make
any dispositioo, by way of lrans-shipment. re-export, diversion, or otherwise, el<CE!pt as said laws and
regutanons may expressly provide. Purchaser expressly agrees, 10 the fullesl exlent permitted by law,
to indemrily.'SG' for any,and all damage arising from the violation of any export law or regulalion
with respe<:t to any goods delivered to Purchaser or al Purchaser's direcbon. Said demages include, but
are rot limiled to,legalfees, court cosls, expert fees , and any and all other resulling costs and
expenses.
21. EVENTS OF DEFAULT: Purchaser shall be in default of this Agreement upon the occurrence of,
but rot timilOOto, any of !he following:
A The Pu-chaser's failu"e 10 make due and punctual payment of any paymenl due pursuant In this
A!1eernen~
B. The Purchaser's failtre In perform any obligation lIlder this Agreement,
C. M order, judgnent or decree entered, with !he approval or consent of 'SG', by any court of
ccmpe1en1 jtrisdclion, approIIing a petition seeking reorg;rization of the Purchaser or appointing a
receiv..., Iruslee, or m,idalor (or other oflicer having power, under applicable law, similar 10 those of a
receiver, _, or Iiqtjdalor) of !he Pu-chaser or of all or a maja" pornon of its assets, and such order,
jud!Jllllnt. or decree shall contiroe lIlStayed and in effect for any period of sixty (60) consecutive days;
D. The Purchaser t.ils to provide 'SG' with adequate assurances of due performance under
!he A!1eemenl. after recaving a written re""",! for same from 'SG';
E. The Purthaser's irmcial positioo materially deteriorates; or
F. The Purchaser sh;iJ cease to do business as a gOing concern.
22. GENERAl: My provi$oo of this Agreement which is protibited by the law of any slate shall, as to
such slate, be ineffective to the extent of such provision without invalidating !he remairing provisions of
\he A!1eemenl. This Agreement shall be construed under the laws of the Commonwealth of
Massachusetis.
Accepted By: (Customer)
Company:
Address:
Sign;atuT9:
Tille:
P.O.#:
Date:
Fire, Security, Communications, Sales & Service
Offices & Representatives in Principal Cities throughout North America
$implexGrinnell
Project: Augusta Reg - IR93 Data Drops
Customer Reference:
SimplexGrinnell Reference: 216404047
Date: OS/24/06
Page 2 of 3
SIMPlEXGRINNELl BUilDING SYSTEMS GENERAL TERMS AND CONDITIONS OF SAlE
For good arid valuable consideration, the parties agree that !he tem1S and conditions cnntainedherein are
the sole ierms and conditions of sale and/or for selVice and represent the soie and complete Agreement
between the parties and supersede all pnor oral and/or written representations, understandings,
proposals, agreements, and communications regarding the subjeci matter hereof. The parties agree !hat
no additional terms will be binding upon SimplexGrinnell LP (hereinafter referred to as 'W) even if
they appear on Purchasers formal purchase order, acceplance form, or 03IT'f other of Purchaser's
documents unless signed by an authorized representative of 'SG' at its headquarters in
Westmmster, Massachusetts.
VALIDITY PERIOD: The price quoles provided are valid for 30 days unless o!helWlse speciiied in
writing by 'SG'.
2. PAYMENTTERMS:
A. GENERAL PA YMENTTERMSarenelthirty(30)daysfrom date ofmvoicewheresatisfacluryopen
account credit is established and maintained. 'SG' reselVes!he right 10 revoke or modify Purchasers
credit at its soie discretion. A mobilization payment up 10 fifty percent(50%) will be invoiced upon
acceptanceofcustomer'sorder. Progresspaymenlslnonehundredpercen!{1 OO%)ofcniervaJuewillbe
invoiced monlhly based upon equipment delivered or stored and wOl1< pelformed. At 'OOs'sole
option, Purchaser shall pay cashin advance, or upon deliV<!!)', or as ofherwise specijjedby 'SG'.ln
the event!hal Purchaser defaults on its obligation to pay each invoice when due, Illen, inadlition loall
other rights and remedies available 10 it, 'SG' shall have !he option to withhold any fuiher shipments
of materia is andIortheprovision ofseMces, ifany, until Purchasers account isfullypaid Ftrther. in !he
evenl payment is not received according 10 Terms, 'SG' may, at its liscretion, assess interest at !he
maximum rale allowed bylaw or el thernte of 1,5% permonth, whil:heverisless. IVchaser8lsoagr-;"
to pay all costs incurred by 'SG' in pursuit of payment which is past due including, but not limited Ill.
collection agency commissions and altorneys fees.
B. CUSTOM SOFlWAREPAYMENTTERMS are asprovidedinsectionA abOllewith ~foIIoomg
exceptions. Anon-refundable twenlypercent(20%) initial paymenlwill be imoicecluponacceplance of
Purchasers order. A non-refundabJe progress payment oHerty parcen! (40%) of order value wiD biJ
invoiced upon Purchasets approval of a Custom Softwa'e Development Specification. The finalfony
percenl (40%) paymenl will be invoiced upon datively by 'SG' of Custom Soflwae.
C. SECURIIY SYSTEM I ACCESS CONTROL SYSTEM PA'1M ENT TERMS <R as provided in
Sec~on A above with the following exceptions. Anon-refundable 20% downpaymentisrOquired with
PurGhasers order. Progress Payments will be iTl\loiced based upon stipments 10 Ptrchaser.
. D. CANCEllJ\TION: My permilled canceltation must be made in writing. Recoiri2ing lhal
'SG's' damages arising from cancellation will be diffia.it to estimate er determine, !he following
charges shall be construedasUquidated damagesrepresentinganapproximationoflheacmrislrati1re,
engineering, and other costs 'SG' will aclually incur in reliance ,""on this Agreement, and not as a
penalty: II, priorloshipmenl PlJ'chasercancels thisAgreemenloranyportionthereof. foranyreasonnot
attributable to 'SG', Purchaser agrees to pay 'SG' an amlUlI equal III 20% of !he price of
!he products canceled. If Purchaser cancets after stipmElll Pt.rchaser agrees to pay Il1e
above 200k of the price of the products canceled, relLm the procb:ts already slipped, and to pay
'Wan additional amOlJ'lt e~a11o 20% of the value of!he rehmed products to cover !he estimated
costs of transportation and restocking.
3. SIM PlEXGRINNELLSERVICES:Purchaserfurtheragreesthal'SG'offersvariouslevelsofservicesand
that the Purchaser, after reviewing the same, has contracted with 'SG' to perfunn only ~ services
described in writing in ttis AgeemenL 'SG' denies tiability for malarials, ~s or w~ pro1Iided
by other persons. Urless specifically contracted for, 'SG' derias any ~ervisoJy role and Ilis
Ageementshall not COOImit'SG' to any supervisory role, incluling, but noltimiled to, !heplacement
or routing of any wires or other Producl
If this Agreemenl includes a quote for Monitoring Services to be st.WIied by'SG', Pt.rchaser
agrees for himself, andeny assignees to thts Agreamenl that 'SG.' shall tave no duty 10 perform
ouch Monitoring Serviceountil -_Ihe f'trchaoer, end...,.~inclucingbutnollimiledlo
the enel-user, agree to and sign a 'SG' Monitoring Agreement approved and sijJled by an authorized
representative of 'SG'.
If this Agreement includes a quote for Maintenance Services to be st.WIied by 'SG', Purchaser
agrees for himself, and any assignees 10 this Agreemenl that'SG' shall heve no duty to perform
suchM aintenance Services until and unlesslha Purchaserandanyassignae,indudingbulnotlirritedto
the enel-user, agree to and sign a 'SG' Maintenance SOrviceAgreement approved and signed by an
authorized representative of'SG'.
4. SHIPMENT: All Equipment is shipped F.O.B. shipping point
5. SECURITY INTERES1: The Purchaser grants to 'SG', and 'SG' retains, a security interest
in all Product Software, and proceeds thereof shipped pursuanllo IIis Agreementlllbl!he IVchaser
shall have mede tiJll paymentfor the Product. Such inlerestis inlsnded to be etfeclive as a pIrchase
money security interest Purchaser agees that 'SG' may file tlis Agreement as a finanQng
statement In the event of failure to make payment on the due dale In accordance with terms designated,
the enfire balance shall become due and payable at once. In case of default of payment, and to the
extent permilled by law, 'SG' shall have !he right 10 take possession oi the Product or Software
Immediately, wherever II may be fO\J1d, and remove it with or without process of law and may retain all
money paid hereunder as Uquidated damages and rental for said Product or Software. For Ihe purpose of
assisting 'SG' in perfecting its seemty interests in any 'SG' Product or Software delivered 10 the
Purchaser, Purchaser agrees to inform 'SG' immediately if any other entity has or may have any
security interest, partected or otherwise, in !he 'SG' Product or Software described on the face of thiS
Agreemenl and shipped to Purchaser. The Purchaser agrees to pay 'SG's' costs of colleeDon.
including without limitation reasonable attorneys fees and legal expenses, and thai the same are
secured by !he security interes! granted herein. The Purchaser shall not sell, prior to payment (except in
the ordinary course of business), mortgage, pledge, or lease said Product or Software without prior wrillen
pennission of'SG'
6. liMITATION OF WARRANTY: Purchaser understands that 'SG' is not an Insurer. Subject 10
the limitations below, 'SG' warrants thai the Product (as distinguished from Softwarel be tree tram
defects in malerial and workmanship IJ1der normal use for a period of one year from the date of first
beneficial use of all or any part of the Product or 18 months after Product shipment WhiCheveT is earlier,
provided, however, !hat 'SG's' sole liability, and purchasers sole remedy, under said warranty, shall
be limited 10 the repair or replacement of any Product, or part !hereof, which 'SG' determines to be
defective, al 'OOs' sllie option and subject to the availability of service personnel and parts, as
determined by 'W. 'SG' warrants expendable items including, but nol limiled to, video and
print heads, television camern lubes. video monitor display tubes, batteries and certain other products in
accordance with !he applicable rnanJfactLrer's waranty. 'SG' does not warrant devices designed
solely to fail in protecting a system such as, but not fimiled 10, fuses and circuit breakers.
'SG" waTants that any '56' So1lwa'e described in this Agreement, as well as !hal Software
contaned in or sllid as part of any PrllliJct described in this Agreemenl will reasonably conlorm to its
published specifications in effect at !he lime of delivery and for ninety (90) days after delivery. However,
Purchaser aglees and acknowledges hal the So1lwa'e may have inherenl defects because of its
complexity. 'SG's' sllie obligation with respeclto Software, and purchasers sole remedy, shall be to
make available published mo<iIications, designed 10 correcl inherenl defects, which become available
dtrng !he warr.nty period.
THIS WARRANTY DOES NOT APPLY TO ANY PRODUCT OR SOFTWARE WHICH
HAS BEER SUBJECTED TO ABUSE, IIISHANDUNG, OR IMPROPER USE AS
DETERMINED BY "SG- AND IS IN UEU OF ALL OTHER WARRANTIES,
EXPRESS OR IIIPUED,INCLUDlNG ANY IIIPUED WARRANTY OF
MERCHANTABIUTY OR RTNESS FOR A PARTICULAR PURPOSE.
Waranty senlice wiD be performed at no charge between !he hours of 8:00 am to 5:00 pm local time,
Monday Ihrough Friday exclusive of 'SG's' holidays. WaTllnty seMce requested 10 be performed at
olher than duing 'SG's' normal wOl1< hours shall be chargeable at 'OOs' standard overtime rates.
All repails Of adjusbnents that are or may become necessary under the WaTllnly provisions of this
Agr- man be porlonned orly by an aulhoIized repr_e of 'SG'. I>ny repairs,
adjusbnents, or inlercomections performed by !he Purchaser or anyone other than an authorized 'SG'
representative shall IIOid all warranties.
7. LIMITATION OF LIABILITY: '56' SHAll NOT BE lIABLE FOR ANY INDIRECT,
INCIDENTAL, ElXlNOMIC, OR CONSEQUENTIAL LOSS OR DAMAGE TO THE PURCHASER OR
USER OF THIS PRODUCT AND/OR SOFTWARE ARISING OUT OF, AMONG OTHER THINGS, THE
OPERATION OR FAILURE OF THE PRODUCT AND/OR SOFTWARE TO OPERATE, THtS
AGREEMENT, THE INSTAllATION, USE, DESIGN OR FUNCTION OF ANY 'W PRODUCT
AND/OR SOFTWARE.
8. LIMITATION OF REMEDY: It is lJ1derotood and agreed that since il is impractical and extremely
<ilfrctil to fix actual damages, if any, or ascertain whal if any, portion of any loss or injury would be
prOllirnately caused by !he faillJ'e of'SG's' Product and/or Software to oPerate, or to operate proPerty,
or 'SG' 10 perform any of its obligations or services described herein, UNDER NO CIRCUMSTANCES
W1l.l 'SG'S" LIABILl1Y FOR. ANY DAMAGES, INQUDING BUT NOT LIMITED TO THOSE
ARISING IN ANY WAY OUT OF THE INSTAllATION, USE, DESIGN OR FUNCTION OR FAILURE TO
FUNCTION OF ANY PRODUCT ANDSOFlWARE SOLD BY 'W, BE IN EXCESS OF THE
PURCHASE PRICE PAID FOR '!HE PRODUCT, SOFTWARE AND/OR SERVICES. THIS SUM SHAll
BE THE PURCHASER'S SOLE, COMPlETE AND EXQUSIVE REMEDY AND SHALL BE PAID AND
RECEJV8) AS UQUIDATBl DAMAGES OR A LIMITATION OF LIABILITY AMOUNT AGREED ON BY
THE PARTIES AND NOT AS A PENAl1Y. IN NO CIRCUMSTANCES WILL 'SG' BE HaD
LIABLE FOR ANY CLAIMS, LOSSES, DAMAGES OR INJURIES ARISING FROM OR CAUSED BY,
THE "PURCHASER'S OR ANY OTHER PAR1Y'S MATERIAL, EQUIPMENT, ACTIONS, OR
OMISSIONS. n Ptrchaser wishes 'W 10 increase Ihe amount of the above limitation of liabHily or
li~dated damages amount stated in lhis Agreement Purchaser may inquire about obtaining an increase
10 this amount in exchange for an increased purchase or contract price. Under no circumstances will an
increase in !he purchase or contract price be construed 10 mean that 'SG' is an insurer or thai !he
obligations of oblairing and maintaining insurance are not wilh the Purchaser.
Fire, Security, Communications, Sales & Service
Offices & Representatives in Principal Cities throughout North America
IR93 Simplex
A.<;
Submitted
Subcontract (Cummins)
Material qty
data cabinet w/fans
cat 6 wire
cat 6 jacks
cat 6 patch panel
face plates
subtotal material
sales tax @ 6%
subtotal material
overhead @ 15%
"-.S Adjusted
~_fb
1
1600
10
1
10
rate
1,845,00
0.38
4.65
265.00
1.75
1,845,00
608,00
46.50
265,00
17,50
2,782.00
166,92
2,948.92
442,34
Subcontract (Cummins)
Material qty
data cabinet w/fans
cat 6 wire
cat 6 jacks
cat 6 patch panel
face plates
subtotal material
sales tax @ 6%
subtotal material
15%
rate
1 1,845.00
1600 0.38
10 4.65
1 265.00
10 1.75
1,845.00
608.00
46.50
265.00
17.50
2,782.00
166,92
2,948.92 v
442.34
Labor mh rate Labor mh rate
data cabinet w/fans 4 22,00 88.00 data cabinet w/fans 4 22.00 88.00
cat 6 wire 22 22.00 484.00 cat 6 wire 22 22.00 484.00
cat 6 jacks 2 22,00 44.00 cat 6 jacks 2 22.00 44,00
cat 6 patch panel 3 22.00 66,00 cat 6 patch panel 3 22,00 66.00
face plates 1 22.00 22.00 face plates 1 . 22.00 22.00
subtotal labor 704.00 subtotal labor 704.00
labor burden @ 23% 161,92 labor burden @ 23% 161.92
subtotal .labor 865.92 subtotal labor 865.92
overhead @ 5% 43.30 overhead @ 5% 43.30
profit@ 10% 90.92 profit@ 10% 90.92
total labor 1,000.14 total labor 1,000.14
Total Cummins 4,900.08 Total Cummins 4,391.40
Simplex Simplex
Labor mh rate Labor mh rate
PM 3 25.00 75.00 PM - 3 25.00 75.00
subtotal labor 75.00 subtotal labor :-75.00
labor burden @ 160% 120.00 labor burden @ 160% 120.00
Subcontract
Cummins
subtotal subcontract
4,900.08
4,900.08
Subcontract
Cummins
subtotal subcontract
total subcontract
4,391.40
4,391.40
subtotal labor & subcontract
subtotal labor & subcontract
4,923.04
ht
Total McKnight
5,267.66
$implexGrinnell
3243 Sunset Blvd
West Columbia, SC 29169-3427
(803) 476-0000
FAX: (803) 476-0039
www.simplexgrinnelLcom
SimplexGrinnell Quotation
TO:
Mcknight Construction Co.
POBox 204718 .
Augusta, GA 30917
Sf\-- \U0
~
Project: IR100 Lowering Ceiling
Customer Reference:
SimplexGrinnel1 Reference: 216403820
Date: OS/26/06
Page 1 of 3
SimplexGrinnell is pleased to offer for your consideration this quotation for the above project.
QUANTITY
MODEL NUMBER
DESCRIPTION
3
IR100 Lowering Ceiling
IR100 Lowering Ceiling
DPSUB SUBCONTRACTING LABOR
District Services - IR100 Lowering Ceiling
PM LAB PROJECT/CONSTRUCTION MGMT
Total net selling price, FOB shipping point,~
.tf~l \Z5.~I-"S(c: ~Ju~-rt:.l?
~1 t3~K.DoWk.(
1\1f~UicD
This quotation includes the equipment, transportation charges, wire and device installation,
programming, test of the system by a factory trained technical representative, all applicable taxes, and
a one year warranty.
Comments
Equipment, Wire & Device Installation, and Commissioning
The price does not include conduit or 120 V AC power wiring to control or sub-panels,
Thank you for the opportunity of quoting and we hope to have the pleasure of serving you.
THIS QUOTATION AND ANY RESULTING CONTRACT SHALL BE SUBJECT TO THE GENERAL TERMS AND CONDITIONS ATTACHED HERETO.
Fire, Security, Communications, Sales & Service
Offices & Representatives in Principal Cities throughout North America
IR100 - Lowering Ceiling Change Order Worksheet
CSRA Quote To SimplexGrinnell
Description
Wire, Flex, Fittings
Labor to Install and Test
SUBTOTAL
6% Sales Tax (if appliciable)
Labor Burden
Totals
15% Overhead
15% Profit
Totals
The total ADD for this change order is
Total change
Qty
Rate
100 24.00
o 000
o 0.00
o 0.00
o 0.00
o 0.00
o 0,00
o 0.00
o 0.00
o 0,00
o 0.00
o 0.00
o 0.00
1.00
$4,085.16
SimplexGrinnell Quote To McKnight Construction
$4,085.16
Project Management
CAD
Design
Totals
15% Overhead
15% Profit
Materials
$2,400.00
$0.00
$0,00
$0.00
$0,00
$0,00
$0.00
$0,00
$0,00
$0.00
$0,00
$0.00
$0.00
$2,400.00
$144.00
$2,544.00
$381.60
$438.84
$3,364.44
MIHours Labor Rate Total Labor
16 $19,50 $312,00
o $0.00 $0.00
o $0,00 $0,00
o $0,00 $0,00
o $0.00 $QOO
o $0,00 $0,00
o $0.00 $0,00
o $0.00 $0,00
o $0,00 $0.00
o $0,00 $0.00
o $0.00 $0,00
o $0,00 $0,00
o $0,00 $0,00
$312.00
$312.00
$624,00
$31.20
$65.52
$720. f 2
Mix Rate Total Labor
3 $25.00 $195.00
o $16.60 $0,00
o $23,00 $0,00
$195,00
$29.25
$33,64
Labor Burden MlHours
2.60
2.60
2.60
$4,085.16
$612.77
$704.69
Totals
$257,89
Total Charge
$5,402,62
~ $5,660.51 f
S;mplexGrinnell
9. INSURP.NCE 08L1GATIONS: It is understood and agreed by the Pu-chaser 1hat'56' is not an
insurer and tha titis the Purthaser's obligation to obtain andmaintainany insurancecollelinganylosses
to property or personal injury or any other damage which may occur at !he premises where the 'W'
Producl, Solmare or Services, which form the basis of this Agreemen, are debvered, assembled,
Installed, used, or performed. The Purchaser agrees io Iisl'SG' as an additional insured on all such
policies and 10 prOllide 'SG' a copy of the Certificale of Insurance upon request Purchaser fur1her
agreesthatthe Certificale oflnsurance shall containaprovision thatcoverageaffordedunderthepolicies
will nol be canceled or malerially altered until at least lhirly (30) days after WOllen notice is given 10
'SG'.
10. WP.IVER OF SUBROGATION: Purchaser does hereby for ilsell and all other parties claiming under
it release and discharge 'SG'from and against all hazards covered by Purchaser'sinstnnee, ilbeing
expressly agreed and understood !hat no insurance company, insurer, or any olher third parlywill have
any righl of subrogafion againsl'SG'.
11 L1M ITA TlO N ON ACTIO NS: The Purchaser hereby agrees that no claim, suilor action of any kind
shall be brought against 'SG', its agants, employees, and/or officers more than one year after the
claim arises, whether known or unknown when the claim arises, provided however, that if the", is a
claim, sui t, or cause of action arising under the Warranty, itmustbe brought, itat all, wilhinsixmoolhs of
expiration of the Warranly period slated above. This clause is in no w~ to be interpreted as an
extension of the Express Warranty staled in paragraph 6 above.
12. DRAWINGS: J'J1 drawings and wire diagrams provided by '56' in connection wi1ll this
Agreement are protecled under Uniled Slales Copyright Laws and intended solely for the use of the
installing contractor as a general guide for the installafioo of !he System. These drawings and wire
diagrams are prepared in accordance with !he project plans and specifications avaiIaIlIe to '56' aI
the time of the bid and are NOT intended to be System design or appro"'" doctmen!s. 'SG' is nat a
design professional. Under no circumstances is any dause;n IhisAgreement or any acfioos taken by
'SG' to be construed in such a way as 10 impose ~ 'W' !he <iJlies or liabifities of a desi!1l
professional.
13. CHANGE ORDERS: This Agreement can be modi~ed, amended or a1lered onIybya1 Agreement in
writing, signed by both parties or their ciUy authorized representatives.
14. SOFTWARE LICENSE AND USE: Software Producls provided by 'S<>' are ticensed, no! sold,
to the Customer. Customer has only a llOn-exclusille, non-lransferabIe rlCl!l'lSe to use !he Software
('License'). 'SG' retains all righ~ tiUe and interesito !he Software. In some cases, '56' may
haYe e right 10 relicense the Software. 'So_' shall me31 any part of Soft!rare prOllided by 'SG'
in machine readable form indicated on ttis Agreement or contained in any'SG' Productin<icated on
IhsAgeemenlororderedsubsequently,anymocifiedversionsarxlatlrelaleddoctmenlalionCuslomlJ
shall uselheSoflware only on !he Produclarxlalthe ProdJctSitelisledherein. AnySoftwarereceived
by Cuslomer at any time is subject to tlis Agreement The Ucense !elm be~ upon deliV8lY of he
Software and continues lUlliI the last use of the Software wi1ll!he Product, lI1Iess lerminaJed. '56'
m~ terminate this License if Customer: (1) flits to perform any obigalion l.I1der !he Agreemenl; (2)
ceases to do business as a going concern; or (3) has its assets assigned oratlachedbylaw. Wl1I'in1lve
(5) days after the License terminates, Customer shall, allls expense, relum the Soflwarelo'SG' and
destroy all copies of !he Soflware, including memory or storage copies.
15. PROTECTION P.ND NON-DISCLOSURE: Cuslomer shaJ maintain the Soflw..-e in shict
confidence ancl shall disclose it only to its employees r~ring access. Customer srial implement
adequale procedures controlling access to and use of the Software consistenl wi1h 1he proiection of
'SG's' rights. Cuslomer m~ duplicate Software only for internal use on the Product according to
'SG' instructions. The 'SG' legend ",shicting Software use must appear on any copies or the
Softwere. Customer shall nol reverse compile the Soflware.
Offered BY'
SimplexGrinnell LP Ucense#:
3243 Sunset Blvd'
Wesl Columbia. SC 29169-3427
Telephone: (803) 47&-0000
Representative:
Project: IR100 Lowering Ceiling
Customer Reference:
SimplexGrinnel1 Reference: 216403820
Date: OS/26/06
Page 3 of 3
16. FORCE MAJEURE: 'SG' shall not be liable for any loss or damage of any kind resulting from
def~ , inabihty to deliver, or inslall, or to perform any other work under this Agreement on accounl of fire,
fioad, labor problems, access to premises, accidenls, acts of civil or military authorities, acts of God, or
from any other causes beyond 'SG's' contiol
17. TAXES, LICENSES AND PERMITS: The Purchaser is responsible for obtaining all licenses, and
permits and fer P'l)'ing all 2PPIicable laXes and fees unless otherwise agreed 10 in writing.
18. INSTALLATION: The installation of any Product is NOT INCLUDED unless speci1ically provided
for in this Agreement
19. DRUG FREE WORKPlACE POLICY: 'SG' has a wrrtten drug free workplace policy available
for ",view by written request
20. EXPORT COMPUANCE: All sales hereunder shall at all times be subject to the -export control
laws and regulations of !he Government of !he United Slates. Purcheser agrees that it shall not make
any disposition, by W"f of 1rans-shipmen~ re-export, diversion, or otherwise, except as said laws and
regulations m~ expressly prOYide. Purchaser exp"'ss1y agrees, to the fullest exlenl permitted by law,
to indemnify '00' for any a1d all damage aising from the violation of any export law or regulation
with respecllo any goods delivered 10 Purchaser or at Purchaser's direction Said damages include, but
are not limited kt, legal fees, courtcosls; expert fees, and arrf and all other resulting cosls and
expenses.
21. EVENTS OF DEFAULT: pl.fchaser shall be in default of this Agreement upon the occurrence of,
but nolfimtled to, any of the following: -
A The Pun:haser's failLre 10 make due and punclual payment of any payment due PLrSuant to this
Agreement
B. The 1'uR:haser's faikn to perform any Obligation l.flder this Agreement
C. An order, judgnerrt Of deaee entered, wiIh !he approval or consenl of 'SG', by any court of
competent ju-isiction, approving a petition seeking reorganization of !he Purchaser or appointing a
receiver, lrusIee, or liqUdaIllr (or other ofticer having power, under applicable law, similar to those of a
recefver, lrusree, or liquidator) of the I'l.fthaser or of all or a major portion of ils assets, and such order,
iudgnen~ or decree shall conlinue unslayed a1d in effect for any period of sixty (50) consecutive days;
D. The Purchaser fails to proIIide 'SG" with adequate assurances of due performance under
!he Agreemen~ aIIer receiving a wIilfen request for same from 'SG';
E. The Purd1aser'sfinancial posifion maleriaHy deteriorates; or
F. The Pu-chaser shall cease to do business as a going concern.
22. GENERAL: Any provision of !tis Agreement which is prohibited by the law of any slaie shell, as to
such state, be ineffective to the extent of such provision without invalidating !he remaining provisions of
!he Ag-eemenl Ths Agreement shall be construed under the laws of the Commorrttealth of
Massachusells.
Accepted By: (Customer)
Company:
Address:
Signature:
me:
P.O.#:
Date:
Fire, Security, Communications, Sales & Service
Offices & Representatives in Principal Cities throughoLit North America
SimplexGrinnel1
Project: IR 1 00 Lowering Ceiling
Customer Reference:
SimplexGrinnell Reference: 216403820
Date: OS/26/06
Page 2 of 3
SIMPLEXGRINNELL BUILDING SYSTEMS GENERAL TERMS AND CONDITIONS OF SALE
For good and valuable consideration, the parties agree that the lerms and concitions contained herein are
the sole terms and condilions ot sale and/or for service and represenllhe sole and comptete Agreement
between the parties and supersede all prior oral andlor written representations, understandings,
proposals, agreements, and commul'l1cations regar~ng the subjecl matter hereof. The parties agree thai
no additional lerms will be binding upon SimplexGrinnell LP (hereinafter relerred 10 as 'SG') even jf
they appear on Purchaser's foonal purchase order, acceptance form, or any other of Purchaser's
documents unless signed by an authorized representative ot 'SG' at Its headquarters in
Westminster, Massactuselts.
1. VALIDITY PERIOD: The price quotes provided are valid for 30 days unless otherwise specified In
wri ting by 'SG'
2. PAYMENT TERMS:
A GENERAL P A YM ENTTERMSareneithirty (30) deysnom dateofinvoicewhere,atisfactoryopen
accounl credilis established and maintained. . SG' reserves the righllo revoke or modify Purchaser's
credil alits sole discretion. A mobilization payment up to fifty percent (50%) will be invoiced upon
acceptance of customer's order. Progresspa)lTl1enls loonehundredpercent(1 OO%)ofordervaJuewillbe
invoiced monthly based upon equipment delivered or stored and work perfolllled. N 'SG's'sole
option, Purchaser shall pay cash in advance, or upon delivery,or as olhelwise specified by 'SQ'.1n
the event that Purchaser delaLdts on its obligation 10 pay each invoice when due, then, in addition ll>all
otherrights and remedies available to it, 'SG' shall have the option towi1hhold any fu1her stvpments
of materials andlor the provision of services, if any ,until Purchaser'saccount isftilypaid. Further, in the
event payment is not received accor~ng to Terms, 'SQ' may, at its discretion, assess interest at the
maximum rale aJtowedbylaw or altherale of 1.5% permonth, whicheverisl_ss: Po.rchsser also agrees
10 pay all costs incurred by 'SG' in pursuit of payment which is past due including, but not limited to,
collection agency commissions and attorneys fees.
S. CUSTOM SOFTWARE PAYMENTTERMSare asprovidedin sectionA abovewiththe following
exceptions. Anon-refundable twenty percent(20%) initial paymenlwill be invoicad upoo acoepiance of
Purchaser's order. A nOfH'etundable progress payment of forty percenl (40%) of order llalue will be
invoiced upon Pllchaser's approval of a Custom Software Development Specfficalion. The iinalforty
percent (40%) payment will be invoiced upon delivery by '00' of CUstom SotIware.
C. SECURITY SYSTEM I ACCESS CONTROL SYSTEM PAYMENT TERMS are '" provided in
Section A above with the fol/owing exceptions. A non-refundable 20% down payment is required with
Pllchaser's order. Progress Payments will be invoiced based upon slipments to.'"Ptschaser.
D. CANCELLATtON: My permitted cancellation must be made in writing. ReCOlJizing thai
'SG's' damages arising from cancellation will be ditlicullll> estimate or determine, the following
charges shall be conslruedasliquidated damagesrepresenlinganapproxima~onoftheacininistaliw,
engineering, and other costs '00' will actually incur in reliance upon this Agreement, and not as a
penalty: If, priortoshipmen~ Purchaser cancels IhisAgreernentora1yportionlhereof, fo..a1yreasonnot
attributable to 'SG', Purchaser agrees 10 pay 'SG' an amOlllt equal to 20% of the price of
the products canceled. If Purchaser cancels a1lar shipmen~ Purchaser agrees 10 pay 1I1e
above 20% of the price of the products canceled, relurn the products already shipped, and to pay
'SG' an adlt tional amounl equal to 20"'!' of the lIaIue of the relimed products ll> cover the estimated
c,",1s of lransportanon and reslocking,
3. SIM PLEXGRINNELLSERVICES:PurchaserfurtheragreestharOO'otfersvariouslevelsofservicesand
that the Purchaser, after reviewing the same, has contracted with '00' to perlonn only the services
described in writing in this Agreement 'SG' denies tiability for materials, supplies or wori< provided
by other persons. Unless specifically contracted for, 'SG' denies any ~eMSOlY role and this
Agreement shall not commit 'SG' to alrf supervisory role, inctu<ing, but not limited to, the p1acemenl
or routing of any wires or other Product
If lhis Agreemenl includes a quote for Monitoring Services 10 be supplied by 'SQ', Purchaser
agrees for himself, and any assignees ll> this Agreemen~ thet'SG' shaIJ have no duty ll> perfam
such Monitoring Services until and unless the Purchaser, and anyassigree inciU<fng butnotlimited 10
the end-user, agree to and sign a 'SG' Monitoring Agreement approved and sipd by an authorized
representative of 'SG',
If this Agreement includes a quote for Maintenance Services to be supplied by 'SG', Purchasor
agrees for himself, and any assignees 10 this Agreement, thal'SG' shall have no duty to perform
such MaintenanceServices until and unless the Purchaser and anyassignee,indulingbutnotlimiledto
the end-user, agree to and sign a 'SG' Mainlenance Service Agreement approved and signed by ill
authorized representative of'SG'.
4. SHIPMENT: All Equipment is shipped F.O.B. shipping point
5. SECURITY INTEREST: The Purchaser grants to 'SG', and 'SG'. retains, a security interest
inall Product, Software, and proceeds thereof shipped pursuantll> lhis AgeementUllillhe Purchaser
shall have made full paymentfor the Product Such interest is intended 10 be effective as a ptJ'chase
money security interest Purchaser agrees that 'SQ' may file tl"is Agreement as a firaicing
siatement. In the evenl of failure to make payment on the due date in accordance with terms deSignated,
the entire balance shall become due and payable at once. In case of delauft of payment, and to the
extent permitted by law, 'SG' shell have the righl to lake possession of the Product or Software
Immediateiy, wherever it may be found, and ramove it with or without process of law and may retain ali
money paid hereunder as liquidaled damages and renla! for said Product or Softwere. For the purpose of
assisting 'SG' in perfecof)g its security interests in any 'SG' Product or Software delivered to the
Purchaser, Purchaser agrees 10 infOlTT\ '00' immedialely if any other entity has or may have any
security interest, perfected or otherwise, in the 'SG' Product or Software described on the face of this
Agreement and shipped to Purchaser. The Purchaser agrees to pay 'OO's' costs of collection,
inclucing without limitation reasonable attorneys fees and legal expenses, and thai the same are
sect..Ued by the security interest granled herein. The Purchaser shall nol sell, prior 10 payment, (except in
the ordinary course of business), mortgage, pledge, or lease said Product or Software without peor written
permission of'SG'.
6. LIMITATION OF WARRANTY: Purchaser understands thai 'SG' is not an Insurer. Subject to
the limitations below, 'SG' warrants thai Ihe Product (as distinguished from Software) be free from
defects in material and workmanship under normal use for a period of one year from the dale of frrst
beneficial use of all or any pat! of the Product or 18 months after Product shipment whichever is earlier,
provided, however, thai 'SG's' sote liability, and purchaser's sole remedy, under said warranty, shall
be limited 10 the repair or replacemeni of alrf Produc~ or part thereof, which 'SG' determines io be
defedive, at 'SG's' sole option and subject to the availabilily 01 service personnel and parts, as
determined by 'SG'. 'SG' warrants expendable items including, bul not limited 10, video and
print heads, television camera tubes, video monilor display tubes, batteries and certain other products in
accordance with the applicable marufacb.rer's warranty. 'SO' does not warrant devices designed
solely 10 fail in proIecfu1g a system such as, but 'not liiiilled to, fuses end circuit breakers.
'SG' wa-rants that a1y 'SQ' Software described in this I'qreement, as well as thai. Software
contained in or sold as patl of a1y Product described in this Agreemen~ will reasonably conform to its
plDlished specifications in effect at the time of delivery and for ninety (90) days after delivery. However,
Purchaser agrees and acknowledges thai the Software may have inherent defects because of its
complexity. 'SG'S" sole ob~gation with respect to Software, and purchaser's sole ramedy, shall be to
make available plillished mo<ifications, designed to correcl inherent defects, which become available
dJing the warranty period.
THIS WARRANTY OOES NOT APPLY TO ANY PRODUCT OR SOFTWARE WHICH
HAS BEEN SUBJECTED TO ABUSE, MISHANDUNG, OR IMPROPER USE AS
DETERIIINED BY "SG" AND IS IN UEU OF ALL OTHER WARRANTIES,
EXPRESS OR IIIPUED, INCLUDING ANY IMPUED WARRANTY OF
MERCHANTABlUTY OR ATNESS FORA PARTICULAR PURPOSE.
Wmalty service will be perfurmed at M charge between the hotJ's of 8:00 am to 5:00 pm local time,
Monday through Friday exdusive of 'SO's' hondays. Warranly service requested to be pertormed al
other Itm durtflJ 'SQ's' normal worI; hours shall be chargeable at 'SO's' standard overtime rates,
AI repairs or aquslments !hat are or may become necessary Lnder the warranty provisions ot this
Agr_l shall be porformed orly by an authorized repr....ntative of 'SG', Any r.pairs,
adjustmen1s, or intercomections performed by the Purchaser or anyone other than an aulhonzed 'SG'
representative shall void all Warranties.
7. LIMITATION OF LIABILITY: 'SG" SHALL NOTSE LIABLE FOR ANY INDIRECT,
INCIDENTAL, ECONOWC, OR CONSEQUENTIAL LOSS OR DAMAGE TO THE PURCHASER OR
USER OF THIS PRODUCT AND/OR SOFTWARE ARISING OUT OF, AMONG OTHER THINGS, THE
OPERATION OR FAILURE OF THE PRODUCT AND/OR SOFTWARE TO OPERATE, THIS
AGREEMENT, THE INSTAllATION, USE, DESIGN OR FUNCTION OF ANY 'SG' PRODUCT
ANDIOR SOFTWARE.
8. LiMITATION OF REMEDY: It is understood and agreed that since it is impractical and extremely
difficult to fix actual damages, if any, or ascertain wha~ if any, portion of any loss or i[jury would be
prOlCimateJy caused by the faijlle of 'SO's' Product and/or Software to operate, or to operate properly,
or 'SQ' ll> perlorm any of its obligations or services described herein, UNDER NO CIRCUMSTANCES
WILL 'SG'S' LIABILITY FOR MY DJlMAGES, INCLUDING BUT NOT LIMITED TO THOSE
ARISING IN ANY WAY OUT OF THE INSTAllATION, USE, DESIGN OR FUNCTION OR FAILURE TO
FUNCTION OF Am PRODUCT MD SOFTWARE SOLD BY 'SG', BE' IN EXCESS OF THE
PURCHASE PRICE PAID FOR THE PRODUCT, SOFTWARE AND/OR SERVICES. THIS SUM SHALL
BE THE PURCHASER'S SOLE, COMPLETE AND EXCLUSIVE REMEDY AND SHALL BE PAID AND
REC8VED AS LIQUIDATED DAMAGES OR A LIMITATION OF LIABILITY AMOUNT AGREED ON BY
THE PARTIES MD NOT AS A PENALTY. IN NO CIRCUMSTANCES Will 'SG' BE HELD
LIABLE FOR Air( CLAIMS, LOSSES, DJlMAGES OR INJURIES ARISING FROM OR CAUSED BY,
THE PURCHASER'S OR ANY OTHER PARTY'S MATERIAL, EQUIPMENT, ACTIONS, OR
OMISSIONS: II Purchaser wishes 'SG' to increase tha amount of the above limitation of liability or
.quidaled damages amount stated in this AgreemenL Purchaser may inquire aboul oblaining an increase
to this ~nt in exchange for an increased purchase or contract price. Under no circLrnSlances will an
increase in the plJ'chase or contract price be construed 10 mean that 'SG' is an insurer or that the
obligations of obtaining and maintaining inSlO'ance are nol with the Purchaser.
Fire, Security. Communications, Sales & Service
Offices & Representatives in Principal Cities throughout North America
IR100 Simplex
Submitted Adjusted
Subcontract (CSRA) Subcontract (CSRA)
Material qty rate Material qty rate
wire, flex, fittings 100 24,00 2,400.00 wire, flex, fittings 100 24,00 2,400.00
subtotal material 2,400.00 subtotal material 2,400.00
sales tax @ 6% 144.00 sales lax @ 6% 144,00
subtotal material 2,544.00 subtotal material 2,544.00
overhead @ 15% 381,60 overhead @ 15% 381,60
total material 3,364.44 total material 2,925.60
Labor mh rate Labor mh rate
install & test 16 19.50 312.00 data cabinet w/fans 16 19.50 312,00
subtotal labor 312.00 subtotal labor 312.00
labor burden @ 100% 312.00 labor burden @ 100% 312.00
subtotal labor 624.00 subtotal labor 624.00
overhead @ 5% 31.20 overhead @ 5% 31.20
profit @ 10% 65.52 profit @ 10% 65.52
total labor 720.72 total labor 720.72
Total CSRA 4,085.16 Total CSRA 3,646.32
Simplex Simplex
Labor mh rate Labor mh rate
PM 3 25.00 75,00 PM 3 25.00 75,00
subtotal labor 75.00 subtotal labor 75.00
labor burden @ 160% 120.00 labor burden @ 160% 120,00
subtotal labor 195.00 subtotal labor 195.00
Subcontract
CSRA
subtotal subcontract
4,085.16
4,085.16
Subcontract
CSRA
subtotal subcontract
3,646,32
3,646.32
total subcontract
3,901.56
subtotal labor & subcontract
4,280.16
subtotal labor & subcontract
4,125.81
McKni ht
Total McKnight
4,414.62
@-.nitz TO
~contracting Company, Inc.
645 Rosewood Drive 29201 · p, O. Box 82 . Columbia, SC 29202-0082
Phone B03.799..Q1 B 1
Fax for RoorCovering 803-799-0593
Fax for Production, Human Resources 803-748-9223
Fax for Corporate 803-756-4327
Fax for Ceiling & Drywall Sales 803-758-4288
www.bonitz.com
Bid Proposal
February 10, 2006
February 13, 2006
Revised May 15, 2006
5~-\.oo
McKnight Construction Co.
P.O. Box 204718
Augusta, GA.. 30917
ph: (706) 863- 7784
fax: (706) 863- 2031
Attn: Pat Patrick
Re: AUGUSTA REGIONAL AIRPORT
AUGUSTA, GA.
We have prepared the following pricing per your request and Progress Meeting held February 9, 2006.
To furnish materials, labor, and equipment to remove and replace portion a/installed acoustical gn'd
system, to allow HVAC trade to have QCC2SS above ceiling in room A122 and A 123 add $ 578.00 to
original contractprlce.
material
labor
markup
total
$ 239.01
$ 263.60
$ 75.39
$ 578.00
To furnish materials, labor, and equipment to remove and replace portion of installed acoustical grid
system, to allow HVAC trade to have access abo-.;e ceiltn.g in room AI26 and A 128 add $ 62200 to
original contract price.
material
labor
markup
total
$ 182.75
$ 358.12
$ 81.13
$ 622.00
/.
/ ~ IZc)() ~
Please inform Bomrz a/when we can expect a Change Order for this work.
If y~u have any questions, please do not hesitaJe to calL
Cc: Jerry Davis
Todd Griffin
ATLANTA · AUGUSTA · CHARLESTON · CHARLOnE · COLUMBIA . FAYE'TTEVILLE · GREENVILLE . RALEIGH . "TRIAD
~nitz '"
~contracting Company, Inc,
645 Rosewood Drive 29201 · P. O. Box 82 · ColumbIa, SC 29202-0082
Phone B03-799-0181
Fax for Floor Covering 803-799-0593
Fax for Production, Human Resources803-748-92.23
Fax for Corporate 803-758-4327
FaxforCeiJing & Drywall Sales 803-758-4288
wwwbonitz.com
Bid Proposal
December 19 2005
Revised May 12, 2006
McKnight Construction Co.
P.O. Box 204718
Augusta, GA. 30917
ph: (706) 863- 7784
fax: (/06) 863- 2031
Attn: Pat Patrick
Re: AUGUSTA REGIONAL AIRPORT I lR-93
AUaUSl'A, GA.
We have prepared the following pricing per your request.
To jUmishmarerials, labor, and equipment to install APCl ceiling in the Conc?ssion Area A127; as
shown on IR-93 response dated December 12, 2005 add $ 5.250,00 to original contract price.
Material
Labor
Marla.t.p
Total
$ 3,283.16
$ 1,282.06
$ 684.78
$ 5,250.00
Note.- 1) This pricing based upon one time installation of Acoustical Ceiling System.
2) This pricing based upon eristing gypsum board soffit to remain in place.
Please inform Bonitz ofh(JW to proceed.
lfyou have any questions, please do not hesitate to call.
~.n rely,
B. ~CITNG CO-"lNC.
J4 n .
S eslEstimator
Cc: Jerry Davis
Todd Griffin
ATU\NTA · AUGUSTA · CHARLESTON · CHARLOTTE · COLUMBIA · FAYElTEVILLE . GREENVIUE . RALEIGH . TRIAD
~nitz 1M
~contracting Company, Inc,
64.5 Rosewood Drive 2.9201 . p, O. Box 82. Columbia, SC 29202.0082
Bid PropostiJ
January 30, 2006
Revised May 15, 2005
McKnight Conslroction Co,
P.D. Bor 2047]8
Augusta, GA. 30917
ph: (706) 863- 7784
fax: (706) 863- 2031
Attn: Pat Patrick
Re: AUGUSTA REG.JOJf.ALAIRPORT / IN-I?
AUGUSTA, GA.
We have prepared the follCJWtng pricing per your request.
Phone 803-799-01 81
Fax for Floor Covering 803-799-0593
Fax lor Production, Human Resources 603-746-9223
FaxforCorporate 603.758-4327
FaxforCeihng & Drywall Sales 803-75B-4288
WWW.bonitZ.com
To furnish materials, labor, and equipment to install temporary walls / mera[ stLld and gypsum board
infi II panels in room A 128, the cased openings leading to rooms A 133 and A ) 34, to ~ecurc the
.>creening areafrom the concourse. add S 1,200.00 to original contract price.
Infill: material $ 123.91
labor $ 506.20
Demo: material $ 12.97
labor $ 112.48
Patch: material $ 62.94
labor $ 224.98
Marlrup
T 010/:
$ 156,52
$ 1,200.00
(Note: Pricing does not include overtime).
. Please infonn Bonitz of how to proceed.
If you have any questions, please do not hesitate to en!l.
Sincerely,
~. ONTRACTING CO.~ INC.
'~
n Sales/Estimator .
Cc: Jerry Davis
Todd Griffin
ATLANTA . AUGUSTA . CHARLESTON . CHARLOTTE . COLUMBIA . FAYETIEVILLE . GREENVILLE . RALEIGH . TRIAD
c.;I elecrrlC, ,nc.
4191-AugustaRegionaIAirport-COs.xls
CO#8-Rev.1
....., Q i, "\
+ 1\-.lUU
Cost Breakdown for
Lowerin!:f conduits and repull wire in rooms A122, A123, A126, A128
due to ceilin~ heiqht beinq lowered to 11 '
Quantity Unit Cost Extended
3/4" emt 200 0.65 130,00
3/4" emt conn/coupl 30 0,70 21,00
allthread - 3/8" 200 0.40 80,00
unistrut 50 1,60 80.00
4x4 jb w/ cover 20 2,65 53,00
scissor lift rental 1 293.61 293,61
Miscellaneous 364 0,10 36.40
Subtotal Material 694,01
7% Sales Tax 48,58
Labor - workhours (overtime) 120 31.50 3,780,00
Labor Burden @ 35% 3780 0.35 1,323,00
Subtotal Labor 5,103.00
Labor & Material 5,845,59
15% Overhead & Profit 876,84
Labor, Material, Overhead & Profit 6,722.43
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil., pull string, ropes, tools, and contingency, etc,
Schedule Implications
All material prices good for 10 days.
Schedule impact is one week.
Exclusions:
All sheet rock and ceiling repairs are by GC.
File: C :\4191-AugustaRegionaIAirport-COs,xls
CO#8-Rev,1
5/25/2006 9:35 AM
CI Electric, Inc..
4191-AugustaRegionaIAirport-COs.xls
CO#11-Rev.1
Cost Breakdown for
Temporary Security Area (Buildinq A)
T' ,,7 (~I. ~r
". ~\ '..........t ---..
~.~\- '-./
power 3/4" emt
power 3/4" emt conn/coupl
power 4x4 jb wi cover
power 3/4" flex
power 3/4" flex connector
power #12 thhn
power 20 amp bolt-in breaker
power 12' power and comm pole
power 3/8" allthread
power 3/8" beam clamps
power duplex receptacle
lighting "E"fixture
lighting 1/2" flex
lighting 1/2" flex connector
lighting 3/4" emt
lighting 3/4" emt conn/coupl
lighting 4x4 jb wi cover
lighting #12 thhn
lighting unis trut
power & lighting scissor lift rental
Miscellaneous
Labor - workhours (overtime)
Labor Burden @ 35%
Quantitv
200
40
20
30
10
1000
4
2
200
30
5
12
100
24
200
40
30
1000
50
1
4360
120
3780
Unit Cost Extended
0,65 130,00
0,70 28,00
2.65 53,00
0.80 24,00
2,25 22,50
0,15 150.00
32.50 130,00
265.00 530,00
0040 80.00
2.25 67.50
6.50 32.50
211,80 2,541.60
0.60 60,00
1,80 43.20
0,65 130,00
0.70 28.00
2.65 79,50
0,15 150,00
1,60 80.00
293,61 293,61
0,10 435,98
Subtotal Material 5,089,39
7% Sales Tax 356.26
31,50 3,780,00
0.35 1,323.00
S.ubtotal Labor 5,103,00
Labor & Material 10,548,65
15% Overhead g; Profit 1,582.30
Labor, Material, Overhead & Profit 12.130,94
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc,
Schedule Implications
All material prices good for 10 days.
Schedule impact will be determined upon approval.
Immediate approval is needed to include this CO in Phase I (Bldg A) turnover.
Exclusions:
Voice & data, low voltage, and communication cabling and terminations.
Circuits not shown on electrical drawing (power pole circuits only are included).
Repairs to ceiling grid and ceiling tile,
File: C:\41 91-AugustaReg ionaIAirport-COs,xls
CO#11-Rev.l
5/25/2006 9:35 AM
.b 10 86 02: 22p
McKnight ConstructlOn LoU. IUU "~ ~---
Parsons
Srinckerhoff
Construction
Services, Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
706-771-5172
Fax: 706-771-5176
-
-
100
YEARS ~
FebmaI)' 10,2006
McKnight Construction Co.
635 North West Fronta.ge Road
Augusta, GA 30907
Attention: Mr. Lee Mooney
Re: Augusta Regional Airport - Terminal Area Improvements
Temporary TSA Screening Area Related l.R. 's and LN,
,I
Dear Lee:
This correspondence is provided as a distillation of the responses provided in Information
Request (LR.) Nos. 93, 95, 100 and 103 as well as direction provided in Information Notice LN )
No. 17. This letter is not intended to revise, delete or otherwise contradict any of the infonnation.
provided by the Design Professional, but summarize the information.
LR.-93 - Provided finishes for Room No, A127 which are as follows:
Floor - CPTT2
Base - RBI
Walls - VWC6 (subsequently modified to Paint in I.R.-I03)
Ceiling - APC]
In addition, Sketch No. SK-E05 provided direction on the electrical requirements for the
temporary screening area and added (12) Type "E" light fixtures, (4) Power Poles and (l) Pov,,'er
Panel.
I.R-95 - Provided direction to add sheetrock to the Southeast comer of the future
Concessiontrenant Upfit Area.
LR.-IOO - Directed the ceiling height to be modified from 16'-4" to 11 '-0" for Room Nos, A122.
A123, A126, A127 & A128.
I.R.-I03 -Identified the final finishes which would be in Room No. A 127. The ceiling CAPC1)
will remain as final and the flooring (CPTT2) could remain. The Designer indicates the previous
designation (l.R.-93) for wall covering VWC6 should be modified to paint. This I.R, also
provides direction on the location of the temporary storefront partition which should be position
on the inside edge of the columns (relative to Room No. A128),
LN.-I7 - Provides direction to install temporary partitions in the cased openings between Room
Nos, AI2S & A133 and A134 to prevent access of screened passenger to the screening area,
Over a: Century of
Enginee,-ing Exceilence
0/
~b 1006 02:22p
McKnight Constructlon L.O. ruo- 11'- u'"-v....
1- . -
Parsons
Brinckerhoff
Construction
Services, Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
706-771-5172
Fax: 706-771-5176
-
.
-;00
YI!'AAS",:,
McKnight Construction Co,
Mr. Lee Mooney
February 10,2006
Although it is not specifically enumerated in these various I.R.' s or l.N., the lights, speakers,
diffusers, sprinkler heads and any other associated equipment must be lowered to meet the newly
designated ceiling height identified in I.R.-l 00. However, it should be extrapolated that this is
the case and any costs. associated with these directions should be included in a detailed cost
proposal to our office. In the meantime, you are directed to continue implementing these
adjustments in the current manner with which you are proceeding,
If YOll have any questions concerning this matter, please feel free to contact me at (706) 771-
5172.
Sincerely,
Parsons Brinckerhoff Construction Services, Inc.
JJ1~ }?/~ -
~a~:J.MCCOY . ( :7
Construction Manager
Cc: W. Boshears', T. Weegar, T. Story, ARA.
P. Patrick, McK
M. Leath, B. Anderson; LP A
R. Roberson, D. Blessing; PBflNT
File
Over e Century of
Engineering Excellence
Jan
18 06 08: ::loa MCKnlgn't. L.ons"r'uc.;".lUII ........... i it... ~~~~
L~/~~f~~~~ ~~... O~~-~(J-a~c~ ~rH ~un~I~~'~C
~'-_ ~ ~';..ICJ-' ~'...A..l1 . '"\Uf 1.1 ..,....A...II"1=' l:~J..I~r
ue~ U~ ~~ u~;~~p n~~"l~n~ ~Qn=~ru~~~on ~O.
."
IU:l~"(~(4!::i
rUl-'lc-r:H:'C.::J
PROJECT Ntl1v1.e.eR.: ARlO')t1211
TERMINAL AR.E.A IMrRO M~NTS
A.UGUSTA REGIONAL AIRPOR.T A S.a: :FIELD
INFORMATION ItEQUll'STNo .IR 21!
SUBJECT: Temp. SeclUrlty Jv:ca
SPECrFlCATION REF,; I
OR.AWTNG REF.: A2,l, PHL2 I
DESCRU?,ION: I
ICntp. Security:arc:1. is located in ~ <\I;l:ll. tb<U. is UD.6nialc:tS (ao lc,.-ujri.or "\IfnI~.. 'l\() 1lnlSh on \O\O':lllR,
no ceiling, flOCltin~ or ti~
,- . -
rMOc.. C,.I-..,uo
P.S
p..;.
.--
l'ROJ>OS.ED SOLUTION: ,
A.dvi$c how to fini$lb oft IW) l11rough JJh;1oo 3,11.
COMPANY NAME: McKIlight Coosuucrlon
..
Submltmd hy: Lct:MOO11cy D:atc: 1212105
RltSPONS,E:
Signed by:'- .'. I :lta:
Arcl\ltel:t
SiGned by: [ ~tI:::
Conllt.motian
M3J'I<\l:cr 1
U wls resposue == any <lOSt or lima im~ 1lI1tJUS" work,. do nc pr a:cl2; submil OJ c~ ~J (COP)
for dJil,lW:S III Olntr.lC% Swn lIn<1Ior TIme w.llhlJt GIJ UO) ~ Jr ,Is Indicates l'O challJrC to \he;
Work Or':t nllnm- c'h.:n~ 10 tbe Won: cons:iStent w.ilh lite ~ )ocl menu, lndic:illl: )'lIW' ~ of
1111s TCSpO'1lSC in the -space iJldlCl(ed bclaow :mil W1:f\Un:oll ~ prior tea &-
Acccptedby: I me:
Coalmc1or S'I~c
Cc. Cl)N~'ItUC'l1ON AolAN^GEJl.
....~CH1TI!CI.
O'M'lJln':lltF.l'IlE:rnl'ITA:t1\'!:
cr.->>TR-\CTOR.
TERM1.'NAL A.'REA TMPROVEMENTS CON tnt, CT MODIFICATION fORMS
AUGUSTA REa [ONAL AIRPORT, A.UGUST A, GEORGiA o 12~O-3
lr--
ur
an 18 06 08: 37a
. .L:L/1:l/:il:ltl:J l::1::a,
McKnight Construction Co.
t1tJ.:l-' (::l-aqtfL
706-772-tlC::tl;:l
~A -='cr~
I
p.o
r-A\::t:. rr':'l tlO
Information Requ.ut-93
Temporary Screening Area Finishes
. Augusta R.egional Airport
December a. 200S
The Drawings indicate that the temporary screening area will loeated In the future arC3S d.csignatc:rl
as Public: Seating A128, ConcessionScating A126 and Concc: . n A121. Both ar=
A128 ami A126 have finishes lisud 00 the finish schcduJo.in th ArchiteC'tunll Drawings A 7.00 :mrl
A7.02.
T.h.c CoJ:lce5$io:n Area A127 was designated IUl tenant up-fit 2Uld ~s no finishes listed. However, we
would T'CCODm\cnd the: following :fin1!lbes to be installed for the ~ce while it ~ being used for the
temporary se:reenlng area.
Floor. CPTI'2
Bage: RB 1
Walls: vwa
Ceiling: APeJ
Reference Sheet A7.02 of Arcl:rii.eclm'a Dm~ for complete ist of products.
~~/~~/~aa~ ~~;~~
Ctl.::l- I {J-i:J'H''':::
W"" I't 1-VVJ1.1. I to. I '-"''-
l\Za~
-:.
GR~E! ~.~
ARCHITECTS. ENGINEERS. PLANNERS
FAX (803) 779-0482
LPAJUBNO. ,AtZ~~
.AtS ~ IIt-#4-
Total Number of Pages Transmitted.-.!/JJ Ar (InCIU~ing Cover Sheet)
If aU pages are not receivcd~ please notify sender.
DATE:
The information in this m~e i:l in\lCnd~ fur the II~ of thI; individu4l
communiclltion in onor, ple&e notify the 5coder immediAtely bytclephonc.
ThIill1c you.
l100W only. If)'Oll ha~ n:c:cived thl!:
THELPA GRoupmCORPORATED
7{)O Huger
Po:rr. Office ,Box 5805
Columbi", SC 29250
. (803) 254-2211
Jan
18 06 08:37a
--
..
~!:~c ~.n.. i S;~~:
Construct i on Co. '/Uti - 'l'll:!. -!jctJ;:J
TSA Airoort Securit
:./'/./..
?;r:z.!
//.//
~/f.~ I @ I
f.~z,
{f,g.
'z~;-',
~f1;
%:;(j
Z/"7/.
;::;,%7
.;/.,;'/-
im
~;.-:~
~;%'/;:;
1fJ.
';/,/.',f'
;/,/;.-"
:.-/./X
~//f'-
;./~A
~-X;-7
'%~:
rf.y~
f%;
.Yf{f-
11' -'
X ~
.. ~
'Z.%,i:;
~J";i
~~".1
....,;.-:..,'
~~z
.-;?; f.
~p'};
~J},
~
.'/'r,%'.
/:;r.:/.-
{XX"
0.0
?'~
;J'{;.
-..../.1',:,
]
~
~ a
~
~
0 0
D i D
Guidelines v.0703
~
NOTE: See AUached Power and Data Requirements MatriX' for det 115
@
([D
12D vult doublo duplex l'C!l'~ (In
flCQl II polIslblft)
120 VOlt dllpll!>< nlCoplcclD (In floor if
Foo=ible)
~
o
~
a:J
~
(()
D
..e.. _ ~
/
l.W1CSS !'fl\
L~~Uon 'lJJ
i~
7.f.~;
~~~
r:&1 i:/'/..1
~ q::}}
~a
~~ }.-;Jffi
\ / i~'
V :'.1,,(Z
-.r,:,.;::'
.:::oZ%"
~
W
%~
..r.?:'-:
n 18 06 08:37a
McKnight
\,JUw " -' U....U4
~4'~~' ~u~~ ~~.4~
.Y. .
~c.
;;;:;: ~
~ t;;.t)
:~~-5
!..~ ~
f.:~~
~::
~
~
~
'~
<i!
Et
..,
~
l
j
!:
I
ti
~.
:!l
.};
~
..;j.
'z.
:&
..
.~
4J
.:l
.il
wll l~.i ~
~1~'~~lll j
~~J.;~~B~~ ~
~i~t~t;~~ Ii
~iji]liiK 'i
e I:'i ~ l1.J1l- ell'
~~ r:i~'!~~ ~
~1J!..~:l!; ~;
~1:~...3! l:ij
il!$!~i'::~l:';
:;{;]~1l~i~
.2"'.~o>l: ~~
~"ii!!',;~ l-~
.It 1/__ ..
>- a c ..,
"
'J::: 'I..
s'"
],~
r: 1.
;:Eo
...~
...
"
~3
~~.
~ ~.
8
"
. .,] ,!i
"Q
. ;;"'::
-Ci
;1
""
t
~
~
",
..
"~
...
~
'll
'0
..-
at!
~~
;1
!~
!
Jl
<lj
J~
~ ".
"'j
!i
. B
-l! ..
il'"
.E
il~
0_""
i~'"
t~;
c-
L
E
.,,"
..
'U
",,,
1;:';
..;.. ..
~o
~.
'::J.,
1
!i
:t':i
too
.~
. ~'
.;
.,.
. lU .
E
i:sl .
:x:il!
~~ !:il
;j"!l
c I!~
~ ~-'l
~!t::1
!.. Ii ·
Na;~
~':
Construction Co. '/Ub-'IC-OCO~
W" --'''r-
I~
"'.~
'111~
~~~
,:;",
"'.II
~:c
~It
~l;.i
O~j:i
~i
l1/.
:i~~
i dl.
e)!!
!-S8
a
..sS
ei
-"lift
~ .!t~
JI' Co"
IItn;:
i~li
~ (.
~l~
.!2.!L
I .!l.....
m'!i
:g-::.
.2
I
iii:a
-II
~:iC
~~j I
,", ..-
~~~
E2~
..'Ii
~i
"
c
,.. ..
jl~
~~~
111<'<
li
...-
!
~ iinti iu
i .hlh lB~
eo
'Ir
.~ ~
C)l~
iii
:zlll
;!i1
a
i
.5i
~~
;/t
~
!
ia
~i
i!
Q
i~~
t!~
"c!I
l!!-
j
1iI
..
ol_ 'I!'
. . 1;
l! ~.!! ~ I
i ~1 '" ~
ii!. I
-,..
~
~~
A~
t: ~
~l
~~
fi
...5
~;fi
~
I
i !.
,;; i1
5" ~
!!L fi: h-
!e t~~!
_ i1 ~
1.,g '~
~ ~~t:-
i ~iii
.:l ~~.1
'" '"
cl!
~;o
i!J~j
~~~
i~
I!!..
...l!
5!~
~gl!
=!rli
ju-
i!C~
1~.i
I ~I
l:i' -
1 ! I t~ !
Al t~'HI
~ 1,,:11"_
B '\ll'! 5 ..
, ..
:::
'"
.
il~
1!~
e-
ll!
~~
~l!
.~
N~
loll
ii i
! ~ 1 i
., t~ "' H
~~Q i~"
'2~1 t:li~
o~~ 1>:i~
i! gi
e e
i Ie
it iil
If",
J !I
d~ S~I'!
i' a i'8.
m>il ~!I
E! ~.. 1J! i" .
o
.... ....
il~--lig
t~~ li~
il~ lH~
i
!.
j_.l
. ! ~ II I I I i
~Ilti_ it
!~:r~il . il.E
-~iha- "ii
. ~!~!I~ i~ .
J:"r- v:'
G
i
';I
II
I
o.
8
..
o
~
5
~
.Ii
~
i
c
i
1 ~
j ~
,8 11
i 11
~ :c
~ !
:lI 0
I IU
~ i
~ "
.~ i
~ ... j
i ~~
b !li
li..IJ
l: It~!
'! eH~
..'i ..e.j!.e -
.u....!'$~
r~!lit ~
~ 11 t a ~ i
J!~l~! i
e f
1
i
-
...
...
B
l
...,
., 18 06 08:37a
McKn 1 gn't. ....ans"ru\.;... ~ UII ......~.
sims gro,u/J.:
ENGINEERS:! INC.
744 SUNSET BOULEVARD, SUITE 203
WEST COLUMBIA, SOUTH CAROLINA 29169
PHONE: (803) 765-1007 FAX: (603) 765-1030
LETTER OF TRANSMITTAL
DATE: 1/13/06 SIMS JOB No. C4075
ATTENTION: Angela Logan
RE: Augusta Regional Airport
TO
. . ~ \
The LPA Group
700 Huger Street
Columbia, SC
} ..L.', .{
,r -..
. . I ;
.\"....-/
..-\
Under separate cover via
., :' ,'~
th~ folJoWihg items:
WE ARE SENDING YOU
o Shop Drawings
D Copy of letter
IZJ Attached
[8J Plans
o Change order
o
D
o
Dis kette
o Specifications
Other
COPI!;,$ DATE " NO: DESCRtPTION '" "
, ,
1 1/13 IR-93 Drawing .
,I
~./?4P t\
I~ I .)-/f:::;:]'
\.
..'
THESE ARE TRANSMITTED ao checked below:
D For record
I2Sl For your use
o As requested
o For review and comment
D FOR BIDS DUE
o Reviewed as submitted
o Reviewed as noted
o Returned for corrections
o Other
0 Resubmit copies for review
0 :Submit copies for distribution
0 Return corrected prints
2.0_
DpRINTS RETURNED AFTER LOAN TO US
REMARKS:
RE~W
'JMt~ 0 ,"uuO
COpy TO:
.... .
~~. r,\ /'>
_ ~ 'i~.r _
- f)t...--I ~'
.~ 1/ ·
~:::; ,~~
~I
~l
~
T' I
J=
~~
'. .., I
S UD WA LS
.
I
po-
:=
,.--'
---1~ ,
l::::.
.~
I
· - 'fA!
~nmg F.): r
I: =:,::':::::::::f3 L'-J- to'
,
.
,
Ii
C .II'J( E.S' 10
.. ..
. .,~~~
l...,_
/
.
RELPCP EC
~ ~R+l-T~9 ~,.
7 I I
.
.
. :
.
I
.~. .
1:'1 ::n'l('
,'r:-ATII\,wl ~
f"=';::i,y .-
;;;;;.-
~
I
. 81 SE BID
n~~i'
I
31. ~C
::::~
I
. ....-
I
L-
r--,
!.la- ~~ I
- -KJ:l2- ,..3
Lf- .---.~..F]{-
~
I:. .
L....
\ S(RE! NI"G
[)o
I t:.
\
u
1 1
. ... -
.
, ~ j:;-'?, "'AL
/' -
'= ./ f."'l ....
, !r-L: Cr ING eOc R
, r;.
, rOo
. l
,
,
,
\
~ ~~
=
II\W
'e
: 'E"
: PApSENGE R
,
.--
.
~h
l I TJ~
. b\[ L
r. I 7''''
......~-
.
e
SCA~: 1/8"..1'-0"
AU~~~IONAL AIRPORT
TER8.h~~l!i ~EA IMPROVEMENTS
. AkfS P.
AUGUSTA, GEORGIA /
GW .. \ ,-, rii::;j
I I.~' C ~~
r-: "I I""
I J
-
, ,..t:.~"
-
V"'I' ,1
IA I""",
. .
.
,.Ail
l: I '
~
.
L-<"'l
T
u
\.-...!
,.
.
~''I :t\M,a~"...."
.lilt
. \"\
L-I-\ '\ ',. '[ ,
"\ , JL,~
m;"':1f:; 'n
I
.l-f -.::::- -' fill L.:
,,,,,,, "[!\..J['::
J1'
) \ I
h
,-
II t:::=:::::I
11lE3
1\~5
~~ L
~ j'ji
I J V
.
.
I
u U
~~J " (<'~ ,,'Ii
. ",- " ,
~:--
. . . ~
v ::>
r.......:..-,-;: ..
-~ L-.: J .
A IC;f ME
I I~fr
... f-
.
\
Irl1!9. 1:"-
II \ ~
, tit'
~;...:-:':
,.....
t i I
)0
t
';0
,t
...
:. \
-,. \ \
c. r\ ~
\ ~~
=
. I~ t
H LL
.
.
;... -!"
>e
, t..
,
/
IL, ,. · .. ·
\,; ~~, _ ~~~. NC rf
IWR PO = LUll Pli rE rim
\ 2,l OA. OU~LE~ R CEF TAC
,'... ....... ......,I..=-- r'I" ...
.~ PeA o~ 0 PClES PR OR T
~~ ,.- 0
.... ~\ uM' n...... .
_ '- F\JR~~ I~ ~A: (.a.,
...,,~.. ., n'.. ,..". ""T+-B'~ :..J.
IN PAt a fkp · As I EO'
IV r l:.I:.u I~l:." I"'n [\ I'" ~u:. .
:-
t:.
~E:.U
~
I:
IN
("i;:i
~ EW 1YP~ -I. FlXTt RE;
~~/,~I~. ..lfl:'tn'~ \';~l:)
-f--
~
c. i"'---. J:,. .!. ,_,. .~.. ,. .
~
Wll
ELECTRICAL PLAN
TEMPORARY SCREENING
slms-9WHlJl
ENGINEERS. INC.
7# BUNSU BIJUUV.a.D, smn llJj
nsr COr.maw. SOU1'lI CUlOUK.A zg"p
PHon: ('0$) 'IU-,m ,JI: (40') 78&-'030
SIM~ PROJECT/'IMJ,". C107.G
DRAWN 6'1': CLP
REFERENCE SHEET: EPH1.2
SKETCH No,;
SK-E05
D~~ 13J~lUARY2~
n 18 UO utl::.:n:la
nct\.nlgnl:. L,;Uri~~1 Ui",,;~.J.""'11 --- .-- ..-
,-,>tJ>.., I' J U"\.I,," L...I ,.., ~"Vf'+ 1c......J.J'~t:..
r,",,~ u...., tJ.J
DEC-l::;-~ 1:!I~:j4F\ ~r1:PAR:S01-lS f3RI~\"IOF'F TO: 1.5el3TT98TQ9 1",0:::
D~c , ~ 05 01: :aOp MoKnie;ht co"struc'C.lon co. ., l:Slf"l~-t1~tl::f . p. z
. 1"RDJECr NUMBeR.: AlU09-lJ24
, TERMINAL AREA IMJ.'RO N'rS
AUGUSTA REG7.0NAL A.l'RP'ORT TBUStl: FIELD
[Nll'OIlMA ~lON REQUEST Na ~ - .1!!!
SUB.JECT: Tetl\p. Soeurity An::a.I Rdoc:ltod Pa I itl~
Sl'EC1F(CA'DON' REF,~ 09260' I
DRAWlNG REF.: PH'.2
DESCRIPTION:
What is the lntonded hl:igbt afUu; n:~
3/PH1.l? Wood the
in place nt this time?
AlIa as shcrwn oBA7.6 be
PRON>SED SOL'0T10rlh
Keep n:lo=tcd ~n:; below ,;ciJing bclg-ht. Pb:ase <1dvi:lc.
I
MPANY AME B
Co
eorJu
CO N : oNtt ntt'l1CtiDglMcKnieht (lbon
"
Submitted by: J. KoonIL. Mooney Dare:
RESPONSE:
I
Signed by: );de;
A.rcbiu:ct
Sia.nad by: )lOlll:
ConstnIctttln
M=.I!l:r
l'f thiS' rt::S)lC1l$e CDUl:I!$: /IJI}' 00l:t _ tillm ia'lpa= I(J fOUl" WOdt. de ' _emu ~ COCt Ptapot::U (r:::P)
1"01" cl~ in ContnlCt Sum :mdIar 7iJne wilbin tL'2J (ltl) IJIIyJ;. rr nsc lndlentcs no ~e: to Ule:
Work or ~ 1\'lifIM ~ lo UIe Wmk CQ1U'isteftl with 6", CoIluoct I = ~am&, klclicatc )'OUr llCCcponce of
Uti.:: nllipOn51: in Ihu l'JPll1:l: i1Il1kalcd balow~nd n:mm. alp)' pdarro. eo:liRt-
A=cpted by: bt'2:
c-...n-r Jllp-'__
C<:: CONS'm0Ci1ON U"l\IA~
AR.CmTECT
'O\\o'NI:!It'r Rm'nES EN1'A'n \II;
COfoITIV'CT.OK
"}:'ER.:MI.N'AL ARBA.1MPROVEMENT.S CON' [1\, to.cr MODlFlCATlON fORMS
AUGUSTA V:8cnONA~AIRPOR.T, AUGUSTA, GEOItG1A 0} 230-3
~
,
:l 10 UO UO...J\....IoQ
'.I.:c.r J. -;,/ '.l:I:lI:lO .I. , ; q-=,
11_1'11.0"-- --..---
t::ltl.:l- I (~-"4l:l:'::
L..I""A A~llll.iIUl<t.
rl""'1\.o14- ....._..........
InformaDt>n Request-1M
Temporary Screening Area Partitions
Augusta Regional Airport
December 19, ZOOS
The intended celling height for the Concession Area hould be 'the same as 'the
adjacent areas 'wVhioh is 11'-0". Once this cei\lng is in,stalled, it wUl be the permanent
ceiling. Please note that the fonowing rooms have th~ 11'-0" ceiling height A 122,
A123. A126. A127 and A12B. Room A125 has an 111'.8- ceiling height. Please
disregard the ceiling heights listed for these rooms o~ the finish schedule, A7.QO.
The relocated storefront partitions should extend to tthe ceUlng. We would recommend
that the addltlonal height needed be added at the be of the temporary partitions that
you will be reusing and the finishes would be paint a d rubber base. (See IR-93 and
tR-103)
The gypsum board soffit between rooms A 127 and A 28 should be installed prior to
finishing the ceiling in room A127.
,>
1 8 06 08: 3 SaM c Kh 19n~-...... u" => '" I ........ - - _. .
~.'.~/~UUJ ~r.~~ V~~ ,,~-U~~ ~M ~~~I~~'~~
/DEC-1E,~20la5 \1.S:11tlP FRCX"1:~ ~~ .. . ro'1003T7QQ749
..JIl!:U ..0 U..,l L..t ..Lt... '....n't...&..1'~ _....,........01 ............"...., ,.",..,.. ,-- #,.. ----
1=).1
1"'--
DJECT 'N1Jl'.1'f.ll!R: AlU0902-l
TJmM1NAL AR.EA.lMJ."'ROVE' . TS
AUGUS-:rA ltEGlDNAL AtRl"ORT AT JJ B FIELD
INFORMA nON JmQUEST'No- III 1m
SUB.TECT: Tomp. 5a;luit)' A=b llJ1d Cort~o... ~in !:nes
SP"!!C'WICA110N REf.: 9260.. 9511
DRAWING REF.~ ef:U.:l
nF.sc Rt:M:'1O l"l: .
I
Will the cc:lllQ~ lUSd 'W8I1 fltrisbcs ltgcd 00 1lt-93 fur the ~~WI
finishes li:Irthis:lJ"C3.. orWlll1lleybc~ aud~~g
:J.r~1 \Vhat is ~ lotelUicd c:billng beis.bt- b' tho ~icn aJ'C!l
~A127 be the fin!.l
wild ot4'to the conc=itln
'JTI
PROPOSED SOLUTION:
1'1~l'UIc <ld.vi!o-
o.xoe; 12/16/05
Submitt:d by:
ReSPONSE:
T"ERMlNAL ~ IMPROVEMENTS CO
AUGUST ^ REGJONM. fJ'RPORT. AUGUSTA. GEOR.GIA ;
. '.! ~. '1)
. ..
. e f .
. IlIODit 1\ Co<< Pt'oposm (CI")
nlllO lac!lofo IlO cNlftF to th<:
lndl= your H(CCJItnnC(; of
Signed by:
Architect
S i.:ncd by:
CotlSuucticn
Manager
u: d,i" ~n_ -=.!1:C8 tIln1 CXIU. ..,. lione is:ap:lCl. 10 )'001' watt. do aDt,
fo. c:II:mgCC In Coclmat Sum atllllar' 'T1mo wilbUolOJ (10) &,G, If thIl1
WoIll. or II minor c1Wl1C 10 00: Went: ~ "i1lIidl tlu: ~ t:io;u
this ~ l1\ lbc .0Cl jl'ldjc:ded bcw. ::pI-relUJ'h~ capyopPar 10
Acc:c:ptcd by:
c--.--!r~
CC": OCI'tS"l'1ttlC7tON Io&Al'IMClI.
AR CJllTl'.aT
OWNDt"IIIl.JWJDl$!NT.I\1W'&
cON'l1U\C1'01\
r,,(OO[J7[CA nON -PO R.MS
Ol2S0~3
n 18 06 08:39a
J-"'-' .L ';;)1' ~tJCI:.J 1. ,.. tl4.:J
MCKnlgn"C. L-UII:::>'-. u'"''''...~.. ---
OO~-('~-U~O~ ~M ~~r~~'u~
r~ Q;./f r.J';J
Information Request-103
Tem:pDrary SereenJng Area Finishes
AugtUta Regio.at Airport
December l~~ 2005
RE: m....93
i
The ceiling Installed in room A127, win be the permane!nt ceiling for that room. The
intended ceiling height should match the adjacent spa4e A 128. The gypsum board
soffit between these two areas should be in place before the installation of the ceiling
In A 12.7. See 'R-1oo for ceiling helg'ht Information. .
As for the finishes for A127, jt Would be our intent for tl'le permanent finishes to be
installed after the space Is no longer being used as t~ temporary screening area.
However, the ceiling will be permanent and the carpet ~ be permanent. As for the
walls, IR-93 stated the use ofwall covering (VWC8). On further revlewhowever, it
would be better to use paint on the walls. The paint ~uld be replaced wlth wall
covering and the rubber base with wood as indicated iri'l1he finish schedule A7.00-
A7.02 in phase 4.
!
Also. locating the temporarY walts to align with the insi~e of the column would help to
alleviate some of the finish Issues. I have enclosed a C;opy of the floor plen Indicating
the location of the wall and 'the finishes. We recomm~d that the additional height
needed for the relocated storefront be added at the bo~om. This area lNOuld be
finiShed wIth paint and rubber base. See IR-93 and 1Rl-100 responses.
,WIt,.;r...II.J. &11..... -_..-
~
._.~--j
rolPO~ ~l\Cl'
~ ~~~~~,?N
~
~--..;
^-> \.
IICIJlIIolII!I' ~~ ~. -~. f'IUI"" D'Ilo'll
~ ~
~l~ .
:tt.~ ~m
,I
,.
tr fOR DE:T~' .
r':WU" SE1!: SHIE! Ptll.G ~ .oC,Ill,S.
~f'OIUR1' SiQtlRflY SCftEOll~
@ ~~.~~A"
~~N\ 1"ft..
it..'T1;IS f't'1-.sl;
'is.ttD ~ ll'1'S1O* ~ ~e:c~ sECT"Olf , ~D.
"
.;{S .l't\ASE
...
llI:8OI fttA.
gl\~_ JIN
Pft()Jt(.T..e. ~~otQ:Z4
HQ.
=--
",,/
nNG
iiiCJWnOIl
Ali_ !)AT(.
.. ,
-'. ....-;._. .......-
. . .
_.! ...._ _...-1. ......._..(-:"".;"...,.:.~.-
1 It:' Ub Utl:.:ltlCl
t-ll.Ji'IIJ.&llv _.......,_...... --",,-.-.. --
\."
PROJECT NUMBER: AR209024
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELD
INFORMATION NOTICE No. IN --...lL
.~1
DATE: January 16. 2006
FROM: The LP A Group Incorporated
TO: McKnight Construction Company, Parsons Brinckerhoff CansL Services
SUBJECT': Temporary Screening A 127. A 128
SPECIFICATION NO:
DRAWING REFERENCE: A2.1, PH1.2, FP2.1
DESCRIPTION:
. Auequesred by the Construction mana~er, this is to clarify two points. In room A128, the cased
openings l~ding to rooms A133 and A134 will require temporary walls to secure the screening area
from the concourse. The infill panels should be gypsum board and can be painted both sides. The
second point concerns the fire sprinkler system. Location of heads in space A127 is indicatcdon FP2.1
Contractor shan replace existing upright sprinlders with concealed 'Pendent sprinklers (escutcheon color
shall be white). Provide additional piping and flexible piping connections (i.e.. Flexhead) for sprinkler
installation in new ceiling.
Architect or Constroction
Mana." Company Name: ~ed
Signature: ~r"'--
-......
If this notice causes any cost or time impact to your work, do not proceed; submit a Cost Proposlll (CP)
for changes in Conlract Sum and/or Time within ten (10) days. If this response indicates no change to the Work
or a minor change to the Work consistent with the Contract Documents, indiclIte your acceptance of this notice
in the space indicated below and return a copy prior to proceeding.
AcCepled By:
Date:
cc: CONSTRUCTION MANAGER
ARCHITECT
CONTRACTOR
OWNER'S REPRESENTATIVE
MARK WATTS- BUFORD OOff &. ASSOCIATES
ATTACHMENTS-l PAGE.. as" x II"
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AlRPORT, AUGUSTA, GEORGIA
CONTRACT MODIFICATION FORMS
01250-3
n 18 06 08:36a
McKni~ht Construction Co. 706-772-8283
L,IM l?i a: '\5MP '~JG.U~.~
. $i:E. ~-6lI.i-
--4
I
I
LOW PLANTER
WALL WI
DECOR. GLAZING
PANELS
}.
'''@TYP.
~
CO~ESI'ON
127 .
TENANT UP FIT
re.
to NCESSION
SEATING
IIA 1 261
I
SLOPE ~ H SIM.. H SIM.
'I I :( SLAB LEVEL 'AT DOOR. OUTDOOR
j 6" WARP TO ME;ET ADJACENT SENrING
[ . ... . SI OPF I '1 (
ItJ- \"7
~N:.6 \ ttIf 1
p..:!
I
"\ 1. 8 0 6 0 8 : 36 a
McKnight Construction Co. 706-772-8283
p...,.
Subj:
Date:
From:
To:
FW: IR 89, 93, 96, 98 and 104 Responses- Augusta Airport
1/6/2006 10:00:00 AM Eastern Standard Time
McCoVM@Qbworld,com
agsairport(cV,aol, com
Lee,
The Professionsal's response 'for the referenced items are below, I am passing this info on for your use. I will
review the responses today,
Matt McCoy
-----Origi nal Message----
From: Logan, Angela R. [mailto:ARLogan@lpagroup,com]
Sent Thu 1/5/20063:25 PM
To: McCoy, Matt
Cc: Anderson, Bob; Leath, Mike
Subject: I R 89, 9.3, 96, 98 and 104 Responses- Augusta Airport
Please find the following responses from Chris Patrichof Sims Group:
I R 89- The proposed solution is acceptable and was actually addressed in addendum #1 , item #9,
IR 93- This is partially addressed on the Electrical Phasing Plans, particularly sheet EPH1.3, Note #2 states,
"PROVIDE ELECTRICAL FOR PASSENGER SECURITY SCREEING EQUIPMENT, FIELD VERIFY
ELECTRICAL REQUREMENTS AND INSTALL ACCORDINGLY. POWER POLES ARE ACCEPTABLE FOR'
TEMPORARY INSTALLATIONS," This note does not address lighting, only power for the security/screening
equipment We will forward a drawing indicating specific electrical items required based on the faxed Electrical
Placement guidelines. Lighting will be designed to matgh surrounding areas. (Matt, this sketch has not been
received as of today),
IR 96- (Mr. Patrich had requested additional information. but has given this answer as of 1/3/05 which may
have preceded and may have subsequently answered during his site visit.)
I briefly discussed IR 96 with bob Anderson followwing the conference call at LPA last week. 'It was determined
that the electrical data being requested needed to come from the .bridge manufacuter, We requested the
information during design but it was not available. I have reviewed the information provided by Bob Anderson
addressing IR 96 and it is acceptable to Sims Group. The Contractor should verify the electrical requirements of
the bridges with the actual equipment being installed as noted on Sheet E7.1. This information also was not.
available tous duirngdesign so the burden of the verfication was placed on the Contractor- the electrical data
shown is based on the existing bridges. .
IR 98- The response issued by Bob Anderson is acceptable to Sims Group.
I R 104- We feel this should be addressed at a meeting of the design team. The conduit and cable tray routing
issues between Building E and Building A require input from many trades. We are planning on discussing this at
the job site meeting on January 3, 2006, (Was this discussed and resol~ed?)
Thanks, ALo
An g ie Logan
Project Coordinator
The LPA Group Incorporated
700 Huger Street
Columbia, SC 29250
803-254-2211
803-779-0482 FAX
Monday, January 09,2006 America Online: AGS.A.IRPORT
~/
William D. McKnight - President
Mason McKnight, III . Vice President
Huey E. Carter - Sec. . Treasurer
McKnight Construction Co., Inc. ( J rxJJtJ/ __
GENERAL CONTRACTORS ~-
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-]994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706]863-203]
March 28, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
Gentlemen:
RE: Augusta Regional Airport
Augusta, GA
PR 37- Weathervane
The following is a cost proposal to furnish the weathervane as selected by LP A and described in the
schedule of allowances.
Construction Services, Inc.
7% Tax
Subtotal
McKnight 7% O/P
Subtotal
Allowance
Total
$5,833.00
408.31
$6,241.31
436.89
$6,678.00
(1,500.00)
$5,J 78.20
A.,f.-'O
\ D::\ \1>-- 00
NfGJ cPo
~~~
of( J. .
t()'J -<. 0~6
~G...<; 0)0
~S~ ,/
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
Pai PCdJu-tL /s~ .
Pat Patrick
Project Manager
@ ~cg~ltW~1ffi
illl MAR 2 9 2006 Jill
PP:sdr
BY: ____________________
cc: Jobsite
pat032806B. wpd
PROJECT NUMBER: AR209024
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELD
COST PROPOSAL No. CP -b -,
DATE:
'3/ Zgl ()~
NOTICE OR REQUEST: IN or IR No.
SUBJECT:
u )~"0A.t
DESCRIPTION OF PROPOSED MODIFICATIONS:
REFERENCE:
list any attached documents
AL~l:e
\'2\0 - '3. ~. E
Within 10 days of recelvmg a related Information Notice or Response to Information Request,
submit an itemized proposal for changes in the Contract Sum and/or the Contract Time for the proposed
modifications, or notify the Architect in writing of the date on which you anticipate submitting aproposaI.
THIS IS NOT A CONSTRUCTION CHANGE DIRECTIVE. THIS IS NOT A CHANGE ORDER.
DO NOT CONSIDER THIS AS INSTRUCTION OR DIRECTION TO EITIIER STOP WORK IN
PROGRESS OR TO EXECUTE THE PROPOSED MODIFICATIONS.
NO PAYMENT WILL BE MADE FOR WORK WHICH IS NOT PRIOR APPROVED IN WRITING.
Adjust Contract Sum for this change ( Increase / ~) . , . . , . . . . .. ..$
6'\7S
~
.'Zc
Adjust Contract Time for this change ( TuLr~ail~ -.,....DeQ'ea~e ,,~l"Il!lftr days )
Print Name
and Title
Date:
3/2€1t)~
Signed by:
(CONTRACTOR)
cc: CONSTRUCTION MANAGER
ARCHITECT
CONTRACTOR
OWNER'S REPRESENTATIVE
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT, AUGUSTA, GEORGIA
CONTRACT MODIFICATION FORMS
01250-5
r:.J:J/LlO/",tJOO
J. I : .1 r
- - - Q"" """
":::>l:).,j::lL::!L'I:>
............11.:::.10..01 Ulr........,Lurl l.,.,u.
L::::>1
IUO- r le-oeo..::l
p.e
t""Al;:zl:. t:Jl
March 6, 2006
CONSTRUCTION SERVICES, INC.
0,.__,# ~~'~~tC;<Z'<<~./ftJ,-tf~i::r.r~;r-
" , 1 CEDAR LAKE ROAD, S.E. . DECATUR, ALABAMA 35603
PHONE (256) 355-7081 · FAX (256) 351-9145 . www.csialabamacom
Mike
McKnight Construction
RE; Augusta International Airport
Augusta, GA.
Dear Mike:
We propose to furnish materials for the above referenced
project in accordance with faxed elevation and no
specifications, consisting of the f.ollowing item ONLY:
1. One-weathervane unit, approximately 4'-6 wide x 5'-0 tall.
We include the support brace, threaded rod, head block,
collar, directional indicator, neoprene washer, copper
weathervane and globe. The entire unit is to haVe a natural
finish.
ALL OF THE ABovE, FOR THE SUM OF. . . . . .:'; . . . $ 5 , 833. 00 ,
J' . O. B. OlUGDf r FREZGBT PRKPA:m. EXCLODIlfG DIS:rA.I.LAnOlf AlQ) SALEs '17.X.
See enclosure for terms and conditions. CSI form #007 dated January
11, 2005.
OUALIFlCAT:rONS:
1. We do not include structural calculations or testing.
2. We do not include fasteners other than those required for OUr
wo r k .
3 - we do not include wood blocking.
4. We do not include field dimensions, or verification of field
condit:ions.
5. we do not include embeds Or, light gage framing.
6. We Exclude demolition, removal and/or disposal of existing
materials, including temporary railing systems and the
removal/replacement of fireprOofing.
7. We ~xO~ude any cut-outs and/or penetrations.
8. We do not include any caulks and/or sealants.
9. Items not specifically mentioned above as being included are
considered to be expressly excluded.
10. Shipment Schedules are estimates only, and are contingent Upon
timely receipt of approved shop drawings, all necessary field
dimensions, workloads and written release for fabrication.
~.
- - .-1
..-......1.1.611"'" .....url~......ruc~lon L.o. IUb- 11~-t:Jc:.tl..::J
p.;:!
MarCh 6, 2006
Page 2
11. We do not include any bonds, permits and/or fees.
12.. The final retainage shall become due upon final completion of
CSI's work and payable within 60 days. At no time shall the
percentage retained by the contractor from CSI exceed the
percentage retained by the owner from the contractor.
13. Many Architectural metal items must be measured after another
trade has completed their work. A reasonable amount of time must
be allowed for completion of CSI'swork. Should contractor
guarantee dimensions it is understood that he shall bear 'the
cost of all re-rabrication and additional erection time to
rework the item(s) when his failure to hold these dimensions
necessitates re-fabrication.
14. Shop drawings will be provided for approval. Without express
written. au.thorization, wor.k will not proceed until return of
shop drawings. This includes orderi~g material for this project.
In all instances CSI assumes no design responsibility which
shall remain with the design professional as per AISC CODE OF
STANDARD PRACTICE section 1.5 and 4.2.1.
15. We do not inclUde final cleaning of CS!'s products after they
have left CSI's care, custody and control.
16. CSI has reasonably relied on the accuracy of the bid documents,
and our proposal is strictly based on this premise.
17. The painting of this material is based on using the manufactures
standard colors. This proposal does not include the cost of
custom colors, exotics, metallic or clear coat-top coats.
18. This proposal is based upon the assumption that the building
structure will adequately support the loads, forces and moments
imposed by this work. csr specifically excludes any
responsibility for engineering design and furnishing of any
additional bUilding framing which miqht be r~quired.
19, This proposal is contingent upon all parties mutually agreeing
upon terms, conditions and scope of work included in our
Purchase Order/sub-Contract. Quotati.on is good for 30 days.
THANK YOU for the opportunity of quoting. Should you have any
questions, please feel free to call.
Yours very truly,
~~;;:INC.
Sales Manager
-.1 VVt ..:..vvv
..I.r';..I. (
~ -
L...JV...J--'J......&.~;.j
(VU (( C- UC-U.....
1"""
r HOC. U.J
'-"'>J.
CONDmONS OF SALE. (CSI #=0(7)
FOR: FURNlSBED MA1:EIUALS
DATED .January 11,.2005
1. ~ are due to !ldJet' within 30 days from the dat:: af1hc invoi~ No rminage.
2. Exccptioas :mdqrmiiii~ per Cnostmc:ticG Services, Inc.. lcUer of qu.ctation. . .'
3. Fn:ight is allowed. 1:0 jobsitr:: by cnnnnmt.c:arricr"wittlDO.specia.l aIr.ll'H=II.~"r ibrtune of delivery
(AM or PM)", ~ ofloadiug or special ~ or aari:og. uni.e;ss specifically a.ddrc:lsed
prior tQ quote in Bid Doc:um:ms.
4. Ma2criallDllSt be im~ opon arrival.:md.my damages or shorcagcs or any otbcr f1ctor
3ifecting acceptana: be tepuItal to Coustmaian ~ Inc. widzin 24 bows at delivery.
Immediate w:riaeI:t notice must be- give:a. in carricrn' agc:Dt' at de$rift:ltjon prior to ~g.
:5. The Seller 'Will accept:NO iu.r$~ cm: my mareri31s fabric:m:d inc:orn::crly unless the Buyer .
~ the Seik:r'-wizhin 72 hoor.3,aftht::enom. The SelJcr~ 1be right to advise the. Buyer
on hew any can:c::ct:i1Iewort: is tD. be l=xiIed.in: an C3.SeS.
~. Seller- sha.Il nix be liable fur any dam:age!, wiu:du:r din::ct and. imrnM!,.-t~ or indirect and
, I __--lby ~_.. ~:.._
~". ~ . -:1 m.....-...........1. ,
7. AJJymaIerial. whiclt.tbe ~is requi1c;d:(bythc Buyer) to S1X;Jr'c aft.e:r1he Seller has,compldz:d
fil.bric:tticm. orlbrwhich. the Buyer steps fubrication iOr' any rcascm. or if the job is sropped by the
Buyr:r- aib:r any mm:rial. is rCcci.ved by the Sdk:r; the Buye:r:-will be n:qnired 10 pay a...sttJppagI: .
clwgeata.r.uc-ofS3.00 / sqasm fuoc:of~ftl storld:pe:rIIlDlIlh (mininnnn space is 3'60 sq. ft.).
. 8. Manlriai! sha.U. 'be.subjecrto ~wt~ ~ toJet3IlCC andclassificatiCIIS.
9. Should the Bu.y.e:r&iI 10' ful6lI. the-1cm:Is or paymaD:.au any order betwec:n the, Bu.yerand.the '
Sella:; the Selle:rmaydc6::r-fiirthcr~~ umiI such paymc:ISS ate amdc or.may ca:ace.I my Or
an orders umbipped.. Buyers shalI. became liable fur (and. pay) SeDas =nt"plht;nn charges in the
CVCl1t of~ c:a~0I1 of" cmicrn <:JIrteleasc.fu.J: any- reason.
10. The SeDer 'will accept adds far 3d.ditionaJ. ~~ whiJe wDdc: is- in: pI"CX=:>, but only iflbc Buyer
acc:cp!$ quou:d.c:ost:fur add aqi.c..u:rlUDIS" that add ia'wriring witbin. five working days.
ll. Samples ahaIl be ~l:mdapproved. by all patties that have an autbolity in the 5Da.l
. ~~af'tbis~1
12. FIJ1'Disb.lic1 assura= irdimnatica,~~ af:.
COmplete job. name:
Addn=m: .
CitylSt:m:lZip:
~of-e.,ilm~
Address:
CitylStatelZip:
PROJECT NUMBER: AR209024
3.3 SCHEDVLE OF ALLOWANCES
,., d'A," "'Allowance No, 1: Include a lump sum allowance of $375,00 per thousand for face brick as
specified in Division 4 Section "Unit Masonry". Include a lump sum of $400.00 per thousand
for solid brick and solid brick shapes as specified in Division 4 Section "Unit Masonry" and in
Division 2 Section "Unit Pavers".
B. Allowance No.2: Include a lump sum allowance of $5000.00 for finishes of and railings on the
side and rear walls of elevator B.
C. Allowance No.3: Include an allowance of $2,500.00 for cast metal building dedication plaque.
Text, layout, and artwork (ifrequired) to be provided by Owner.
D, Allowance No.4: Include a lump sum allowance of $7,500.00 for purchase and installation of
audio-visual equipment (beyond the requirements indicated in the documents) to be installed in
Room E224.
E. Allowance No.5: Include a lump sum allowance of $1,500,00 for the fabrication and delivery
of a custom weathervane on the cupola above Connector, Room B 1 02 (see also sheet A3.5 for
elevations). Installation of the weathervane should be included in the cost of the metal roofing.
F. Allowance No, 6: Include a lump sum allowance of $22,000.00 for furnishing and installation
of the landscaping and irrigation of the long term parking lot expansion as shown in sheets Ll.l
and L2.l of the drawings.
END OF SECTION 01210
. ,
;"'"
~l210-3
Allowances, Revise paragraph 3.3.A to read as follows:
"Allowance No. 1~: Include a lump sum allowance of$375.00 per thousand for face brick as
specified in Division 4 Section "Unit Masonry". Include a lump sum of$2.75 per unit for
each solid brick and solid brick shape as specified in Division 4 Section '"Unit Masonry".
Include a lump sum of$7.50 per unit for each solid brick internal and external comer or cap
as specified in Division 4 Section "Unit Masonry". Pavers are excluded from the allowance
but shall be as specified in Section 02780."
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT, AUGUSTA, GEORGIA
ALLOWANCES
01210 - 3
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
Gf4fjGb
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. 0, Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
May 31,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport
Augusta, GA
PR26 REVISED
Gentlemen:
Per your request, the following is a revised cost proposal with the requested breakdowns, to install
the temporary acoustical ceiling in the connector hallway. .
CI Electric
Bonitz
Augusta Fire Protection
Subtotal
7% McKnight.
Total
$5243.05
4580.00
1063.00
$10,886.05
762.02
$11,648.07
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INe.
PoI P aJ:7tLciL)~
Pat Patrick
Project Manager
lID U; @U;TI"WU;l
I jUi~ 05 lOOn
MlJ~ ______---
BY' -------
. .---
PP:sdr
cc: Jobsite
pat053106.wpd
CI Electric, Inc.
4191-AugustaRegionaIAirport-COs.xis
CO#14-Rev.1
Cost Breakdown for
temporary Iiqhtinq at hallwav entrance to Buildinq A
Quantitv Unit Cost Extended
1/2" emt 50 0.42 21,00
1/2" emt conn/coupl 10 0,65 6,50
4x4 jb w/ cover 20 2.65 53,00
allthread - 3/8" 50 0.40 20,00
12-2 mc cable 500 0,75 375,00
12-2 mc cable connector 50 0,92 46,00
2x4 grid troffer fixture w/lamps 6 85,00 510.00
1 x4 wrap fixture 4 50.00 200,00
scissor lift rental 1 293.61 293,61
Miscellaneous 1525 0,10 152.51
Subtotal Material 1,677.62
7% Sales Tax 117.43
Labor - workhours (overtime) 65 31.50 2,047,50
Labor Burden @ 35% 2048 0.35 . 716,63
-' Subtotal Labor 2,76~,13
Labor & Material 4,559,18
15% Overhead & Profit 683.88
Labor, Material, Overhead & Profit 5,243,05
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc.
Schedule Implications
All material prices good for 10 days.
Schedule impact will be determined upon approval.
Immediate approval is needed to include this CO in Phase I (Bldg A) turnover.
Exclusions:
Repairs to ceiling grid and ceiling tile.
File: C:\41 91-AugustaRegionaIAirport-COs,xls
CO#14-Rev.1
5/25/2006 2:12 PM
a~ 08 06 05:34p
MoKni~ht Construotion
7067728283
p.7
~nitz na
~contracting Company, Jne,
645Ro$e\lloodD~29201 . P_Q, Box82- Columbia, SC29202-OO82
Phono800.?'9~le1
Fax tar AoorCovsrinq 803.799-0~93
Fax for Productlon, Human Re.'lources 803-743.0223
Fax 'orCclpcmtC' 003-756-4327
Faxfor~ling& Crywilll3ale6 603-7564288
WWW.bonltz.com
May 9. 2006
McKnIght Construction Co.
P.O. Bo-x.2(U718
Augusta,. Ga. 3Q917
ph: (106) 863-7784
fw:; (706) 863- 2031
Arm: Ue Moonl1Y
Re: A UGUST.A. REGIONAL AJRPORT
AUGUSTA. GA.
We have prepared the j(>J1owtltg b,.eaJ::down of pricing for the Te.mporary Celhng in Conrwi;tOT rOOm
# A J 49 per Revised Fcbntary 16. 2006 Proposal and your nque3t.
2 ' x -I. Aevustica/ tile and grid ee( ltng syStem:
mat~rlal.$ 616,20
labor .r 63-1.07
2' x ~' Acqustical flIe and grid vertiC4l break:
materia! S J 39.41
labor S )86,68
De11Wlltic", of:Z' ~ 4' Acoustical tilt: and grid.
ceiling systum and w:rlicallermtnatiOI1:
L:zbol' $ 4 J 5.66
Addiritmai labo,. to Install Lmear Wood Ceiling
System in ocC1lpfed environment:
labor $ 1,780..59
MLukup;
$ 597.39
Totlll:
$ 4,5&o.(}()
CTING CO..,lNC.
Cc: JIl17y Davis
Al1.ANTA . Al)GUSTA . CHARLESTON. CHARLOTTE . COUlWJlA . FAYE:TTI:VIl.l..! . GREENVILLE . RALEIGH . TIllAD
AUGUSTA FIRE PROTECTION
CHANGE PROPOSAL COST SUMMARY
PCR#
869-04
Revision No,
Imcumbrace Record
McKnight Project #
PM
Contract: McKniqht Construction CO.,lnc
P.O. 204718
Augusta GA 30917
'oject Auqusta Reqional Airport
in: Pat Patrick
escription of Change: Reworkinq of pipe to facilliate temporary ceilinq
in the connector corridor
Date Submitted:
7%
$267.13
MATERIAL
$249,65
DESCRIPTION OF COSTS
1 Material from Pa e 2
2 Consumables and Scra
3 Subtotsl: Item 1 + 2
4 Sales tax
5 Local Deliveries & Frei ht.
6 Material Return and Cancellation Costs
7 Subtotal Material Cost: Item 3 thrciu h 6
8 Desi n & Coordination Costs from a e 3
9 E ui ment Rental & Small Tools from Pa e 3
10 Sales tax on Line 9
11 Labor Cost from a e 3 item 27-A
12 Payroll Tax & Insurance (from page 3 item 27-B)
13 Subtotal of Labor, Equipment and Material
14 TOTAL COSTS BEFORE SUBCONTRACTS
15 Overhead/Profit of line 14 Above
16 Subtotal of Direct Costs
17 Net Subcontractor Costs (from page 3)
18 Subtotal of Direct and Subcontractor's Costs
19 Overhead on Subcontractors of line 17 Above
20 Home Office Overhead on line 16 above
21 Profit on line 18 above
22 TOTAL COSTS AND PROFITS BEFORE BONDS & OTHER COSTS
23 Bonds, Performance and Pa ment
24 S eciallnsurance or Other Char es
25 Extended Overhead (From Page 4,if provided)
26 TOTAL PRICE OF CHANGE PROPOSAL
27 Extension of Time for this change order in Workdays 1
to be a lied' in ro er Schedule Se uence to each Cate 0 of work,
28 This Pro osal is based on X Strai ht Time Overtime Shift Work
29 This Proposal is void unless a written Change Order or written Notification to Proceed is
received b 45 calendar da s if no date shown
30 Extended Overhead Cost: Included X Deferred" Not A licable
$249.65
$17.48
.'
7%
$523.80
$87.65
$611.45 I
$267.13
10%
10%
Field Crew Size 2
SDPCrew Size 1
Submitted By:
Approved By:
Signature
.. If deferred, cover letter should describe
22-Feb-06
-0-
J-430
GK
Date:
Date:
$878.58
$87,86
$966.44
$966,44
$96,64
$1,063.08
$1,063.00
22-Feb-06
AU9l1sta Fire Protection, Inc.
COST BREAKDOWN
PROJECT: McKniqht Construction Co.lnc
Description: Reworkinq of pipe to facilliate temporarY ceilinq
in the connector corridor
QUANTITY
DESCRIPTION
MATERIAL
UNIT TOTAL
4 ea 60" flex drops for temp. ceiling
$62.4 1
".
Labor to install flex drops
labor to unstall
Totals - This Page
AFPCR #
Imcumbrace Record
McKnight Project #
$249.65
$24965
769-01
J...BO
LABOR HOURS
UNIT TOTAL
20.00
20.00
-I
o
;;;
en
c
C"
n
o
a
0;
n
~
n
o
~
....
<:>
o
<:>
'"
...
g' g'~
'" II> Il1
Cll Cll-
"T1 e-G)
o 0 CT
-1::r:@-t:r:~Q
~g3~g~g-
po~~~~3~
:5":;oI3";CDJtD
!PD>g!AQ)::3
::cm"':C<D:C
o_l:no_O
ca ca~
"'"3 ~ 3 II>
~~ ~~
Cll)> Cll ')>
-na "c-
02 a ~
3 Cll 3 Cll
N
....
."
;;;
c:
r
Il1
c-
o
~
~ ~
'" '"
w :>
)> )>
CT CT
o 0
< <
Cll '" Cll
o
'ift.
g,
r-
5'
II>
'"
o
)>
C"
o
tft~~
!Jl!':l
~ w
OlO
""
"" '"
wo
0,0
<0 Ol
n
o
~
~
o
6
o
o
0>
;;
'U
::l,
::l
;;
'"
~
'"
'"
N
o
o
Ol
....
Ut
N
to>
Co
<:>
'"
w
'"
~
o
o
'"
'"
o
o
ex,
o
...
Q)
~
'"
<.n
'"
'"
~
'" '"
~p
............ ......~.....
~:--J!>>~~
()CIlZC/lC/l
(j)mo"'C"'C
~~~~.~
c::oo!!.m
"'0 (tl a. ~ '""'l
"!' n. 2!. ~
Qo<=-~.~
C/lCll!!!.::c
;.~~g
-<gaij;
""0..,-_
S ~'3
~ 3
3 ~
3" cg
""Q. '"
m' -
3
II>
::J
2t
0'
::J
o
o
o
'$.
~'" '"
oop90!=,~O
00000000
00000000
::c
o
C
;:0
C/l
::c
;:00
)>c
-i;:o
mr
-<
"
-i::c
~o
""c
_;:0
zr-
~-<
o
Cll
II>
Q
"9:
0'
::J
o
C
Il1
::J
.z
C
~
n
o
~
-I
o
![
r-
>
tll
o
::u
en
c:
5:
5:
>
::u
-<
en
c:
tll
n
o
z
-I
::u
>
n
-I
n
o
en
-I
en
"'en
0-0
CD ::1.
3 ~
~ ~
...
'"
w
CD
o
...
-I
<..'
o
'"
o
CJ
""
'"
'"
c..,
o
~
a,
'"
""
w
c..,
0>
""
o
6
o
...
'"
~
-I
o
~
o
..
co
cC
::I
n
o
~
...
<:>
o
<:>
C/l
.,,-0
OJ = S'
Cll 7'"
-. ~
o
II>
II>
" c....
)>~g.
0'
::J
'"
01
<.n
CJ
C-'l '
'"
'-"
Ol
'"
o
o
""
'"
D
o
CD
....
0,
~~
'"
m
....
m
'"
'ift.
...,
it>
~
Po",
0>",
t..Jw
~w
...,
~"T1C1l
~c=i ~
cn-t:> -
,,)>
~ Qa
D
'$.6't
o
o
o
~cm
o C Q) >< ......
'eft. ~ ~ ~ ~
n.:cco
Cll
'"
'"
0.
m
z
n
m
-i
r
m
<
m
or
~<
;:0
m
<
in
:E
m
z
G'l
Z
m
m
;:u
Z
G'l
o -i
m
." 0
jjj' ::c
a: z
~ 0
-;;' >
CD Z
@:iJ
)>
<
m
r
m
x
"tl
m
Z
en
m
en
o
::c
o
c
en
@
v,
o
o
o
'"
o
o
D
:OW
Il1 Il1
-0>
Cll CD
~
~.
11>
II>
-i
"Uo;
~ ~
;:o::C-i
~g5tco
CD =.. tLl
'<
-n
(')
)>
S'
~ ~ d......
@x-w
~ QQ!!.
Cll
(I)
w
o
o
o
'"
o
6
_0
'"
0>
...,
'"
~
D
::C-l
en 0 0
g.~~
-i:o~
9. m c
!!. m @
'"
"" "-'
Ot.ncaoo
0--0000
0-0000
::c
o
c:
::u
r
-<
~
-I
m
en
(0)>0
5"l!'Qo
-o~s:
0=
m in ~
;ii, ~
,g ~
"U II>
iil
-0
'"
~
0'
::J
o
3
w
(j;
II>
"
C.
o
:;
::J
-I
S?
!!!..
m
.c
c
ii'
3
11>
a
go
-I
o
S?
n
o
~
... ...
<:> 0
o (:)
<:> D
(j)
~b>g>~s;'s;'s;'s;';r~6
""'ocra.tDCJDJQ)-o"'O
g.a.3Qj2:~:::.a.c:_
~ 5':i~.g c5<E c5 g> ~ 0
S'~~ol I<::JO
~ g'''''fi:!1:!12:'::!1~;;:::;
;:]o~nibmg.2.m~:O
~ ~~ ~ ~ ~ ~ ~ ~. (D' f;
__<0 :=,0 0 n 0> :=':;-i
~.~01 g CDmC':JrE Qoc
E :OUlgg~ o~~
~ :J::J~ gQ~
i:f ng,>n 9,-gz
g g~6 5'o;G'l
en aIDa ~::-.iJ
U)~5 g~
Qo g. "'0
:0 >
~' ~
~ =!
o
z
00
OOO:JO
o::>::>c-
~ 0
00
00
00
---OOaJO:OO'::'.:J--C
OOOOO;:'O::lOOZ
ggggg5gggg~
000000000
000000000
000000000
en
3
~
-i
o
o
..
"'cnOCl> "'Il
ogo;~r-::c""":oo
-n",,=> n "'~:::._,::
gQ.CD;-~~Q.~~
-9:::01;:;:..... m ~ 0:""""
~Egr-c~~~wg
~ ~CD~~~giii"
-, 03 c:."U 0
= i: II> ~. ~ ~ ~
OJ 0' Sfi ~ ~.
~ ~ens: "-
~ rot ~ ~ g
c ~=2:
::J 1H:~
o 0
Il1 0
C. <
g ~
0000
0000
cooa
0000
0000
0000
Q,
c: c: c: c::
2.2.2.2...
ururU;-U)
c c: c c
2. 2. 2. 2.
U)U)ii1iP
'"
'"
'"
'"
a,
D
tA t.'t ~ ~
CD-U'ICO,
f'VU\"""N
o,oCnw
<<>OtO--
'" ""'"
"''''....
...."'0
moo
<000
<1> i,l rg Cll
~~~~
!;! ~ g: ~
"
NffNl
':; :; :; :;
m ~ m m
ro ~ CD ll)
^,"'7'\ ^A
CD
'"
'"
11>
r-
Dl
CT
Q
n
o
~
Ett tJ't ttt-&'lt
0000
0606
0000
tit b't tilt f7't
0000
0000
0000
C
Z
::j
en
::c
o
C
;:0
en
-i
o
-i
)>
r
::c
o
DC
, ;:0
gen
C
:e,
ii>
n
o
~
"U
~
0'
c.
--l
o
![
Cl
m
Vl
C5
z
O'U
~ ;:0
g,e
'E.m
0' 0
~ :-:i
5' :0 s:
g~~
m 0 ::I
8 ~ e:
55;::>;
mon
n - 0
Q ~' iil
n ro ~
~ 0" ~
g:m-g:
...., Q. ~
=n
!!<o
11>'
ro~
~
o
~
n
~
~'
o
m
en
C5
z
Cl
m
<
m
r
o
"'C
m
5:
m
z
-I
n
o
en
-i
-
~
5
"'C
:i:
m
z
-I
po
-I
o
o
r-
en
;::3
~g
::l 3
cO.g-
::l' '"
- n
'UCll)>
]. ~ ~
II> n 0
!lo;;o
=tt:a~
'- ;;
.1.otO
~ 6
()
o
(J)
-j
OJ
?J
m
)>
^
o
o
:?:
z
:t>
C
G>
C
en
~
:t>
"T1
-
;U
m
"tJ
;U
o
~
m
()
~
o
z
"'~'-'. '-~'-',- . ,~.'
,.......... ,-.....-, .~.~'" ,-'p,--.,
-.....".....'....-.......".."."."
Parsons
Srinckemoff
Construction
Services, inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
706-771-5172
Fax: 706-771-5176
June 5, 2006
McKnight Construction Co.
635 North West Frontage Road
Augusta, GA 30907
Attention: Mr. Pat Patrick
Re: Augusta Regional Airport - Terminal Area Improvements
PR 26 Revised
Dear Pat:
PB received your PR 26 Revised correspondence dated June 1,2006. The revision
appears to be the addition of costs associated with McKnight's supervision. These costs
are not permissible under the contract, Specification Section 00800, para. 7.3.6.2 (copy
attached). Please advise if PB should proceed with the previously submitted cost of
$11,648.07 for this work.
.-
If you have any questions concerning this matter, please feel free to contact me at (706)
771-5172.
Sincerely,
Parsons Brinckerhoff Construction Services, Inc.
7!~9 ~~/
. Matthew J. MCCoy
Construction Manager
Cc: W. Boshears, T. Wee gar, T. Story; ARA
L. Mooney; McK
M. Leath, B. Anderson; LP A
R. Roberson, D. Blessing; PB/INT
File
l~cG: \ O~~
7,3,6:
"7,3,6
7,3,6,1
Delete Sub-paragraph 7.3.6 in its entirety and substitute as follows:
Where an adjustment to the contract sum is required for which no basis of payment has been
provided in the contract documents, previously issued change orders or supplemental
agreements, and a change to the contract sum is required, the Contractor sh<11l include an
allowance for overhead and profit with an itemized accounting together with appropriate
supporting data, Costs for the purpose of this Sub-paragraph 7,3,6 shall be limited to the
following actual costs and allowances,"
Labor: For all labor (skilled and unskilled) and foremen in direct charge of a specific force
account item, the contractor shall receive the rate of wage (or scale) for every hour that such
labor or foreman is actually engaged in the specified change order work. Such wage (or scale)
shall be agreed upon in writing before begimling of the work.
7.3.6.3
7,3,6.4
No payment will be made for additional work unt! ontractor has fumished the Architect
or Construction Manager with duplicate itemized statements of the cost of such additional
work, detailed as follows:
Name, classification, date, daily hours, total hours, rate and extension for each
laborer and foreman.
Designation, dates, daily hours, total hours, rental rate, and extension for each unit of
machinery and equipment. .
Transportation of materials.
Cost of property damage, liability and workmen's compensation insurance premiums,
unemployment insurance contributions, and social security tax.
Statements shall be accompanied and supported by receipted invoice for all materials used
and transportation charges, However, if materials used for additional work are not
specifically purchased for such work but are taken from the Contractor stock, then, in lieu of
the invoices, the Contractor shall fumish an affidavit certifYing that such materials were taken
from his stock, that the quantity claimed was actually used, and that the price and
transportation claimed represent the actual cost to the contractor."
TERMINA.L AREA UviPROVEMENTS
AUGUSTA REGIONAL AIPJ)ORT, AUGUSTA, GEORGIA
SUPPLEMENTARY CONDITIOl'-.JS
00800 - 3
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
6~
William D, McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
March 31, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
Gentlemen:
RE: Augusta Regional Airport
Augusta, GA
PR38
The following is a cost from Augusta Fire Protection for the additional trips required by the fire
pump start up company. Because of the compressed schedule to receive, install, connect and start
up the generator, there was no way to have correctly scheduled the fire pump start up. Instead of
being able to perform this work in one trip, additional trips were required. This extra cost could
actually be an added cost to PR No.7.
Augusta Fire Protection
McKnight 7% O/P
Total
$1,227.00
85.89
$1312.89
Please issue a change order for this item.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
PO:t~/~
Pat Patrick
Project Manager
\U)!%@!%!tW!%l
I APR 0 3 2006 )ID
BY' ----------------
..---
PP:sdr
cc: Jobsite
pat033106.wpd
10213
( f.)IJf.)--I...JJ.OI.ot.:J
AI.J'.:lI.J:::i I A r J.T":t:. rT":l-! I t:.'.~
rH\.:J~ r.J.I.
!AUGUSTA ~~~i~~~1:~T10N, INC.
109 Commercial Blvd.
Martinez. Georgia 30907
(706) 863.93741 Fax 855-1 &49
~ff(R No. - ~~t~~.:-_9:?:
McKNIGHT CONSTRUCTION Co
P.O. Box 204718
Augusta, GA 3091 7
March 28, 2006
Attn.: Pat Patrick
Project Manager
Gentlemen:
Because of additions and/or changes in the work covered by the above referenced
contract, it is hereby agreed that the sum of One Thousand Two Hundred and Twenty Seven
Dollars ($1,227.00) to be added to the total amount of the contract according to the terms
and conditions of the contract.
Re: A.ugusta Regional Airport
Augusta GA
ADDITIONAL TRIP TO TEST THE FIRE PUMP
WITH THE EMERGENCY GENERATOR
This work is not provided for by the base or previously revised contract documents and,
therefor I is additional work that would not have been part of the original or prevlou sly
modified scope of work. This change order is for Augusta Fire Protection's subcontractor,
Applied Industrial Controls, to make a second trip to the jobsite to test the fire pump
controller on emergency generator. This second trip was necessary due to the fact that the
generator was not ready when the Fire Pump was certified. See the attached Breakdown for
additional information.
CGK/wfw
cc: file
""\
u~ LUi~U~O ~O.~O
{tJl:ltJ:l:llb'l';j
AUGUSTA FIRE PROTEC
PAC3E FJ2
AUGUSTA FIRE PROTECTION
-
CHANGE PROPOSAL COST SUMMARY
AFPCR # 869-05
Revision No, -0-
Imcumbrace Record
Contract: McKniqht Construction CO"lnc McKnight Project # J-430
P.O, 204718 PM GK
Augusta GA 30917
Project AUQusta ReQional Airport Date Submitted: 28.Mar-06
Attn: P~lPatrick
Description of Change: Additional trip for Fire pump
Eac;tory Rep to test the Emeroencv Generator
DESCRIPTION OF COSTS LABOR MATERIAL TOTALS
1 Material (from Paoe 2) .:~;*?f1t;:~~~l~~~}~:~~ili~i~~~iN~!fu~~i;~ :!~~::!i~~~!rl~~f~ili~~~g~::!~;~fm~!f:~;:::~m~u~~
2 Consumables and Scrao !~;i~i~lj~1~!~~~~;:~~;{~~~~~~~~;~~~;~~;~~r~;~~~;!~~~~~~~} ~":~;'~;!:;~;;i~i!~~1~~1!t~1~\I~i~
3 Subtotal: Item 1 +2 &iji~~;~~~~~~i~~~m~~~r}ji~~~j~j1~~i~iW~i;~[~j~!;~1~i~i~~
4 Sales tax 7% ~! ~~:~~tN~t?~~t~!~nH~~~~~~m~f~~~j~~g
5 Local Deliveries ~ Freioht .i~~~~:;~~~t~mn;~~~~!~~~;n;~~;1~~i@;~i~;{j~~i;
6 Material Return and Cancellation Costs :~~~~ii!i{~;~i~~~~~M!~~~@;~m~1i!t{;f.~~1~~i~tf
7 Subtotal Material Cost: Item 3 throuah 6 ~~74i~~~?~~AA~~:~)~i;!~j~!~j~i~~~~~!~tfJ~~~~t .;;:;::;:;:;::::,::~:~fil:\;'~ii~j!:~~~:~;~i;
8 Desion & Coordination Costs (from paoe 3)
9 Eauipment Rental & Small Tools (from Paoe 3) tt;t~~~;~~J~~;i~i~~~~!i};~i;;~~~~;~l~~~~t:~~~~!~~~~
10 Sales tax on Line 9 7% ft~~1~~P.i~~~~~~~i~!~~i~~i~if:~~*~~~*@1~
11 Labor Cost (from paQe 3 item 27-A) $129,20 :!ili!m~~~~~~~~~~~~~N;~~~~~~1~~~~~1~1N~~~tW~~~~~;
12 Payroll Tax & Insurance (from page 3 i1em 27-8) $20.71 :,;~~;~i~Jt~1~tM~~i~1f:;~t~ifit:~il@~j~{~~i~1
13 Subtotal of Labor, Equipment and Material ~149.91 ~~;~~~~i~l~~~fIT?f:~~t~~~~~S1.~l~~
14 TOTAL COSTS BEFORE SUBCONTRACTS $149.91
15 Overhead/Profit of line 14 Above 15% $22.49
16 Subtotal of Direct Costs $172.39
17 NetSubcontractnrCos~ (from page 3) . $986,00
18 Subtotal of Direct and Subcontractor's Costs $1,158,39
19 Overhead on Subcontractors of line 17 Above 7% $69.02
20 Home Offjce Overhead on line 16 above
21 Profit on line 18 above
22 TOTAL COSTS AND PROFITS BEFORE BONDS & OTHER COSTS $1,227.41
23 Bonds Performance and Payment
24 Special Insurance or Other CharQes
25 Extended Overhead (From Page 4,if provided)
26 TOTAL PRICE OF CHANGE PROPOSAL $1,227.00
27 ExtenSion of Time for this change order in Workdays Field Crew Size 1
to be applied in proper Schedule Seauence to each Cateqory of work. SDPCrew Size 1
28 This Proposal is based on X StraiQht Time Overtime Shift Work
29 This Proposal is void unless a written Change Order or written Notification to Proceed is
received bv (45 calendar days if no date shown)
30 Extended Overhead Cas;' Included X Deferred" Not Applicable
Submitted By: ~ rn7) Date: 2B-Mar-06
SignaturM f / 1/
Approved By: Date:
Signature
... If deferred. cover letter should describe
AFPCR869-0S - Summery
Page' of 3
Date Printed: 3/28/2006
B~!28/2BB6 16:16
7068551649
AUGUSTA FIRE PROTEC
Augusta Fire Protection, Inc.
PROJECT, McKniQht Constru!=.!lon CQ"lnc
Description: &lditioI1SI!l:ip for Fire Dumo
Factory Reo to test the Emeroencv Generator
COST BREAKDOWN
QUANTITY
MATERIAL
UNfT TOTAL
DESCRIPTION
Additionlll ma~J)()W9tto facilial8 Genorntorttlo61J51
,
Totals - This Page
AFPCR8e9.05 - MLF-4
Page 2 Or :I
AFPCR 'II
Imcumbrace Record
McKnight PrDjed 'I/.
PAGE 83
8S9-05
J..430
LABOR HOURS
UNIT TOTAL
4,00
Dall:! Primed; 312812008
l>
-"
-"
~
~
:;~:::~:'::;'.::;W~
I~'
If
'~:"':':';':"':';':':'
I
:~:~:.~:~:~:-~:~:~;:
:;:
~
...
...
""
...
b
o
":?
""
..
f..l
~
'.1
:...;:....:.... ;~. "
~~i1~~1~~m~i
Ir
.....
o
~
th
C
[T
..,
o
::J
:i
<>
[
n
~
'"
...
"'....
- 0
- - -
~~cn~A
(")(1) ZCIJ rn
[ j t ~. a.
~~~~r
~C:!!l.:!!
po ~ ~. g
ll)"S
~:;~t
"" [ it 01
". =:-.
.8 ii!
iil
:I ':t
3' ~
~ ..,
~. ~
co
;J
I!
g
)>
i.
~
S
Q.
c:
[
C')
"
=.
0 0
u;- OJ
..
3,
~
z::
:>
I
):f.I~11.1~11.
I
I
~
z m
0 z
tff !;)
.... 2:
.r- m
~ m
:II
or- Z
I:>~ (;l
1.€;l! 0 ;;l
S .., 0
.. :l:
~ cs: z
....2
~. ~
@~
~
r-
~
'U
,..
.:z:
'"
m
en
0
:l:
8
OJ
@
o
S
:::r
~
en
c::
tlI
n
~
~
~
.....
n
o
en
OJ
c::
:::r
~
-.
c
[
o
..
'"
~
::J
(')
o
-=-
~
C>
o
'"
Q
l!l..
."
."
...
0>
o
o
Qi
![
..
co
o
CI
en
'"
o
o
.., (Jl !p 0
~ltn~!>~.~
/!!- -tlj g
:.:I e .... 0
:::r
... U) ;'2' '"
,." -
fo' (II ii ~
CD '"
"" Q
:!1
~ ... ~. .'"
N
'" ~ ..
..
0
....
en ~ii1 ...
- '" ~ ~
I:> -
'" ~
~ '--'
~ ~ ... ::llJ:-i
llU 0 0 lD
.... 0;5.S'
(/I '" <:>
.... 0 '< -
c:: '" ...
3:
;c
~
;:a ... '" ..,
-< a. 0. ~ ;;
~ ~... '"
",. - If:
'" ""
'" Ol
.... ...
On ~..,cn
If:
." ~~ c::C =
..., ~....>
.... No (~ ",,)>0110
co ~ t..l ~
:;
0 o~~W_
~ ~Ut ;f( iil g~..,
0 ~.;fw
8 0
0
5"
.. -i-i
c: e~-
iil
E ... :::r lo'o l '"
'" "
'" '"
CD '"
~U~U~I~ r~~~ r~ul~~
C/)~o
lf~1/B
;~:1:
iil [
~. c:
lQ ..
." ..-
m
!
co
o
;J
~
07
~
>("
Q.
~
'"
'-'
'-'
'"
o
:I:-i
CJl g a
ij.~-
-i:ll~
~ Ol c:
_ lO 01
DI
lIn(Jl:l:t;JD!:j1oZ1~:r
i;gg.~ii!~ll>~~~!6
~ ~ i [~ ~. i ~. ~ ~ 0
ii, '" _n I I I I .. :;, 0
~ !'~~~~~~~;;~
&.-~g "O.""".,,~~,);
=-~a~a~"iil~~::
5,:x:-~g lf~g"'~ ~2
/5 ~'" fl'~!!!. l]=> >
11- ""00 :>.~:;:
ai ()~~ ~~;!
~ gvq~ go..!;)
.. [[g ~g;."
tI\o UJl::l ;;;J ~
~ ~ ~
~ .....
OJ _
~
00
00000 0000
r :0-
.. IP
.. -
j~i:i;m~[~:; ~ ~ f ~ ~ J !
)( c: ...c t:.$ 0
o.~~e-~~c:
5"::o:l:;;:II..iil
lb ~ 6- o;l ~ ~
,j;,;;;~i :r ;; ~ ::t: iD ;j:
g~ ~a~
~ ~3
:;0'" ::IllD
!to, !!!.:J,.
!:!!:lj!i!I!!i!I;;~f if
;;: j:
)>
8'
-<11
o
~
q,
r-
5'
..
,,.
'"
8
.,,~
OU'locoo
g:'ggg8
~ 0
o~
Q C
Q"
:t:
o
c:
::0
<n
....
OOOlocnooo....c
~oo8888ggg~
g88~o.=>".::>Co
....
~i.."...>~
-Ii
-I
o
~
~
ooooocooooC
ggggggggg~d~l
~rn~~ '!
"'i~~~~~~~
~"':::ll;:~JlI~~:""
E=~ ~ "=f li' ~ :t-:: 8
~ !!!. ~;~g.;r
~ 0 - c: . ""0 0
-.. 2 ~ ~ :!:
"- .~ co III g
~ ?~; rn;
s' ~:;o!: g'
C ~~~
:::r ~' CO) ;;
[ g
~. ~
ooco 0000
gggg g600
coo
:z: 2-
0 CCCc l:: ~ r:: e
c: .;a ~ .;:;;J :::l ;.. . =. :'..
-.- -:=I:
;0 aM;'", .. lA..
l"- II l3JfEllI61
-<
~
iif
'" .,.
- ...,."... ""~<tJl7.,.,
N "''''-'' ~ rJl CD
-f '" ...."'0 t'V0I-..r!'.J
0 ~ iggg OlOc.:.w
g ttlOlD_
\);l ~.~ i ~ ~~~~
m co
,Q :!:
c Q.Q.:f:~ :f: ~ ~ ~
i3" .- ~~~s;: g * .. %
..
i ~ ><' ;J#O;ar 'If'" >c-
:. ~
II"
-f
0
!?.
(")
c .,
~
~
b
c
...
<:>
8
~~~~
0000
00,00
~
~~C:!j
0000
C100C
c
:!;
-I
r.n
c::
~
..
('")
o
~
-;
i'l'
Q.
rHt.:Jc:.
~~
S.2
~ I'TI
8'C"J
" -i
~~~.
~r~
" :::r-
III -
~~()
0 6' g
m -~~
fA ~."
i5 :;. ~ ,
z ~~ ~
-
c I ~ ~
m
'"
!;) ~ ~
z
c G)
~ '"
a:
r iil
0 ~
'11
~
m
:z:
-t
0
0
en
-f
-
~
==
~
~
m
z
.....
JIB
.....
o
o
,;;
~g
-. Q'
~ii1
~Iil)oo
a :ll"
-. ~ ~
'" ()
!l ;0
..0....
(- g::
t\'o6
o .....
'-'''I
()
o
en
-i
CD
;::0
m
J>
/::.
o
o
~
z
>
C
G)
C
CJ)
-i
)>
"TI
-
;.0
m
"tJ
;.0
o
-4
m
(")
-I
-
o
z
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
{V\P - ( Ii -401 rip
if~~~
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - See, - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr, 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 15,2006
Parsons Brinckerho:tI Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport
Augusta, GA .
PR36
Gentlemen:
The followingis a credit cost proposal to provide the 3/8" Rain Tempered Glass as specified by LP A.
:~,
T & L Services Credit ($36,151.75)
Please issue a change order for this proposal.
[&1)1\ I\lEGollb-.,TE.P 1"0
( ~L\ct,:'l'-\."S'-t 0,-/
\ DC.!2.2!Oc. ""I PKI P"1l..\c..K.
'---\ - ,,~ J ~I\ ~/
--~
Sincerely,
MCKNIGHT CONSTRUCTION CO., INe.
Pa:kPc:dJiA-d0J~'
Pat Patrick
Project Manager
PP:sdr
cc: Jobsite
pat061506.wpd .
\~:~~~o~l
B Y: ---~Q~------:
T & L SERVICES, INC.
30 N. Industrial Rd.
Palmetto, GA 30268
770-463-1036
Fax 770-463-1037
Revised June 12,2006
April 3, 2006
Lee Mooney
McKnight Construction
Via Fax: 706~ 772-8283
RE: Augusta Regional Airport
Glass Type #10 Pricing
Dear J~ee;
Per your request, below is pricing alternates for Glass Type #1.0.
1.) Credit fur the specified Cesar product:
Ceasar
Tax
Total Credit
$47,922.00
3.354.54
$51,276,54
2.) Alternate #1: 3/8" Rain Tempered as manufactured by AFO, Inc.
AFG
15% OI-I&P
Tax
Total
$12,397.00
1,860.00
867.79
$15,124.79
As discussed, above pr9ducts arc not priced by square foot.age. However, there are roughly 37 lites, approximately
1,211 square foot. The above 3/8" rain product has a lead time of 8 to 10 weeks.
Sincerely,
~~
Lance Rill
,-'
5\, 1/v'"
,.,.?
--
\ ,-- '. ""'t..' ~'
-.. \ "
.,.~ '. t .
, -7q
--
Cc:
Pat Patrick
Tedra McFarlin
Barry Kirby
/'~
(/'/ i "2.,! l c::: \ 1 7S ~""'\ ,-,::' ""'fD t-~~
\ ' ""U1 ./1 )
'"", //
....~-~ ----"'..--~~
,',
CV-4:t r-
From: Anderson, Bob
Sent: Friday, April 21, 20068:17 AM
To: 'McCoy, Matt'; 'AGSAIRPORT@aol.com'
Cc: 'Willis Boshears'; 'Tim Weegar'; Leath, Mike; Logan, Angela R.
Subject: AGS Glass Type 10
This is to recap our discussion yesterday regarding the alternate supplier for Glass type 1 0 for the
interior butt glazed panels. The 3/8" "Rain Glass" from Architectural Glass Art should be
acceptable, and the sample has been approved by the Airport staff. The supplier needs to confirm
that the 3/8" glass (in lieu of Y:z" originally specified) is acceptable from a load standpoint for
interior use in the panel sizes shown on A6.3. Since it appears there will be a credit, there is no
need to use Y:z" clear tempered glass in locations other than those already scheduled for that type
in the documents. Let me know if you need any further assistance.
-
Pat Patrick
From:
To:
Cc:
Sent:
Attach:
Subject:
"Anderson, Bob" <BANDERSON@lpagroup.com>
<mccoym@pbworld.com>; <AGSAIRPORT@aol.com>
"Leath, Mike" <MLeath@lpagroup.com>; "Logan, Angela R." <ARLogan@lpagroup,com>;
<tweegar@augustaga,gov>
Monday, June 05, 2006 8:28 AM
AGS Glass Type 10 approval 0421 06.rtf
Type 10 Glass- Letter of 053006
I have reviewed the letter of 5/30/06 from McKnight / T L Services regarding the patterned glass, Unfortunately, it
raises more questions than it answers. As per the attached, we had an alternate product approved by the Owner
as manufactured by Architectural Glass Art. The data included from TL Services is for AFG Industries and
includes data for two different products ("Heavy Rain" and "Rain"), It also indicates that these products are.
annealed as opposed to tempered as specified. Please clarify what the intended product is. If it's different from
what was previously approved by the Owner, please submit a sample, I am not opposed to a similar product by a
different manufacturer, but the information submitted is not sufficient for approval.
<<AGS Glass Type 10 approval 042106.rtf>>
Confidentiality Notice
This message is intended exclusively for the individual or entity to which it is addressed, This
communication may csmtain information that is proprietary, privileged, confidential or otherwise legally
exempt from disclosure. If you are not the named addressee, you are not authorized to read, print, retain,
copy or disseminate this message or any part of it. If you have received this message in error, please
notify the sender immediately either by phone (800-572-1115) or reply to this e-mail and delete all
copies of this message,
...-: I::; .'''':,....:.'-;,<;
William D, McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
McKnight Construction Co., Inc. f!0)/Z5
GENERAL CONTRACTORS c2fC~)
\'
!
FOUNDERS:
Mason McKnight, Sr, 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 7,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport .
Augusta, GA
PR 42 (Revised)
Gentlemen:
The following is a revised amount to provide power tot eh hot water recirculation pumps WH-2,
WH-4and WH-5. -
CI Electric
McKnight 7% O/P
Total
$584.60
40.92
$625.52
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
foiP~~
Pat Patrick
Project Manager
lID ~(g~~W~1ID
ml JUN 0 9 2006 1W
PP:sdr
cc: Jobsite
pat060706g. wpd
BY: ____________________
CI Electric, Inc.
4191-AugustaRegionaIAirport-COs.xls
CO#18-Rev.1
Labor - workhOllr' .
Labor Burden @ 35%
Cost Breakdown for
power to hot water recirculation pumps - WH-2, WH-4, WH-5
per Field Report dated 15-Mar-06
Quantity Unit Cost Extended
60 0.42 25.20
12 0,65 7,80
4 2.65 10,60 \
180 0,15 27,00 d N4.,
71 0,10 7,06 Ij'ifivv.
Subtotal Material 77,66, ~o \_ Q...
7% Sales Tax 5.44.J S t.. rfJ.. "'\
~\\OO ~ }\5,ot> (' t, ·
0,35 165.38 \ \ 0, 1.) ~
Subtotal Labor ~ &\1..S'.1,..: ~ ,.s-
Labor & Material "f20,tJ'.... 50 ' _
15% Overhead & Profit J.flO. 1::; -, ~. "l-~
Labor, Material, Overhead & Profit ~9.~IL-
S'~ ~.loD
15
473
1/2" emt
1/2" emt conn/coupl .
4x4 jb w/ cover
#12 thhn
Miscellaneous
c. "GI..J S:-z e
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc,
Schedule Implications
All material prices good for 10 days.
Schedule impact will be determined upon approval.
Exclusions:
File:C:\4191-AugustaRegionaIAirport-COs.xls
CO#18-Rev.1
5/25/2006 3:16 PM
y...." .w,_...........,.
ilC01/0';'2
: 7:~:" 1"';,.-.
J ',.' ..." I.' 0:0.,
, I.J:C\:,,:,:',r'; .l:"." '
-
=- sims gro ufJ.
ENG'NEERS, INC.
744 SUI'l$ET BOUl.EVARC. surrE 20'3
WEST COl.UM!lIA, SOU1li CAROl.rNA29te~
PHON!: (803) 7i5-1Q07 FAA; f!iJ3) 78S....Q3G
TO:
FROM:
o URGENT
. ~ .
)
FIELD
REPORT
! . .
., "',
1".~ L.~:'" /," . I"
If'-fC,,=-;~'.r,;. ~... ,...J-.;'
CoLI'/ ::. \.',",;\ '::"~
, v \tiL.{.~. Qr..'.: .',_
I I It_I';:
','
',,\ rl'"
It)', ...: 4.~'"
...,
The LPA GrOL.lp, Inc.
Fax No. (803) 779-8749
r.:JATE 03/t6/2OQS , SIMS Jot! N'o. C.4C75
A'T'TiNnoN: Ang.ta L.ogan
R~: Augusta Terminal Site Visit
Chris Partrfch~ PE
r: L PAGES: 2 IN I..UDING COVER SHEET
o REPLYASAP
o F1.CASE COMMENT
~ FOR YOUR INF~IMTION
. . ~ ,; ,t._ .' . ., I.
.~~. I' I'}o', 1',' ;~,
A wal~-th"" of the si~ was pefformed by Cht\! Parmeh af Slfr$ Group on Febl\lary 20, 2C06. The follOWlhQ Item!'
were noted and/or drscu~:
-K 4.
--$
COFlY TO:
1,
Thejockey !:lump must be fad sspar.ately ftcm the fire pump a)rJtrollet. The 51~drlcal Contractor he$
agreecl to provide iil separate 2OA1 4ffQV CiI'tWit frClm nearby panel "EHA",
IR11S . Pan.ts "l<P1- & -EKP1. tlava not been Ih!talled. Th. Eladi1cal Corrtrac:tci- Shall refl1!in from
installing t'hese panels until 1tle twl18nt uptlt d Ih~ area t'IilS been 1IM'1Ized. ThIs work Is currently'
und@r d~lgn._
2.
3,
The oorM'll.lni~ns oonduits for !he. Jatw.ll)' BHdg'eS shan be addna18Dd by Ross &. Baruzzlnl.
IR126 . Slge attached SlCeItGhSK.Ef'7 far ccmmuntc:aUons c::ondu1w 10 replace cable tray In the
connector.
S.
7.
Water heaters WH-2, WH-4, &'WH-5~ fwmisihed wttn a 11S1Tp, 120V re-elrc. pump. Wn pump to
nearest 120Vret:ei'pt&cle arcuft. . "
Adjust Ioe:atlona of LCD monfttn' ~pt;c1es In HoldIng 8S d~ by ~ & Sa~nl.
The clQQtric:al CQntrwcf:tw shall provide It prtc:a to Alrnish & Indaft (!I) ~, 4-l:.mp ~ troffers md
(4) 4-root, 2...,jamp wn!lliJalQ./nds in canneQf.c:1r fc:Jr tempo/wy IIQhUng. Wire to connedter Itghting dl'C(jlt
breakllrs. !!venly spIlOQ lights ft req~,
Per Phone convernatlon with Tommy Peele of CI. ~drIo on Maret) 7, 2008, tmnsftirmer T --3 in the .
service yard must ~ rel~ tb a~mrtlQdete tl18 swltr:hbOard snd U1e a'l.ltometic transferswftcnes.
There ~hcuk.l be no CCl9! to theOwrler or Sngineer for this work.
8,
Mal'O Peel, Ct ~ ('70UG1-ae!5)
1f~1U""'~' a"".. iItJItr;~ -:It onC't.
aE.~ .' IV'lD
IM~\{~
70~--77/--\5/7~
McKnight Construction Co., Inc,
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr, 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
May 30, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn:Matt McCoy
RE: Augusta Regional Airport
Augusta, GA
PR39
Gentlemen:
The following is the cost proposal to delete the type N fixture per your letter dated 5-11-06
CI Electric
(2313.76)
Please issue a change order for this amount.
~
.~.
'"
Cr((O(l N6:;o1 !"lcD 1" 0
~ 2, Co ~l, .'00 oFJ o(./I2./a~
lA.-{ f~-r f~\IUc..J(.
-t-.11rJ\.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
P cd: Pa1;wJ-fs~
Pat Patrick
Project Manager
PP:sdr
cc: Jobsite
1m 1J; (g 1J; Lt"{1f1J;l
1 'jIJl.'i :; 1 lOOIi l\\l
nil v13 _____--
B '(: ../.'!;.-------
pat053006d. wpd
(;1 Electric, Inc.,
4191-AugustaRegionaIAirport-COs.xls
CO#16":Rev.1
Cost Breakdown for
Credit for deletion of installation of Fixture N
per directive from Matt McCoy
Quantity Unit Cost Extended
Miscellaneous
Labor - workhours
Labor Burden @ 35%
o
0,10
Subtotal Material 0.00
7% Sales Tax 0,00
21,00 168.00
0,35 58.80
Subtotal Labor 226,80
Labor & Material 226.80
0% Overhead & Profit 0.00
Labor, Material, Overhead & Profit
Delete Fixture N (less rebate of OH)
Total for deletion of Fixture N
226.80
2,086,96
2,313,76
8
168
* Miscellaneous includes the following items: fuel"nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, 'ropes, tools, and contingency, etc,'
Schedule Implications
No credit for equipment since the lift was available during the installation of the other fixtures in
the same area. A lift will be needed if the architect deCides later to add the Fixture.
Exclusions:
File:C:\4191-AugustaRegionaIAirport-COs,xls
CO#16-Rev.1
5/25/2006 3:28 PM
.~~)
~ ~'I.
\.., ~
Q1\\-
en
--
en
~
en
c
<(
:t=
-0
Q)
~
o
~
::J
+-'
><
.-
LL
Z
Q)
0..
~
I-
e III
:::l :::l
- 0
~ QI
LL I:
Z~
QlQi
c,t)
~.!!.!
III :;E
::: ~.....
QI._ I:
C=QI
.l9 E
III C,
1:-
_ :::l
_0'
OW
Z ..
... ...
o 0
-..Q
QI III
:::l..J
'0.
e III
:::l :::l
:E g
LLI:
Z~
QlQi
c,t)
~~
_ C) ... '"
t>.5c 8
= Q) C
.l9 E .
III c,
.5"3 ~
... C" ~
~~ &
~~
~~
'0
e III
:::l :::l
')(0
.- QI
LL I:
Z~
QlQi
c,t)
>..!!.!
I-:;E
CO OJ -
a. .:: c
= QI
.l9 E
III C,
I: .-
_ :::l
_ 0'
OW
Z ..
... ...
o 0
-..Q
QI III
:::l..J
'0
G'
....
....
~
i ~~~!:
~ ~~ J,;
. .
_ 0'.
~ ~~
u . ~
g ~
;;:
~
~
.
0'_
1
~
~
- ~
'5 . 1='*
."
e ::. e.~
() ::J . ~@
~
E g o c
~ ~
o c ,,11
o m
m~ ~.il
9 .~ H
~:;; jj
G'
....
....
~
'li
"
c
~
.
-
'5
QI
...
()
I
~
~
~
m
"
:!::: '"
-' g
E ~
8 Iii
~8
~~
G'
....
....
~
0 co
<Xl '" co
.; .; ....
'" ::i
'" <Xl
0 '"
"," ,..;
'" 'I
'" ..
~ :l :c ..
'" 0 :l
;; ~ '"
'" ;;
e '"
~cii: l.> .,. e
~ E e 0 l.>
..;
'" Co Co '" ~ :B
'5" e '0
.,.." 0
00 loo Gl III .., .. I-
~ a::l 0 aa at ftj
coa:i.c...€ '"
~1O=,g~ " .c
. '" 0 .. e
0- € 1Il
8LO:E .. 1Il
:; > ..!!
. '" . 0
NO'" ..
..; :l
c: '"
..
"'''' E ;;
~ e
~
e
:l
;:c
'"
~~~
~N
"[N
;;
Jill t
g~5!m
8):1~]~
'" . 0
0-
:5
;;:
~""
0'"
_M
~@
o c
~ ~
,,11
~.il
r
j~
<Xl
co
~
~
.,.
o
..;
~
'"
~
....
..;
N
~
}
~
5
~
"
z
~
E
~
~
9
f
i
~
.
E
~
U
..
:l
'"
.. ..
:l :l
'" '"
;;
e
l.>
n;
0
I-
'E
..
E
c.
'5
..
~.j\U'''''1
rlf. P-$ c
ISJL
La (II) f t4..(.
U-f:;.or'\ ~R...CAiL.Doc-)"-i
c.l'~
1W~,\iJ K.. ..,
I
10
IV! p..,1f
.. dl
....... r
\:
~'\~\.
.J I ~ \
o( r: '\
, \ Ifi \~
\ \ - \
~~ }\
~ ~, I \
~... \
....... ~,
N";; '\
, \
cc
,-
f
co
,.
..:
~
,Vi, (./}
(.J \1'
(j ---
fji
~i, ~~I ~
,...... ~ \ ~
. .~'t 00
~":t~ ~5;
IS'):e:aC.~ _0
." \ ' rl _- m ~ ~
,,' ~> _ :i""
~~~H p;n~:n:
~5l~[~ <H.8~.e
Ql ":it; lite;=~~
~ tr If) ',5 ~ 0
:g8~~~ ~o .s
a02~C):f!~~ ~
g .g \'" c<),
, .
~~~
N N~
- -,-
l::r ,0:
f ~l
:ji
u
.S
-
'5
QI
...
()
~
'"
"
:s~
E lil
o "
o '"
m~
~.~
~:i;
\
~ ~t
()
,.J
r"1
~~
~@)
,g "
~~
~~
EE
j.5
..
:l
'"
:B
o
I-
;;
e
l.>
e
E
~
f~!'ar.-${Ptl1S:
&i1!'5Qlict'::edurwff
C;"lIlJstrocfi:D@Ej;
Sen:kes, IiEJIc.
/[;10 Hanger F;oad. !3uhe /\
.Augusta. Gi\ a0906
706-"771-5172
Fax: 706-771-5176
May 11,2006
McKnight Construction Co.
635 North West Frontage Road
-------Augusta,-GAJ09-O '1---------____________________ _ _______
-.-------------------.-...----.-----.-------------.-------_.-_._._.__._._._-----_._-----~
Attention: Mr. Pat Patrick
Re: Augusta Regional Airport - Terminal Area Improvements
Type N Fixture Credit
Dear Pat:
PB has reviewed the costs presented in PR 39 which outline the costs associated with the
installation ofthe Type N light fixture. After review and consideration, the Bwner has decided to
delete the fixture and, as such will request a credit for the fixture and the associated installation
labor costs. Please note that the clip from the attached fixture schedule indicates the $2,400.00
allowance for the fixture and lamps and directs the Contractor to include labor, overhead and
profit in their bid. This position is further bolstered by the Contract Documents General
Conditions Paragraph 3.8 Allowances, sub paragraph 3.8.2.3, which states the following (copy
attached ):
.,r,r) /j.
i>/~-./':"1-
Contractor's costs for unloading and handling at the site, labor, installation costs,
overhead, profit and other expenses contemplated for stated allowance amounts shall be
included in the Contract Sum and not in the allowances;
Utilizing the quantities provided for the installation of the Type N fixture in the quote from CI
Electric, PB has arrived at an installation credit of $1,737.48 (breakdown attached with CI
breakdown). Therefore, PB requests PR 39 is revised to reflect a credit of $ 4,137.48 for the
fixture allowance and the installation costs,
If you have any questions conceming this matter, please feel free to contact me at (706) 771-
5172,
Sincerely,
Parsons Brinckerhoff Construction Services, Inc.
,;7 {za:;tu-~:!--.)/
/ .
Mdtthew J. MCCoy (
Construction lvlanager
C".
/
(---
,/'
Cc:
W. Boshears. T, Weegar, T. Strange: ARA
R. Roberson. D. Blessing; PBIINT
1\1, Leath, B_ Anderson: LPA
File
..,....,
,~~
1,.
/.
L"
, j
. ,
I
I
.~
i'l
I~)
~!
~
:ji,
l~'
.~
~:
ill; _
".
It~
~J
~,
;ti
jff;
~,;
n
o
o
(\1
-.
~; .1
.::
t:l(
SAME PS TYPE K, D(CEPT 2-LP11r FDJURE.
BEAM/SURFACE MOUl'ffiD ADJUSTABLE HID F1KTURE WITH EA'TRUDED ALUMINUM HOUSING, WEi
LOCATION USTING, AND HIGH ErI'1CIENCY PSYMMETRIC REFLECTOR. PROVIDE WITH PHIUPS
DOUBLE-ENDED MASTERCOLOR CERAMIC METAL HAUDE LAMP WITH COMPATIBLE LOW-
FREOUENCY, LOW-NOISE WET LOCATlOI. REMOTE ELECTRONIC 8I\U)>.ST. INSIGI-IT \\TT519-WBR- 2
OR EQUAL OF SPI OR WINONA. STANDARD COLOR PS SELEC1ED BY ARCHITECT. REFER TO ARCH.
DRAWINGS FOR MOUNTING HEIGHTS (FJELD VERIFY WITH ARCHITECT PRIOR TO ROUGH-II..)
FIXTURE TO INCLUDE FLEXIBLE WEATHERPROOF POWER CORD WITH WATERTlGI-IT FITllNGS.
PROVIDE MFR's POINT-BY-POINT CALCULATIONS FOR FRONT CANOPY WITH SHOP DRAWINGS.
SAME PS TYPE L, FY.CEPT WALL MOUIW.ll INDOOR FIXTURE WITH DECORATIVE SCOOP HOUSING
AND INTEGRAL BAWST.
SAME PS TYPE u.. FY.CEPT WITH QUARTZ RESTRIl(E,
4 FT SURFIICE MOUNT FLUORESCENT WRAPAROUND, MYOlT ELECTRONIC B.>\W.ST.
UlHONIA LB-232-277-GEB101S OR EQUAL OF METALUX OR DAYBRlTE.
l
LL
LQ
M
;;,
N
DECORATIVE DAMP LOCATION PENDANT F1KTURE TO BE SELECTED BY OWNER. ALLOW. t2,400.00
EACH FOR FIXTURE, LAMPS, AND SALES TAX ONLY. INCLUDE LABOR, OVERHEAD, AND PROm FOR
FIXTURE. LAMPS, AND SALES TAX ONLY. INCLUDE tJroR, OVERHEAD, AND PRom ELSEWHERE IN
CREDIT OWNER WITH mY AMOUNT NOT SPENT, .
. I
ROD JOUNTED r I:. SUC D t. 'n:> PED USHED AL
TRIM RINGS. FIXTURE SHALl BE HUNG UP TO 60" BELOW THE CEIUNG USING AROD HANGER WITH
AIRCRAFT CABLE HANGERS, AND SI-lAll. HAVE E1GI-IT COMPACT FLUORESCENT LAMPS WITH INTEGRALLY
MOUt..fTED MVOLT ELECTRONIC BAUPSTS. VERIFY ACTUAL MOUlfflNG HElGI-IT wm; ARCHITECT PRIOR
TO ORDERING Fll.'1URE. SHAPER 494S-40-CFB/32-MVOlT-SC-FAUX-XX"OA OR EQUAL OF SPI.
SAME />S rrr'E 0, FY.CEPT SMALLER 34" FIXTURE WITH lAMPS />S NOlED. .
SAME JlS TYPE a. EXCEPT SHALLOW 24" RECESSED PENDANT F1Xl1JRE WITH IAMPING PS lIDTED.
SHAPER 494RP-24-CF2/32-MVOLT-SC-FAUX OR EQUAL OF SPI OR WINONA. .
SAME />S TYPE P, EXCEPT WflHLU1RON HI-LUME ELECTRONIC DIMMING BAI.lJo.ST (1~).
SAME /IS TYPE. 0, EXCEPT MATCHING .1HREE-BOWL CHANDEUER' WITI-l 34" FIXTURES AND
I.AI.IPING />S NOlED.
R RECESSED WALL SLOT SYSTEM WITH IIillRNAL REFlECTOR, RAIL MOUNTING. AND MYOLT
ELrcTRONIC BAllAST. SEE DRAWINGS FOR lEN..'lHS REQUIRED, PROVIDE ALL END CAPS
AND EXTENSIONS REQUIRED FOR. CONTINUOUS RUNS. UTE CONTROL 2O-14ID-CWM-ELB10
OR EQUAL OF UNEAR. COORDINATE INSTAllATION IF FIElD WITH. MECHANICAL CONTRACTOR.
00
P
. 1
P2
Q
S
TELESCOPING STAGGERED STRIP UGHT WITH MVOLT ELECTRONIC BALLAST FOR CONTIN'JOUS COVE
UGHTlNG. SEE DRAWINGS FOR LENGlHS REQUIRED. COORDINATE OUANTITlES WITH M.:.NUFACTURER
PRIOR TO ORDERING. Ul1iOt.llA SST-232-MVOLT-GEB10IS-PLF2AB OR EQUAL OF METALUX.
COMPANION WALL SCONCE TO lYPE 0 FIXTURE WITH MYOLT ELECTRONIC BAll.AST, MOUN11NG
HElGI-IT />S DIRECTED BY ARCHITECT. SHAPER S93j4S-CF2/13-MVOLT-SC-FAUX OR EQUAL OF
WINONA OR ADVENT.
WAIl. MOUNTED COt.lPACT FLUORESCENT VANITY FlXTURE WITH MVOLT ELECTRONIC BAWST.
MOUNTING HEIGHT />S DIRECTED BY ARCHITECT. WINONNA 5250-VB-F-277V-FAH-BAL OR EQUAL
OF SHAPER.
U 4 FT WAll BRACKET FLUORESCENT WITH UP/DOWN UGHT, ELECTRONIC BAllAST.
LITHONIA WP-232-MVOLT-GEB101S OR EOUAL OF METALUX OR COLUMBIA.
T
12
V 12" ROUND LOW PROFILE, HIGH ABUSE, SURFACE MOUNT FIXTURE WITH 0.125' INJECTION
MOLDED POLYCARBONATE LENS, DIE C/>ST ALUMINUM HOUSING, MVOLT ELECTRONIC BALLST.
LITHONIA VGRl-2/26TRT-MVOLT OR EOUAL OF FAILSAFE OF KENNALL
V2 SAME />S TYPE V, EXCEPT ov/>'- Wfti MOUNTED FIXTURE wm; LAMP is Nom,
Ope" DENOTES BUILT-IN PHOTOCELL.
V3
4 FT HIGH ABUSE WP-APAROUHD WITH HIGH IMPACT ACRYUC LENS AHD MVOLT ELECTRONIC BAUJ'.ST.
UlHONIA VW-232-ACR-MVOLT-GEB10lS OR EQUAL OF FAILSAFE OR I(ENNALL
W LOW PRORLE CUTOFF WALL PACK WITH PHIUPS WSTERCOLOR CERAMIC METAL HALIDE LAMP WITH
COMPATIBLE PULSE START BAUAST, BUILT-IN PHOTOCELL. AND STAI~DARD COLOR AS SELECTED BY
ARCHITECT. LITHONIA WST-150CDM-WT-TB-PE OR EQUAL OF GARDCa OR LUMARIC
xc CaUNG MOUNTED ARCHITECTURAL EDGE UT LED EXIT WITH EVEN ILLUMII~A110N. RED O~j
CLEAR PANEL AND WHl1E HOUSING, 120/277'1. lITHOI~IJ., LRP-W-1RC-i20/277, OR
EQUAL OF SUREUTES. OR CHLORIDE.
XO SAME AS TYPE XC, EXCEPT DOUBLE SIDED WITH MIRRORED PANEL
KW
SAME />S TYPE XC. EXCEPT \VA!.!.. MOUI'ffiD.
y
RECESSED 0" RETRACTABLE INcAHDEScarr SPOTUGhT, LlTrlot~li'. Dei-PDG OR EQUAL OF PORTrOUO.
21
50 FT HIGH WSf POLE WliH LOWERING Df:.VrCE AND FOUR (4) HIGH PERFC":I..IIINCE
FLODUGI-t'TS WID: IN1ERl~A'- GLARE COIlTROL LOUVERS PAINTED BLACI\ FOR :CHARP \/illTICAL
CUTOFF, QUAl.ITY UGHTlNG 5trl0-W-50-4J..-TL-SS-4C-8-D2-HI.,H'W-FF!.,2 LOWERIIK;
Sl'ST8/. WlTX 51)' STffi POLE AND TOUR (4) UTHONIA 17DS-'iDOOIvl;"HPH-480 FLOODLIGHTS,
OR EQUAL OF COOPER i';. MI:.L:.""RBERND FlXTURES, POLES, AND LOWERIi.G SYST8i:.
(!J
~ \.
o \
\
'\
'..." Z2 ,. 16" ROUI-[l OIJIDOOR Rl81JRE VlITH DECORf\T[I'E FLOATII~G RII~G .A.I~D MVOLi ElECTROHIC 8f"UJ.Si.
'" i SHAPER Eill3VJP-CFL/26-IY1VOu-SZ, SPI AEW106Cl-2F2G-!JVOLi":SAl. OR ECIU/Il OF WI~IOW..
......~~~tlWl'l>J___~~... ."Ai~.
0-1
rfi
q)
'-'. ",r=~.!;..':l'EI~,----~
3,5.1 The Cuntractor warrants to the Owner, Construction 3.8.1 The Contractor shall include in the Contmct Sum all
lvJJnager and Architect that materials .1l1d equipment allow;mces slated in the Contract Documents. Items uivered
furnished under the Contract will be of good quality and new by allowances shall be supplied for such amounts and by such
unless otherwise required or permitted by the Contract persons or entities a,~the OV'l11er may direct, but the
Documents, that the \iVork will be free [rom defects not Contractor shall not be required to employ persons or entities
inherent in the quality required or permitted, and that the against which the Contractor makes re;:[illill1b.~.nhji~liilll__.___.._.______
._.._-1Y-C)d",-\.\T.j.1-l--<::OHf0F1:B-'1Nit.t1-.t.:J.1.e'-recjljirem-ents-of-the-C0111ni:r--.-.----.-----
Documents. \Nork not confom1ing to these requirements, 3.8.2 Unless otherwise provided in the Contract
including substitutions not properly approved and authorized, Documents;
ma)' be considered defective. The Contractor's wananty
excludes remedy for damage or defect caused by abuse,
modifications not executed by the Contractor, improper or
insufficient maintenance, improper operation, or normal wear
and tear under nom1al usage. If required by the Construction
Manager or Architect, the Contractor shall furnish satisfactory
evidence as to the kind and quality of materials and
equipment.
3.7 PERMITS, FEES AND NOTICES" '.
\NSoTll.uc.Tta'-l'S. 16 B IPPCIt'\ - t"o..n". \'\. Z.....&IltPllo.l (, P6tM-lIT 1...Jci.uOi:O 1'-1
3.7.1 Unless otherwise provided in the Contract Co-./To\c.'rotl's
Documents, the Owner shall secure and pay for the building t..u/V'If ~ll""
permit and the Contractor shall secure and pay for all other 610.
pem1its and governmental fees, licenses and inspections
necessary for proper execution and completion of the Work
which are customarily secured after execution of the Contract
and which are legally required when bids are received or
negotiations concluded.
J 11'. '...\IJllr.'h:ll)r .0,1'1:.111 enl.,r.:c :;tncl dISCIpline and
nrdcr amollg the Contr.'lctur':, employee:; and other
'ill:; c;.,T)'ing out ihe Contract.. The Cllntractor shall not
{mit cmployrllcnl of unIit per:;ons or persons not skilled in
sks .'l.c,signcd to them, .
3.5
WARRANTY
3.6
TAXES
3.6.1 The Contractor shall pay sales, consumer, use and
similar taxes for the \^lork or portions thereof provided by the
Contractor which are legally enacted when bids are received or
negotiations concluded, whether or not yet effective or merely
\-ledulea toga into effect.
3.7.2 The Contractor shall comply with and give notices
required by laws, ordinances, rules and regulations and lawful
orders of public authorities bearing on perfOlmance of the
Work.
3.7,J I t is not the Contractor's responsibility to asceltain
that the Contract Documents are in accordance with
appUcable law~, stMutes, ordinances, building codes, and rules
and rcbulations. However, if the Contractor observes that
portion:. of the Contract Documents are at variance therewith,
lhe Contractor shall promptly notif)' tbe Construction
Jvbnager, Architecl and Owner in writing, and necessary
changes :;haU h.., .'lccomplished by appropriate Modificalion.
1 -.. ~L~~" " '11:. r,"U"'"1Jli~ Jl lU ',_
conlra!'y to 13\\15, stall1tc~;, f1rJin;lnces, huil.jin~ code.';, and
rulc:; and re~,l1latioilS without such nntice to the Construction
'lvlanagcr, j\rchitect ;Jl1d (1\</11cr, the Cuiltr3ctor ,;11alJ assume
full responsibility for such Work and ,;hal1 bear the altribulable
co,~ts.
J,8
ALLOWANCES
.1
materials ,md equipment under an allowance shall be
selected promptly by the Owncr to avoid dclay in the
Work;
.2 allowances shall cover the cost to the Contractor of
materials and equipment delivered at the site and all
r uired taxes, less a . . . unts'
Contractor's costs for unloading and handling at the
site, labor, installation costs, overhead, profit and
other expenses contemplated for stated allowance
amounts shall be included in tbe Contract Sum and
not in the allowances;
whenever costs are more than or less tban allowances,
the Ccmtract Sum shall be adjusted accordingl)' by
Change Order. The amount of the Change Order
shall reflect (1) the difference between actual costs
and the allowances under Clause 3.8.2.2 and (2)
changes in Contractor's costs under Clause 3.8.2.3,
3.9
SUPERINTENDENT
3.9.1 The Contractor shall employ a c:.~:)]l1petent
superintendent and necessary assistants who shall be in
attendance at the Project site during performance of the
Work The superintendent shall represent the Contractor, and
communications given to the superintendent shall be as
binding as if given to the Contractor. Important
communications shall be confi.lmed in writing. Other
communications shall be similarly con firmed on written
request in each case,
3,10
CONTRACTOR'S CONSTRUCTION
SCHEDULE
3,10,1 The Contractor, promptly after bl~ing awarded the
Contract, shall prep;He and submit for the CJwner's and
Architect's information and the Construction Manager'.:;
approval ;J Contractor's Construction Schedule fo!' lilt' \'\Iork.
Such [,( heJuk shall nol exceed time limits curren! under the
tc'I:!9~ THE AI.'IEf:I':AIJ II.I:,TITU I E OF hHCHITECTS, Ins NEW YORV, ",VENUE, N.W., W/\SHII'J'..lTulj, [J.r:., 1(JO!jtj':,191. AlA [)C!UJfYlEfIT ":',101/':1,;1" .
'HcM COIICiITIOr,)S OF THE CCHHPJ\CT FOR cmISTRUCTIOIJ. cor'jSTRUCTIOI.1 MAfoI/\CiER.A,DVISEF: EDITICin . 1992 EDITIOf\! . AIMj. VJA,F:lIIIJC,
.1I':"!I~,=d phOlor:e'pyinf': '1i..'!"I"" US coPyrif;ht laws cmd will ,ubj'"ct Ih,= violalor lu 102;,1 prosecution. Thi, document WiJ, ..,I,,,,=tr,.,rlic,dly IJlod\lced
with i,clIlll:::,imt (,f Ille ,6,lf\ and GJII h,~ r'!jlroduc.ed in accordance liillh YCilJr li,;",ns', VJllh'.l1J1 VI(,Liliolt IJltlillhe dal': rA 0J:piraliol'l a" !Iuted b"luw, 11"')/
[JrJ(Urrl'?-llt: '-':I'n:.~ l(ll.ai;1 -- S/2C/20('~ /1,1/\ Licen::e r"Jurnber 101771;4, VJllich ei<pir':'~J on 8/6/~~O(l4.
EI\:,-:tr(Jnic FUI rn~lt
t"\20V(lvLI--!~!':J ..'
~)
Cred[t due for Not ~nstat~~ng Type N Frxture ([R-1 i 6)
- Labor, Equipment~ M~sceHaneous
quantity unit cost extended
JLG Boom Lift (1 day incl deiivery) 1 504.00 504.00
Miscellaneous 2574 0.10 257.40
subtotal equipment 761.40
7% sales tax 53.30
_______J...i::lQ.QL workh0J1[~LQJ..)_______________________.1.6_____3j~5.~.5lliLOQ___________________________________________
Labor Burden @ 35% 549 0,35 192.15
subtotal labor 696.15
labor & equipment 1,510.85
i 5% overhead & profit 226.63
labor, equipment, overhead & profit (credit due) 1,737.48
l!!1 ~/~ #.~~~
~.Iii' 6ii;i&:.....'ll8JVlIIf... 1Tt~ t!=";J~_
4191-AuaUS""~Re(doFtatAimort...cOs"xIs'
"iI!il - - -. . ..... ..
C0#16
Cost a~awn for
~remern:. deiive.."Vand installation of F~rf! N1 UR-116l
Olxan~lv Unit Cost Exllend8li
Fi:rturs ~ (il'l~ ~I.) 1 2.07Q..00 2.070J)O
-.-.---.-----.--.-J03~i!ffp (,ia)<lnO ~r-r-.~
Misealisl'leout> 2574 a.10 257.40
~~ 2.831.40
1% Sal.!!l& Tm:: f96.20
45.00 45J)()
31.50 504-.00
0.35 '% S2.15
~r l...-bor' 741.15
!...1Ibo;- t, ~l 3,710.75
0v8I:iMad &. Pnmt. 5S5.61
UIbor, ~,~&~
uiIDf -iIIroOOloorn (~ CO)
19bar - WC~1.li'$ (""'~.::;e)
LaOO;-- Burdefi @ 35%
1
16
549
i$%
4.,336..36
~ AII;;No~ wr F"~ t4 2.400.00
!\kit d!JJ!!) ti!is ~ 1,936,36
.. ~eou:s indul:Ies 1h8 ibllowing items; IUd, JMs.. ~,~, ~ lube. pv:~, wlra II"dts, .,~, ~.
~~. dl'ilbim. saw ~,1hreadingoi. pull ~ ~ ~and~, stc.
Schedule Implfieations
Aii n.a~ p:ices good fut 10 dBy$.
&:~"e :mp'~m1i be ~"m!~ ~."polll ~a!. Six 1'0 e!ght~ deHMqr.
s~~
Exdusions:
Caf:cm made med;;mun by ~
....,'*-"~ '-f'"l,
.~'ll~~.V
, ~i: ~ ~
.. ~t~..~~-n p)
-<..... 'i,4,', \ "._, I ;\ ,-,I "'
~V Y~"~,{ !)i.t-!
~';'a~ 'l '.
P:tk~:C~W 1S..i-A.ugu~::a~egkm~44~rt-C,C'e~~
C:'!?#-r 5
iiJ,!~Y2t-oo ~2:4€i ?~.;l
CI Electric1 Ine",
4191-AugustaRegionatAirport-COs.xls_
CO#16-Rev.1-
Cost Breakdown for
Credit for deletion of installation of Fixture N
per directive from Matt McCoV
Quantity Unit Cost Extended
Miscellaneous
o
Labor - workhours
Labor Burden @ 35%
8
168
0,10
Subtotal Material 0,00
7% Sales Tax 0,00
21,00 168,00
0.35 58,80
Subtotal Labor 226,80
Labor & Material 226.80
0% Overhead & Profit 0,00
Labor, Material, Overhead & Profit
Delete Fixture N (less rebate of OH)
Total for deletion of Fixture N
226..8Q" .
;Z-,'086,96j
2,313.76
. Miscellaneous includes thefollowing items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
'safeTy glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc. .
Schedule Implications
No credit for equipment since the lift was available during the installation of the other fixtures in
the same area. A lift will be needed if the architect decides later to add the Fixture.
Exclusions:
File: C:\4191-AugustaRegionaIAirport-COs.xls
CO#16-Rev,1
5/25/2006 3:28 PM
v'
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D, McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
p, 0, Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 7, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regiona[ Airport
Augusta, GA
PR 40 (Revised)
Gentlemen:
The following is a revised cost proposal to provide power to the exit lights on the holding room
ramps per your directive dated 3/16/06.
CI Electric
McKnight 7% O/P
Total
Please issue a change order for this amount.
395.37
27.68
423.05
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
PoiPaiJwJC !~
Pat Patrick
Project Manager
1~@~J1\W~1ffi
JUN 0 9 2006 lID
PP:sdr
cc: Jobsite
pat060706h. wpd
.8 Y: --------------------
CI Electric, Inca
4191-AugustaRegionaIAirport-COs.xls
CO#17 -Rev.1
395.37
12-2 mc cable
12-2 mc cable connector
scissor lift rental (1 day)
Miscellaneous
Cost Breakdown for
installation of power to exit si~ms above temporary doors
Buildinq A
Quantity- Unit Cost Extended
50 0,75 37.50
4 0,92 3,68
1 106.40 106.40
148 0,10 14,76
Subtotal Material
7% Sales Tax
31.50 126,00
0.35 44,10
Subtotal Labor 170,10
Labor & Material 343,80
Overhead & Profit 51,57
Labor, Material, Overhead & Profit
162.34
11,36
Labor - workhours (overtime)
Labor Burden @ 35%
4
126
15%
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, -drillilits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc,
Schedule Implications
All material prices good for 10 days. .
Exclusions:
Repairs to ceiling grid and ceiling tile.
File:C:\4191-AugustaRegionaIAirport_COs.Xls
CO#17 -Rev.1
5/25/2006 3:47 PM
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
P. O. Box 204718
Augusta, Georgia 30917
April 20, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta" GA 30906
Attn: Matt McCoy
4~
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
Office Phone: [706] 863-7784
Fax: [706] 863-2031
RE: Augusta Regional Airport
Augusta, GA
PR44
Gentlemen:
The following is a cost proposal for the added hardware and installation for the doors added to the
covered walkway per the fIre marshal's directive.
GA Hardware (material)
(installation)
$8,670.80
850.00
$9,520.80
666.46.
$10,187.26
Subtotal
McKnight 7% O/P
Total
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
PcttPcdxKL/s~
Pat .Patrick .l~ @ ~ JT\W~J.
Project Manager U III .
APR 2 5 2006
PP:sdr
cc: Jobsite
pat042006a. wpd
BY- ---------.-
..--------
,.---
1
-~..,..-.,...:ll..'K..............,............
1704 NORTH LEG COURT
Georgia AUGUSTA, GEORGIA 30909
" TEL: 706-736-1328
Ha rdware FAX: 706-733-8772
Distributors,Inc.
INVOICE NUMBER:
38652
INVOICE DATE:
3/13/06
PAGE: 1
SOLD TO:
McKnight Construction Company
P. O. Box 4718
Augusta, GA 30917
SHIP TO:
McKnight Construction Company
Augusta Regional Airport
Augusta, GA
QUANTITY
ITEM NUMBER
CUSTOMER PO
Matt/Lee
SHIPPING METHOD
Delivered _~o Jobsite
DESCRIPTION
SHIP DATE
3/13/06
PAYMENT TERMS
Net 30 Days
DUE DATE
4/12/06.
CUSTOMER 10
Mcknight
SALES REP ID
Dennls
'UNIT PRICE
EXTENSION
1.00 5
Job: Augusta Regional Airpor t
(Change Order/Temporary Doors)
Lot of Finish Hardware (08710) as
per the Finish Hardware Schedule
-
(Gate No 4)
Lot of Finish Hardware (08710) as
per the Finish Hardware Schedule
(Gate No 5)
Lot of Finish Hardware (08710) as
per the Finish Hardware Schedule
(Tug Gate 8)
Lot of Finish Hardware (08710) as
per the Finish Hardware Schedule
(Temp 1A)
Lot of Finish Hardware (08710) as
per the Finish Hardware Schedule
(Temp 1B)
Lot of Finish Hardware (08710) as
1,350.00
1,350.00
1.00 5
1.00 5
1,350.00
1,350.00
1.00 5
1,000.00
1,000.00
1. 00 5
1,565.00
1,565.00
1.00 5
1,565.00
1,565.00
1,350.00
1,350.00
Subtotal
Continued
Sales Tax
Continued
TOT AL DUE
Continued
9120
1 Y2% PER MONTH CHARGED ON PAST DUE ACCOUNTS
PLEASE PAY BY INVOICE' NO STATEMENT WILL BE MAILED
1704 NORTH LEG COURT
AUGUSTA, GEORGIA 30909
\ TEL: 706-736-1328
Hard war e FAX: 706-733-8772
Distributors, Inc.
SOLD TO:
~cKnight Construction Company
P.O. Box 47 1 8
Augusta, GA 30917
CUSTOMER ID
Mcknight
SALES R~P ID
CUSTOMER PO
Matt/Lee
SHIPPING METHOD
Delivered to Jobsite
QUANTITY .
38652
INVOICE NUMBER:
INVOICE DATE:
3/13/06
PAGE:
2
SHIP TO:
McKnight Construction Company
Augusta Regional Airport
Augusta, GA
PAYMENT TERMS
Net 30 Days
DUE DATE
4 12 06
..._'.,.~, ."""-,, .....:~n
ITEM NUMBER
DESCRIPTION
UNIT PRICE
per the Finis h Hardware Sehe dule
(Temp lC)
. . ".." -. ".
~ '-'-: . . .: , . ;"',' ' . ... ,', :. .
~i1~jg:M{:. '~;:;~\~ri:~,
20
)~ PER MONTH CHARGED ON PAST DUE ACCOUNTS
,ASE PAY BY INVOICE. NO STATEMENT WILL BE MAILED
('
Subtotal
Sales Tax 7"1.
TOTAL DUE
8,) 80,00
...49tt8tr
572...(,0
$8,670.80
"
1704 NORTH LEG COURT
AUGUSTA, GEORGIA 30909
\ TEL: 706-736-1328
Hardware FAX: 706-733-8772
Dist ributors, IOc.
, - ~'.~"~':"'-'''''.r,""~:.;.,,..'
INVOICE NUMBER:
3 8653
INVOICE DATE:
3/13/06
PAGE: 1
SOLD TO:
McKnight Construction Company
P. O. Box 4718
Augusta, GA 30917
SHIP TO:
McKnight Construction Company
Augusta Regional Airport
Augusta, GA
CUSTOMER 10
Mcknight
SALES REP 10
ennlS
CUSTOMER PO
Matt/Lee
SHIPPING METHOD
-SH~ DATE
3/13/06'
PAYMENT TERMS
Net 30 Days
DUE DATE
4/12/06
1. 00 10
ITEM NUMBER DESCRIPTION UNIT PRICE EXTENSION
Job: Augusta Regional Airport
Installation of Finish Hardware for 300.00 300.00
Tug Gate 8
Installation of Finish Hardware for 200.00 200.00
Temp. lA
Installation of Finish Hardware for 200.00 200.00
Temp IE
Installation of Finish Hardware for 150.00 150.00
T~mp 1e
"
QUANTITY
1.00 10
1. 00 10
1.00 10
Subtotal
850.00
Sales Tax
TOTAL DUE
$850.00
9:20
\0200 PER MONTH CHARGED ON PAST DUE ACCOUNTS
'LEASE PAY BY INVOICE. NO STATEMENT WILL BE MAILED
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
May 10, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport
Augusta, GA
Revised PR-45
Gentlemen:
The following is a revised cost proposal from Bonitz and Davis Painting for the work to patch and
paint existing walls in the US Air Building per your direction.
Bonitz.-
Davis Paint
Subtotal
McKnight &%
Total
$1,325.00
1,501.00
2,826.00
197.82
3,023.82
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
P cdPohLLrJL 1sdA-
dECEIVED
MAY 1 2 2006 .
Pat Patrick.
Project Manager
PP:sdr
cc: Jobsite
pat051 006. wpd
0(f: C;:;02-
~nitz ru
~contracting Company, Inc. .
645 Rosewood Drive 2.9201 . P. O. Box 82 . Columbia. SC 29202-0082
phone 803-799.0181
Fax for Floor Covering 803-799-D593
Fax for Production, Human Resources 803-748-9223
Fax for Corporate 803-758-4327
Fax for Celllng & Drywall Sales 803-758-4288
www.bonitz.com
Bid Proposal
Revised May 9, 2006
McKnight Construction Co.
P.a. Bor 204718
Augusta., GA. 30917
ph: (706) 863- 7784 .
fax: (706) 863- 2031
Attn:~es ??\T ?AI ez-; c..L
Re: AUGUSTA REGIONAL AlRPORI
AUGUSTA, GA.
We have prepared the following pricing per your request.
To fUrnish materials, labor, and equipment to patch eristing walls at the US Air Building
tuid $ 1,325.00 to original contract price.
Material 117.38
Labor 1,034.80
Markup 172. 82
Total 1,325.00
Please inform Bonitz of when we can erpect a CJ..ange Order for this work.
Jfyou have arry questions, please donor hesitate to call.
CTING CO., INe.
Cc: Jerry Davis
Steve Jordan
Judy Riley
. ATIANTA . AUGUSTA . CHARLESTON . CHARLOTTE . COLUMBIA . FAYETTEVIu.E . GREENVILLE . RALEIGH . TRIAC
Ma~ lU UO u~:~~a
MCKnlgn'C L.OnS'CrUCl:.10n l..O. (UO-' ,c.-oc.o..:>
t"'. J.
P.O. Box 6097
North Augusta,SC. 29861
Ph: 803-441-6464
Fax.:803 -819-1257
aP.~.~~
D;"~-Painting
Contractors,Iric.
Change In Scope.
To: Lee,
From: Richard Littleton
Fax: 772-8283
Phone: 772~8282
Project: Augusta Regional AiIport
Pages: One
Date: May 9, 2006
o Urgent 0 For Review 0 Please Comment 0 Please Reply 0 Please Recy~le
. Comments:
Lee?
The following is the additive amount for the painting of additional walls
and doors in the US Air Ticket Area= '
Labor ~ r . ---$1,084.00
Materials -------- '417.00
Total Add ---..... - $1 SOl 00
, .
If you have any questions please do not hesitate to contact me.
Sincerely,
!? ~ 1, ' 7 ff....
, It'd cl '7',J') . u
e i)fl /+-L pr) ~([ fur
P~+G~J~ '-I~e ~
A B)1 J "r, (0/,
C' i' r "Lt\.l CIt l j
0r.), . ,
Davis Painting Contractors, Inc.
~~
Richard Littleton, Vice Presi.dent
t~~j
~v..x
i n/.'1 r~
U!' (l-~
-111~~(1lf
I FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D, McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
May 18,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
Gentlemen:
RE: Augusta Regional Airport
Augusta, GA
PR 47, IR-19R
The following are the costs associated with the work involved in the trailer modifications as shown
in IR-19R. .
McKnight Construction Co.
Please issue a change order for this amount.
COSTS~Dj0S-rf.,V TO ft ~8(.l. I .
I
1 \ C.11~\~ LI~K.. rc~CJ:., P/>-,I D A-,s
f~t.-( Or L 11--11: llttv'\ ~qo 6~
Uhj 11 t()":..-r 8.~E. ~(\l)(5\,Jfj. 'S::. c::: \) l::.1l\k...
~1f~t.J) .
- t-'\ j tv\
ec: Jobsite
pat051806d. wpd
$7387.21
Sincerely,
MCKNIGHT CONSTRUCTION CO., INe.
P~--tfM;WjLISA~
Pat Patrick
Project Manager
lID n; @ ~~\W~1ID
ml MAY 2 2 2005 JJ)J
B Y: ___~________
,HRACT NO MCB NO, "
JCA TION OEseR:
2ROJECT
SUBMITIED BY DATE,
r: ;/ - / q CONTRACTOR COST ESTIMATE PROPOSAL
QUANTIT'{ LABOR MATERIAL
DESCRIPTION NO UNIT PER PER SUB
UNITS MEAS UNIT TOTAL UNIT TOTAL eOST
Install doors $0,00 $0,00 $1,070.00
Lumber for steps $0.00 $476,00 $0,00
110'Y1 ~o...\) 235 feet of fence $0.00 $0,00 $4,230,00
carpenter 16 $13.00 $208,00 SO.OO $0.00
carpenter 16 $15.00 $240,00 $0,00 $0,00
labor 32 $10,00 $320.00 $0.00 SO.OO
$0,00 $0.00 $0,00
$0.00 $0.00 SO,OO
$0.00 $0.00 SO,OO
$0.00 $0.00 $0,00
$0,00 $0.00 SO.OO
SO,OO . $0.00 SO,OO
-c;:- SO.Oo $0.00 $0.00
SO,OO $0.00 $0,00
SO.OO $0.00 $0,00
.' $0,00 $0,00 $0,00
. 50,00 SO.OO $0,00
$0,00 SO.OO $0.00
$0,00 $0.00 $0,00
$0,00 SO,OO $0.00
$0,00 SO.OO $0,00
, $0.00 SO.OO $0,00
- $0.00 SO.OO $0.00
$0.00 SO.OO $0,00
SO.OO $0,00 $0.00
SO.OO $0.00 $0,00
$0,00 $0.00 $0,00
$0.00 $0.00 $0,00
$0.00 $0,00 $0,00
$0.00 $0,00 $0.00
$0.00 $0,00 SO.OO
.... . -- - -
5/9/2006
oj? (~L\<V\;~t.Jr.5 lo.\;;Y \ 50/0
r;300 ~
26% T
S~~
RECEIVED MAY 0 5 2006
Parsons
Brlnckerhoff
ConstructIon
ServIces, Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
706-771-5172
Fax: 706-771-5176
---
--
--
--
---
- --
- --
- --
- -
100
YEARS ':!I
May 4, 2006
McKnight Construction Go.
635 North West Frontage Road
Augusta, GA 30907
Attention: Mr. Pat Patrick
Re: Augusta Regional Airport- Terminal Area Improvements
Information Notice #19R
JI
Dear Pat:
Attached herewith is Information Notice #19R McKnight is directed to proceed with the
work shown in this document. If McKnight believes this 1. N. has cost implications,
additive or credit, a detailed cost breakdown should be provided for review.
If you have any questions concerning this matter, please feel free to contact me at (706)
771-5172.
Sincerely,
Parsons Brinckerhoff Construction Services, Inc.
r~Cf.'1 t;/
Matthew J. MCCoy
Construction Manager
Attachment
Cc: W. Boshears, T. Weegar, T. Story; ARA
M. Leath; LP A
R. Roberson, D. Blessing; PB/INT File
Over a Century of
Engineering E::cellence
PROJECT NUMBER: AR209024
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELD
INFORMATION NOTICE No. IN -19R
DATE: May 3, 2006 (supersedes IR19 issued 3/9/06)
FROM: The LPA Group Incorporated
TO: McKnight Construction Company, Parsons Brinckerhoff Const. Services
SUBJECT: Revisions to Temporary Rental Car Office Trailer
SPECIFICATION NO: 01500
DRAWING REFERENCE: TF1.2
DESCRIPTION:." .
Based on Input from the using agencies, the interior layout is preferred as shown originally in TFI.2.
After review on site of the trailers procured, the location of public entry / exits has been changed on
the attachment to reflect the location of existing doors. Doors from the back hall are needed to prevent
the creation of dead end corridors. These could be installed in the existing window openings. The
modifications include stairs to grade from these openings, and use of temporary fencing to provide
Separation from the secure area / AOA.
Architect or Construction
Manager Company Name: The LPA GroM"ted
Signature: ~. ~
If this notice causes any cost or time impact to your work, do not proceed; submit a Cost Proposal (CP)
for changes in Contract Sum and/or Time within t.en (10) days. If this response indicates no change to the Work
or a minor change to the Work consistent with the Contract Documents, indicate your acceptance of this notice
in the space indicated below and return a copy prior to proceeding.
Accepted By:
Date:
cc: CONSTRUCTION MANAGER
ARCHITECT
CONTRACTOR
OWNER'S REPRESENTATIVE
ATTACHMENTS- 2 PAGES 8.5" X II"
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT, AUGUSTA, GEORGIA
CONTRA.CT MODIFICATION FORMS
01250-3
-l
:>>
c:
ffi~
U1 -f:;O
() mSi
:l>
r :::~
I'l
"C~
Z 00
0 :oZ
Z
I'l )>~
:08
-<:;0
:0"1:1
m~
:z:
-f
)>
r-
0
)>
:0
0 en
tJ1
"- :z:
0
(,.J .
"- .....
N <.0
0
0 :0
Ol
~I
,
,
.
,
"
:1
~I
:'
.
.
.
.
.
.
.
.
.
.
.
.
,
.
.
.
.
.
.
.
.
.
,
.
~
.
.
.
.
.
.
.
.
,
.
,
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
,
.
.
.
.
.
.
.
,
.
.
r
.
.
.
,
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
.
'"
z
--<
:u
-<
I
:u
".
;::
."
)>
--<
'"
12'
. 12'
12'
;::
'"
~S!
- ".
a> Z
n
".
r
e;
)>
Ul
'"
n
c
a> :u
o. ~
I ..,
o. '"
Z
n
'"
Remove first and last
window and install exit doors
from rear hallway
IN-19R
Page 2 of 2
~)
~
'<:'-
"""
(~
-..\--,
~
~s
....::::
~-s:.
---
~
~
:~
~
~
<2"
~
....
!E
'(ij
....
I-
:- en
......
Q:;
en
"0
o
:2
.,....
.,....
..J .,....
<( lQ
I- CCI
0 N
I-
0 0 0 0 0
0 , 0 en Q) Q)
0 c:i -i ..,f ..,f
;; I'- I'- I'- ..,. ..,.
I- - O. C!, .,.... .,....
(,) 0 ...... .,.... .,.... .,....
<( -
0::
I-
Z
0 en
(,) N
00- N
::l .- N
en g
~
0 0 N N 0 N
0 0 M C"l ..,. I'-
<0 u:i M en <0 an
;; I'- I'- M 0 I'- CCI
B ..,. ..,. It) It)-
..J
<(
12
w
I-
<(-
:E .-
I:
:l
...
18
0 00 0 ..,. ..,. to 0
0 00 0 0 0 ..,. It)
<Xi 00 cO to M ~ c:i
;; 0 ..,.N lQ ...... CCI ..,. C"l
'0 N NM ' I'- N Q) .,.... "':
- .,....
-
0::
0
00 eft. eft. eft.
:5 0 00 ;; jij jij
0 0 0 - I'- co '0 It) -
M to 0 0 N ...... 0
Q) ...... ...... ...... :c - I-
.c
- :l :l
f! en Ul
en ~
III g
Q)
E .r: .r: .r: Ql
... ~ E E E Cii
0 0
>=:: '0
l- I: ~
i= :l 1:
z
<( 0 toto N 0
...... ...... M 0
::l .0
0 :J
en en
- ....
'2 .E
:l >.
C
0
!!!
0
'5 0
"0
en .9
'l:t:
E "0
(])
~ 8
(])
I:: ~
12
(])
Ie;; 0
I::
g (])
z u..
0 enti .:.::
i= I::
o 0 :.J .... ....
a. o:t:. 1::2 (])
12 0.... '(ij I:: 1:
(])
(,) =.0 62 (]) ....
en l!! E 0.0
.....0
W en :J . CIJ ro t\l
C I::..J I'-u U..J
William D, McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
P. O. Box 204718
Augusta, Georgia 30917
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
June 7, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
Gentlemen:
\!
JpcU[~) __.
IO~-171-v:J '7~
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
Office Phone: [706] 863-7784
Fax: [706] 863-2031
RE: Augusta Regional Airport
Augusta, GA
PR 43 (Revised)
The following is a cost proposal to provide power to the battery changer at gate 4, and credit for
power to the jet bridges.
CI Electric
Credit
Subtotal
McKnight &% O/P .
Total
$4,437.21
(3,698.80)
738.41
51.69
790.10
Please issue a change order for this amount.
PP:sdr
cc: Jobsite
pat060706f. wpd
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
Rrt Poitudv~~
Pat Patrick
Project Manager
lID ~cg~lt\W~1ffi
Jftl JUN 0 9 2005 illJ
BY: ____________________
CI Electric, Inc.
4191-AugustaRegionaIAirport-COs.xls
CO#20-Rev.1
.~
c v~ $;ze
Labor - workhours I
Labor Burden @ 35%
Cost Breakdown for
power to battery charqer for Gate No.4
per directive from Matt McCoV
Quantity Unit Cost Extended
1020 1,26 1,285,20
340 0,36 122.40
1 150,00 150.00
1408 0,10 140.76
Subtotal Material 1,698.36
7% Sales Tax 118,89
48 31,50 1,512,00
1512 0,35 529,20
Subtotal Labor 2,041,20
Labor & Material 3,858.45
15% Overhead & Profit 578,77
Labor, Material, Overhead & Profit
#2 thhn
#8thhn
wire tugger (day)
Miscellaneous
4,437.21
..;..
* Miscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc.
Schedule Implications
All material prices good for 10 days.
Work was completed in accordance with direction from Matt McCoy prior to turnover of Phase 1 and
an e-mail from Chris Patrick of the Sims Group dated 16-Mar-06. #2 thhn was used instead of #3 due
to availability.
Exclusions:
File:C:\4191-AugustaRegionaIAirport-COs.xls
CO#20-Rev.1
5/25/2006 4:23 PM
C'.Elecfric, Inc.
4191-AugustaRegionaIAJrport-COs.xls
CO#32
C#
#2 thhn
#8 th hn
wire tugger (day)
Miscellaneous
Cost Breakdown for
Credit for power to iet bridaes
per directive from Matt McCoy
Quantitv Unit Cost Extended
2800 0.52 1,456.00
750 0.14 105.00
1 150.00 150.00
1561 0.10 156.10
Subtotal Material 1,867.10
7% Sales Tax 130.70
~ (co 21.00 ~OO:eQ. \ u,o.<JQ
1008 0.35 ae;Z.ClCl- ,-\"",l.oo
Subtotal Labor 1~S8.8Q r liol.OO 11 00
Labor & Material ::,::;:::;O.C& 3lP'\'v. V
0% Overhead & Profit 0.00
Labor, Material, Overhead & Profit -:t,J:::;O.CQ-l
_ 3\7~ 10 . e 0
Labor - workhours
Labor Burden @ 35%
*1v1iscellaneous includes the following items: fuel, nuts, bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc.
Schedule Implications.
All material including conduit, wire, disconnects, and breakers are purchased and on-site. The 100
disconnects are installed except the o,:,e used for the battery charger. None of the 60 amp disconnects
were mounted, but are delivered. .-
Exclusions:
File: C:\4191-Augusta RegionaIAirport-COs.xls
CO#32
5/25/2006 4:29 PM
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
q O~ - ~11- b { -, (0
apOJjG~
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 19,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: AuguSta Regional Airport
Augusta, GA
PR SO/IN 22
( Revised)
Gentlemen:
The following are the costs associated with work to revised the Java Hut per your letter revising IN-
22 dated 6-5-06.
CI Electric
McKnight 7% OIP .
Total.
$2,703.80
189.27
$2,893.07
Please issue a change order for this amount.
COStS Nf.G:.OlI4ED TO ~1,8t..[D.>'S
~ OS "S\-\()W(~ aN k.1W<.u{Ej;) &e:b4C.DeW~ .JJCKNIGHT CONSTRUCTION CO., INC.
1?6VIE.WE.,O B'I ?,,' r".\?\a.. .f: 1\,""'~iPa.t pa:J.Ju..ciG I~ .
6 '-I 6(., [ 'U / Q (., . ~/ Pat Patrick. '
-fv'\JiV\ // Project Manager
PP:sdr
cc: Jobsite
m~:~~:~~
B Y: _uJlj_~~____
pat061906. wpd
,. - '-0
+~~, ~
CI Electric, Inc.
4191-AugustaRegionaIAirport-COs.xls
CO#29-Rev.1
Cost Breakdown for
installation of Dower circuit for temDOrary Java Hut
Der In-22
Quantity Unit Cost Extended
30 amp 2p breaker 1 160.00 160.00
30 amp 2p receptacle 1 50.00 50.00
4' square box 5 2.15 10.75
4" square box cover blank 4 0.50 2.00
4" square plaster ring 1 6.25 6.25
10-2 mc cable 250 1.52 380.00
mc cable connector 15 1.60 24.00
scissor lift 1 269.64 269.64.
Miscellaneous 229 0.10 22.90
Subtotal Material 925.54
7% Sales Tax 64.79
Labor - workhours 48 21.00 1,008.00
Labor Burden @ 35% 1008 0.35 352.80
Subtotal labor 1,360.80
labor & Material 2,351.13
15% Overhead & Profit 352.67
labor, Material; Overhead & Profit 2,703.80
. Miscellaneous includes the following items: fuel, nuts,bolts, hardware, wire lube, pvc glue, wire nuts, tape, straps, gloves,
safety glasses, drill bits, saw blades, threading oil, pull string, ropes, tools, and contingency, etc.
Schedule Implications
All' material prices good for 10 days.
Exclusions:
After hours or weekend work due to schedule compression
File:C:\4191-Augusta RegionaIAirport-COs.xls
C0#29-Rev.1
6/16/2006 3:02 PM
~
Parsons
Brinckerhoff
Construction
Services, inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
706-771-5172
Fax: 706-771-5176
----
----
----
---
--
--
--
---
- --
- --
- --
- -
- -
- -
- -
100
YEARS ..
June 5,2006
McKnight Construction Co.
635 North WestFrontage Road
Augusta, GA 30907
Attention: Mr. Pat Patrick
Re: Augusta Regional Airport - Terminal Area Improvements
Information Notice #22 Revised
Dear Pat:
This letter is intended to confiml the direction provided by Robbie Roberson of this
office concerning the temporary power to the Java Hut. It is noted that this direction was
provided in the presence of Messrs. Lee Mooney and Kelly Peel of McKnight and CI
Electric, respecti vel y.
The required power, both 220V and 11 OV is to be taken from circuits immediately
available and identified on-site. Specifically, the feeds will be taken from the overhead
door circuits in the vicinity of the temporary Java Hut location. It is also noted that a
datalcomm. feed is required and is addressed in the original contract documents.
If you have any questions concerning this matter, please feel free to contact me at (706)
771-5172.
Sincerely,
Parsons Brinckerhoff Construction Services, Inc.
J11dttb) ?7V.
M~hew J. MCCO; (
Construction Manager
Cc: W. Boshears, T. .Weegar, T. Story; ARA .
L. Mooney; McK
M. Leath, B. Anderson; LP A .
R. Roberson, D. Blessing; PB/INT
File
Over a Century of
Engineering Excellence
30 amp 2p breaker
30 amp 2p receptacle
4" square box
4" square box cover blank
4" square plaster ring
10-2 mc cable
mc cable connector
scissor lift
miscellaneous
labor workhours
labor burden @ 35%
CI Electric
Power Circuit for Temp Java Hut
I N-22
quantity
1
1
5
4
1
250
15
o
229
28
588
unit cost
160.00
50.00
2.15
0.50
6.25
1.52
1.60
269.64
0.10 22.90
subtotal material
7% sales tax
extended
160.00
50.00
10.75
2.00
6.25
380.00
24.00
655.90
45.91
21.00 588.00
0.35' ""205.80
subtotal labor 793.80
labor & material 1,495.61
15% o&p 224.34
labor, material, overhead & profit 1,719.95
McK@
7%
120.40
Total
1,840.35
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
June 19,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: Augusta Regional Airport
Augusta, GA
PR61
Gentlemen:
The following is a cost proposal for CI Electric to install communications conduit for (2) jetways
per PB's directive, and IR-96.
CI Electric
McKnight 7% OIP
Total
$231.26
16.19
$247.45
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
Pcx1 PaJJ<1cfc I~
Pat Patrick
Project Manager
PP:sdr
lID lE: (g lE: TIW ~ lID
ml JUN 2 1 2005 lliJ
B Y: __~~~______uu.
cc: Jobsite
pat061906dwpd. wpd
CI Electric, Inc.
4191-AugustaRegionaIAirport-COs.xls
CO#7-Rev.1
Cost Breakdown for
Installation of communications conduit and cablina
IR - 96 - Jetwav Foundations
Quantity Unit Cost Extended
20 1.05 21.03
o 1.25
2 2.65
o 45.00
o 0.72
o 0.40
o 3.50
o 250.00
o 550.00
26 0.10 2.63
Subtotal Material
7% Sales Tax
31 :50 126.00
0.35 44.10
Subtotal Labor 170.10
Labor & Material 201.09
Overhead & Profit 30.16
Labor, Material, Overhead & Profit
1" emt
1" emt - couplings
1" emt - connectors
8x8x6 JB N3R
Mineralac straps
allthread - 3/8"
Caddy beam clamps
Hammer drill (rental/week)
Scissor lift (rental/month)
Miscellaneous
Labor - worl<hours (overtime)
Labor Burden @ 35%
Schedule Implications
All material prices good for 10 days.
Schedule Impact Is five (5) days.
f R .Co "
-----
5.30
28.96
2.03
4
126
15%
231.26
No overtime or after hours work Included to due to schedule compression.
Exclusions:
Telephone and communication cabling ($8,'050).
Removal, repair and reinstallation of sheetrock walls and ceilings.
Removal, repair and reinstallation of ceiling grids and tiles.
File:C:\4191-AugustaRegionaIAirport-COs.xls
CO#7-Rev.1
5/25/2006 4:34 PM