HomeMy WebLinkAboutJ HARRIS TRUCKING CHANGE ORDER NUMBER ONE STORM DRAINAGE IMPROVEMENTS AT VILLAGE WEST Change Order Form
Change Order Number: ONE Date: 10/26/2010
Project Title: Storm Drainage Improvements at Village West
Original Contract Date: 4/1/2010 Project Number: 324 - 041110 - 210824702
Owner: ARC P.O. Number: P180285
Contractor: J. Harris Trucking
TOTAL AMOUNT OF THIS CHANGE ORDER $ 25,229.79
As a result of this Change Order, the anticipated contract completion date is thirty (30)
days from Commission approval date.
Original Contract Amount $ 297,101.48
Previous Change Order(s) Total $
This Change Order $ 25,229.72
TOTAL CONTRACT WITH CHANGE ORDER(S) $ 322,331.27
* * * * * * * * * * * * *
Funding Source /Account Number: 324 - 041110- 0000000
Requested By: L ' /
, ig../ Date: / /0
onstruct 1. Man eV
Submitted By: _ Vi/ 4._— Date: ////7 /0
Department Head
Finance Endorsement: r_ _ &L ,ri,. Date: / /-- /9 )
Finance Director
Approved By: C..0(:-se 'Q • yor Date: ii /z s (1a
M
Accepted By: .. 4.4 �Li l Date: f �3 -Z �i
1 / ontractor
cc: Anthony (Tony) Williams, Construction Manager
Geri Sams, Director Procurement
Valerie Jenkins, Dept Accountant
Tim Schroder, Finance
File
a
J. Harris Trucking & Construction, Inc.
Post Office Box 14311
%\/ 1736 Barton Chapel Rd.
� Augusta, Georgia 30909
f %A� Office:
. I \ 1/21_ (706) 667 -9904
Facsimile: (706) 667 -9905
JEFF&Ry HAR.RJS
TRIG GKI NCt, (NC.
October 5, 2010
Augusta Richmond County
Engineering Division
520 Greene Street
Augusta, GA 30901
Attention: Tony Williams
RE: Village West Shopping Center
Change Order to add to Contract
Dear Mr. Williams,
As per your conversation with Robert Barker this morning the change order has and /or
about to be completed. Initiate the change order and execute the contract to show the
revised change order as listed below.
315 sy type E asphalt $2,296.35
115 If curb and gutter @ $11.00 $1,265.00
173.42 sy type E $1,264.23
173.42 sy type B $1,467.13
255 Additional asphalt 6 inch curb @ $9.00 /If $2,295.00
Underground with curb cuts and patch @ $225.00 each $ 900.00
Undercut for 30" RCP 437.28 cy @$36.00 $15,742.08
437.28 cy @ $36.00
Total change order $25,229.79
pe lcer- y,
d ik
Jeffery Harris Trucking, Inc.
Owner