CHANGE ORDER
Order No.1 (FINAL)
Date April 23', 1996
Agreement Date November 14, 1995
PROJECT:
1995 WATER SYSTEM IMPROVEMENTS, BROWNS ROAD WATER LINE
OWNER:
BOARD OF COMMISSIONERS OF RICHMOND COUNTY, GEORGIA
CONTRACTOR:
EAGLE UTILITY CONTRACTING, INC.
The following changes are hereby made to the CONTRACT DOCUMENTS:
JUSTIFICATION: FINAL QUANTITY ADJUSTMENTS TO RECONCILE CONTRACT TO ACTUAL
INSTALLED QUANTITIES (SEE ATTACHED SHEET)
CHANGE TO CONTRACT PRICE:
Original CONTRACT PRICE
$ 325,947.19
Current CONTRACT PRICE adjusted
by previous CHANGE ORDERS
$ 325,947.19
The"CONTRACT PRICE due to this
CHANGE ORDER will be (increased)
(decreased) by:
$ 24,394.24
New CONTRACT PRICE including this CHANGE ORDER
$ 350,341.43
CHANGE TO CONTRACT TIME:
The CONTRACT TIME will be increased by
o
calendar days.
Requested by
be
June 1, 1996(Date).
The date for
Recommended
Ordered by
Accepted by
GEORGE McELVEEN, AUGUSTA-RICHMOND
APPROVED
MAY 2 1 1996
IAUGUSTA-ftJCHMOND COUNTY COMMISSION)
9422
CHANGE ORDER
:
"-'-'~" .- ,.
Browns Road 12" Water Line
Augusta-Richmond Utility Department
Final Contract Quantities
and Cost
Original Contract
Item No. Description Quantity Unit Cost Total Cost
1 12" Dip 17163 If $ 14.63 $ 251,094.69
2 B & J Hwy 25 1 Is $ 8,250.00 $ 8,250.00
3 12" Gate Valves 8 ea $ 910.00 $ 7,280.00
4 Fire Hydrants 17 ea $ 1,375.00 $ 23,375.00
5 2" Air Release Valves 5 ea $ 1,050.00 $ 5,250.00
6 Tie to exist. 2" line & 2" Is $ 575.00 $ 575.00
line at Liberty Church
.""t Tie into exist. 12" @
7 1 Is $ 1,985.00 $ 1,985.00
H #25
Connect to exist. 12"
8 Line at inter. of Liberty Is $ 500.00 $ 500.00
Church Rd and Old
Wa esboro Rd
9 DIP Fittings 4 tn $ 3,225.00 $ 12,900.00
10 Abandon Bores 50 If $ 5.00 $ 250,00
11 3/4" Service Connect. 17 ea $ 400.00 $ 6,800.00
12 3/4" Service Line 170 If $ 4.00 $ 680,00
12a Service Bores 0 $ (200.09) add
13 Borrow Material 100 cy $ 6.00 $ 600.00
14 Select Refill Material 15 cy $ 8.00 $ 120.00
15 Cone. Encase.,Collars 2.5 cy $ 85.00 $ 212,50
16 Asphalt Replacement 100 sy $ 32.50 $ 3,250.00
16a Special Asphalt Overlay 1 Is add add
at Ke s Road
17 Gravel Drive Rreplace. 300 sy $ 3.25 $ 975.00
18 Concrete dlw Repalce. 50 sy $ 28.00 $ 1,400.00
19 8" thk. Rip-Rap 10 cy $ 45.00 $ 450,00
Total for Original Contract $ 325,947.19
Change Order NO.1 (Final) Add $ 24,394.24
Adjusted Contract Totals $ 350,341.43 $ 350,341.43