HomeMy WebLinkAboutCHANGE ORDER NUMBER 1 BEAMS CONSTRACTING INC
.
&4Jf.. ~j
. (/
DISTRIBUTION:
CHANGE ORDER
Owner
FAA Atlanta ADO
Contractor
LPA - Columbia
No. One (1)
PROJECT:
Augusta Regional Airport
Augusta, Georgia
Augusta Aviation Commission
1501 Aviation Way
Augusta, Georgia 30906
Beam's Contracting, Inc.
2335 Atomic Road
Beech Island, SC 29842
DATE OF ISSUANCE:
July 5, 2007
OWNER:
(Name,
Address)
CONTRACTOR:
OWNER'S Project No.
ENGINEER:
THE LPA GROUP INCORPORATED
P.O. Box 5805
Columbia, SC 29250
CONTRACT FOR:
FAA. A.I.P. Project No. 3-13-0011-26
Runway 17-35 Safety Overrun Improvements Project
ENGINEER'S Project No.
CC209026.4e
You are directed to make the following changes in the Contract Documents.
Description: See Attachment 'A'
Purpose of Change Order:
See 'Attachment 'A'
Attachments: (List documents supporting change)
Attachment 'A',
Summary of Final Quantities
CHANGE IN CONTRACT PRICE:
CHANGE IN CONTRACT TIME:
Original Contract Time
Original Contract price
$
355,996.75
55 Calendar Days
days or date
Net change from previous Change Orders
Previous Change Orders No.
o
to No.
o
$
0.00
o Calendar Days
days
Contract Time Prior to this Change Order
Contract Price prior to this Change Order
$
355,996.75
55 Calendar Days
Net Increase (decrease) of this Change Order
Net Increase (L'n"uflii) of this Change Order
$
8,038.91
o Calendar Days
days
Contract Time with all approved Change Orders
Contract Price with all approved Change Orders
$
364,035.66
55 Calendar Days
days or date
.J
APP~O'tP. :
Q fJPt LJG;l;I, Y
fJ T -~
DATE: 0( (,g 01
RECOM~ED~
by ~ r9c/1J
;/f/rr-
-
by
DATE:
DATE:
Co actor
'1/ fO (o[
ATTACHMENT "A"
CHANGE ORDER NO.1
Augusta Regional Airport
F.A.A. A.I.P. Project No. 3-13-0011-26
Runway 17-35 Safety Overrun Improvements Project
The purpose of this change order is to adjust all quantities to reflect the as-built final quantities as paid in the final pay
request and as shown on the attached Summary of Final Quantities
SUMMARY OF CONSTRUCTION COSTS
Original Contract Amount
Change Order No.1 Final Quantity Adjustment Amount
$355,996.75
$8,038.91
FINAL AS-BUILT CONTRACT AMOUNT
$364,035.66
TOTAL INCREASE DUE TO CHANGE ORDER NO.1
$8,038.91
,
OWNER
AUGUSTA-RICHMOND COUNTY AND AGUSTA AVIATION COMMISSION
1501 AVIATION WAY
AUGUSTA, GEORGIA 30906 FINAL QUANTITIES
CONTRACTOR AND ADDRESS I. CONTRACT AND DESCRIPTION I
RUNWAY 17-35 SAFETY OVERRUN IMPROVEMENTS PROJECT
BEAM'S CONTRACTING, INC. AUGUSTA REGIONAL AIRPORT
2335 ATOMIC ROAD THE COUNTY OF AUGUSTA-RICHMOND
BEECH ISLAND, SC 29842 FAA AlP 3-13-0011-26-2003
ITEM ITEM DESCRIPTION
NO. ESTIMATED FINAL FINAL %
UNIT QUANTITY UNIT PRICE QUANTITY AMOUNT COMP
2 Mobilization L.S. 100% $79,000.00 100.00% $79,000.00 100.0%
01000
1 Supplementary Insurance Provisions l.S. 100% $2,360.00 100.00% $2,360.00 100.0%
00800
3 Barricades l.S. 100% $6,750.00 100.00% $6,750.00 100.0%
01530
4 Asphalt Pavement Removal S.Y. 1,350 $5.85 1,350.00 $7,897.50 100.0%
S-140A
5 Storm Drain Pipe (15" -18") Removal L.F. 36 $8.50 60.00 $510.00 166.7%
S-140B
6 Remove Existing MAlSR Equipment l.S. 1 $3,500.00 100.00% $3,500.00 100.0%
S-140C
7 Unclassified Excavation C.Y. 12,000 $10.00 11,809.83 $118,098.30 98.4%
P-152A
8 Unclassified Excavation - WASTE C.Y. 500 $15.00 1,344.83 $20,172.45 269.0%
P-152B
9 Crushed Aggregate Base Course C.Y. 300 $50.25 300.00 $15,075.00 100.0%
P-209
10 24" Class III RCP L.F. 56 $55.75 56.00 $3,122.00 100.0%
D-701A
11 Type III Rip Rap TON 75 $73.15 34.98 $2,558.79 46.6%
D-753
12 Temporary Silt Fence L.F. 1,500 $6.00 1,500.00 $9,000.00 100.0%
E-893
13 Temporary Erosion Control Matting S.Y. 6,000 $4.15 5,998.00 $24,891.70 100.0%
E-895
14 Grassing and Mulching ACRE 12 $1,800.00 12.00 $21,600.00 100.0%
T-901
15 Onsite Topsoil C.Y. 8,250 $6.00 8,250.00 $49,500.00 100.0%
T-905
FINAL AMOUNT
$364,035.74
ORIGINAL CONTRACT AMOUNT
$355,996.75
QUANTITY OVERRUN
$8,038.99