HomeMy WebLinkAboutCHANGE ORDER NO 14 MCKNIGHT CONSTRUCTION AUGUSTA REGIONAL AIRPORT . . j , ~ . . '- i / , I TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 14 June 7, 2007 MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: See Attached Change Order # 14 Summary Original Contract Sum.. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ..$ 25,254,192.45 Change by Previous Change Order.................. ...$ 471,815.61 Contract Sum Prior to this Change Order...... . . . . . ..$ 25,726,008.06 f- This Change Order... . . . . . . . . . . . . . . . . . . . . . . .: .. . . . . . . . . . . $ 402,812.17 New Contract Sum ........................................$ 26,128,820.23 Contract Time will be as follows: 0 Calendar Days are added to the duration of Phase 3 and the Total Contract Duration Signed by: ~ onstruction Co., Inc. The LP A Group, Inc. Ju ^-It 28 2007 DATE g ~lli Regio al Airport b . 27 .01 DATE ~ "11,~liJ7 1)Of Augus DATE Must be signed by Construction Manager, Architect, Owner. Mayor and Contractor Cc: All Signers j A Hotel/Bank Demolition Change Order #14 Summary June 7, 2007 Quantity Unit Unit Cost ($) Total ($) Time Extension (Days) LS $402,812.17 $402,812.17 0 Total $402,812.17 $402.812.17 0 Item No. Item Description S:ICM FileslCO 14 Hotel/Bank Sitework Demolition Rev. 1 (April 16, 2007) Item Description Quantity Units Cost/Unit Labor Material Subcontract Cost Cost Cost Abatement Costs - Hotel/Bank 1 LS 66000 0 0 66000 Demolition Costs - Hotel/Bank 1 LS 226075 0 0 226075 McKnight Working Foreman 120 HRS 25.6 3072 Silt Fence - Required 4000 LF $4.54 $0.00 $0.00 $18,160.00 Construction Fence - Required 2000 LF $6.00 $0.00 $0.00 $12,000.00 TopsoillHotel- Required 1503 CY $18/$5 $0.00 $27,05400 $7,515.00 Topsoil/Bank - Required 378 CY $18/$5 $0.00 $6,80400 $1,890.00 HydroSeed - Required 6 AC $2,00000 $0.00 $0.00 $12,000.00 Subtotal $3,072.00 $33,858.00 $343,640.00 McKnight Mark-Up (15%) $460.80 $5,078.70 McKnight Mark-Up (7%) $0.00 $000 $24,054.80 Bond (1.2%) $5.53 $467.24 $4,412.34 Total- Required $3,538.33 $38,936.70 $372,107.14 $414,582,17 Cost Savings Options Option #1 . Use On-Site Fill Fill MateriaUHotel- USE ON-SITE 4555 CY $6.00 $0.00 $0.00 $27,330.00 Fill MateriallBank- USE ON-SITE 1148 CY $6.00 $0.00 $0.00 $6,888.00 Subtotal $34,218.00 McKnight Mark-Up (7%) $2,395.26 Option #1 Added Costs $36,613.26 Option #2 - Remove Stone Base Remove Stone Base 10000 CY $4.00 $0.00 $0.00 $40,000.00 Subtotal $40,000.00 McKnight Mark-Up (7%) $2,800.00 Option #2 Added Costs $42,800.00 Option #3 . Eliminate Access Road Estimated Savings LS' 11 000 0 $0.00 $11,000.00 Subtotal $11,000.00 McKnight Mark-Up (7%) $770.00 Option #3 Cost Savings $11,770.00 Option #4 . Eliminate Bank Abatement/Demo Bank Demo Cost Estimate 1 LS $9,000.00 $0.00 $0.00 $9,000.00 Subtotal $9,00000 McKnight Mark-Up (7%) $630.00 Option #4 Cost Savings $9,630.00 The Least Expensive Option Selection would be to perform the Required Work ($414,582.17), Eliminate the Access Road ($11,770) and Eliminate the Bank Abatement and Demo. ($9,630) Best Cost = The recommended option would be to perfonm the Required Work Recommended ($414,582.17) identified above and accept Option #3 (11,770) to eliminate the Cost = Access Road $393,182.17 $402,812.17 Uq/~J/~UUi ~D.UD rAA IUD ODd ~U~L lnLI\H I \:JUl. L"\\~''l,.; l...Ul',:) 1 4:!:JUUl/VVu McKnight Construction Co., Inc. GENERAL CONTRACTORS William D. McKnight - President Mason McKnight, HI - Vice President Huey E. Carter - Sec. - Treasurer FOUNDERS: Mason McKnight, Sr. 1900-1973 Mason McKnight, Jr. 1930-1994 P. O. Box 204718 Augusta, Georgia 30917 Office Phone: [706] 863-7784 Fax: [706] 863-2031 April 13, 2007 {FE NIUlfberI Parsons Brinckerhoff Construction Services Inc. 1510 Hangar R~ Suite A Augusta. GA 30906 Atin: Matt McCoy RE: AUGUSTA REGIONAL AIRPORT Cost Propostll HtItel tliid /Jimk DemoIititm ( RevisioIJ) Gentlemen: Per your request, the following is a revise cost proposal for the work involved for the Hotel and Bank demolition. This revised price includes the Hotel demolition, and all associated ~ however; it excludes any Bank demolition, constmction oftbe access ~ and the haul-in fill to create the sloped finish grade shown by LP A Basiailly, the CODtractorwill remove the buiIdin& parking,. as shown, and leave the site level. Four inches of topsoil will be installed, and this site will be hydroseeded. Ross &. Logan Additional si:tework ( see breakdown) Subtotal McKnight 1% OIP Subtotal 1/2% Bond Total $212,075.00 93,154.18 $365,229.18 25,566.08 $390,795.86 4,689.55 $395,485.41 RECEIVED 1 6 ZOu7 Please call if you ~ any additional information.. Sincerely, MCKNIGHT CONSTRUCTION CO., me Poi ;JoJ;wJ/~~- Pat Patrick Project Manager PP:sdr cc: Jobsite pat041307. wpd U't/.Lu/'::'U\11 ..LU.VU rot\..:\. IVU UUd ~VUl m l...l\.n J UIL Ln............... \..Iun~.J J ~ V"'~I '\./VU 04/12~2007 '1.13 FAX 9043789747 ROSS AND LOI3At~ [4]001/001 , , Ross &- LOGAN INDUSTR/~5 v7a Facsimile (706) 868-7516 April 12,2007 McKllight Construction Co., !nc- Post Office Box 211900 Augusta, Georgia 30917 Attention: Pat Patrick RE: Hotel and Bank DemGlition Augusta Regional Airport Augusta, Georgia ""Revised Proposal" Ross & Logan Industries, Inc. is pleased to provide you v..'ith'this proposal for demolition. removal and disposal as per drawing no.'s DM1, DM2 andDM 3, by The LPA Design Group, Inc., at the above~ referenced project for a. total lump sum price of $292,075.00. This price is inclusive of labor. supervision, equipment and materials necessary to complete OUI' scope of work. Pl'ic.e breakdown; Hotel $206,075.00 \ , Ba.nk.. ~~~~" /9,000.00> ~17"2.. Dr5"~ Access Road ~. t) , ) ~ 11,000.00 I Asbestos Abatement 66,000.00 .,....... Price includes tite following: v' Removal and documentation of proper disposal of refrigerant from Ale units in buildings to be demolished v' Fill in depression from pool removal with fill dirt .;' Upon COIllpletion, rough gradinS of area. disturbed during demolition operations Price excludes the following: x Permits )C Temporary protection )C Erosion. noise andio-r dU5t control x; Protection and/or relocation of items to remain j; Backfill and/or eomps.ction .Ie Shoring and/or bracing Thank you for t..l-),e opportunity to propose Ibis service, I look forward to working with you. lfyou have any questions or concerns, please contact me at (904) 378-9700. ~~~-tfuny, /?;J /J ..--..- I ~ :Z;:~ T odd Pritchard PrQject Mani2g~ 1) e m oh t to n · R e c y cl i 11 9 " Sit e Prep 6507 West Beaver Street, Jacksonville, FL 32254 P.O. Box 61206.. Jacksonville, FL 32236 904-378-9700 904-378-9747 Fax '. V '1: f ..1.. ~.. "" v v II -1. U . V i .i.' .fl....\. I V U U U ... 24 31 32 -&:,' J' "'B "' -. -'" _Jl~r.8IDn.R. Timl,4.,....o1){',4 Eye-t:.Me. "" 45-J()4 2 - Pad, ~ \ &afi'vl ~l'o l,' . \M ~ ..z V~s.c..t,..l - I'C l r~) ~_, \ . L OS "\ ~;... iLa., \!.Cl..Q \AM ~ 11 I 2 [I: 4~ "" ; .(,. l t .It -<.iN IV 3 I I ~ 12~ l..f to'lt'S"t t-UU:..z @ 51 I _ , . 61i 2~~ S-{ I A50kLt- R'f'~'V @. 7 I I I \ L $' f)-epot'V .tIvt\.4,'jfr\ C.' I I U I I 10 G; k. f,Vle. ~ -SAe T 1- ,-~ .... - wi . i ! : 4- ~ (po.::: I I . , , t: \.-zl:l"/s" ,I I :~. , ii, l:v.....s I I: i ~O:() I ! ' I ; : j ! i3 OOD: I ! I : , ; Li t[~bo! I I i, , I ! @ looD ~ I 12 Ii lto 1r.l"s, \'it L-l. LUrnk;v\,-, .\-v-t-!.Vt\'-\M ~ U 1311 I ..J I 14\, i i JO~:( ::11/5.1:;1 ~ rO+-tO I'Z:~.,,~F.,;' .~;hi I Ii 13 Ifll"~' VfJ I, \t\jclvose.ect I 11 I i ; t" I ! I i ~ ! ; II > i ! ! 1-! i , i' I I I : ' I 17 19 2011 21 r 22 I I , I 23 33 ),1 ..* 35 i ')011 1,,' 37 i:.. ]R I' I' 39!f--i' 4CJ ; t' II : I r---r- I /" ( M C:~t ",'v,* 'J ~ L.) II i ! I I i I 2 I I Ii .J H II I ! ! rl s i ; I ' !ZOIDioio: . : ( : \ iZ 0:0:0; , , i I I r :"jpbb' i : I I , , i ..jls;o:Q I :' ~ i : i : I i I!' ! : r------~ '-.._~.. ' i 1';00 I I' .,~ i I ' , I , , i :1 .g I !~ "eI v..'~~ v..,~ . I ( 41 \";j 0 7 j Pre-pared B\l j : Approved By ! i I i I I : ! I I It Ii: r I ; ; lnilia~s i 03tE ,1 T , i ! i ! i: ! I ' , I Ii II I [ I I i2 i ,14 , 5 , i ; j , I . i i i : :, i: i I; ; I I ' I ,---1 8 : !! i 9 ; .!; !!; 1-1W1!~~~ ~: ! i 'i I '! j I : i : : i i I' , I : : I ; i i i j i I 1~1 I Iii I 1 i ' , I I ! I ! , ! l J ! ., , i I ' ! ; I 'I i:! !! Ii! , i i ! I . 110 I ; ! j1 I :; ! 1) I , , ; i I I I :j:: ' i.z.o; ~ ' (;'2 oplO; ---r+- I TTI ' ! i I;j': --T-.-';' ,!! ! :, I, i I I j; I i ! ! ! ; ! ! I Ii: ! ; Iii ,I' ! i! I ' : I II ; i~ qbirl ~ -LzRbs~ ~ i~~B l!51 2~ '} I ,i} rrh! rJf!: :,.,1, '-:>bfl,S II i J..; I _ Ii -1-1 I .p::>I'::', -hi f.t, :.QD ~._, II I' 2511 II ! : ~S-5Z I igi\-bSl;'1jl I :5:415:i S: 26 II I ![+-Ll I I,' _:' I [':+! 27 II I I,. I I: !', , 28-Hi i;' ,'f-IH~' I i i-t- 29 ! -~ ~-+--t-H-lil I i 't ,~~ l-l1:t: j 30 ! l' !\loTe " i i i ii',. : I':! : ' f1 i"'iII,"; b....etJ..V~~,h'\ A.oe ~f; i i\..krtJ)~~ : "m' . . . l1tw" ~ \'1 t:.Jg 1 ~I ' b 'I ; : <:: i i i i ~ I;, it I : I ' 'S :'r-P -to c..V&I-.-\-e.., e.VVl'\. Aj,,:: VldJft\ ,~,), t.,..ft,;-. I i, ',' I , { I . , -~ if"T----:-y -- r-rt- i t ~ p"\'ce.. ~t; v1.f,T i lI\cG .o..~(~t..v i :.'st)V'.~~.~ t _~: _-t11._. ','^'1 ...... ...... .: i I r I '" ., ' .' II j t ,. " f-~ '-T ' , i, A -OI4,,"5.t~Vv, OCMV~; ,(,. :t~4-1 i i~ I ~rr tlJJ- il'. i ' ! , : i , .-J -' \ .JI" I, 'I' ',f ' I i!I' !i ! l! !: !. 1 ~ 1 I ' : IiI Ii; ! II! '. ,;' 'i Ii. Ii:. i ',' i. I; jl L~-~---H-'-'~ ! 'I ' i; I !i'.' I L i' !': I ii I ;1 -1~-'__IL-I' 1 I I ! Jj :--r- ,T' ;-t=til ~'=tP1 I:; I I I' I ,-- '!--.;---:, -. "-~I- "i , !"'"III I., .-~.'--'. ' .-:-1,--' .! I-~-t--'- !,~.i! I 9'.! 3';- I . , ! ' I II I': I .. III! I Ii; .::0 I-i-Tj~:-- -I-o--,-r:1' M ' I I : '!-I ~: j; '; 'tPf: I, ; : I \,~! l~;;t~5~-.,~1 i , i 12 ! i i I 13 j ! r i ! I ! ! I I 14 15 \6 17 18 , " i, I f9 i : 20 i ! 21 : i I 22 23 26 27 : i I i I ! I 128 'I 1[29 ,- 130 I 13 ) ~') ! J~ 33 34 I:: , ~,; .". 38.. ~f~~ ~..'O!~(:Ji/A Public Service Committee Meeting 5/7/200712:30 PM Airport Hotel/Bank DemolitionGost~ c.\.-{b.;~c.G ottoa.. Department: Caption: Background: Analysis: Financial.lm pact: Alternatives: Recommendation: Funds are Available in the Following Accounts: Augusta Regional Airport Request approval of the cost regarding the airport HotellBank Demolition. The Augusta Aviation Commission requested a cost for demolition and redevelopment of the property where the hotel and bank buildings are located. This was not included in the original cost for the new terminal construction. Due to the condition of the existing facilities of the hotel and bank buildings on airport it was decided that the property would be better utilized as additional parking for airport customers which would increase revenue for the airport. $402,812.17 is the recommended cost for demolition and will be funded 50% from customer facility fees and 50% from Airport Capital Improvement Fund Deny the request. Accept the recommendation of the Augusta Aviation Commission to approve the cost of the airport HotellBank Demolition. 551081301/5411110 REVIEWEIlAND APPROVED_Ity: ~ ~ Office OfTbe Administrator A Frederick L. Russell, Administrator Tameka Allen, Interim Deputy Administrator Robert Leverett, Interim Deputy Administrator Room 801 - Municipal Building 530 Greene Street - AUGUSTA, GA. 30911 (706) 821-2400 - FAX (706) 821-2819 www.augustaga.gov May 15, 2007 Mr. Willis Boshears Director - Augusta Regional Airport 1501 Aviation Way Augusta, GA 30906 Dear Buster: The Augusta-Richmond County Commission, at their regular meeting held on Tuesday, May 15, 2007, approved of the cost regarding the airport Hotel/Bank Demolition. (Approved by Public Services Committee May 7,2007) If you have any questions, please contact me. cc: Ms. Donna Williams 05-15-07: #8