Change Order Form
.'
Change Order Number: Four Date: 03/09/04
Project Title ARC Drainage Improvement Phase I
Original Contract Date: 1-05-04 Project Number:. 323-04-201823101
Owner: ARC P.O. Number: P84060
Contractor: Beams Contracting
The following change order is hereby made to the proposal for the above project:
See Attached
TOT AL AMOUNT OF THIS CHANGE ORDER
$ 3,607.45
The Contract time will be Increased/Decreased by ~ calendar days as a result of
this change. The date of completion including this change order is. 7-22-04
Date: 3- /tJ--O'f-
Date: 3- (~~{)1
Date: "3) o-f 0 y
.
Date: J/~/'Y
Date: ~r'ftf
.
Date: J -- // - t:J<7
Original Contract Amount
Previous Change Order
(Increased 1 Decreased)
This Change Order
(Increased 1 Decreased)
TOT AL CONTRACT WITH CHANGE ORDER(S)
*************
Funding Sourcel Account Number:
Requested By:
Submitted By:
Approved By:
Accepted By:
COPIES: Errick Thompson, P.E. Assistant Director-Engineering
Purchasing, Geri Sams
Kakoli Basu, Accountant, Public Works
Pre Construction File
$ 931,575.75
$ 83,309.50
$ 3,607.45
$ 1.018.492.70
.~
Field conditions prevented the concrete slope paving tie-in at the existing double 72" RCP. In order to
prevent the taking of several trees and maintain the aesthetics of the entire project, a vertical Class A
Concrete, Including Reinforcing Steel was added. The addition of this wall allowed us to reduce and/or
eliminate other items.
ADDITION OF: 19 CY OF RETAINING WALL @ $934.55/CY
$17,756.45
TOTAL ADDITIONS
$17,756.45
DELETIONS OF:
1) CONCRETE DITCH PAVING..... ....................................... .$3,477.00
2) GRANITE CURB ............................ .................. ......... .....$. 480.00
3) SANITARY SEWER, 12 INCH.......................................... ..$4,200.00
4) CATCH BASIN, GP. I ....................... .............................. .$1,782.00
5) SANITARY MANHOLE................... ,............................... .$1,660.00
6) SANITARY DROP MANHOLE......................................... ..$2,550.00
TOTAL DELETIONS
$14,149.00