HomeMy WebLinkAboutCHANGE ORDER 9 MCKNIGHT BUSH FIELD TERMINAL
~r 1
,
MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS:
RECEIVED
TERMINAL AREA IMPROVEMENTS
AUGUSTA REGIONAL AIRPORT AT BUSH FIELDacr '9 2006
CHANGE ORDER NO. - 9 ~l~GnDl1P
September 26, 2006 ~'ffi1\T81)
ftOUdf.ifBIA ([JFrF:/CE
See Attached Change Order #9 Summary
Original Contract Sum ................................. ..$
25.254,1 92.45
Change by Previous Change Order.................. ...$
228.052.75
Contract Sum Prior tg this Change Order... . . . . . . . . ..$
25.482.245.20
This Change Order. . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . .. . . . . . . $
47 .906.62
-f
New Contract Sum ....................................... $
('
25.530.151.82
.~
Contract Time will be as follows: 0 Calendar Days are added to the duration of Phase 3:'
and the Total Contract Duration
Signed by:
C'\{~
'ATE The LP A Group, Inc.
10.'0.0(.
DATE
i(/~ (vf,?
DATE
Must be signed by Construction Manager. Architect. Owner. Mayor and Contractor
Cc: All Signers
S:ICM FileslCO 9
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President'
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
September 19,2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: AUGUSTAREGIONALAIRPORT
PR57
Gentlemen:
In response to your letter dated 5-23-06, the following is a credit amount not to install the water and
toilet for the rental car trailer.
The estimate is based on pumping the holding tank once a week, for (12) months. Also, the water
line would have been an insulated garden hose.
Pump holding tank $155.00/mo X 12 months
Misc. fittings, hoses, etc.
Total credit
$1860.00
100.00
$1960.00
Please issue a change order.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
Ped pcdJud0 /&etu
Pat Patrick
Project Manager
PP:sdr
cc: 10bsite
If;@lf;11'Wlf;)
i SE.? Z 1 ~""n .
rV\OI.-' .-----..
8", __J-..-.
\ . ...--
pat091806. wpd
,.
August 22, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: AUGUSTA REGIONAL AlRPORT
PR59
Gentlemen:
The following is a cost proposal from Simple Grinnell for the work required. to install the 25 pair
jwnpers to the phone block in A003.
Simplex Grinnell
McKnight 7% OIP
Subto1al
1360.39
95.23
1455.62
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUC110N CO., lNe.
Pat Patrick
Project Manager
PP:sdr
CiJ~t''?
tt"B 'j .Mt\\\j'O
C;~~ ~ t
,.,
cc: Jobsite
pat082206.wpd
SiIJJplexGrinnel1
3243 Sunset Blvd
West Columbia, SC 29169-3427
(803) 476-0000
FPV<: (803) 476-0039
www.simplexgrinnell.com
SimplexGrinnell Quotation
TO:
Mcknight Construction Co.
POBox 2Q4718
Augusta, GA 30917
Project: PR 59 Phone Block add
Customer Reference:
SimplexGrinnell Reference: 216403820
Date: 07117106
Page 1 of 3
SimplexGrinnell is pleased to offer for your consideration this quotation for the above project.
QUANTIT'C
MODEL NUMBER
DESCRIPTION
1
PR 59 Phone Block add
PR 59 Phone Block add
DPSUB SUBCONTRACTING LABOR
District Services - PR 59 Phone Block add
PM LAB PROJECT/CONSTRUCTION MGMT
2
Total net selling price, FOB shipping point, $1,360.39
Comments
Equipment and Commissioning
This quotation includes the equipment, transportation charges, and installation of the phone block
cables as directed by McKnight Construction, and all applicable taxes.
The price does not include conduit or 120 VAC power wiring to control or sub-panels,
This quotation is for the additiDn of phone block cabling to interfaoe the Bell South equipment to the
main A003 rack for the phone system.
Thank you for ttle opportunity of quoting and we hope to have the pleasure of serving you.
THIS QUOTATION AND PJtJ.Y RESUL TlNG CONTRACT SHALL BE SUBJECT TO iHE GENERAL TERMS AND CONDITIONS A TIACHED HERETO.
I='ir.:o ,c;:;'::>l":llritv (";nmmllnlr:",tinn~ Sales & Service
Augusta Regional Airport PR-SS
CONTRACTORS QUOTE TO SIMPlEXGRINNELL
Oe$crlptlon Qty Rate Materials MlHours Labor Rate Totallabor
50ft Amp F to M Cables 9 56.85 $511.65 12 $22.00 $264.00
Red Freight 1 48.00 $48,00 0 $0.00 $0.00
0 0.00 $0,00 0 $0,00 $0,00
0 0.00 $0.00 0 $0.00 SO.OO
0 0.00 $0.00 0 $0.00 $0,00
0 0.00 $0.00 0 $0.00 SO.OO
0 0.00 $0.00 0 $0.00 $0.00
0 0.00 $0.00 0 $0.00 $0.00
0 0.00 $0.00 0 SO.OO $0.00
0 0.00 $0.00 0 $0.00 $0,00
0 0.00 $0.00 0 $0.00 $0.00
0 0.00 $0.00 0 $0.00 $0,00
. 0 0.00 $0.00 0 $0.00 $0.00
Labor to Install ana Test
SUBTOTAL $559.65 $264.00
6 % Sales Tax (if appliciable) $33.58
23 'Yo Labor Burden 1 $60.72
Totals $593,23 $324.72
10% Overhead $59.32 . $32.47
10% Profit $65.26 $35.72
Totals $717.81 $392.91
The total ADD for this change order is $1,110.72
Total change $1,110,72
Simple>::Grinnell Costs
Labor Burden M/HouJ'S Mix Rate Total Labor
Project Management 2.60 2 $25.00 $130.00
CAD 2.60 0 $16.60 $0.00
Design 2.60 0 $23.00 $0.00
Tech I Comm 2.50 0 $0.00 $0.00
PARTS Q $0.00 SO.OO
6% Sales Tax (if appliciable) $0.00
Totals sno,OO
15% Overhead $19.50
1 5% Profit $22.43
Totals $171.93
Cummins Cost to SimplexGrinnell $1,110,72
7% markup for SimplexGrinnell on sub $77.75
Simple){Grinnell Cost $171.93
T ofal Cost
I $1,360.39f
/~~
.' .
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
August 8, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: AUGUSTA REGIONAL AIRPORT
PR66
Gentlemen:
The following is a cost proposal for the removal of the additional unforseen asbestos encountered
during the building demolition, and the removal of the contaminated soil discovered during the
removal of the underground storage tank.
Pyramid Remedial Systems
McKnight Construction 7% O/P
Total
$38,944.00
. 2,726.00
$41,670.00
Please issue a change order for this amount. The time impact for this additional work was submitted
to your office last week.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
fo:tPa/:Jwh~
Pat Patrick
Project Manager
PP:sdr
lID~@~lrW7~1ffi
1m AUG I (J 2006 ~
BY: ---!!J!!/i_________
cc: 10bsite
pat080806b.wpd
PY,RAMID.Remedial Systems, Inc.
. .
Revised Change order #1
PO BOX 1268
Alpharetta, GA 30009
(678) 366-1919, (770) 777-5981 FAX
Page...L of.1
PROJECT NAME: AUQusta Reoional Airport
PROJECT NO.: PRS - 05-354
CHANGE ORDER DATE: 8-7-06
CONTRACT: McKniaht Construction and between PYRAMID
Remedial Systems. Inc (PYRAMID) DATED 3-5-05
==================================================================================
DESCRIPTION OF CHANGE -
1. Performance and payment bond increase due to change order
Additional amount of payment and performance bond due to change order @ 2.5 % of increase in contract amount.
2. Asbestos Containing Material (ACM) abated in addition to original scope of work
Removal and disposal of approximately 2,520 SF of carpet over yellow glue over black mastic. (Contour A3)
Removal and disposal of approximately 702 SF of ceramic tile over multi layers of asbestos floor
tile and mastic. (Contour A4)
Removal and disposal of approximately 770 SF carpet over yellow glue over black mastic. .
Removal and disposal of approximately 120 SF of black mastic bebind mirrors.
Removal and disposal of approximately 500 SF of floor tile and mastic from back corridor of rental center
telephone room. (Contour AI)
Removal and disposal of approximately 150 SF of floor tile in the bar area (Contour A5)
Removal and disposal of asbestos tiles and mastic Wlder the walls while demolition was in progress.
· Maintain two (2) asbestos technicians and one (I) supervisor on site for two (2) weeks (40 hour week)
and include per diem, hotel stay, mobilization to the site, material cost, transportation and disposal of
asbestos waste to the landfill.
· Obtaining Georgia EPD approval of the process of wet demolition and extension of notification.
Additional floor tile and mastic per contour's JWle 22,06 survey and designated A2, A6, A7, A8:
Total additional abated area 654sf (see break down below)
· Removal and disposal of 288 SF of floor tile and mastic from telephone lobby (Contour A2)
· Removal and disposal of 96 SF of floor tile and mastic from mechanical room north of
The telephone lobby. (Contour A6)
· Removal and disposal of 126 SF of Floor tile and mastic from the restrooms, west of
US Airways Bag room. (Contour A7)
· Removal and disposal of 144 SF of floor tile and mastic from the Overflow men's room
( east of the terminal restrooms). (Contour A8)
Credit for designated Contour area C1, C2,C3, C4 and C5
Total additional Credited area 1286 SF (see break dO\>TI below)
· Area beneath middle section of ticketing counter, 105 SF (contour C1)
· Area at Continental baggage hallway, 72 SF (Contour C2)
· Continental ticketing area, 714 SF. (Contour C3)
· No tile, no black mastic, No removal work was conducted at US Airways
bag room, 339 SF (Contour C4)
G
$4,582.00
$3,550.00
$1,706.00
$ 360.00
$ 1,975.00
$ 455.00
$ 12,840.00
$981.00
<$1,929.00 >
PYRAMl,D'Remedial Systems, Inc.
Revised Change order #1
PO BOX 1268
Alpharetta, GA 30009
(678) 366-1919, (770) 777-5981 FAX
PROJECT NAME: AUQusta Reoional Airport
PROJECT NO.: PRS - 05-354
CHANGE ORDER DATE: 8-7-00
CONTRACT: MeKniaht Construction and between PYRAMID
Remedial Systems, lne (PYRAMID) DATED 3-5-05
Page2. of.2
----------------------------------------------------------------------------------
------------------------------------------- ----------------------------------
· Area at hallway extending west from US Airways Bag Room, 56 sf. (Contour C5)
Sub-total additional asbestos abatement and credits
3. Remediation of UST contaminated soil
Over Excavation, transportation and disposal of contaminated soil from the UST pit included:
· Management and administration of remediation activities
· Cost of Subcontractor Excavation and transportation to Sub title D landfill plus lO%
· Landfill charges on 10 tandem truck loads, plus 15%
· Cost of Backfill charge, 16 loads plus 1(11/0
· Credit to GC for backfIll covering original tank cavity in original scope of work. (one Load)
Subtotal Remediation of UST contaminated soil and credit
The above changes are hereby made to the Contract Documenb:
Total this Change Order
$ 38,944.00
Please note that previously submitted change order numbers 1,2,3 and 4 are now included in this Revised Change order #1
By authorization of this change orqer, McKniaht Construction hereby authorizes PYRAMID to perform additional work at the Above-referenced
Location.
Accepted by:
Date
(PYRAMID Remedial Systems, Inc.)
Accepted by:
Date
(McKniQht Construction)
.' .
7CXP-77/~5/'7(
McKnight Construction Co., Inc. Iy?
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, III - Vice President
Huey E. Carter. Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
August II, 2006
Parsons Brinckerhoff Construction Services Inc.
1510 Hanger Road, Suite A
Augusta, GA 30906
Attn: Matt McCoy
RE: AUGUSTA REGIONAL AIRPORT
Gentlemen:
During the building demolition, Thompson Wrecking encountered unforseen concrete from a
previous building under the Airport Terminal scheduled for demolition. Parson Brinckerhoff was
informed of this unforseen condition. The flooring are the cost for the removal of this existing
concrete.
Thompson Wrecking
McKnight 7% O/P
Total
$6,300.00
441.00
$6,741.00
Please issue a change order for this amount.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
-Pot Po1AU'L I-s~
Pat Patrick
Project Manager
PP:sdr
cc: lobsite
1m IT: @ IT: TI"W lli: W
lli1 AUG 1 4 2006
B Y: __~p.~_._---,.<
pat081106.wpd
:. ....
HIRAM E. THOMPSON
President
GLEN F. THOMPSON
Vice President
THOMPSON BUILDING WRECKING CO~, ~NC.
631 Eleventh Street
P.O. Box 932
Augusta, Georgia 30903
Phone (706) 722-1432
Fax (706) 722-4253
Commercial
Demolition
Equipment Rental
Grading / Clearing
August 10, 2006
TO: PAT PATRICK
McKNIGHT CONSTRUCTION CO.
FROM: HIRAM E. THOI\1PSON
REQUISTION NO. 081106
AUGUSTA REGIONAL AIRPORT DEMOLITION CONTRACT
During the last demolition phase of the Augusta Regional Airport in July 2006,
Thompson Building Wrecking broke out, trucked away and disposed of (28) 20 yard
loads of additional concrete per the superi.ntendent's request. It was agreed that We treat
this as an extra.
28/20 YARD LOADS OF CONCRETE @ $225.00 PER LOAD............ .$$6,300.00
~~~
Hiram E. Thompson