HomeMy WebLinkAboutCHANGE ORDER 13 MCKNIGHT CONSTRUCTION TERMINAL AREA IMPROVEMENTS BUSH FIELD " TERMINAL AREA IMPROVEMENTS AUGUST A REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 13 June 7, 2007 / MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: See Attached Change Order #13 Summary Original Contract Sum ...................................$ 25,254,192.45 Change by Previous Change Order............... ... ...$ 374,158.24 Contract Sum Prior to this Change Order...... .......$ 25,628,350.69 ~ This Change Order............. . . . . . . . . . . . . . . . . . . . . . . . . . . $ New Contract Sum ... ... ............ ......... ............$ 97.657.37 25,726,008.06 ~ Contract Time will be as follows: 12 Calendar Days are added to the duration of Phase 3 and the Total Contract Duration Signed by: ~ . 'f' t..c2?l!1nstruction Co., Inc. uM1E The LP A Gronp, Inc. I Y(O 7r) cJ4 f/ f\TE ~:l1J ~ c. Z? 6 , DATE ~ It1'/oL "]) ~re- Must be signed by Construction Manager, Architect, Owner. Mayor and Contractor Cc: All Signers