HomeMy WebLinkAboutCHANGE ORDER 13 MCKNIGHT CONSTRUCTION TERMINAL AREA IMPROVEMENTS BUSH FIELD
"
TERMINAL AREA IMPROVEMENTS
AUGUST A REGIONAL AIRPORT AT BUSH FIELD
CHANGE ORDER NO. - 13
June 7, 2007
/
MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS:
See Attached Change Order #13 Summary
Original Contract Sum ...................................$
25,254,192.45
Change by Previous Change Order............... ... ...$
374,158.24
Contract Sum Prior to this Change Order...... .......$
25,628,350.69
~ This Change Order............. . . . . . . . . . . . . . . . . . . . . . . . . . . $
New Contract Sum ... ... ............ ......... ............$
97.657.37
25,726,008.06
~ Contract Time will be as follows: 12 Calendar Days are added to the duration of Phase 3
and the Total Contract Duration
Signed by: ~ .
'f' t..c2?l!1nstruction Co., Inc. uM1E The LP A Gronp, Inc.
I Y(O 7r) cJ4 f/
f\TE ~:l1J
~
c. Z? 6 ,
DATE
~ It1'/oL
"]) ~re-
Must be signed by Construction Manager, Architect, Owner. Mayor and Contractor
Cc: All Signers