Additions and Renovations to the Webster Detention Center
Description of Change Enhanced Base of Security Fence (CCR 6l & Required Revisions to Existing Roof Storm Drainage (CCR 17)
to the Scope of Work:
Project Duration:
Number of Days added to the Substantial Completion Date as a result of
this Change to the Scope of Work:
0 Days
$ 27,041,000.00
$ 6,113,118.58
$ 33,154,118.58
$ 55,753.33
$ 33,209,871.91
Contract Amount
Original Contract Amount
Previo!,is 'Change Orders
Previous Contract Amount
Amount of this Change Order
Current Contract Amount
All terms and conditions of the Contract Agreement between the Owner
and the Contractor apply to this Change .Order.
Signatures:
Ag-pU:.t-
Pat Patrick
Project Manager
~
G . on, rchitect
0( ~ loq
Date
~ oh/1e/Oo,
Date '
Recommended for Acceptance by Project Manager:
N~
66-tO'OY
Date
Recommended for Acceptance by Program Manager:
HP::2ti~
Bob Munger, Program Manager
Date{,/7/0~
Recommended for Acceptance by The Owner:
Captain Chester Huffman
WDC Jail Administrator
Date
t 1r~1
Da ,
Page 1 of 1
Cost Event
Page 1 of 1
H~ "E'-E"'K Y....
'... I f~' ,/
",.,r! .. .,' ....r __~ q...~_~_ .}., ",_.._ ,_
Cost Event
Project [0400101 - Task 07] - ARC - Task 07 - Webster
Detention Center
View Date 6/5/2009
Heery International Inc. (Augusta, GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
Cost Event No. 004
Date
Type
Description
1/30/2009 Budget Status
Owner Directive/Request ,. Cost Status
~evislons to Security Fencing & Existing Roof Drainage
New
New
Responsible
Pat Patrick
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Initiated By
Bob Munger
Heery International Inc. (Augusta, GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
Funded By
Initial Estimate
Expected Final
$50,000.00
$55,753.00
(0.00 days)
(0.00 days)
Long Description Enhanced security of base of inner security fence, and required revisions to existing roof storm drains.
Scope of Work
1. extend fence fabric 6" into trench and backfill with compacted crusher run (CCR 6)
-.
2. Revisions to roof drainage as per ASI 4. (CCR 17)
Items
No. Budget
Code
1 6011110
Contact
Revisions to
Base of
Security
Fencing
Description Estimated Proposed Submitted Approved Committed Budget Cost
Status Status
- other Pending
$22,000.00 $33,488.88 $21,227.56 $21,227.56
2 6011110 Pat Patrick (McKnight Revisions to
Construction Existing Roof
Company) Drainage Per
ASI4
- $34,525.77 $34,525.77 $34,525.77
- Pending Pending
Estimated Proposed Submitted Approved Committed
Items $22,000.00 $68,014.65 $55,753.33 $55,753.33
Markups
Total $22,000.00 $68,014.65 $55,753.33 $55,753.33
http://heery.constructware.com/Common/View/Document_ Display .asp?DocumentType= 1 &... 6/512009
Contractor Change Request
Page 1 of 1
NCK
Contractor Change Request
Project [0400101 - Task 07] - View Date 6/5/2009
ARC - Task 07 - Webster
Detention Center
McKNIGHT CONSTRUCTION
COMPANY; INC
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Contractor Change
Request No. 00006
To
Submitted By
Description
Bob Munger (Heery International Inc. (Augusta, GA))
McKnight Construction Company Date
Revised Proposal Embed Fence Fabric Status
State
Referenced CCO No.
2/27/2009
Processed
Submitted
Estimated Effects of Request
ITime
Amount
10 days
$22,274.84
Work Description
Embed Fence Fabric@ inside fence only. Two prices are submitted,
embed fabric in crusher/run, and embed fabric in concrete.
Recommendation
Issue a change order for this proposal
Response By
Response
Bob Munger
Expect quick approval if less than $20K.
Linked Documents
Document Type Document
Doc 0400101 - Task 07-00385
Description
Revised Embed Fence Fabric
http://heery.constructware.comlCommonIView/Document-Pisplay .asp?DocumentType=33 ... 6/5/2009
McKnight Construction C~., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight. III - Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706] 863-2031
February 24, 2009
Heery International
Attn: Bob Munger
RE:Webster
Cop/BUry Fence Bottom (Revised)
Mr. Munger,
The following are (2) cost proposal options to install the perimeter security fence fabric in the ground 6",
only for the inside fence.
Option 1: (Bury fabric/ backfill crush/ run)
Maner Fence $21014.00
McKnight Construction 6% O/P $1260.84
Total $22274.84
Ootion 2: (Bury Fence/ Backfill 2500 psi concrete)
Maner Fence $20026.00
McKnight Construction 6% DIP $1201.56
Total $21227.56
Please review the proposal and issue a change order for this work. Call me and the office if you need to
discuss this matter.
Sincerely,
MCKNIGHT CONSTRUCTION CO. INC.
+>Oxq}l
Pat Patrick
Project Manager
pp; kdr
CC: Jobsite
02/27/2009 13:11 FAX 7064342520
MANER FENCE
QUOTATION FORM
MANER FENCE AND SPECIAL TIES CO.
Fence Sales
3801 Martinez Blvd. P.O. Box 2045989 Augusta Ga. 30907 Phone 706-434-3717
To: McKnightConst.
Job: Webster Detention Center Temp Fence
Attn: Pat
Fax # 706-863-2031
02/27/09
Quoted By: Chris Davis
Augusta Office
706-434-3717
We propose to fnrnish labor, materials and equipment required to do the following:
Change order for installing fences 6" in ground
Option (1) Bury appox 3,800 If of chain link fence (inside fence only) in a 6" wide x 8"
deep trench pouring 2500 psi concrete.
Material: $ 6,107.00 @ 15%
Equipment: $ ] ,098.00 @ 15%
Labor: $ 9,818.00 @ 15%
Total: $ 7,184.00
Total: $ 1,292.00
Total: $ 11,550.00
Total installed: $ 20,026.00
Option (2) Bury approx 3800 If of chain link fence (inside fence only) in a 6" wide x 8"
deep trench backfilled with crush & fill.
Material: $ 2,314.00 @ 15%
Equipment: $ 1,098.00 @ 15%
Labor: $ 14,450.00 @ 15%
Total: $ 2,722.00
Total: $ 1292.00
Total: $ 17,000.00
Total installed: $ 21,014.00
Exclusions: Bonds, core drilling, clearing/grading. underground utilities, grounding,
privacy slats.
Addenda included as follows: _n/a
TERMS: Net Thirty Days with approved credit.
141 002/003
02/27/2009 13:11 FAX 7064342520
MANER FENCE
141003/003
THIS QUOTATION good for 30 days unless otherwise indicated.
We do not accept responsibility for delayed shipments or deliveries occasioned by strikes, fires, accidents.
delays in common camers or other causes beyond our control including delays in receiving materials or
parts obtained from outside carriers.
ACCEPTANCE:
Maner Builders Supply
Fence Division
Contractor Change Request Page 1 of 1
NCK
Contractor Change Request
Project [0400101 - Task 07] - View Date 6/5/2009
ARC - Task 07 - Webster
Detention Center
McKNIGHT CONSTRUCTION
COMPANY, INC.
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Contractor Change
Request No. 00017
To
Submitted ,By
Description
Bob Munger (HeerFInternational Inc. (Augusta, GA))
McKnight Construction Company Date
WDC ASI 4 - Revisions to Roof Drainage Status
State
Referenced CCO No.
5/28/2009
Processed
Submitted
Estimated Effects of Request
ITime
Amount
10 days
$34,525.77
Work Description
Revisions to Roof Drainage at G (A) and D Pods per ASI 4
Recommendation
Response By
Response
Bob Munger
Linked Documents
Document Type
Doc
Document
0400101 - Task 07-00766
Description
Webster 5.28.09 CP ASI 4
http://heery.constructware.com/Common/View/Document_Disp1ay .asp?DocumentType=33 ... 6/5/2009