HomeMy WebLinkAboutCHANGE ORDER #5 MCKNIGHT WEBSTER DETENTION $120,652.30 ~ RECEIVED R'S OFFICE 5 June 4, 2009 Contractor: McKnight Construction 635 NW Frontage Road Augusta/GAl30907 Project Description: Additions and Renovations to the Webster Detention Center Description of Change Mise Unforeseen U/G Utilities & Earthwork; incl CCR 9, 10, 11, 13, 14 & 15 to the Scope of Work: Project Duration: Number of Days added to the Substantial Completion Date as a result of this Change to the Scope of Work: Contract Amount Original Contract Amount Previous Change Orders Previous Contract Amount Amount of this Change Order Current Contract Amount All terms and conditions of the Contract Agreement between the Owner and the Contractor apply to this Change Order. Signatures: ~'~I!a; . ~ , lt~ Pat Pa rick Project Manager N Recommended for Acceptance by Program Manager: _IS)') M ~ Heery Internation'al V Bob Munger, Program Manager Recommended for Acceptance by The Owner: Page 1 of 1 2009 04001-07 AUGUSTA.RICHfv OND COUNlY Reference: COP# 9,10,11,13.14, 15 30 Days $ 27,041,000.00 $ 5,992,466.28 $ 33,033,466.28 $ 120,652.30 $ 33,154,118.58 ro/4/0L Date DG~04,04 Date ao -oL{~ 09 Date &/4-/0'L Date ' 0'/0 y/W() 7 Date . f jr)l Date Cost Event Page 1 of2 H"'E""E"'RY j , , , :~ \ .: . ! ,.i .', ...~.! ,'. .; '. '/ Cost Event Project [0400101 - Task 07] - ARC - Task 07 - Webster Detention Center View Date 6/4/2009 Heery International Inc. (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 Cost Event No. 006 Date Type Description ~e$ponslble Funded By Long Description Scope of Work 3/2/2009 I$udget Status Field Condition Cost Status Misc Unforeseen U/G Utilities & Earthwork Pending Pending Pat Patrick McKnight Construction Company 645 Frontage Road NW P.O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Initiated By Bob Munger Heery International Inc. (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 Initial Estimate Expected Final (10.00 days) (30.00 days) $100,000.00 $125,743.00 Miscellaneous unforeseen site work Includes the following CCR's: 9 - Abandon in Place Inactive Water Line Below MMH and Plug .Ends 10 - Credit for Revisions to Storm Drainage 11 - Remove Unforeseen Sanitary Manhole 13 - G Pod U/G Plumbing Changes due to Varying Field Condition (Invert elev.) 14 - Offset of Existing 10" Water Line to Avoid SD Conflict 15 - Haul in of Fill Dirt due to Unsuitable Soils Also includes Cancellation of Change Order No.3 Work (CCR No.4) Items No. Budget Contact Description Estimated Proposed Submitted Approved Committed Budget Cost Code Status Status 1 5413130 Pat Patrick (McKnight Revisions to ($7,335.00) ($7,335.00) ($7,335.00) Pending Pending Construction Storm Company) Drainage Design 2 6011110 Pat Patrick (McKnight Revisions to $11,610.65 $18,628.18 $18,628.18 - Pending Approved Construction Water Line Company) to Avoid Conflict with Storm Sewer 3 5413130 Pat Patrick (McKnight Cancellation ($18,907.69) ($18,907.69) ($18,907.69) ($18,907.69) - Pending Pending Construction of Change Company) Order 3 (CCR No.4) 4 6011110 Pat Patrick (McKnight Remove $1,123.55 $1,123.55 $1,123.55 $1,123.55 - Pending Pending Construction Unforeseen Company) Sanitary Manhole 5 6011110 Pat Patrick (McKnight Abandon In $5,000.00 $6,190.22 $6,190.22 $6,190.22 - Pending Pending Construction Place Company) Transite Water Line and Plug Ends 6 6011110 Pat Patrick (McKnight G Pod $11,852.88 $11,852.88 $11,852.88 - Pending Pending Construction Underground http://heery.constructware.com/CommonIView/Document_ Display.asp?DocumentType= 1 &... 6/4/2009 Cost Event Page 2 of2 Plumbing Changes (RFI 37) 7 6011110 Pat Patrick (McKnight Haul in Fill $100,000.00 $114,191.59 $114,191.59 $109,100.16 Construction Dirt Company) Company) - Pending Pending Estimated Proposed Submitted Approved Committed Items $87,215.86 $118,726.20 $125,743.73 $120,652.30 Markups Total $87,215.86 $118,726.20 $125,743.73 $120,652.30 http://heery.constructware.com/CommonlView/Document_ Display.asp?DocumentType= 1 &... 6/4/2009 Contractor Change Request Page 1 of 1 NK:K Contractor Change Request Project [0400101 - Task 07] - View Date 6/3/2009 ARC - Task 07 - Webster Detention Center McKNIGHT CONSTRUCTION COMPANY, lNC McKnight Construction Company 645 Frontage Road NW P.O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00010 To Submitted By Description Bob Munger (Heery International Inc. (Augusta, GA)) McKnight Construction Company Date Credit for Not Installing the RCP Storm Pipe Status State Referenced CCO No. 3/25/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days ($7,335.00) Work Description Credit to the owner for not installing the 30" RCP @ storm line B5 to B6, and not installing the 18" RCP along Phinizy Road. Recommendation Accept the credit amount Response By Response Bob Munger Linked Documents Document Type Doc Document Open Description Date 0400101 - Task 07-00480 ~ Credit for Not installing RCP Storm Pipe See Roo. 3/25/2009 http://heery.constructware.com/CommonIView/Document Display.asp?DocumentType=33... 6/312009 McKnight Construction Co., Inc. GENERAL CONTRACTORS William D. McKnight - President Mason McKnight, IIl- Vice President Huey E. Carter - Sec. - Treasurer FOUNDERS: Mason McKnight, Sr. 1900-1973 Mason McKnight, Jr. 1930-1994 P. O. Box 204718 Augusta, Georgia 30917 Office Phone: [706] 863-7784 Fax: [706J 863-2031 March 25, 2009 f706-821-2484/ Heery IntemationalInc. 501 Greene St., Suite 313 Augusta, GA 30901 Attn: Bob Munger . RE: Webster Detention Center COP Creditfor storm lines Mr. Munger: The following is a credit proposal for the storm pipe installation that was deleted from the scope of work. Nordmann Contracting: Delete 30" Rep @ B5 and B6 Delete 18" RCP @ Phinizy Rd.. Total credit (3,750.00) (3,585.00) (7,335.00) Please notify this office if you need additional information regarding this matter. Sincerely, MCKNIGHT CONSTRUCTION CO., INC. P ~"*vu~ Pat Patrick Project Manager PP:sdr cc: Jobsite pat03.2509. wpd Request For Quote Page 1 of HEERY Request For Quote Project [0400101 - Task 07) - ARC - Task 07 - Webster Detention Center I View Date 3/16/2009 Heery International Inc. (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 RFQ No. 003 Date Cost Event No. Description From Funded By Ref No. r Self-Performed Long Description Scope of Work Items No. Budget Code 1 5413130 3/2/2009 006 Status New Pat Patrick McKnight Construction Company 645 Frontage Road NW P.O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Credit for elimination of select storm drainage Work, as approved by AlE and Owner's Rep, Eliminate from the scope of work the replacement of existing storm drain beneath Phinizy Road and replacement of existing storm drain beneath the prisoner transport drive, adjacent to vehicular sallyport. Provide appropriate credit. Pat Patrick (McKnight Construction Company) Revisions to Storm Drainage Design Proposed Budget Status - New Revisions to Storm Drainage Design Bob Munger Heery International Inc. (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 To Response Due Date Returned Date Contact Description I Total - I http://heery.constructware.com/CommonJV iewlDocument_Display. asp ?DocumentType=5&ItemID=205692 3/16/20Q!; NORDMANN CONTRACTING, INC P.O. Box 16] 03 Augusta, Georgia 309] 9 Telephone: (706) 733~ 7285 PROPOSAL Date: February 26, 2009 To: McKnight Construction Co., Jnc. P. O. Box 204718 Augusta, Georgia 30917 A TTN: Mr. Pat Patrick Job: Webster Detention Center Delete 30" Storm Pipe NORDMANN CONTRACTING, INC., hereinafter referred to as NCI, agrees to furnish all labor, tools and equipment required to provide, install, and complete the items of work set forth below in accordance with the plans and specifications for the above mentioned job: Delete 30" RC pipe between structure # B 5 and existing structure B 6. Delete 30" RCP Delete 8" Graded Aggregate Base 57.0 LF 6.0 Tons TOTAL CREDIT $ 3,750.00 Notes: Terms: Add to contract as a change order. This proposal expires thirty (30) days from the date hereof, but may be accepted at any later date at the sole option ofNCr. NORDMANN CONTRACTING, INC. Patrick 1. Nordmann President Page I of I NORDMANN CONTRACTING, INC P.O. Box 16103 Augusta, Georgia 30919 Telephone: (706) 733-7285 PROPOSAL Date: February 26, 2009 To: McKnight Construction Co., Inc. P. O. Box 204718 Augusta, Georgia 309] 7 A TIN: Mr. Pat Patrick Job: Webster Detention Center Phinizy Road Outfall NORDMANN CONTRACTING, INC., hereinafter referred to as NCI, agrees to furnish all labor, tools and equipment required to provide, install, and complete the items of work set forth below in accordance with the plans and specifications for the above mentioned job: Delete replacing 18" RC pipe at Phinizy Road outfall. Delete removal of 18" RCP Delete installation of 24" RC pipe Delete installation of 24" Flared End Section Delete 8" Graded Aggregate Base (for road patch) Delete traffic control (for our work) 36.0 LF 39.0 LF 1.0 LS 15.0 T 1.0 LS TOT AL CREDIT $ 3,585.00 Notes: · This credit does not include any deduction for the asphalt patch or overlay. Terms: Add to contract as a change order. This proposal expires thirty (30) days from the date hereof, but may be accepted at any later date at the sole option ofNCI. NORDMANN CONTRACTING, INe. Patrick J. Nordmann President Page J of J