HomeMy WebLinkAboutCHANGE ORDER #5 MCKNIGHT WEBSTER DETENTION $120,652.30
~
RECEIVED
R'S OFFICE
5
June 4, 2009
Contractor:
McKnight Construction
635 NW Frontage Road
Augusta/GAl30907
Project Description:
Additions and Renovations to the Webster Detention Center
Description of Change Mise Unforeseen U/G Utilities & Earthwork; incl CCR 9, 10, 11, 13, 14 & 15
to the Scope of Work:
Project Duration:
Number of Days added to the Substantial Completion Date as a result of
this Change to the Scope of Work:
Contract Amount
Original Contract Amount
Previous Change Orders
Previous Contract Amount
Amount of this Change Order
Current Contract Amount
All terms and conditions of the Contract Agreement between the Owner
and the Contractor apply to this Change Order.
Signatures:
~'~I!a;
. ~ , lt~
Pat Pa rick
Project Manager
N
Recommended for Acceptance by Program Manager:
_IS)') M ~
Heery Internation'al V
Bob Munger, Program Manager
Recommended for Acceptance by The Owner:
Page 1 of 1
2009
04001-07
AUGUSTA.RICHfv OND COUNlY
Reference:
COP#
9,10,11,13.14,
15
30 Days
$ 27,041,000.00
$ 5,992,466.28
$ 33,033,466.28
$ 120,652.30
$ 33,154,118.58
ro/4/0L
Date
DG~04,04
Date
ao -oL{~ 09
Date
&/4-/0'L
Date '
0'/0 y/W() 7
Date .
f jr)l
Date
Cost Event
Page 1 of2
H"'E""E"'RY
j , , , :~ \
.: . ! ,.i .', ...~.! ,'. .; '. '/
Cost Event
Project [0400101 - Task 07] - ARC - Task 07 - Webster Detention
Center
View Date 6/4/2009
Heery International Inc. (Augusta, GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
Cost Event No. 006
Date
Type
Description
~e$ponslble
Funded By
Long Description
Scope of Work
3/2/2009 I$udget Status
Field Condition Cost Status
Misc Unforeseen U/G Utilities & Earthwork
Pending
Pending
Pat Patrick
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Initiated By
Bob Munger
Heery International Inc. (Augusta, GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
Initial Estimate
Expected Final
(10.00 days)
(30.00 days)
$100,000.00
$125,743.00
Miscellaneous unforeseen site work
Includes the following CCR's:
9 - Abandon in Place Inactive Water Line Below MMH and Plug .Ends
10 - Credit for Revisions to Storm Drainage
11 - Remove Unforeseen Sanitary Manhole
13 - G Pod U/G Plumbing Changes due to Varying Field Condition (Invert elev.)
14 - Offset of Existing 10" Water Line to Avoid SD Conflict
15 - Haul in of Fill Dirt due to Unsuitable Soils
Also includes Cancellation of Change Order No.3 Work (CCR No.4)
Items
No. Budget Contact Description Estimated Proposed Submitted Approved Committed Budget Cost
Code Status Status
1 5413130 Pat Patrick (McKnight Revisions to ($7,335.00) ($7,335.00) ($7,335.00) Pending Pending
Construction Storm
Company) Drainage
Design
2 6011110 Pat Patrick (McKnight Revisions to $11,610.65 $18,628.18 $18,628.18 - Pending Approved
Construction Water Line
Company) to Avoid
Conflict with
Storm Sewer
3 5413130 Pat Patrick (McKnight Cancellation ($18,907.69) ($18,907.69) ($18,907.69) ($18,907.69) - Pending Pending
Construction of Change
Company) Order 3
(CCR No.4)
4 6011110 Pat Patrick (McKnight Remove $1,123.55 $1,123.55 $1,123.55 $1,123.55 - Pending Pending
Construction Unforeseen
Company) Sanitary
Manhole
5 6011110 Pat Patrick (McKnight Abandon In $5,000.00 $6,190.22 $6,190.22 $6,190.22 - Pending Pending
Construction Place
Company) Transite
Water Line
and Plug
Ends
6 6011110 Pat Patrick (McKnight G Pod $11,852.88 $11,852.88 $11,852.88 - Pending Pending
Construction Underground
http://heery.constructware.com/CommonIView/Document_ Display.asp?DocumentType= 1 &... 6/4/2009
Cost Event
Page 2 of2
Plumbing
Changes
(RFI 37)
7 6011110 Pat Patrick (McKnight Haul in Fill $100,000.00 $114,191.59 $114,191.59 $109,100.16
Construction Dirt
Company)
Company)
- Pending Pending
Estimated Proposed Submitted Approved Committed
Items $87,215.86 $118,726.20 $125,743.73 $120,652.30
Markups
Total $87,215.86 $118,726.20 $125,743.73 $120,652.30
http://heery.constructware.com/CommonlView/Document_ Display.asp?DocumentType= 1 &... 6/4/2009
Contractor Change Request Page 1 of 1
NK:K
Contractor Change Request
Project [0400101 - Task 07] - View Date 6/3/2009
ARC - Task 07 - Webster
Detention Center
McKNIGHT CONSTRUCTION
COMPANY, lNC
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Contractor Change
Request No. 00010
To
Submitted By
Description
Bob Munger (Heery International Inc. (Augusta, GA))
McKnight Construction Company Date
Credit for Not Installing the RCP Storm Pipe Status
State
Referenced CCO No.
3/25/2009
Pending
Submitted
Estimated Effects of Request
ITime
Amount
10 days
($7,335.00)
Work Description
Credit to the owner for not installing the 30" RCP @ storm line B5 to
B6, and not installing the 18" RCP along Phinizy Road.
Recommendation
Accept the credit amount
Response By
Response
Bob Munger
Linked Documents
Document
Type
Doc
Document
Open
Description
Date
0400101 - Task 07-00480 ~
Credit for Not installing RCP
Storm Pipe See Roo.
3/25/2009
http://heery.constructware.com/CommonIView/Document Display.asp?DocumentType=33... 6/312009
McKnight Construction Co., Inc.
GENERAL CONTRACTORS
William D. McKnight - President
Mason McKnight, IIl- Vice President
Huey E. Carter - Sec. - Treasurer
FOUNDERS:
Mason McKnight, Sr. 1900-1973
Mason McKnight, Jr. 1930-1994
P. O. Box 204718
Augusta, Georgia 30917
Office Phone: [706] 863-7784
Fax: [706J 863-2031
March 25, 2009
f706-821-2484/
Heery IntemationalInc.
501 Greene St.,
Suite 313
Augusta, GA 30901
Attn: Bob Munger .
RE: Webster Detention Center
COP Creditfor storm lines
Mr. Munger:
The following is a credit proposal for the storm pipe installation that was deleted from the scope of
work.
Nordmann Contracting:
Delete 30" Rep @ B5 and B6
Delete 18" RCP @ Phinizy Rd..
Total credit
(3,750.00)
(3,585.00)
(7,335.00)
Please notify this office if you need additional information regarding this matter.
Sincerely,
MCKNIGHT CONSTRUCTION CO., INC.
P ~"*vu~
Pat Patrick
Project Manager
PP:sdr
cc: Jobsite
pat03.2509. wpd
Request For Quote
Page 1 of
HEERY
Request For Quote
Project [0400101 - Task 07) - ARC - Task 07 -
Webster Detention Center
I
View Date 3/16/2009
Heery International Inc. (Augusta, GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
RFQ No. 003
Date
Cost Event No.
Description
From
Funded By
Ref No.
r Self-Performed
Long
Description
Scope of Work
Items
No. Budget
Code
1 5413130
3/2/2009
006
Status
New
Pat Patrick
McKnight Construction Company
645 Frontage Road NW
P.O. Box 204718, 30907
Augusta, GA 30907
Phone: (706) 863-7784
Fax: (706) 863-2031
Credit for elimination of select storm drainage Work, as approved by AlE and Owner's Rep,
Eliminate from the scope of work the replacement of existing storm drain beneath Phinizy Road
and replacement of existing storm drain beneath the prisoner transport drive, adjacent to
vehicular sallyport. Provide appropriate credit.
Pat Patrick (McKnight Construction
Company)
Revisions to Storm Drainage
Design
Proposed Budget
Status
- New
Revisions to Storm Drainage Design
Bob Munger
Heery International Inc. (Augusta,
GA)
501 Greene Street
Suite 313
Augusta, GA 30901
Phone: (706) 842-5543
Fax: (706) 821-2484
To
Response Due
Date
Returned Date
Contact
Description
I Total - I
http://heery.constructware.com/CommonJV iewlDocument_Display. asp ?DocumentType=5&ItemID=205692 3/16/20Q!;
NORDMANN CONTRACTING, INC
P.O. Box 16] 03
Augusta, Georgia 309] 9
Telephone: (706) 733~ 7285
PROPOSAL
Date: February 26, 2009
To: McKnight Construction Co., Jnc.
P. O. Box 204718
Augusta, Georgia 30917
A TTN: Mr. Pat Patrick
Job: Webster Detention Center
Delete 30" Storm Pipe
NORDMANN CONTRACTING, INC., hereinafter referred to as NCI, agrees to furnish all labor, tools and
equipment required to provide, install, and complete the items of work set forth below in accordance with
the plans and specifications for the above mentioned job:
Delete 30" RC pipe between structure # B 5 and existing structure B 6.
Delete 30" RCP
Delete 8" Graded Aggregate Base
57.0 LF
6.0 Tons
TOTAL CREDIT
$ 3,750.00
Notes:
Terms: Add to contract as a change order.
This proposal expires thirty (30) days from the date hereof, but may be accepted at any later date at the sole
option ofNCr.
NORDMANN CONTRACTING, INC.
Patrick 1. Nordmann
President
Page I of I
NORDMANN CONTRACTING, INC
P.O. Box 16103
Augusta, Georgia 30919
Telephone: (706) 733-7285
PROPOSAL
Date: February 26, 2009
To: McKnight Construction Co., Inc.
P. O. Box 204718
Augusta, Georgia 309] 7
A TIN: Mr. Pat Patrick
Job: Webster Detention Center
Phinizy Road Outfall
NORDMANN CONTRACTING, INC., hereinafter referred to as NCI, agrees to furnish all labor, tools and
equipment required to provide, install, and complete the items of work set forth below in accordance with
the plans and specifications for the above mentioned job:
Delete replacing 18" RC pipe at Phinizy Road outfall.
Delete removal of 18" RCP
Delete installation of 24" RC pipe
Delete installation of 24" Flared End Section
Delete 8" Graded Aggregate Base (for road patch)
Delete traffic control (for our work)
36.0 LF
39.0 LF
1.0 LS
15.0 T
1.0 LS
TOT AL CREDIT
$ 3,585.00
Notes:
· This credit does not include any deduction for the asphalt patch or overlay.
Terms: Add to contract as a change order.
This proposal expires thirty (30) days from the date hereof, but may be accepted at any later date at the sole
option ofNCI.
NORDMANN CONTRACTING, INe.
Patrick J. Nordmann
President
Page J of J