HomeMy WebLinkAboutCHANGE ORDER #11 MCKNIGHT CONSTRUCTION WEBSTER DETENTION $147,780.89 e If) I ~ I ~ '1 ~~~-k. ~ ' Change Order # 11 Date of Change Order: October 6, 2009 Project No.: 04001-07 Contractor: McKnight Construction 635 NW Frontage Road Augusta/GA/30907 Additions and Renovations to the Webster Detention Center Reference: COP # 22,25,31,32,33 Project Description: Description of Change Add water heater & accessories, add surveillance cameras, add stair railings, extend firewall, etc. to the Scope of Work: Project Duration: Number of Days added to the Substantial Completion Date as a result of this Change to the Scope of Work: Days Contract Amount Original Contract Amount Previous Change Orders Previous Contract Amount Amount of this Change Order Current Contract Amount $ 27,041,000.00 $ 6,221,343.98 $ 33,262.343.98 $ 147,780.89 $ 33,410,124.87 All terms and conditions of the Contract Agreement between the Owner and the Contractor apply to this Change Order. Signatures: Date qj'l3/01_ ~;'" ~~" -------, 4 . 2-1- ..,"' KSGW Date Gregory Washington, Architect oC[. d'f. Or Date Recommended for Acceptance by Program Manager: H.&~5a'~ Bob Munger, Program Manager 4(~-z.,/ (?1- Date ' I Recommended for Acceptance by The Owner: Captain Chester Huffman WDC Jail Administrator Date 1/1, f.,/ v. 7 Oat . Page 1 of 1 en o o N rn~ N .... Q) .0 E Q) - c.. Q) V) cLi III U Q) Q) QJ c: c: u u u ~ Q) a III ..!!! III I tl.O ... '.j:i a. 0.. a. ...... III Q) c: a c: c: Q) c: c: ,~ Q) ... 3: vi > ,- III III c: c: "0 "0 "0 III ... Q) 0 a "0 c: a Q) Q) Q) ..c 3: III ',i:i U c: c: c: .... ...... :J U c: a a a III a 0 a. Q) "0 "0 "0 > a .... .... c: c: c: ... vi vi > vi III .... .... tl.O ..c a Q) III III III ';: "'0 c: c: c: c: U "'0 ..c ..c ..c :J c: a a a "0 a a .... III III .... III U ',i:i 0.. '.j:i '.j:i Q) '.j:i '.j:i oCl 0 Z. Z. Q) Q) III U U .... U U Q) > III 'x tl.O Q) Q) III Q) Q) c: Q) III III c: Vi Q) c: ... .... Q) ... ... a tl.O :J :J 'liO :J "0 'Vi .... .... :J ... ... vi '.j:i c: a a a Q) ~ :J a a C" a a .... III III '::; '::; c: '::; u a u u Q) u u c: "~ ...c: l.U c: "'0 o(l o(l .... oCl oCl Q) u Q) Q) ~ Q) III a ...c: .... E "0 ... ... ... ...c: E 3: c: c: c: c: c: .... III 0.. 0.. 0.. c: a a Q) a a Q) a .... i::~ i::~ 'u i::~ Q) Q) u a a a c: '.j:i '.j:i E ',i:i ',i:i c: u c: a a III a "0 .... III III Q) III III III E E u.. :-2 Q) "0 tl.O c: c: u c: c: ...c: c: "'O~ > .... ~ c: c: c: tl.O "0 "0 .c "0 III '.j:i "0 "0 III "0 "0 'Vi ;xi Q) ... .... ... ... Q) c: c: c: ~ .... a a ...c: a a Q) a a "0 a :J :J "0 "0 Q) U U Q) U C" .... ..c a a c: a a Q) .... .... Q) Q) III U U Q) U U .... tl.O III c: c: III c: ... Q) c: c: c: c: c: III "~ III c: Q) Q) Q) Q) Q) Q) Q) Q) .... :J 0 c: .... tl.O tl.O tl.O tl.O tl.O "0 .... Q) III "0 "0 C" "0 Vl 'liO Q) 'Vi 'Vi 'Vi 'Vi 'Vi :J c: c: ~ ~ ~ C" 0 .... Q) u c: ...c: Q) Q) Q) Q) Q) Q) <( Q) Q) Z III J: :c IX: :c IX: l.U 3: Cl Cl Cl Cl Cl .... 0.. ... a 1Il~ Vi' ..Q >. III Q) u.. (5 ... .... a tl.O 3: Q) III .... 0.. E c: = III ,~ a '0 ... ... III Q) Q) c: ...c: ....J Q) .... a III ~ U <( c: ~ 'Vi :J III :J ~ :.J l/l .... u:: .... ,5Q c: - Q) :J a '::; Vl I- ';: a .... .... a 3: Q) QJ ... .S ',i:i > u Q) 0) :J E III - c: ...c: IX: III :J ,S U III .... III III t '::; a "'0 Q) .... "0 .... ~ Q) III o(l QJ I- a (5 Vl 'Vi "0 I: ... U W IX: ...c: 0.. a 1Il~ - :> <( 0 QJ Q) QJ U () III U 3: - .... ~ u c:~ .... I QJ 3: a "0 '00 ~ c: a III L..:' ';: QJ QJ III QJ l/l QJ QJ S a a QJ "'0 .... Vl c: '.j:i Q) ... 0.. I: ~ a Q) L.L tl.O III - Cii III u::: :> QJ '60 Q) .~ :e ~ III 0) III > I- ...c: .... OJ Q) QJ U ';: - C/) c: "Vi c: "'0 a u u III c: :;:; ';: C/) u 0 c: ::) III :> 00 Cl '~ u c: .... III c: c: III :J QJ .... Vl Q) "'0 .... " ..c <( QJ c: III .... Q) Q) Q) C) u Cl a N 2 .E III .... QJ 0 tl.O - QJ Cl oCl X III c: - c: l/l l/l -.. QJ in a c: en .... "0 <( QJ Vl E L.L l.U QJ ',i:i Q) Q) ::) "0 ::!.. ',i:i 'Q) ... c: :J lI.O QJ ... :J ..... .... :> tl.O QJ 1Il~ :J U c: "'0 III .E c: a a ,~ III .... 0) Ui .... tl.O III a a QJ C" Q) .... "'0 ,~ ...c: .S c: III a c: .... u ... c: Q) QJ V') .... ,S L.L I: 0.. ..E ::) 0:: Q) III III a ...c: "0 l/l 0 a QJ - QJ .... l/l III ..... 0.. III ... Q) .... '(ij :c tl.O .... QJ Q) I ~ a Qj :J a ::E.E l/l III c: u I: c: ..... .... co '::; c: c: ... "0 0 Cii a Q) a QJ ~ u:: a ... IX: :i2 III :J QJ .... ~ E ~ c: .E "0 IX: .... .... u Q) ,S Q) a QJ ... a 0.. 0 Cii QJ V') QJ .... Q) 0:: :;:; .... ,~ c: QJ QJ 3: c: III III Q) > > ::) U tl.O "'0 .... QJ .- 0:: III S III ';: "'0 E III QJ ';: LL a 0 c: c: III III tl.O ~ "'0 "'0 .... Cl ... <( III tl.O a ',i:i c: c: U III .... c: V') 0 u E E 0 III a Q) a III c: III "'0 "'0 ,~ ...c: III QJ 'ro .... "'0 0.. :J "0 ~ "0 t ... III QJ ~ QJ Q) ~ c: 'x .... ... QJ (5 ~ ..c I~ "0 X "0 QJ QJ ...c: x u:: III C IX: 0:: ::E l.U l.U l.U Cl IX: > <( l.U <( lI.O ... "E u I: f-- .... f-- ~ tl.O III c: 0 .c a c: III III III U U QJ c: lI.O c: c: c: .... 0 lI.O III I: III I: a a a QJ ,5 III E 0 :E ',i:i :-e oCl c: c: "'0 "liO .c QJ :t:i "0 :0 "0 3: l.U I: U .... III c: c: c: 0 + QJ ";: lI.O "'O~ u 0 It: a a ... a .... ... 0.. I: U U QJ U + QJ QJ :0 QJ 'iij - III III .....: .....: c: .....: 0 0 0 c: 0 c: 0 III III I: :J 3: 3: 3: .... .... III c: c: c: o(l oCl oCl oCl o(l ~ {l. QJ c: U ~ ~ 0 ~ l.U l.U l.U 0 l.U 0 l.U 0.. ~ LO 0> '<t 0 (") (") (0 00 0 0 0 co 0 CJ'l (") ~ C\! C":l C":l ~ tC! ~ C":l ~ ~ 0) 0 0 Lri I'- (") C\I (") I'- (0 0 I'- ..- 0 ~ 0 V') (0 0 0> LO LO (0 0> C\I 00 00 0 N 0 0 ..- 0> (") (0 I'- ..- tC!. (") 0 I'- o. ~ 0 '#. 0 I'- a:i cD ci Lri' C\I (0 0) ..,f ,..: (0 an rl~ en CJ'l ..- ..- C\I LO ..- ..- ..- '<t ~ CJ'l N .... ..- ..- CJ'l ...i I: N~ ::J ("/") 0 E fh fh fh fh fh fh fh fh fh fh fh ~ 1.1). 1.1). III :l:t: 0 rl 0 rl N ("/") '<t LI') \0 I'- 00 CJ'l rl rl U I ~ QJ "'0 ... o QJ lI.O I: III .c u u c 3: Cost Event Page 1 of 1 H:E:ERY Cost Event Project [0400101 - Task 07] - ARC - Task 07 - Webster Detention Center View Date 9/18/2009 Heery International Inc. (Augusta, GA) 501 Greene Street Suite 307 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 Cost Event No. 016 Date Type Description 9/4/2009 Budget Status Coordination Cost Status H20 Tie-In; Ext, Stair Railings, Firewall Extension Pending Pending Responsible Pat Patrick McKnight Construction Company 645 Frontage Road NW P.O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Initiated By Pat Patrick McKnight Construction Company 645 Frontage Road NW P,O, Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Funded By Initial Estimate Expected Final $140,000,00 (0,00 days) (0,00 days) Items No. Budget Code 1 6011110 Pat Patrick (McKnight Extend Construction Existing Company) Firewall & Expansion Joint (ASI 19) Contact Description Estimated Proposed Submitted Approved Committed Budget Cost Status Status - Pending Approved $3,000,00 $3,100.00 $3,064,87 $3,064.87 2 6011110 Pat Patrick (McKnight Add exterior $1,200.00 $1,250.00 $1,205,00 $1,205,00 Construction stairs & Company) railing (ASI 35) 3 6011110 Pat Patrick (McKnight Video $1,800.00 $1,729.50 $1,729,50 $1,729.50 Construction Visitation Company) Water Line Tie- In 4 6011110 Pat Patrick (McKnight Add Housing $60,000.00 Construction Pod Water Company) Heater and Pumps per ASI 22 - Pending Approved - Approved Approved - $64,813,04 $64,813.04 - Pending Pending 5 6011110 Pat Patrick (McKnight Add Security $75,000,00 Construction Cameras per Company) ASI 25 - $76,968.48 $76,968.48 - Pending Pending Items Markups Total Estimated $141,000.00 Proposed $6,079,50 Submitted $147,780,89 Approved $147,780,89 Committed $141,000.00 $6,079.50 $147,780.89 $147,780.89 http://heery.constructware.comfCommonIView/Document_ Display.asp?DocumentType= 1... 9/18/2009 Contractor Change Request Page 1 of1 tICK Contractor Change Request Project [0400101 - Task 07] - View Date 9/21/2009 ARC - Task 07 - Webster Detention Center McK~JIGHT CONSTRUCTION COMPAN\{, INC McKnight Construction Company 645 Frontage Road NW P.Q, Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00032 To Submitted By Description Bob Munger (Heery International Inc, (Augusta, GA)) McKnight Construction Company Date Revise Fire Wall at G Pod Status State Referenced CCO No. 8/26/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days $3,064.87 Work Description Cost proposal PR 17 Recommendation Response By Response Bob Munger Linked Documents Document Type Doc Document 0400101 - Task 07-01053 Description Webster CP PR 17 Date 8/26/2009 http://heery.constructware.com/CommonIView/Document_ Disp1ay.asp?DocumentType=3... 9/21/2009 William D. McKnight - President Mason McKnight, III - Vice President Huey E, Carter - Sec. - Treasurer P. O. Box 204718 Augusta, Georgia 30917 Heery International/CIPM 501 Greene St., Suite 307 Augusta, GA. 30901 Attn: Bob Munger Mr. Munger, McKnight Construction Co., Inc. AIJG:I'1' 20m3) GENERAL CONTRACTORS FOUNDERS: Mason McKnight, Sr, 1900-1973 Mason McKnight, Jr, 1930-1994 August 25, 2009 Office Phone: [706] 863-7784 Fax: [706] 863-2031 RE: Webster Detention Center Cost Proposal PR -17 ASI-19 : RFQ - 12 The following is a cost proposal for the work described in ASI -19, RFQ -12; to revise the fire wall at G- pod. Concrete/Masonry Triad Spec. (Exp. Jt Cover) McKnight 6% O/P 1,2% Bond Total $ 1862.00 995.10 $ 2857.10 171.43 $ 3028.53 36.34 $ 3064.87 Please issue a change order for this amount. PP:pgn Attachments cc: Jobsite Sincerely, MCKNIGHT CONSTRUCTION CO. Pat Patrick Project Manager rp.R ~- 17 ----------------.-.--.--...----.-- _.-------------,,---------,-,---.,- .----.---~-,----------,-- ~ As \ - \ q =--~rn-=- \ 2--~- initial'; Dah' I ~------~.--.-..>--,--~-~_..i i -;- , , . -,; , , , 7EA-~ - ; -------- , ii' u' . -; - i . , - ---- . . I Prepared 51' I , ' i -. I Approved ~)' I ~>/)(---- . --,------- ------------ +---,..,... t ..-- __ __ L~~':t_____ __1~t L__n___ __S~,,1a_________ lo~_ A ~ ~riohi\~ [ .J ---j- i _, i E'Xco..vo...hoV\ @.. 2r:r/ ~ I Cov\cve-te.__L1>Q" /hI ~ Ma.&t>V\I/i : i 1 8 I i/ID1Wy' Z\I/4- ~ "'~_ 9 :23 (J e ~ " d M. L\ G I' Ii [ 10 110 S MolI"bv Q. 7 ~ ------------r 11 2,~~ bV'L.\.v't"' Q 10'6 ~ I 12 l 1- I -5~ i 2 I 3 Z~ " 2ctl I i iJ I I 14 i 15 i ! I , 16 ! I I I 17 I -- 18 i I I 19 I 20 . t 21 I 2? -t ---L- I' 23 24 i 25 I 26 I ?7 I 28 i 29 I I ! 30 I 31 I 32 i 33 I 34 I 3S I i 3S i i i " ~i 39 I 4'1 _J ! i ! I I i I , i i ---------- . .---- J I I I i I I I I --- : i ! i I -----~~--_. I i - I i !' ~~ ~ i .2D~ , ! ! I i I i i i ~ ; ;... i I a. ~ ii, i 1" ii, i ! 1, . i i i Ii, I, i i 15 vb ~ Iii I 6~Si ~ i !8tl it: <t- i i JiJ. , I i 16 II R:~ 7%i~~h-~! i ! ~ inH i I+J--l- ,-, i : ~ ,____:!_: ~ : : : - , i i. ~.; ; _., __.;:; ~-+...J.+- I' -BFl~E UU~2e[ i i I ~Rb!1It I fllll : I 18 , i I. 1 ' ,---'~.--r-- -~r--~-'-t-~-'--- t--,-l--+-,-I--1~--~-T-- i , i : i_LJ_ 1___1 i I LJ I! ._; I L~-,-4~ 19 , i I ; I.. : i ,.,-..:.l! t :; .1/01.' I"ll.. - 20 r if, f I Ol~ ;) O!fQlC : : ", [. , . , , . , ; I : t .'__ ' !:, I i ! , : i. __ ___ i!' ....__ ; ii, '! I! i i ii, I it i i , , ; i B% : : i : i , . : . I . i ; i ! , I , i i ~.-_.__.- , : ~ ' , , I : . , ; ! ; , I I q IZJ'J. : T : ! , ! i 1"" I , @,il.o!~ -. i i ~LQ ~ ?Z It. Q,C I I ., I i ,_. . i: :' : , I' : ; . : I -e- , -c---- , -- -'---- _ _u , , -- , u_ ,--- .---j, ----. . - '-- ---------- . .,-------- ;. 1 , , ; ; , , , s I :~ I 12 2; I 22 23 24 . I 25 i : -,' : '1'.1 , L:' : i i 28 : : 28 I I I 30 j i 3: : , I l: 32 ! ! 33 '-'-,-:- : i -'-i--- 3, . .! ; i 35 i !. ; 3D J! --- , :.' : I i , 38 L_ 39 40 -----I , P,O. Box 14009' 1807 Wylds Road' Augusta, GA 30919 Telephone (706) 736-1430' FAX (706) 736-3402 QUOTATION DATE: August 24, 2009 TO: McKnight Construction Attn: Pat Patrick FROM: Triad Specialties, Ine. John Demons III JOB: Webster Detention Center 1 - Expansion Joint Covers Price #01 - Model RJ-28LP with Standard Finish 1 - Required @ 10'0" (Each) Lot. Material Only $ 400,00 + Tax Price #02 - Model SMC-l NX with Standard Finish 1 - Required @ 20'0" (Each) Lot. Material Only $ 530,00 + Tax Quotation is valid for 30 days. All prices quoted F.O.B. shipping point., freight allowed to job site. Terms: 1%lOlNet 30 No Taxes included: Unless otherwise staled We do not accept responsibility for delayed shipments or deliveries occasioned by strikes, fireS, accidents. delays of common carriers or other causes beyond our control including delays in receiving materials or parts obtained from outside sources. -- 4DD a:t y: tg 1if; - ,.c._",:,:"~,,,.~I!"I"_"'.-?"!!'I'Wi ~ '"I 1..8 tA~ 1J3D l~. "--/' /J ~ ft;i IJ./"\\ By: /'" y. 1:,1~:! If, i 5~7' I,g, 'f;qqS Ii? -,. '-D~ &f' S+.{pV-t/v), SPECIALTY BUILDING PRODUCTS Architect's Supplemental Instruction Page 1 or: .. t.t j' f' 1 It ~ I ,. . . I .~ Architect's Supplemental Instruction Project [0400101 - Task 07] - ARC - Task 07 - View Date Webster Detention Center 5/15/2009 KSGW Architects 2500 Northwinds Parkway Suite 250 Alpharetta, GA 30004 Phone: (770) 619-5913 Fax: (770) 619-5919 ASI No, 019 Date 4/29/2009 From Gregory Washington KSGW Architects To Pat Patrick (McKnight Construction Company) CC Plamen Borissov (ATC Associates) Bob Munger (Heery International Inc, (Augusta, GA)) Norman Davis (Heery International, Inc. (Dukes Edwards & Dukes - Subconsultant)) Bernard Dunstan (McKnight Construction Company) Reason for Instruction Action Requested Probable Cost Effect Initial Estimate Cost Probable Time Effect Initial Estimate Time Insufficient Information Direction Unknown Cost None Subject -awing No. Expansion joint cover at firewall ASI019 Spec Section CSI Code 03 30 00 - Cast-In-Place Concrete 04 20 00 - Unit Masonry Detail No, Status Other Ref RFI Instruction Details Unit G, the attached is provided as supplemental information to extend the existing masonry firewall at the face of the new male housing pod exit stairs, Remarks Linked Documents Document Type Drawing Drawing Drawing I)rawing rawing Document ASK-13 ASK-14 ASK-iS RJ-28LP SMC-1N WI RFX-1W Open Description Unit G-Male Housing building Elevations Unit G-Male Housing Wall Sections Unit G-Male Housing First level plan Specification Item Specification Item Date 4/28/2009 4/28/2009 4/28/2009 4/28/2009 4/28/2009 > Ul ?' :; ::" ~;o ~m ~~ )> r r (f) m () -I o Z o m -I )> r !$!: x !$!: x ~ "'n iTl.~ ill.... l<~ c>0 o-C m '" ." ;;;n mO "'2 gg "C zg C>CJl ... ": ;;: ~ ~ m n ~ X ~ 0 CJl 2 ~ -< :I: '" Z o->m m CJln > -< C "tlUlX ~~ -< C 0 ~~~ Z 0 C o-:::! C> @ CJl ~~!!?m >2'" ~~ 2 C 0 Of fJ~!i1!~ ~ ~ ~ 0 g~Q~ mCJlO (-) -<~ ""OmzO _ ::O-C::tl ~ x _n ~O ",Z 5:::! nZ "C zg C>en ~ ~ Of -: ~ OJ ~ ~ OJ ~ ~ @-<"tl ~$~ ~g~ C/)~m ~.~~ -~~~ N:E~ <Ii ~ ~ 9~~ 0StSl ~:;~ "tl>o- .:.-~~ !BC> ~ " o > Ul ?' :; ::" ~;o ~m ~ ~~ ~ )> r r "U ..., - ~ r ~ ~ )> Of Z 0 m ~ ~ ~ OJ r ~ ~ ~ e me!!' )> ~ ~ in ~~~ '" . CJ) ill ~ ~ ~~~ ~ . ~ i"~ ^ ~ "'''' WEBSTER ~ c ~. I ~g DETENTION FACILITY ...Jo. c ~~ n ~ ~ Q AUGUSTA, GEORGIA ." ;;; m ~ o n " Z Cl ~u;>mrn n~~~~ ~tz~~~ ~ ~ !< ~-~ ~~~Q ~mZ :;".... t' o \ :1;11I~ en J ",!~~J on ilhlO:t: -1-1- j;m ,oZ =" ~m ~~ ";I: :~ -l N t~E; ~~~ ~~O 0"'0 lDQom !g~ ",r :;,,'" ~ Z>Z Ozo -l0-l ~~fI:I >>cn z8m o",m 0(;)0 _."m s:o-l m;u~ z-lr Q!-<:::: O'U> z-O> (j)()o . > '" r(;) ~ ~ OJ ~ ~ ~ OJ . z>z ozo -l0-l ~~fI:I >>cn z8m o",m 0(;)0 _."m s:o-l m;u~ z-lr ~-<~ 0'U> z-O> cn()o . > '" r(;) c "H~ ml~ ~ eel ~ D' n: !!! a !;' ~ != ~~ ~ ; ~ >-.. =- i''' a.il ~ 'H > "" III ~ !" ~ gY~ ~ i II ~ lr a-~ ~ '2,.0,oQ41 I~~g I .. ~ I -f~ I -i I I ~ s.g" "0 8 ~:; Q... ~ I ~ I ~.. ~^ ~ (I) .. "col:,,:,+-(~;;+:t:;.:...~......."g ! t.::i....+~!.+".t:....~.e ~ "" I !!. ~ 0> .. 2l + I t (II lIl-. ~ CII ,. I + I CJt N - cr 0,-0 ur ~ t;\; ,!, 'I' ~ '" 'I' ~ I '" Zii:r- ! I t:t~NPfJ.T I N~ I ~.. U-...UI"""'NU'NcnlOltn - t;11 I ....;:;l8"'1 "'~'r'''''~ i: 0 INUlO, 01 mcn_~ ... 9 Ci ~ ~ ~ If 8 J.. :: =='":;; g I 8 "'S;18"'~J::l!::l~8~1l!'!o Ii ~~ ~,~~~~e ~~ '@"U;- I ;;'''~'''o''''''';;''''+''''~''' 0 iii )(+........ex~)(e<olQo.s. 0 u co..., .. + )( .. .. (,I ~ ~ (J'I ::J + ..... ~ + QII .. + + I + - .... CI ~I+~g:~l!l~t:t!::l'r 2" li:~~Nl.J.~.!..t~ ~ 1ft: I I I ~~ I f I ~N ::J U1-t~~mUl!:3Oi~~~ UJ t;1J,"'S-N'r"'I....O>.......5' '" IOfl",)I""11Q Nina'. N N C>> tit I g ta (jI, ~ g 0 g. ~~~~8(J1~CJ'= gin 2 ~r~~~~~~!t*~ : li~iP U r~~~ ! ~'~'111i~'~ ~ ~ : ~,~.:; 0 ~ ~ ~. i: .:; g ~9.dg~~~i~g3 ~I~~agoh ~ 0:,(,8c:'O-60 8 3 ~~ ? ~ g g ~ ~ ~.Ng3~~1O i ~~ (f) s: () I ~ a I '-- r- 0 "1J 0 0 C ::c III 0 en 0 z ~ -i '-- P 0 m (5 3: 0 ~ m :-:l ;D , en 0 en en :r ~ c 0 ;-l ~ :J> f1:I r- III f1:I ~ ~ 0 " , , Z ~ :...; 0 ! ~ S ~ z ~ -- :::0 11 >< I ~ ~ j'':J ~~c~ h o~:::! ....zz DlCC o;r::o 805i ~ ~o ........ <.~ .... '" . ~ 'tiC ~g '" ~ .......lIlC ~:I:C ~O:::O o'tlO N_;n "'Z'" (;;!!jx .e~~ "'", c~ ~ D , o , o I"'1nc:: :l:n~ a -0:: % !a:;':> """S", ;i ff~l[e.g~.3"~~~hC1 ~ c:M....~eIl'<,,~gg-, "" .., ~. N ~ :> '" ~ 'll .. ll. -i::'~ g g .. I ~ = , s ", , I ' .. C:!!:'O .. '< ...... - .. ell'" -i;;:: ~o ,~g,~ "";<:L~<.n.il:> -1+a.....{~I!.-I~+;..~ ~ .. ~ I .. c'li ;: + ~ '" .. ~ ~ '] ;- I -i -; ~ ~ l!: ci 'i' t ~ ~ ::>2- ~ t ~ l!:,(, ell':' <.n ~ iN 'r 4"::;: 'l''''.;:.r:,'l<llch'1'~~<.n'''jf 'J'7tJ,~~~,{,~'r':'~ l;'!" "'N"'~N.oI~CD"'l!:'n5' ~ ~ J.'j' cl, 'J' ~ ~ g ~ 1::;;' ~n c!,.....~<.nN.."'N....l5;;'l! 0, N;;'J,g~~~~P'::;~~~o ~>:!:-"";;""'''''l!''l!lO .... "~~;;'~~~~t:;~UI~ '1 ~;::!:;hc'li!!1'l!"'''N&; b' + '''+Gl+O'j...:,t....., :l ""....x O'aHDcrUlw_....m III Cll.:,ci~,{,~'i'ch'1',{,~~ !j ..:,7tJ,,{,::l~..:,~~~:::, ~ J.gt~~13'r;:j~.:,;;-~ ~ rANl/l'i' I ,.o~~:gg~ :l 1~1Dl/l:g:il~<.n......"n '" r:,ncl,...ml;!:!::~~tg-,,\ ~ ~ III ~ ~;;- ;;- ;;- ;;-"8 5' ~"'l g. ;;-~ ..... '" 0 0 00 l." 'g _ I g S' !!. ~ a a ~ III ~~ '9 it ~~C;>~"~~~a~dg '" Slt~~~~~~..~~,~ g -t>, '..nnn_.. n 3 IIlP"."":>:>00 '0" .....,'....II\'!ln{j:J :l ~;:2g"l'll~..~n '< ~i'9~2~~~,~ .....nO~,,'9o 7: g~g~gss~ i:: Nc~~~() "< II X""< t- o [Xl z p r- o (') )> ...... o ;;;: (') c (J) b s:: m ;:0 ~ .., " .. ! iii ~ ~ .. ^:1>n -ro Nez ~!~ '-Izz <.nee ~zg !IJ;J'" :1>fTl zx fTl-i :0 e t:l fTl t::l 1'1 ":1>0 ....r-c Nec l>zz 0.......... CDZ.... Nez g:Z2j 8nc ~~l "'x ;0...... .,;0 r-C lOt::I ......,., ,.,t::I '" / ^n/ Z:1> NZ.... /i--e ....10' nr .."". '-'''' o Ox" Z nz.... Cl ';0 :D-<~ 01O.j>. :l:z . onVl ....:1:, g~"" e 0 (J) (J) (J) C (') :r )> !l' )> ,... ...... ...... r- rn OJ rn ~ , 6 0 0 ; ." Z :... en i ...; ~ s ! D c~ N;o <0 0.., Nr CDfTI (;jx ~Cl ~ '" fTI -i ~b. 1:::. ~ "b. ;0 C- I I'V ex> r -U / <N 10. ., 0< ;0_ t::l tIlfTI ~" ;00 -r ,.,-< :OfTI -i ~~ Nr <fT1 ~~ o o 8 s(fj ....... ~c 11=2 ~- q-i G) I s: )> r- m :c o c en 2 G) ." ;:;0 en -i r- m < m r- CJ s: m 2 en o 2 ""U s;: 2 s (fj w ~CJ lI=m ~~ r- )> -i 2 m :;E ." ;:;0 m ~ r- r- III 10'-0' 1'. :;:::c...." ~o::::o oozo ~-1< ~8~ <-n ~55 ,m "'?;! Hl;;j ~o ,; F ~ ~ ~ c ~ ~ " }> ~ ~ cc' ~z m m m::t !!1 ~ j eo> ~ CJ} ~ ~~ ~ Z ^ 0 ~ ~ ;;l h WEBSTER 0 I ~~ DETENTION FACILITY ~ c !1 ~~ CJ1 2 6$ f AUGUSTA, GEORGIA ~ .. = ~ ~!e)>Q ;;J>O ;II ~~~ ~ o G') 0 5 g 0 ~ m ,; r- :1:ltH rn · WII~Q !Ii,! ,;m .oZ :;ll; .m ~r- ;cn c:I: ~c::: t'"' ..., N :J!- ;~i.: s 1 ~ ~ I ! 'i ~ J ~ i~H 33C ,,=2 ~--i 0 =G) s: )> r- m :r: 0 c en Z G) en 0 c --i :r: m )> en --i m r- m ~ --i 0 Z 33C II'Z ~--i C> 'G) s: )> r- m I 0 C en '" 2 <i G) Z 0 ::0 --i I m )> en --i m r- m ~ --i 0 CD z '" 0 ~ ~ ~ )> ~ ,,~ ~ ~z m > 6~ (J) ~ ~ ~ z~ ~ " z o~ ^ ~ rn~ WEBSTER ~ mm ~ ~e I 2~ DETENTION FACILITY ~ fi "'z 2 Cl W AUGUSl A, GEORGIA w ex> G1 ..... " .. ~ ~ ~ ~ ~ N,D. < m ~ ~ (j5 ~ o Gl 0 is ~QDZ ~ ~~ ~~ (5r il!lll! C/l '. ii:_.~~1 00 I '5i o:r:: 'Iii" ,;m ,oZ =" ~l!! .cn c;:r: :c:: t'" "-l N :r: " "~1_ ::; ., ..,[ mr " " !4 ' " Contractor Change Request Page 1 of 1 tCK Contractor Change Request Project [0400101 - Task 07] - View Date 9/21/2009 ARC - Task 07 - Webster Detention Center McK~JIGHT CONSTRUCTION COMPANY,INC McKnight Construction Company 645 Frontage Road NW P,O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00033 To Submitted By Description Bob Munger (Heery International Inc. (Augusta, GA)) McKnight Construction Company Date WDC PR 32 - Add stair railing & nosings Status State Referenced CCO No. 8/26/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days $1,205.00 Work Description Exterior stairs at new Female Pod Recommendation Response By Response Bob Munger Linked Documents Document Type Doc Document 0400101 - Task 07-01059 Description Webster PR 32 Date 8/26/2009 http://heery.constructware.comlCommonIView/Document Display.asp?DocumentType=3... 9/21/2009 William D. McKnight - President Mason McKnight, III - Vice President Huey E. Carter - Sec. - Treasurer p, O. Box 204718 Augusta, Georgia 30917 Heery International/CIPM 501 Greene St., Suite 307 Augusta, GA. 30901 Attn: Bob Munger Mr. Munger, McKnight Construction Co., Inc. GENERAL CONTRACTORS ,~t i 2009 FOUNDERS: Mason McKnight, Sr, 1900-1973 Mason McKnight, Jr. 1930-1994 August 26, 2009 Office Phone: [706] 863-7784 Fax: [706] 863-2031 RE: Webster Detention Center Cost Proposal PR - 32 ASI-35 The following is a cost proposal to furnish and install the stair nosings and handrail as noted in ASI- 35. American Metals McKnight 6% OIP 1.2% Bond Total $ 1123.32 67.40 $ 1190.72 14.28 $ 1205.00 Please issue a change order for this proposal. PP:pgn Attachments cc: Jobsite Sincerely, MCKNIGHT CONSTRUCTION CO. ffcdvJ Pat Patrick Project Manager American Metals Inc 3925 Goshen Industrial Blvd Augusta, Georgia 30906 August 25, 2009 McKnight Construction Co., Inc P.O. Box 204718 Augusta, Ga 30917 Attn: Pat Patrick RE: Webster Detention Center Subject: ASI NO. 35 Mr. Patrick This is a cost breakdown of the Exterior Handrails added in ASI NO. 035. . Materials: $110.00 . Galvanizing: $105.31 . Sales tax (7%) : $15.07 . Shop Labor: $222.12 . Field Install: $100.00 . Subtotal: $552.50 . Profit (15%) : $97.50 . Total: $650.00 This is a cost breakdown of the Stair Nosings added in ASI NO.35. . Materials: (5) 3" Cast Aluminum Stair Nosings 7'-0" by American Safety Tread. . Cost:: $376.00 . Sales Tax (7%) $ 26.32 · Subtotal: $402.32 · Profit (15%) $71.00 . Total: $473.32 Total Cost Added by ASI NO. 35: $1123.32 Cc: FWB ArChlteCrS ~upplemental mstructlon rage 1 01 L .... lJ r ..' 11 . 1 'I.~ I.' ( ~ I Architect's Supplemental Instruction I Project [0400101 - Task 07] - ARC - Task View Date 8/6/2009 07 - Webster Detention Center . KSGW Architects 2500 Northwinds Parkway Suite 250 Alpharetta, GA 30004 Phone: (770) 619-5913 Fax: (770) 619-5919 ASI No. 035 Date 8/5/2009 From Gregory Washington KSGW Architects To Pat Patrick (McKnight Construction Company) CC Plamen Borissov (ATC Associates) Bob Munger (Heery International Inc. (Augusta, GA)) Norman Davis (Heery International, Inc. (Dukes Edwards & Dukes - Subconsultant)) Reason for Instruction Action Requested Probable Cost Effect Initial Estimate Cost Probable Time Effect Initial Estimate Time Insufficient Information Direction Unknown Cost None Bernard Dunstan (McKnight Construction Company) Subject ASI NO.035 Drawing NO.~, 3/A401F, C-201 Spec Section CSI Code 03 30 00 - Cast-In-Place Concrete Detail No. Status 3/A401F Other Ref RFI Instruction Details Pat, the attached ASI is in regards to the exterior exit stair at Female Housing Unit at the rear chase. If you have questions please contact KSGW Architects in writing. Remarks Linked Documents Document Type Drawing Document Open Description Date ASK-33A [E(fjJ ~fiil ~1iI ~l.fj] UNIT F-FEMALE HOUSING FIRST LEVEL DIMENSION 5/19/2009 PLAN UNIT F-FEMALE HOUSING BUILDING ELEVATIONS UNIT F-FEMALE HOUSING BUILDING ELEVATIONS Layout & Staking Plan 1 of 2 5/19/2009 5/19/2009 5/15/2009 Drawing Drawing Drawing ASK-33B ASK-33C CSK-8 http://heery.constructware,com/Common/View/Document_ Display .asp?Docu... 8/6/2009 ~c ,,2 ;;=i ..." . .." m ~ )> r- m :J: o C (f) Z Gl .." ;U (f) -l r- m < m r- o ~ m 2 (f) o 2 -0 ~ 2 o ." m z -< o ,. '" o < m '" ~81ii ;.~~Q ~~ ~~ ~~ mr )> ~ 0 ~ ;;;i i ~ ~ en ~ ~~ ~ . ~ ~ o. ~ 3 f~ " rtH IJl ^ ~ ~i ;;; ... i ~ WEBSTER :WloO -'1 I ~ B s 2~ p~ ' ill I: ffi (1- <..V ~ ~~ DETENTION FACILITY -~ ~ ,oz <..V ~ T~ f;;11 1 , '" I ! .. , " . 1\ ~ ~ :" )> ~ .m ,,;1 AUGUSTA. GEORGlA ~ ~r ,,'~ ~ .Vl 0""" > ~C 0 0 r' " ~ ...., N w ~~ :;=i '.,., .,., m s:: )> r- m :I: o c en Z G> en o c -l :I: ~ m en -l r- m < ~ o )> ~ ~ ~ me. 1 ;;1 S:Z 1: ~" .. (f) i 2." ~ ~ ~ ~:,,~ ^ ~ ~ ~i .. WEBSTER I ~ ~ ~~ W ~ DETENTION FACILITY W ~ .~ OJ i AUGUSTA., GEORGi/\ ~~~ S~E ~.~ ~ Ii ~ ~ o g z ..... ~ o --H_ '\" .. ... ..E E~{ . I ) 3 I ! ~ J I ~ :: -~~l w -0 ;XJ )>0 z:S 00 :r:m oS: ;XJm b~ " m )>en 00 mc 0..... ,,0 s::r: &;6 OZ z" ;XJC -<~ :::c ;qz ~~ ~"T1 . "T1 m :s:: )> r- m I o C en Z Gl Gl c ~ o ~ ;= (') o z z m (') --i o Z o m ~ ;= otSl 0-0 r- 0-0 ;XJm CD-i -<0 )>CD ;XJm 0-0 :r:)> :::j~ iIim 0 -i . )> ~ c m" ~ ~ "z x ~~ m Cf) e.... '1t ~ j ~ ~~ ~ ^ ~ ;; ~ ~~ m I z ~ ~ h WEBSTER CJ.) I DETENTION FACILITY UJ i " () A.UGUS1A. GeORGIA :I' ..,. )> )>-0 ;=.~z-t::C :j5~~~ :r:zO-i h G:l ~ ~~ ~~~o~ ODIV':J:)>~Z ~~r=~~ ~~~(")$ z 0I:I1U\ 0 '-< ~ tSl 6~ ~ ~ 3~ mrn~;: s: <. z CDm 0 g) ~ 6 s: 0 ;XJ ~15 en -i;>:J 2~oa _~mc ~~~~ ~ ~ I il z :1'lill VI ~ ' !1~'lon . ! ill i:~ ~ nZ ~ :~ ~r- .(1) ;2 r- -l N ._,\~. ~I .. - .. --'I . : :":j , I ) ~ 1 ! ~ - ) J . .~_ :r ~;fi 1"- I~I ~I!II~I 'i . s -j!~ '::tI'~: . rilij I I ~~ 5~ ..~'" ~c!~ u: ~N ~-,-... 5' ~c I.... ,:~g~'2~1 ~::j!o~ J'.~"'~':"- R-gl/l g ~f?1oz zV)~ r> CJ~> lJ') ;r>2;j ",00 !;In- " ;J:N. I'l~" ~~~ 0' ~.~ _;:J!,> -..J(")::o ''''0 ?":""fJ) 0- g <',""'~ '"", " \-, J" \~'.. \. \ " '-\ =8.~ . ~ 1"Tl' I. ! s::.:. .': ;:,.. ,.- ,rTvl"Tl "':""::>:zo -,..Jlr:~'() ~;;:;:!;e~)> ~'~',.r o I () II III ,~ I~h !eol n V> -l )> :;:0 n z:;:O 00 1IlV> ~V> '" '" " q ~. 0' 1'-6- ~~ ..."'- ~~-5 .-.!=' . ~.~i f^~~ r " !~ ... n.. :;n 020 .,;;l .".0 -<~ >z in r 8 ~ ~ n I 9 o ~b'~ " ' ..,I':~ z~~ ~"" ",0::.. ,,"''' "'0 ~~~ ,,20 !"'~ o r> V> fT1 n :::! o z WEBSlER DElENTlON FACIUTY ""1111 en I i lti'H~ I I~; :r- ~~ ~ i' '. ..:~ ..,~ 1oIJClIJIITA._ Contractor Change Request Page 1 of 1 NCK Contractor Change Request Project [0400101 - Task 07] - View Date 9/21/2009 ARC - Task 07 - Webster Detention Center McKNIGHT CONSTRUCT1CH'-J COMPANY,It\lC McKnight Construction Company 645 Frontage Road NW P.Q, Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00031 To Bob Munger (Heery International Inc. (Augusta, GA)) Submitted By McKnight Construction Company Date Description Webster Detention PR 35- Extend Water line 40' at Status State Referenced CCO No. 8/19/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days $1,729.50 Work Description Recommendation Response By Response Bob Munger Linked Documents Document Type Doc Document 0400101 - Task 07-01040 Description Webster PR 35 Date 8/19/2009 http://heery.constructware.com/CommonIView/Document_ Disp1ay.asp?DocumentType=3... 9/21/2009 McKnight Construction Co., Inc. GENERAL CONTRACTORS William D, McKnight - President Mason McKnight, III - Vice President Huey E. Carter - Sec. - Treasurer AUG ! 0 2009 FOUNDERS: Mason McKnight, Sr, 1900-1973 Mason McKnight, Ir, 1930-1994 P. O. Box 204718 Augusta, Georgia 30917 August 19, 2009 Office Phone: [706] 863-7784 Fax: [706] 863-2031 Heery International/CIPM 501 Greene St., Suite 307 Augusta, GA. 30901 Attn: Bob Munger RE: Webster Detention Center Cost Proposal PR - 35 Water Line Mr, Munger, During the installation of the new water line at the video visitation, it was discovered the existing water line is actually 40' further than is shown on the contract drawings. The following is a cost proposal for the additional material, and labor to extend this connection. Nordmann Contracting $ 1612.30 McKnight 6% O!P 96,74 $ 1709.00 1.2% Bond 20.50 $ 1729.50 Please issue a change order for this proposal. Sincerely, MCKNIGHT CONSTRUCTION CO. {) Ox,J,. Pat Patrick Project Manager PP:pgn Attachments cc: Jobsite Page 1 of 1 f!!.patrick Subject: "Pat Nordmann" <pjnordmann@nordmanncontracting.com> "Bernard Dunstan" <bernarddunstan@yahoo.com> "Pat Patrick" <patrick@mcknightconstructionco.com> Tuesday, August 18, 2009 3:59PM WEBSTER PROPOSAL - WATER LINE TIE-IN @ VIDEO VIS.pdf; WEBSTER BREAKDOWN - WL @VIDEOVIS.pdf FW: Water Service to Video Visitation From: To: Cc: Sent: Attach: Bernard, We have physically located the existing water line that we tie to in order to supply fire and domestic water to the Video Visitation Building. It is forty feet farther away from the building (east) than shown on the plans and therefore will require additional material and labor. Find attached our breakdown and proposal for this additional work. If there is an alternative the owner or engineer would prefer please let us know soon because we want to begin this work in the near future. Thank you. Pat N. NORDMANN CONTRACTING, INC. P. o. Box 16103 Augusta, Georgia 30919 (706) 733-7285 Office (706) 736-9666 FAX pjnord mann@nordmanncontracting.com ~/1 ~/?nnq NORDMANN CONTRACTING, INC P,O. Box 16103 Augusta, Georgia 30919 Telephone: (706) 733-7285 PROPOSAL Date: Augusta 17, 2009 To: McKnight Construction Co" Inc, p, O. Box 204718 Augusta, Georgia 30917 A TTN: Mr. Pat Patrick Job: Webster Detention Center Water Service to Video Visitation NORDMANN CONTRACTING, INC., hereinafter referred to as NCI, agrees to furnish all labor, tools and equipment required to provide, install, and complete the items of work set forth below in accordance with the plans and specifications for the above mentioned job: Furnish and install an additional 40 If of 4" ductile iron pipe to service the Video Visitation Building & remove and replace existing concrete sidewalk, Additional material and labor were necessary because existing line was not as shown correctly on the plans. Labor Equipment Material Sub total Overhead & Profit TOTAL $ 398.03 $ 225.00 $ 778,96 $ 1,401.99 $ 210,30 $ 1,612.30 Notes: Terms: Add to contract as a change order. This proposal expires thirty (30) days from the date hereof, but may be accepted at any later date at the sole option ofNCr. NORDMANN CONTRACTING, INe. Patrick J, Nordmann President Page I of 1 DAILY REPORT OF FORCE ACCOUNT JOB: WEBSTER DETENTION FACILITY DATE: August 14, 2009 Incumbrance No. NCI # FA 8-1 DESCRIPTION: Additional 4" C-900 water line pipe @ Video Visitation Building LABOR: 1) Eric T. Coleman 4.0 $ 23.75 $ 95.00 2) Mario Molina 4.0 $ 9.86 $ 39.44 3) Ervin Kendrick 4.0 $ 12.50 $ 50.00 4) Quentin Ware 4.0 $ 9.00 $ 36.00 5) Lance Singletary 4.0 $ 9.00 $ 36.00 6) Jose Luis Binzha 4.0 $ 9.60 $ 38.40 7) 8) 9) 10) 11 ) Direct Labor Cost $ 294.84 Payroll Taxes, Insurance & Benefits @ 35% $ 103.19 Total Labor Costs $ 398.03 EQUIPMENT 1) Ford F-250 P/U # 329 1.0 $ 25.00 $ 25.00 2) Hitachi 330 Excavator 1.0 $ 90.00 $ 90.00 3) Ingersol Rand Vibratory Roller 1.0 $ 35.00 $ 35.00 4) Wacker Trench Roller 1.0 $ 20.00 $ 20.00 5) Kawasaki Z 70 Loader 1.0 $ 55.00 $ 55.00 6) John Deere 700 Dozier $ 75.00 $ 7) $ Direct Equipment Cost $ 225.00 Sales Tax @ 0% Total Equipment Cost $ 225.00 MATERIAL 1) 4" PVC C 900 Pipe 40.0 $ 2.10 $ 84.00 2) Concrete (3000 psi) 2.0 $ 104.50 $ 209.00 3) Delivery Charge for Concrete 1.0 $ 85.00 $ 85.00 4) Utilities Locate 1.0 $ 350.00 $ 350.00 5) $ 6) $ 7) $ 8) $ 9) $ Direct Material Cost $ 728.00 Sales Tax @ 7% $ 50.96 Total Material Cost $ 778,96 Net Cost $ 1,401.99 15% Overhead & Profit $ 210.30 Total $ 1,612,30 Contractor Change Request Page 1 of 1 ACK Contractor Change Request Project [0400101 - Task 07] - View Date 9/21/2009 ARC - Task 07 - Webster Detention Center McK~'JIGHT CO~~5TRUCTjOf\j COMPA~-JY, INC McKnight Construction Company 645 Frontage Road NW P,O, Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00022 To Submitted By Description Bob Munger (Heery International Inc. (Augusta, GA)) McKnight Construction Company Date ASI-22 - Addition of Water Heater to G Pod Status State Referenced CCO No. 6/24/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days $64,813,04 Work Description File was too large to upload just the money pages were uploaded the rest will follow via post office. Recommendation Response By Response Bob Munger Linked Documents Document Type Doc Document 0400101 - Task 07-00861 Description Webster PR 19 Date 6/24/2009 http://heery.constructware.com/Common/View/Document_ Disp1ay.asp?DocumentType=3 ... 9/2112009 McKnight Construction Co., Inc. GENERAL CONTRACTORS .v~ ~~ij ~'1\ ([~~ FOUNDERS: Mason McKnight, Sr, 1900-1973 Mason McKnight, Ir, 1930-1994 William D, McKnight - President Mason McKnight, III - Vice President Huey E, Carter - Sec, - Treasurer P. 0, Box 204718 Augusta, Georgia 30917 June 24, 2009 Office Phone: [706] 863-7784 Fax: [706] 863-2031 Heery International/CIPM 501 Greene St., Suite 307 Augusta, GA, 30901 Attn: Bob Munger RE: Webster Detention Center Cost Proposal PR - 19 ASI - ZZ Mr. Munger, The following is a cost proposal to add or modify the water heaters as described in ASI - 22 Menk Company Sack Electric Total $ 58,134.35 2285.00 $ 60,419.35 3625.16 $64,044.51 768,53 $64,813.04 McKnight 6 % alP 1.2% Bond Please issue a change order for this amount. Sincerely, M~wUCTION CO. Pat Patrick Project Manager PP:pgn Attachments cc: Jobsite ',". ,.' ,'THE',S'.A.C.K' 'C.OM'PA.N'Y May'19, 2009 '\ .' .'-. ". .' - . . Project:.W~bster Detention'Center Mcknight ConstructionCo.,'lnc. p.;O., Box 2Q4718. .'. '...' . Augusta/.Georgia 30917 . \' r ..,Regarding: ASI #22/ Sack Electri,cal,Change Order 'C , I I. Pat, .... ... . ,.. .. ..... . Per your- request'o'urpricing fO'rASI #22 is 52.285,00, Please IS5u,e a change Order for this 'arnbunt if we. . are to'.proceed.with.'work: lHlO,nd i,s requited please.addl% to. the total~amount,.'The fqllowing:i$ our .... 'taboraiidmatefiai breakdown:' , . . .. ,. ,'.,". '~~;~:~fir~U~:~:"$'~~jiiii;flJ:'~?~~l~:::;~:s" .'. "X i '15 OH h Profit .. '~I..i:'~, . in.., ,. i ......f ",3 j.: .', [;.,~,' I ' \'<.;{,~.:'S':.\"':.~~,~,'.;.',:.::~~;~;.::''''!\~~..,.';~,~:':f:I:"'~\":'.'.~'::'i~.:-.,,;.'..~..l.';?"'"';"~.'.""~...',;, . ' ' . . ~i;,,"~:~:,"~nrn! i\~!i ~ " . P'): 'r::J r.:.j i:~~'~ ,. _' , . 'c, ~' . .' " " ..' !"'-<',,,,. , ~ ~ 'I,. >>L'~~" ~ J '" ,y' h:,',t " . , ".r~'~ R f. !I~ i ~ ~ ' ;.... ~..,-!I;lRiftl;.1!.j.}JI.f~ll ~ 11',-..1"- r.\'~\.;t ~" ~ ~'~''='r.I''~HI''HJ'':'il!~r.~ft, ,,'--:?':c:t$4Gg97.::25'.~ ~il,~ 71 H!:Ul !Ti'f, j. . $888~> j'YrFf.J " tr-,,', otal'CO'$'2'.2B5~aO'!f'I;~ n ;. ',. ,,", ."\ ,t~~ l' ." I" ,:1" d,. ti '. ',"'1 ,.1, ., '; , """",,,1' ,. ,. !.' ii,'. ,; '"'" -,::..l-.....f..l":-:.'~".~'.'-...'";i}:rtl,~\ ;1\1.1(; :~~IF: ~1hhtlil . t \. '\ ;,~\.~ I ~;"~~~'~,,- -',.t '" ~-'/J.~~t~\'lir.:llt~)~~~~'j , ~~,;,,~".~ ,~t,!~,~.t~:;::~4~:\,~:~~~1.~'}--~;'~:'.~~~~,..(:.~I,. ~~ 't~}{~.::- l>l'l::'~:" I r, '~'r;< t ~ I,J, \<':.',rrl"II~'! . '. . '~Ie'~~e, l~t'.l;Is::knq'w:.if',yoij' Iiave~ a ny q ue~io!1~ to r.!cor:lc~r:hs. ' 'I:;';)]' ',j/ ! ' . /~;,/";;::T::;,: ,:'.::::,:~L), T_':.';;.'~ ,J-i. .; Ii y~~: "',:-:. .~ \.,.;':' i..' "}<::.:.:( I :~ ,-..) i"',,' \:' .... _, '" ....:'::/ f,:- ..t~.. fi. (t . 'Ii. ;/~~.:.,.,:.:,.... L....::,j.:. '. .' ... ,. ..d ' . ." ,.\ . t:;;"':'c,$lncerely, :"<..f:J.. '. . '~(<,~,;,. ,:"i b'il',;'; , , ,i3;t$.,,;::s~:rn~T"Sa~'we~m1p~ny" . , . "",,- 14 1,,, . C..~.~;.~~~:~ . ~o.~ey Hinson-,' , . Seniod),r.o.je:ct M,,!nger. .'1" , .(. ",i ,,' .' , ',. " ) '. - ..'r.' .;. ' :>' I. . ., . ,.~ ' . '.;' .., .........:..-.-. -. ~.. " '\-. ~. ...,,"': . I ... ~ ,'1 ..? electrical .refrigeI"?l~on.hvac . process pipins'plumbi.n!;.t'. mill~ghts '..energymanagement.contra:ctors . riggers , ' ~.. 3302zellMiller~rkWay .'(912)871-8771. 'Electrical Fax: . (912l.6Bi4S17:: ' PostOfficeBox528', . . . $tatesboro, GA. 30458 ".FrOnt qffice Fax::. (912) 6$1 ~6001.. . Mechanical FaX: (912) 681-6317 . 'Sta~b<;>r6, GJ\'30459 . ) 'j \:" i I . I :',1 I I ., . 'I , .1 \ . ., ~ , . . , ., ;, PHONE: 706--724.7371 9he uUenk Company P.O. BOX 3147 AUGUSTA, GEORGIA 30914-3147 June 23, 2009 McKnight Construction Company, fne, 645 Frontage Road NW Augusta, GA. 30907 Attn,: Mr, Pat Patrick RE: Webster Detention Center Change Order Per ASI No. 022 Adds for Male Unit G Dear Mr. Patrick, We respectfully transmit a Change Order in the amount of $ 58,134,35 For the above referenced project. *Clarifications: No electrical or any other type trade work. See attached Breakdown and Copies, Lahor: Journeyman Wage Rate $ 23.52 + (30%) TSS $ 7,05 + Benefits $ 11.13 :: $ 41,70 359 man hrs. X $ 41.70 = $ 14,970.30 Material w/7% tax: $ 24,916,81 Labor: Material: SME CI SouthEast $ 14,970.30 $ 24,916.81 $ 3,847.00 $ 3,153.00 $ 3.164.00 $ 50,051.11 $ 7.507.66 $ 57,558.77 $ 575.58 $ 58,134.35 15% OH&P Bond 1 % If you should have any questions or comments, feel free to contact me. Thank You, ff/l,l.. <-lJ1r P,H.F.Tnlith'V The Menk Company "AX' 7()R-7?4-9911 Sheet :M.eta{fEneineers, 1'#,c . . '. .J. , '.......:....-...-.. t~l::-=-~ t...:..:.......~~....,....~~-:_ )KJ 'nh!:,", l/{fIrl4' OJ (1(Jla( ]1).J(;l.;r · ~.milfct;, gA JC91' ""'62" · ~17lU loo~~-iOSh -\")1': ~(J~.l-;f.W) . ....:.:.:;.~ Tht: MCIU\ Company. rOBox.3J47 Augusta, GA 3091,4 AI1.rl: Vee Smith " ~" TlE: W~bster Detention SM~: .JclbH 6826 Vcc. Pf'r yuur re4ueill for pricillg on AS} #22 & sketch ~.sK~J Q~ tf~;~~\ye:rClerel~-d job we have. th~ foil owi l'lg: . ,Material Curb , Type ".J:l" vent wl2-45's., cap colJar " tla$hing Field l.abor Subtotal C)vcrh~Rd & Pm fit Totnl ~ 1'50,00. . I ~~'34~(W: . -~~..: . S2.9S~~.OO .'':' .. " -.:...W:JJS1' , :..' . .$3\847~.OO :' .,', Sinci!rcly. /"' I . J'" . t' I,I.:,I', l .t )lU:J.I ,),Jtb-..A,.... ~ Chris Uodwill ': 'j ... 'I' From: Jesse Payne [ppaynecisi@hotmaiLcomJ To: VEE SMITH Subject: Webster Detention Center-ASI #22 PSK 8 and PSK 9-Male Housing is the only change that effects insulation as follows; Additional cold-hat-hot water circulating pipe, fittings and valves Insulation Material-$l,200.00 Insulation Labor -$1,682.00 Pipe Saddles/Shields Material-$101.00 .." " Labor -$ 60,00 Identification Material-Supplied by Menk If Labor-$60.00 Valve Tag Material-Supplied by Menk " "Labor-$50,OO Total Additional Cost of $3,153.00 J, Paul Payne Senior Project Manager Carter Insulation and Services, Inc. (Off) (803) 593-5993 (M) (803) 640-0129 Fax (803) 593-5566' SouthEast AUTOMATED SY~TEMS Date: Project: 5/20/2009 Webster Detention Center Building Automation System Proposal #: OB-CG026-ASI#22 SouthEast Automated Systems is pleased to quote the following scope of work for the Building Automation System portion of Webster Detention Center, Augusta GA, as per ASI No.22 ASI No.22 SCODe of work: · Provide control panel, interface relays and automation programming to control and monitor Male Housing gas fired water heaters. · Supply and return immersion temperature sensors will be added to the system for monitoring and alarm. · Current switches and relays for circulating pump control and interlock will be added to the system. · Graphic for system command/control will be added to existing front end console. · Interlock, status and enable of the gas fired heater with flow switch safety interlocks will be added to the system. General Clarifications for work: · All control wirina to be installed in EMT and or rigid conduit. · All area ceiling smoke detectors and/or fire alarm modules are to be provided and installed by others. · No starters, variable frequency drives (VFD's), contactors or disconnects are included. · Control panel power not included. · Dampers of any kind are not included and assumed integral to the unit. · Complete engineered submjttals and as-built documentation are included. · System commissioning and owner training included. · No bid bond or performance bond is included in this price. · All work is to be provided during normal working hours (M-F, 7:00 am to 3:30 pm). Any work required to be performed outside of these hours will be at additional cost. The attached break-down pricing is firm for 30 days. Attached Terms and Conditions apply to this proposal Thank You. Best Regards, Tim Williams Managing Panner Ph: 803-341-9088 Fax: 803-341-9089 Cell: 803-540-7055 SouthEast Automated Systems, UC Mail to: P,O. Box 7570 North Augusta, SC 29861 Ship to: 1213 Summerhill Road North Augusta, SC 29841 08-CG015 Page 1 of 2 SouthEast "UTOM>\,TED SYSTEMS Terms & Condltionti; 1. RENITT ANCES All mvolces shall be aue and payabla upon reoeipl in United Stlltea currency, free of exchange. or any other cl1arges, or as otherwise ~reecl .upon an,d set forth in writing by Sou1hElIlIl Automated Systems, (h8l'einllfter called "Salle!"). The Custaner, if 50 requested agrees to fumish Seller with III information Indudlng finanCIal stlllementl, necellary to make a proper credilsppraisal. Reluslll to supply infolTlllltion may cause this proposal to be withdrawn. Terms of payment origifllllly gnlnted are subjec\ to the approval d continued Cl'8dlt ltl.tU$, Prices Ira SUbject to comlCtion for error. 2. PROPOSALS Proposals lire based upon straight-time labor, Any request by the Custornl>r for overtime we", ahall be conSIdered an extra. Thl. proposal expires 30 days liter i1s dale, sUbjact to the provisions d the tirst sentence 01 the paragraph below antiled "Acceptance 01 Terms' 3. PROGRESS PAYMENTS Seller reserves the right to invoice Customer monthly as the work progresses, for aft ma1ariala aelivered to the job sita or to an otI- .ite faCility lInd to<' all work performed on-lrie and oIr-slle. Engineering. drafting and other mobWiz8lion coats incurred prior to instllNation shall be indudad in Sellel'8 Initial invoice and be equal to filteen percent (15%) of the contract price, InYOices are due upon receipt by Cu&tomer. It the Customer beComes overdue ,n any progrell5 payment. Seller Ihall be entilled to suspend work, shall ~ enliled to inl1lr8st at tile annual rate C1f 18% or the mallimum permitled by tha Slate of Georgia; and allo to lIVailltaelt of any other legsl remedies. Seller shall also be entlUed to interest on all amounls rel80ned by- Customer from progntllS payments or otherwise. Customer.agreesthat he will pay snd/or reimburse Seller for any and all rea..,nable attomeys fees wllich are incurred by Seller in the collectiOn C1f amounts due and payable hereunder. .. CANCELLATION AND SUSPEIlISION Any contract r&sultng from this propenl is sUbjact to cancellation or instructions 10 auspend work by the customer only upon agreement III pay SeHer adjustment charge. 5 TAXES The amount of any tuture IIle&, use. occupancy, excise, or ather tax, federal, state, or local which Seller h..re8ller shall be obligated legally to pay, either on ita own behalf of the Cuatomer or otherwise. with respact to the malarilll covered by this proposal, ahall be lidded to such prices and paid by the Customer 6. LOSS, DAMAGE OR DELAY SeNer shallllot be liable tor any losa, damage. or delay occasioned by any causes beyonCl Selle~& conlrol. including, but not limited to. governmental actionl or ordara, embargoes, strikes. d~rences with workmen, fires. ftooda,'accidents, or transportation delays. IN NO EVENT SHALL SELLER BE LIABLE FOR ANY CONSEQUEIlITIAL OR SPECIAL DAMAGES 7, WARRANTY Saller watr.:lnts that the equipment manulactured anll a&rvlcea fumished by- it and covered by this proposal all!! free from defects in material and workmanahip under nonnal uae and a8I'Vioe and. wlthou! charge, equipment found to be so deI1Ictive in matarlal or workmanship will tie rllpaired or replaced, I written notice of faNurll is recall/eel by Seller within one (1) year llfter date of installation. pIO'<ided Hid equipment hlUl been operated in accordance with SeHer's inatruCtiol'll and provided such defacta SIB not d~. to abuM, fira or d"c;ompoalton by chemical or gllvenie edion. TH IS EXPRESS WARRANTY IS IN LIEU OF AND EXCLUoe:S ALL OTHER WARRANTIES, GUARANTEES, OR REPRESENTATIONS, EXPRESS OR IMPLIED, THERE ARE NO IMPLIED WARRANTIES OF MERCHANTABILITY OR OF FITNESS FOR A PARTICULAR PURPOSE. Seller aasum_ no responsibility for repairs mtlde on Seller's equipment urne.. done by S4IIIers auth0tiZ8d peraonnel, or by- written BUthorlty from S8ller Seller makes no guarantee with rllspect 10 material not manufactured by n, ' 8. PURCHASER'S REMEDIES The Customer'a remedies with IBapeet III equipment found 10 be defeotive in materisJ or workmen..hlp shall be lim~ed eKdUlively Ie the right of repaif or replacement of aucl1 detecllve equipment. IN NO EVENT SHALL SELLER BE LIABLE FOR CLAJMS (BASED UPON BREACH OF IMPLlEO WARRANTY} FOR ANY OTHER DAMAGES, WHETHER DIRECT, IMMEDIATE. FORESEEABLE, CONSEQUENTIAL, OR SPECIAL OR FOR ANY EXPENSES INCURRED BY REASON OF THE USE OR MISUSE OF EQUIPMENT WHICH DOES OR DOES NOT CONFORM TO THE TERMS AND CONDITIONS OF ANY CONTRACT RESULTING FROM THIS PROPOSAL g, PATENT INFRINGEMENT SeNer wal hold its Cuatomer and the Owner harmleas from Infringament C1f any Un~ed Slatell patent ""vering equipmenl of ita manufacture Thi6. of nee_~y, ia limited to the eqUipment per .. and cannot be elllended to application a 01 such equipment in a system. except in writing by an officer of Seller. The Customer and Owner ahall 8l2vlse Seller Immediately in the event any claims of infringement lIRt brought to their attention. 10. GOVERNING LAW Any contract "'lulling from this proposal shali be governed by, construed. and entcrced in accordance with the laws of the Stale of Georgia. 11, CERTIFiCATION The per$On WIlose algnatura appear& on the attached hereof hereby certifies thst. to hia beal knowledge IIf1Cl belief. the snnalead bid is nettile result of any ag~ment. arrangement or und8r518nd4ng between the Seller and any other manulacturer or &elIar of automatic tamperalure control aysb!ms and thBttne prices, teons or condition. thereof have "ot been communicated by or on behalf of the Seller to any such person and will not be communicated to any auch person prior to the offICial opening C1f said bid. 12. ACCEPTANCE OF TERMS This proposal shall become a binding contract between the Customer and Seller when accep\ed in wri~nli1 by tne Customer. Such acceptlloce shall be wlth mutual undel'8tanding that the term. and conditions of thil proposal a", a part thereof with the ....me eflact a. though signed by both panial named herein and .hall prevail over any inconsistent provision of said order. 13 No waiver. lIile ration , or modification of the terms and conditiona on this ancl the anached hereof shall be binding unleal in writing and signed by an authorized rapra$8ntati"., of Seller. SouthEast Automated Systems, LLC Mail to: P.O. Box 7570 North Augusta, SC 29861 Ship to: 1213 Summerhill Road North Augusta. SC 29841 08-CG015 Page 2 of 2 SouthEast Automated Systems, LLC 4. LABOR HRS. ADJUSTMENTS & EXPENSES Pricina Summarv Mech. Elec. spec. Desn. Pro;. Project: Webster Detention Center ASI.22 HourB Hours Hours Hours Hours L.ocatlon: Auguste. GA Estimate Totals: 1--- 0 0 0 01 .Q ____~i!~~~~p~j~.~t~~___________________________________________ Efficiency Adj. /--. J Report Dllte: 512012009 - ==---t==- ---------~!~-Y.2.~!!!_ll!..~~_________1!.1.l~9.Q.9_____._____.____________ TOTAL HRS. 0 0 0 _. 0- () Comments: ASI-22 break-down TRAVEL & EXPENSE FACTORS Oist8nce One-Way: Electrical & Mechanical: r 0 Distance One-Way: Sys. Spec. & Proj. Mgmt: 0 Rate per Mile or Km: SO.55 Per Diem Travel Expenses: $0.00 5. MECHANICAL LABOR Description From To Rate Hours Cost 1. MATERIAL Journeyman 50.00 I 0 $0 DescnDtloo CDS Journeyman 0.1. $0.00 I O. $0 Material list Price 51,200 SuperviSion I . ~~:~g+::-_.~ 50 less Discount @ I 20% L_____E.4i SO Net Material Price 5960 Travel & Expenses $0 Material Escalation @: 0% 1________.Ji.q, TOTAL MECHANICAL LABOR (Transfer to TOtals) IAdjusted Net Material Price $960 011 SO Taxes @ 7.000/. .: $67 . &, ELECTRICAL -4Ang $0 Descrinlion From To Rate Hours Cost Freight @ 3% $29 Journeyman 546.00 01 SO Warranty @ 3% $29 Journeyman O.T. 569.00 -~ SO TOTAL MAT'l PRICE (Transfer to Totals) $1,086 Supervision $0.00 0, $0 Outside Material (Non DOC) Cost t-- .~~ $000 O. SO less Discount @ I 0% ______~~ Travel & Expenses $0 Net Out~de Material Material Price $252 Material Escalation @! o%l__..___~..o TOTAL ELECTRICAL LABOR (Transfer to Totals) 011 $0 !Adjusted Net Outside Material Cost $252 7, DESIGN & MGMT. LABOR ---..-- Taxes @ 7.00% $18 Descriotion From To R8te Hours Cost SO System Spec. $74.00 I 4 $296 Freight @ 3% $8 50.00 I 0 SO Warranty @ 2% $5 Travel & Expenses SO TOTAL OUTSIDE MATERIAL 5282 Design J S80.00 I ---oJ $0 2. SUBCONTRACTS Project Mgmt. $110.00 l J $220 Dewiotion Cost I SO.oo _ 0 SO Electrical S ubcontracl L---~ Travel & Expenses ~$o'O~~E~ $0 Matenal Handimg SO r---- SO SO rrOTALSUBCONTRACTS II $920 TOTAL DESIGNlMGMT LABOR /Transfer \0 Totals) 5516 3. DIRECT PROJECT SUPPORT TOTALS Desoriotion Cost Net Project Cost (From Outside Material, 2, 3 & laber) $1,718 Small Tools & Supplies - Consumable & Expendable SO Overhead @ I 10% I______!!g Major Tools.. Depreciation & RepaIr, Rental SO $1.890 .-.....-..--- Profit @!.q_h_-,ooi.~L.______.!lMl Sub-lotsl 52,079 i .. ....-....---- ........ Material Price (from 1) 51,085 -- OTAl PROJECT SUPPORT $0 OTAl PROJECT PRICE . $3 16<1 ~AS.r - ~.;) ?tfi.;)r& AAI-E LA&~:35g/1,5 ,u~ 1 _ I\J 35- 9: (; D /1--:a-i'( Iv'!, PIH.uJ.~~ + J-l\lAL 'v -L n~i2' <~". IJ~ P.sK. -ID -L p., _I A' '-.~6 I J. .i. c. 1 "1 r-rL:.I ~ V ~ :~~. DC t3 1 b 00 ,< T - J .R L -.. ,- ~ 1- ~-r~ wn"pA.h '-~ ~ \J - _ .:1.. u-I p", ~ I. f) ~ wJF/~~ - -~ I'd) b. Of) v v ~ ~ I r.... -- 1- .. .c: , . . J " ,... 1 J L<:;/~V ;:-~ '" ;.ffi TAAk ~ hf""j ~ f"f!) , r I .. J :J.. 'I .d'vJ- I llJ_ t... 31 b 38' , 'J 4 J~ 1__~ .- ISD 1 Df) J 3'" . ~ ./ I. ,:'.. 1. 135' I, 3S t, :J!I 6d,e ~< 1'1# 5 bt/ I ;:;'0 / ..iI/'/i- I~ I...,. '11f Cl1./ 1 ;;t" 1 ~ J,J.' t"..L I ..... :J li- d 10 , v . d.. 3/,," f~~_ 1/ J 5~ /, I~ - , 1 3jJ.l II / '/'~/.J. J /.1 5t. 5b J 311.{ II Ii),,,,, ~J: I .. I I.:> " J CiS v 13 l&./tJe- -r dA. 'I 'h._. 115 1, ;:, ,..-' , ~J V' 5 j:~. ' .J 1A.4 ~ , 157 1. &5 v ' \J -- "-" -- ~ . 1'7 I '"'~ d.~ .- -- *ASI d..~ PSK- q~PSI<-lo ~, ('..,A ~ - ..c:,cA, '-IV &/k, PE j)~ wi -; ,-; ~4l 2" ~<;d'lOA/~ A~ I orL rl-#h~i!!' ;;('1 PI"f",e.- /)_ / I .~L-".. .1/ . A..1 . \J ;;( ;;; ,t t::.~, ./:.. ~ /_ J , ) . ::J U X ::l.. iJ X .:<. II T~ ~ I ~ ;f J fa i 3 ..:l It &JOD L!( .;:211 /'" ' # <.oJ all x. ~ ,i--' I<Jk,<:;....L'ID ,tl1. I a" JJ l - .:J.. " /' Afl .;;2." Jj .J I.l. -J .... Pm,., / A~l~ 1/1 ~<; u l/()f I~ ~ Ti. i /fJ. J. I ~.I - I . ^'. n,..... I . \ " ' , J J r(" I I I -r->_ ' ?- I -L_~- /11 -' I t~ )tdJ < !P/I ),0 G?) .I III , I 7~ 35~ 350 13(/ ~ r1/ . l0 I.lql/ I ,'1 JJ , / 4 ,I~q 14 /1./ 1~'1 i" :lCf 01 ::2f /.35 ':) 70 ,i" '8 c,9 If}<' } ::1/) C) 3~ 3')LJ ~ . II'\ ;1_ r~' ,. ;-1 JJ ...- --, Ie J DD ~1f)D nD . <8. tJO ~ rf) .." v 3.bD -~ r: "'1 . ...' ",.. ~~8L *AS1;Z~ . @ PSI< - <g I PSI< -9 ,~ P5K -10 7/(. ~M II J~/' tint uJA.Jl'r /-Inf uJ~.j,.r () 1 I . U;1.Jb!!i" ./ ~ , 40', iff' / /' A "-,, TW h- '-J t P/Df" I~ rz :Jf) SO' ,"? " ' I \ .., ... ~ 1/1/ ~ 1 I. ;)D ~D' ::J." . 109 7. ;2D . _.. JDo' JJ. 'u" V I~ I~ OQ J 1./'1 r I.} / .... ~ l~.c;" .-, , ,-'- f d ~.:"J.,.... j , ,'3'1 .... I l~< II. ,.... t" .).) I :1'1 V f '/1./ . (7 ~.I .. . -} LI,I", 4'1" '-#" 7 j:'~ :J. :J'7 "\ ,;/ r/ .~'I)("L~" X. ?,'J ;2, l.r~ '/ " , . t) t:> ~ ;)!~;;.tJ .J. ;l!' I. ~b r "/1./ .! c..... , -. 77 '3/JJ "x. 3~ "J(.3Jl/" ~ . r;' ! 4 1..1 " qooL 2- Jq g 7~ 3 l~" I. hl/ L! () -\ '- . .~ 7:l ;1" i~ ,I'" t". .", : .... .. I......,. JD :J}LJ I' v ItlS4 5 tJJ :J.. 411 R~~.< . .1..,1..l. I'. sJ Ai IhJ. ~/k ' .. liD f; DO 3 ,~" \I \; .SD /, DO 7 4" v ,~.., ~ I. f) J d.. 03 Id. D~ 1j 3'1 )(" ;;;." I V I. qq 1.;- !9~ t"J ;::2 II" lib.." ?S 14. 1.'iO .-. L I 'l;." 'i J" .t..~ l:-J. 17.;2 -:; J II ~ 3jJ,/' .." ......- 51:> . /.. 0g - L. 3)'1 iI){ 'J~" V- ,I/S I gO J ,~ 1/ /..r AI... ~ J 1-:=3 , bJ.. ,2" I V -. 81/ , 84 -.J. I 3/J/' v 5lI 51/ 7.[ I/a'l f:IP.s MiL ..4'1 T ~9 .. , D 5 35 *ASI ~~ @ PS)!-g P.sK-'1.a~ A(,Jt-lo /'..i.J. J.1 uJ. J.{ uJ Il LLVlI.J.. r , . /,.'j- 1,L., ~ I . J. I I /4/11\ I I ~~ ,~ II IILlJ , I ~ " ..,) LJIt} ...,V'. o.;;la 10 1./" ) f ;;'/1) I, JI~ I I,~g Jd.. L~ II \; I Jh/') 1. I/D I J 1./ fJ1) ',- .~ '~IJ I I ~ ,.?: Q., - ~ AlJe~ .- , J~g ~,5D 1 ~~77u.... \J .IS 45 J bt .~ -,~ II. /( J /d.fNJ..,~ J..i<'''I._ .ldL. ,.-IL A-1-~~\ ..., !~ goD I -r:. ~ J ..; ..- :JLJ 1'1'0 k?- 40V J (' L J.l +)/" _ J.. - I ~ -..J t:JO eD"D 5 /; L 11 (, /.1- .-- ~ JIt#"l I '5 ! [) i') {, .. .. J I ~ I~ .---.." .. ... -. - -.- to MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC, . EQUIPMENT, PLUMBING DOMESTIC HOT WATER GENERATORS HORIZONTAL PACKAGE DOMESTIC VERTICAL PACKAGE DOMESTIC STORAGE HEATER STORAGE HEATER 510np Tuk Size Approximate Weilhl Man Storace Tank Siu Appram.we Weipl Man (Ga\kms) DiI.. I LcnStb Ovc.raIl Size (lbs. ) Houn; (Gallons) Dia. x Lcngth OveRIl Size (Un. ) Houn (iu::;hQ ) L%W:xH (iDc:hcs ) L:rWxH (iDches) (inches) 170 30%60 &h: 32 % 61 2S10 30,00 110 6OX60 54X38XBS 2495 30,00 240 3Ox84 106138%67 28SO 30.00 240 30XIW S4X38XI08 - 2790 30,00 338 361M l08x41:r 68 3220 36.00 284 36X72 6OX48XIn 3020 30.00 360 36%96 110 x 47 %70 3500 36.00 --7'338 36X84 6OX48XI09 3210 36.00 600 421108 130 x 47 x 70 4040 39.00 392 36X96 6OXS9 X 121 3400 36.00 770 48X108 .132 x 58x 76 47BO 39.00 460 42X84 nX59XI09 3550 36.00 US 4hl20 144xS8:r76 5100 39.00 530 4ZX96 nX60X120 3800 39.00 lOSD 48%144 17Z158x76 5750 3!l.oo 680 48XP6 78 X 6SX 120 4680 39.00 1235 4S x 168 196166:x 76 6540 39.00 86S 48 X 120 78X74X14S 5180 39,00 1600 601144 178:1:66x92 6920 39.00 1300 60 X 120 !lOX 74 X 148 6210 39.00 l!lOD 6Dx 168 198:1: 66 x: 92 7890 45.00 1980 72X 120 I02X 74X 148 7840 45.00 Z300 72x 144 174x72 1 105 8770 45.00 2720 721168 198x72x 105 10150 54.00 3250 84 1 144 174172% 118 11760 54.00 4170 96 % 144 174x72% 130 14260 S4.ClO NOCes: 1. Above ~ iocludei skid moUlltcd jackelc.d and IiDed lank <:omplete willi :emovabI.c: bEating section and control ~Yes, circulating pumps, trapli, strainers, tbenaometers, pups, aDd reliefs all prepped lIUd wired.. 2.. Weipt based 011 125 lb. w<<ting pressure . 3. HeatiDg medium is 5team. COMPACT PACKAGE WATER HEATER: SEMI-INSTANTANEOUS GPM Size Weigbt Slotage Mall LxWxH (Ibs.) (pIloas) HoIl1'S (ilICbc.s ) 8 39 x 2&x 51 1l3O 27 16.50 16 39%28151 1140 27 16.50 36 41136%52 1225 3S 16.50 43 45x4O%53 1300 4S 18.00 69 4Sx40x 53 l32S 4S 18.00 72 52x42%57 1410 13 18,00 106 52142:r 57 1430 73 18.00 131 S9xS2xS8 1800 120 1950 177 64x60166 2100 19& 24.00 NOles: 1. GPMbased 0040" F to 140" Fwalerwith2 psi stcam. r 2. AbO\I8 package includes skid mOl1lltecl jacketed and liDed tank c:omp1ele with reancrvable heating aec:uon ano control VlI1ves. c:irculatir:1g pwllps, traps, sllainers, thcrmo~ters, puges, and reliefs all prepiped and wired, 3. Wcigbt hued on 125 lb. working prusure 4. Heating medium is steam CMCAA 1972 14-10 Re\'ision -0- (04/01/7"E) €la MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC. EQUIPMENT. HVAC TANKS. EXPANSION EXPANSION TANK ACCESSORIES Oil. ElCplnaion Sc::rd, Fig, ANtra' Capacity Dimen.lon. WeiGhta Men In. Tanio; Witter In lln, In Line Tank {Gall linl ' llba' HDun Galle Airtrol Rot. Fitting Di.meter x L wI" Valve, Ai"rol 125' -;?-ID1: 9 x 32 30 3.00 12 x 30 50 3.00 318 1.85 18 12.36 62 3.00 112 1.88 1.00 314 1,26 24 12.48 73 3.00 30 12.60 7& 3.00 I 1.35 1.35 40 14.60 90 3.00 1 1/4 1.S0 1 112 1.70 60 20 x 48 125 4.50 eo 20 Ie 63 200 4.50 2 1.82 100 ! 24 . 60 260 4.50 2 112 2.2'5 3 2.50 120 24 . 70 338 4.50 150 24 . 114 370 6.00 4 4.85 175 24 . 86 ' 420 6.00 '5 6.25 S 6.75 200 3Ox72 485 (1,00 300 30 x 108 ?60 9.00 8 9.00 400 36 x 96 805 9.00 10 t2.:JQ Nota: ea....clion factor for height not IIeHed if hUI1ll 13 feet or Ie.. olf tn. floot. TANKS. PRESSURE VESSELS ClPKity W8lght Man (Gan llbal HOUri 100 300 4.50 150 400 6.00 200 600 6.00 275 730 9.00 500 1020 &.00 1000 171M) 8.00 1500 2400 12.00 3000 4000 12.00 4000 4"0 18.00 5000 BilBO 18.00 7500 8270 24.00 1??oo 11600 24.00 15000 16700 30.00 " 1892 by MeA" 11.2.. Aeloliaion-2-(2/15182l . MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC, . EQUIPMENT, HVAC PUMPS PUMPS Centrifugal Flexible Centrifugal Duplex Condensate Coupled End Suction Pump With Receiver Diameter Molor DimellSions Weights Man E.D.R. Receiver DimensiollS Weight Man (In) HP (in.) (Ibs) HDurs (Sq. Ft.) Capacity (in.) (lbs) Houri LxWxH (Gal.) LxWxH 11/4 :2 38 x 1.5 x 13 257 6,00 3000 [2 SO x 22x 22 39.5 12.00 11/2 .5 43% 18x 17 389 9.00 6000 12 50xZ2x22 390 12.00 2 10 43x18x21 .3'29 12..00 1??oo IS 48x22x22 440 18.00 21/2 20 48x 19x21 671 12.00 1S000 25 .54x26x22 S5S 18.00 3 30 55 x 24% 21 834 12.00 20000 2S 54x26x2.2 .555 18.00 4 40 .551:24x21 920 12.00 25000 35 56:11: 28x 22 aSS 18,00 5 '0 .55%24x21 998 12.00 30000 35 .56x28x22 655 18.00 6 2S .5.5%24X 21 868 12.00 40000 .55 62:1: 28x 22 720 18.00 5??oo 5.5 62x 28:1: 2.2 765 18.00 Add for Alignment: 0- SO HP 6.00 Man Hours PUMPS PUMPS Centrifugal Duplex Centrifugal Close Coupled Vacuum Heating Pump End Suction Water Air Dimension Motor Weight Man Discharge MOlor Dime Mions Weigh I Man GPM CFM (in.) HP (lb5 ) Hours Diameler HP (in.) (Ibs) Hours LxWx H (in) LxWxH S 1 54x24% 14 1 200 12.00 11/4 1/2 211111 119 6.00 9 6 .54x24x 14 [ 215 12.00 11/2 Il/Z 22x 17 182 6.00 15 9 S4x 24% 14 1112 230 12.00 2 10 29% 17 28.5 9.00 23 9 .57x27% 16 11/2 245 12.00 21/2 20 33:1: 18 371 9.00 30 13 .57 x 27:r. 1~ 2 260 12.00 3 30 3.5 x 18 491 12.00 38 13 63 It 33 x 19 2 27.5 12.00 4 40 36x21 5415 12.00 4.5 13 63 x 33x 19 2 290 12.00 .5 SO 37 x 21 609 12.00 6() 13 63 x 33:1; 19 3 320 12.00 6 25 33 x 22 S04 12.00 PUMPS In Line Circulation Suction Molor Dimeasions Weight Man Size HP (ill.) ((hs) Hours (in) LxWxH 1 1/4 20x 11117 60 3.00 ~1/4 113 21:1t 1111 8 65 3.00 11/2 1/2 Zh 12x 8 70 3.00 2 3/4 2.2 x 12x8 7.5 3.00 2. 1 23x 14x 10 110 4.S0 2 11/2 24% 14x 10 115 4.50 CMCAA 1972 11- 26 R.evision -O-(04120nI) .. MECHANI~AL CONTRACTORS ASSOCIATION OF AMERICA, INC. SPECIALTIES, PLUMBING THERMOSTATIC MrXING VALVES Manual Thermostatic Water M"lXing Valve Unit complete \\lith handle operated dial type mixing valve, union angle check - stops with removable inlet strainers. Screwed connections. Completely factory assembled Connection Sizes Capacity No. of Recessed with Inlet Outlet GPM@ Shower Wall Box or (inches) (inches) 45 Psi. Heads Surface Served. Mounted (Manhours) 3/4 1 25 5 4.13 1 1 30 6 4.43 1 11/4 50 10 4.73 1114 1114 60 12 5.40 11/4 1112 75 IS 5.70 1112 1112 100 20 6.00 1112 11(2 125 25 6.00 ~112 2 150 30 6.38 . 2 2112 225 7:13 2112 3 300 7.88 · Labor for shower he~ds not included. Manual Thermostatic Water Mixing Valve, complete with handle operated dial type mixing valve. pipe mounted. union angle check - stop with removableinletstrainer, volume control & shutoff valve, thermometer vacuum breaker, screwed connection completely factory assembled Connection Size Capacity Inlet Outlet GPM@ (inches) (inches) 4S Psi, 112 1/2 10 112 3/4 15 314 3/4 20 3/4 1 25 1 1 30 1 11/4 50 11/4 1 1/4 60 Man Hours 2.63 2,70 2.8S 3.00 3.38 3.75 4.13 CMCAA1992 13-4 Revision-O-(04~lm) .. to MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC. VALVES BRASS AND BRONZE VALVES * Gate · Globe · Dia. Flgd. Scrd. &rd. Scrd. Swc.al F'I8d. Scrd. Scrd.. Senl. Sweat in. CllSO C. 150 Cl. 200 a. 300 a 150 a. 150 a. 150 a. 250 a 300 c. 150 1/2. .52 .54 .54 ,41 .54 .52 .53 A2 -:;> 3/4 .72 .72 ,75 .56 .72 ,74 .75 .56 1 .87 .87 .851 .93 .66 .88 .851 .90 1.00 .68 11/4 ,91 .1.05 1.0S I.OS .75 .92 1.04 un l.ll8 .77 1112 .93 1,16 1.16 1.23 ,81 .96 1.17 1.19 1.23 .83 --;> 2 1.10 138 1.44 LS8 .94 1.13 1,46 1.49 1.48 .99 2112 1.23 2..23 2.30 2.51 1.50 1.29 2.31 2.51 1.58 -"'7 3 1.35 2,10 2.84 3.11 1.85 1.61 2.84 3,11 1.97 _~4 2.55 .2.98 HOSE BIBB VALVE* BRASS AND BRONZE FOOT VALVES CHECK VALVES BcOme Cast Iroll - DiL Di&. Scrd. Scrd, F1gd. Sweat DiL No Press. No Pres. No. Pres in, Scrd in.. a.12S 0.300 C1.150 a. 12S in Sent Sent F1gd, 1/2 .53 S3 .42 1/2 .69 1/2. .27. 3/4 ,71 ,71 .56 3/4 .82 3/4 .36 1 .87 .87 .68 1 ,91 1 .5() 11/4 1.01 1.01 .88 .77 11/4 1.00 11/2 .65 11/2 1.11 1.11 .9Z .83 11/2 1.05 1.04 2 .81 2 1.37 1.37 1.12- .\)9 '2 1.20 1.19 21/2 134 21/2 2.19 1.35 1.58 21/2 1.57 1.66 3 2.69 1.41 1.97 :; 1.81 1.94 4 2.60 .. 2.51 6 4.43 2.43 8 3.14 10 6.01 12 '.16 CMCAA 19518 8-1 Revision ;,OS-{03115!l18) to MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA I , SPECIALTIES, HVAC STRAINERS TRAPS Dia. aIlS 0.125 a.12S C1.12S Cl.12.5 C1..2S0 0.250 3 . Bucke F&T Thrmc Ball Snap Impulse in. Sere!. Scrd.. Flgd. Flgd. FIgd. Serd. Flgd. Sepnent Trap Trap stat Float Action (Thrml.) Simple.r Simplex Simplu DuplCl: Wye Wye Wyc Camp Trap Air Air Basket Basket Basket Basket TyPe 1Ype 1Ype 'Ii'ap Trap Steel cr. el, cr. C.I. e.I. C.r. 1/2 1.17 2.01 1.02 .67 1.10 1.01 .77 un .77 -," 3/4 1.40 2.01 234 1.28 .73 1.46 1.35 1.13 1.2S U9 1.13 1 1.59 2..2S 2..34 .137 .87 1.71 !.Ss 1.33 2.03 1.76 133 11/4 1.76 2.70 2.58 1.47 1.08 2.10 1.74 2.15 11/2 1.91 2.93 2.70 1.62 1.75 t.27 2.44 2.01 2.63 "-72 2.28 3.27 2.01 3.21 1..64 2.16 2.28 1.56 3.llS 2.5:5 2.8S 21/2 3,48 5.03 2.68 4.95 1.80 2.83 2.86 1.86 3 4.05 5.69 2.75 sm 2.00 3.44 3.23 2.31 DRIP PAN ELLS 4 4.37 7.89 3.38 ),74 5 6.23 10.49 4.34 4.56 Dia. c.r. c.I. CSt!. CSt!. 6 7,47 lUO 5.04 6.26 iD. Scni Flgd.. Sen!. FIgd. 8 8.03 12.29 6.80 7.75 End End End End 10 1Q.82 14.18 9.32 10.22 Z l.24 1.01 12 12.69 15m 1133 13.00 21/2 1.74 lS1 1.80 1.57 14 14.00 16.89 13.83 14.9S 3 2.01 1.70 2.05 1.75 16 15.32 19,17 15.23 15.27 4 3.03 2.81 ),11 2.89 18 16.01 21.51 16.58 20.26 5 4.38 3.76 4.45 3.83 20 19.23 26.30 17.18 Z2.04 6 5.28 4.38 S.34 4.44 24 2135 3L62 2O..S8 2434 8 5.28 5.36 WATER ACCESSORIES * Dia. Flow Flow. Solder Scrd. Flow Hydro Float FlL Opt, BALANCE VALVES in. Meier Meter Mono- Mono- Switch seopic: Oper. AU Vent (CALI BRA TED) Wafer Wafer Do no hdcDe Air AU '11/10' DiI.. Sent Socket F1gd. Type Type ruting Fitting Veat Vent Capi - in, Weld Orifice Flgd. Iary 1n 1.02 .82 In ..38 .75 1-'0 3t. 1.29 ,95 3/4 .86 1.D2 1.10 1 1.48 1 .96 1.20 1.13 1114 U7 11/4 .56 1.05 1.37 11/2 l.n 11/2 .59 1.0$ 1.46 2 2.07 2 1.16 1.65 21/2 2.85 2.SO 21/2 .65 1.36 3 338 2..5S 3 .66 l.36 4 5.39 4 .69 2.30 5 6.23 , 2.60 6 7.IT 6 .78 2.60 8 8.60 S ,9Z 2.65 Note: ~g of system Dol included 10 3,84 12 3.84 CMCAA 1998 10-1 Rcvision-7-(Cl:3/1519S) . MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC. MISC. LABOR OPERATIONS TAGGING & MARKING LABOR OPERATION M&2I Houn ~ wLlll Brass Valve Tag -4> IIIJLIIl Labels., Buds or Direetiou.l At'rolItI ~ IIISLIIl Plastic &paved Plaque .1$ .38~r S1 PIPE BENDING Pipe Setup TUDe Labor per Size MlID Houn Belll1 MaD. Hours 1/1 .75 .38 3/4 .7$ .3& 1 .75 .3& 1 U. .75 .3& 11/2 .." .38 1. 1.OS .38 21/1 LOS ,7$ 3 1.OS .75 311.Z 1.35 1.50 4 135 1.S0 N01"ES: 1.. BcDds up \0 11ll iD.. pipe siz~ ~ assumed co be made wnth rowing &able machiDe. 2.. BeDds m 1. in.. 10 4 ill.. pi~ si:ze life USUmecllO be IIIade wil11 bydraulic beadcr, 3. All brn..:iiIlS aquipmallt e>1ecxtic pcMere4. 4. AU Mcds haw .. radius atleMt . times l11c pipe aiu.. ,. All beads an 90 aqic: or icac. 6. All beads are made in the field. 7. All beads are for schedllle 40 c:arboll stc:el pipe or bcaYicr waiL CM(:AA 1993 17-5 Revisioa. -1- (1011187) to . MECHANICAL CONTRACTOR ASSOCIATION OF AMERICA, INC. . EQUIPMENT, PLUMBING GAS PRESSURE REGULATORS DiL I..a.w DbI.Port Law Press. ill. PrcA. au Reg. Scrd, Flgd. Gas Reg. ScrvAgd. 3/4 1.74 1 1.98 11/4 2.16 1112 3.35 2.30 ~2 3..56 5,51 3 5.64 4 8.76 6 10.58 GAS METERS 12511' 300tJI 6001I' 30011' 6001I' 12511' c.s. Alum. Flgd, Flgd. FIgd, Agd Flgcf. F1gd. Sent Scrd. Turbine Turbin Turbin Po.it. Posit, Posit. Domestic Domestic Displ, Displ. DispJ, 1.31 . 1,52 1.67 1.805 4.29 4.37 2.2S 5.27 7.01 7.41 3.30 7.10 5.07 2.60 4.85 Sl..5!l 7.98 3.02 6.89 8.07 3.95 U4 10.73 6,56 9.35 12.05 Dia. in. 3/4 1 11/4 1112 2 3 4 6 8 10 PACKAGE WATER SOFTENERS: COMMERCIAL Max. Continuous Softener Tank Brine Tank Approximate Approximate TWin Single Exchanse Service Diam. x Height Diam. x Height Dimen. · Weight. Ullit Unit Capacity Flow (inches) (incbc:.l) LxWxH (Ibs) Man MaD (1000', Grains) (GPM) (inches ) Rou" Hours 180 Z70 420 510 600 750 870 5190 Notes: .1. Dimcnsi.on$ and weights are based on Twin Unit which hll$ ZIOf&cner IAInb and 1 brine I&nk. 2. The package includes a dad mounted softener tank and brine tank together with all internal tank piping. face piping. and interconnecting piping all prepipcd at the factory .Ild Ihipped assembled. Add for field piping or field erection of factory piping duasselllbled {or shipment, 3. The fill material is assumed to come leparate from the Llnia. The labor for loading the materUiIs is included in the above unils 4. Labor for handling and/or of nIt i$ not included. 3D 45 65 70 75 100 110 110 20x 60 24 x 60 30x 60 30x72 36%60 361 72 "2 x 72 42 X 72 24x48 30 x 48 36 x 60 36x60 36 x60 421 60 481:60 48x 60 88x28x83 10lx34x83 120x40x84 120x 40x 96 132x46x 86 138x46x98 156 x 52x 100 156x52x 100 1420 Z400 3760 4310 5260 6430 7990 849(} 37 .sO ~S.OO 49.s0 54.00 60.00 67.50 7S.00 &4.00 31.50 36.00 40.50 43..50 48.00 54,00 60.00 67,50 CMCAA 1992 14-7 Revision -OO-(04~lnz) NOlES: 1. Hanger size mU$1 be selected to accommodate steel saddle Dr ill$Ulalioll if so specified. 2. Add tor saddles or shields. Hanger Sizes S1teetmetaJ. Steel In. Shield Saddle 1/2 to 2 .23 .75 14 to 24 .30 1.13 HANGER, ROD & 'e' CLAMP INSTALLATION Hanger Rod Oem Yolce 2 Rod 2 Rod 3Rocl Add to Size Size type Roll Roll inpeze Trapeze Trap. for in. in ea. pipe 112-2 318 .86 .93 1.73 1,49 2.19 .15 2112-3112 112 .92 1.01 1.83 1.58 2.33 .17 4-5 5/8 .98 1.08 1,94 1.68 2.48 .18 6 3/4 1.04 1.16 2.06 1.79 2.63 :1IJ 8-12 718 1.10 131 2.18 1.89 2.79 .21 14-16 1 1.2.3 1.46 2.43 2.12 3,14 .27 18 1118 1.38 1.64 2.72 2.37 3's1 .33 20 11/4 1.53 1.83 3.03 2.64 3.92- 39 24 11'4 1.68 2.06 3.38 2.94 4,37 .45 to --- MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC.O HANGERS, SLEEVES, INSERTS HANGER, ROD & MACHINE DRIVEN SELF DRILLING SHIELD Hanger Rod Clevis Y olee ZRod 2 Rod 3 Rod AdcIIo Size Size T)pc ~on RoU Trapeze Trapeze Trap. for in. in ea. pipe ~1J1-2 318 1.05 1,13 2.12 1.88 2.78 .15 --)::'2112-3112 1/2 1.11 1.20 2.22 1.97 2.91 .17 ......:;> 4 - 5 518 1.40 1.sn 2.78 2.52 3.74 .18 ~6 3/4 1.46 1.$8 2.90 2.63 3.89 .20 8-12 718 1.67 1.88 3.32 3,03 4.50 .21 14-16 1 UlO 2.03 3Sl 3.26 4.85 .27 18 1118 1.95 2.21 3.86 3S1 5.22 33 20 11/4 2.12 2.40 4.17 3.78 5.63 39 24 11/4 230 2.63 4.52 4.08 6.08 .45 CiMCAA 1972 9-3 Revision -Ol-(04mlm) NOTES: 1. Hanger size must be selected to accommodate steel saddle or insulation if so specified, 2. Add ror saddles or shields, Hanger Sizes Sheeunetal In. Sbiekt 1/.2 10 :z .23 14 to 24 .30 Steel Saddle .75 1.13 ~ .' ".. . . MECHANICAL CONTRACTORS ASSOCIA nON OF AMERIC~ INC. i I PIPE CARBON STEEL PIPE PllIiIlEnd ~ TIC II G_ Il..lMd Mh Gm Jaw N g~i 1ft. Sd\~ SdI. 80 SCI'l.IC Sd\. 'Cl SdI. 80 r I SdI. 80 Sc:II. 40 lIciI.80 I Sdl. 180 Bdl. 20 SctI. 'Cl Sell. iO Sdl. 40 210Ft. ~~ 20Ft. 2OF~ 20FL 2llFl. ~ .cl't. 4OFl. 20Ft. 20ft. 40FL 40Ft. :If4 .oa .08 .09 .01 .08 .07 .08 ,06 .oa .06 .08 ,CI .09 .12 ,OIl ;OIl .oa .og ..oa .oa .08 .os 1 1/4 .11 ,t2 .15 .10 .11 .09 .10 .08 .09 .08 ,OIl , 112 .11 .12 .17 .10 .12 .10 .,, .09 .11 .oe .1' ~2 .,. .15 .21 .12 .14 .11 .1~ .11 .12 ,II .12 21/2 .11 .21 ,2g .15 .18 .15 .15 .1. .17 .1. .17 3 .2:l .27 .33 . I'll .2:l .18 ,20 .17 21 .17 ,Ie 3112 .2lI .30 .21 .2$ .20 .21 .20 .204 .1' .20 ~ .29 .33 M .24 .28 .2:l .23 21 .2Il .1& ,21 5 .39 ..u .30 .34 .24 :n ,25 .30 ..21 .a II ,4S ,51 .34 .1.0 .27 ,33 ,2ll .35 .2~ .:10 . .57 ,31 ,~2 ,$2 .31 ,35 .38 ,3$ .1.7 .30 .35 10 .61l .43 .52 .61 .:IS .3lI .42 ..45 .54 ~ .:Ill 12 .Bl .47 .59 .115 .'J7 .~, .4$ .54 .5Q .. M 14 .~ .81 ,.. ~ .43 At .56 .Il2 ,30 ,1.7 18 .eo .85 .13 .41 .4$ .54 .SlI .. ~ .51 II .c .89 .19 .43 .50 ,60 AS .72 .47 ,M 20 .sa .13 .86 .47 ,~ .. .. .78 .50 .62 :M ,71 .113 l.Cl2 .!SlI .12 .., .74 .113 .57 ,77 Note: Refer to P-o. 4-0.2 nCl.~ 2. 3 end 5 · 1991 by MCAA 4.2 RIt\Jlalon.4'15" 6191 I ........ OMECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, IHC, to FITTINGS MALLEABLE IRON SCREW FITTINGS - CLASS 150 Dil. 9lrElI 9O"E11 9C" 180" 90" 45' Tee Red. 45"Wye Cross Caps Coup. Cone. Flush Ground In. Long Red. Street Rctllnl Street Ell Tee Lateral Red. Face Joint Radius l-R Ell Bend Ell Lng l-R l-R BISbing Union Turn l-R 1/2 .51 .47 .27 .51 .27 .51 .74 .69 .74 .96 27 .51 ,4$ .21 .51 3/4 ,69 .57 .36 ,71 .36 ,69 1.02 .92 1.02 1.35 .36 .69 .59 .26 .71 1 .86 .75 ,47 .86 .47 .86 1.26 1.16 1.26 1.65 .45 .84 .75 .35 .80 11/4 .98 ,86 .53 .99 .53 .98 1.44 1.26 1.46 1.92 .53 .98 .89 .42 .90 1112 1.07 .97 .57 1.10 ,57 1.07 1.S9 1,43 1.59 2.l0 .57 1,07 .98 ,48 .99 _"72 1.31 1.14 .69 1.34 .69 131 1.94 1,76 1.94 2.54 .68 1.29 1.13 .51 1.35 2112 2..10 1.89 1.10 2.16 2.09 3.11 2.90 3,12 4.11 1.07 2.09 1..86 .86 2.10 3 2.:a 2.40 1.3S 2.60 2's1 3,7.5 3.53 3.17 4,94 1.29 2.49 2.30 1.OS 2.52 31f2 2.94 2.93 4.37 .5.79 1.49 2.72 1.26 4 3.38 3.00 1.80 3.54 3.35 .5,04 4.59 5.07 6,63 1,70 3.32 2.94 1.47 5 5.48 5.43 8.15 10.79 2.76 4.88 1.68 Ii 6.65 6S7 9.84 8,72 13.04 3.32 5.45 2,70 MALLEABLE IRON SCREW FrTTINGS - CLASS 300 Dia. WEll 90"ElI 90" 4S" 4S" 180' Tee Red.. Cross 'Caps Coup. Colle. Ground In. Long Red.. Street Street Ell Return Tee Red. Joint Radius l-R Ell Ell Bend l-R l-R Union If]. .51 .47 .27 27 .51 .75 .69 .98 .27 .51 .47 ..53 3/4 .71 .60 .39 .39 .71 1.02 .92 1.35 .36 .71 .60 ,71 1 .86 .77 .47 .47 .B6 .87 1.28 1.17 U7 .45 .86 .75 ,86 11/4 .99 ,90 .54 .54 .99 1.01 1.47 1.37 1.94 .51 ,99 .89 ,99 11/2 1.08 1.01 .59 .59 1.08 1.17 1.61 1.52 2..13 .57 1.08 .I)\) 1,10 2 1.34 1.17 .72 ,71 1.34 1.40 1.97 1.80 2..58 .68 1.34 1,17 1.37 21/2 2.13 1-94 1.13 2.12 3.17 2,96 4,17 LOS 2.12- 1.89 2.16 3 2,57 2.~ 1.40 2.5S 3,83 3.60 5.07 1.28 2.55 233 2.60 3112 3.14 3.05 4.62 6.09 4 3,50 3.4S 5.19 4.73 6.84 ),00 3.53 5 5,85 5,70 8.57 6 6.92 6,75 10.34 CMCAA 1992 5-26 Revision -04-(04~)Jn8) CMCAA 1990 -4-6 llcmioa -04- (01lU'llO) . MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC. . PIPE COPPER PIPE AND HARD TUBING 20 FT.LENGTH Sc%ewed GnJOII'edt ~..,;;, Dia. S\'d..Wt. X-BY)' TypeM Type L 'IYPc K. ACR. 1)pc .. 1Jpc L 1)pc K. . In. 1/2 .09 .09 .D6 .06 ..(k) ..(k) -"";1314 .oP .09 .D6 .06 m .()6 1 .m .11 .ll6 ll8 .os .DB 11}4 .12 ,12 ..os .Qll .08 Jl8 11/2 .12- .14 .os Jl8 .Q8 .os _72 .1$ .17 .IS IYJ .D9 .IS 21/2 .20 .24 .D9 ..10 .11 .11 .12- .1Z .12 ~3 .24 .29 .11 .12 .13 .12 .1-4 .15 .IS 31/2 .30 33 .lS .15 .17 .17 _ ";> " .33 36 .104- .IS .17 .17 .18 .20 .20 S A2 .43 .19 .20 .23 .21 .23 .26 Ii .48 .$7 .23 ..2j .30 .26 :n .n 8 m .74 .3(i 39 ,44 10 ,78 ..&3 12 .B9 -Note: Refer to pap 4-(U notCl 2,J aDd S SIlYcr Solder Silver Solder SiIfoI; Iucn ... ~M 'TypeL 1YPeK ACR ~M ~L 'l)pcJC ACR. 1YPe L '1)pc1t 1/2. Jl6 .ll6 .os .ll6 .AJ6 ..os .06 ..06 J)6 3J4 .D6 .D6 .os .os .D6 .Q6 .os .os ..(k) .os ] .os .oil .()8 .os .os .os .os .os .os .os 1114 .os ..08 ,08 .os .os .os ..08 .os ..os .D8 1112 .os .os m .ll9 .os .os .l)9 J1} ..os .l19 2 .m .ll9 .11 .11 JJ9 1>> JJ9 JJ9 1>> .11 21/2 .12 .11 .12 .12 .11 .u .12 .IZ .12 .14 3 .14 _12 .IS .15 ,12 ,14 .IS .15 .14 .17 31J2 .15 .15 .18 ,18 .~ .IS .17 .17 .17 .20 4 .18 .18 .2.1 ..11 .17 .18 .20 .20 .18 .24 S ..n .24 .2.7 .21 .23 .26 6 .27 .29 33 .26 .19 ..n 8 .39 .41 .45 .3(i ..41 .AS to MECHANICAL CONTRACTORS ASSOCIATION OF AMERICA, INC to FllTlNGS WROT COPPER SWEAT FITTINGS-95/5 SOLDER JOINT Dia.. 90"EI1 90"Ell · 4~" 9O"EU 9O"El.\ W 4S' 90" Tee · Red. Street UDion Union In. Loug Short Sbott Ret1. I..oDg Street Street Street Tee Tee exc Dia- Radius Radius Radius 1-R Tangent Ell Ell En Lng l-R le<:lric R8d. 'J\IJu 1-R 1/2 .41 .41 ,41 .36 .36 .23 .23 .23 .59 .54 .59 .41 .59 _;>3/4 54 .54 .54 .45 .45 ..29 .29 .29 .Tl .69 .77 .54 .78 1 .63 .63 .63 .56 .56 .33 .33 .33 .92 .86 .6.5" .94 11/4 .71 .71 .71 .63 .65 .39 .36 .39 1.02 .96 .71 1.08 11/2 .7.5" .74 .74 .69 .69 .41 Al ,41 1.08 1.02 .75 1.17 --=;- Z .86 .86 .86 .75 ,75 047 .47 .47 1.26 L17 .87 lAD 2112 138 1.37 1.37 1.25 .72 .72 .32 2.03 1.89 --=3> 3 1.65 1.64 1.62 1.50 .86 ..84 .87 2.43 2.30 31/2 1-94 1.92 1.89 .99 .99 1.01 2..85 ........;.. 4 2.21 2.19 2.18 1.92 1.16 1.13 1.19 3.27 5 4.14" 4,19. 6.14. 6 S.Ol" 5.08" 7.41. 8 6,98. 6.85" 10m" Dia.. Adapler Red. Street Adapccr Red. Caps Plugs Coup. Cooc. " Ecc. Adapw- Red. Street B1lShing IlL 'I'ecx Adapter Adapter :lI: Adapter Reli Red. :lI: Adapte{ Adapter .1-R F.P.T. Tee: F.P.T. F.P.T. : 1-R 1-R. M.P.T. x M.P.T. F.P.T. F.P.T. M.P.T. l-R l-R l-R -:;> 1/2. ,65 .54 .26 .47 ,42 .23 .05 .41 .36 .36 .21 .23 .os .23 ~3/4 .87 ,69 .33 .63 .56 .29 .05 .54 AS .45 .27 .29 .OS .29 _>1 1.05 .41 ,75 .69 .33 .05 ..63 .56 .56 .32 .33 ,OS .33 11/4 ,47 .86 .78 .36 .71 .63 ,63 35 .39 .OS .36 .....:;> 1112 .sO .92 .89 ,41 .74 .68 39 .41 ,OS ,41 _>2 .59 1.10 5-48 .45 ..84 ,75 .44 .47 .06 ,45 21!2 1.74 .71 1.37 1.23 1.05 .go .71 --:po 3 .84 1.62 1.49 1.28 .84 31!2 .98 1.88 1.76 .98 _>4 1.10 ,,/' 2.16 2.03 1.68 1.11 5 4.07 4.09" 6 4.91 4.89' 8 6.63 6.58" CMCAA 1997 5-51 Revision -3-(OJn.5/97) *,Asr ~d.~ tUvJrb A4J.E .., /Pt(TEIJ~~ 4 ~..~ ;<:3'(;. ~1N 7~ TAx J$ J' ""'," " '7 ,~,-~'iJ~.;.J I Pi- ... 1.L.o. + u. vA L ~t -J 4''> !' '/ . ) t.... .: i. ....; / '~ / I I (;.)/ (; ~ ()phl <. ~A . IJ.I.. P~K.-ID J A-I. A' I J. .L L L - ... Loe Illn !'1 I es DU ru;;Jf'.I L t.o . ..., .<:r- J ~ t -- ~ . ,~.I....-.. - ~M~ u)/T{p' ~.It 'l1Ju.. .:: '"-- " '~ R -I ''J[) .... '"' \ol :J.. u-j I), . ~.J... 0. .A wl~J. 7io 00 1/ ,... I ') DO ~ " 01 . V . I L'A' -r:L ... _. j 1 L:.., .. 11... L ~ .s'iJ,GII_ /85 DO I ." 5. 1)::1 ;' t- ..~ I I 2 "/il'yhM .J.../". -.. , 7~D. 00 1'7 !;;l f) [)!J '. . 'I J-[ fA I -.... 31. Dt) } 4 6' {)D .--..- J 3"''' /'Jn~ IJ 1,1.... I~o DO ~J r. . .J DO ~ ;1/1 6~ d~ '"Uf. . <<'1. co ,.. 'j J. (0 ... 'J I :l II / p,,;r t I fl. jlJi: lI\rl I \, r: DO .. ~JI lA.J IM"_ ,.. (- I - Ji2. DD r: ;;( !t!'D ) v ~ 3J~/' /~ JL I...~ ~ DO ~ ~. r1D . 3/~ JI ./ .1,,,/J t/dut:& _0. J.! J. ~ OD I nl"1 .. ;.,;\...' 3JI.{ II /)) ~ ' }IJ M } Y. It V . ~(, '"Utd 13 I.k.l lie. I AA. C; I,. c.n '6 Y. 6D 1.1 5 .;:> . ..1 . IM.t:, - J 0, 50 5 ,J 5D tI I OJ ., ". .. .-.. ~ ~ 3D, D'O .. - ..- .-. -'" -'-. ., *ASI' ~:2 G?) *ASJ c2~ _ PSI< -~, PSi< - '1 ~ P..c,~ -10 *- uM /1 J.nI-~. . tint 1~ t.JJ>r /-lor uJ~-br D_ . 40'. 1./ 1/ SO' L":? " <ri 0' :J. " I DD' 3//.111 /. ~. , I T~ \L' Apf:. \ ' V' .. I J,/' h. . I i J 3" [..- I ;;;"" "" l./ fiX i./" ~ 1l" -r~r ~ .~~)(,,?U y. ~'I 4 ;1.." ~~.. -i. ~' I '3JLJ"x3JlJx 3/,," 1.0- -4 ,-/0 3 :~" I ~ .2 I' J D 3}4" q DOL yo ~ 4 ., B..tU.lu .. J M' J. ^ ,JJ ~ I.;,..l IC/tc ~ ,~/I v t..: I 4")( 3'" ~ /MU ~ 1../ . ~ II X a" . ~'",.""O b :::2 II" {Ib" UL, , 'l;.,0I ,{ I JI I " )( 3),,/' 3/J!"X II~'I ~ - ~ ". <If 0 ... .. A J. ~ , :;;" I \J 3J4" . I l.-- 4 'I~II F;Ps ~. @ /.1. . ~Ud' ..J 'J. '7. f)q ~ ~~~ f,'{) d./), 1/.5 i /,., .~ It, In" 9.195 '7 a lb. .00 2119 ~ 1 q DC) 1,-:('7'7.100 ~~ I" '7 D'D .., r""J ~ ~I~ .., f'J'D I fl'llJO ~ r7 1',",) , . .,~ L"j. J.~fLJ DO I f... -" ,.';~ , .);(" .)i,/ ~. tJD I '';/ . i 0, 0(: _) ,:wi ~I"I Le- e'" ..'" . ~'" . ,: i .", ". :J.. ! '11/ ......, !..:/ '1 R """ -;.,' I .~ tfi) 3900 I I n.:u 1.~.DO J F;~, 'fSD ::J..lJf) 'J. ", ",<) - . '~# '1'l /)0 } ~ q .~D t.(I)D I) >? ",,1) ,',1 ..... ..- 751 .., I .a.t J 2""7 "1 '/'" ( I.h ~.III'< SOW) - .~.IJ1fp 1:JI}.~4 2.~.(' 17.05 . J, 1'7,1 t:- .g ~ J -. -.... I b.lg5 I 'Klg~ 10.191 I~ ,,-,(1 ,1t5 ....' : .. "--1 r I '. " , , IIJ~L 6 biJ I Ihl~ g.3, 53 *As.r ~~ @ P.5)1- ~ P5J<-9.~ PSJ(-IO r:.lAJ. H W. M w IJ.. L"..Mt ~ 7. I~J~ J.-I~~H~~ " . J. I J Nil) "'JC IN'} I Iq 5 CfD ~- '" II \oJ \ -.J I..!/t ) as I/)() I~ f) 0 C0 10 411 ) t .;(1') .QA I^^ I:J. iO 10, CfD JJ. 3" ~ { J)4/') J,~- ~ j ~ D ro .... "p- Ane Ltkls . -- ~ 5- 50 I 3 r-; .,")[) ~ ~}~ TaA5 /- 1:'1'\ J q 50 \I Jkt ;;. 1/./(. J I IJ ,../ A"mi", J.},Ll L'-'L" ,A-fui! \ J7.5. f)D J ? t" ....-. ~I~ - \wi - .-- J 7e--L ~. ()t) l~ 0 () 0'0 .,j . J c LL/~ -f11'- _ h r. .'-1 J J J J' ( /~.... J,r -. ... , II I~ S. 14"\- ... - L.; 00 - ~ ~ 1=\ !1 I~ nO '''~''_M_._.. . - '-.. - .,.. - ,.- -- -- .- .. Architect's Supplemental Instruction Page 1 of: Architect's Supplemental Instruction Project [0400101 - Task 07J - ARC - Task 07 - View Date 5/15/2009 Webster Detention Center Johnson Laschober & Associates 1296 Broad Street Augusta, GA 30903 Phone: (706) 724-5756 Fax: (706) 724-3955 ASI No. 022 Date 5/5/2009 From William Farmer Johnson Laschober & Associates To Gregory Washington (KSGW Architects) CC Subject Drawing No, Reason for Instruction Action Requested Probable Cost Effect Initial Estimate Cost Probable Time Effect Initial Estimate Time Engineering Conflict Approval Increase Cost Unknown Time Housing Pod Water Heaters Spec Section P-201F, P-202H, P-201G, P-202G, P-401, CSI Code M-102G, E-201F, E-202G, E-202H, E-60( Detail No, Status Open Other Ref RFI Instruction Details G - Male Housing - Add gas fired water heater, modify gas and potable water piping, and add flue vent. Added circuits for pump power. P-401 - Modified gas fired water heater detail to add water heater in male housing. F & H Units - Modified notes to match gas fired water heater detail on P-401. Added circuits for pump power. Remarks linked Documents Document Type Drawing Drawing Drawing Drawing Drawing 'rawing Jrawing Drawing Document Open ESK-10 ESK-ll ESK-5R1 ESK-6R1 ESK-8 ESK-9 MSK-1 PSK-10 _4...L._. In Description UNIT H - MEDICAL MENTAL HEALTH SECOND LEVEL POW... ELECTRICAL PANEL DETAILS - SHEET 1 Panel Details Panel Details UNIT F - FEMALE HOUSING FIRST LEVEL POWER PLAN UNIT G - MALE HOUSING SECOND LEVEL POWER PLAN UNIT G - MALE HOUSING SECOND LEVEL HVAC PLAN PLUMBING SCHEDULES - NOTES AND DETAILS Date 5/1/2009 5/1/2009 5/4/2009 5/1/2009 5/1/2009 5/1/2009 4/22/2009 4/22/2009 ,rchitect's Supplemental Instruction Page 2 of2 Drawing Drawing awing Drawing PSK-ll PSK-12 PSK-8 PSK-9 UNIT F - FEMALE HOUSING FIRST LEVEL POTABLE W AT... UNIT H - MED. MENTAL HEALTH SECOND LEVEL POTABL,.. UNIT G - MALE HOUSING FIRST LEVEL POTABLE WATER.., UNIT G - MALE HOUSING SECOND LEVEL POTABLE WATE,.. 4/22/2009 4/22/2009 4/22/2009 4/22/2009 Distribution Recipient Company Method Date Bernard Dunstan McKnight Construction Company Message 5/14/2009 Bernard Dunstan McKnight Construction Company Email: bernarddunstan@yahoo.com 5/14/2009 Bob Munger Heery International Inc. (Augusta, GA) Message 5/14/2009 Bob Munger Heery International Inc. (Augusta, GA) Email: rmunger@augustaga.gov 5/14/2009 Gregory KSGW Architects Message 5/5/2009 Washington Norman Davis Heery International, Inc. (Dukes Edwards & Message 5/14/2009 Dukes - Subconsultant) Norman Davis Heery International, Inc. (Dukes Edwards & Email: ndavis@augustaga.gov 5/14/2009 Dukes - Subconsultant) Pat Patrick McKnight Construction Company Message 5/14/2009 Pat Patrick McKnight Construction Company Email: 5/14/2009 patrick@mcknightconstructionco,com Pia men Borissov ATC Associates Email: 5/14/2009 Pia men ,Borissov@A TCAssociates,com Ralph Salzmann Johnson Laschober & Associates Message 5/5/2009 ;~I ~dll& figSli nihi I ~iil ;lj;; 1m I: i ~ II o (J) () "t?- '" I '" I'T1 )> r ~ I ;;; I c: (/) I'T1 () '", 0 ~ Z '"0 "- CD II' c Z -i I I 3:: I'T1 o () )> r 3:: D I'T1 - Z '" -i .. )> r r I'T1 < I'T1 r '"U o :E I'T1 ;0 '"U r )> Z ! III ! II ~ · r ! ~ WEBSTER DETENTlON FACILITY 111III: I .....I~ . : . . . .......,.,-- ~ -<B -0 (Jl I --0 :JIFBIiI ;;:1' I ~. I' 'II;t " 1ln ?' ..... co Dl o CD o t.l ~ o ~~~ ~~. ~ i i II ~ iillll ~ ij 11 5 ~ hil!. ~ ,I) .... I;!W '" ;~ 8 co ;u CJ) '" ~ >ij .. fA ~ g:rn ~ "O~m ~ r.~cn ~ ED iii ~ ":c; m"'"r'" ... 5::: ~ ~ ~ 3 ~ I g ~ ~ ~ ~ ~ I ~ ~ g g~ 'C:liil ~':tt :I: ~ !E > ~ ;a ICl en ......~ ~ ~"O C1I~ >19 rail! z!;l .., R' ~ IT1 "'U )> Z rTJ r '1 r ~o )> i$liS! (f) >z ~~ () ::::r <1l !or. a. t:z c - ~R CD p "0 :u 0 :S: m; cl'r z ~m 0 ;;f en ~E "O~ ~." J!I~ '" () >- r ~ Z ~ m ~ I ~ ~ ~ Ii ~ ~t~iIH en I f l"~1 ~n g Ih I :z: B I;m I I "Z =" ...m mr- 1~ I-j N ;~ ihl ..",. -- ./_.'./7 WEBSTER DETENTION FACILITY AUGUSTA, GEORGIA U1 (J) LJ ;;IO rO r'l ;?; :E zZfTl ~C);o r'l ~;o ~- rTJ(/) ;;ufTl )>;0 ~O 0- rTJ)> ::;EGJ )>;0 -<)> (J)~ I !mlRi 0 I C)~~ 0::0")> o PPZ I I I lfl:::O I ..po ~ F; I X.' r'l ~::f -4: pP Z -< I '" If) U1 I ;u "T] -j I '" 00 C) ;0 n I C o P I -j c s: r;1 )> f"Tl :::u z:U -j P I ~ U1 I :~I ;11'11 'lIb) I~ ; II! U 1m i~ ~~ i ~ I ~~~~~~~~~t~~~OL:~'O' n~ ~ ~J ~ ~ J Y - ^ 0 C5 ~~~~~~~~~~~~~~~~~~~~ --~~ - ~ _~__~_ 'll:l:> ~~_~_~~_~O::Ofi1 r- '" "- /";> [;l ~ !l!l! '.: U Ii i pH :, i ! i [ ~" ~ i: ~ ~ H i, < ' i!!! ~ ~ ~ n i i 8 ~ ~o ~ ~ = ~ ~~~~~~ r'l ;}l(; '\. IJ ~t!:::~':I:~ I~!!: u ~ T"'" U1 ~ )> ~~i ~ ~i ~ ~ ~~ iii ~ i ~ * ~ ~ ~ j,rft :~ ~ ~. ~i ~ ~ ~ ~ ~ u ~ ~ ro \~~ D ~Oc ~~IP~'Pa;a{l ~~ ~ ~;~ ~~~igR~ ooo.~~" ~g ~~~."l'~~~~~~<] ~o jll!!!' c~~~~~,~~~~~~ ~1I ~ 1Jl::J::J~>: ).~>" :(< -<:( ~ !::t~~~3~ !!: 'll ::0 o :s: ..,0 ",,,, '" 0'" C -HD OJ 2~ c'tl ::0, "'c ~B\ Z" ",0 r-::o ___.~~~_ . =-z ~~_.~~~~1... ~ ~ ~~~j~~~~~~jj~~jj~~~~j~\ " ~5~~~~~~~~~~~~~~~~~~~W i Illiilll~1 ~_ ! I ~~;_ E~ ..:I WEBSTER DETENTION FACILITY AUGUSTA, GEORGIA ~ .. PANEL HLA Schedule i~1 ;dlll 'XII Ih il~ I E i1~ i ~m ~U> ~^ ~ I 0> II ! I ~ I AUOUSTA, GEORGIA ~ I h ~ '" ~ WEBSTER DETENTION FACILITY 19510 17629 163 147 PANEL HLA SHALL BE 2 SEC1l0N WITH 30 CIRCUITS IN EACH SECTION. COMMON COVER AND TRIM REQUIRED. i Ilrl~1 ~_ II ~~ ill ~ :~ ~ ~ ;:; 0 < 0 r --< .- n ;0 n " c C s:: " Z --f ., ., fTl f s::: )> r 0 fTl '" ... '" I 0 (/) C n (J) )> a; r !:' Z ~ G) 0; ., II I .... :::0 '" c: (J) --f r ... fTl CD :::J < fTl r '1J 0 ~ :::0 '1J r )> Z i~i ~I!I.il j':"~S -!~ i~ilii l ;:! il~ I rn I i ~ I ~ ! IU ~ ! ~I = i Ii I ~ Iltilllll' ~ ~ I .m .z ~~ ~~ ~ "f!fBIi ;~..,....,.. im WEBSTER DETEN110N FACIUTY ......... -- ;~I ~l.Ui6 i '511 ~'Ji .. ~ii~U i . jl h Irn I; i ~ II c ~ i!; ; ~I e , I i ill II II II :11: "'''' II '- II "'~t~. II !: ~ -1111 - II - II - ~ II ~ III~;S:: 1111 ~g I . I 1+ ;n II~ ~2! II ~.,,~ c;) , I - ;:: C'> - --l-- '" -- N "'''' '- .""" ,OJ .. !f'" ",:< 0- 0<'> ." 1 ---+ !f1<1 ~;; I ';: II ;.~ ... ~ .~.~ !ji"J1N .. . ~~I...J... ! ~.i El",: !;. ,~,,=.~.J ~rr~] ~~: ~r_ . ~ '~~ t:1 i! ..r i'I~':-: @ ~ri ",,,, tol'; '-.J r'.-- :; ': I (')..-.... ",r'''C-1 'lol'i' '" ri~'~ WEBSTER DETENTlON FACIUTY ..........- " r )> I ~ ./ ~l~-;:,a "'~ ~z =<cl ! ~~~ ~~:::J fij; I U :""""J ,j ! -. I ."'111 (It ~ ; lIi'HI :JIfB& I ~i:i m1 "."..., I :~ ml E~ ;! ...... 1155 _"'h;""'fj~~ H ..c _ ~ N f-< .....:i :;>- ::I::~ en' ..J~ W' ~ ~i! iii zo I ~ w~ I i1l1i r r3~ Ilf -,hi; ~ l/) ~! lill UI1I::>'O':! NOI1N313C ~31S83M VlDlf03El 'Vlsn~nv J-~~~--U-lri7I iJ--u------ ~ ~~~~I ~~ -_.~~-~----- ~~t ~~ I tJ .'\t.' iIl~lli i~ ,~y/ II: // 1 ~/ II ~o,:f I: I I I: ~~ << (I)'" ZO W 0'" zO . 00'" u-,ID "-0 '" 5:2::l; ~~8 -'" "-- ~a:5 IZW =><i'::l; :r:", - <o~ '" "'<0 UI 0,,- -'w "'(I) ~....... ~ ;0 ----1 ~ 1 "- 1~8 1 10:: I~z 0::0 I 1 ,I '" 1 ~5 II w'I'" I "- W::l;< 1,,0 Vl.......~ I~O e::-N", , I 0:: ......." Z I~z VlZO 1"'0 :r:~U u<'" I , 0::0 1')0"- , -\--.-J ~ :~ <0 :J:~ ~9 , ' ~ I ~ ~ Q C/) l!! l'i !i! ~ "' ~ < ~ ~ ~ < Q li!i III ~ I UII~~ ... !~~ Ili~:! i I ~ 11;-1 .., l z <{ -I a... u <{ > I -I W > '"' w "- ... -I N 0 Z 0 '0 U ~ I W II (I) io ....... '" w -' Z lD < U (I) (I) ::> 0 N I - 0 W -I <{ ~ I o f- Z ::> I.:: _",hi,,,,,!;; 'i> H N I- -l ::Jw ~~ CI)" u:l~ ~ :s::; ~ Z"jr ~ W:. -~p.~~ ~ ::t:O I Ilili WI' 0011,';" l/l iu;H i:\ n: :i '" , ,,0 ",,,, z'" <I >-<; w>- " < -' . ",wa. 00< >-OU UJ:>' Z c;!OS ~~<t -,UJ" ~o~ ~.o:in --:- I 1 I I-"z-- --- --.I ' I N' ,____---1 I > i ~ 'NI i :~--TuJ ~ ,:>' ' i ~ ~' I I I , , I I I t , I I I I 'NI , I I I , I I I I I I I I I L___-----J ,,0 e I I t ~ t:. '" I::' w :>' o :>' '" ~ .,~~ a.<oW :>"I ~~~ _u.. " ~~~ <- . ..J......~ :::>0"- ~~~ U>-_ w :::> -' u.. 0'8 N ~6 VI~~038 -Vlsn~nV' Al.111:l\f:l NOI.lN3.l30 H3.lS83M z :;;' '" c o >- '" 0 w " Cl .. to z~1 ~d ~~cj w>-o >-00 <I:>' w IU;!O- ffi~:i~ a.WUJ ~~og u8.cie 0 z ~ 0 " I _ u ~ ~ ~~ ~ ~ ~ ~ C/)~ 0 ~ z oj '" ~ < i ~ '" Ui w ~ '" < ~ 0 fi!i !~ ! UUU IlilI' ! .f~ i I ~ ~l .., E ~~; ~~:. t~~ arc 11 j tee l g ~ f"~ 1;' z~ ~~ d<___ '/ J) . - > _ J V "", N ~ ....:l ::Jw ~~ (1)1- ..J" W~ :::.:::~ z" W~ :I: 0 Uo U) VIEJ~03EJ 'V1SnEJnV UI1I:)":I NOI1N3130 ~31S83M CJ) Z o en :;: w a: I U I- W >:: CJ) UJ ...J I- ~ t;j UJ J: C/) -~ ~t ~g; ~11~ ~i~ z IJt <: --' 0.. e" >(/)0:::1- 0a5<(O:::::> C> Z <(<-,I-n.. <(Z ,'Z - .............J- 0.. ~~~..c t-= o <-'00 (f) - u... O:::(/)W~ 0.. .q- l.J..<(0::: :::> N (/)<-'00 <(: Z~ ,0 a::: <-'N<(,-", I W J- ~I W <: <.0 0 I :c: --' ~ ~ . ~I ~ .......... <( II ~i r<) , ~~ ~ W 0Cl ....JO ......... WO W --' Uu... I~ l.L..(D w ....J I UL{) <( CO <( W~ L-d U ~u... J- (/) 0 l.L.. 0... .q- M'J.J:. N J- --' ~ - W 0 Z > :::> w --' J- en a::: l.L.. ~ Z ~ 0 i= I "- u 0 :;) ~ en a: N 0 I- ci. Cl 0 CJ) UJ N ~ C/) CJ l- N -' z 0 N <( ?i z -' l- e... C/) ii: z ~ <( 0.. W 0 <( :; w w CJ) W -' W ...J 0.. CJ) <( I- 0.. :;: U <( :;) CJ) Cl CJ) w a: ~i !,=~ lu~!h . ~,., II~ ~~! :>~~ ;I~i~ ~it... = i ii ~ :..t~ 1:;1 ~ ..., ~ N f-< ....:l Ow ~~ tZJl- ...J~ WI- ~; " Z"j a:l'~~e~ W 0( : ~~~~~ :I: 0 i ~:~:;~ U 0 i~.;~H~ en HhH~ N z ~ 0 I J: ~ '" \>'IEl~03El '\>'lSnEln\>' ~ e ::J ~ 0:: 0.. 0> l- e en (j) (!) e ~ Z Cl '" ~ UI1I:>":I NOI1N3130 ~ N ...J '" <( a... ...J I- Z Z 0 W ~ OC w en ~31S83M ...J 0.. ::;; w I- <( w C/) i= ...J :;; W W 0.. I- ...J 0.. W W c5 !;( ::J 0:: w 0 C/) J: CI) C/) i7:~:: ::. ~~:: {~~~ ~~ i. ~~ ~J-:: __ hit c c t s arc .- > ,/ ~ ~ -' - ~i I!;.~ I ~ ~ ~ ~.~ ()!!~"':1l , . ~ ~ "=fi~~~ ;,CgW8 a "':_,.... !h~! Ip ~ d~ .., d: @- ~ 2 <( I.....I 1--0.. .....I~ <(W'-= Wl--~ I <( N ~ 3: o --l w ro :::2 o 0:: li.. 0:: 3: :c "v ........... I") ~ u o U (/)0::1- <iO~ c..?1-0.. <iZ --l - Z ...........~~ ~ ;;: c..? ro o (/)W:::2 <(0:: c..?o~ - Z (0 "N <i '--' .....I <(W I-- .....I (0 2m W<( ~I-- .0 00.. W a:J ~.....I W -t I ~ N I .....I 0 1--0 -2 20 ::::>0 W (f) '0 I " ~ II "co ........... W --l <i U (/) I 0.. 5\!8 ,,6- c..? --l --l ~o IT) --l N Otj I :t;::~ ~ r c h . g~~ ~j'" ~~~.~ I m I :3 I (/) I ei I ~ 001 2 51 ~ (/)1 S i:+' _21 ~1 {;'I ;::;'1 I I I I 1 I 1 I I L 1.. ~ N t- ...:l ::>w ::r::~ r:n" ..J" w= '" ~; ~ ZUI ~ w:. i"I< ~ ::I: 0 I ,!'l~ u 00 il.,ll' ~ l/l illlil; "' Vm~03!:l VJ.sm::Jnv % CO 0 ~ I ~ u ~ ~~ ~ ~ ~ ~ C/)~ 0 ::i ~ z d o.j ~ ~ ~ ~ w '" ~ ~ '" ~ ~ 0 ~ li!i .~ ! Ui~H II 5 ~!i aif~ ~l .., l AiI1l:>":! NOI1N3130 H31S83M '" g ~ '" '" " >-.....~ --'e::'" <io 0 (/)Q. '-' z <( -' CL '-' Z CL Ci- a::: w I- <( ;: W -' >-' (D ... <( ... N I- 0 CL -' ~ 0 I W II > '0) W '> -' Ii w I- co --' <! I (I) U I UJ I a::: I I - ... I I l.J... ~~ i Ii I N '-' ~ n::: 0 r I Z ~'-' ': I z II (I) -I : ::::> 0 I I >-.....~ In ~gs ~ w UJQ. '-' -' I <( I ~ I , I I i I '-' I- Z ::::> 1;:::' i!-55 ~r;; ~H:: N f-< ....1 ~~ en. ...l" w: g ~; . Z"' ~ w~! -Ill' , 5~!i~h: g CIJ Hili l ~ A.1.1lI:>\I'.:I NOI1N3130 ~31S83M in ~ 6 ::i z ~ :> a: i\, ~ OJ ~ VlD~03~ "'Vlsnoov I I 10 ~~ ~(j) G I l:3 ~ ~Z ~_ U) i ~ a..~ w "' ~ w ~ "' ~ ~ "' ~ lI!i I~ ! fil!= ".If'} I!hn ~I ..., l ,..: "- .... N ~ "6 I Ii , l[) '- o z OJ o () .... w en N C) Z en => o I W .....J <( 2 I w -' <( u Vl o Contractor Change Request Page 1 of 1 A<<:K Contractor Change Request Project [0400101 - Task 07] - View Date 9/21/2009 ARC - Task 07 - Webster Detention Center McKNIGHT CONSTRUCT10~'J COMPAr\JY,INC McKnight Construction Company 645 Frontage Road NW P,Q. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706) 863-2031 Contractor Change Request No. 00025 To Submitted By Description Bob Munger (Heery International Inc. (Augusta, GA)) McKnight Construction Company Date ASI 25 - Additional Security cameras Status State Referenced CCO No. 7/6/2009 Pending Submitted Estimated Effects of Request ITime Amount 10 days $76,986.48 Work Description Cost Proposal PR 14 ASI 25 Recommendation Response By Response Bob Munger Linked Documents Document Type Document Open ASI 025 Doc 0400101 - Task 07-00898 ~ iii Description Additional security cameras Webster PR 14 ASI 25 Date 5/13/2009 7/6/2009 http://heery.constructware.comlCommon/View/Document_ Disp1ay.asp?DocumentType=3... 9/21/2009 McKnight Construction Co., Inc. GENERAL CONTRACTORS William D. McKnight - President Mason McKnight. III - Vice President Huey E. Carter - Sec. - Treasurer FOUNDERS: Mason McKnight, Sr, 1900-1973 Mason McKnight, Jr. 1930-1994 P. O. Box 204718 Augusta, Georgia 30917 July 6, 2009 Office Phone: [706] 863-7784 Fax: [706] 863-2031 Heery Internatlonal/CIPM 501 Greene St., Suite 307 Augusta, GA. 30901 Attn: Bob Munger RE: Webster Detention Center Cost Proposal PR -14 ASI - 25 Mr. Munger, The following is a cost proposal for the work described In ASI - 25. (Security Cameras) The Sack Company 151 Total $ 6,336.00 65.431.55 $ 71,767,55 4306,05 $ 76,073.60 912,88 $ 76,986.48 McKnight 6 % OIP 1.2% Bond Please issue a change order for this amount. Call me If you want to discuss this matter. Sincerely, MCKNIGHT CONSTRUCTION CO. -9~ Pat Patrick Project Manager PP:pgn Attachments cc: Jobsite II- . I 12903 Delivery Drive San Antonio, Texas 78247 www.isidet.com AN AAGYL.E SeCURITY COMPANY Phone 210.495.5245 Fax 210.495.5613 July 2, 2009 Pat Patrick McKnight Construction P,Q. Box 204718 . Augusta, Georgia 30917 Re: Cost Change Proposal, ASl #25 Dear Pat: Our estimate for Cost Change Proposal. ASI #25 is $65,431.55, Attached is the quote from my vendor. Regards, Sam Youngbloo . ISI Detention Contracting Enel. JIWIC' ... -- . DETENTION 12903 Delivery Drive. San Antonio, Texas 78247 Phone (210)495-5245. Fax (210)495-5613 www.metroplex-control.com June 23, 2009 Mr. Sam Youngblood IS! Detention 12903 Delivery Drive San Antonio, TX 78247 Reference: Webster County Jail Addition And Renovation Subject: Cost Change Proposal, ASI #25 Mr. Youngblood, 1.0 INTRODUCTION Metroplex Control Systems, Inc. (MCS) is pleased to present this quotation for the Facility needs on the above referenced project, After review of the following information, if there are any questions or should you require addJtionallnformatlon, please contact our office. 2.0 SCOPE OF WORK In response to the information provided. MCS is proposing to change the following: 1. Add (12) cameras, cabling, DVR, Interfaces, labor and warranty for same. 2.0 REQUIREMENTS Our Scope of Work is based on the following reaulrements: 3,1 The timely receipt of change agreement. This price is valid for 30 days from issuance, 4.0 CLARIFICATIONS Our Scope of Work includes the following: 4,1 Labor. material and management to execute the listed change. 5.0 EXCLUSIONS Our Scope of Work excludes the following: 5.1 Attendance to Weekly Job Site Meetings. unless crews are on site and are requested to attend. 5.2 Cost of random Drug Testing or Screening 5.3 Full time Project Management or Field Superintendent on Job Site. 5.4 Sales or Use Tax. 5.5 Temporary power, lighting and site water. 5.6 Concrete work. 5,? All Standard Supply voltages above 30 VAC. 5,8 Conduit and raceway needs. 6.0 PROJECT TIMING AND DELIVERY ---~ .. 1'1- - - DETENTION 12903 Delivery Drive. San Antonio, Texas 78247 Phone (210)495-5245. Fax (210)495-5613 www.metroplex-control.com Equipment will be staged to meet the Owner's schedule. 7.0 WARRANTY To be concurrent with all other MCS provided systems; 2 years. 8.0 COST ANAL VBIS 8.1 Base Bid: Material: $41, 367 Labor: $16, 491.00 Bid Total: $56, 897,00 8.2 BONDSrrAXES/FREIGHT This price does not include any applicable taxes, bonds or bond premium, Metroplex Controls can provide a performance and payment bond if required. Freight Is included In the price above. 8.3 PRICING GUARANTEE Because of conditions beyond our control, this quotation is effective only for a period of (30) days from the date above. Terms of payment are net thirty (30) days from invoice. No cash discounts for prepayment. Any order based on this quotation shall be subject to approval and acceptance by MCS. If you have any questions concerning this malter, please call (210) 885-6918. Sincerely, Metroplex Control Systems, Inc. . Detention Division Robert Ahl Project Manager Metroplex Control Systems, Inc. - Detention Division .' I' <rH.E ;'8 A c..k. '.':C..()'~P'A'N'.y . .' May 19, 2009 , . '. . .;. . ,'Project: Webste,"Dete(lt;~n Center' . . , , . .' , .' .' -. .. ~ , ; '.' ." McKnight Cbnstr\Uction Co~, Inc. ..... P,Q. BOx.2047-18':.... , Augusta, Georgi~.3091? ',' . ' .' .' . , .\ .~ , , ., : '. RegardiiJg~ASt~ 25/ S!lck..Elec~rlcal Change or.~e(' fP. .. ;;.;. ,.'" I".:' . '. .... .'. ."... .': . Pat . . "/" . . '. ' " , , '. , . ,'. , ' '.' .' Perypur reqtlestour priclngfor~I:# 25:15 S6.336~QO:P)ea.se issue a change.l;mierf.or.ttJis amou.nt lfwe '.'. ': 'are to proc.eed<~ith:~oTk, .if bond ;is requi~ed ple~~e add"l% ~?,th~. total ~mo.urit; 'T.he /ollr;>'!'!rig,lsour.' : ...., . labor,:md rriciteripl breakdown: " ,; "'. ." ;:':''':''~c:""~...,,,./'. .: . ". . ..:' ..,...., .' ...:.... ':. ' .., '. I" -...... 1.... .~~ ~~. :,,",..titt.~~~::~~'~f1~~ . ~'" ' . '. .:" ",': ~.:. . \ ..,'. '~ ~ .. '.' T' ...M11~~(~ ~Ir" ~t~..':;::,J.~~~-:~< "t I' ':..~.:. ,.' . .~... '". Labot. ". - " ,:. ,. ~Matel:r ,.' . ~ ..\ .).; :. '~.RE~f~f(."ii";o., '.. .' . ( . . ..' .:, '150 Man.Hours''','''' ". . .", $.-i)53('l'{g~ej>~~:;.r...:.,":::;;'lii5Q~{.~:657:56 :. '..., ',......... ' . - . . '. .': ~ l~..!f. ...~'Irt.:5.../. ',,": ._....;:1r~.;~l . :t~...~... I.~""~l"".'" :.' . , l '.: ., .x $20.00 Per Hours: '. ':_':";' 'x~~Q:Z~TaK<" f.:-':'l!:....'F\ F".{Material:,$j;,p7S...tO..... . :'., '" -.... ; .. ~ .. / '. ..... ......~:li:.;~~.........R -:';i'.. .:.'!..L'i~i:~.ll-\...~& i',' i.~ '1. ~'~':.t:,\. ~,. ~':"1.:.~...,:\""".':"::~""'~' ".. ... . . X 1.3'5 we 55: ;:-;:;;.v;..:'.~' ...', .j'x:J;jl5t'l'ilrl.z.;Pf~TI1; Lj~F: .'~. . . j;",'l" '\, '.;: '.~,' , """':;~,,,. .. . . ;' ".' : X'i:15'bi::j:t!pr~fit~1:~llflti:i" ':.":r .' /A~;r''tH~~t. "II;~II~~r',,, ..~' ;.:: \".<:.~~.. '::~-:.::;.~~:,~:" ,'.', .',,', ..-,: . ::'" ::.::. <,:.' t;,lf.i'(.rrU~l A '. JIl"'" 'W~ ;,.~,..~' : .It.~;\':'' 'f: 'f'~:' .;"; , .... :'.. .', . . . ,,~: .llJlunqa j I"""" c,r-'~""'"~ .[,;: .,......... j. " . ~i! . . ,:'. :"::JJ~~~~f.~~~$hn rrY~! H ~~~. 1:_:-',1 .'.$'~f6~8~f~;~~P;f.~~~i! .r~~ar~~~$6'f36; ~):~. _'" , '1 ~ n !~~~;~:::~:.~~;>:- .'. : -. ',;..f'3 n,'" ,."!i,;,i\,~i!~~H'~,\",,,,,,- ;."." ...... ;..1 ',j""1;...11~.~f. . I.'. ..,.~ f !-:k"" iii~~'qt~lUtlJ:t r,' 1',I.C..j"" .' . 1 'r ~.. I 'ltl~fi.l ~ I. ..~ ...'.... .... .. . 'f" M'" !' .f' ...... ., .' '- . ...~,\.~. .!.....';.hl .., ... . , . . .p.,....' "'II~,,,,..,'t',.r."'f ..-"'I..~'~...,., y';' d" ", ~ . ".". I.'!.',...;.. ",,-'.'.',.." "'''-. \1~ ',"i ,t.~ .1 ~..',." .1,' , .", ease! e~_us'.~now'l 'you "ave'an que..",lons 0.. co cerns. ..;;,:/ .;!' '~"'>' . """ii" .!, 'II I. ~ .. ~ .:, . . . ~?'~ ~ ~ .:.~; :;~'~~~t'~~~~~~'" '..~. ~~'.:'~ .:~\~.- .~,:~~~: ~~'.~:",~' . ~:~} .,~' /~.~' ~-~~:.~~:..;;>~r.~ ~.~ 1'- ~ J:,:,' . . '!/ ,. l ti ~.h'~'''''. 1:i1'" . ,'. ......j.. '\:""'~"',jt:I~" "1';; " ,..b:,"'.. ,!/'./ ,.' .. .' ~i' w.~~; l~~ ~ ' .,V~: . '.'. . ". .1:!;..,...tSiI1~~r.elW~~. ~f, , . . I', ,". \'~~. .', :~:<';i.;}l':( . ~:i ~,:.~ty,.l V .tf. '. . ):.)r ,,,:." ,~~~,:..~. ~ .' '.~\. , . . '. I) . ,. , .... -.t1~f.;1 .. J . ~~..:r..' 'J ft~~ ." 'r~,f;!5' . .{q...,. . ." A-!fJ:':,:,': . fJA . ":,.,.'(-='-':r.I1er.Sac~edmpal1y. ". '1,:'.':...:..' ,... ~i "<l . ...., '. "f.;,"' .'. , . . ,;=..l:i.1:i~~""..~ . *' .' ~.. f. i_~\..:~.;f, . . . ..... . ~ 'a :--.,. ~ ~ .: . A~~k ,M.. ;':~~~~~~~~~~~~~~.~)I . .,~~~~v'. .' _ :-' .. ., . \. _ :~.. ':'~'~~ ~"'!:'_<l.~ I : I": 'C(J..~ :J{Vn.i6JJ,.7i .1 '''. ~1.7r;..\l.'i?~JOI;J'~\""':;:,"r-~' i{,\l,"lH.t):;J'~ 'r';{~i\' . I',', . .. r -'., . ," I .,'. . r,' . .... ,./, .",:..',':'. . . '," :~':.!<..'{~~~:::i~;::;f::~; .'.'ti '~~'t;;;,~' ," . .:. '. '.:, .... . ..' .~ Corey Hinson .... < J.,.:I..~."".~.:~....~.::..-::,.;:::.':-:.:..,_;..,.. ' ..' . .' . . .' ';' -.1...............;.-J:M........_ J" . .Se~ior' Project !'l'anger '.' . '. . . ".- .... t 7' . ,'. I , " >. " .,,' '. ' -. ',. ' .., .'. ., . - , '.. :1, ' ~ .. .: . ., : ... . . ~ .. I. ',' , '. . ... . . ..' - ~. ., ".,..'.'. ~, ..," ", ' 1 ~. , ' ..... :. ..) ,... , . \~ .' '. : , ..; '.: .... ~ .' . " .' , . i '., \. .', " . .- . " . , ,... . !. . '.electrical '. refrigeration. qVac ....process piping · -plumbing' millwrights · erietgy mana!1JElmertt · confracldrS' ~ rip%S . .. ......~.. . .,.. .' ..' ,> 3302 ZeU Miller' ~~y . . (912)' 871-87-71 , SmtBsboro. QA:~0458'. FrontOffjce Fax: (~12).6B1-~001 'EIeetricai' ~. (912) 6814517 'Mechanical fa?t": (912) 681-6317- I "'. '. '." . ," -: , Post Office BoX 528 . I 'Siatesbo1 GA30459 . .0, .... . '. . " '1 , , . '.; i 1./ I '\ I '. 'I . '''1 '! .' , : ~ ' . , - '. - I i I . . . . . \ .... . , . " Request For Quote Page 1 of 1 HE'ERY I View Date 5/28/2009 Request For Quote Project [0400101 - Task 07] - ARC - Task 07 - Webster Detention Center Heery International lnc, (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 Fax: (706) 821-2484 RFQ No. 009 Date 5/26/2009 Cost Event No. Status New Description Add Security Cameras As Per ASI 25 From Bob Munger To Heery International Inc. (Augusta, GA) 501 Greene Street Suite 313 Augusta, GA 30901 Phone: (706) 842-5543 . Fax: (706) 821-2484 Pat Patrick McKnight Construction Company 645 Frontage Road NW P,O. Box 204718, 30907 Augusta, GA 30907 Phone: (706) 863-7784 Fax: (706)863-2031 Funded By Ref No. ASI 25 r Self-Performed Response Due Date 6/24/2009 Returned Date Long Description Provide additonal security cameras as requested by RCSO in accordance with AS! 25, Scope of Work Provide additonal security cameras as requested by RCSO in accordance with AS! 25. I Total - I htto:/ lheerv.constructware.comlCommon/ViewlDocument Disnlav .asn?DocumentTvne=5&Item Tn=?17 4t\? 'iI?RI?OOQ Architect's Supplemental Instruction Page 1 of2 Architect's Supplemental Instruction Project [0400101 - Task 07] - ARC - Task 07 - View Date 5/15/2009 Webster Detention Center Johnson Laschober & Associates 1296 Broad Street Augusta, GA 30903 Phone: (706) 724-5756 Fax: (706) 724-3955 ASI No. 025 Date 5/13/2009 From Ralph Salzmann Johnson Laschober & Associates To Gregory Washington (K5GW Architects) CC Reason for Instruction Action Requested Probable Cost Effect Initial Estimate Cost Probable Time Effect Initial Estimate Time Alternate Proposal Approval Increase Cost None Subject Drawing No. Additional security cameras. LV-2llF, LV-201FC, LV-211F, LV-211G, LV-2llH, E-201H, E-201F, E-602 Spec Section CSI Code Detail No. Status other Ref RFI Instruction Details LVSK-002 - Added interior corridor cameras C-F27 & C-F28 in Female Housing. LVSK-003 - Added 2 wall mount exterior cameras C-F25 & C-F26 on the exterior of Female Housing. C-F25 field-of-view is the employee entrance to the Muster Room, C-F26 field-of-view is the vehicle driveway up to the loading dock, LV5K-004 - Added 2 interior corridor cameras C-FC10 & C-FCll in FC corridor. LVSK-005 - Added 2 interior corridor cameras C-FCB & C-FC9 in FC corridor, LV5K-006 - Added interior corridor camera C-G29 in Male Housing. LV5K-007 - Relocated interior corridor cameras C-G3 & C-G4 for overlapping views in corridor. Added interior corridor camera C-G2B. LV5K-009 - Added wall mount exterior camera C-H47 on MMH Unit for fleld-of-view of the FC Corridor exit door, LV5K-OIO - Added interior fixed camera to sallyport in MMH Unit. ESK-15 - Added power for camera C-H47. ESK-16 - Added power for cameras C-F25 and C-F26. ESK-17 - Revised panel MLA to add circuit for cameras C-F25 and C-F26. .emarks htto:/ lheerv.constructware,com/CommonIView/Document Display .asp?DocumentType= 13 2&ltemID=2329... S/lSI200S Architect's Supplemental Instruction Page 2 of2 .nked Documents Document Type Document OPi- Description Date Drawing ESK-15 ~ UNIT H - MEDICAL MENTAL HEALTH FIRST LEVEL POWE... 5/12/2009 Drawing ESK-16 b8ml1 UNIT F - FEMALE FIRST LEVEL POWER PLAN 5/12/2009 Drawing ESK-17 ~. PANEL DETAILS 5/12/2009 Drawing LVSK-002 ~. Unit F - Female Housing First Floor Security Plan 5/8/2009 Drawing LVSK-003 ~II UNIT F - FEMALE HOUSING FIRST FLOOR SECURITY PLAN 5/8/2009 Drawing LVSK-004 ~II UNIT FC - FEMALE CORRIDOR LOW VOLTAGE PLAN 5/8/2009 Drawing LVSK-005 ~II UNIT FC - FEMALE CORRIDOR LOW VOLTAGE PLAN 5/8/2009 Drawing LVSK-006 ~II Unit G - Male Housing First Floor Security Plan 5/8/2009 Drawing LVSK-007 ~ Unit G - Male Housing First Floor Security Plan 5/8/2009 Drawing LV5K-009 W UNIT H - MEDICAL FIRST FLOOR SECURITY PLAN 5/8/2009 Drawing LV5K-010 1H Unit H - Medical Housing First Floor Security Plan 5/8/2009 Distribution Recipient ComDanv Method Date Bernard Dunstan McKnioht Construction Company Message 5/14/2009 Bernard Dunstan McKnight Construction Company Email: bernarddunstan@yahoo.com 5/14/2009 Bob Munoer. Heery International Inc. (Augusta, GA) Messaoe 5/14/2009 ~ob Munger Heery International Inc, (Augusta, GA) Email: rmunger@augustaga.gov 5/14/2009 tegory KSGW Architects Message 5/13/2009 Washington Norman Davis Heery International, Inc. (Dukes Edwards & Message 5/14/2009 Dukes - Subconsultant) Norman Davis Heery International, Inc. (Dukes Edwards & Email: ndavis@augustaga.gov 5/14/2009 Dukes - Subconsultant) Pat Patrick McKnight Construction Company Message 5/14/2009 Pat Patrick McKnight Construction Company Email: 5/14/2009 patrick@mcknlghtconstructionco.com Pia men Borissov ATC Associates Emall: 5/14/2009 Pia men . Borissov@ATCAssociates.com htto:/ /heerv.constructware.com/Common/View/Document Disnlav.asn?DocumentTvne= 132&Item TD=2329... 5/15/2009 ~ ::!J "Tl :::0 :--l ;~ (J) -I r rr1 ~ .IUII r Jils -u ~;jl'il.. 0 li1ai I :e I iJ rr1 ~ ;0 I rn I 5 IIII ! ; -I! ~ WEBSTER i~ I I ii I DETEtmON FACIUlY d en AUGWfA"lBIUIl\ c: z - -I ::r: I 3:: rr1 0 - (') )> or "-3 ~ 3:: fT1 U) Z (") -I )> m r )> P." r ~ ::c . II rr1 ..... I ... )> 0 Dl . r ~ r------------ I --- I I I I I I I I I I I I I I L_______________ -0 ~~z o )>:i:: m -)> o --1--1 fTl ~:J: 5 or ......0 ......z C'> ~ or- '!:: fTl )> )> Xm ::I:l"ll d ~r- :I: (J) Vl C --1~ Z "T\ --I JTI )>0 z:I: . I 1111111 ,. g i IIII~M ]1 I oZ . !lp.lII '"'~ .... :; m ~~r !i dQ ~ _t> ...... J\) a ..... J 8~ uel< ,-0 -f'-zr- . )> --l --l p:>fTI:Q N~~ I :r~ r- .....Vl · :I: C"> am)> om'!:: z --I [Tl or-:;O C <)> ~IC"> (J}~O '1l-f'-2 J'TI)>JT1 :;OzC"> r-o::::f < 0 o~z :;Om )>~ ~::r z C'>r- Vlt7j ^ I o o to /' _. - .....-:_.J,/, ~I ~dlil llJl1t. Iii i I I EJ =~ 1m I ; i~ II m c Z -I "TJ I "TJ fT1 ~ )> 0 r - (T1 10.) ~ :c 0 u> C ("') (J) > lXl I - ~ z ..... G") , Ol . II ::!] ..... I - :;0 0 en . (J) -t r 10.) (T1 ~ ..., rii ;-I r -0 0 ~ :;0 -0 r )> z III i ; II j ~ II ~ -I en :I:JTl ti)fTl Iu>Z ~ E:I:~ 0', fT'IJTl -If') ---D iJTl oX .....> ~3::: ::0 J :=J~("') IOJTl ~ 10.)1 :=J CD I io ofT'l ("lr' ("ll --~ ~ f')O..... I 8~ Vl~< ,-0 ~Zr- ,)>-1 -I ~fT'I$ f')~~ I -I)> II r .....w 'IO OfT'l)> OfT'l3::: Z -IfT'I oen:::o c r> =i'fo Vl~O '"tJoZ l'Tl~ffl :::0)>("') rZ=' <00 oenZ :::0'" >fTl ~-l -0 BI Vl, ~ '" I o o ("l I '111111 ,. I i 1111:2 -.~I I ;z ~tJ.I...,,'..n .. ra iill :r-. .. i~ ~ .,.". _. - /-.'./.,/, WEBSTER DETENnON FACILnY AUlIUlII'A, __ ;~ i!!IU nil!j I ~J 5~ Imi i 5~ I ~ ! II I Ie ~-'J- , -, ,/, o '" <: ~ 8 P '()iil ~~ :I: " :i> ~ ;01<1 en 1T1~ ;0 ,.., -" 0> Oz 0 ~f!l III "VI!! en tif:l z > g~ :::I 0 ~ z ,.., -0 )> Z fT1 r s::: r ~o )> ;0> "'l!!! (f) ~~ () ::r (1) :"ll: 0.. ~z C NlII (1) ~g 0 p ,.., I!! en ~ ~;;j :::I 0 0 z en:ll r~ i: !; z 0 ~ WEBSTER DETENTION FACIUTY I '11tlll ,. I IIIII~~ ~.il I : = =JI z ~ ~~:I ::;m ~EIJ ~i .. , ~ AU8lJ8TA.--. 111 s . ~M~~_ . ~~V~IJ '~ JlERA t" DAY! [J O~Q / C ) I ~' 0/) 0,-.0 ~v~~. _ Owe;&:~~ " c , / OPEN TO ABOVE OPEN TO A80VI 1m IWIJJ 1~ A , Project Title: hEngineering. LLC Webster Detention Center . BNGINEBRING CONSULTANTS Sketch Title: PHONE: (770) 817-4220 FAX: 17701 23+6878 Owner's Change/Coordination 4343 ShaRowford ROild Suite FS. Marietta. GA. 30062 Elecrronic Path: P"\2007\07001 WEBSTER DETENTION CENTER\fN HOUSE\2009-05-07\LVSK-002.DWG PrOject No: Sheet Ret Scale: Drawn B : 0!H>B-09 PrInt Date: 07001 lV-21IF 1/8'-1'-0' MMK VSK-OO Drawing No. ~ ~ - J --~ rT' II I' CELL IF 0331 r- ~ WALL MOUNT CAMERAS AT J 0'-0" AFG ill WALL MOUNT EXTERIOR CAMERA AT 10'-0" ABOVE GRADE. COORDINATE EXACT LOCATION OF WALL PENETRATION WITH ALL OTHER ENGINEERED SYSTEMS. SEE EXTERIOR WALL MOUNT INSTALLATION DETAIL. ill ALL VIDEO SIGNAL FIBER OPTIC CABLE TO BE ROUTED TO THE VIDEO SURVEILLANCE RACK IN THE EXISTING MAIN CAMPUS SECURITY EQUIPMENT ROOM. PROVIDE SEPARATE RACEWAYS FOR J 20 VAC POWER AND FIBER OPTIC VIDEO SIGNAL CABLES. ALL RACEWAY SYSTEMS TO BE CONCEALED IN INMATE ACCESSIBLE AREAS. MINIMUM CONDUIT SIZE FOR FIBER OPTIC CABLE TO BE J". J~ A , Project Title: hEngineering, LLC Webster Detention Center . J ENGINEERlNG CONSULTANTS Sketch Title: PHONE; (770) B17.4220 FAX. j770j 23+6B7B Owner's Change/Coordination 4343 Shallowford Road SUIte F5. Mariella, GA 30062 Electronc Path P:\2007\0700 I WEBSTER DETENTION CENTER\IN HOUSE\2009-os.o7\LVSK-003DWG PrOject No: 0700 I Sheet Ref: lV-211F Scafe: 1/8"-1'-0' Drawn. MMK 05.(J8-09 Pnnt Date; VSK-OO Drawing No. o WALL MOUNT DURESS BUnON IN COORDINATION WITH FURNITURE P~CEMENT. CEILING MOUNT CAMERA l.Jt:I\lt:I'\I'\L '\lU II:.~: A. FOR ALL 3'-0. SWING DO. INTERCOM STA TrON IN 8 KEY NOTES: (D ROUTE VIDEO AND LO,^, SYSTEM. o WALL MOUNT DURESS 8 PLACEMENT. o MOUNT INTERCOM ST A 1 '::R ROOM c1021 ROUTE ALL SE ROUTE ALL IN CHASE IH 1041 T1\Engineering, LLC J 'kNGINEERING CONSULTANTS PHONE: (7701 817.4220 FAX: (7701 234-6878 4343 Shaflowfcrd Road Suite FS. Marlena. GA 30062 Project Title: Webster Detention Center PrOject No: 0700 I Sheet Ret LV-20IFC Scale: 1/8'-1'-0" Drawn By: MMK 05-08-09 Print Date: Sketch Title: Owner's Change/Coordination VSK-OO EleclI'onlc Path: P\2007\0700 r WEBSTER DETENTION CENTER\IN HOUSE\2009..o!Hl7\LVSK.{)04.DWG Drawing No. OUNTED (TYPICAL) CEILING MOUNT CAMERAS y. "" , " '^ , "~ ~" " / " ..7.../\. / " " IT DATA / ROOM ~ ~ ~~ MECHANICAL ROOM & CH ASE I FC1011 - - - - - - - - - - I I I r--------i I . "JI ~ ~ I ^ ^ ~ ^ ^ JI'. 7.. ^ ,,~^ .~,~, A-x- -L ~~Engineering, LLC Jl 'kNGINBERlNG CONSULTANTS PHONE: (7701 817.4220 FAX: (770) 23~78 4343 Shallowford Road Suite FS. Marietta. GA 30062 Project Title: Webster Detention Center PrOject No; Sheet Ref. Scale: Drawn By. 05-0S-D9 Print Date; 07001 LV-lOlFe 1/8'-1'-0' MMK Sketch Title: Owner's Change/Coordination VSK-OO EJectronic Path: P\2007\07001 WESSTER DETENTION CENTER\lN HOUSE\2009.os.o7\lVSK-OOS,DWG Drawing No. ;'/~:.'-'.::-',-,,:":'~:' '. ..' - . . ~ ....~ :......., -: ...,.... .".",.. o ::l . '.' . .... ..-,...,....., 6=L JO (>~) b~6 ) ] ) ]-5 > ~OPEN TO ABOVE . CEILING M ; rn"Ar-n^ [0 UNT7 fFSI (\ 11\/"lI OP$N TO AaOVE r~ ?r-') ~--D ~O /'-. /~ ~ OPEN TO ABOV:// rC ILlNG MOUNT ~ \ I MFRA " ( ~J D > l~ A , Project Title: ,hEngineering, LLC . Webster Detention Center ENGINBERINGCONSULTANrS Sketch Title: PHONE: (770) 817-4220 FAX: 17701 234-6878 Owner's Change/Coordination 4343 Shallowford Road SUIte FS. Marietta, GA 30062 Electronic Path: P-\2007\07001 WEBSTER DETENTIONCENTER\lN HOUSE\2009-0S.{)7\lVSK-D06.DWG PrOject No: 07001 Sheet Ref: LV-21IG Scale: 1/8'81'.{)' Drawn By: MMK 05-08-09 PrInt Date: VSK-OO Drawing No. J~ A , Project Title: : hEngineering, LLC . Webster Detention Center , ENGINEBRING CONSULTANTS Sketch TItle: PHONE: 1770) 817-4220 FAX, (770)234-6878 Owner's Change/Coordination 4343 Shallowford Road Suite FS. Marietta GA 30062 Electronic Path: P'\2007\0700J WEBSTER DETENTION CENTER\JN HOUSE\2009-05-07\LVSK-o<J7.DWG ~IW = ~ ~PEN T~E I ~ o1Jo] C-GJ ~ _I, c--- ~T I t I I ~ I t : ~1 f- I --& ~-~ o CEILING MOUNT CAME S I WALL MOUN CAMERA AT '4'-0" AFF Project No: 07001 Sheet Rd: LV-2IJG Scale: 1/8'-1'.0' Drawn By. MMK 05-08-09 Print Date: VSK-OO Drawing No. 8H ^ I I I I I I r- CEIILI G MOUNT CAME L______~ 1~ A , Project Title: hEngineering, LLC , Webster Detention Center ENGINEERING CONSUL TANI'S Sketch Title: PHONE: (770) 817-4220 FAX; 1770) 234-6878 Owner's Change/Coordination 4343 ShaRowford Road Suite FS. Marietta. GA 30062 Electronic Path: P:\2007\0700 1 WEBSTER DETENTION CENTER\IN HOUSE\2009-<l5-07\lVSK.oo9.DWG o <D II.Jlv1A TE WAIT I HOBO I r 11("\01 I LAB WALL MOUNT EXTERIOR CAMERA AT 12'-0" ABOVE GRADE. COORDINATE EXACT LOCATION OF WALL PENETRATION WITH ALL OTHER ENGINEERED SYSTEMS, SEE EXTERIOR WALL MOUNT INSTALLATION DETAIL. ALL VIDEO SIGNAL FIBER OPTIC CABLE TO BE ROUTED TO THE VIDEO SURVEILLANCE RACK IN THE EXISTING MAIN CAMPUS SECURITY EQUIPMENT ROOM, PROVIDE SEPARATE RACEWAYS FOR 120 VAC POWER AND FIBER OPTIC VIDEO SIGNAL CABLES. ALL RACEWAY SYSTEMS TO BE CONCEALED IN INMATE ACCESSIBLE AREAS. MINIMUM CONDUIT SIZE FOR FIBER OPTIC CABLE TO BE 1", & PrOject No; 0700 I Sheet Ref. L V-21l H Scale: 1/8'-1'-0' Drawn By. MMK 05-0S.09 Pnnt Date; VSK-OO Drawing No. 1m '~I ~I~CH [H104l UP SP I rmJ3 1- STG. C ELEC [Hi02A] I H102 I ~E'4 o ) DB ~ T1\.Engineering. LLC J "kNGINEERING CONSULTANTS PHONE; (770)817-4220 FAX: {no! 234-6878 4343 Shaflowford Road Suite FS. Marietta. GA 30062 Project Title: Webster Detention Center ProJect No: Sheet Ref. Scale: Drawn By. 05'0lHl'l Pnnt Date; 07001 LV-2I1H 1/8'= I'-Q' MMK Sketch Title: Owner's Change/Coordination VSK-Q 1 Electronic Path: P:\2007\0700 I WEBSTER DETENTION CENTER\IN HOUSE\2009.{)5-07\l VSK-D IO.DWG Drawing No.