CONSTRUCTION CONTRACT CHANGE ORDER
1
See attached
12/22/06
PROJECT TI'ILE
ORIGINAL CONTRACT DATE
OWNER AUGUSTA, GEORGIA
12/22/06
Belair Hills Subdivision Sanitary Sewer System
PROJECT NUMBER
PO NUMBER
5QDQ
112SZ1
The following change is hereby made to the contract for the above project
Description of Change (for a more detailed description see attachment):
Add 145 additional sewer ties and associated piping, extend the sanitary sewer by 1,315 linear feet, and correct
unforeseen roadway deficiencies at Ruth, Murray, and Hilda Streets. Approved by Augusta-
Richmond Commission 12/19/06
PAYEE Chandler Construction Services, Inc.
TOTAL AMOUNT OF THIS CHANGE ORDER
$
253,500
The contract time will be INCREASED by 120 calendar days as a result of this change.
ORIGINAL CONTRACT AMOUNT $ $4,135,310.00
PREmOUSCHANGEORDERONCREAS~ $ 0
THIS CHANGE ORDER ON CREASE) $ 253,500
TOTAL REmSED CONTRACT AMOUNT WITH CHANGE ORDER $ 4,388,810.00
FUNDING NUMBER/ACCOUNT NUMBER
510043420
PROPOSED BY:
l I I ))J150130
r-JA-/~
Vi CONTRACTOR
j"t) ~
~~
REQUESTED BY:
SUBMITTED BY:
FINANCE ENDORSEMENT:
.f:f/jlIM&!5/(U(l1.' (!,1"IJ1
COM7/.-d
ADMINISTRATOR
:{f$-
or
Approved BY:
Approved By
54-25210
54-25210
DATE: j') '-1J-~()6
DATE: /2 /~7/"b
DATE: /2/Z,7(O~
DATE: /.2 - 28-~ y:;
DATE: J L//[ ~ )'-
.
DATE: 1/2- IDh
RECEIVED
DEe 2 8 2006
ACCOUNTING
DEPARTMENT
~
, .
Belair Hills Sanitary Sewer---Chan2e Order#l Summarv---
(Bid Item #06-097)
Item Cost Reference
Murray Street Repair $43,881 Chandler Construction Services letter of 10/1 0/06
Foundation Backfill
Adjustment @ $21.00
(Estimate of 1300 C.Y.) $27,300 Chandler Construction Services letter of 11/10/06
145 Additional Sewer
Services @ $810 each
$117,500 Chandler Construction Services letter of 8/28/06
Additional Milling for
Ruth, Hilda,& Murray
Streets @ $3.20 S.Y.
(Estimate of 4844 S.Y.) $15,500
Chandler Construction Services letter of 10/12/06
Extend Sewer on Padrick, $49,319
Ruth, Grape, Murray,
Bolton &Barrett Streets
(Increased estimates
of quantities applied
to bid items S-6A,S-7-A,
S-8A-l,S-8A-2 & S-22A
Directed by AUD letters 8/9//06, 9/8/06, 10/5/06,
& 10/27/06
The total cost ofthe contract change is $253,500. The negotiated contract time extension
is 120 calendar days. The new contract completion date is 9/7/07.