CHANGE ORDER
NUMBER 1
DATE 11/1/99
PROJECT TITLE Bedford Heights Water and Sewer System Improvement
ORIGINAL CONTRACT DATE June 29, 1999 _ PROJECT NUMBER: U98-0098
OWNER Augusta-Richmond County Commission-Council P.O. NUMBER: P11740
CONTRACTOR Blair Construction, Inc.
The following change order is hereby made to the proposal for the above project:
6" Water Main LF $17.10 3,825 LF $65,407.50 5,710 LF $97,641.00 $32,233.50
2 Fire Hydrant EA $1485.00 3 $4,455.00 5 $7,425.00 $2,970.00
3 6" Tapping Sleeve EA $1,310.00 8 $10,480.00 3 $3,930.00 ($6.550.00)
4 6" Valve EA $692.00 0 0 6 $4,152.00 $4,152.00
5 8 x 6 Tapping EA $1,460.00 0 0 $1,460.00 $1,460.00
Sleeve
6 8" Sanitary Sewer LF $21.30 3,400 LF $72,420.00 3,433 LF $73,122.90 $702.90
(8-10)
7 Water Services EA $399.60 20 $7,992.00 37 $14,785.20 $6,793.20
(Near Side)
8 Water Services EA $747.35 26 $19,431.10 43 $32,136.05 $12,704.95
(Far Side)
Change $54,466.55
Order
Amount
TOTAL AMOUNT OF THIS CHANGE ORDER $ 54,466.55
The contract time will be increased/decreased by 0 Calendar days as a result of this change.
ORIGINAL CONTRACT AMOUNT
$
896,771.02
PREVIOUS CHANGE ORDER (INCREASE/DECREASE)
$
0.00
THIS CHANGE ORDER (INCREASE/DECREASE)
$
54,466.55
TOTAL CONTRACT WITH CHANGE ORDER $ 951,237.57
************************************************************************
FUNDING SOURCE/ACCOUNT NUMBER
JnL:507043420-5425210
G/L: 89800090-5425210
REQUESTED BY:
Robin A. McMillon
ENGINEER
DATE: 11/1/99
11/01/99
~ ,. 'C.'
-;-
'.
SUBMITTED BY:
Max Hicks '111:/-
DEI) ARTMENT HEAD
FINANCE ENDORSEMENT:
~M~"~b
RECOMMENDED BY:
APPROVED BY:
DATE:
DATE:
DATE:
11/1/99
IIl11/'1f
p-/>/~)
~ATqtJ
11/01/99