CHANGE ORDER
NUMBER:
1
DATE:
6-11-97
PROJECT TITLE:
Bovkin Road Drainaqe Improvements
ORIGINAL CONTRACT DATE:
9-16-96
PROJECT NO.: 51-8775-094
OWNER: Augusta-Richmond County Commission-Council P.O. NUMBER: 128211
CONTRACTOR:
Mabus Brothers, Construction CompanY, Inc.
The following change order is hereby made to the proposal for the above project:
(SEE ATTACHED SHEET)
Add: (A) Seven (7) water main offsets
(B) Ductile iron pipe 145.6 LF @ $35.46/LF
= $ 9,725.00
= $ 5,162.98
(C) Drop Inlet, Gp 2. Special Desiqn 1 each @ $2.300
= $ 2,300.00
(D) Plain conc. ditch pavinq 888.57 SY @ $20/SY
= $17,771.40
(E) Excavate. repair septic tank and drain line - resod
yards 3 @ $2,287 each = $ 6,861.00
TOTAL AMOUNT OF THIS ORDER:
$ 41.820.38
The contract time will be increased/--------- by ~ calendar days as a result
of this change.
ORIGINAL CONTRACT AMOUNT:
$ 1.273,410.85
PREVIOUS CHANGE ORDERS (INCREASED/DECREASED):
$
$
.00
THIS CHANGE ORDER (INCREASED/---------):
41.820,38
TOTAL CONTRACT WITH CHANGE ORDERS:
$ 1.315.231.23
****************************************************************
FUNDING SOURCE/ACCOUNT NUMBER:
PROJECT CONTINGENCIES
REQUESTED BY:
Robert Clements
DATE: 6-10-97
DATE: 6-10'-97
DATE: 7/7{#1
DATE: '1 ! q.l<2t 'I
DATE: r~f~,7
SUBMITTED BY:
RECOMMENDED BY:
APPROVED BY:
7" p ~
Ij or
,
fA)
B)
(C)
I~
-...
Mabus Brothers Construction Co., Inc.r
920 Molly Pond Road
Augusta, Ga. 30901
706-722-8941
Fax 706-722-7521
TO: Public Works/Engineering
1815 Marvin Griffin Road
Auqusta, GA 30906
CHANGE ORDER
C/O # 1
C/O DATE 6/9/97.
JOB NAME BOYkin Road
JOB #
ST ATUS (NP)
DATE APPROVED
WE HEREBY AGREE TO MAKE THE CHANGE(S) SPECIFIED BELOW:
WATER LINE OFFSETS
2" W/L OFFSET @ STONE RD./MONCRlEFF ST.
3" W/L OFFSET @ERVAY ST. I TRAVIS RD.
6" W/L OFFSET @ FIELDCREST RD.
6" W/L OFFSET @ SOUTHFIELD DR.
6" W/L OFFSET @ BOYKIN RD. I STONE RD.
6" W/L OFFSET@ STONE RD. I MONCRIEFF ST.
6" W/L OFFSET @ STONE RD. I TRAVIS PINES RD.
STA. 0+50.0 STONE RD.
STA. 1+89.0 STONE RD.
STA. 4+81.4 STONE RD.
STA. 9+58.0 STONE RD.
1 EA @ $1,000.00 = $1,000.00
1 EA @ $1,100.00 = $1,100.00
1 EA @ $1,525.00 = $1,525.00
1 EA @ $1,525.00 = $1,525.00
1 EA @ $1,525.00 = $1,525.00
1 EA @ $1,525.00 = $1,525.00
1 EA @ $1,525,00 = $1,525.00
SUB-TOTAL
$9,725.00
DUCTILE IRON PIPE CROSSDRAIN 16"
39.2 LF @
36.8 LF @
37.0 LF @
32.6 LF @
$35.46
$35.46
$35.46
$35.46
$1,390.03
$1,304.93
$1,312.02
$1,156.00
SUB-TOTAL
$5,162.98
DROP INLET
PAY ITEM 668-2205 DROP INLET, GP 2, SPCL. DES. (DITCH DROP INLET)
1 EA @ $2,300.00 $2,300.00
SUB-TOTAL
$2,300.00
An Equal Opportunity Employer
.., ",11'. ~_.-, ~.:..:...! .-
1'- If..;.,...
f
(D)
(~)
~
PUBLIC WORKS / ENGINEERING
JUNE 9, 1997
PAGE 2
PLAIN CONCRETE DITCH PAVING 4"
- 888.57 SY @ $20.00
'I
$17,771.40
SUB- TOTAL
$17,771.40
EXCAVATE / REPAIR SEPTIC TANKS AND DRAIN LINES - RESOD YARDS
3818 SOUTHFIELD DRIVE $2,287.00
2310 ROCKVIEW DRIVE $2,287.00
2308 ROCKVIEW DRIVE $2,287.00
SUB-TOTAL
$6,861. 00
TOTAL
$41,820.38
DATE OF ACCEPTANCE
SIGNATURE
(OWNER)
$MCc'5 fxr/#6k'r- dvS7V & ;:t.<--.
/;:~