Change Order Form
Change Order Number: Six Date: February 28, 2005
Project Title Barton Chapel Road. Ph. II
Original Contract Date: 04-15-03 Project Number: 322-04-292822678
Owner: ARC P.O. Number: P75245
Contractor: Beams Pavement Maintenance Co.
The following change order is hereby made to the proposal for the above project:
See Attached Sheet
TOTAL AMOUNT OF THIS CHANGE ORDER
$
9.120.15
The Contract time will be increased by 7 additional days due to this change order.
Original Contract Amount
$ 2.364.707.93
Previous Change Order
(Increased / Deoreased)
$ 205.582.20
This Change Order
(Increased / Decreased)
$ 9.120.15
-
TOTAL CONTRACT WITH CHANGE ORDER(S)
$ 2.579.410.28
Jt-
~
*************
Recommended By:
Requested By:
Date:
Submitted By:
Date:
Approved By:
Date: '0 I I Vj~
Date: <J/;//c .J'-
Date: '/17~S
, f
Date: .7 - ;( ~Ub
Accepted By:
Copies: Assistant Director-Engineering
Procurement Geri Sams
Kakoli Basu, Accountant, PWE
Pre-Construction File
.
6-27-1995 7:51PM
FROM
P.2
"
.;
#
\'
Beam's Contracting.
Bobby Matthews.
2335 Atomic Road
Beech Island S.C. 29842
Thursday 2/24/05
Ricky LaBrew
Re: Catch basin 46 Barton Chapel, Change To 18" Pipe
Additional cost for installing Catch basin 46 and l11110ing pipe to catch basin 53 and changing to 18" pipe
1) lnstal1465' of 18" pipe @18.33 a foot
2) Delete 50' of 15" pipe @ ]5.20 a foot
$8523.45
($760.00)
+$7763.45
Total change for pipe
3) Reconstruct catch basin 53
+iJ 356.70
Total extra cost for change order
$9120.15
Total time needed
7 Days
Thanks
4-I4~
Bobby Matthews
~ ,
""
'"
;'
;
Project :Barton Chapel Road Improvements Phase II
Project CPB #: 322-04-292822678
A conflict with an existing 20" water main and sewer lines are preventing the installation
of 15" RCP storm drain pipes from catch basin # 45 to catch basin #46. 18" RCP storm
drain pipes will be used in lieu of the 15" RCP storm drain pipes. The total cost of
$9.120.15 is available in the project construction account for Change Order #6.
ITEM # Description OTY. UNIT PRICE TOTAL AMOUNT
550-1180 Storm Drain Pipe, 465FT. $18.33 $8,523.45
18 In, H 1-10
611-3000 Reconstruct catch 1LS $1,356,70 $1.356.70
Basin #53
Total: $9,880.15
The 50 feet of the 15" RCP storm drain pipe will not be used as shown in the plans
between catch basin #45 to #46. The 50 ft. will be deleted from the total cost needed for
Change Order #6.
ITEM#
550-1150
Description
Storm Drain Pipe,
15 In, H 1-10
UNIT PRICE
$15.20
TOTAL AMOUNT
- $760.00
OTY.
- 50
Total Cost: $9,880.15 - $760.00 = $9.120.15
Comment: 7 additional days are requested to complete this work.