Change Order Number: 2 Date: October 22. 1999
Project Title: Barton Chapel Road Improvements. Phase I
Original Contract Date: January 26. 1998 Project Number: 322-04-292822675
Owner: Augusta-Richmond County P.O. Number: 155955
Contractor: APAC- GA , Tnc
The following change order is hereby made to the proposal for the above project:
See Attachments.
TOTAL AMOUNT OF THIS CHANGE ORDER
$ 18.800.00
The Contract time will be Increased by 112 calendar days as a result of this change. The
date of completion including this change order is December 24. 1998.
Original Contract Amount
$ 965.886.40
Previous Change Order
(Increased / Decreased)
$ 27.994.90
This Change Order
(Increased / Decreased)
$ 18.800.00
TOTAL CONTRACT WITH CHANGE ORDER(S)
$1.012.681.30
*************
Funding Source/Account Number: 321-04-1110-6011110-288821675 ($18.800.00)
Date:
11/1>/11
Requested By:
Submitted By:
Date:
Date: ~
(ql
, '2--/(O/~?
t 1..{'O /99
I
Date:
Approved By:
Date:
Accepted By:
Date:
/~ -Z2-- .ftJ1
;.-
.'
0'
..
.....
,
,-
-::
ATTACHMENT
BARTON CHAPEL ROAD IMPROVEMENTS, PHASE I
CHANGE ORDER NUMBER TWO
PROJECT NUMBER:322-04-292822675
OCTOBER 22, 1999
Item No.1: 30" RCP shown on plans but inadvertently left off Detailed Es~imate. This
was a required item. GADOT will participate in cost.
40 L.F. @ $55.45/L.F. = $2,218.00
Item No.2: Flood of July 16, 1998 washed away the Barton Chapel Road roadway just
East of Glenn Hills Drive. Contractor had to install a gate valve and box
on an existing 8" ductile iron pipe so the water could be cut off without
disrupting service.
LUMP SUM Cost = $ 970.00
Item No.3: Proposed pavement widening required an existing water vault be adjusted
to the new grade. This was not provided for in the plans but was a
required item.
Total Cost = $3,795.00
Item No.4: Approximately 3 1/2 months after the adjustment in Item No.3 above the
doors and hinges broke under traffic. New hinges and doors had to be
installed.
LUMP SUM Cost = $2,300.00
Item No.5: The aforementioned July 16, 1998 Flood washed away a portion of Barton
Chapel Road, causing Augusta-Richmond County to close the road for a
week while the contractor repaired the road. The detoured traffic damaged
a private drive and parking area during this time period. Repairs required
an additional:
a) 220 Tons Asphalt "E" @$36.35/Ton = $7,997.00
b) 65 Tons GAB @ $16~00/Ton = $1,520.00
Item No.5 Total = $9,517.00
SUMMARY
Item No.1 = $ 2,218.00
. Item No.2 = $ 970.00
Item No.3 = $ 3,795.00
Item No.4 = $ 2,300.00
Item No.5 = $ 9.517.00
Total =$18,800.00
TOTAL THIS CHANGE ORDER = $18,800.00
Page 2 of2