Change Order Form r
Change Order Number: One Date: January 15,2004
Project Title ARC Drainage Improvements, Phase I
Original Contract Date: 1-05-04 Project Number: 322-04-20l823101
Owner: ARC P.O. Number: 84060
Contractor: Beams Contracting
Justification:
See (Page Two)
TOTAL AMOUNT OF THIS CHANGE ORDER
$ 6,887.50
The contract time will be increased by 30 calendar days as a result of this change. As a
result the new completion date is 6-02-04.
Original Contract Amount
$ 931,575.75
Previous Change Order(s) Total
$
0.00
This Change Order (Increased)
$ $6,887.50 .
TOT AL CONTRACT WITH CHANGE ORDERS(S)
******************************************
$ 938,463.25
Finance Endorsement:
Date: /- /6 -09-
,
Date: o(~JlJcf
Date: f (1. I { ~ y
Date: . // /[1/ tJ I
Requested By:
Submitted By.
Recommended By:
Approved By:
.f1At~y~
Contractor
Date:
Accepted By:
Date:
/--1'& -aV
CC: Errick Thompson, P.E., Assistant Director-Engineering
Purchasing Department, Geri Sams
Eric Edwards, Pre-Construction Engineer
Kakoli Basu
Valerie Jenkins
PreConstruction File
Change Order Form
ARC Drainage Improvements, Phase I
Change Order Number One
Project No.: 322-04-201823101
EXPLANA nON:
Plans required the removal of a large box that connected two 72" RCP, plus the removal of the downstream
portion of the 72". The purpose of this was to align the flow from this 72" RCP and that of the proposed
adjoining concrete ditch paving with an existing double line of 72" RCP. Once the downstream portion of
the 72" RCP and the connecting box was removed it was determined that the remaining 72" RCP was
approximately 20-25 degrees out of the plan alignment. Three options were explored to accomplish what
was proposed by this project.
1) Construct another connector box of cast-in-place concrete and reinforcing steel.
2) Construct the box with brick
3) Fabricate a joint of72" RCP with a 22 degree bend in it
The third option was selected because it will cost approx. $4,000 less than the second option above and
approx, $7,000 - $8,000 less than the fIrst option. The selected option also provides the most structurally
sound and hydraulically desirable of the three solutions.
This problem was discovered on Tuesday, 1-13-04 and pipe fabrication will take approx. 10 days. The east-
in-place option would require approx. the same. The brick option is not acceptable due to the proposed
alignment, volume and velocity and was not a viable option.
BEAMS CONTRACTING,INC.
2335 ATOMIC ROAD
BEECH ISLAND,SC 29842
Telephone (803) 827-0136
Fax (803) 827-1868
January 15, 2004
RICHMOND COUNTY PUBLIC WORKS
1815 MARVIN GRIFFIN ROAD
AUGUST A,GEORGIA 30906
ATTENTION: Mr. Robert Clements
RE: ARC-DRAINAGE IMPROVEMENTS-PHASE I,PROJECT NO.322-04-201823JOl
V ASSAR DRIVE & OBERLIN ROAD SECTION.
Dear Mr. Clements,
We are writing this letter for the proposed changes of items that are needed for
the above referenced project. Listed below are the items and there amounts.
1. Furnish and Install 72" R.C.Pipe,22 Deg.Bend, 1 EA. @ $3,233.00
2. Remov,e Existing 72" Pipe, 16 L.F. @$17.00 = $272.00
3. Furnish and Install Found Backfill,TP II 75C.Y. @ $23.10 = $1.732.50
4. Install 6' Chain Link Fence, 150 L.F. @ $11 .00 = $1,650.00
TOTAL AMOUNT FOR PROPOSED CHANGE ORDER = $6,887.50
We will need to add some days to this project since it will take up to two weeks
for delivery of the R.C.Pipe Bend,and additional days for this change order to be
processed we are requesting and additional 30 :.. Days be added.
If you should have any questions or should need any further information please
give us a call.
Sincerely,
Buddy Rowland
Buddy Rowland
Estimator
BEAMS CONTRACTlNG,INC.
2335 ATOMIC ROAD
BEECH ISLAND,SC 29842
Telephone (803) 827-0136
Fax (803) 827-1868
January 15,2004
RICHMOND COUNTY PUBLIC WORKS
1815 MARVIN GRIFFIN ROAD
AUGUST A,GEORGIA 30906
ATTENTION: Mr. Robert Clements
RE: ARC-DRAINAGE IMPROVEMENTS-PHASE I,PROJECT NO.322-04-201823101
VASSAR DRIVE & OBERLIN ROAD SECTION.
Dear Mr. Clements,
We are writing this letter for the proposed changes of items that are needed for
the above referenced project. Listed below are the items and there amounts.
1. Furnish and Install 72" R,C.Pipe,22 Deg.Bend, 1 EA. @ $3,233.00
2. Remove Existing 72" Pipe, 16 L.F. @ $17.00 = $272,00
3. Furnish and Install Found Backfill,TP II 75C.Y. @ $23.10 = $1,732.50
4. Install 6' Chain Link Fence, 150 L.F, @ $11.00 = $1,650.00
TOTAL AMOUNT FOR PROPOSED CHANGE ORDER = $6,887.50
We will need to add some days to this project since it Will take up to two weeks
for delivery of the R.C.Pipe Bend,and additional days for this change order to be
processed we are requesting and additional 30 - Days be added.
If you should have any questions or should need any further information please
give us a call.
Sincerely,
Buddy Rowland
Buddy Rowland
Estimator