HomeMy WebLinkAbout MCKINGHT CONSTRUCTION CHANGE ORDER 1 J, TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 1 June 16,2005 IODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: he Contract Duration is adjusted as follows: Phase 1 - Original Duration 300 calendar days; Adjusted Duration 310 calendar days Phase 2 - Original Duration 120 calendar days; Adjusted Duration 120 calendar days Phase 3 - Original Duration 365 calendar days; Adjusted Duration 365 calendar days Phase 4 - Original Duration 120 calendar days; Adjusted Duration 120 calendar days 'otal Contract Duration - Original Duration 905 calendar days; Adjusted Duration 915 alendar days See attached for additional summary and details lnal Contract Sum ...................................$ 25,254,192.45 1ge by Previous Change Order .....................$ o ract Sum Prior to this Change Order......... . ...$ 25,254.192.45 Change Order ... . .. . . . . . . . .. .. . . . . . . . . .. . . . . . . . . . . .. $ o Contract Sum .......................................$ 25,254.192.45 ract Time will be as follows: 10 Calendar Days are added to the duration of Phase 1 and the Total Contract Duration PfL ~ (,lz~/o~ vicKnight Construction Co., Inc. DATE t>. Z.7. cf;;, DATE 4'&r:ritW . ort Must be signed by Construction Manager. Architect. Owner and Contractor :c: All Signers TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 1 ODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: (CONTINUED) noted on the attached correspondence, McKnight Construction Co. Inc. was unable to acquire Building Permit for the project until April 18 (5 calendar days after the designated Notice to )ceed). Further, the Contractor was restricted by regulations of the State of Georgia dictating t a Notice of Intent (NOI) must be provided to the Environmental Protection Division prior to rting work. Following the submission of the NOI, the Contractor is prohibited from starting th disturbance activities for a duration of 14 days. neeting was conducted on May 31, 2005 which included the following individuals: Mason McKnight, Pat Patrick, Lee Mooney, Lynn Reeves - McKnight Construction Co. Mike Leath, Tom Lochstampfor - The LP A Group Willis Boshears, Tim Weegar - Augusta Regional Airport Robbie Roberson, Brian Holland, Matt McCoy - Parsons Brinckerhoff CS, Inc. le duration of 10 calendar days was agreed by all parties present because there were several ivities which were able to be performed by the Contractor prior to the NOI 14 day earth turbance prohibition. :achments: · National Pollutant Discharge Elimination System General Permit Fee Form - Submitted to Environmental Protection Division on April 13, 2005 · PB Correspondence - Permit and Notice ofIntent Issues Dated April 15, 2005 · Augusta-Richmond County Land Disturbing Activity Permit - Permit No. 2005-043 - Dated April 14, 2005 and Received April 18, 2005 · Inspection Card - Permit No. 200504078 - Dated April 19, 2005 · PB Correspondence - Permit and NOI Issues Dated April 21, 2005 mn CLDF. 2 Revised January 2004 H<X. ~ 1.2.00. \ ional Pollutant Discharge Elimination System leral Pemlit Fee Form )rgia Dept. of Natural Resources rironmental Protection Division ase print or type this form. >mit original and payment to: D-Construction Land Disturbance Fees D. Box 932858 lanta, Georgia 31193-2858 lke check payable to: partment of Natural Resources - EPD (DO NOT MAIL CASH) (Complete thefollowing information) mary Permittee l!usta Aviation Commission at Il!Usta Rel!ional Airport mittee Address n Aviation Way ll!Usta. GA 30906 ntact Telephone 3-798-3236 :res Disturbed in an area with a local issuing authority , not include fees payable to local issuing authorities. Project Name Terminal Area Improvements Proiect Location / Address 1501 Aviation Way AUl!usta. GA 30906 County Richmond City AUl!usta 13.0 x $40 per acre = $520.00 :res Disturbed in an area with no local issuing authority x $80 per acre = ;res Disturbed by an entity exempt from local issuing thority regulation pursuant to statute x $80 per acre = TOTAL FEE SUBMITTED = $520.00 Check Number Ibmitted By: ill ",-,~~JL ~ Date: Lj-/3 - uS- gnature: lnt Name: Willis M. Boshears. Jr. Title: Executive Director ATTACH CHECK HERE VOID IF SUBMITTED WITHOUT PAYMENT III. b .57 bill ':0 b .000052': 003 28 2 SO 7 b 58111 {v 'tl't.. I'L:Jz.""" (' =- Parsons Brinckerhoff ConstlVction SelVices, Inc. 1510 Hanger Road, Suite A Augusta, GA 30906 706-771-5172 Fax: 706-771-5176 o riSi,J ,priI15, 2005 1cKnight Construction Co. 35 North West Frontage Road ,ugusta, GA 30907 ,ttention: Mr. Pat Patrick ,e: Augusta Regional Airport - Terminal Area Improvements Permit and Notice oflntent Issues 1r. Patrick: 'his correspondence is provided in response to your letter dated April 13, 2005 concerning ermit and Notice ofIntent (N.O.I.) issues. Parsons Brinckerhoffhas been working diligently rith the Architect for the project to resolve the outstanding issues. ife acknowledge that the N.O.I. was submitted on April 13, 2005 (see copy attached). In ccordance with the state regulations, activities which involve earth disturbance may not Dmmence for 14 days following this submission date. However, as discussed while you were n-site April 13, there are several activities that do not require earth disturbance and may be erformed in the interim and are clearly identified on McKnight's Initial Construction Schedule. urther, we discussed the need to move forward with several of the administrative and technical llbmittal issues. ifith regard to Permits, Parsons Brinckerhoff is currently aware that the Office of License and Ispection is seeking a site plan approved by the Planning and Zoning Commission. We are lorking with the Architect to work through this issue. '0 document the record, McKnight Construction began mobilization activities on April 13. 'hese activities included on-site coordination with the Owner's maintenance representatives, tility location, tree cutting, surveying and site layout. ~you have any questions concerning this matter, please feel free to contact me at (706) 771- 173. incerely, arsons Brinckerhoff Construction Services, Inc. ~~7;?7 :onstruction Manager :c: Willis Boshears, Tim Wee gar; ARA Bob Anderson. A,ndy, Busbee, Mike Leath; LP A Dick Kennedv}:BrriiIf;H~lil'fi'(fr Robbie Roberson; PB/INT t!$JJ1f flJrl .. 'l~~0~~MJ~i8"fi~~.; ; !E;'~-C:f:J!JiS:n;<<;;; NOTICE OF INTENT For Official Use Only State of Georgia Environmental Protection Division For Coverage Under NPDES General Permit To Discharge Storm Water Associated With Construction Activity PRIMARY PERMITTEE eraae Desired (Check Onlv One) AR 100001-Stand Alone 0 GAR 100002-lnfrastructure 0 GAR 100003-Common Development SITE/OWNER/OPERATOR INFORMATION :lroject Name: AUQusta ReQional Airport - Terminal Area Improvements Proiect f applicable): AUQusta County: Richmond 1r9)--'~[;~'~-i~c:." rj ~/7 j~ '\"r-'\ O ~ '~-.J t..!:::...; \0 ~ t== UI <, r-- ---.. -~.__.,-~, ' I ;-', I '\ J .U Ut AI>R (J 2005 ~D \' ~~101\LPR01Er:TION ON ~, , EASTCENTRALI)lS1RIC J' AUGUST/, OFFICIO Location of Construction Exit: N 1228089.9753, E 715029.9401 ~t Address: 1501 Aviation Way iivision Name: N/A ~r's Name: AUQusta Aviation Commission at AUQusta ReQional Airport 3SS: 1501 Aviation Way City: AUQusta State: GA Zip Code: 30906 ator's Name: AUQusta ReQional Airport Phone: 706-798-3236 3SS: 1501 Aviation Way City: AUQusta State: GA Zip Code: 30906 Ity Contact: Willis 'Buster' Boshears. Executive Director Phone: 706-798-3236 SITE ACTIVITY INFORMATION Date: 4-13-2005 Construction Activity: Completion Date: October,2008 Estimated Disturbed Acreage: 13.0 V Commercial 0 Industrial V Municipal V Linear V Utility 0 Residential/Subdivision Development )er of Secondary Permittees: Zero (0) RECEIVING WATER INFORMATION Name of Initial Receiving Water(s): To South: DrainaQe ditches to tributary of TwiQQS Dead River to Savannah River (Outfall #1, 3. & 4) To North: DrainaQe ditches to Butler Creek to Savannah River (Outfall #2) o Trout Stream .y Warm Water Fisheries Stream Name of Municipal Storm Sewer System Owner/Operator: WA Name of Receiving Water(s): N/A o Trout Stream o Warm Water Fisheries Stream V Sampling of Outfall(s) o Sampling of Receiving Stream(s) o Trout Stream Number of Outfalls: ~ Appendix B NTU Value: 50 Surface Water Drainage Area: 28.4 acres Date: Lf -1:3 - () r ATTACHMENTS. (Check those that apply.) cate below the items attached to this Notice of Intent: .y Location map showing the receiving stream(s), outfall(s) or combination thereof to be monitored. I Erosion, Sedimentation and Pollution Control Plan (if project is greater than 50 acres or if project in areas without local Issuing Authorities regardless of acreage). List of known secondary permittees. .y Schedule for the timing of the major construction activities. CERTIFICATIONS. (Owner or Operator or both to initial as applicable.) t-.13 I certify that the receiving water(s) or the outfall(s) or a co1mbination of receiving water(s) and outfall(s) will be monitored in accordance with the Erosion, Sedimentation and Pollution Control Plan. c,.....{S I certify that the Erosion, Sedimentation, and Pollution Cont~ol Plan (Plan) has been prepared in accordance with Part IV of the General NPDES Permit GAR100001, GAR 100002 or GAR 100003, the Plan will be implemented, and that such Plan will provide for compliance with this permit. . L.-J;? I certify under penalty' of iaw th~t t~s document and all attachJents were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based upon my inquiry of the personl or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that ther~ are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. ,er's Printed Name: Willis M. B....a: Jr. for Auqusta Avtation Commission lature: (p fA ~ ~ ~~ / Title: Executive Director Title: Executive Director -' Date: Lf ~ ( ~. 'o:i lature: KlJ\lJOCSIDESIGNlGANPOES Perm~;IlJ\Term AJe! Imp-Local"" of <MUob & Ree W'leB.dwg lB~ Mo<liied: "fr 13, 2005 .1~llpm PlolIerl 011: PfJ 13. 2005 .1~IBpm by abusbe. / / l'-.,) ,... r- m 0 -l G> m ~ ~ m ~ Z r- r- 0 r- > I.. 0 n ... ~ ~ 5 ~ z ...., ... ~ 0 ~ " m Z m ::l 3: m -n ~ / n ~ 5 ...., z 0 ...... m () -l r- ~ :::j en III I I -- - -II I I III I I I I I (W'O 1 cj TfW?! w.JW IIw26 J Parsons Brinckerhoff Construction SelVices, Inc. 1510 Hanger Road, Suite A Augusta, GA 30906 706-771-5172 Fax: 706-771-5176 ~p{i;i,' r'\p.s ~;, April 21, 2005 McKnight Construction Co. 635 North West Frontage Road Augusta, GA 30907 Attention: Mr. Pat Patrick Re: Augusta Regional Airport - Terminal Area Improvements Permit and NO! Issues Mr. Patrick: The Notice oflntent (N.O.I.) was submitted to the State of Georgia Environmental Protection Division on April 13, 2005. You correctly note that land disturbance activities may not proceed until April 27. In addition, the undersigned received the Land Disturbing Activity Permit from Mr. Bob Austin with the Planning & Zoning Office on April 18. This Permit was hand carried to McKnight Construction Company personnel on the same date. With regard to the Building Permit, Matt McCoy spoke with Mr. Richard Manning with the License and Permits Office to confirm he would be available the afternoon of April 18 to issue the permit. Parsons Brinckerhoff affirms that the inability to perform land disturbance activities may impact the progress of work, but also confirms that there are numerous activities that may be, and are being performed by forces with McKnight Construction prior to the need to disturb earth. Of greater concern to this office is the lack of progress in providing the administrative and technical submittals for the project. For example, key administrative submittals identified in the project specifications include: Erosion Control Schedule (Section 01160), Submittals Schedule (Section 01320), Quality Control Program (Section 01410), Certificates on Location & Elevation (Section 01700), Certificates of Land Surveyor (Section 01700) and Schedule of Selective Demolition (Section 01732). To date, none of these submittals have been received. [fyou have any questions concerning this matter, please feel free to contact me at (706) 771- 5173. Sincerely, Parsons Brinckerhoff Construction Services, Inc. !~- ?f<c/, Construction Manager Cc: Willis Boshears, Tim Weegar; ARA Bob Anderson, Andy Busbee, Mike Leath; LP A ;ntw')' oC Dick Kennedy, Brian Holland, Robbie Roberson; PB ij;!:~ EJ:ceGh'efft!~!:-' J. TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 1 June 16,2005 MODIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: The Contract Duration is adjusted as follows: Phase 1 - Original Duration 300 calendar days; Adjusted Duration 310 calendar days Phase 2 - Original Duration 120 calendar days; Adjusted Duration 120 calendar days Phase 3 - Original Duration 365 calendar days; Adjusted Duration 365 calendar days Phase 4 - Original Duration 120 calendar days; Adjusted Duration 120 calendar days Total Contract Duration - Original Duration 905 calendar days; Adjusted Duration 915 calendar days See attached for additional summary and details ~inal Contract Sum ................................ ...$ 25.254.192.45 mge by Previous Change Order.................. ...$ o ltract Sum Prior to this Change Order .............$ 25.254.192.45 s Change Order ....................................... $ o v Contract Sum.......................................$ 25.254.192.45 ltract Time will be as follows: 10 Calendar Days are added to the duration of Phase 1 and the Total Contract Duration ~L ~. (,lz~/o~ McKnight Construction Co., Inc. DATE t>. Z7. cf;;, DATE ~~S2 ttMl Must be signed by Construction Manager. Architect. Owner and Contractor Cc: All Signers TERMINAL AREA IMPROVEMENTS AUGUSTA REGIONAL AIRPORT AT BUSH FIELD CHANGE ORDER NO. - 1 )DIFICATIONS TO THE CONTRACT ARE AS FOLLOWS: (CONTINUED) loted on the attached correspondence, McKnight Construction Co. Inc. was unable to acquire Building Permit for the project until April 18 (5 calendar days after the designated Notice to :eed). Further, the Contractor was restricted by regulations of the State of Georgia dictating a Notice of Intent (NOI) must be provided to the Environmental Protection Division prior to ing work. Following the submission of the NOI, the Contractor is prohibited from starting 1 disturbance activities for a duration of 14 days. .eeting was conducted on May 31, 2005 which included the following individuals: Mason McKnight, Pat Patrick, Lee Mooney, Lynn Reeves - McKnight Construction Co. Mike Leath, Tom Lochstampfor - The LP A Group Willis Boshears, Tim Weegar - Augusta Regional Airport R.obbie Roberson, Brian Holland, Matt McCoy - Parsons Brinckerhoff CS, Inc. : duration of 10 calendar days was agreed by all parties present because there were several Tities which were able to be performed by the Contractor prior to the NOI 14 day earth ubance prohibition. chments: t National Pollutant Discharge Elimination System General Permit Fee Form - Submitted to Environmental Protection Division on April 13, 2005 t PB Correspondence - Permit and Notice of Intent Issues Dated April 15, 2005 t Augusta-Richmond County Land Disturbing Activity Permit - Permit No. 2005-043 - Dated April 14, 2005 and Received April 18, 2005 t Inspection Card - Permit No. 200504078 - Dated April 19, 2005 t PB Correspondence - Permit and NOI Issues Dated April 21, 2005 rm CLDF. 2 Revised January 2004 H<X. ~ lJ.. 00. \ onal Pollutant Discharge Elimination System eral Pemlit Fee Form rgia Dept. of Natural Resources ironmental Protection Division Be print or type this form. mit original and payment to: )-Construction Land Disturbance Fees ). Box 932858 mta, Georgia 31193-2858 ke check payable to: lartment of Natural Resources - EPD (DO NOT MAIL CASH) (Complete the following information) nary Permittee !usta Aviation Commission at Hlsta Rel!ional Airport mittee Address 1 Aviation Way !!usta. GA 30906 ltact Telephone >-798-3236 'es Disturbed in an area with a local issuing authority not include fees payable to local issuing authorities. Project Name Terminal Area Improvements Proiect Location / Address 1501 Aviation Way AUl!usta. GA 30906 County Richmond City AUl!usta 13.0 x $40 per acre = $520.00 :es Disturbed in an area with no local issuing authority x $80 per acre = res Disturbed by an entity exempt from local issuing hority regulation pursuant to statute x $80 per acre = TOTAL FEE SUBMITTED = $520.00 Check Number bmitted By: ill ",-,~~JL .) Date: Lj-/3 - uS- ~ature: nt Name: Willis M. Boshears. Jr. Title: Executive Director ATTACH CHECK HERE VOID IF SUBMITTED WITHOUT PAYMENT III . b . 5 7 bill .: 0 b . 0 0 0 0 5 2 I: 00 3 28 2 SO 7 b 5 a III .~ "llt~. fL.".;]~v\' '7 Parsons Brinckerhoff Constl1lcfion Services, Inc. 1510 Hanger Road, Suite A Augusta, GA 30906 706-771-5172 Fax: 706-771-5176 , S 'ol Jri115,2005 cKnight Construction Co. ,5 North West Frontage Road 19usta, GA 30907 :tention: Mr. Pat Patrick ~: Augusta Regional Airport - Terminal Area Improvements Permit and Notice ofIntent Issues r. Patrick: lis correspondence is provided in response to your letter dated Apr-H 13, 2005 concerning :rmit and Notice ofIntent (N.O.I.) issues. Parsons Brinckerhoffhas been working diligently lth the Architect for the project to resolve the outstanding issues. e acknowledge that the N.O.I. was submitted on April 13, 2005 (see copy attached). In cordance with the state regulations, activities which involve earth disturbance may not mmence for 14 days following this submission date. However, as discussed while you were I-site April 13, there are several activities that do not require earth disturbance and may be rformed in the interim and are clearly identified on McKnight's Initial Construction Schedule. lrther, we discussed the need to move forward with several of the administrative and technical bmittal issues. ith regard to Permits, Parsons Brinckerhoff is currently aware that the Office of License and spection is seeking a site plan approved by the Planning and Zoning Commission. We are )rking with the Architect to work through this issue. ) document the record, McKnight Construction began mobilization activities on April 13. lese activities included on-site coordination with the Owner's maintenance representatives, ility location, tree cutting, surveying and site layout. you have any questions concerning this matter, please feel free to contact me at (706) 771- 73. ' ncerely, lrsons Brinckerhoff Construction Services, Inc. ~~~7?'Y mstruction Manager Willis Boshears, Tim Wee gar; ARA Bob Anderson.;\ndy,BlJsbee, Mike Leath; LPA !t''''''''''..,.Ff''''''!~''''''''''i' ." Dick Kennedv!BtHiri'HolIand; Robbie Roberson; PB/INT 7..931' Ql .v '~~~~~tJ):~t~;; . ffE:zc:eJ.i'fiiiJr,iC2 applicable): AUQusta County: Richmond 1r9)---If:-rFt~ -fJ)-~V7 ir-; 'l'r-'~ ~ \-.!l U::....: \. d ,.::.=7 I 0< ~ ---.. __'___"_-"'1 I I, IfU/ Ai'R {3 2U05 : 10 ~ i ~O~'~~NTI\L PROTECTION 010"-4 EAST CENTRALmSTRIC AUGUST', OFFICE NOTICE OF INTENT For Official Use Only State of Georgia Environmental Protection Division For Coverage Under NPDES General Permit To Discharge Storm Water Associated With Construction Activity PRIMARY PERMITTEE raae Desired (Check Only One) .R 1 00001-Stand Alone 0 GAR 100002-lnfrastructure 0 GAR 100003-Common Development SITE/OWNER/OPERATOR INFORMATION roject Name: AUQusta ReQional Airport - Terminal Area Improvements Proiect .ocation of Construction Exit: N 1228089.9753, E 715029.9401 Address: 1501 Aviation Way lision Name: N/A "s Name: Auausta Aviation Commission at AUQusta Reaional Airport ~s: 1501 Aviation Way City: Auausta State: GA Zip Code: ~ tor's Name: Auausta Reoional Airport Phone: 706-798-3236 ~s: 1501 Aviation Way City: Auousta State: GA Zip Code: 30906 ,Contact: Willis 'Buster' Boshears, Executive Director Phone: 706-798-3236 SITE ACTIVITY INFORMATION )ate: 4-13-2005 Completion Date: October. 2008 Estimated Disturbed Acreage: 13.0 "Commercial 0 Industrial " Municipal " Linear " Utility 0 Residential/Subdivision Development ~r of Secondary Permittees: Zero (0) ~nstruction Activity: RECEIVING WATER INFORMATION Name of Initial Receiving Water(s): To South: Drainaoe ditches to tributary of TwioQS Dead River to Savannah River (Outfall #1. 3, & 4) To North: Drainaoe ditches to Butler Creek to Savannah River (Outfall #2) o Trout Stream "Warm Water Fisheries Stream Name of Municipal Storm Sewer System Owner/Operator: N/A Name of Receiving Water(s): N/A o Trout Stream o Warm Water Fisheries Stream " Sampling of Outfall(s) o Sampling of Receiving Stream(s) o Trout Stream Number of Outfalls: 1 Appendix B NTU Value: 50 Surface Water Drainage Area: 28.4 acres Date: Lf -1:3 . () r ATTACHMENTS. (Check those that apply.) ate below the items attached to this Notice of Intent: ..J Location map showing the receiving stream(s), outfall(s) or combination thereof to be monitored. Erosion, Sedimentation and Pollution Control Plan (if project is greater than 50 acres or if project in areas without local Issuing Authorities regardless of acreage). List of known secondary permittees. ..J Schedule for the timing of the major construction activities. CERTIFICATIONS. (Owner or Operator or both to initial as applicable.) t-.!3 I certify that the receiving water(s) or the outfall(s) or a combination of receiving water(s) and outfall(s) will be monitored in accordance with the Erosion, Sedimentation and Pollution Control Plan. c...-f5 I certify that the Erosion, Sedimentation, and Pollution Control Plan (Plan) has been prepared in accordance with Part IV of the General NPDES Permit GAR100001, GAR 100002 or GAR 100003, the Plan will be implemented, and that such Plan will provide for compliance with this permit. t-J;? I certify under penalty" of iaw th~t t~s document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gather and evaluate the information submitted. Based upon my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations. 'fs Printed Name: wnl1s M. B_ea: Jr. for AUQusta Aviation Commission 3ture: [Plt~ ~~~ / Title: Executive Director Title: Executive Director -' Date: L(...., ~. 'OJ 3ture: =- Parsons Brinckerhoff Construction SelVices, Inc. 1510 Hanger Road, Suite A Augusta, GA 30906 706-771-5172 Fax: 706-771-5176 ~1:~' ms ~:;, \pril 21, 2005 \1cKnight Construction Co. ;35 North West Frontage Road \ugusta, GA 30907 \ttention: Mr. Pat Patrick k Augusta Regional Airport - Terminal Area Improvements Permit and NOI Issues \1r. Patrick: fhe Notice ofIntent (N.O.I.) was submitted to the State of Georgia Environmental Protection )ivision on April 13, 2005. You correctly note that land disturbance activities may not proceed mti! April 27. In addition, the undersigned received the Land Disturbing Activity Permit from \1r. Bob Austin with the Planning & Zoning Office on April 18. This Permit was hand carried to vIcKnight Construction Company personnel on the same date. With regard to the Building )ermit, Matt McCoy spoke with Mr. Richard Manning with the License and Permits Office to :onfirm he would be available the afternoon of April 18 to issue the permit. )arsons Brinckerhoff affirms that the inability to perform land disturbance activities may impact he progress of work, but also confirms that there are numerous activities that may be, and are leing performed by forces with McKnight Construction prior to the need to disturb earth. )f greater concern to this office is the lack of progress in providing the administrative and echnical submittals for the project. For example, key administrative submittals identified in the lroject specifications include: Erosion Control Schedule (Section 01160), Submittals Schedule Section 01320), Quality Control Program (Section 01410), Certificates on Location & Elevation Section 01700), Certificates of Land Surveyor (Section 01700) and Schedule of Selective )emolition (Section 01732). To date, none of these submittals have been received. fyou have any questions concerning this matter, please feel free to contact me at (706) 771- ;173. ;incerely, )arsons Brinckerhoff Construction Services, Inc. !~, ?fCC/ :onstruction Manager :c: Willis Boshears, Tim Weegar; ARA Bob Anderson, Andy Busbee, Mike Leath; LP A ~ttmy ::if Dick Kennedy, Brian Holland, Robbie Roberson; PB ~!:; f1:Jr.cef!h'ance J\OOCS\DESIGMGA NPOES Pennill'llIT.m Area Imp.Localiol1 or Orlf.~ & Reo W.~~.dwg lJl~ Modifted: ~r 13, 2005 .1~11"" P10Ited on: I;r 13, 2005. f~fBpm by abusbe. / / l'Y ~. DIXON AIRLINE RU r- m 0 ...... C> m ~ ~ m ~ Z r- 0 r- 5 r- I. ,.. n "" ~ ~ <5 ~ Z ." 0 Q m Z m ...... ~ :;; m / R ~ ~ <5 ." "" Z 0 .... m !:l r- ~ :::j (/I I -- --II I I III I I I I I ~ <l I T{W~ T{W'f! RJW 8.26 ~ cj J ~ ,U :J ~ :i?o ~ " " It ~i iii ~ ::To 0" " It It :1 s: )> AI 0," "')> ",'U w~ OJ'" o~ :;j)> m'U COAl 00 OJ'" ~. f... ~ ~ " .~ I;!. .~. ,~' :1J ll! 'fui " ~ ~f- 1"1 1l~ ill ~. ."'f '~i. ,;C~ :e ff. r.~;; ,~ 1, .~. Jt ,~ ft: ~~ :~l' ~li ,11 ~. e ~. ~ 'Q1.i ~ ~ !;',l )>. -0 ;:;0 c::::> t:O l:9 a t;f J-{ <: ~ t:J ~ ffi tn ~ ~ o .... .... 8 0 N ~ 0 ~ 0 ~ 0 0 ~ ~ 0 ~ 8 ~ ~ ~ ~ ~ ~ A ~ 8 ~ 0 ~ a CD o o III ~ .... 0> A N .... C>:> J>. ,. '- c c G) b 5': 01 J>. 01 0 (,) Ol .... 0 .... 01 '- '- c c b b 01 01 en "T1 "T1 ciI () 38~C"g 3 g: I/O I/O ~ O~OOen DJ nJ !!. ~ 6" ~ ~ g1 g 3 ~ "T1 0 ~ 0 3g"'~OJ "O::J ~ 5' C/l lir 0 f [ ~ ;;f Q ~ .... A 0> !:': ~ '-. '- c c z z 5': 5': C>:> .... J>. J>. CD (,) N o 0 N .... CD 0> J>. <0 '- '- s:: s:: ~ ~ ~ ~ o 0 0 0 01 01 01 01 .... .... 0 .... .... Ol ~ ~ ~ 5': 5': 5': (,) .- .- Ul 0) 000 0> 01 01 So: s:: s:: ~ ~ ~ 000 01 01 01 .... 0 01 (,) o 0 = ~ ~ ~ = ~ ~ ~ ~ ~ ~ = ~ Ol ~ ~ N J>. ~ 0 C>:> 8 ~ 0 C>:> N .... .... o 0 0> 0 .... (!) o 0 8 0 .... .... .... ;0 "T1 ;0 o III 0 c: C" c: 'go I/O 'go G)~:i" OJ c g. i;ll E!: aJ ~ [t 5. . fJ) c: c; ~. OJ "J .\ ~ 0. '" -6'-6' g-6'-6' b' ~ i1f ~ ~ ~ ~ W~.s ~ ~ ~ ~ ~ :1 'Cl g ~ ~ ~ C" 1i o' 0 ~ ~ ~ ~ ~ a s ~' ~ ~ ~ ~ ro m ~ '" '" G) '" '" "T1 ~ aJ ;0 () C/l :1 ~ ~ ~ ~ ~ ~ ~~. [ ~ g g ~ ~ E ~ ~ ~ ~ ~ 5' ~ ~ ~ ~ ~ ~ n: 2"-':1 ii lO iD~ma> ~ ~ m en ~ ~ lC C/l aJ - '" m ~ ~ !t 0)" ii1 "T1 '" :1 o !!!. G) ~ '" 0- <t 41 '" -0 o :1 .w N o o Ul o '" 3 o i);' -0 :r ~ ~ () c: 6- ~ )> ~ -..j o J>. s:: .~ o 01 ~ m ~ ~ ~ ~ ~ ~ w ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ m ~ ~ ~ ~ A ~ f ~ ~ u ,. ,. ,. ,. ,. ,. - ,. ,. ,. ,. ,. ,. - ,. ,. ) ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 1 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ;0 ~ 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': ~ ~' ; -~:.I i} , "iI ~ ,: ~ ~ ~ ~ 'l1lr.3! -':n:g ;O"Tl Oi.S!ro-o g ~ ~: ~ ~ ~ lQ l/O '0 , ",!!1. aJ :r 0 i g-;,. C" g' 0" ~ !!.. ~ ;:;:"!:E ~ ~ 0 tu _I.... -, "" ~g.~ ~:~ ~ "mg- ~tD c: ...,... -... 1Il . .- .. .=' 0.= .. ! "f _, ..; c .5 o. , 2- ~ ~ : ;J Co ~ i~ tE ,11 :r :i" c ~ ! ......- -- -,- a-: .......1... .... ,....,.- '" III S o:! r S' '" ~ o o :1 ; III .r+ o c o ~ w w ~ ~ N W ~ 0 N N ~ 0 ~ 0 0 0 .- ~ ~ ~ N 0 ~ ~ m ~ ~ ~ A ~ W ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ ~ 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': 5': L I 1 I ! T" I ! ~. .... ~ J>. (,) .i-' ! :11 ----l n I~; ~ ~ DJj 2.. a. ~. ~ ~ =' ~ c: 't1 -< 3:1 g Q ~: , ~ g. 3 0; ! a: !:to _c:: ~ 0 '8 is. i ~ iJl c: Dl: Dl (;-5'.;- "'-- g ~~~ B n C" @ i l/O <t 0 ~"tl !!. ~' ~ III 2 o g e!. . !II '.[;..- .. < ": o o :1 III r+ "-l r- Dl :1 '" en o ... Z ~ :::: o .- Ei ....-! . o o 3 -0 iP <P 41 a. ro n. ; , '1 aJ , Dl n I '" : ::!I -,_,"d i1 -a fa ~ ~ S' 0 -c~Ei Co c cnlC" ; ~ iii"jC i;1 Dr ~:E to C'" ::J 1 :to o Gl III ~.,~ -OJ: III -=: c. i ... ~ fb: ~ fb i o III '< III 1Il .~: .- ~ c: n. 5; e!. 1Il <P !!. l<J l<J! "Tl "Tl Dl Dli tT tT. I/O l/O; o oi !!. !!.. aJ 0 i 0" g ~ !:li !! .. ro"; '1Il S 3 ~o .... .l-@" I :i" o c 19 0- ., () c: if} "Tl a ,::> _. ~ to - i~ Dl !~ ,Ill ; ...k . -~mrn:::1i..p ~ z , to. .- (IJ' (j') If. 0' S- 'l ..); g. ~! 6- .'t a 0" ~ 'Cl a. 1Il: E!. ~ III '" r S m &rO ~ a d ~_~ "Tl - 3 0 - ~ ~...s: ..8. ~'I'~ (J).; 0 ~ ~ ~ n, 0 '" ~! 0; g. ~ g ~ tS ~ g-, it ~, ~ ~ u: ~ ~ . ~ ~ ~ ~ i 2 ~ ::J ; @ -0 e!. !!.' ro !!. Ii; 1 ~ ! ;... ! f~ L I . -6' I i ~! ,., o. <10 ~! g O!CI1 ::I:"' n:"Tl @i~ it10 ,5 Dl 'It !~ '" !~ .in 1'0 '0. ::> ien !Iil' :lQ .~ 5' :'" :~ l1> Dl IW .'" '" C) o (1l